17
Material Management Org. Structures Organizational Structures Valuation Level You define the valuation level by specifying the level at which material stocks are valuated. You can valuate material stocks at either the company code level or at the plant level. If you want to use the Production Planning (PP) module or Costing, then you should set the valuation level to plant. The valuation level is valid for the entire client. Once the valuation level is set, then it cannot be changed except by a trained SAP consultant, and it requires a data conversion. To see the valuation setting, following the menu path Tools Customizing IMG Edit Project Enterprise Structure Definition Logistics - General Define valuation level (click clock icon ) You should get the following screen: Note that the valuation level is already set at the plant level. Also, the choices are "grayed-out," which means that they cannot be changed. Since the valuation level is set for the client and all students are in the same client, it has already been set and cannot be changed via this screen. 2- 1 02/09/09

Configuration Guide to Create Organizational Structures in Sap Mm

Embed Size (px)

Citation preview

Page 1: Configuration Guide to Create Organizational Structures in Sap Mm

Material Management Org. Structures

Organizational Structures

Valuation Level

You define the valuation level by specifying the level at which material stocks are valuated. You

can valuate material stocks at either the company code level or at the plant level. If you want to

use the Production Planning (PP) module or Costing, then you should set the valuation level to

plant. The valuation level is valid for the entire client. Once the valuation level is set, then it

cannot be changed except by a trained SAP consultant, and it requires a data conversion. To see

the valuation setting, following the menu path

Tools Customizing IMG Edit Project Enterprise Structure Definition Logistics - General Define valuation level

(click clock icon )

You should get the following screen:

Note that the valuation level is already set at the plant level. Also, the choices are "grayed-out,"

which means that they cannot be changed. Since the valuation level is set for the client and all

students are in the same client, it has already been set and cannot be changed via this screen.

2- 1 02/09/09

Page 2: Configuration Guide to Create Organizational Structures in Sap Mm

Material Management Org. Structures

1. Define Plant

The plant usually represents a manufacturing facility, a distribution center or a warehouse,

although it does not have to represent an actual physical facility. Manufacturing Requirements

Planning (MRP), the process of determining what production and purchase orders should be

released and when, occurs at the plant level. In the University Cellular company, there is only

one plant, and it can be defined using the following menu path:

Tools Customizing IMG Edit Project Enterprise Structure Definition Logistics - General Define, copy, delete, check

plant (click clock icon )

This will bring up the following screen:

Double-click on

Define Plant

Double-click on Define Plant, which will produce the following screen:

Click on New Entries

2- 2 02/09/09

Page 3: Configuration Guide to Create Organizational Structures in Sap Mm

Material Management Org. Structures

Click on the New entries icon ( ), which will produce the following screen:

Enter:

##CP for plant

## University Cellular Plant

US for Factory Calendar

Then click on the address icon

The factory calendar defines which days are working days. The entry US is the standard US

factory calendar, which defines Monday through Friday as working days and Saturdays, Sundays

and Public Holidays as non-working days.

Click on the address icon ( ), which will produce the following screen:

2- 3 02/09/09

Page 4: Configuration Guide to Create Organizational Structures in Sap Mm

Material Management Org. Structures

Click Here

This screen is just like the screen for entering company code data. Enter the following

information for the plant:

Title:

Name:

Search Term:

Street:

House Number:

Postal Code:

Company

## University Cellular Plant

##

Business Court

83

49008

2- 4

02/09/09

Page 5: Configuration Guide to Create Organizational Structures in Sap Mm

Material Management Org. Structures

City: Kalamazoo

Country: US

Region: MI

Next, click on the more fields icon ( )in the address panel: This will bring up additional fields. Enter Tax Jurisdiction Code MI0000000 (MI followed by

seven zeros):

Enter Tax Jurisdiction Code

MI0000000 here (seven 0's)

Click the checkmark ( ) and then click on the save icon ( ). This will bring up the address screen again for some reason. Click on the checkmark ( ) again and the data will be

saved. Click on the back icon ( ) and confirm that your plant is now listed:

2- 5 02/09/09

Page 6: Configuration Guide to Create Organizational Structures in Sap Mm

Material Management Org. Structures

Click on the back icon ( ), and then click on the cancel icon for the Choose Activity window

to return to the IMG.

2. Define Storage Locations

A storage location is a subdivision of a plant where materials are managed. It may be a physical

location, or it may just be used as an organizational tool. For the University Cellular Company,

we will create three storage locations:

Sloc Description

100 Raw Materials

200 Production

300 Finished Goods

2- 6 02/09/09

Page 7: Configuration Guide to Create Organizational Structures in Sap Mm

Material Management Org. Structures

Where Sloc is the number assigned to the storage location. By using Sloc numbers 100, 200 and

300, we can add more detailed storage locations in the future and still have a rational numbering

scheme.

