Upload
jon-kealy
View
216
Download
0
Embed Size (px)
Citation preview
7/25/2019 Communications Mgt Plan - 11102015
1/26
Assignment 1 Group 3
Student Names
Brett Ward
Jon KealyMark Robinson
Henry Baxter
Student Numbers
C3175979
C3101368
C3214379
C3249822
Due 11.59pm, 19thOctober 2015
Teacher Stuart Landrigan
ARBE6403 Project Communication
7/25/2019 Communications Mgt Plan - 11102015
2/26
Document Control
Title Glenbawn Dam Project
Name Position Signed/Approved Date
Originator Brett Ward Associate BW 11/10/15
Originator Jon Kealy Associate JK 11/10/15
Review MarkRobinson
Senior Associate MR 13/10/15
Approval Henry Baxter Director HB 14/10/15
Details of Revisions
Rev Date Description Approved
0 23/09/15 Preliminary plan Issued for draft JK/BW1 29/09/15 First Draft for Review JK
2 10/10/15 For Approval JK/BW
3 11/10/15 For Issue JK
4
5
6
7
7/25/2019 Communications Mgt Plan - 11102015
3/26
7/25/2019 Communications Mgt Plan - 11102015
4/26
Glenbawn Dam Project | Communications Management Plan i
Contents1. Project Description.................................................................................................................................... 2
1.1 Background for Glenbawn Dam Project........................................................................................ 2
1.2 Description of the Glenbawn Dam Project..................................................................................... 2
2. Definitions................................................................................................................................................. 3
3. Purpose and Scope of this Management Plan......................................................................................... 4
3.1 Objectives...................................................................................................................................... 4
4. Organisation and Accountabilities............................................................................................................ 6
4.1 Management Team Structure........................................................................................................ 6
4.2 Key Project Roles........................................................................................................................... 6
4.2.1 Project Director............................................................................................................... 6
4.2.2 Project Manager............................................................................................................. 7
4.2.3 Communications Manager.............................................................................................. 7
5. Strategic Approach................................................................................................................................... 8
5.1 Stakeholder Identification Approach.............................................................................................. 8
5.1.1 Stakeholder Identification............................................................................................... 9
5.2 Communication Tools for Issuing Information............................................................................. 10
5.3 Communication Escalation Process............................................................................................ 13
6. Key Issues Identification......................................................................................................................... 14
7. Key Messages........................................................................................................................................ 15
7.1 Project Positioning Key Messages............................................................................................... 15
7.2 Issue Specific Key Messages...................................................................................................... 158. Community Engagement and Feedback Mechanisms........................................................................... 17
8.1 Community Information Sessions................................................................................................ 17
8.2 Objectives.................................................................................................................................... 17
8.3 Structure....................................................................................................................................... 18
8.4 Enquiries/Complaints Management............................................................................................. 18
9. Templates............................................................................................................................................... 20
9.1 Complaint Form............................................................................................................................ 20
9.2 Meeting Agenda........................................................................................................................... 21
9.3 Meeting Minutes........................................................................................................................... 22
9.4 Notification to the Community...................................................................................................... 23
List of Figures
Figure 1: Project Location .. ................................................................................................................... ..2
Figure 2: Project Organisation Chart........................................................................................................ 6
List of Tables
Table 1: Proposed Glenbawn Dam Project Communication Tools.....10
Table 2: Priority Definition .13
Table 2: Key Stakeholder Issues Analysis Functional Issues...............................14
7/25/2019 Communications Mgt Plan - 11102015
5/26
Glenbawn Dam Project | Communications Management Plan 2
1. Project Description
1.1 Background for Glenbawn Dam Project
The New South Wales Government has been extensively planning to secure long term water
supplies for the Upper Hunter region that has endured high unemployment, minimum
existing local industry and a shrinking agriculture industry. Following a feasibility study
conducted by Pricewaterhouse Coopers Pty Ltd it was indicated that if the supply of
sufficient water is guaranteed, the private sector will invest significant amounts of money
into new industries. As well, the private sector will invest in the redevelopment of existing
industries and significantly upgrade the regions agricultural base. Further feasibility studies
indicate that a Government investment of approximately $150million will result in significant
economic, social and community benefits. The Government will also have opportunity for
significant reform to its water resources policy and the sale of water rights.
