Coal Supply to TPPs-Issues and Challenges

  • Upload
    kannan

  • View
    216

  • Download
    0

Embed Size (px)

DESCRIPTION

Coal Supply to TPPs-Issues and Challenges

Citation preview

  • -ISSUES AND CHALLENGES

    1

    Gopal Prasad, Regional DirectorCMPDI, Asansol

  • 1200 million people - Second-largest population

    after China

    Impressive annual GDP growth averaging 7.6%

    from 2000 to 2007 and around 8 % since then

    INDIA-SOCIO-ECONOMIC SCENARIO

    from 2000 to 2007 and around 8 % since then

    Among top five countries of the world in terms of

    absolute GDP, based on purchasing power parity

    (PPP)

    2

  • BUT..

    On per-capita income basis - well behind other

    fast-growing nations

    Human development index Very poor

    Poverty still remains a major challenge.

    INDIA-SOCIO-ECONOMIC SCENARIO(Contd.)

    Poverty still remains a major challenge.

    Per capita electricity consumption (779 KW) far

    below the world average (2500 KW)

    Nearly 60 crore Indians do not have access to

    electricity

    3

  • Must maintain Economic growth of 8 % to

    10 % over the next 25 years to eradicate

    poverty and meet human development goals

    And to achieve sustained growth Growth

    of Power Sector is paramount because:

    WHAT NEEDS TO BE DONE

    of Power Sector is paramount because:

    Electricity a basic human need and

    economic indicator

    Electricity - Critical infrastructure on which

    the socio-economic development of the

    country depends

    4

  • Access to Electricity To be made available

    for all households

    Availability of Power - Demand to be fully

    met by 2012

    NATIONAL ELECTRICITY POLICY OBJECTIVES

    met by 2012

    Per Capita Electricity Ensuring Per capita

    availability of electricity over 1000 units by

    2012.

    5

  • One of the largest and most important industries in

    India fulfilling the energy requirements of various

    other industries.

    One of the most critical components of infrastructure

    affecting economic growth and the well-being of our

    nation.

    INDIAN POWER SECTOR

    nation.

    Significant progress after Independence 1362 MW

    in 1947 to 190592 MW (Feb, 12) 140 fold increase in

    65 years

    Per capita consumption of electricity from 15 kWh in

    1950 to about 779 kWh in 2009-10 about 52 times.

    6

  • Thermal Power65.4 % of total installed capacityMain raw material used is coal around 84.5 % of thermal

    power generated using coal and rest (14.5 %) by using Gas and Oil

    Hydro Power20.4 % of total installed capacity Hydro power generation potential worth 1,50,000 MW Only

    25 % harnessed till date

    share of generating capacity declined from 34 per cent at the

    end of the Sixth Plan to 20.5 per cent at the end of the eleventh

    PRIMARY SOURCES OF POWER

    end of the Sixth Plan to 20.5 per cent at the end of the eleventh

    Plan.

    Nuclear Power2.5 % of total installed capacity Heat sourced from nuclear reactors is used

    Renewable Energy Sources11.7 % Renewable sources like sun, wind, biomass

    Great potential to contribute to our energy security and

    reducing green-house gas emissions

    Among top 5 largest wind power generators in the world. 7

  • PRESENT INSTALLED CAPACITY

    All

    India

    Thermal Power Nuclear Hydro RES Total

    Coal Gas Oil Total

    MW 105437.4 18093.9 1199.8 124731 4780 38848.4 22233.2 190592.6

    % 55.3 9.5 0.6 65.4 2.5 20.4 11.7 100

    POWER GENERATIONPOWER GENERATION

    798949.5 Million Units up to Feb-12 against

    the target of 855000 Million Units for 2011-12

    Energy deficit of 11.1 % and peak demand

    deficit of 12.1 % during February-2012.