To create the storage locations, follow the menu path

Tools Customizing IMG Edit Project Enterprise Structure Definition Materials Management Maintain storage

location (click clock icon )

This will produce the following screen:

Enter ##CP for plant,

then click on Continue

Enter ##CP for plant and then click on the check mark ( ), which will produce the following

screen:

2- 7 02/09/09

Page 8: Configuration Guide to Create Organizational Structures in Sap Mm

Material Management Org. Structures

Click on the New entries icon ( ), which will allow you to enter the storage

locations:

Enter the three storage

locations here

Click on the save icon ( ), and then on the exit icon ( ) to complete the creation of the

storage locations.

2- 8 02/09/09

Page 9: Configuration Guide to Create Organizational Structures in Sap Mm

Material Management Org. Structures

3. Define Purchasing Organization

The purchasing organization is responsible for all purchasing activities, including requests for

quotations (RFQ) and purchase orders (PO). A purchasing organization can be assigned to

several company codes (e.g. centralized purchasing for General Motors divisions). A purchasing

organization must be assigned to one or more plants. Each purchasing organization has:

• Its own vendor master data and vendor evaluation

• Its own pricing conditions

• Its own external purchasing documents (RFQ, PO, Contract, Scheduling Agreement)

To define a purchasing organization for University Cellular, follow the menu path:

Tools Customizing IMG Edit Project Enterprise Structure Definition Materials Management Maintain purchasing

organization (click clock icon )

This will produce the following screen: Click on the New entries icon ( ), which will allow you to create a purchasing

organization for University Cellular:

2- 9 02/09/09

Page 10: Configuration Guide to Create Organizational Structures in Sap Mm

Material Management Org. Structures

Enter purchasing

organization here

Enter:

Purch. organization: ##CR

Purh. org. descr.: ## Purchasing

Click on the save icon ( ) and then on the exit icon ( ) to complete the creation of the

purchasing organization.

4. Create Purchasing Groups

A purchasing group is a buyer or group of buyers who are responsible for a group or category of

items. The purchasing group in SAP provides for reporting functionality. Business Reports in

the Logistics Information System (LIS) can be summarized according to purchasing group.

For University Cellular, two purchasing groups will be defined: ## Components and ##

Packaging.

To define a purchasing group, follow the menu path:

2 - 10 02/09/09

Page 11: Configuration Guide to Create Organizational Structures in Sap Mm

Material Management Org. Structures

Tools Customizing IMG Edit Project

Materials Management Purchasing Create purchasing groups (click clock icon

)

which will produce the following screen:

Click on the New entries icon ( ), which will allow you to create purchasing

groups for University Cellular:

2 - 11 02/09/09

Page 12: Configuration Guide to Create Organizational Structures in Sap Mm

Material Management Org. Structures

Enter Purchasing Group

Enter the following purchasing group:

Purchasing

Group Description

##C ## Components

##P ## Packaging

Click on the save icon ( ), then on the exit icon ( ) to complete the creation of the

purchasing groups.

Definition and Assignment

Much of configuration involves definition of objects and then assigning these objects to each

other, a process that can be referred to as "Definement and Assignment." With all of the basic

materials management structures defined, it is time to assign them to each other.

2 - 12 02/09/09

Page 13: Configuration Guide to Create Organizational Structures in Sap Mm

Material Management Org. Structures

5. Assign Plants to Company Code

Follow the menu path:

Tools Customizing IMG Edit Project Enterprise Structure Assignment Logistics-General Assign plant to company

code (click clock icon )

And click on New entries icon ( ), which will produce the following screen:

Enter your

company code

##UC and plant

##CP then Save

Click on the back icon ( ), you should be able to see that the assignment has been made. You

may need to scroll down to find your company and plant:

2 - 13 02/09/09

Page 14: Configuration Guide to Create Organizational Structures in Sap Mm

Material Management Org. Structures

Assignment of plant to

company code has been made

Click on the save icon ( ), then on the exit icon ( ) to complete the assignment of the

plant to the company code.

6. Assign Purchasing Organization to Company Code

Follow the menu path:

Tools Customizing IMG Edit Project Enterprise Structure Assignment Materials Management Assign purchasing

organization to company code (click clock icon )

which will produce the following screen:

2 - 14 02/09/09

Page 15: Configuration Guide to Create Organizational Structures in Sap Mm

Material Management Org. Structures

Enter your company code

##UC

Click on the save icon ( ), you should be able to see that the assignment has been made and then on the exit icon ( ) to complete the assignment of the purchasing organization to

the company code.

7. Assign Purchasing Organization to Plants

Follow the menu path:

Tools Customizing IMG Edit Project Enterprise Structure Assignment Materials Management Assign purchasing

organization to plant (click clock icon )

2 - 15 02/09/09

Page 16: Configuration Guide to Create Organizational Structures in Sap Mm

Material Management Org. Structures

And click on New entries icon ( ), which will produce the following screen:

Enter your purchasing organization ##CR and

your plant ##CP

Click on the save icon ( ), then on the back icon ( ), to confirm the assignment of the

purchasing organization to the plant.\

2 - 16 02/09/09

Page 17: Configuration Guide to Create Organizational Structures in Sap Mm

Material Management Org. Structures

Your purchase organization has

been assigned to your plant.

2 - 17 02/09/09