1.2 Description of the Glenbawn Dam Project
The proposed site of the Project is approximately 20 kilometres east of Scone, 30 kilometres
west of the Barrington Tops National Park.
The Lake Glenbawn Dam Project, will result in regional employment during construction andlong term regional employment growth. It will also assist the New South Wales Government
in reaching its regional policy objectives. The project is located in an area that minimises the
dams environmental impact and the amount of private land that will be flooded. However,
the project requires the support of four local government areas and there are vocal sections
of these communities that do not support the construction of a dam.
Figure 1: Project Location Google Maps 2015
7/25/2019 Communications Mgt Plan - 11102015
6/26
7/25/2019 Communications Mgt Plan - 11102015
7/26
Glenbawn Dam Project | Communications Management Plan 4
3. Purpose and Scope of this Management Plan
The purpose of this Communications Management Plan (Plan) is to present the community
engagement objectives, delivery framework and the potential issues the project needs to
manage. It also provides information on the communication tools and protocols which will
support implementation and descriptions of how community stakeholders will be kept
informed of and consulted about the Glenbawn Dam Project throughout the delivery and
commissioning phases.
This Plan provides the framework for communication between the Project Team, the local
community and key external stakeholders. In particular, it details the following elements:
Identification of community and key external stakeholders
Identification of project related issues, affected stakeholders and communication
tools
Procedures and mechanisms for providing information to the community and key
stakeholders
Explanation of the purpose and operation of community information sessions
Procedures and mechanisms for how the Project Team will receive and respond to
community feedback, enquiries and complaints
Explanation of how disputes will be resolved.
3.1 Objectives
All communication developed and distributed throughout the Glenbawn Dam Project is
intended to achieve the following goals:
Stakeholders are aware and informed: stakeholders receive timely information about
what is happening, why, when and how, and what it means to them. This informationstarts at a generic level (which is repeated throughout the programme/Project), and
becomes more detailed, specific and targeted as the programme/ Project progresses.
This information enables stakeholders to think about, understand, plan for and be
prepared for the change.
Stakeholders are engaged: Opportunities are created and communicated to key
stakeholders to support them in exploring and becoming involved in and committing
to a new way of doing things. Different stakeholders will move through this transition
7/25/2019 Communications Mgt Plan - 11102015
8/26
Glenbawn Dam Project | Communications Management Plan 5
at different rates. Communication will aim to gain key stakeholders commitment by
implementation. However strategies will also be developed to manage stakeholders
who are still in denial or resistance after the transition. Communication is two-way with stakeholder input and feedback sought and valued at all stages.
Stakeholders expectations are managed: The aim of communication is to provide a
set expectation of scope of what is planned (and associated constraints, risks &
dependencies), explain why this may differ from expectations (in targeted messages),
and provide ongoing updates on expected and actual outcomes.
7/25/2019 Communications Mgt Plan - 11102015
9/26
Glenbawn Dam Project | Communications Management Plan 6
4. Organisation and Accountabilities
4.1 Management Team Structure
The Communication Teams (CT) main function is to support the Project in the delivery of
works. The CT works in parallel with the Environment Management team to manage and
resolve construction issues including the event of a pollution incident, environmental impacts
(noise, water dust).
The Community Manager (CM) liaises, as required with the projects nominated
Environmental Manager to ensure issues relating to the management of environmental
complaints/enquiries have been satisfactorily addressed. The CM will report directly to the
Project Manager as seen below in the Organisation Chart.
