Y:\Projects\8819-ms-001 METHOD STATEMENT & SEQUENCE OF WORK TO CONSTRUCT BASEMENT STRUCTURE SITE ADDRESS: 57 BRONDESBURY ROAD, LONDON, NW6 6BP. PROJECT REF: 8819 Ref. to Dwg. 8819/SK01. Underpinning Excavate the individual bay to be underpinned to the new formation level. The soffit of existing foundations is to be thoroughly cleaned and cut back to a sound face before concreting and dry packing. The existing corbelled brick foundations will be carefully cut back to the wall line on the internal face. Extra precaution is to be taken in excavating further to allow underpinning and bay widths are to be limited in width (1 max) or permanent props installed. Adequate temporary supports are to be provided where walls are to be underpinned and arching of brickwork is deemed not to be present or brickwork not sound. Steel prop supports shall be inserted locally if necessary after excavation beneath the foundations and shall be bedded on the approved formation and concreted into the underpinning. Concrete to be GEN 3 (20 N) mass concrete uno. The sequence of underpinning is to be agreed with the Engineer before proceeding with the work. Each bay including excavation to be 1m wide maximum and to be sequenced in conjunction with a sequencing plan drawing. Typically a 1-5 numbering system for bays is provided for construction. Works to be sequenced to maintain adequate foundation support to the building at all times. Excavate and cast bays marked 1. Allow 24 – 48 hours to cure before dry packing. Allow 24-48 hours to cure before excavating the subsequent bay. Excavate and cast bays marked 2 and dry pack as above. Repeat for 3, 4, 5 until underpinning complete, or similar sequencing (Note: sequential ordering for bays in a length of wall is 1st bay, 3rd bay, 5th, 2nd, 4th and so on, such that a subsequent bay is not located adjacent to a most recently constructed bay uno).

Construct Basement Structure

Embed Size (px)

DESCRIPTION

MS

Citation preview

  • Y:\Projects\8819-ms-001

    METHOD STATEMENT & SEQUENCE OF WORK

    TO CONSTRUCT BASEMENT STRUCTURE

    SITE ADDRESS: 57 BRONDESBURY ROAD, LONDON, NW6 6BP.

    PROJECT REF: 8819

    Ref. to Dwg. 8819/SK01.

    Underpinning

    Excavate the individual bay to be underpinned to the new formation level.

    The soffit of existing foundations is to be thoroughly cleaned and cut back to a sound

    face before concreting and dry packing.

    The existing corbelled brick foundations will be carefully cut back to the wall line on

    the internal face. Extra precaution is to be taken in excavating further to allow

    underpinning and bay widths are to be limited in width (1 max) or permanent props

    installed.

    Adequate temporary supports are to be provided where walls are to be underpinned

    and arching of brickwork is deemed not to be present or brickwork not sound. Steel

    prop supports shall be inserted locally if necessary after excavation beneath the

    foundations and shall be bedded on the approved formation and concreted into the

    underpinning.

    Concrete to be GEN 3 (20 N) mass concrete uno.

    The sequence of underpinning is to be agreed with the Engineer before proceeding

    with the work. Each bay including excavation to be 1m wide maximum and to be

    sequenced in conjunction with a sequencing plan drawing. Typically a 1-5 numbering

    system for bays is provided for construction. Works to be sequenced to maintain

    adequate foundation support to the building at all times.

    Excavate and cast bays marked 1. Allow 24 48 hours to cure before dry packing.

    Allow 24-48 hours to cure before excavating the subsequent bay.

    Excavate and cast bays marked 2 and dry pack as above.

    Repeat for 3, 4, 5 until underpinning complete, or similar sequencing (Note:

    sequential ordering for bays in a length of wall is 1st bay, 3rd bay, 5th, 2nd, 4th and

    so on, such that a subsequent bay is not located adjacent to a most recently

    constructed bay uno).

  • Y:\Projects\8819-ms-001

    The width of the underpinning base at formation level is to equal the width of the

    existing brickwork foundations.

    New Basement RC Retaining Wall Horizontal Restraint

    Adequate temporary horizontal supports are to be provided to replace the horizontal

    restraint the existing floor currently provides to the foundations during the works.

    The permanent horizontal support is by means of a new internal basement RC

    retaining wall constructed of reinforced concrete. This internal retaining wall provides

    horizontal restraint up to the foundations. The walls and base are to be constructed

    of 150mm thick reinforced concrete. Walls to be poured against the mass concrete

    underpinning to the level of the existing floor slab. The base is to be constructed off

    of 50mm level and compact blinding. Concrete to be grade RC40.

    During construction adequate temporary horizontal supports are to be provided to

    the head of the retaining wall as required where the floor is removed or the base not

    fully constructed at all times.

    New Basement Floor Slab

    The new basement floor slabs are to be of ground bearing nominally reinforced

    concrete construction. Slabs to be 150mm thick with A142 mesh in the centre of the

    slab. Concrete to be grade RC40.

    This report assumes a competent contractor is appointed to undertake the works.

    Killian OReilly

    Gurney Consulting Engineers