civil project report

  • Upload
    kamran

  • View
    216

  • Download
    2

Embed Size (px)

Citation preview

  • 7/25/2019 civil project report

    1/96

    1

    A major PROJECT REPORT

    ON

    national HIGHWAY CONSTRUCTIONS

    Session 2009-13

    Under guidance of

    Er. S.K.Gupta

    H.O.D CIVIL ENGINEERING)

    SUBMITTED BY

    CHANDRADEEP SHUKLA 0307CE091017)

    ABHINAV JAISWAL 0307CE091001)

    AMAR DEEP GAUTAM 0307CE091006)

    PRAKASH NARAYAN MISHRA 0307CE091030)

    PAWAN GAUTAM 0307CE091029)

    SUBMITTED TO

    Er. S.K.Gupta

    H.O.D CIVIL ENGINEERING)

    ADITYA COLLEGE OF TECHNOLOGY AND SCIENCE

    SATNA (M.P.)

  • 7/25/2019 civil project report

    2/96

    2

    Rajiv Gandhi Proudyogiki Vishwavidyalaya, Bhopal(M.P)

    Aditya College of Technology & Science

    Satna (M.P)

    CERTIFICATE

    This is to certify that the project entitled asnational

    HIGHWAY CONSTRUCTIONS which has been completed &submitted by CHANDRADEEP SHUKLA , ABHINAV JAISWAL, AMAR DEEP

    GAUTAM , PRAKASH NARAYAN MISHRA,PAWAN GAUTAMin partialfulfillment of the requirement for the award of the degree of Bachelorof Engineering in CIVIL ENGINEERINGfor the session 2009-2013 is a bonafied work by them and has been completed under my

    guidance and supervision. It has not been submitted elsewhere for anyother degree.

    H.O.D Principal Guided By

    Er.S.K.Gupta Dr.J.S. Parihar Er.S.K.GUPTA

    (Civil Engg)

  • 7/25/2019 civil project report

    3/96

    3

    RAJIV GANDHI PROUDYOGIKI VISHWAVIDYALAYA, BHOPAL(M.P)Aditya College of Technology & Science

    Satna (M.P)

    CERTIFICATE

    This is to certify that the Project entitled as national

    HIGHWAY CONSTRUCTIONS which has been completed &

    submitted by CHANDRADEEP SHUKLA , ABHINAV JAISWAL, AMAR DEEP

    GAUTAM , PRAKASH NARAYAN MISHRA , PAWAN GAUTAM in partial

    fulfillment of the requirement for the award of the degree of Bachelor

    of Engineering in CIVIL ENGINEERING for the session 2009-

    2013.

    (External Examiner) (Internal Examiner)

  • 7/25/2019 civil project report

    4/96

    4

    ACKNOWLEDGEMENT

    A Project report like this one involves many people and would be

    incomplete without the mention of all those people whose guidance and

    encouragement helped in the successful completion of this report.

    Our heartily thanks to all faculty members of Department of

    CIVIL ENGINEERING ,Aditya College of Technology Science,

    Satna for their effort towards our report.

    I would like to thanks our H.O.DER. S.K. GUPTAwho has been

    a great source of inspiration for us and without whose humble guidance

    the report was never to shape.

    I am also thankful to many people whose timely help but paucity

    of space is restricting us from mentioning their name. And finally we also

    thank to all my colleagues who were constant support during the whole

    report.

    CHANDRADEEP SHUKLA 0307CE091017)

    ABHINAV JAISWAL 0307CE091001)

    AMAR DEEP GAUTAM 0307CE091006)

    PRAKASH NARAYAN MISHRA 0307CE091030)

    PAWAN GAUTAM 0307CE091029)

  • 7/25/2019 civil project report

    5/96

    5

    DECLARATION

    We hereby declare that the work which is being presented in the

    Training report entitled national HIGHWAY

    CONSTRUCTIONSin partial fulfillment of the requirement of the

    degree of Bachelor of Engineering in CIVIL ENGINEERING

    branch is an authentic record of our work carried out under the

    guidance of ER. S.K.GUPTA . The work has been carried out at

    Aditya College of Technology Science, Satna.

    CHANDRADEEP SHUKLA 0307CE091017)

    ABHINAV JAISWAL 0307CE091001)

    AMAR DEEP GAUTAM 0307CE091006)

    PRAKASH NARAYAN MISHRA 0307CE091030)

    PAWAN GAUTAM 0307CE091029)

  • 7/25/2019 civil project report

    6/96

    6

    INTRODUCTION

  • 7/25/2019 civil project report

    7/96

    7

    In a National Highway project, the engineer has to

    plan, design and construct either a network of new

    roads or road link.

    Once a highway is constructed, development takes along the

    adjoining land and subsequent changes in alignment in geometric

    standards become very difficult. A badly aligned highway is not

    only a source of potential traffic hazard, but also causes a

    considerable increase in transportation cost and strain on the

    drivers and the passengers. Therefore, proper investigation and

    planning are most important in a road project, keeping in view

    the present day needs as well as the future development of the

    region

  • 7/25/2019 civil project report

    8/96

    8

    NATIONAL HIGHWAY

    PROJECT

    DEFINITIONS

  • 7/25/2019 civil project report

    9/96

    9

    In the contract the following words and expressions shall

    have the meanings here by assigned to them, except

    where the context otherwise requires:

    i) A BOLLARD is a short vertical post typically found

    where large ships docks. While originally it only meant a

    post used on a quick for mooring, the word now also

    describes a variety of structure to control or direct road

    traffic. The term may be related to bole, meaning the

    lower trunk of a tree.

  • 7/25/2019 civil project report

    10/96

    10

    ii) A BYEPASS is a road or highway that avoids or

    bypasses a built up area, town, or village, to let

    through traffic flow without interference from local

    traffic, to reduce congestion in the built up area, and to

    improve road safety.

    If there are no strong land use controls, buildings are

    built a bypass, converting it into an ordinary town road,

    and the bypass may eventually become as congested as

    the local streets it was intended to avoid.

    iii) A CURB or KERB is the edge where a raised

    pavement/footpath, road median, or road shoulder meets

    an unraised street or other roadway. Typically made from

    concrete, asphalt, or long stones, the purpose is twofold:

    first as a gutter for proper drainage of the roadway, and

  • 7/25/2019 civil project report

    11/96

    11

    second for safety, to keep motorist from driving into the

    shoulder, median, sidewalk, or pavement.

    iv) EMPLOYERS means the person named as such in

    part II of these conditions and the legal successors in

    title to such person. But not any assignee of such

    person.