Figure 2: Project Organisation Chart
4.2 Key Project Roles
4.2.1 Project Director
The Project Directors accountabilities in relation to communication relations are as follows:
a) Review monthly reports from the CM and be copied in on daily complaints report to
stay informed of key stakeholder issues raised and associated resolutions;
b) Review and approval of internal and external stakeholder reports; and
7/25/2019 Communications Mgt Plan - 11102015
10/26
Glenbawn Dam Project | Communications Management Plan 7
c) Participate in project presentations to stakeholders and site visits, as required
4.2.2 ProjectManager
The Project Managers accountabilities in relation to communication relations are as follows:
a) Understand and comply with the Communications Management Plan processes and
protocols that relate to the works carried out and ensure compliance on-site
personnel;
b) Assist the CM to liaise with contractors to ensure understanding and acceptance of
communication protocols and processes as they relate to the conduct of on-site work
activities;
4.2.3 Communications Manager
The Communications Managers accountabilities in relation to communication relations are
as follows:
a) Ensuring the community is well informed and are aware of the project activities by
providing regular, accurate and timely information through a range of communication
channels;
b) Delivering effective community engagement and two-way communication to provide
stakeholders with opportunities to connect and interact, identify issues/concerns and
actively participate in developing solutions;
c) Responding to complaints within the required timeframes and minimising the
potential for issues to minimise the potential for issues to escalate into areas such as
media and/or political arenas;
d) Identifying potential project issues and their impact and proactively devising
communication strategies to avoid, minimise or resolve them (or their impact);
e) Ensuring the project team is aware of the consultation framework and is made aware
of issues as and when they arise; and
f) Identifying opportunities to build community goodwill and a positive attitude towards
the project.
7/25/2019 Communications Mgt Plan - 11102015
11/26
Glenbawn Dam Project | Communications Management Plan 8
5. Strategic Approach
The Project Teams approach to communications management focuses on building
relationships and targeting information to meet specific stakeholder requirements.
Essentially, the intended approach incorporates:
a) No surprises;
b) Ongoing consultation with stakeholders (tailored to meet needs and expectations)
that is delivered within an open and honest environment, engenders trust and
encourages beneficial two-way communication;
c) Information is effectively communicated in a clear, timely and accurate manner;
d) Prompt handling and resolution of enquiries and complaints ; and
e) Use of a range of communication activities, tactics and channels to achieve maximum
information distribution and widespread stakeholder understanding of construction
constraints and programme.
5.1 Stakeholder Identification Approach
For the purpose of this plan, the projects community comprises a diverse range of
stakeholders that have a direct interest in and or will be affected by the project. For further
information please read the Stakeholder Management Plan.
During the project stakeholder identification, it will be the responsibility of the Project
Manager to undertake stakeholder engagement in order to determine the frequency and
deliver method of the communications to meet their needs. Once all stakeholders have been
identified and the establishment of communications requirements are finalised, this
information will be transferred into the Projects Stakeholder Register and retained for the
duration of the project.
Project communication will be undertaken in line with the identified key areas as outlined in
the Communication Matrix at 5.2. There may be times when individual communication is
required to achieve any project constraints, however these must be clearly documented and
retained for future referencing if required.
7/25/2019 Communications Mgt Plan - 11102015
12/26
Glenbawn Dam Project | Communications Management Plan 9
In addition, to the identified communications preferences, there is a need to clearly define
the delivery mechanism for providing the communications and ensure that the stakeholders
have access to the required information.
5.1.1 Stakeholder Identification
a) Local Residents and Property Owners
b) Schools, Educational Facilities and Childcare Centres
c) Pre Schools/Day Care Centres
d) Primary/ High schools
e) Emergency Services
f) Local Councils x 4g) Political Stakeholders
a) Federal
b) State
h) Government Agencies (State-based)
i) Federal
j) Service and Utility Provider Organisations
k) Sporting and Other Community Facilities
l) Local Community Groups, Action Groups and Churches
m) Action Groups
n) Community Groups
o) Local Businesses
7/25/2019 Communications Mgt Plan - 11102015
13/26
Glenbawn Dam Project | Communications Management Plan 10
5.2 Communication Tools for Issuing Information
Table 1: Proposed Glenbawn Dam Project Communication Matrix
CommunicationType
Objective ofCommunication
Medium Frequency Audience Owner Delive
Kickoff Meeting Introduce the projectteam and the project.Review projectobjectives andmanagementapproach.
