Construction Handbook[1]

Embed Size (px)

Citation preview

  • 8/12/2019 Construction Handbook[1]

    1/479

  • 8/12/2019 Construction Handbook[1]

    2/479

    Update 15 published December 2003

    Update 14 published September 2003

    Update 13 published May 2003

    Update 12 published January 2003

    Update 11 published October 2002

    Update 10 published August 2002

    Update 9 published December 2001

    Update 8 published October 2001

    Update 7 published July 2001

    Update 6 published December 2000

    Update 5 published October 2000Update 4 published May 2000

    Update 3 published December 1999

    Update 2 published October 1999

    Update 1 published April 1999

    Please note:References to the masculine include, where appropriate, the feminine.

    Extracts fromParrys Valuation and Conversion Tables, A W Davidson (1989),(Estates Gazette) reproduced by permission of the College of Estate Management

    which owns the copyright.

    Appendix A, Section 2.3 is reproduced from the Building Cost Information Service publication,

    Standard Form of Cost Analysis: Principles, Instructions and Definitions(1969).

    Published by RICS Business Services Limited

    a wholly owned subsidiary of

    The Royal Institution of Chartered Surveyors

    under the RICS Books imprint

    Surveyor Court

    Westwood Business Park

    Coventry CV4 8JE

    UK

    No responsibility for loss occasioned to any person acting or refraining from

    action as a result of the material included in this publication can be accepted by the

    author or publisher.

    ISBN 0 85406 865 1

    RICS Business Services Limited (RBS) December 2003. Copyright in all or part

    of this publication rests with RBS, and save by prior consent of RBS, no part or parts

    shall be reproduced by any means electronic, mechanical, photocopying, recording or

    otherwise, now known or to be devised.

    Typeset and printed by Q3 Print Project Management Ltd, Loughborough.

  • 8/12/2019 Construction Handbook[1]

    3/479

    1998 FOREWORD

    Knowledge is of two kinds: we know a subject ourselves, or we know

    where we can find information upon it.Samuel Johnson (17091784)

    The fact that our profession serves a changing world increases the need for

    it to rely on well thought-out and reliable practices and procedures. Events

    move at an ever-increasing pace, imposing a requirement for quicker

    response times. Modern communication methods such as facsimile and now

    e-mail result in the need for information to be available almost instantly.

    This is made more difficult by an industry growing in complexity and which

    is subject to increasing customer expectations in terms of service and

    quality.

    The RICS has published this Surveyors Construction Handbook to help

    surveyors meet these needs. It is intended to become an important source of

    reliable information and guidance to all Chartered Surveyors who practise in

    construction. Much of the excellent information produced by the divisions

    in the past has now been updated for inclusion. Other material not yet

    revised will be added. The whole will be regularly reviewed and updated as

    necessary. RICS practice panels are continuing to produce information for

    inclusion to make it a useful construction reference document.

    We hope that this Handbook will become an invaluable aid to yourday-to-day activities.

    Christopher Powell,FRICS

    P RES IDENT, QUANTITY S URVEYORS DIVIS ION, 1 9 9 7 98

    Trevor Mole, FRICS

    P RES IDENT, BUILDING S URVEYORS DIVIS ION, 1 9 9 7 98

  • 8/12/2019 Construction Handbook[1]

    4/479

    ACKNOWLEDGEMENTS

    Professor Roy Morledge, Professor of Construction Procurement at The

    Nottingham Trent University, for contributing the text of Part 3, Section 1.

    Major D.R. Bassett, Royal Engineers, for his contribution to the research

    underpinning the construction time charts in Part 3, Section 1; Central Unit for

    Procurement, HM Treasury (now Office for Government Commerce), for

    permission to use CUP guides extensively in the drafting of Part 1, Section 1

    and Part 3, Section 1.

    Alan Turner, JP FRICS ACIArb, author of Building Procurement, for

    permission to use a number of the diagrams from his text in Part 3, Section 1.

  • 8/12/2019 Construction Handbook[1]

    5/479

  • 8/12/2019 Construction Handbook[1]

    6/479

    Page 2 Contents (12/03) The Surveyors Construction Handbook

    1Introduction 1

    2.1.1 Pre-contract Cost Planning and Cost Management 2

    2.1.2 Preliminary Cost Studies and Feasibility Studies 4

    2.1.3 Budget 4

    2.1.4 The Cost Plan at Outline Proposals Stage 8

    2.1.5 The Cost Plan at Scheme Design Stage 11

    2.1.6 Cost Checking 13

    2.1.7 Action after Receipt of Tenders 14

    Appendix A: Sources of Cost Information 1

    Appendix B: Format of Budget and Cost Plans 1

    Appendix C: Element Unit Quantities Generation for Hypothetical

    Buildings 1

    Appendix D: Further Reading 1

    1Introduction 1

    2.2.1 The Client Context 1

    2.2.2 The Life Cycle Costing Calculation 5

    2.2.3 Tax Allowances, Incentives and Business Rates 10

    2.2.4 Data Sources 14

    2.2.5 Worked Examples 15

    Appendix A: Residual Values 1

    Appendix B: Obsolescence 1

    Appendix C: Costs And Values 1

    Appendix D: Glossary of Terms for Taxation 1

    Appendix E: Examples of Items of Expenditure Likely to Attract

    Taxation Allowances 1

    Appendix F: Further Reading 1

    1Introduction 1

    2.3.1 Elements 1

    2.3.2 Elemental Cost Analysis 1

    2.3.3 Other Uses 2

    Appendix A: BCIS Standard Elements 1

    1Introduction 1

    2.4.1 Background 2

    2.4.2 Contract Documentation 3

    2.4.3 Additional Services 3

    2.4.4 Employers Requirements and Contractors Proposals

    (including contract sum analysis) 5

    2.4.5 Design and Build Variants 6

    2.4.6 Novation 8

    Appendix A: Potential Services Associated with the Role

    of Employers Agent 1

    Appendix B: Employers Requirements/Contractors Proposal Checklist 1

  • 8/12/2019 Construction Handbook[1]

    7/479

    The Surveyors Construction Handbook Contents (12/03) Page 3

    1Introduction 1

    2.5.1 Definitions: The Difference Between a Project Manager and

    Lead Consultant 1

    2.5.2 Benefits of Appointing a Chartered Surveyor as Lead Consultant 22.5.3 Issues to Consider before Undertaking the Role 3

    2.5.4 Schedule of Lead Consultant Duties 3

    1Introduction 1

    2.6.1 Technology Swaps 2

    2.6.2 How Can the Environment and Sustainability be Valued? 3

    2.6.3 How Does This Effect the Construction Industry? 4

    2.6.4 Green Building Materials 7

    2.6.5 Whole Building Sustainability 8

    2.6.6 The Government Line 9

    2.6.7 What Might the Future Hold 11Appendix A: Embodied Energy Content of Building Material 1

    Appendix B: Useful Addresses 1

    1Introduction 1

    3.1.1 The Clients Role 2

    3.1.2 Procurement Strategy 12

    3.1.3 Selection of Most Appropriate Procurement Strategy 25

    3.1.4 Implementation 29

    Appendix A: Procurement Options 1

    1Introduction 1

    3.2.1 Appointing the Building Services Designer 3

    3.2.2 Design Coordination 11

    3.2.3 Appointing a Building Services Contractor 19

    3.2.4 Tender Documents 34

    Appendix A: Typical Example 1

    1Introduction 1

    4.1.1 What Happens in Practice 1

    4.1.2 Standard Form Approaches 3

    4.1.3 Effects of Practical Completion 13

    4.1.4 Methods for Dealing with Practical Completion 14

    4.1.5 Definitions 16

    4.1.6 Subsidiary Issues 20

    Appendix A: General Objectives to be Achieved at Practical

    Completion for Small to Medium-sized Building Projects 1

    Appendix B: Table of Cases 1

    Appendix C: Further Reading 1

  • 8/12/2019 Construction Handbook[1]

    8/479

    Page 4 Contents (12/03) The Surveyors Construction Handbook

    1Introduction 1

    4.2.1 General Principles 1

    4.2.2 Definitions 44.2.3 Entitlement 4

    4.2.4 Ascertainment 7

    4.2.5 Admissible Items 9

    4.2.6 Inadmissible Items 13

    Appendix A: Ascertaining the Cost of Running a Site 1

    Appendix B: Disruption 1

    Appendix C: Ascertaining the Cost of Head Office Overheads 1

    Appendix D: Checklist of Items for which Loss and/or Expense are

    Allowed 1

    Appendix E: Checklist of Steps Required when Considering

    Submissions by Contractor 1

    Appendix F: Further Reading 1

    1Introduction 1

    4.3.1 Definitions 2

    4.3.2 The Rationale for Risk Management in the Construction Process 2

    4.3.3 The Risk Management Process 5

    4.3.4 Summary 14

    Appendix A: Further Reading 1

    1Introduction 1

    4.4.1 Valuations 1

    4.4.2 Assumptions 2

    4.4.3 Valuation Under a JCT Contract: Background 3

    4.4.4 Recommended Action at the Start of a Contract 4

    4.4.5 Communications 5

    4.4.6 Approach 6

    4.4.7 Content of a Valuation 8

    4.4.8 Administration 15

    4.4.9 Special Situations 16

    4.4.10 Other Contract Terms (relative to valuations) 17

    4.4.11 Valuations Under Other Forms of Contract 18

    Appendix A: Further Reading 1

    Appendix B: JCT Definition of Reasonable Proof 1Appendix C: Example of Priced Activity Schedule 1