    8

  • Year Projected

    population

    (million)

    Projected demand of Electricity Target for

    2011-12Total

    Electricity

    (Billion KWh)

    Peak

    Demand

    (GW)

    Capacity

    (GW)

    2011-12 1200 1167 168 233 Capacity192

    PROJECTION OF COUNTRYS ELECTRICITY

    DEMAND - IEP REPORT

    2011-12 1200 1167 168 233 Capacity192

    Giga Watts

    Generation

    880 Bl. Units

    2016-17 1275 1687 250 337

    2021-22 1347 2438 372 488

    2026-27 1411 3423 522 685

    2031-32 1468 4806 733 960

    Power generation to grow at an average rate of not

    less than 6 % in years to come

    9

  • COAL TO REMAIN AS MAINSTAY

    Indian power sector heavily dependent on coal for

    meeting its power generation targets

    Consumes about 66 % of the coal Consumption (Year-

    2010)

    Power Steel Cement Others Total

    Million 372 41 26 127 566Million

    Tonnes

    372 41 26 127 566

    % 65.8 7.2 4.6 22.4 100

    Above trend to continue in future It is estimated

    that Coal would account for 56 % of installed capacity

    in 2030

    10

  • POWER COAL DEMAND-SUPPLY GAP

    Most of the recent incremental generation

    capacity additions - coal based

    Future Scenario - to remain unchanged

    IX Plan

    (Actual)

    X Plan

    (Actual)

    XI Plan

    (Likely)

    XII Plan

    (Potential)

    Incremental capacity

    addition (MW)

    19119 20950 52000 80000

    Coal Based (MW) 7930 8575 35000 62700

    11

  • Period Coal

    consumption

    Total Coal receipt by TPPs

    including import (MT)

    Import of coal

    by Power

    Trend over the years - gap between demand of coal

    and its indigenous availability is increasing resulting

    into increased volume of coal import

    POWER COAL DEMAND-SUPPLY GAPContd.

    consumption

    By TPPs (MT)

    including import (MT) by Power

    Sector (MT)

    2006-07 300.561 301.417 7.780

    2007-08 322.437 321.433 8.067

    2008-09 346.543 349.754 14.190

    2009-10 360.845 367.652 23.230

    2010-11 377.875 380.336 30.302

    2011-12 (up to

    Dec-12)

    292.652 292.370 33.251

    12

  • Projected Demand Supply Gap : As high as 943

    POWER COAL DEMAND-SUPPLY GAPContd.

    Gap between demand and supply of thermalcoal is showing increasing trend.

    Besides Power, Coal is also required by theother industrial sectors of the Country.

    Projected Demand Supply Gap : As high as 943

    MT in 2031-32

    XI Plan (2011-12)

    (Target in MT)

    XII Plan (2016-17)

    (Projection in MT)

    XIII Plan (2021-22)

    (Projection in MT)

    IEP (2031-32)

    (Projection in MT)

    Demand of Coal 696.3 980.50 1373.00 2343.00

    Domestic

    production

    554.00 795.00 950.00 1400.00

    Gap 142.03 185.50 423.00 943.00

    13

  • SECURED COAL SUPPLY FOR POWER

    SECTOR WAY FORWARD

    To achieve the objective of secured supply of coal,

    effective management of both-the supply side and

    demand side of Coal - is of paramount importance.

    Supply side comprises coal resources

    augmentation, production and procurement of coal

    and movement of coal from the source to the Power

    Plants.

    Demand side of coal is represented by conversion,

    distribution and utilization of electricity.

    14

  • MANAGING THE SUPPLY SIDE

    Augmentation of Coal resources

    Type of Coal Proved (MT) Indicated (MT) Inferred (MT) Total (MT)

    Coking Coal 17669.03 13703.32 2101.91 33474.26

    Non-Coking Coal 95738.76 12368.44 31488.11 250895.31

    Tertiary Coal 593.81 99.34 799.49 1492.64

    Grand Total 114001.60 137471.10 34389.51 285862.21

    (GSI Figures)

    Geological hard coal resources of 286 BT, but only 40 % proven

    Geological hard coal resources of 286 BT, but only 40 % proven

    Experts estimate that only 21% of the inplace resources can be

    recovered (inplace resource to mineable reserve ratio of 4.7:1)

    Recoverable coal reserves, thus, about 58.6 BT.