    V) CONTRACTOR means the person whose tender has

    been accepted by the employer and the legal successors in

    title to such person. But not any assignee of such

    person.

    Contractmeans the conditions, the specification,

    the drawings, the bill of quantity, the tender, the

    letter of acceptance; the contract agreement and

    such further documents as may be expressly

  • 7/25/2019 civil project report

    12/96

    12

    incorporated in Letter of Acceptance or Contract

    Agreement.

    Specifications means the specification of the work

    included in the contract and any modification

    therefore or addition.

    Drawings means all drawings, calculations and

    technical information of a like nature provided by

    the Engineer to the contractor under the contract

    and all drawings, Calculations, Samples, Pattern,

    Models, Operations and maintenance, manuals and

    other technical information of a like nature

    submitted by the contractor and approved by the

    Engineer.

    Bill of Quantities means the priced and completed

    bill of quantities forming part of tender.

  • 7/25/2019 civil project report

    13/96

    13

    Section means a part of the works specifically

    identified in the Contract as a section.

    Site means the places provided by the Employer

    where the works are to be executed and any other

    places as may be specifically designated in the

    Contract as forming part of the site.

  • 7/25/2019 civil project report

    14/96

    14

    SETTING OUT

  • 7/25/2019 civil project report

    15/96

    15

    The contractor shall establish working Bench marks tied

    with the reference Bench Mark in the soon after taking

    possession of the site. The reference Bench Mark for the

    area shall be as indicated in the contract document of

    the values of the same shall be obtained by the

    Contractor from the Engineer. The working bench mark

    shall be at rate of 4 per km and also at or near all

    drainage structures, over bridges and under passes. The

    working Bench Mark/levels should be got approved from

    the Engineer. Check must be based on this Bench Mark

    once every month and adjustments, if any, got agreed

  • 7/25/2019 civil project report

    16/96

    16

    with the Engineer and recorded. An up-to-date record of

    all Bench Mark including approved adjustments, if any,

    shall be maintained by the contractor and also a copy

    supplied to the Engineer for his record.

    The lines and levels of formation, side slopes, drainage

    works, carriageways and shoulders shall be carefully set

    out and frequently checked, care being taken to ensure

    that correct gradients and cross sections are obtained

    everywhere.

    In order to facilitate the setting out of the works, the

    centreline of the highway must be accurately established

    by the contractor and approved by the engineer. It must

    then be accurately referenced in a manner satisfactory to

    the engineer, every 50m intervals in plain and rolling

    terrains and 20m intervals in highly terrain and in all

    curve point as directed by the engineer, with marker pegs

  • 7/25/2019 civil project report

    17/96

    17

    and chainage boards sets in or near the fence line, and

    schedule of reference dimensions shall be prepared and

    supplied by the Contractor to the Engineer. These

    markers shall be maintained until the works reach finished

    formation levels are accepted by the Engineer.

    On construction reaching the formation level stage, the

    centre line again be set out by the contractor and when

    approved by the Engineer, shall be accurately referenced

    in a manner satisfactory to the Engineer by markers pegs

    set at the outer limits of the formation.

    No marker pegs or markers shall be moved without the

    approval of the Engineer and and no earth work shall be

    commenced until the centre line has been referenced.

    The contractor will be the sole responsible party for

    safeguarding all survey monuments, bench marks, etc. The

    Engineer will provide the Contractor necessary for setting

  • 7/25/2019 civil project report

    18/96

    18

    out of the centre line. All dimensions and levels shown on

    the drawing or mentioned in documents forming part of

    the or issued under the contract shall be verified by the

    Contractor on the site and he shall immediately inform

    the engineer of any apparent error in such dimensions.

    The Contractor shall in connection with the staking out

    of the canter line, survey the terrain along the road and

    shall submit the engineer for his approval, a profile along

    the road centre line and cross section at intervals as

    required by the Engineer.

    After obtaining approval of the engineer, work on

    earthwork can commence and the profile and cross section

    shall from the basis for measurements and payments.

    The work of setting out shall be deemed to be a part of

    general works preparatory to the execution of work and

    no separate payments shall be made for the same..

  • 7/25/2019 civil project report

    19/96

    19

  • 7/25/2019 civil project report

    20/96

    20

    TEST DONE IN

    PROJECT

    LABORATORY

    TEST ON SUB GRADE SOIL

    (I)

    GRAIN SIZE ANALYSIS

    INTRODUCTION:

  • 7/25/2019 civil project report

    21/96

    21

    Most of the method for the soil identification and

    classification are based on certain physical properties of

    the soil. The commonly used properties for the

    classification are the grain size distribution liquid limit

    and plasticity index. These properties have also been used

    in empirical design method for flexible pavement; and in

    deciding the suitable of sub grad soil.

    Grain size analysis also known as mechanical analysis of

    soil is the determination of the percent of individual

    grain size present in the sample. The results of the test

    are of great value in soil classification. In mechanical

    stabilization of soil and for designing soil aggregates

    mixture the result of gradation test are used .correlation

    have also made between the grain size distribution of soil

    and the general soil behavior as the sub grade material

    and the performance such as susceptibility to frost

  • 7/25/2019 civil project report

    22/96

    22

    action, pumping of rigid pavement etc.also permeability

    characteristics, bearing capacity and some other

    properties, are approximately estimated based on grain

    size distribution of the soil. The soil is generally divided

    into four parts on the particle size. The fraction of the

    soil which is larger than 2.00 mm size is called gravel,

    between 2.00 mm and 0.06 mm is sand 0.002mm silt

    and that is smaller than 0.002 mm size is clay. Two

    type of sieves are available, one type with square

    perforation on plate to sieves course aggregate and

    gravel, the other type being mesh sieves made of woven

    wire mesh to sieves finer particle such fine aggregate and

    soil fraction consisting of sand silt and clay. However the

    sieves opening of the smallest mesh sieves commonly

    available is about 0.075 mm, which is commonly known

    as 200 mesh sieves therefore all soil particle consisting of

    silt and clay which are smaller than 0.06 mm size will

  • 7/25/2019 civil project report

    23/96

    23

    pass through the fine mesh sieves with 0.075 mm

    opening. Therefore the grain size analysis of course

    fraction of soil is carried out using sieves the principle of

    sedimentation in water.

