Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
Construction Coordination & Management Planning
MassDOT-Highway/MBTA495/MetroWest Partnership Briefing
July 11, 2018
• The Construction Coordination and Management Planning exercise was a 100-day joint effort between theHighway Division and MBTA to identify potential schedule conflicts and impacts to the public during the2018 construction season
– Collected data for over 1000 projects in the Greater Boston area
– Identified “hot spots”
– Reviewed construction schedules and 24-hour/off-peak impacts
– Identified projects that allow for schedule flexibility
• Results will allow the Highway Division to focus on improved public outreach strategies
Overview
• Data Collected & Analyzed: Collected and analyzed transit andhighway project data: 1,045 projects for 2018-2022 and 246projects for 2018. Modeled project profiles and schedules
• Identified Impacts: Reviewed projects by 24-hour/off-peaktrack/lane impacts, diversion and/or capacity impacted projects,impacts on bus network, and opportunities to combine projectresources
• Reviewed Project Schedules: Determine where Highway andMBTA projects can coordinate schedules and perform multipleoperations during the same outage
• Communications and Outreach Plan: Implementing lessonslearned and best practices from past projects (Wollaston Station,Commonwealth Avenue, Fast 14) to improve outreach to thepublic
Process
2018 Metro Boston Projects with Impacts
Hot Spots
High Density of
Active/Planned Construction
Projects
Low Density of
Active/Planned Construction
Projects
MassDOT Highway
Districts
Municipal Boundary
As of February 13, 2018
2
3
1
Highway & transit
projects with roadway
lane closures, transit
service disruptions/
diversions, and/or parking
impacts during all time
periods.
Fenway/Weston Interchange
Mystic River
Quincy Bay
Owner/
Proponent Number
Percent
of Total
MassDOT
Highway74 30%
MBTA 146 59%
Other 26 11%
Project Type Number
Percent
of Total
Roadway 49 20%
Bridge 27 11%
Transit * 146 59%
Ped/Bike 3 1%
Utilities 11 5%
Development 3 1%
Other 7 3%
115 Projects with
Impacts Reviewed
PRELIMINARY DATA: SUBJECT TO CHANGE
MassDOT (5)
Commonwealth Avenue over I-90 Deck
Replacement (Phase 2)
Mass Ave (Route 2A) over Comm Ave Bridge
Replacement
I-95/Route 128 Add-a-Lane (6 Bridges)
I-95 Pavement Resurfacing
Route 9 Resurfacing
Commuter Rail (2)
Positive Train Control (Worcester Line)
Worcester Line CP6
Utility (1)
MWRA Water Main Rehabilitation
(Boston: Brighton, Newton, Watertown)
Projects in grey have schedule flexibility.
MBTA (38)
Green Line Track Infrastructure Restoration
- B Line (4 locations)
- D Line (6 locations) – (flexible on locations)
Green Line (Non-GLX) Grade Crossings (25 locations)
(flexible on locations)
Reservoir and Riverside Signal Imp. (flexible on locations)
Fenway Portal Flood Protection
Direct Fixation - Orange Line Southwest Corridor (On-Call)
(flexible on locations)
46 ProjectsAs of February 13, 2018
30
95
20
16 9
2018 Hot Spot #2: Fenway/Weston Interchange
Project Owner
Regional View
2018 Hot Spot #2: Fenway/Weston Interchange
Anticipated Schedule46 Projects
As of February 13, 2018
3-M
ar
10-M
ar
17-M
ar
24-M
ar
31-M
ar
7-A
pr
14-A
pr
21-A
pr
28-A
pr
5-M
ay
12-M
ay
19-M
ay
26-M
ay
2-J
un
9-J
un
16-J
un
23-J
un
30-J
un
7-J
ul
14-J
ul
21-J
ul
28-J
ul
4-A
ug
11-A
ug
18-A
ug
25-A
ug
1-S
ep
8-S
ep
15-S
ep
22-S
ep
29-S
ep
6-O
ct
13-O
ct
20-O
ct
27-O
ct
3-N
ov
10-N
ov
17-N
ov
24-N
ov
1-D
ec
8-D
ec
15-D
ec
22-D
ec
29-D
ec
1Green Line - B Line Track Infrastructure
Restoration
2Green Line - D Line Track Infrastructure
Restoration
3 Green Line (Non-GLX) Grade Crossings
4Reservoir and Riverside Signal
Improvements
5 Fenway Portal Flood Protection
6Direct Fixation - Orange Line Southwest
Corridor (On-Call)
7 Positive Train Control (Worcester Line)
8Commonwealth Avenue over I-90 Deck
Replacement (Phase II)
9Mass Ave (Route 2A) Bridge
Replacement over Comm Ave
10 I-95/Route 128 Add-a-Lane Contract
11 I-95 Pavement Resurfacing
12 Route 9 Resurfacing
13 MWRA Water Main Rehabilitation
*Dates subject to change based on availabe resources, weather, emergencies, etc.
MBTA
Commuter Rail
Private
MassDOT Highway
• $110 million project that is scheduled to be fully completed in the spring of 2019.
• The project uses Accelerated Bridge Construction (ABC) to replace the
superstructure over two intensive construction windows:
• Summer 2017 (eastbound portion of the bridge) - complete
• Summer 2018 (westbound portion of the bridge)
8
About the Project
The Summer 2018 construction
window will occur from
July 26 – August 11 (15 ½ days).
• I-90:• Weekday: 165,000 per day
• Commonwealth Ave• Vehicular: 4,000+ per hr• Pedestrian: 2,000 per hr• Bicycle: 500 per hr
• Green Line – B Branch:• 27,000 per weekday
• MBTA Bus:• CT2: 2,300 per weekday• 47: 4,800 per weekday
Impacted Users
• Commuter Rail – Worcester Line:• Weekday: 18,500 per day• Saturday: 2,800 per day• Sunday: 1,800 per day
That is over 200,000 people a day under or on-top of the bridge–over 3 Gillette Stadium or 5 Fenway Park sellouts
• Successfully replaced the eastbound
side of the bridge in approximately 3
weeks.