    Thus, urgent need to bring inferred and indicated resources under

    proven category by increased rate of detailed exploration

    Prop up the rate of promotional drilling for augmenting the overall

    resource base

    Introduce modern techniques for achieving higher exploration rate.

    15

  • INITIATIVES TAKEN

    CIL in association with GSI, MECL and private drillers

    has upped drilling performance

    Aim - to increase resources in proved category and

    add new resources through promotional drilling.

    Drilling targets increased from 520000m in FY-10 to

    610000m in FY-12.610000m in FY-12.

    Going for adoption of modern exploration

    technologies for rapid delineation of resources.

    Efforts are being made towards classification of

    resources as per UNFCC code.

    16

  • MANAGING THE SUPPLY SIDE (Contd.)

    Enhancement of Indigenous Coal production

    Envisaged targets

    Sources CIL

    (MT)

    SCCL

    (MT)

    Captive Block owners

    and others (MT)

    Total

    (MT)

    2011-12 447 51 56 554

    2016-17 615 57 123 7952016-17 615 57 123 795

    2021-22 650 63 237 950

    IEP (2031-32) 1400

    Indigenous coal production from primarily three

    sources CIL, SCCL and Captive Block Miners and

    others.

    Limited scope of augmenting coal output from SCCL

    Onus on CIL and captive Mining.17

  • MANAGING THE SUPPLY SIDE (Contd.)

    CHALLENGES BEFORE CIL

    Growth from 70 MT in early 1970s to in excess of

    400 MT at present

    Stagnating in recent years

    Year FY-05 FY-06 FY-07 FY-08 FY-09 FY-10 FY-11Year FY-05 FY-06 FY-07 FY-08 FY-09 FY-10 FY-11

    MT 324 343 361 379 404 431 431

    Reasons

    Problems of Land acquisition

    Delays in obtaining Environmental Clearances

    Law and Order problems

    Low Productivity18

  • Problems of Land acquisition

    Biggest bottleneck for CIL in achieving targets

    Projects delayed due to non-acquisition of land

    Against the target of 62000 Ha of land during XI Plan,

    acquisition of only 6000 Ha

    In-ordinate delays in acquisition of forest land In-ordinate delays in acquisition of forest land

    multiple State and Central Government agencies

    Delays in acquisition of Tenancy land

    non-availability of ownership records

    non-cooperation from local administration

    absence of uniform R&R policy

    19

  • Delays in obtaining Environmental Clearances

    Normative time for obtaining EC is 2-3 years,

    but on average it takes 5-6 years

    In the FY-11, 154 projects (210 MT total

    capacity) of CIL were waiting for environmentalcapacity) of CIL were waiting for environmental

    clearance.

    Augmentation of production from existing

    projects also requires fresh EC delay in

    expansion Projects

    20

  • A good chunk of CILs mining areas fall in Naxal-

    affected belts

    Frequent Bandhs affecting coal output adversely

    Land acquisition in these areas is doubly difficult.

    Law and Order problems

    Low Productivity

    Production from the UG mines showing downward

    trend over the years

    UG mines are operating with very low productivity.

    Mass production technology adopted in very few

    mines.

    Many small Open cast mines also operating with

    very low capacity HEMMs and low efficiencies

    21

  • 91 projects (ultimate capacity 207 MT) identified in X

    Plan of which 86 approved and underway Expected to

    contribute 100 MT in FY-12

    76 projects (ultimate capacity 178.78 MT) identified in XI

    Plan approved and underway

    Adopting latest technologies in its mines going for high

    capacity equipment in Open Cast mines.

    INITIATIVES TAKEN BY CIL

    capacity equipment in Open Cast mines.

    Introduced high wall miner to win the coal blocked beyond

    the ultimate pit boundary.

    Introduced independent truck dispatch system in OCPs

    Introduced continuous miners in several UG mines

    aiming to introduce mass production technology for UG

    operations.