- Face toFace
Once - ProjectSponsor / Client- Project Team- Stakeholders
ProjectManager
- Agenda- Meeting
Project Team Meetings Review status of theproject with the team.
- Face toFace- Conference
Call
Weekly - Project Team ProjectManager
- Agenda- Meeting - Project S
Technical DesignMeetings
Discuss and developtechnical design
solutions for theproject.
- Face toFace
As Required - ProjectTechnical Staff
TechnicalLead
- Agenda- Meeting
Monthly Project StatusMeetings
Report on the status ofthe project tomanagement.
- Face toFace- ConferenceCall
Monthly -Project Sponsor/ Client
ProjectManager
- Slide UpProject Sc
Project Status Reports Report the status ofthe project includingactivities, progress,
costs and issues.
- Email Monthly - ProjectSponsor / Client- Project Team
- Stakeholders- PMO
ProjectManager
- Project SReport- Project S
Community informationsessions
Outline the projectobjectives and discussitems of contention
-Face toFace
Once -Project Team-Stakeholders-Governmentrepresentatives
ProjectManager &Sponsor
- Agenda- Meeting
7/25/2019 Communications Mgt Plan - 11102015
14/26
Glenbawn Dam Project | Communications Management Plan 11
Project Notifications Update on projectstatus and up andcoming works
-Web page-Email-Letter box
drops
Monthly -Client-Project Team-Stakeholders
ProjectManager
Project No
Targeted notifications Residents / tenantsnotification of works inclose proximity to themWorks identified asnoisy or causingtraffic/pedestrianchanges
-Letter boxdrops-Face to face-Email-Project Webpage
As required andidentified in theproject programme
-Stakeholders-residents-Business
ProjectManager
Project No
Written correspondence(letters/emails)
As required -As required As required As received ProjectManager
Responsesender
Advertisements Update on projectstatus
During critical projectstages
-Localnewspapers
MonthlyAt critical stages
-Stakeholders-residents
-Business
ProjectManager
Confirmpublicatio
Fact sheets and FAQs Project informationand frequently askedquestions
-Stakeholderforum-Project Webpage
Planning stage & asrequired
-Stakeholders-residents-Business
ProjectManager
Confirm reand updatrequired
Project key contacts Provision of keycontacts foremergency or generalcontact
-Letter boxdrops-Face to face-Email-Project Webpage-Part ofAdvertisements
As required -Stakeholders-residents-Business
ProjectManager
Create capreparatio
Translation service Provide avenues fortranslation services tobe provided forpersons who may notbe English spoken
-Letter boxdrops-Face to face-Email-Project Webpage
As required -Any partyrequiringtranslationservicesassociated withthe project
ProjectManager
Have the confirmedplace
7/25/2019 Communications Mgt Plan - 11102015
15/26
Glenbawn Dam Project | Communications Management Plan 12
-Part ofAdvertisements
Fixed and variablemessage signs
Provide information atkey points for personswho may not receiveproject information
At keylocations
At key intersectionsas outlined in theProjectCommunications
Any party ProjectManager
Confirm lothat are idas key to transmiss
Website
Provide web basedservice for any partieswho require access tothe project information
Web Weekly Any Party ProjectManager
Have the operationathe planni
Enquiries/complaintsprocedures
Formulate theprocedure formanagement of projectenquiries andcomplaints
WebPhoneFace to FaceWritten andemailed
Correspondence
As required Any party ProjectManager
Have theprocedureand sign ooutset of tplanning p
7/25/2019 Communications Mgt Plan - 11102015
16/26
Glenbawn Dam Project | Communications Management Plan 13
5.3 Communication Escalation Process
As the project progresses there may be occasions when issues or complications arise with
regards to project communications. This may require these to be escalated if resolution
cannot be achieved within the project team. While escalations are a normal part of project
management, there must be a documented process that defines how those escalations will
take place.