    1Introduction 1

    4.5.1 Extension of Time Clauses 2

    4.5.2 Assumptions 2

    4.5.3 Extension of Time Under a JCT Contract 3

    4.5.4 Notice by the Contractor of Delay to Progress 4

    4.5.5 The Award of an Extension of Time during the Contract

    Period and Before the Completion Date 5

    4.5.6 The Award of an Extension of Time after the Completion Date 6

    4.5.7 Relevant Events 7

    4.5.8 Concurrent Delays 12

    4.5.9 Consequential Entitlement 13

  • 8/12/2019 Construction Handbook[1]

    9/479

    The Surveyors Construction Handbook Contents (12/03) Page 5

    4.5.10 Administration 13

    4.5.11 Extension of Time under an ICE Contract 14

    4.5.12 Extension of Time under a GC Works Contract 14

    Appendix A: Further Reading 1

    1

    15.2.1 Schedule of Sources of Useful CDM Information 2

    1

    15.4.3 BCIS Online 1

    5.4.4 Other BCIS Publications and Services 2

    5.4.5 Further details 4

    15.5.2 BMI Quarterly Cost Briefing 1

    5.5.3 Building Maintenance Price Book 1

    5.5.4 Special Reports for Benchmarking 2

    5.5.5 News, Digests and Reports 2

    1Introduction 1

    5.6.1 Code of Practice DISC PD 0008: 1999 2

    5.6.2 Weight of evidence and document destruction 3

    5.6.3 Authenticity 3

    5.6.4 Photocopies, microfilm and image processing 4

    5.6.5 Document storage 45.6.6 Storage and access procedures 5

    5.6.7 Format of the Code of Practice 6

    5.6.8 Conclusion 20

    Appendix A: Specimen form for recording scanning information 1

    Appendix B: Specimen form for recording retrieval 1

    Appendix C: References 1

    1

  • 8/12/2019 Construction Handbook[1]

    10/479

    The Surveyors Construction Handbook Abbreviations (10/02) Page 1

    LIST OF ABBREVIATIONS

    ABE Association of Building Engineers

    ABI Association of British InsurersACA Association of Consultant Architects

    ACE Association of Consulting Engineers

    AQL Acceptable quality level

    BCIS Building Cost Information Service

    BEC Building Employers Confederation

    BMI Building Maintenance Information

    BRE Building Research Establishment

    BRECSU Building Research Energy Conservation Support Unit

    BREEAM Building Research Establishment Environmental

    Assessment Method

    BSI Building Standards InstitutionBSRIA Building Services Research and Information Association

    BWIC Builders Work in Connection

    CA Contract Administrator

    CAWS Common Arrangement of Works Section for Building

    Works

    CDM Construction (Design and Management)

    CD-R Compact disc recordable

    CECA Civil Engineering Contractors Association

    CIB Construction Industry Board

    CIBSE Chartered Institution of Building Services Engineers

    CIC Construction Industry CouncilCIRIA Construction Industry Research and Information

    Association

    CITES Control in Trade of Endangered Species

    CCT Compulsory Competitive Tendering

    CSM Chartered Surveyors Monthly

    DBFO Design Build Fund and Operate

    DoE Department of the Environment (now known as the

    DETR)

    DETR Department of the Environment, Transport and the

    Regions (formerly the DoE)

    DMS Document Management SystemDOM Domestic Sub-Contract

    EC European Commission

    EU European Union

    FAST Functional Analysis Systems Technique

    FCEC Federation of Civil Engineering Contractors

    GNP Gross National Product

    HBF House Builders Federation

    HMSO Her Majestys Stationery Office (now known as

    The Stationery Office)

    HSE Health and Safety Executive

    IChemE Institution of Chemical Engineers

    ICE Institution of Civil Engineers

    IDMA Information and Document Management Association

  • 8/12/2019 Construction Handbook[1]

    11/479

    Page 2 Abbreviations (10/02) The Surveyors Construction Handbook

    IFC Intermediage Form of Contract

    JCT Joint Contracts Tribunal

    LCC Life Cycle Costing

    LQ Limiting quality

    M& E Mechanical and Electrical

    MERA Multiple Estimate Risk Anaylsis

    MW Minor Works

    NEC New Engineering Contract

    NEDO National Economics Development Office

    NJCC National Joint Consultative Committee for Building

    NSC Nominated Sub-Contract

    OMR Optical Mark Reading

    PFI Private Finance Initiative

    PSA Property Services Agency

    RIBA Royal Institute of British Architects

    RICS Royal Institution of Chartered SurveyorsVAT Value Added Tax

    WCD With Contractors Design

    WORM Write-Once-Read-Many

    WRC Water Research Centre

  • 8/12/2019 Construction Handbook[1]

    12/479

    INTRODUCTION

    The Surveyors Construction Handbook Introduction (4/98) Effective from 1/6/98 Page 1

    INTRODUCTION

    A Aim and Scope of this Handbook

    A1 The aim of this Handbook is to help both building and quantity surveyors to

    provide construction-related professional services effectively and efficiently.

    It seeks to achieve this by providing guidance which reflects what is often

    good custom and practice, and relevant information (including references to

    other useful material). It should be appreciated that this Handbook does not

    attempt comprehensive coverage of necessary or good practice. The

    Handbook is addressed to surveyors providing services to clients (as defined),

    not surveyors undertaking the role of the clients representative who gives

    instructions to surveyors on behalf of the Client.

    A2 Construction in this Handbook means new construction, conversion,

    refurbishment works and alterations to the form of buildings, and also civil

    engineering works. The contents of this Handbook apply across the complete

    range of this definition unless otherwise stated. So construction does not

    embrace building surveys or building maintenance.

    A3 Client in this Handbook is used to include companies and their Directors or

    Officers, Trusts and their Trustees, partners, managers and employees who

    may instruct a surveyor.

    A4 Throughout the Handbook, it is assumed that possession and necessary access

    to the site are available and, in principle, the rights to construct the

    development and use the buildings when constructed. The Handbook does not

    cover project management services, obtaining planning permission and

    building regulation approvals, or dispute resolution.

    A5 The document is drafted on the basis of UK law and practice, although much

    of it is relevant to practice elsewhere.

    B Arrangement of Content

    B1 After sets of Definitions and Abbreviations which apply throughout, the

    Handbook is arranged in five Parts. The first four Parts represent sequential

    phases of the construction process. The last Part, Part 5, provides Additional

    Guidance and Information. Each part is followed by Further Reading, to

    which the numbered cross references in the Parts apply.

    B2 The first four Parts are as follows:

    Part 1: The Client seeks to help surveyors to work with clients. It discusses the

    establishment of their construction objectives and constraints, leading to the

  • 8/12/2019 Construction Handbook[1]

    13/479

    INTRODUCTION

    Page 2 Introduction (4/98) Effective from 1/6/98 The Surveyors Construction Handbook

    development of construction briefs. It defines the clients roles during the

    construction process, and comments on the engagement of professionals

    involved in the construction process.

    Part 2: Construction Design and Economics covers development of the design

    concept, feasibility studies, design and economics (including life-cycle

    costing, risk assessment, and cost-value relationships), and confirmation of

    the final design proposal.

    Part 3 relates to Construction Planning and Procurement, i.e. to the time the

    construction contract is placed.

    Part 4 covers Construction Administration and Management, i.e. all

    post-contract matters.

    Any Appendices are situated at the end of each Part.

    B3 An Index follows Part 5.

    C Status of Content

    C1 For convenience, Guidance and Information is integrated. Each paragraph is

    prefixed with a or an to indicate its status.

    C2 Guidance, as the word implies advice to Members of the RICS on aspects of

    their profession. Where recommended for specific professional tasks,

    procedures are intended to embody best practice, i.e. procedures which in

    the opinion of the RICS meet a high standard of professional competence.

    Members are not required to follow the advice and recommendations

    contained in such paragraphs. They should, however, note the following

    points.

    Should an allegation of professional negligence be made against a surveyor,

    the Court is likely to take account of the contents of any relevant guidancenotes published by the RICS in deciding whether or not the surveyor had acted

    with reasonable competence.

    In the opinion of the RICS, a Member conforming to the practices

    recommended in this Note should have at least a partial defence to an

    allegation of negligence by virtue of having followed those practices.

    However, Members have the responsibility of deciding when it is appropriate

    to follow the guidance. If the guidance has been followed in an appropriate

    case, the Member will not necessarily be exonerated merely because the

    recommendations were found in RICS Guidance.