    The sieves analysis is a simple test consisting of sieving a

    measured quantity of material through successively

    smaller sieves. The weight retain on each sieves. The

    weight retain on each sieve is expressed as a percentage

    of the total sample. The sediment principle has been used

    for finding the grain size distribution of fine fraction;

    two methods are commonly used pipette method and the

    hydrometer method.

    The grain size distribution of soil particle of size greater

    than 63 micron is determine by sieving the soil on set

    of sieves of decreasing sieve opening placed one below the

    other and separating out the different size ranges.

  • 7/25/2019 civil project report

    24/96

    24

    APPARATUS:

    Various apparatus set of standard sieves of different

    sieves size, balance, and rubber covered pestle mortar,

    oven, riffle, sieves shaker.

    Procedure

    For the fraction retained on 2.0 mm sieves.

    Sufficient quantity of dry soil retained on 2.0 mm

    sieves is weighed out. The quantity of sample taken

    may be increased when the maximum size of particle

    is higher. The sample separated into various fraction

    by sieving through the set of sieves of size100, 63,

    20, 6, 4.75, and 2 mm is sieves. After initial

    sieves, material retained on each sieves carefully

    collected and weighed.

    For fraction passing 2.0 mm sieves and retained on

    0.63 mm size.

  • 7/25/2019 civil project report

    25/96

    25

    The required quantity of soil sample is taken by

    riffling or quartering method, dried in oven at 105

    to 110 c and is subjected to dry sieves analysis using

    a set of sieves with sieves opening 2.0, 0.6, 0.425,

    0.15, and 0.075 mm, pan lid. The material collected

    on the each sieves and on the pan are separately

    collected and weighed.

    CALCULATION:

    The weight of dry soil fraction retained on each sieve is

    calculated as a percentage of the total dry weight of the

    sample taken. The gravel, sand , silt ,and clay contain in

    percentage.

    RESULT:

  • 7/25/2019 civil project report

    26/96

    26

    The gravel, silt sand clay contents are marked as result.

  • 7/25/2019 civil project report

    27/96

    27

    (II) CONSISTENCY LIMITS &

    INDICES

    The physical properties of fine grained soil, especially of

    clay differ much at different water content. Clay may be

    almost in liquid state, or it may snow plastic behavior or

    may be very stiff depending on the moisture content.

    Plasticity is a property of outstanding importance for

    clayey soil, which may be explained as the ability to

    undergo changes in shape without rupture.

  • 7/25/2019 civil project report

    28/96

    28

    Liquid limit it may be defined as the minimum content

    at which soil will flow under the application of a very

    small shearing force. The liquid limit is usually determined

    in the laboratory using mechanical device.

    Plastic limit may define in general term, as minimum

    terms, as minimum moisture content at which the soil

    remain in a plastic state. The lower limit is arbitrarily

    defined and determined in the laboratory by prescribed

    test procedure.

    Plastic index is defined as the numerical difference

    between the liquid and plastic limit.

    p.i thus indicates the range of moisture content over

    which the soil in plastic condition.

  • 7/25/2019 civil project report

    29/96

    29

    Consistency limit and plasticity index vary for different

    type. Hence properties are generally used in the

    identification and classification of soil

    LIQUID LIMIT TEST:

    Liquid limit is the moisture content at which 25 blow in

    standard liquid limit apparatus will just close a groove of

    standardized dimension cut in the sample by grooving tool

    by a specified amount.

    APPARATUS:

    Mechanical liquid limit device consists of a cup and

    arrangement for raising and dropping through a specified

    height, grooving tool. Other apparatus include spatula,

    moisture containers, and balance of capacity 200g

    sensitive to0.01 g oven to maintain 105 to110c.

  • 7/25/2019 civil project report

    30/96

    30

    PROCEDURE:

    About 120 g of dry pulverized soil sample passing 425

    micron sieve is weighted, and mixed thoroughly with

    distilled water in the evaporating dish to from a uniform

    thick paste. The liquid limit device is adjusted to have a

    free fall of cup through 10mm.a portion of the paste is

    placed above the lowest spot, and squeezed down with

    the spatula to have a horizontal surface . the specimen is

    trimmed by firm strokes of spatula in a such a way that

    the maximum depth of soil sample in the cup is 10 mm.

    the soil in the cup is divided along the diameter through

    the center line pf the cam followed by firm strokes of

    the grooving tool. So as to get a clean and sharp groove.

    The crank is rotated at the rated at the rate of two

    revolutions per second by hand so that the cup is lifted

    and dropped. This continued till the two halves of the

  • 7/25/2019 civil project report

    31/96

    31

    soil cake come in to contact at the bottom of the

    groove along a distance of 10 mm, and the number of

    blows given is recorded . a representative soil is taken,

    placed in moisture container, lid placed over it and

    weighed. The container in dried in oven and the dry

    weight determined the next day for finding the moisture

    content of the soil. The operations are repeated for at

    least three more trial with slightly increased moisture

    content each time, nothing the number of blows so that

    there at least four uniformly distribute reading of

    number of blows between 10 and 40 blows.

    CALCULATION:

    the flow index The flow cure is plotted by taking the

    number of blows in the log scale on the x-axis, and the

    water content in arithmetic scale on the y-axis, of

    format sheet .the flow curve is straight line drawn on

  • 7/25/2019 civil project report

    32/96

    32

    semi-logrithmetic plot. The moisture content

    corresponding to 25 blow is read from this curve

    rounding off the nearest whole number and is reported as

    the liquid w1 of the soil. The slope of the straight line

    flow cure is flow index. It may be calculated from the

    following formula;

    For index, If=

    =

    =w

    Hence if the flow curve is extrapolated and moisture

    w10 and w100 corresponding to 10and 100 blows

    respectively are found, then the difference in these

    water content would give of the soil.

  • 7/25/2019 civil project report

    33/96

    33

    PLASTIC LIMIT TEST

    Plastic limit is the moisture content at which a soil when

    rolled in to thread of smallest diameter possible, start

    crumbling and has diameter of 3 mm.

    APPARATUS:

    Evaporating dish, spatula, glass plate, moisture

    containers, rod of 3 mm diameter , balance sensitive to

    0.01 g, drying oven controlled at temperature 105

    to110c.