Communications need to be managed efficiently and in a timely manner to ensure the project
is not adversely impacted upon. It is therefore imperative that disputes, conflicts, or
discrepancies regarding project communications are resolved in a way that is conducive to
maintaining the project schedule, ensuring the correct communications are distributed, and
preventing any ongoing difficulties. In order to ensure projects stay on schedule and issues
are resolved, we intend to use a standard escalation model to provide a framework for
escalating communication issues. The table below defines the priority levels, decision
authorities, and timeframes for resolution.
Table 2: Priority Definition
Priority Definition DecisionAuthority
Timeframe for Resolution
Priority 1 Major impact to project or businessoperations. If not resolved quickly therewill be a significant project impacts.
GeneralManager
Within 4 hours
Priority 2 Medium impact to project or businessoperations which may result in someadverse project impacts
ProjectSponsor
Within one business day
Priority 3 Slight impact which may cause someminor scheduling difficulties with the
project but no adverse project impacts.
ProjectManager
Within two business days
Priority 4 Insignificant impact to project but theremay be a better solution.
ProjectManager
Work continues and anyrecommendations are submitted viathe project change control process
7/25/2019 Communications Mgt Plan - 11102015
17/26
Glenbawn Dam Project | Communications Management Plan 14
6. Key Issues Identification
Table 3: Key Stakeholder Issues Analysis
FunctionalIssues
Stakeholders Impacted Strategies and CommunicationTools
Relocation ofresidence
Residents Up front communications and negotiations.Face to face discussions outlining theproject impact to property owners individually
Reduction inresidential property
Residents Up front communications and negotiations.Face to face discussions outlining theproject impact to property owners individually
Road closures Members of the Public /Residents / Businesses
Meetings, Advertisements in local papers,road side variable message screens, Projectnotifications via letter box drops, email andweb, Face-to-face discussions.
Environmental Flora / Fauna Meetings with environmental groups todiscuss the significance of the project andthe assessed impacts to the environment.Formulation and sign off of theEnvironmental Impact Statement (EIS). TheEIS will identify the environmental impactsand any Fauna that may be endangeredwhich may be relocated. The EIS will alsoconfirm that the Fauna impacted upon is notendangered.
Construction noise Residents / Businesses Meetings, Advertisements in local papers,road side variable message screens, Projectnotifications via letter box drops, email andweb, Face-to-face discussions.
Higher vehiclemovements
Members of the Public /Residents / Businesses
Meetings, Advertisements in local papers,road side variable message screens, Projectnotifications via letter box drops, email andweb, Face-to-face discussions.
7/25/2019 Communications Mgt Plan - 11102015
18/26
Glenbawn Dam Project | Communications Management Plan 15
7. Key Messages
7.1 Project Positioning Key Messages
Due to the requirements for long term water supply in the region, the government has been
lobbied extensively to ensure that the region remains sustainable into the future.
The government has completed a feasibility study which indicates an investment for the
project of approximately $150million. The delivery of this project will allow the Government
the opportunity to meet sustainability and growth opportunities and achieving its regional
policy objectives. In additional, there will be an opportunity for a return on investment with
the sale of water rights after the project is complete.
The key messages pertaining to the new dam project are:
a) A boost to regional employment during and after the project through the use of local
resources and businesses. Currently the region has a high rate of unemployment with
local industry unable to support the existing growth.
b) The area selected will have minimal impact on residential dwellers, and Flora &
Fauna.
c) Provide future growth opportunities to regional agricultural industry that over theprevious years has been reducing due to restrictions on water
d) The supply of water after the project has been finished will be guaranteed as indicated
in the feasibility study. This in turn will provide continued investment in the region.
7.2 Issue Specific Key Messages
From the outset and throughout all stages of this project there will be a need to clearly
engage with the local community impacted upon by this project. The project team intends to
manage these specific issues effectively and efficiently to allow the project objectives to bemet with the least amount of impact to the local community, infrastructure and Flora and
Fauna. This will be achieved through:
a) Regular Stakeholder forums to allow open discussion around the project and its
deliverables.