    G I

  • 8/12/2019 Construction Handbook[1]

    14/479

    INTRODUCTION

    The Surveyors Construction Handbook Introduction (revised 10/01) Effective from 1/12/01 Page 3

    On the other hand, it does not follow that a Member will be adjudged

    negligent if he has not followed the practices recommended in this Handbook.

    It is the responsibility of each individual surveyor to decide on the appropriate

    procedure to follow in any professional task. However, where Members

    depart from any practices recommended in this Handbook, they should do so

    only for good reason. In the event of litigation, the Court may require them to

    explain why they decided not to adopt a recommended practice.

    In addition, Guidance Notes are relevant to professional competence in that

    each surveyor should be up to date and should have informed himself of

    Guidance Notes within a reasonable time of their promulgation.

    C3 Material classified as information is intended to provide information and

    explanations to Members of the RICS on specific topics of relevance to the

    profession. The function is not to recommend or advise on professional

    procedures to be followed by surveyors. It is again, however, relevant toprofessional competence to the extent that a surveyor should be up to date and

    should have informed himself of such information within a reasonable time of

    its promulgation.

    Members should note that if an allegation of professional negligence is made

    against a surveyor, the Court is likely to take account of the contents of any

    relevant information published by the RICS in deciding whether or not the

    surveyor has acted with reasonable competence.

    D Currency of ReferencesThe cases cited and the editions quoted were up-to-date at the time of writing.

    However, readers should check current rulings and additions.

    E Invitation

    RICS Books would welcome comments upon and suggestions for additions

    and amendments to this Handbook. They should be provided in writing to

    RICS Books Publishing, Surveyor Court, Westwood Business Park,

    Coventry, CV4 8JE.

    F Subscription Service

    Any change of address should be notified to the address appearing below:

    The Surveyors Construction Handbook Subscription Service

    RICS Books

    Surveyor Court

    Westwood Business Park

    Coventry CV4 8JE

    Tel: 020 7222 7000 ext 647

  • 8/12/2019 Construction Handbook[1]

    15/479

  • 8/12/2019 Construction Handbook[1]

    16/479

    PART1, SECTION1

    Page 2 Part 1, Section 1 (01/03) Effective from 1/3/03 The Surveyors Construction Handbook

    (b) Marketability

    maximise prompt or future disposal (freehold or otherwise).

    (c) Use-related

    optimise operational requirements of intended occupier(s)

    provide greatest flexibility in potential uses

    reflect intended occupiers requirements/preferences/ability to afford

    meet social/management/occupiers special needs (e.g. disabled).

    (d) Environmental

    minimise health and safety risks

    choose materials which reflect sustainability

    aesthetically please (e.g. impression on occupiers customers)

    minimise any alterations to specific features

    reflect planning authoritys brief/policies minimise potential opposition

    reflect corporate style or personal preferences of proposed

    occupier/employees

    maximise comfort of occupants

    minimise inconvenience to others during construction.

    (e) Timing

    construct within a defined period

    minimise risks of delay during construction.

    1.1.1.6 The importance of each of these criteria will be relative to the objectives of theclient, the business case for the project and to the extent to which he/she is

    able to cope with risk (see 3.1.2.9). It is important that the client seek

    investment appraisal advice in respect of the project and that the appraisal

    considers what if questions to ensure that the impact of changes of key

    components in the appraisal is clearly understood. A chartered surveyor will

    be able to assist the client in these matters. However, the giving of advice on

    some of the requirements listed above is, of course, outside the competence of

    the surveyor. Where such a particular requirement is important to the client

    and outside the clients expertise, the client should be advised to seek other

    professional advice.

    1.1.1.7 Many construction projects suffer from poor definition due to inadequate time

    and thought being given at an early stage1. This is often because there is a

    sense of urgency fuelled by the desire for an immediate solution. Investing

    time at the beginning of a project in developing a complete definition taking

    account of all the requirements will reduce the likelihood of changes later. The

    later that changes are made in a project, the more they are likely to cost in both

    direct and knock-on effects (see 3.1.4.14 and 3.1.2.14(f) & (g)).

    G

    G

    1 Construction Industry Board,Briefing the Team, Thomas Telford Publishing, London, 1997.

  • 8/12/2019 Construction Handbook[1]

    17/479

    PART1, SECTION1

    The Surveyors Construction Handbook Part 1, Section 1 (01/03) Effective from 1/3/03 Page 3

    1.1.2 The Role for Independent Advice

    1.1.2.1 With the potential for the involvement of many consultants and/or

    constructors in a project and the range of contracts associated with theiremployment, all but the most experienced client may need advice. The advice

    offered should be informed and unbiased and it should be based upon a logical

    analysis of the needs of the client, the type and character of the project and the

    range of appropriate strategies available.

    1.1.2.2 This advice can be offered by a member of the clients design team or can be

    a separate function. It may be more difficult for a design team member to

    remain impartial in carrying out this process and it is recommended that any

    expert retained should be solely for this purpose. This function can be

    identified as the role of the principal adviser and may encompass:

    Assistance in preparing the business case (the business case)

    underpinning the project

    Identifying the needs and requirements (briefing)

    of the client

    Defining the project (project definition)

    Matching needs and project characteristics (procurement strategy)

    with appropriate procurement strategy

    Facilitating the associated selection and (implementation)

    contractual processes and policies

    1.1.2.3 Possible sources for the appointment of independent advisers include suitably

    qualified and experienced construction professionals such as chartered

    surveyors.

    1.1.3 Project Brief

    1.1.3.1 The importance of a clear project brief to the successful completion of the

    project and in ensuring appropriate performance of the project cannot be over

    emphasised. The inexperienced client will need professional help in the

    preparation of the brief. The project brief is a comprehensive statement of the

    clients requirements for the project based on close consultation between the

    client and users and based upon the parameters established (see 3.1.1.10 and

    3.1.1.12).

    The project brief may include:

    (a) project description;

    (b) how it fits into the clients corporate plan (e.g. it may be part of a larger

    planned development);

    G

    G

    I

    G

  • 8/12/2019 Construction Handbook[1]

    18/479

    PART1, SECTION1

    Page 4 Part 1, Section 1 (01/03) Effective from 1/3/03 The Surveyors Construction Handbook

    (c) number of people that are to occupy the building, together with their space

    requirements;

    (d) schedule of accommodation and quality of internal environment;

    (e) standards;

    (f) equipment and special services/requirements;

    (g) when the building needs to be available for use;

    (h) quality and cost limitations;

    (i) life span;

    (j) site; and

    (k) statutory controls.

    1.1.3.2 This is the initial control document for the early planning of the project;

    without it, little constructive work can be done. If all the information required

    for the project brief is not readily available, it is better to issue it in an

    incomplete form and to update it progressively1.

    1.1.4 The Clients Role

    1.1.4.1 This section briefly explains the clients responsibilities through the life of a

    construction project. In carrying out their role, clients, depending on their

    knowledge and expertise, will need help from their professional advisers,

    project managers and other consultants, whose roles are also explained in this

    handbook. This section aims to outline the clients task in setting policy and

    formulating strategy, and explains how it should be carried out.

    1.1.4.2 The success of any project will depend upon the motivation given by the

    client. Experienced clients may take a leading role in the procurement process;

    less experienced clients will need to seek advice or to appoint advisers to

    assist them. Where projects are of a large or complex nature it may be

    advisable to consider the appointment of a project manager.

    1.1.4.3 Effective management is vital in any construction project. The clients prime

    role is to establish a structure for the management of the project and to make

    sure that it works. A crucial part of any effective management structure is

    efficient communication. To perform effectively, all parties must have timely

    G

    1 Construction Industry Board,Briefing the Team, Thomas Telford Publishing, London, 1997.

    G

    G

    G

  • 8/12/2019 Construction Handbook[1]

    19/479

    PART1, SECTION1

    The Surveyors Construction Handbook Part 1, Section 1 (01/03) Effective from 1/3/03 Page 5

    access to all information relevant to their tasks and the projects objectives and

    status (see 3.1.4.11).

    1.1.4.4 The client has substantial influence on the design of the project in respect both

    of functional efficiency and of overall appearance, and, therefore, has to take

    particular care to:

    (a) understand fully the purpose of the building; ensure that the requirements

    of the users are accommodated; and communicate those requirements to the

    designers (see 3.1.1.10); and

    (b) appoint designers with proven ability in designing buildings which satisfy

    users requirements and harmonise with and contribute to the quality of the

    built environment. The selection of the right people is emphasised as a key to

    success (see 3.1.4.8).

    1.1.4.5 The accompanying figure indicates the activities in the procurement process

    and when activities are usually performed. As can be seen, the clients role is

    significant, with a wide range of activities to perform and implement before

    both the design and the construction processes. In the performance of these

    activities, the client can expect to be supported and advised by his/her adviser

    or (if appointed) the project manager. More detail for each of these activities

    can be found in the section of this handbook indicated in brackets in the

    figure.

