Cirebon Power Plant_R0

Embed Size (px)

Citation preview

  • 7/24/2019 Cirebon Power Plant_R0

    1/213

    JOB NO. 2338

    CIREBON ELECTRIC POWER PT

    J A K A R T A

    SOIL INVESTIGATION

    FOR

    POWER BLOCK AREA

    CIREBON THERMAL POWER PLANT PROJECT

    CIREBON, WEST JAVA

    I N D O N E S I A

    FINAL REPORT

    AUGUST 2007

    01 10/08/2007 All Issued Final Report, R0 Ir. Padmono, PE Ir.Iman Mulyana Ir.Wirastusrini, PE

    No Date Page Description Prepared by Checked by Approved by

  • 7/24/2019 Cirebon Power Plant_R0

    2/213

    Final Report, Part I : Power Block Area Revision-00

    Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007For Cirebon Electric Power PT, Jakarta Job No. 2350

    PT. Soilens, Bandung Page i

    TABLE OF CONTENTS

    Cover

    Executive Summary

    Table of Contents.......i

    1 INTRODUCTION..1

    2 SCOPE AND PURPOSE.......1

    3 FIELD INVESTIGATIONS...............1

    3.1.Drillings...........1

    3.2.Standard Penetration Tests......2

    3.3.Undisturbed Samplings.......2

    3.4.Water Level Observations.......2

    3.5.Dutch Cone Penetration Test......2

    3.6.Coordinate and Elevation of the Investigated Points.........3

    4 SUBSURFACE CONDITIONS.............3

    4.1.Geology...3

    4.2.Seismicity............4

    4.3.Stratigraphy.........4

    4.4.Soil Profile based on the UBC 1997.......6

    5 LABORATORY TESTING...........6

    5.1.Description of Test..........6

    5.2.Engineering Properties of the Undisturbed Samples......6

    5.2.1. Physical Properties......6

    5.2.2. Strength Parameters.....8

    5.2.3. Compressibility Characteristics...........8

    6 ANALYSIS AND RECOMMENDATIONS...............9

    6.1.Plant Site Preparation............9

    6.1.1.Areal Fill..........96.1.2.Areal Settlements.....9

    6.1.3.Vertical Drain and Deep Mixing...........11

    6.1.4.Provisions Against Secondary Settlement.11

    6.2.Liquefaction........11

    6.2.1. General .......11

    6.2.2. Liquefaction Analysis.11

    6.2.3. Results of Analysis......12

    6.3.Foundations.....12

    6.3.1. General Foundation Criteria........136.3.2. Shallow Foundation....13

  • 7/24/2019 Cirebon Power Plant_R0

    3/213

    Final Report, Part I : Power Block Revision-00

    Cirebon Thermal Power Plant Project, Cirebon, West Java August, 2007For Cirebon Electeric Power PT, Jakarta Job No. 2340

    PT. Soilens, Bandung Page ii

    TABLE OF CONTENTS

    6.3.3. Deep Foundation.....13

    6.3.3.1. Axially Loaded PC-Piles...14

    6.3.3.2.Negative Skin Friction on Piles....14

    6.3.3.3. Laterally Loaded Piles..15

    6.3.3.4. Allowable Pile Capacity...15

    6.3.3.5. Pile Spacing..16

    6.3.3.6. Pile Driving Procedures .......16

    6.3.3.7. Full Scale Vertical Pile Loading Test.......17

    6.3.3.8. Lateral Load Test......196.3.3.9. Pile Dynamic Analyzer (PDA) Test.....19

    6.4. Chemical Properties of Water Samples..........21

    6.5. Hydrology...........22

    6.6. Inspection and Monitoring......22

    Plates :

    PLATE 1.1 to PLATE 1.15 : Areal Settlements Analysis

    PLATE 2.1 to PLATE 2.2 : Vertical Drain Calculation and Spacing

    PLATE 3.1 to PLATE 3.13 : Liquefaction Analysis

    PLATE 4.1 to PLATE 4.15 : Axial Spun Presstresed Concrete Pile Capacity

    PLATE 5.1 to PLATE 5.5 : Lateral Pile Capacity Curves Pinned Pile Head

    PLATE 6.1 to PLATE 6.5 : Lateral Pile Capacity Curves Fixed Pile Head

    PLATE 7.1 to PLATE 7.5 : Lateral Pile Response Pinned Pile Head

    PLATE 8.1 to PLATE 8.5 : Lateral Pile Response Fixed Pile Head

    PLATE 9.1 to PLATE 9.3 : Allowable PC Pile Capacity

    Appendices:

    Appendix A.1 : Project Location Map

    Appendix A.2 : Boring Log

    Appendix A.3 : Graph of 2 ton DCPTAppendix A.4 : Map of Seismic Risk Zones of Indonesia