    Invited bids for private participation in winning coal in

    abandoned mines. 22

  • Efforts to identify sources of coal in the foreign countries acquired two

    virgin blocks in Mozambique

    Invited EOI from global operators for selection of strategic partners for

    overseas operations

    Efforts for long term contracts with foreign sources of coal with an aim

    to ensure secured supply of coal on sustainable basis

    Envisaging buying stakes in foreign coal companies for obtaining coal

    supplies.

    INITIATIVES TAKEN (Contd.)

    Strengthening coal evacuation infrastructures MOU with RITES for

    upgrading existing Sidings and also for launching new rail line projects

    Proposal to Railways for allowing self owned railway wagons

    Proposal to build three new rail links totaling 350 km to connect interior

    coal fields

    JV with Shipping Corporation for handling import of coal and with Indian

    Railways to transport imported coal to customers doorstep.

    Constant touch with various Ministries and State/local administration for

    statutory clearances in time and to obtain the assistance of local/state

    administration, wherever needed.23

  • Coal sector has been one of the most regulated sectors of Indian

    Economy till 1993

    Subsequently, captive coal mining has been allowed in several sectors

    including Power generation aim was to augment domestic coal

    production.

    Captive mining did not perform, as envisaged

    Out of 208 allotted blocks, mining could be started in only 26 blocks till

    date

    Likely contribution around 50 MT against targeted 100 MT (FY-12)

    CAPTIVE MINING CHALLENGES

    Likely contribution around 50 MT against targeted 100 MT (FY-12)

    Reasons for poor performance

    Lack of serious efforts by several block allottees towards

    development of allotted blocks leading to de-allocation of blocks

    Land acquisition problems

    Employment claim of land losers irrespective of quantum of land

    Resistance of PAPs against shifting to rehabilitation sites

    Scarcity of land for rehabilitation sites,

    Demand of exorbitantly high rate of land compensation

    Failure/ delays in obtaining Environmental and forestry clearances

    Delay in issuance of mining leases by State Governments

    24

  • Captive mining will have to come of age in future

    Output from these blocks needs to be enhanced from a

    level of around 50 MT in FY-12 to 123 MT in FY-17 and 237

    MT in FY-22.

    Some of the required reforms/steps for augmenting the

    coal output from captive blocks may be:

    Allocation to serious players newly introduced system of

    CAPTIVE MINING WAY FORWARD

    Allocation to serious players newly introduced system of

    competitive bidding likely to eliminate non-serious entities

    To create market mechanism for surplus coal produced

    Adopting single window system for statutory clearances

    Formulating an effective and uniform Land Acquisition

    and R & R Policy

    Provision of cost effective coal evacuation infrastructure

    Support from State Govt. agencies25

  • MANAGING THE SUPPLY SIDE (Contd.)

    Import of CoalGap between demand of Coal and indigenous availability of power coal is

    showing increasing trend.

    Besides Power Sector, Coal is also required by the other industrial

    sectors of the Country.

    In view of the projected demand of coal and anticipated indigenous

    availability, the demand-supply gap is likely to get wider:

    XI Plan (2011-12) XII Plan (2016-17) XI Plan (2021-22) IEP (2031-32)XI Plan (2011-12)

    (Target in MT)

    XII Plan (2016-17)

    (Projection in MT)

    XI Plan (2021-22)

    (Projection in MT)

    IEP (2031-32)

    (Projection in MT)

    Demand of Coal 696.3 980.50 1373.00 2343.00

    Indigenous

    availability

    554.00 795.00 950.00 1400.00

    Gap 142.03 185.50 423.00 943.00

    Up till now, the demand-supply gaps were not very wide and therefore

    have been managed by import of coal at a relatively smaller scale.

    However, to meet the burgeoning coal demand, there is no other way but

    to go for the import of coal in a comprehensive and planned manner.

    26

  • MANAGING THE SUPPLY SIDE (Contd.)

    Import of CoalIssues involved

    International coal market is facing severe competition owing to

    spurt in coal demand from all corners.

    Rising demand of coal in the international market to lead to

    increased price volatility.