    G

    G

  • 8/12/2019 Construction Handbook[1]

    20/479

    PART1, SECTION1

    Page 6 Part 1, Section 1 (01/03) Effective from 1/3/03 The Surveyors Construction Handbook

    1.1.5 The Clients Responsibilities

    1.1.5.1 The client should set policy and outline strategy including:

    (a) setting and prioritising the project objectives within the business plan;

    (b) planing to meet the objectives (the pre-design phase);

    (c) implementing the plans (the pre-construction phase);

    (d) controlling their implementation (the construction phase);

    FIGURE TO INDICATE THE ACTIVITIES IN THE PROCUREMENT PROCESS

    Pre-Design Phase Pre-Construction Phase Construction Post-Construction

    Clients Role Develop business case for

    project (3.1.1.9)

    Appoint adviser

    (3.1.1.6)

    Define clients

    responsibilities (3.1.1.7)

    Project Brief

    (3.1.1.12)

    Appointment of PM (if

    appropriate) (3.1.4.7)

    Appointment of design and

    cost consultants (3.1.4.8)

    Procurement strategy*

    (3.1.1.13)

    Value management

    (3.1.4.16)

    Procurement strategy

    (3.1.1.13)

    Design overview*

    (3.1.4.12)

    Cost Control overview*

    (3.1.4.13)

    Whole-life Costs

    (3.1.4.15)

    Value Engineering

    (3.1.4.17)

    Time control overview*

    (3.1.4.14)

    Quality control overview*

    (3.1.4.18)

    Appointment of constructors

    (3.1.4.9)

    Confirming the business

    case (3.1.1.9)

    Design overview

    (3.1.4.12)

    Cost control overview

    (3.1.4.13)

    Time control overview

    (3.1.4.14)

    Quality control overview

    (3.1.4.18)

    Change control

    overview

    (3.1.4.19)

    Commissioning

    (3.1.1.17)

    Occupation and takeover

    (3.1.1.18)

    Procurement

    Strategy

    Procurement strategy

    development (3.1.2)

    Implementation Resources (Client)

    (3.1.4.35)

    Organisational structure

    (3.1.4.6)

    Contractual arrangements*

    (3.1.4.10)

    Systems and controls*

    (3.1.4.11)

    Implementation policy

    (3.1.4.2)

    Contractual arrangements

    (3.1.4.10)

    Systems and controls

    (3.1.4.11)

    Systems and controls

    (3.1.4.11)

    * Indicates the activity will continue into the next phase

    ( ) Indicates the section of this document referring to the activity in more detail

    G

  • 8/12/2019 Construction Handbook[1]

    21/479

    PART1, SECTION1

    The Surveyors Construction Handbook Part 1, Section 1 (01/03) Effective from 1/3/03 Page 7

    (e) arbitrating between conflicting demands; and

    (f) evaluating the complete project against the objectives (the

    post-construction phase).

    1.1.5.2 The client also has a dual management function:

    (a) to manage the client input; to co-ordinate functional and administrative

    needs; to resolve conflicts; to act as the formal point of contact for the project

    (see 3.1.4.11); and

    (b) to supply the technical expertise, to assess, procure, monitor and control

    the external resources needed to implement the project (see 3.1.4.35).

    1.1.5.3 In particular, the client should be satisfied that:

    (a) the project brief is comprehensive and clear and has the full support of the

    users1&2 (see 3.1.1.12);

    (b) any constraints demanded by the project funder(s) are known and their

    impact understood;

    (c) the critical assumptions made in preparing the initial estimates and

    programmes are valid, realistic and achievable (see 3.1.1.9);

    (d) cost estimates are comprehensive and include all capital and resource

    costs;

    (e) allowances made in the feasibility and viability assessments to cover

    possible risks are sufficient (contingency allowance);

    (f) substantial sensitivity analysis and what if studies have been carried out

    to assess the effect of possible changed criteria on the viability of the project;

    and

    (g) plans are in place for adequate project management including systems forcost, time, quality and change control.

    1.1.5.4 The client should also co-ordinate and resolve conflicts between all interested

    sections of the client organisation including (see 3.1.4.6):

    (a) user groups who will work in the building;

    G

    G

    1 Kelly, J., MacPherson, S., and Male, S. (1992), The Briefing Process: A Review and Critique, RICS, Department ofBuilding Engineering and Surveying, Heriot Watt University. This document is out of print.2 Construction Industry Board,Briefing the Team, Thomas Telford Publishing, London, 1997.

    G

  • 8/12/2019 Construction Handbook[1]

    22/479

    PART1, SECTION1

    Page 8 Part 1, Section 1 (01/03) Effective from 1/3/03 The Surveyors Construction Handbook

    (b) specialist groups responsible for technical systems within the building,

    e.g. communications, computers;

    (c) facilities management who will manage the completed buildingincluding maintenance and security;

    (d) finance and accounts who will plan and control expenditure and pay bills

    as they arise; and

    (e) legal advisers who will advise on and monitor the clients formal

    relationships with outside parties.

    1.1.5.5 The client is responsible for ensuring that all necessary decisions are made on

    time. Timely decisions are necessary to avoid delays and increased costs: the

    decision-making process requires as much planning and management as anyother activity. This will include (see 3.1.4.11):

    (a) scheduling the key decisions to be made;

    (b) identifying the decision makers and their required procedures;

    (c) ascertaining the time required for making decisions;

    (d) establishing a formal programme for decisions;

    (e) warning decision makers regarding forthcoming submissions making

    sure items are on the agenda;

    (f) preparing on time fully detailed submissions and/or presentations in full

    compliance with procedural requirements;

    (g) following up submissions throughout the decision making process; and

    (h) promptly communicating decisions made to the parties affected by

    them.

    1.1.6 Appointment of Project Manager (where appropriate)

    (see 3.1.4.7)

    1.1.6.1 Due to the complexity of modern buildings and the potentially large number

    of parties involved in the process the client may wish to appoint a single

    person to draw the process together and manage it to ensure that the overall

    performance, time, cost and quality requirements are achieved. The project

    manager may be a member of the client organisation who is given sole, or

    predominant, responsibility for the project. Project management practices also

    exist to enable appointment to be made on a consultancy basis. In this case,

    G

    G

  • 8/12/2019 Construction Handbook[1]

    23/479

    PART1, SECTION1

    The Surveyors Construction Handbook Part 1, Section 1 (01/03) Effective from 1/3/03 Page 9

    selection should be based upon resources, reputation, and price; and services

    should be clearly identified.

    1.1.6.2 It should be emphasised that the role of the project manager should be to act

    as part of the client organisation.

    1.1.7 Appointment of Consultants (see 3.1.4.8)

    The process of selecting and appointing the design team and the cost

    consultant is carried out by the client who may seek the advice of his/her

    advisers. The terms and conditions of these appointments are governed by the

    procurement strategy adopted for the project.

    1.1.8 Appointment of Constructors (see 3.1.4.9)

    The selection of those who will actually construct the project is often key to a

    successful outcome. Selection should always be on quality as well as price and

    ideally the procurement strategy governing when they are appointed should

    facilitate the early involvement of constructors in the design process.

    The selection of procurement strategy is a complex one and is referred to in

    Part 3 section 1 of this handbook.

    G

    G

    G

  • 8/12/2019 Construction Handbook[1]

    24/479

    PART1, SECTION1, APPENDIXA

    The Surveyors Construction Handbook Part 1, Section 1 Effective from 1/3/03 Page 1

    A endix A (01/03)

    Appendix A: Further Reading

    Construction Industry Board,Briefing the Team, Thomas Telford Publishing, London,

    1997

    Construction Industry Board, Partnering in the Team, Thomas Telford Publishing,

    London, 1997

    Construction Industry Board, Selecting Consultants for the Team: Balancing Quality

    and Price, Thomas Telford Publishing, London, 1997

    Construction Industry Council,The Procurement of Professional Services: Guidelines

    for the Value Assessment of Competitive Tenders, CIC, London, 1997

    European Construction Institute, Partnering in the Public Sector: a Toolkit for theImplementation of Post-Award, Project Specific Partnering on Construction Projects,

    ECI, Loughborough, 1997

    Kelly, J., MacPherson, S., and Male, S.,The Briefing Process: A Review and Critique,

    RICS, Department of Building Engineering and Surveying, Heriot Watt University,

    1992. This document is out of print.

  • 8/12/2019 Construction Handbook[1]

    25/479

    PART 1, SECTION 2

    The Surveyors Construction Handbook Part 1, Section 2 (12/99) Effective from 1/1/00 Page 1

    PART ONE: THE CLIENT

    SECTION 2: VALUE ENGINEERING

    Introduction

    Value management (and within it, value engineering) is a structured method

    of eliminating waste from a clients brief and from the design on a

    construction project before binding commitments are made. Used to deliver

    more effective and better quality buildings, for example, through taking

    unnecessary costs out of designs, value management ensures a clearer

    understanding of the brief by all project participants and improves team

    working. According to the Construction Task Force report, RethinkingConstruction (published by the DETR in July 1998) it is practiced by up to a

    quarter of the construction industry in the UK. The report also estimates that

    while the objective of value management is to increase value, it can also

    reduce costs by up to 10 per cent.