7/25/2019 Communications Mgt Plan - 11102015
19/26
Glenbawn Dam Project | Communications Management Plan 16
b) Engagement of a Communications Manager to assist the Project Manager in
resolution of issues as they arise and implementing the communications plan
effectively.
c) Regular face-to-face discussions with property owners and businesses to clearly
define the project, keep them informed and take into account the stakeholder
concerns and where possible find an agreed solution to ensure escalation of the
issues does not occur.
7/25/2019 Communications Mgt Plan - 11102015
20/26
Glenbawn Dam Project | Communications Management Plan 17
8. Community Engagement and Feedback Mechanisms
The Glenbawn Dam Project will seek to engage and receive feedback from all community
stakeholders who are impacted by the project design and construction activities. Feedback
is important to ensure that the project benefits from local input and knowledge and causes
minimal disruption to the local community.
Two key tools which will be used to engage the community; receive and respond to feedback
are:
a) Community information sessions
b) Enquiries/complaints management procedure.
Feedback received on the project will be responded to in accordance with the
complaints/enquiries response time target of within two hours.
8.1 Community Information Sessions
Issue-specific community information sessions are a proactive way to provide information
and receive quality feedback from a wide range of stakeholders on issues that are relevant
to the targeted participants. They are especially effective on large projects like this where
the project impacts affect multiple stakeholder groups in different ways.
Community information sessions are used to address community issues/milestones as they
arise, to provide information and seek feedback.
8.2 Objectives
General and issue-specific information sessions will ensure that community members have
the opportunity to discuss with the project team issues that are of most interest/concern to
them. Specific objectives of community information sessions are to:
a) Establish personal contact with the community and reduce potential for prolonged
antagonism;
b) Encourage participation from relevant community members or groups affected by the
issue/s;
c) Respond to the particular needs and concerns of the community; and
d) Ensure an open and transparent way of sharing information.
7/25/2019 Communications Mgt Plan - 11102015
21/26
Glenbawn Dam Project | Communications Management Plan 18
8.3 Structure
Information sessions managed by the Communications Team are open to all members of
the community. To encourage community participation, invitations to information sessions
are distributed in a variety of ways including via newsletters/monthly project updates, in local
newspapers, and on the Project website.
One information session will be held primarily midweek (subject to community consensus
for alternate days) and one on the weekend. Information sessions will run for between two
and three hours depending on the issue and the level of community interest.
Where relevant and possible, the location of information sessions will be held nearby the
location of the topic being discussed.
Every effort is made to ensure community information sessions are open and accessible
and encourage maximum community attendance and participation. One of the information
sessions will preferably be held in the early evening (4pm to 7pm) and another on a Saturday
morning (10am to 12pm) to allow the widest cross-section of audiences to attend (eg. people
arriving home from work, elderly residents and business representatives).
8.4 Enquiries/Complaints Management
The Communications Team will be responsible for the management of all complaints and
enquiries received either via the /24-hour Complaint Line, project email, correspondence or
direct contact from stakeholders.
The key processes involved in recording complaints and enquiries are as follows:
Complaints
a) All complaints will be recorded daily;
b) All complaints received for the duration of the project will be responded to verbally by
the Communications Team within two (2) hours from the time contact is received;
and
c) A complaints report will be distributed to Project Team by COB;
Enquiries
a) All enquiries will be recorded daily;
7/25/2019 Communications Mgt Plan - 11102015
22/26
Glenbawn Dam Project | Communications Management Plan 19
b) All email enquiries will be responded to by the Communications Team within one (1)
business day of receipt; and
c) All phone enquiries will be responded to by the CLT by phone within two (2) business
hours from the time contact is received.
7/25/2019 Communications Mgt Plan - 11102015
23/26
Glenbawn Dam Project | Communications Management Plan 20
9. Templates
9.1 Complaint Form
FIRST NAME:LASTNAME:
RESIDENTIAL ADDRESS: POSTAL ADDRESS:Same asresidential
No No:
Street Street
Suburb Postcode:
Suburb Postcode:
Telephone (work): After hours /mobile:
Fax: Email:
Who received the inquiry:
Name: Date &Time:
Contact No: Facsimile:
Details of Concern:
Where? What? & When?