  • 7/25/2019 civil project report

    34/96

    34

    PROCEDURE:

    About 20 g of dry, pulverized soil passing 425 micron IS

    sieve is weighed out. The soil is mixed thoroughly with

    distilled water in the evaporating dish till the soil paste

    is plastic enough to be easily molded with fingers. A small

    ball is formed glass plate to a thread. The pressure just

    sufficient to roll into a thread of uniform diameter

    should be used. The rate of rolling should be between 80

    and 90 strokes per minute counting a stroke as one

    complete motion of hand forward and back to starting

    position again. The rolling is done till the diameterof thread is 3

    mm . then the soil is kneaded together to a ball and

    roller again to from therad this process of alternate

    rolling and kneading is continude untill the thread. This

    process of alternate rolling and kneading is continude until

  • 7/25/2019 civil project report

    35/96

    35

    th ethread crumbles under prassure required for rolling

    and the soil can no longer to roll into a thread.

    If the crumbling start at diameter less than 3 mm, then

    moisture content is more than the plastic limit and if

    the diameter is greater while crumbling starts, the

    moisture content is lower.

    CALCULATION:

    The plastic limit (w0) is expressed as a whole number by

    obtaining the mean of the moisture content of the

    plastic limit.

    Plastic index is calculated as the diffrence between liquid

    limit and plastic limit.

    Plastic index = liquid limit plastic limit

    W1-wp

  • 7/25/2019 civil project report

    36/96

    36

    (III)

    COMPACTION TEST

  • 7/25/2019 civil project report

    37/96

    37

    Compaction of soil is a mechanical process by which by

    which the soil partical are constrained to be packed more

    closley together by reducing the air void. Soil compaction

    causes decreases ia air void and consequently an increase

    in dry density. This may result in increase in shearing

    strength., the possible of future settelment or

    compressibility decrease. Degree of compaction is usually

    measured quantitativily nby dry density.

    APPARATUS:

    (a)

    Cylindrical mould of capacity 1000 cc. with an

    internal diameter of 10 cm and height 12.73 cm. the

    mould is fitted with a detachable base plate and

    removable collar extension of about 6 cm hight.

  • 7/25/2019 civil project report

    38/96

    38

    (b) For the light compaction, a metal rammer having 5

    cmdiameter circular face, and weight 2.6 kg is used

    which has drop oif 31 cm.

    For heavy compaction, the rammer has 5 cm diameter

    circular face, but havin g weight 4.89 kh free

    drop of 45 cm.

    (c) Steel straight edge having behaving beveled edge for

    trimming top of the specimen.

    (d)

    Other accessories include moisture container, balance

    of capacity 10kg and 200kg, oven, sieves, mixing tools.

    PROCEDURE:

    In case of soil sample has particle bigger than 4075 mm

    sieve, about 20 kg of the representstive soil is air dried,

    mixed pulerized and sieved through 20 mm and 4.75 m

    sieve is not use in the test the percentage passing 20

    mm sieve and retained on 4075 mm sieve is noted and if

  • 7/25/2019 civil project report

    39/96

    39

    this is less than 20 percen this sample is used as such.

    It is more than this phenomenon is repeated. In case the

    sample passes 4075 sieves, than the bdry pulverized

    sample is sieved through 4.75 mm sieve and the portion

    passing this sievesis only used for the test. About 16 kg

    of dry soil in total may be neccessery for the compaction

    test in the 1000 cc mould. For compaction the soil in

    the mould every time the required quantity quantity will

    depend on the soil type, size of mould, moisture content

    and amount of compaction. As arough guidance, for each

    test 2.5 kg of soil may taken for light compaction. As

    arough guidance, for each test 2.8 kg for heavy

    compaction, and than the required water ia added. The

    estimated weight to be added to the soil every time may

    be measured in in a jet graduated in cc. enough water is

    added to to the specimen to bearing the moisture

    content to about 7% less than the estimated o.m.c. for

  • 7/25/2019 civil project report

    40/96

    40

    sandy soil and 10% less for clay soils. The processed soil

    stored in an air tight container for about 10 to 20

    enable moisture to spread uniform in the soil mass.

    The mould with base fitted in is weighed. The process

    soil water mixture throughly and divided into eight equal

    part.

    (1) For light compaction the wet soil is compacted

    into the mould in three equal layers, each layer being

    25 blow of the 2.6kg rammer.

    (2) For heavy compaction the wet soil mix is

    compacted in the mould in five equal layer being 25

    bloq of 4.89 kg hammer.

    The blow should be uniform ly disributed over the surface

    of each layer. Each layer of the compacted soil is scored

    with a spatula before placing the soil for the succeeding.

    The amount of the soil used should be just sufficient to

  • 7/25/2019 civil project report

    41/96

    41

    fill the mould leaving about 5 mm to strike off on the

    top after compacting the final layer.

    The coller is removed and the compacted soil is leveled to

    th top of the mould by mean of straight edge. The

    mould and the soil are then weighed. The soil is then

    ejected out of the mould and cut in the middle and a

    representative specimen is determine by finding the wet

    weight, keeping in the oven at 105c to 110c and finding

    the dry weight the next day.

    CALCULATION:

    Let weight of mould copacted soil be = W1 g

    Weight of empty mould =W2 g

    Volume of mould = W

    Wet density =

    g/cc

  • 7/25/2019 civil project report

    42/96

    42

    Then dry density =

    ()

    RESULT:

    The result are dry density and wet density.

  • 7/25/2019 civil project report

    43/96

    43

    CALIFORNIA BEARING

    RATIO TEST

    INTRODUCTION:

    The California bearing ratio (CBR) test was developed by

    the California division of highway as a method of

    classification and evaluating soil-subgrade and base course

    material for flexible pavements. Just after world war-2,

    the U.S.Crops of engineers adopted the C.B.R. test for

    use in designing base course for air field pavement. The

    test is empirical and result can not be related accurately

    with any fundamental property of the material. The CBR

  • 7/25/2019 civil project report

    44/96

    44

    is a measure of resistance of a material to penetration of

    a standard plunger under controlled density and moisture

    conditions. The test procedure should be strictly adhered

    if high degree of reproducibility is desired. The CBR test

    may be conducted in remould or undisturbed specimen in

    the laboratory. U.S. crops of engineers have also

    recommended a test procedure for in-situ test. Many

    methods exist today which utilize mainly CBR test value

    for designing pavement structures. The test is simple and

    has been extensive investigated for field correlation of

    flexible pavement thickness requirement briefly, the test

    consist of causing a cylindrical plunger of diameter 50

    mm to penetrate component material at 1.25

    mm/minute. The loads, for 2.5 mm and 5.0 mm are

    recorded. This load is expressed as a percentage of

    standard load value at a respective deformation level to

    obtain CBR value.