    Value management is the wider term used in the UK to describe the overall

    structured team-based approach to a construction project. It involves clearly

    defining the clients strategic objectives, considering optimum design

    solutions within the context of the clients business objectives and deciding

    which of these provides the optimum lifetime value to the client, as well as a

    review of the whole process after occupancy. Value management includesvalue engineering as part of this process.

    Value engineering is a systematic approach to delivering the required

    functions to the required quality at the least cost, i.e. a method of ensuring

    that the client gets the best possible value for money in terms of safety,

    performance and delivery targets. It is a structured form of consensus

    decision making that compares and assesses the design solutions against the

    value systems declared by the client.

    This section of the handbook looks at the carrying out of a value engineering

    exercise during the early design phase of a project, i.e. an evaluation of design

    solutions against the clients brief. Value engineering, as described here, can

    be a stand-alone exercise (a value engineering workshop) or may be part of an

    overall value management process.

    In describing the value engineering process this section aims to assist

    surveyors both in advising clients on the use of value engineering and taking

    part in a value engineering exercise as part of the design team. It is not

    intended for surveyors acting as value engineering facilitators and makes no

    attempt to address the very particular skills required for this role.

  • 8/12/2019 Construction Handbook[1]

    26/479

    PART 1, SECTION 2

    1.2.1 Why Value Engineering?

    1.2.1.1 Value engineering has grown in popularity for the simple reason that it

    actually works. Construction projects can often take on a life of their own

    when members of the design team become focused on their own particular

    problems and time constraints. Consequently, the true objectives of the client

    get lost along the way. Value engineering relates design proposals directly

    back to a clients business, thus ensuring that a management system is in place

    which forces designers to justify their decisions when tested against the

    clients required function.

    1.2.1.2 A value engineering exercise can only relate design proposals to a clients

    business requirements if early value management studies have encapsulated

    these requirements within the brief. If a value engineering exercise is carried

    out in isolation from any strategic review of the project requirements, it canonly act as a functional assessment of the technical design solutions and their

    relative cost. However, even in this limited function it can still be very useful.

    1.2.2 Applicability

    1.2.2.1 The technique of value engineering can be employed on any project. However,

    more complicated and higher value buildings are likely to benefit the most

    (seefigure 1). This is because it is more difficult to develop the design brief

    in such instances and consequently a design solution may be adopted without

    being questioned, usually because of time constraints placed upon thedesigners.

    1.2.2.2 Many client organisations will only undertake value engineering on schemes

    over a certain value. For example, Railtrack will carry out the technique on

    projects valued at 250,000 or more and Northumbrian Water will only

    consider it for projects worth over 1m. Despite this, there is no reason why

    the process should not be applied to smaller schemes. Furthermore, value

    engineering will be invaluable where repetitive schemes are being considered

    Page 2 Part 1, Section 2 (12/99) Effective from 1/1/00 The Surveyors Construction Handbook

    G

    G

    Optional

    EssentialHigh

    Complexity

    Low

    Value

    Low High

    Figure 1: Projects Benefiting from Value Engineering

  • 8/12/2019 Construction Handbook[1]

    27/479

    PART1, SECTION2

    The Surveyors Construction Handbook Part 1, Section 2 (revised 10/01) Effective from 1/12/01 Page 3

    as improvements and savings can be incorporated into future schemes. They

    can also be tested in practice, leading to the sort of continuous improvement

    recommended by the Rethinking Construction report.

    1.2.2.3 Value engineering works irrespective of the procurement route taken. It is a

    discipline upon the design team members and the clients who appoint them.

    Where the contractor is mainly responsible for the design, for example, design

    and build, develop and construct or PFI projects, the technique is just as

    appropriate in ensuring that a well-defined statement of requirements is first

    established and that subsequent design solutions address the function of the

    building most economically.

    1.2.3 At What Stage Should Value Engineering be Carried Out?

    1.2.3.1 The greatest benefits can be obtained by commencing the VE process at the

    earliest possible stage. Once it has been established that the clients needs will

    best be met through a construction project the purpose of the first VE exercise

    should be to inform the brief. When an experienced client has prepared the

    brief, or a value management exercise has already examined the clients

    requirements, the value engineering exercise (which will address the proposed

    design solutions) is best done towards the end of the scheme design. Several

    workshops may be necessary at each of the crucial decision-making stages of

    a project:

    (a) A first exercise (a functional analysis of requirements), to define the

    project needs and inform the brief, could be carried out as early as option

    appraisal, and since this could generate the greatest benefit to the client the

    timing is crucial. Carry it out too early and not enough will be known about

    the problems associated with the building function, whereas too late and

    minds become set on the solutions formulated by the design team.

    (b) A review of the project at outline design could be conducted to ensure

    that the decisions taken earlier have been implemented or, if changed, that

    they still meet the functional requirements.

    (c) Another review (a functional analysis of the solutions) would then be

    carried out at scheme design to test individual building elements involvingtraditional cost planning/life cycle costing techniques.

    1.2.3.2 This section of the handbook considers the evaluation of a design at the end of

    the scheme design phase, but the process will be the same whenever it is

    carried out. The objectives of the project should remain the same throughout

    the process and they should be validated at the beginning of each workshop.

    The objectives of each workshop may be different. If the project objectives do

    change the whole direction of the project will need to reassessed.

    1.2.3.3 It is important that time for the value engineering process and any resultant

    redesign is included in the scheme design programme at the outset.

    G

  • 8/12/2019 Construction Handbook[1]

    28/479

    PART1, SECTION2

    Page 4 Part 1, Section 2 (revised 10/01) Effective from 1/12/01 The Surveyors Construction Handbook

    1.2.4 Who Should Carry Out Value Engineering?

    1.2.4.1 It is strongly recommended that a value engineering exercise is organized by

    an experienced value management facilitator to ensure that the valueengineering participants retain their objectivity and that an unbiased approach

    is maintained.

    1.2.4.2 The value engineering participants should represent the principal stakeholders

    in the project namely, the client, the building users and the design team

    (designer, engineers and quantity surveyor) and also the contractor, where

    applicable. It is important that each of the participants have the authority to

    make decisions at the workshop. It may also be appropriate to include clients

    advisers, for example, letting agents or rating valuers.

    The participants should be those who can make decisions and provideinformation related to the specific aims and objectives of the workshop. These

    may include:

    those people with responsibility for the needs of the business;

    those with specific responsibility for development, design and

    implementation of the operation/project;

    those with responsibility for the management and/or maintenance of the

    operation; and

    those who will be affected by the outcome.

    Different stakeholders will be required to participate at different stages of the

    project.

    1.2.4.3 The optimum size of a value engineering panel would depend upon the

    complexity of the project as well as the skills of the facilitator. However, it is

    considered that panels of more than twelve members are difficult to manage.

    Panels with fewer than four members could be considered ineffective.

    However, it is important that all stakeholders are represented even if this

    results in a larger group.

    1.2.4.4 It is common practice in North America to appoint an outside team of

    consultants to question the design teams solutions. However, this practice has

    been known to cause resentment between the project team and the external

    advisers and might therefore compromise the final design solutions. It is

    considered that an experienced facilitator independent of the design team,

    with an appropriately briefed panel, will ensure that the design teams

    solutions are adequately tested at the workshop.

    G

  • 8/12/2019 Construction Handbook[1]

    29/479

    PART1, SECTION2

    The Surveyors Construction Handbook Part 1, Section 2 (revised 10/01) Effective from 1/12/01 Page 5

    1.2.5 How Long Should It Last?

    1.2.5.1 The length of time taken over the value engineering workshop will depend on

    the complexity of the project and the level of design detail that has beencompleted.

    1.2.5.2 The 40-hour workshop is the classic industrial value engineering standard.

    However, two-day workshops at key points during the design process are

    more common in the UK construction industry.

    1.2.6 Preparing for a Value Engineering Workshop

    1.2.6.1 Prior to the workshop, it is most important that an agenda is agreed by the

    panel and distributed by the facilitator.

    1.2.6.2 In addition to an agenda, a functional analysis of the clients requirements

    should be drawn up.

    The clients value criteria will have been developed in the first value

    management workshop. With each successive workshop these criteria will be

    developed further into a function diagram. This should be included in the

    workshop handbook. If it is to be developed further this will take place as part

    of the information stage of the workshop.

    The functional analysis should always be generated by the clientrepresentatives with the help of the other members of the workshop. It is the

    role of the facilitator to facilitate this process, not to take part in it.

    All participants must be prepared to propose and challenge design solutions.

    The input of all participants (not just those who are experts in a particular

    discipline) is one of the strengths of the VE process and should be encouraged

    by the facilitator.

    1.2.7 Functional Analysis of Design Relative to the Clients

    Requirements

    1.2.7.1 It should be understood that it is not possible to find meaningful alternatives

    to a technical solution without first identifying the function required of it.

    1.2.7.2 Functional analysis is any technique designed to appraise value by careful

    analysis of function. This can be simple creative session of the functions and

    possible alternatives, but the most common method is using a functional

    analysis systems technique (FAST) diagram.