    Present capacity of Indian ports not enough to handle the

    imported quantity

    Total coal handling capacity of 81 MT against coal traffic of 92

    MT (FY 09) idling of vessels

    Entry of cape size vessels restricted owing to lower draft of

    Indian ports requiring more number of trips of small size vessels

    Proposed capacity addition of ports will not be sufficient to

    handle the projected volume of coal import.

    27

  • INITIATIVES TAKEN AND WAY FORWARD

    To ensure sustainable import of coal at reasonable price, assured

    coal supply sources need to be located either by entering into long

    term agreement with foreign suppliers or by owning mines in a foreign

    country or by combination of both.

    Indonesia, South Africa and Mozambiqe would be ideal countries to

    approach for the sustainable import.

    Urgent need to ensure coal supply through import through bilateral

    Government level understanding between the two countries.Government level understanding between the two countries.

    Indian ports will have to be upgraded to meet the increased volume

    of coal import.

    Time has come to develop a modern and exclusive deep sea Coal

    terminals accompanied with dedicated/captive cargo.

    Besides augmenting the cargo handling capacity of ports, it is also

    essential to enhance the evacuation capacity for the outward

    movement of imported coal from the port to its destination.

    Government has taken a welcome decision in the Budget-2012-13 to

    exempt the import of coal from custom duty.

    28

  • MANAGING THE SUPPLY SIDE (Contd.)

    Strengthening logistic infrastructure

    Ironical that at on one hand Power Plants are facing shortage of coal

    and on the other hand CIL has a pit head stock of around 50 MT (as on

    1.1.12) lying unutilized.

    Mismatch clearly indicates that the countrys coal evacuation

    infrastructure is not capable enough to handle its entire coal

    production. The evacuation infrastructure has failed to keep pace withproduction. The evacuation infrastructure has failed to keep pace with

    coal production constant increase in the pit head stock from 27.20

    MT on 01.01.07 to 49.16 Mt on 01.01.12.

    Indigenous Coal production to rise constantly and may reach the

    level of 1400 MT by 2030.

    Also, about 900 MT coal likely to be imported (2030) to meet the

    Countrys projected energy demand.

    Thus, role of coal evacuation infrastructure is of paramount

    importance.29

  • WAY FORWARD

    Major chunk of coal movement by Rail (49 %) [ Road (27 %) and MGR (19

    %)]

    Scope of augmenting evacuation capacity through roads is limited.

    MGR is an area specific mode of transport cater to a limited area

    Hence, burden of coal transportation to be borne primarily by the

    Railways Coal traffic by rail mode to surpass 900 Million tonnes by 2030.

    Need of dedicated rail lines special NS & EW corridors may have to be

    considered by railways.

    Introduction of lighter wagons Will reduce the high net to tare load Introduction of lighter wagons Will reduce the high net to tare load

    ratio.

    A good option is to use Inland Water Transport for Thermal Power Plants

    located near the river basins eg Farakka & Kahalgaon Super TPS

    Emphasis on coal beneficiation will result in enhanced thermal

    efficiency of power plants and also reduction in hauling need by 6-10 %.

    Need to upgrade sidings and associated loading equipments,

    Loading & unloading infrastructure needs to be fully mechanized

    Aerial ropeway, Conveyor belt and Merry-Go-Round rail systems etc.

    need to be created and re-vamped wherever necessary30

  • MANAGING DEMAND SIDE OF COAL A VIABLE

    OPTION OF REDUCING DEMAND-SUPPLY GAP

    The Demand side of Coal can be monitored and managed

    by focusing primarily on three key areas namely:

    Improvement in conversion efficiency of TPPs

    Average conversion efficiency - 30 %, lower than world average of 36 %.Average conversion efficiency - 30 %, lower than world average of 36 %.

    Results in increased specific coal consumption - more CO2 emissions

    Steps needed to improve the efficiency of thermal power plants, which

    in turn would ensure reduced coal demand:

    Maintenance of existing TPPs

    Adopting high standards of plant maintenance, to maintain efficiency for

    longer periods.31

  • Design of new Power PlantsAdoption of supercritical (SC) and ultra-supercritical (USC) steam conditions for

    new generating plants, in conjunction with modern steam turbine designs key to

    improved plant efficiency Coal consumption is almost half in comparison to

    conventional sub-critical power plants.