  • 7/25/2019 civil project report

    45/96

    45

    APPARATUS:

    Loading machine: Any compression machine which can

    operate at a constant rate of 1.25 mm/minute can be

    used for this purpose. If such machine is not available

    then a calibrate hydraulic press with proving ring to

    measure load can be used. A metal penetration piston or

    plunger of a diameter 50 mm is attached to the loading

    machine.

    Cylindrical moulds: Mould of 150 mm diameter and 175

    mm height provided with a collar of about 50 mm

    length and detachable perforated andbase are used for

    this purpose. A spacer disc of 148 mm diameter and

    47.7 mm thickness is used to obtain a exactly 127.3

    mm height

  • 7/25/2019 civil project report

    46/96

    46

    Compaction rammer: The material is usually compacted

    as specified for the work, either by dynamic

    compaction or ISI are given in table bellow:-

    TYPE OF

    COMPACTION

    NUMBER

    OF

    LAYERS

    WEIGHT

    OF

    HAMMER,

    Kg

    FALL,

    cm

    NUMBER

    OF

    BLOWS

    Light

    compaction

    3 2.6 31 56

    Heavy

    compaction

    5 4.89 45 56

    Adjustable stem, perforated plate, tripod and dial

    gauge: the standard procedure require that the soil

    sample before testing should be soaked in water to

    measure swelling.

    Annular weight: in order to stimulate the effect of

    the overlying pavement weight, annular weight each of

    2.5 kg and 147 mm diameter are placed on the top of

  • 7/25/2019 civil project report

    47/96

    47

    the specimen, both at the time of soaking and testing

    the sample, as surcharge.

    Beside above equipment, coarse filte r paper, sieves,

    oven, balance, etc. Required

  • 7/25/2019 civil project report

    48/96

    48

    TEST ON

    CEMENT

  • 7/25/2019 civil project report

    49/96

    49

    (1) FINENESS TEST:

    INTRODUCTION:

    The object of this is to check the proper grinding of

    cement. The rate of hydration depends on the fineness

    of cement. The finer is the cement, the earlier the

    hydration and the faster and greater is the gaining of

    strength. This because of hydration starts at the surface.

    Larger the surface area (i.e. finer the cement), faster

    will be hydration. However, very fine cement is

    susceptible to air set and deteriorates earlier. The

    grinding of cement shall be as fine as to conform to the

    standard specification and also shall be uniformly fine .If

    the cement is not uniformly fine, the concrete made out

    of it will have poor workability and will require a large

    quantity of water while mixing. Also bleeding of concrete

  • 7/25/2019 civil project report

    50/96

    50

    can occur i.e. even before the concrete is set , water will

    come out of the surface due to the settlement of

    concrete particle. To check the fineness of the cement

    IS: 4031-1998 gives three methods:

    By drying sieving.

    1.

    Blaine air permeability method.

    2.

    By wet sieving.

    First method is used to find the fineness of cement in

    the project laboratory.

    DRY SIEVING METHOD:

    The fineness of the cement depends on the particle size

    distribution. A small mass of fine cement may have

    surface area have large surface area than a large mass of

  • 7/25/2019 civil project report

    51/96

    51

    coarser particle of cement. It is therefore necessary to

    reduce the percentage of coarse particles to get require

    fineness of cement .In this test mass of coarser cement

    particle is found out which is limited to specified

    percentage for various cements as per respective Indian

    standard. Take 100g of various cements from samples and

    breakdown any air set lumps with finger. Place it on a

    standard IS sieve no.9. Continuously sieve the sample

    with a gentle wrist motion for 15 minutes. The mass of

    residue shall not exceed 10g in case of ordinary Portland

    cement and 5g in case of rapid hardening cement.

    CALCULATION AND RESULT:

    The weight of cement retained is divided by weight taken

    and is multiplied by 100 so the percentage retained

    cement on 90 micron sieve is calculated. Three trials are

  • 7/25/2019 civil project report

    52/96

    52

    done and the average of percentage.

    Cement retained is calculated. The average

    percentage of cement retained should not be more than

    the specified limit.

  • 7/25/2019 civil project report

    53/96

    53

    (II) TEST FOR

    CONSISTENCY, INITIAL &

    FINAL SETTING TIME OF

    CEMENT

    CONSISTENCY OF CEMENT

    PASTE:

    INTRODUCTION:

    This test determines the quantity of water required to

  • 7/25/2019 civil project report

    54/96

    54

    produce a cement paste of standard consistency for the

    use of other test. The vicat apparatus is used for this

    purpose. The consistency of standard cement paste is

    defined as that consistency which will permit the vicat

    plunger 50mm long and having 10mm diameter to

    penetrate to a point 5mm to 7mm from the bottom of

    the vicat mould. The unit of the consistency is

    percentage of water by mass of dry cement and denoted

    by P.

    PROCEDURE:

    Take 400g cement and add to it 30% water on a glass

    plate or any non porous surface. Mix thoroughly and fill

  • 7/25/2019 civil project report

    55/96

    55

    the mould of vicat apparatus. The interval from the time

    of adding water to the dry cement until commencing to

    fill the mould is known as the time of gauging and must

    be not less than 3 minutes and not more than 5

    minutes. Lower plunger gently to touch the surface of

    test block and quickly release it, allowing it to sink into

    the paste. Note the settlement of the plunger. The

    settlement of the plunger should be 5mm to 7 mm from

    the bottom of the mould. If not, repeat the procedure

    using fresh cement and other percentage of water until

    the described penetration of theplunger is obtained.

    The consistency of standard cement paste is expressed

    as the amount of water as percentage by mass of dry

    cement.

  • 7/25/2019 civil project report

    56/96

    56

    Let, m1= mass of cement taken

    m2= mass of water added when the plunger

    has a penetration of 5mm to

    . 7mm from the bottom of the

    mould.

    Then the percentage of water or standard

    consistency is

    P = (m2/m1)x100

    Usually standard consistency P lies between 26 to

    33 percent.

  • 7/25/2019 civil project report

    57/96

    57

    TEST FOR SETTING

    TIMES

  • 7/25/2019 civil project report

    58/96

    58

    INTRODUCTION:

    The change of the cement paste from fluid to rigid state

    may be referred to as setting. The gaining of strength of

    a cement of a set cement paste is known as hardening.