    1.2.7.3 The FAST system uses a function diagram which identifies the basic

    function what is required on the left-hand side and more detailed secondary

    functions working from left to right until all the means of achieving these

    G

    G

    G

  • 8/12/2019 Construction Handbook[1]

    30/479

    PART1, SECTION2

    Page 6 Part 1, Section 2 (revised 10/01) Effective from 1/12/01 The Surveyors Construction Handbook

    functions how are they to be fulfilled are identified on the right. See figure 2

    for an example of a FAST diagram. It should be understood that this is a

    broad-brush technique.

    The objective of functional analysis is to produce a complete description of

    the end purpose of the design in terms of what it must do.

    Reference is sometimes made to different types of FAST diagram: Classical

    FAST, Technical FAST or Customer/Task FAST.

    The original FAST diagram was a presentation of the user-related and

    product-related functions of a design solution. It was a technique used to

    assemble the functions of a product in a hierarchy and to assess why and

    how they are delivered. This is known as a Classical FAST.

    Subsequently it was recognized that all functions did not fit into the flow logicso it was decided to separate out the functions that are always active, whether

    the product is operational or not. It was also decided to separate out those

    functions that only occur one time regardless of repetitiveness of the process.

    This diagram describes what a product, element or component must do and is

    known as a Technical FAST.

    It was then recognized that, ideally, it is the customer who should determine

    the value of the product and that the FAST diagram should include the

    customer/user in the development of value study projects. The resulting FAST

    Figure 2: FAST Diagram

  • 8/12/2019 Construction Handbook[1]

    31/479

    PART1, SECTION2

    The Surveyors Construction Handbook Part 1, Section 2 (revised 10/01) Effective from 1/12/01 Page 7

    diagram has become known as a Customer or Task FAST. It is this concept

    from which the Value Tree has developed.

    All FAST diagrams should include a scope line on the left-hand side of the

    diagram. The scope line limits the area of the project on which attention is

    being focused. The scope is the portion of the project that is selected for the

    value study.

    The FAST model displays functions in a logical sequence and tests their

    dependency. It does not indicate how a function should be performed.

    There is no such thing as a correct FAST model, only a valid FAST model.

    1.2.7.4 Most practitioners insist that functions are defined in terms of active

    verb/measurable noun (or phrase) combinations, for example, minimizeenergy consumption. This improves clarity, helps all panel members develop

    a shared understanding and promotes the examination process. These should

    be interrogated by asking why the client requires this in order to examine

    how it should be achieved.

    1.2.7.5 The process of setting up a FAST diagram is of matching the functional

    elements of the building (object functions) to the clients required functions

    (user functions). The functional requirements need to be broken down until

    they are reflected in elements which can be priced (and built). This process is

    called functional decomposition. For example, the requirement for increased

    energy efficiency might be provided by increased levels of insulation whichmight be achieved by changes to all or any of roof, walls, floor, windows and

    doors or finishes. The number of levels of decomposition required cannot be

    predetermined.

    1.2.7.6 VALUETREE

    A Value Tree is a diagram that describes the business driver (mission) for a

    project or need and the criteria that need to be satisfied in order to achieve it.

    A Value Tree should be developed at an early stage in order to inform the

    brief. However, it can be developed at any stage in order to confirm the brief.

    It will generally be carried out by the client organization in order to establish

    whether a project is the solution to their needs. The criteria are then developed

    further into the functions required in order to achieve them. The scope line for

    a project will begin to the right of the Value Tree.

    1.2.7.7 Appendix A gives an example of part of a Value Tree and a FAST diagram for

    a health centre.

    Function elements (object functions) are defined in the BCIS publication,

    Standard Form of Cost Analysis: Principles, Instructions and Definitionsand

    in Section 2.3 of this handbook.

    A typical example of a value engineering process is included in Appendix B.

  • 8/12/2019 Construction Handbook[1]

    32/479

    PART1, SECTION2

    Page 8 Part 1, Section 2 (10/01) Effective from 1/12/01 The Surveyors Construction Handbook

    1.2.8 Pricing the FAST Diagram

    1.2.8.1 As the FAST diagram progresses and different solutions are found, it becomes

    possible to establish alternative costs for achieving a given function.However, it is important that all functions are clearly defined if costs of

    alternative proposals are to be meaningful. Also, it should be remembered that

    it is the design solutions to the functional requirements that are being priced

    and compared to the value and importance that the client puts on that function.

    For example, the client can identify the value of savings from reduced energy

    consumption or may rank this as important for other reasons. The value

    engineering teams task is to put a price on the various design solutions

    suggested that will achieve this end. It is creativity in finding the most

    economical solution that is the essence of the value engineering exercise.

    1.2.8.2 Fees and value added tax (VAT) and other financial and fiscal matters mayalso need to be considered.

    1.2.9 Presenting a Design Solution to a Value Engineering Workshop

    1.2.9.1 Design solutions should be presented as designers normally would to any

    panel of users. However, they should expect to be questioned quite

    extensively. They should keep an open mind and maintain objectivity in

    justifying their proposals because the objective is to find the most

    cost-effective solution, not to criticize for the sake of it. On the other hand,

    designers should be prepared to stand by their design solution if they think itis correct for the function being considered.

    1.2.10 The Workshop

    1.2.10.1 A value engineering workshop will work through phases of information,

    speculation, evaluation, development and presentation:

    (a) The information phase identifies the spaces, elements and components in

    terms of the functions they fulfill. It asks the questions about what is the primefunction of an element?; what are its subsidiary functions?; what does it

    cost?; what is its value? It is at this stage that the FAST diagram is developed

    and it is against the background of this information that the value engineering

    evaluation will be made.

    (b) Speculation is the brainstorming stage which will generate the ideas from

    which solutions will be developed. It is important that each member of the

    panel thinks positively. The facilitator will ensure that no one is allowed to

    become overly critical of another members contribution in order that ideas

    flow. All ideas should be logged at this stage. However, in order to encourage

    idea building, they should not be analysed or rejected. It is important that the

    underlying functions of suggestions for improvement are listed for evaluation

    later. Design solutions should not be developed at this stage to ensure that

    G

    G

    G

  • 8/12/2019 Construction Handbook[1]

    33/479

    PART1, SECTION2

    The Surveyors Construction Handbook Part 1, Section 2 (10/01) Effective from 1/12/01 Page 9

    what is to be achieved is properly addressed. All optional solutions should

    only be considered at the evaluation stage.

    (c) Evaluation is the analysis of the ideas generated by the earlier

    speculation. Again, a positive feeling will be encouraged by the facilitator

    with advantages/disadvantages being discussed in an even-handed manner. At

    this stage some ideas will be rejected and the best taken forward. It is essential

    to ensure that all the ramifications of any suggested changes should be

    considered. For example, if the exercise has suggested a change to a piece of

    M&E equipment, the effects on the control management systems and

    structural requirements must also be considered.

    Life cycle costing can be an important factor in the process when considering

    optional solutions but the criticality of this aspect will hinge on the clients

    philosophy.

    (d) Development of the ideas to be taken forward will be initiated at the

    meeting and a programme established for completion of this stage. Often the

    detailed development including life cycle costing, if appropriate, will be

    continued beyond the initial meeting and the outcome presented to a

    subsequent meeting for the panel to determine which design options to adopt.

    (e) Presentation takes the form of a report prepared by the facilitator which

    records in some detail all elements of the study and concludes with those

    options to be incorporated in the developed design. This report is normally

    presented to the client by the value engineering panel at a meeting held within

    one or two weeks of the date of the workshop.

    1.2.10.2 The workshop should focus on expensive items or mismatches, for example,

    parts of the FAST diagram which are important to the client but which have

    been allocated little money or have cost a lot of money but do not contribute

    to the function.

    1.2.11 Assessing the Value of the Workshop

    1.2.11.1 Areas for research/change identified at the workshop could be grouped into

    three categories:

    (i) those that are removed/changed and result in reduced cost;

    (ii) those that are added/changed and result in additional cost; and

    (iii) those that are identified for investigation but not implemented

    1.2.11.2 The financial benefit should then be identified against all elements within

    categories (i) or (ii).

    1.2.11.3 A major benefit of the workshop which will be enjoyed by the panel members

    is a better understanding of the project functions and common ownership of

    the team-based designs solutions which have evolved.

    G

  • 8/12/2019 Construction Handbook[1]

    34/479

    PART1, SECTION2

    Page 10 Part 1, Section 2 (10/01) Effective from 1/12/01 The Surveyors Construction Handbook

    1.2.12 Implementing the Results

    1.2.12.1 The value engineering panels decisions are recommendations that need to be

    accepted by all stakeholders. Those stakeholders that are not part of the panelare likely to have a right to comment before decisions are adopted.

    1.2.12.2 Once the workshops proposals have been sanctioned by the client, decisions

    should be fed back to the design team, briefing those members whose work is

    affected as to why the changes were made.

    1.2.12.3 If necessary, amendments to the design brief, design programme and scope of

    professional teams brief should be incorporated into these documents.