    Drying of coal to reduce moisture content

    MANAGING DEMAND SIDE OF COAL A VIABLE

    OPTION OF REDUCING DEMAND-SUPPLY GAP

    contd.

    Drying of coal to reduce moisture content High moisture content of coal reduces the efficiency of Coal-fired plants up to five

    percentage points

    Adoption of efficient coal-drying technology using either waste heat or low-grade

    steam

    Reduction of Ash percentage Causes loss of heat Results in reduced conversion efficiency

    High ash content coal should be beneficiated prior to feeding to the power plants.

    32

  • Checking the Transmission and distribution losses

    Transmission and distribution losses are still

    hovering around 30 % a staggering loss.

    On the other hand such losses are as low as 4 % in

    Japan, South KoreaJapan, South Korea

    Even many developing countries have managed to

    peg this loss under 15 %

    Urgent need to curb such losses, which in turn

    would result in reduced coal demand.

    33

  • Judicious use of electricity, use of energy

    efficient home appliances, conservation of power

    etc. Electricity saved is equivalent to electricity

    generated.

    FEW MORE STEPS FOR REDUCING THE DEMAND OF COAL

    More emphasis on other sources Non-

    conventional sources, Nuclear power, Hydel power,

    gas based power etc.

    Developing alternative sources of energy such as

    CBM, CMM, Shale gas, Coal to liquid etc.

    34

  • 35

  • Conclusion

    India has the secondlargest population after China, with an estimated 1200 million people. Although Indias annual GDP

    growth has been impressive in recent years, but human development index has not improved. Poverty still remains a

    major challenge. If India has to eradicate poverty and meet its human development goals, it needs to sustain an

    economic growth of 8 % to 10 % over the next 25 years for which proportionate growth in power sector is a must. Power

    sector has a very important role to play in achieving the desired growth rate in a sustainable manner. To meet the power

    requirements, the sector will have to add at least 20-30 GW of generation capacity on yearly basis.

    Indian power sector is heavily dependent on coal for meeting its power generation targets. About 66 % of the coal in the

    country is presently consumed in the power sector (Year-2010). At present about 55 % of total electricity production in

    India is from Coal Based Thermal Power. It is estimated that Coal would account for about 56 % of power generated in

    India even in 2030. Thus coal is going to remain mainstay for achieving the Power generation targets for many years to

    come.

    At present, India is unable to meet its thermal coal requirements from indigenous sources. The gap between the demand

    of thermal coal and indigenous supply is gradually getting wider. During the current financial year 2011-12, the

    anticipated gap between the requirement and availability of domestic coal has been estimated around 54 MT, which isanticipated gap between the requirement and availability of domestic coal has been estimated around 54 MT, which is

    being made up by import of coal. In view of the projected demand of coal and projected availability of indigenous coal,

    the demand-supply gap is bound to get wider in the coming years.

    It, therefore, becomes extremely important for the growth of countrys power sector to not only ensure development and

    availability of domestic coal resources but also look for import of coal in a sustained manner to fill up the demand-supply

    gap.

    However, there are various issues and challenges, which need to be tackled for a secured supply of coal to the country

    in general and power sector in particular. There is immediate need for initiating multipronged corrective actions to

    overcome the various issues and challenges, which are coming in the way secured supply of coal to the industries.

    Some of the suggested actions are augmentation of indigenous coal resources, ease and clarity in land acquisition

    process, effective and time bound Environmental & Forestry clearance process, emphasis on increased productivity in

    mines, adoption of modern technology-both in mining as well as power generation, stress on coal beneficiation, effective

    action towards securing import of coal from reliable foreign sources in a sustained and cost effective manner,

    modernization of coal evacuation infrastructure, laying emphasis on increased generation efficiency, checking T & D

    losses etc.

    36