    During the setting, cement acquires some strength,

    however it is not considered in definition to distinguished

    setting from hardening, where hardening is gain of

    strength of a set cement paste.

    Objects of these tests are:-

  • 7/25/2019 civil project report

    59/96

    59

    1.

    To find initial and final setting times of cement.

    2.

    To distinguished between quick setting and normal

    setting types of cement

    3.

    To detect deterioration due to storage.

    When water is added to cement and mixed properly. The

    chemical reaction soon starts and the paste of cement

    remains plastic for a short period. During this period, it

    is possible to remix the paste for a short period. During

    this period, it is possible to remix the paste. This period

    is called initial setting time. It is assumed that no

    hardening will starts in this period .As time lapses, the

    reaction is continued and cement begins to harden. At

    some stages it gardens also called finally set and the

    time elapsed since the water was added is called final

    setting time. It is not possible to express the exact

    state of hardening and hence empirical measurements are

  • 7/25/2019 civil project report

    60/96

    60

    taken.

    This is purely a conventional one and does not relate to

    the setting and hardening of actual concrete.

    PROCEDURE:

    Mix 400g of cement with 0.85 P percentage of water

    where P is the consistency of standard cement paste.

    Start the stop watch at the instant when water is

    added to cement. Fill the vicat mould with this paste

    and smooth of the surface of the paste making it level

    with the top of the mould attach 1mm* 1mm square

    cross section needle to the vicat rod. Lower the needle

    gently near the surface of the block. Note whether the

    needle pierces completely .If so, wait for a while drop

  • 7/25/2019 civil project report

    61/96

    61

    the needle at a fresh place. Repeat the procedure till

    the needle fails to pierce the block for 5+ 0.5mm

    measured from the bottom of the mould. The interval

    between the time when water was added to cement and

    the time at which the needle fails to pierce the block by

    5 + 0.5mm is known as initial setting time.

    Replace the needle by the needle which has a sharp

    pointing, projecting in the centre with a annular

    attachment and release it on the same test block as

    before. Note the time when needle makes an impression,

    but the attachment fails to do so. The interval between

    these time and the time when water was added is known

    as the final setting time.

  • 7/25/2019 civil project report

    62/96

    62

    The initial setting time for a ordinary Portland cement

    should not be less than 30 minutes and the final setting

    time should not more than 10 hours. For quick setting

    cement, the initial setting time should not be less than

    5 minutes and the final setting not more than 30

    minutes.

    The minimum limits on initial setting are specified

    because:

    Concrete once placed should not be distributed after the

    initial setting has taken place.

    There must be sufficient time for placing of second batch

    which may be distribute the first batch of the concrete.

    The transportation of concrete from the place where

    concrete is prepared to the placing of concrete requires

    some finite time.

  • 7/25/2019 civil project report

    63/96

    63

    The maximum limits of the final setting time are

    specified because the concrete should achieve the desired

    strength as early as possible so that the shuttering can

    be remove and reused.

    (I) AGGREGATES IMPACT TEST

    INTRODUCTION:

    Toughness is the property of the materials to resist

    impact. Due to traffic loads, the load stones are

    subjected to the pounding action or impacts and there

    possibility of stones breaking into smaller pieces. The road

    stones should therefore be tough enough to resist

    fracture under impact. A test designed to evaluate the

  • 7/25/2019 civil project report

    64/96

    64

    toughness of the stones therefore the resistance of the

    two fractures under repeated impacts may be called an

    impact test for road stones. Impact test may either

    carry out cylindrical stone specimens as in page impact

    test or stone aggregates as in a aggregate impact test.

    The aggregate test has been standardized by the British

    Standard Institution and the Indian Standard Institution.

    The aggregate impact value indicates the a relative

    measure of the resistant of aggregate to sudden shock or

    an impact, which in some aggregate differ from its

    resistant to slow compressive load. The method of test

    covers the procedure for determine the aggregate impact

    value of coarse aggregates.

    APPARATUS:

    The apparatus consists of an impact testing machine, a

  • 7/25/2019 civil project report

    65/96

    65

    cylindrical measure temping rod, IS sieve, balance and

    oven.

    Impact Testing Machine: The machine consist of

    a matter base with a plane lower surface supported

    well on a firm flour, without rocking detachable

    cylindrical steel cup of internal diameter 10.2cm and

    depth 5.0cm is rigidly fastened centrally to the base

    plate. A matter hammer of weight between 13.5 and

    14 kg having the lower and cylindrical in shape, 10cm

    in diameter and 5.0 cm long, with 2.0 mm chamber

    at the lower edge is capable of sliding freely between

    vertical guides, and fall concentric over the cup. There

    is an arrangement for raising the hammer and allowing

    it to fall freelybetween vertical guides from a height

    of 38 cm on the test sample in the cup, the height

  • 7/25/2019 civil project report

    66/96

    66

    fall being adjustable up to 0.5 cm a key is provided

    for supporting the hammer while fastening.

    Measure: A cylindrical metal measure having internal

    diameter 7.5 cm and depth 5.0 cm for measuring

    aggregates.

    Tamping rod:A straight metal tamping rod of

    circular cross section, 1.0 cm in diameter and 23 m

    long, rounded at one end.

    Sieve:IS sieve of size 12.5mm, 10mm and

    2.36mm for sieving the aggregates.

    Balance: A balance of capacity not less than 500g

    to weight accurate up to 0.1g.

  • 7/25/2019 civil project report

    67/96

    67

    Oven: A thermostatically controlled drying oven

    capable of maintaining constant temperature between

    100oC and 110oC.

    PROCEDURE:

    The test sample consist of aggregates passing 12.5mm

    sieves and retained on 10mm sieve and dried in an oven 4

    hours at a temperature 100oC to 110oC and cooled. The

    aggregates are filled up to about one third full in the

    cylindrical measure and tamped 25 times with rounded

    and of the tampering rod. Further quantity of aggregates

    is then added up to about two third full in the

    cylinder and 25 strokes of the tamping rod are given.

    The measure is now filled with the aggregates to over

    flow, tamped 25 times. The surplus aggregates are stuck

    off using the tamping rod as straight edge. The net

  • 7/25/2019 civil project report

    68/96

    68

    weight of the aggregates in the measures determined to

    the nearest gram this weight of the aggregates is used

    for carrying out duplicate test on the same materials.