    1.2.13 Feedback from Post-Occupancy Evaluation

    1.2.13.1 It is important for any client to carry out a project review to demonstrate how

    project objectives have been achieved and particular problems overcome. As

    part of the project evaluation process, it should be established whether the

    project represents best value for money and whether or not key design changes

    made as a result of value engineering have achieved the benefits expected.

    These should always be set against the cost of carrying out the exercise.

    G

    G

  • 8/12/2019 Construction Handbook[1]

    35/479

    PART1, SECTION2, APPENDIXA

    The Surveyors Construction Handbook Part 1, Section 2 Effective from 1/12/01 Page 1

    A endix A (revised 10/01)

    Appendix A: Health Centre Value Tree

  • 8/12/2019 Construction Handbook[1]

    36/479

    PART 1, SECTION 2, APPENDIX B

    The Surveyors Construction Handbook Part 1, Section 2 Effective from 1/1/00 Page 1

    Appendix B (12/99)

    Appendix B: Typical Example of a Value Engineering Process

    B1 BACKGROUND

    A retail client with a regular development programme for a series of new

    stores (typical size 8,000m2) entered into a partnering agreement with key

    members of the construction team for four new projects.

    To encourage value engineering, the partnering contractors share in any

    savings that relate to any accepted proposals.

    For two of these projects the client opted for a design and build contract for

    the services installations (mechanical, sprinklers and electrical).

    In an effort to reduce costs and ultimately add value to the schemes, the client

    set a target of reducing the costs on these projects by 10 per cent, with no

    material effect on quality or health and safety.

    To set a benchmark for this reduction model cost plan costs for a typical store

    (derived from historical records) were modified to suit the new scheme

    layouts. Allowances were included for any items that were classified as site

    specific (e.g. acoustic requirements stipulated by the district surveyor). Cost

    plan figures were based on the clients current specification.

    Due to the volume of developments undertaken by the client and the repetitive

    nature of the works, the savings generated by value engineering can beincorporated in any future schemes.

    B2 SPECIFIC EXAMPLE: VENTILATION TO SALES FLOOR

    The original design was based on previous solutions and included traditional

    ventilation.

    At the information phase, the functional requirement, including the need for

    ventilation, was examined against the clients desire to reduce capital costs.

    This identified that a high proportion of the cost of the mechanical installation

    related to the provision of ventilation to the sales floor of the store (plant,distribution ductwork, diffusers, etc.)

    At the speculation phase, the clients engineering department worked closely

    with the mechanical partnering contractor to consider alternative methods of

    ventilating the sales floor of the store.

    The alternative method of ventilation proposed was of the displacement type.

    With displacement ventilation, air is only conditioned at the level at which

    occupiers are breathing. Air is introduced at low level and at low velocity.

    Natural convection currents are utilised to remove excess heat and pollutants

    out of the occupied zone. There is a saving in the amount of ductworkrequired, as only two runs of ductwork are needed on the sales floor. (The

  • 8/12/2019 Construction Handbook[1]

    37/479

    PART 1, SECTION 2, APPENDIX B

    Page 2 Part 1, Section 2 Effective from 1/1/00 The Surveyors Construction Handbook

    Appendix B (12/99)

    traditional method is designed for four separate branches of ductwork.) The

    new specification requires diffusers of the displacement type, with the facility

    of automatically varying the air throw pattern whether in heating or cooling

    mode.

    Furthermore, the proposed system required ventilation to the occupied zone

    only rather than the full building space. This has resulted in capital cost

    savings on plant and in the likely running costs of the system.

    The evaluation identified significant savings.

    Summary of Value Engineering Exercise

    Original installation: Traditional ventilation

    Value engineering proposal: Displacement ventilation

    Benefits: Saving on air handling plant size

    Saving on chiller plant size

    Saving on sales floor ductwork

    Savings on capital cost: Air handling plant 10%

    Chiller plant 5%

    Ductwork and diffusers 25%

    At the development phase, the proposed method was discussed with other

    members of the design team to ensure that any impact on the other building

    elements, the project programme and the interface with other subcontractors

    were taken into account.

  • 8/12/2019 Construction Handbook[1]

    38/479

  • 8/12/2019 Construction Handbook[1]

    39/479

    PART1, SECTION2, APPENDIXC

    Page 2 Part 1, Section 2 Effective from 1/12/01 The Surveyors Construction Handbook

    A endix C (10/01)

    Palmer, Angela. A Critique of Value Management, Chartered Institute of Building,

    Berkshire, 1990

    Royal Institution of Chartered Surveyors. Value and the Client (papers presented at a

    conference held at the RICS on 29 January 1992) , RICS, London, 1992

    Smith, J., Jackson, N., Wyatt, R., Smyth, H., Beck, M., Chapman, K., Shirazi, A.,

    Hampson, K., Royal Institution of Chartered Surveyors. Can Any Facilitator Run a

    Value Engineering Workshop?RICS, London, 1998

    Zimmerman, Larry, W. and Hart, Glen, D.Value Engineering: A Practical Approach

    for Owners, Designers and Contractors, Van Nostrand Reinhold & Co, New York,

    1982

  • 8/12/2019 Construction Handbook[1]

    40/479

    PART2, SECTION1

    The Surveyors Construction Handbook Part 2, Section 1 (4/98) Effective from 1/6/98 Page 1

    PART TWO: CONSTRUCTION DESIGN AND ECONOMICS

    SECTION 1: PRE-CONTRACT COST PLANNING AND

    COST MANAGEMENT

    Introduction

    This Section of the Handbook sets out procedures which enable pre-contract

    cost management of building projects to be carried out from the clients brief,

    through the various design stages to the acceptance of a contractors tender.

    Control of costs can only be achieved by the actions of the whole project team,

    including the client. The quantity surveyors role is to facilitate the design

    process by systematic application of cost criteria so as to maintain a sensible

    and economic relationship between cost, quality, utility and appearance which

    thus helps in achieving the clients requirements within the agreed budget.

    The information and guidance which follow are based on a traditionally

    procured new-build project, but varying client requirements and different

    procurement methods may prevent implementation of some aspects of the

    following procedures. In practice, the design of the elements may proceed atdifferent speeds and the stages described here may overlap. However, the

    principles of budget, cost plan, cost checks and reconciliation should be

    adhered to whenever possible. (See the figure showing the outline of the cost

    planning procedure.)

    On projects where non-traditional procurement routes are used, the

    responsibility for developing the cost plan may change but the stages

    suggested here remain appropriate. For example, on Design and Build (D&B)

    schemes, the clients quantity surveyor will be responsible for the cost plan at

    feasibility and outline proposal stage and the D&B contractors quantity

    surveyor will be responsible for developing the cost plan with the contractorsdesign team to produce the tender.

    The process described would apply to refurbishment or conversion schemes

    and the elemental approach would be suitable even if all elements were not

    required.

    The procedures are not designed for use with civil engineering projects, but

    should provide a framework appropriate to civil engineering needs.

  • 8/12/2019 Construction Handbook[1]

    41/479

    PART2, SECTION1

    Page 2 Part 2, Section 1 (4/98) Effective from 1/6/98 The Surveyors Construction Handbook

    2.1.1 Pre-contract Cost Planning and Cost Management

    2.1.1.1 DEFINITION

    Pre-contract cost planning is the technique by which the budget is allocated to

    the various elements of an intended building project to provide the design

    team with a balanced cost framework within which to produce a successful

    design. It allows for the redistribution of the budget between elements as the

    design develops.

    Cost management is the total process which ensures that the contract sum is

    within the clients approved budget or cost limit. It is the process of helping

    the design team design to a cost rather than the quantity surveyor costing adesign.

    I

  • 8/12/2019 Construction Handbook[1]

    42/479

    PART2, SECTION1

    The Surveyors Construction Handbook Part 2, Section 1 (05/03) Effective from 1/7/03 Page 3

    2.1.1.2 OBJECTIVES

    (a) To ensure that the client obtains an economical and efficient project in

    accordance with the agreed brief and budget;

    (b) to make the design process more efficient, thus reducing the time needed

    to produce a successful design;

    (c) to ensure that all requirements arising from the clients brief to the design

    team are included in the cost planning process (e.g. the engineering services

    should also be subject to the cost planning process); and

    (d) to advise the client and members of the design team of cost-in-use or

    life-cycle costing techniques.

    2.1.1.3 GENERALLY

    (a) A general principle applies throughout the cost planning process that any

    agreed budget or cost limit is seen as the maximum cost, and the quantity

    surveyor should, at all times, work with the other design team members to

    satisfy the client at a lower cost if possible, whilst still maintaining the desired

    objectives for quality and function.

    (b) If, at any time, sums have been included in the approved budget, for

    example, for abnormal site costs which subsequently are found to have been

    wholly or partially unnecessary, the consequential saving should always be

    notified to the client.