Sign: Date:
Action Taken (to be completed by Project Manager /Communications Manager)
Sign: Date:
7/25/2019 Communications Mgt Plan - 11102015
24/26
Glenbawn Dam Project | Communications Management Plan 21
9.2 Meeting Agenda
Meeting Number: Document ref No: xxxxxxxxx
Title / Purpose: Glenbawn Dam Project Community Information Meeting
Date: [INSERT]
Time: [INSERT]
Location: [INSERT]
Invitees: [INSERT] [INSERT]
Item
1. Introduction
2. Project Status Update
3. Address Unresolved Concerns from Previous Meeting
4. Upcoming Program of Works on the Project
5. Potential Impacts on the Community for the Upcoming Program of Works
6. Comments from the Floor
7. Discussion of Action Plan to Resolve Issues
8. Other business
9. Next Meeting - [INSERT]
7/25/2019 Communications Mgt Plan - 11102015
25/26
Glenbawn Dam Project | Communications Management Plan 22
9.3 Meeting Minutes
Meeting Number: [INSERT] Documentref No: xxxxxxxx
Title / Purpose: Glenbawn Dam Project Community Information Meeting
Date: [INSERT]
Time: [INSERT]
Location: [INSERT]
Attendees: [INSERT] [INSERT]
Apologies [INSERT] [INSERT]
Distribution As Above Plus Project Website, Local Paper, Letterbox Drop
ItemItemItemItem Action (by)Action (by)Action (by)Action (by)
1111.... IntroductionIntroductionIntroductionIntroduction
1.1
2.2.2.2. Project Status UpdateProject Status UpdateProject Status UpdateProject Status Update
2.1
3.3.3.3. Address Unresolved Concerns from Previous MeetingAddress Unresolved Concerns from Previous MeetingAddress Unresolved Concerns from Previous MeetingAddress Unresolved Concerns from Previous Meeting
3.1
4.4.4.4. Upcoming Program of Works on the ProjectUpcoming Program of Works on the ProjectUpcoming Program of Works on the ProjectUpcoming Program of Works on the Project
4.1
5.5.5.5. Potential Impacts on the Community for the Upcoming Program of WorksPotential Impacts on the Community for the Upcoming Program of WorksPotential Impacts on the Community for the Upcoming Program of WorksPotential Impacts on the Community for the Upcoming Program of Works
5.16.6.6.6. CommCommCommComments from the Floorents from the Floorents from the Floorents from the Floor
6.1
7.7.7.7. Discussion of Action Plan to Resolve IssuesDiscussion of Action Plan to Resolve IssuesDiscussion of Action Plan to Resolve IssuesDiscussion of Action Plan to Resolve Issues
7.1
8.8.8.8. Other BusinessOther BusinessOther BusinessOther Business
Next Meeting:Next Meeting:Next Meeting:Next Meeting: xx/xx/xxxx : xx:xx AM/PMxx/xx/xxxx : xx:xx AM/PMxx/xx/xxxx : xx:xx AM/PMxx/xx/xxxx : xx:xx AM/PM
7/25/2019 Communications Mgt Plan - 11102015
26/26
9.4 Notification to the Community
[INSERT MONTH] [INSERT YEAR]
[INSERT INFORMATION ON PROJECT STATUS AND/OR NOTIFICATION OF WORKS]
How can I have a say?Youre welcome to provide your feedback on the proposal by emailing [email protected] writing to:
Community Relations Glenbawn Dam Project
Att: Communications Manager
Locked Bag 1000
Newcastle NSW 2300
NOTICE TO RESIDENTS AND BUSINESSES
Contacto Enquiries: 1800 123 123o Urgent enquiries or complaints 24 hours: 1800 321 321o Email: [email protected] o Visit: www.glenbawndamproject.nsw.gov.au
[INSERT PROJECT PHOTO IF REQUIRED]