• Managed impacts to local community
and the region.
• Traveling public made smart
decisions.
10
Summer 2017 Highlights
• In 15 ½ days, crews will
replace the westbound side of
the Commonwealth Avenue
Bridge.
• Over 200 workers are
expected to work around the
clock.
• Crews will utilize three 600-ton
cranes.
• The westbound side of the
bridge will be constructed with
45 steel beams and 214 pre-
fabricated concrete deck
panels.
11
Summer 2018 Construction
12
July 26 – August 112018 Project ScheduleFacility Impacts Notes
Commonwealth Avenue
(Packard’s Corner to
Kenmore)
Closed to through motor vehicles for
15½ days
Two-way access will be maintained for local businesses
and residents, MBTA buses, emergency services,
pedestrians, and bicyclists. There will be no access for
private vehicles between St. Paul and St. Mary’s Streets.
Boston University (BU) Bridge Closed to motor vehicles and buses for
15½ days
Two-way access will be maintained for pedestrians and
bicyclists.
MBTA Bus Routes
(CT2 and 47)
Detoured from normal routes
for 15½ days
Detour maps are available on the project website.
MBTA Green “B” Line
(Blandford St. to Babcock St.)
Closed from Blandford St. to Babcock
St. for 15 days
Shuttle bus service will run between Blandford St. and
Babcock St.
I-90 (Mass Turnpike) Lane reductions and ramp closures for
9½ days
Two lanes in each direction during peak periods. The I-90
Eastbound on-ramp from Cambridge Street/Soldiers
Field Road will be closed during this entire period. The I-
90 Westbound Exit 20 off-ramp to Brighton/Cambridge
will also be closed intermittently.
MBTA Commuter Rail
(Framingham/Worcester Line)
Service impacts for two weekends:
July 28-29 and August 4-5
Bus shuttles will replace train service between
Framingham and Wellesley Farms. After Wellesley
Farms, the shuttle bus will then continue nonstop to
Riverside, where riders can connect to the Green D Line.
In addition to local shuttles, express shuttle service will
be available between Framingham and Riverside.
Amtrak
(Lake Shore Limited Line/
Chicago)
Service impacts for two weekends:
July 28-29 and August 4-5
Shuttle bus service from Albany, NY to Boston with stops
in Springfield and Worcester.
13
2018 Project Schedule
Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat Sun Mon Tue Wed Thu Fri Sat
July 26 July 27 July 28 July 29 July 30 July 31 Aug 1 Aug 2 Aug 3 Aug 4 Aug 5 Aug 6 Aug 7 Aug 8 Aug 9 Aug 10 Aug 11
Comm Ave CLOSED to
through motor vehicles7:00 PM X X X X X X X X X X X X X X X
BU Bridge CLOSED to
motor vehicles7:00 PM X X X X X X X X X X X X X X X
MBTA CT2 & 47 Detours 7:00 PM X X X X X X X X X X X X X X X
MBTA Green B Line Bus
Diversion5:00 AM X X X X X X X X X X X X X X
I-90 Lane Restrictions 9:00 PM X X X X X X X X X 5:00 AM
Commuter Rail Bus
DiversionX X X X
Limits of the crossover are Allston/Brighton Toll Plaza and Beacon Street Overpass (~6600 feet)
I-90 Crossover
14
I-90 Impacts During Shutdown
16
• I-90 will be reduced to 2 lanes in both directions
from 9:00 PM on July 27 to 5:00 AM on August 6
(with additional lane closures during off-peak hours)
• The I-90 Eastbound on-ramp from Cambridge
Street/Soldiers Field Road will be closed during
this entire period and the I-90 Westbound Exit 20
off-ramp to Brighton/Cambridge will also be
closed intermittently during this timeframe
• The eastbound lane reductions will begin in
advance of the Allston Interchange
• Westbound lane reductions will begin at the on-
ramp from Mass Ave
State troopers escorting contraflow traffic during 2017 Dry Run
MBTA Commuter Rail Framingham/Worcester Line
Weekends July 28-29 and August 4-5Free bus shuttles will replace Commuter Rail train service between Framingham and Wellesley
Farms. After Wellesley Farms, the shuttle bus will then continue nonstop to Riverside, where
riders can connect to the Green D Line. In addition to the local shuttles, express shuttle service
will be available between Framingham and Riverside.
Important to know• Weekday train service on the Framingham/Worcester Line will run as usual.
• Station parking lots are expected to fill up early. Please plan ahead, car pool, or seek alternate routes.
• For more info, go to mbta.com/Worcester.
Amtrak Lakeshore Limited Line
Service impacts for two weekends: July 28-29 and August 4-5
• Shuttle bus service will run between South Station and Albany, NY. – with
stops in Springfield and Worcester
• No service disruption on weekdays.
Added Green Line Resources
• During the Commuter Rail weekend suspensions
and Red Sox games/Fenway Park events, extra
Green Line service will be added to:
• C branch (Cleveland Circle)
• D branch (Riverside)
• Customer service personnel will be located at
Babcock Street, Blandford Street, and Riverside
stations
• Police details along the route to progress bus traffic
Project Website and Contact
www.mass.gov/massdot/CommAveBridge
• Sign up for email construction updates and traffic alerts
• View a detailed project schedule, including temporary traffic impacts
• Download maps of detour routes
• Learn more about traffic options in your area
• View project documents and presentations
• Find out about upcoming meetings
Contact Information:
20