    2.1.1.4 DESIGNSTAGES

    References to Design Stages are to the RIBA Plan of Work (taken from the

    RIBAHandbook of Architectural Practice and Management) and refer to the

    main stages through which a project design typically passes. The links to the

    cost planning procedures outlined in this section are summarised here:

    Design Stages Quantity Surveyor

    Stage B: Feasibility Prepare feasibility studies and determine

    the budget

    Stage C: Outline Proposals Consider with client and design team

    alternative strategies and prepare cost plan

    Stage D: Scheme Design Carry out cost checks and update cost plan

    if necessary

    Stage E: Detail Design

    Stage F: Production Information Carry out cost checks

    Stage H: Tender Action Prepare reconciliation statement

    G

    G

    G

  • 8/12/2019 Construction Handbook[1]

    43/479

    PART2, SECTION1

    Page 4 Part 2, Section 1 (05/03) Effective from 1/7/03 The Surveyors Construction Handbook

    2.1.1.5 VALUEENGINEERING

    A value engineering exercise may be carried out on all or part of the design

    during the design process. (For further details see part 1, section 2 of this

    handbook.)

    This might affect both the clients requirements and the chosen design

    solution and changes would, therefore, affect the budget and the cost plan.

    2.1.2 Preliminary cost studies and feasibility studies

    2.1.2.1 It is recommended, as a matter of importance, that before and during the

    formulation of the clients brief (Design Stage B: Feasibility), the quantity

    surveyor, in consultation with other members of the design team and the

    client, should undertake such feasibility studies as may be necessary to ensure

    that the clients requirements can be reasonably accommodated within the

    finance that is available for the project. The clients budget is established as a

    result of these studies. (See 2.1.3.)

    2.1.3 Budget

    2.1.3.1 DEFINITION

    Budget is the total expenditure authorised by the client which is the

    responsibility of the design team at the end of the feasibility stage (DesignStage B).

    2.1.3.2 OBJECTIVES

    (a) To establish the limit of expenditure necessary to meet the clients brief.

    The clients and projects status with regard to VAT (Value Added Tax) will

    also need to be established;

    (b) to provide the client with a statement of the likely area and quality of

    building, which is achievable within the limit of expenditure;

    (c) to provide a statement of the recommended methods of construction and of

    the contractual procedures to achieve the required occupation date; and

    (d) to provide the client with alternative budgets for different occupation dates

    and qualities of building, if appropriate.

    2.1.3.3 INFORMATIONREQUIREMENTS

    (a) The ideal requirements from the client and members of the project team

    to the quantity surveyor are given below. On projects where this level of

    information is not available, the quantity surveyor should state clearly any

    assumptions made. It is possible to produce a typical elemental estimate for

    I

    G

    I

    G

    G

  • 8/12/2019 Construction Handbook[1]

    44/479

    PART2, SECTION1

    The Surveyors Construction Handbook Part 2, Section 1 (4/98) Effective from 1/6/98 Page 5

    a particular type of building from very little information, but it is important to

    clarify as many information issues as possible before such an estimate is

    accepted as the budget for a particular project.

    (b) Information required from the client:

    location of the site; availability of the site for commencement of

    construction work;

    in conjunction with the designer, architect or building surveyor, a

    schedule of accommodation;

    names of other similar buildings of broadly suitable quality if

    appropriate;

    the required occupation date or phased occupation dates;

    any specific requirements relating to life-cycle costs;

    any specific requirements as to specification and/or procedures;

    requirements in respect of the treatment of inflation; instructions regarding Construction (Design and Management)

    Regulations; and

    the clients VAT status and any other tax matters which may affect the

    overall cost of the project.

    (c) Information required from the designer, architect, building surveyor, or

    other source:

    approximate location of the building on the site;

    advice on necessary storey heights for any specialist areas shown on

    schedule of accommodation;

    advice on statutory regulations;

    advice on routes of public sewers and the like;

    designers concept of building; and

    names of similar projects previously designed by the practice.

    (d) Information required from the structural engineer:

    advice on probable ground conditions;

    advice on probable floor loadings; and

    any information on structural solutions.

    (e) Information required from the services engineer: advice on areas of building which will require specialist engineering

    services;

    any information on the types of systems; and

    advice on availability of public utility services.

    Note: If the quantity surveyor is not responsible for cost planning the

    engineering services, this should be clearly stated in the budget and cost plan.

    The information from the quantity surveyor to the design team is as follows:

  • 8/12/2019 Construction Handbook[1]

    45/479

    PART2, SECTION1

    Page 6 Part 2, Section 1 (4/98) Effective from 1/6/98 The Surveyors Construction Handbook

    (An example of a format for the quantity surveyors report is given in

    Appendix B to this Section.)

    (f) Information to be provided to the client involves a report containing:

    the budget, with alternative proposals if appropriate;

    a statement of the basis of the budget calculation including any

    important assumptions made;

    a statement setting out the programme for design and construction on

    which the budget is based;

    an outline cash-flow forecast;

    a statement of any items not included; and

    assumptions in respect of inflation forecasts and current/future market

    conditions.

    (g) Information to be provided to the designer: a copy of the report sent to the client; and

    a more detailed statement of the quantity and quality parameters

    included in the calculations.

    (h) Information to be provided to other consultants:

    such quantity and quality parameters as relate to their area of design.

    2.1.3.4 METHODS OFPREPARATION

    (a) The method of preparation depends on the type of project involved.

    Unusual projects, projects of great complexity and projects containing a large

    element of alterations are more difficult to budget accurately at an early stage.

    (b) For most types of project, it is possible to build up an elemental budget

    using the parameters set out under 2.1.3.5. This can be based on cost

    information from previous projects, from the RICS Building Cost Information

    Service (BCIS), other published sources, or on an appropriate cost model.

    (c) The main elemental quantities of hypothetical buildings can be generated

    using agreed parameters, to which rates applicable to agreed quality and

    performance standards can be applied. An example of a method of calculatinghypothetical quantities is described in Appendix C to this Section.

    (d) Once the budget has been established, it provides the first cost plan for the

    project, and the framework for the actual design to be developed.

    2.1.3.5 STATEMENT OFQUANTITY ANDQUALITYPARAMETERS

    The main parameters which should normally be incorporated in the

    calculation are as follows (the list is not exhaustive):

    G

    G

    G

  • 8/12/2019 Construction Handbook[1]

    46/479

    PART2, SECTION1

    The Surveyors Construction Handbook Part 2, Section 1 (05/03) Effective from 1/7/03 Page 7

    (a) Quantity

    in addition to the briefed areas, a statement of the allowances (e.g.

    circulation) used to calculate a gross floor area;

    the number of storeys of a possible solution;

    the storey height(s);

    the square index or wall/floor ratio (see appendix C to this section);

    the density of vertical division or partition/floor ratio (see appendix C

    to this section);

    proportion of window area;

    floor loadings;

    thermal resistance values of fabric;

    air change rates;

    heating and hot-water loads;

    lighting levels;

    total electrical load; areas of the brief with special functions of significant cost;

    road area and number of car parking spaces;

    paved pedestrian areas; and

    length of boundary walls or fencing.

    (b) Quality

    A general statement of quality and specification which relates to the

    rates used for the budget calculation. This should cover specifically at

    least the following: foundations, roof, external walls, floors and

    vertical circulation, internal vertical division, internal finishes,

    lighting and other services. External works should include roads,

    paths, landscape, boundary walls and fences, and service mains,

    planting and the like.

    2.1.3.6 INFLATION

    (a) The prediction of future inflation may not be necessary for some clients,

    and a statement of cost at current prices may be adequate. Where an

    assessment of inflation is required for more than a few months ahead, a range

    of probable inflation is best provided. This can be calculated using

    predictions published, for example by BCIS or the Department of Trade andIndustry. The assumptions upon which the prediction is made should be

    stated.

    (b) Some clients, particularly in the public sector, have their own inflation

    controls. Where the client requests that a particular level of inflation be

    included in the budget, the quantity surveyor should inform the client if he or

    she believes it to be unrealistic.

    2.1.3.7 COSTREPORTING

    If at any time during the design process it becomes apparent that the agreed

    budget is likely to be exceeded without the brief being changed, the client

    should be informed and instructions requested. Likewise, if it becomes

    G

    G

  • 8/12/2019 Construction Handbook[1]

    47/479

  • 8/12/2019 Construction Handbook[1]

    48/479

    PART2, SECTION1

    The Surveyors Construction Handbook Part 2, Section 1 (4/98) Effective from 1/6/98 Page 9

    (d) Information required from the services engineer:

    outline proposals for installations, indicating any alternative systems;

    and

    an indication of the preferred specification, after acceptance by the

    designer of its visual implications.

    (e) Information required from specialist consultants:

    outline proposals.

    The basic information requirements from the quantity surveyor to the design

    team are as follows:

    (An example of a format for the quantity surveyors report is given in

    Appendix B to this Section.)

    (f) Information to be provided to the client involves a report containing:

    a statement of cost;

    a broad indication of the specification;

    a statement of floor areas;

    a request for decisions on any alternative proposals and/or procurement

    routes, with advice thereon;

    an updated cash-flow forecast;

    allowances for contingencies and design reserve; and

    an update of inflation projections.

    (g) Information to be provided