    The impact machine is placed with its bottom plate on

    the flour so that the hammer guide columns are vertical.

    The cup is mixed firmly in position on the base of the

    test sample from the cylindrical measure is transferred to

    the cup and compacted by tamping with 25 strokes.

    The hammer is raised until its lower face is 38 cm above

    the upper surface of the aggregates in the cup ,and

    allowed to fall freely on the aggregates. The test sample

    is subjected to a total 15 such blows, each being delivered

    at an interval of not less than one second. The crushed

    aggregates is then removed from the cup and whole of it

    sieve on the 2.36mm sieve until no further significant

    amount passes. The fraction passing the sieve is also

  • 7/25/2019 civil project report

    69/96

    69

    weighed accurate to 0.1gm.The fraction retained on the

    sieve is also weighed and if the total weight of the

    fraction passing and retained on the sieve is added, it

    should not be less than the original by 1g, the result

    should be discarded and a fresh test made

    METHODOLOGY OF PQC.

    SCOPE:

    The work shall consist of construction of un-reinforced,

    dowel jointed plain cement concrete pavements in

    accordance with the requirements of MOST specification

    and in conformity with the lines grades and cross sections

    as shown on the approved drawings. The work shall

    include furnishing of all plant and equipment, materials

    and labour as directed by the Engineer.

    MATERIALS:

    CEMENT:

  • 7/25/2019 civil project report

    70/96

    70

    Ordinary part land cement 43 grade confirming IS: 8112.

    ADMIXTURES:

    Admixtures used conforming to IS: 9625 and IS: 9103.

    COARSE AGGREGATE

    The maximum size of aggregate is 20 mm. the coarse

    aggregate complying with IS: 383

    FINE AGGREGATE:

    As approved in mix design confirm to IS: 383.

    WATER:

    It shall meet the requirement as stipulated in IS: 456.

  • 7/25/2019 civil project report

    71/96

    71

  • 7/25/2019 civil project report

    72/96

    72

    Bitumen testing

    Bitumen is a mixture of organic liquids that is black,

    highly viscous, sticky product used for paving roads,

  • 7/25/2019 civil project report

    73/96

    73

    waterproofing products (used in sealing roofs). There are

    many tests which are conducted to check the quality of

    bitumen. Bitumen is very important component of many

    construction sites like roads, highways. Many tests are

    done to ensure the quality of bitumen. Some of these are

    given below :-

    1 Bitumen Content

    2 Ductility Of Bitumen

    3 Penetration of Bitumen

    4 Specific Gravity of Bitumen

    5 Softening Point Of Bitumen

    6 Flash And Fire Point Of Bitumen

    7 The Marshall Stability of Bituminous Mixture

    This test is done to determine the bitumen content as

    per ASTM 2172. The apparatus needed to determine

    bitumen content are -

    http://www.engineeringcivil.com/determining-bitumen-content.htmlhttp://www.engineeringcivil.com/determining-the-ductility-of-bitumen.htmlhttp://www.engineeringcivil.com/determining-penetration-of-bitumen.htmlhttp://www.engineeringcivil.com/determining-specific-gravity-of-bitumen.htmlhttp://www.engineeringcivil.com/determining-softening-point-of-bitumen.htmlhttp://www.engineeringcivil.com/determining-flash-and-fire-point-of-bitumen.htmlhttp://www.engineeringcivil.com/determining-the-marshall-stability-of-bituminous-mixture.htmlhttp://www.engineeringcivil.com/determining-the-marshall-stability-of-bituminous-mixture.htmlhttp://www.engineeringcivil.com/determining-flash-and-fire-point-of-bitumen.htmlhttp://www.engineeringcivil.com/determining-softening-point-of-bitumen.htmlhttp://www.engineeringcivil.com/determining-specific-gravity-of-bitumen.htmlhttp://www.engineeringcivil.com/determining-penetration-of-bitumen.htmlhttp://www.engineeringcivil.com/determining-the-ductility-of-bitumen.htmlhttp://www.engineeringcivil.com/determining-bitumen-content.html
  • 7/25/2019 civil project report

    74/96

    74

    i) Centrifuge extractor

    ii) Miscellaneous bowl, filter paper, balance and

    commercial benzene.

    A sample of 500g is taken.

    Procedure to determine bitumen content

    i) If the mixture is not soft enough to separate with a

    trowel,place 1000g of it in a large pan and warm upto

    100oC to separate the particles of the mixture uniformly.

    ii) Place the sample (Weight A) in the centrifuge

    extractor. Cover the sample with benzene, put the filter

  • 7/25/2019 civil project report

    75/96

    75

    paper on it with the cover plate tightly fitted on the

    bowl.

    iii) Start the centrifuge extractor, revolving slowly and

    gradually increase the speed until the solvent ceases to

    flow from the outlet.

    iv) Allow the centrifuge extractor to stop. Add 200ml

    benzene and repeat the procedure.

    v) Repeat the procedure at least thrice, so that the

    extract is clear and not darker than the light straw colour

    and record the volume of total extract in the graduated

    vessel.

    vi) Remove the filter paper from the bowl and dry in the

    oven at 110 + 5o

    C. After 24hours, take the weight of

    the extracted sample (Weight B).

    REPORTING OF RESULTS

  • 7/25/2019 civil project report

    76/96

    76

    Bitumen content = [(A-B)/B]100 %

    Repeat the test thrice and average the results.

    Determining the Ductility Of Bitumen

    This test is done to determine the ductility of distillation

    residue of cutback bitumen, blown type bitumen and other

    bituminous products as per IS: 1208 1978. The principle

    is : The ductility of a bituminous material is measured by

    the distance in cm to which it will elongate before

    breaking when a standard briquette specimen of the

    material is pulled apart at a specified speed and a

    specified temperature.

    The apparatus required for this test:

    i) Standard mould

    ii) Water bath

    iii) Testing machine

    iv) Thermometer Range 0 to 44oC, Graduation 0.2oC

  • 7/25/2019 civil project report

    77/96

    77

    Procedure to determine the Ductility Of Bitumen

    i) Completely melt the bituminous material to be tested

    by heating it to a temperature of 75 to 100oC above the

    approximate softening point until it becomes thoroughly

    fluid. Assemble the mould on a brass plate and in order

    to prevent the material under test from sticking,

    thoroughly coat the surface of the plate and the interior

    surfaces of the sides of the mould with a mixture of

    equal parts of glycerine and dextrin. While filling, pour the

    material in a thin stream back and forth from end to end

    of the mould until it is more than level full. Leave it to

  • 7/25/2019 civil project report

    78/96

    78

    cool at room temperature for 30 to 40 minutes and

    then place it in a water bath maintained at the specified

    temperature for 30 minutes, after which cut off the

    excess bitumen by means of a hot, straight-edged putty

    knife or spatula, so that the mould is just level full. ii)

    Place the brass plate and mould with briquette specimen

    in the water bath and keep it at the specified

    temperature for about 85 to 95 minutes. Remove the

    briquette from the plate, detach the side pieces and the

    briquette immediately.

    iii) Attach the rings at each end of the two clips to the

    pins or hooks in the testing machine and pull the two

    clips apart horizontally at a uniform speed, as specified,

    until the briquette ruptures. Measure the distance in cm

    through which the clips have been pulled to produce

    rupture. While the test is being done, make sure that the

    water in the tank of the testing machine covers the

    specimen both above and below by at least 25mm and the

  • 7/25/2019 civil project report

    79/96

    79

    temperature is maintained continuously within 0.5oC of

    the specified temperature.

    REPORTING OF RESULTS

    A normal test is one in which the material between the

    two clips pulls out to a point or to a thread and rupture

    occurs where the cross-sectional area is minimum. Report

    the average of three normal tests as the ductility of the

    sample, provided the three determinations be within

    0.5 percent of their mean value.

    If the values of the three determinations do not lie

    within 0.5 percent of their mean, but the two higher

    values are within 0.5 percent of their mean, then

    record the mean of the two higher values as the test

    result.

  • 7/25/2019 civil project report

    80/96

    80

    Determining Penetration of Bitumen

    This test is done to determine the penetration of

    bitumen as per IS: 1203 1978. The principle is that

    the penetration of a bituminous material is the distance

    in tenths of a mm, that a standard needle would

    penetrate vertically, into a sample of the material under

    standard conditions of temperature, load and time. The

    apparatus needed to determine the penetration of

    bitumen is

    i) Penetrometer

    ii) Water bath

    iii) Bath thermometer Range 0 to 44oC, Graduation

    0.2oC

  • 7/25/2019 civil project report

    81/96

    81

    SAMPLE

    Bitumen should be just sufficient to fill the container to a

    depth of at least 15mm in excess of the expected

    penetration.

    Procedure to determine the penetration of bitumen

    i) Soften the bitumen above the softening point

    (between 75 and 100oC). Stir it thoroughly to remove

    air bubbles and water.

    ii) Pour it into a container to a depth of at least 15mm

    in excess of the expected penetration.

  • 7/25/2019 civil project report

    82/96

    82

    iii) Cool it at an atmospheric temperature of 15 to 30oC

    for 11/2hours. Then place it in a transfer dish in the

    water bath at 25.0 + 0.1oC for 11/2hrs.

    iv) Keep the container on the stand of the penetration

    apparatus.

    v) Adjust the needle to make contact with the surface of

    the sample.

    vi) Adjust the dial reading to zero.

    vii) With the help of the timer, release the needle for

    exactly 5 seconds.

    viii) Record the dial reading.

    ix) Repeat the above procedure thrice.

    REPORTING OF RESULTS

    The value of penetration reported should be the mean of

  • 7/25/2019 civil project report

    83/96

    83

    not less than three determinations expressed in tenths of

    a mm.

    MACHINERY USED IN

    CONSTRUCTION

  • 7/25/2019 civil project report

    84/96

    84

    LIST OF PLANT & MACHINERY

    DEVELOPED AT SITE:

    WM M M ixing plant

    Tailor

    Stone Crusher unit 100TPH

    Tipper 6/8)

    GSB Crusher unit 100 TPH

    Tipper 14cum)

    Weight Bridge

    Tractor

    Concrete Batching Plant

  • 7/25/2019 civil project report

    85/96

    85

    Plate Compactor

    Transit Mixer

    Concrete Mixer

    Motor Grader

    Generator set 250KVA

    Front end loader

    Generator set 180KVA

    Generator set 125KVA

    Generator set 100KVA

    Generator set 22KVA

    Generator set 17.5KVA

    Generator set 5KVA

    Excavator

    J.C.B

    Soil Compactor

    Sensor Pavers

    WM M Pavers

    Vibratory Tandem Roller

    Static Roller

    Hydra

    Air Compressor

    Needle Vibrator

  • 7/25/2019 civil project report

    86/96

    86

    Water Pump

    Bitumen Spryer

    Welding set with Generator 8KVA

    Mechanical Boomer

    Vehicles

    Water Tanks

  • 7/25/2019 civil project report

    87/96

    87

  • 7/25/2019 civil project report

    88/96

    88

  • 7/25/2019 civil project report

    89/96

    89

  • 7/25/2019 civil project report

    90/96

    90

  • 7/25/2019 civil project report

    91/96

    91

  • 7/25/2019 civil project report

    92/96

    92

    SUGGESTION AND

    CONCLUSION

    1.Civil engineer should perform the work at their

    level best so that it will give better result and

    improve the production of the company.

    2. Infrastructure of Civil Contractor Cell should be

    more developed for giving the contract to the

    best contractor.

    3. Welfare facilities should be increase in for civil

    engineers of Construction Company.

    4. For the safety of civil engineers at the

    construction, company should give the best

    equipments of safety to the civil engineers.

  • 7/25/2019 civil project report

    93/96

    93

    5. The hostel facility and amenities should be

    improved so that the civil engineers could work

    with more efficiency.

    6. The civil engineers are advised to do their work

    in slot as they do it bulk which create adverse

    problems for example the road was dug during the

    rainy season in one flow which resulted in heavy

    loss of material, money and machinery of the

    company. The work should have been done in small

    phases and according to the circumstances. The

    clipping can be seen on the next page as to how

    destruction was made during the time when I was

    undergoing my training.

  • 7/25/2019 civil project report

    94/96

    94

    BIBLIOGRAPHY

  • 7/25/2019 civil project report

    95/96

    95

    1.

    I.S. specification book on highway.

    2.

    Highway material testing book by

    3.

    S.K. Khanna, C.E.G Justo.

    4.

    Organizations Laboratory.

    5.

    Organizations Engineers.

  • 7/25/2019 civil project report

    96/96