    Appendix A.5 : General Cross Section

    Appendix B.1 : Laboratory Test Table

    Appendix B.2 : Consolidation Curves

    Appendix B.3 : Unconsolidated Undrained Triaxial Test

    Appendix B.4 : Consolidated Undrained Triaxial Test

    Appendix B.5 : Grainsize Analysis

  • 7/24/2019 Cirebon Power Plant_R0

    4/213

    Final Report, Part I : Power Block Revision-00

    Cirebon Thermal Power Plant Project, Cirebon, West Java August, 2007For Cirebon Electeric Power PT, Jakarta Job No. 2340

    PT. Soilens, Bandung Page iii

    TABLE OF CONTENTS

    Appendix C.1 : Term and SymbolsAppendix C.2 : Equipment and Procedures

    Appendix C.3 : Conversion Factors

    Appendix C.4 : Analytical Procedures

  • 7/24/2019 Cirebon Power Plant_R0

    5/213

    Final Report, Part I : Power Block Area Revision-00

    Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007

    For Cirebon Electric Power PT, Jakarta Job No. 2350

    PT. Soilens, Bandung Page 1

    1. INTRODUCTION

    This geotechnical engineering report is carried out by PT. Soilens for Cirebon Electric

    Power PT. It contains the discussion on engineering properties of the groundrecommendations of foundations system and solution of the anticipated geotechnical

    problem for the Power Block area as part of Cirebon Power Plant Project.

    This final report presents a comprehensive sub-surface information of the proposed plant

    site and a geotechnical assessment for the site preparation, and foundation of variousstructures to be constructed. This includes analyses of areal settlements, soil improvement,

    liquefaction analysis, deep pile foundation and other relevant information for design of the

    proposed plant.

    The analysis of axial compressive and tension pile capacities were performed using

    PLEAXI computer program. The analysis of lateral pile capacities were performed using

    Lpile Plus V5 computer program based on p-y method.

    This work is carried out under the PO No.: 7017-CI-004 dated June 28, 2007 from

    Cirebon Electric Power PT. to PT.SOILENS.

    2 SCOPE AND PURPOSE

    The purpose of the investigation is to explore the soil at the proposed plant site and toprovide recommendations in relation to the foundation design. The scope of the

    investigations included:

    (1) Soil drilling of 15 points, with a total depth of 480 m, performing standard

    penetration test, collecting undisturbed samples, and continuous coring.(2) Performing Dutch Cone Penetration Test of 2 ton capacity at 8 points(3) A laboratory testing program on undisturbed and disturbed samples to evaluate the

    engineering characteristics of the sub surface strata encountered.

    (4) Performing engineering analysis to evaluate and to provide site specific geotechnicalinformation, should include recommendation on most suitable foundation type for

    each facility, recommendation on soil improvement, area settlement and others.However, detail analysis and calculations of foundation design in relation to the

    foundation arrangement and configuration, and working load is beyond the scope of

    works of this report.

    The lay-out of the project and the location of the investigated points are shown in

    Appendix A.1.

    3 FIELD INVESTIGATIONS

    3.1 Drillings

    The field investigations were carried out by a team consisting of Iman Mulyana as TeamLeader, Ujang, Mamay, Omay, E. Slamet, Unang M, Iyang as Drilling Master, Untung as

    CPT Master and Arif S. as Assistant Geologist.

    The drillings were carried out using 6 (six) Long Year drilling machine with Long Year

    535-RQ pumping unit. The bore holes were advanced by continuous coring using NX-

    size, single tube core barrels apparatus with outer diameter of 73 mm. All drillings weresupervised by the Assistant Geologist, who also maintained a continuous logging on the

  • 7/24/2019 Cirebon Power Plant_R0

    6/213

    Final Report, Part I : Power Block Area Revision-00

    Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007

    For Cirebon Electric Power PT, Jakarta Job No. 2350

    PT. SOILENS, Bandung Page 2

    core samples. These core samples were placed in wooden boxes, each containing 5 meterlong of samples, and stored at the site. The undisturbed soil samples were carried out on

    cohesive soil at approximately 5 meter interval or at every change in soil layer.

    The detailed classification of the soil samples after refinements in relation to the laboratorytest results are presented in boring logs included in Appendix A.2.

    The information on the logs also includes the field test results and locations of samples.The samples were brought to PT.SOILENS Soil Laboratory in Bandung where the tests

    were performed.

    3.2 Standard Penetration Tests (SPT)

    The standard penetration test was performed in accordance to the ASTM Standard method

    D1586. The test consists of driving a standard split spoon sampler into the soil at requireddepth in a bore hole.

    A hammer of 63.5 kg weight falling freely from a height of 75 cm on the drill rod is used

    to drive the sampler. The number of hammer blows to drive the second and the third 15 cmof penetration are called the SPT N-value which represents the number of blows per 30 cm

    of penetration. The standard penetration test was performed at 2.0 meter interval. Inaddition, pocket penetrometer tests were also performed on cohesive soil samples that

    indicated plastic behavior. The SPT results presented in the boring log enclosed in this

    report.

    3.3 Undisturbed Samplings

    The undisturbed samples were taken from cohesive soil at depth interval of approximately

    5 meters. This is done by taking samples from bore hole by means of seamless thin walledsteel tube commonly known as shelby tube.

    The tube is 76.2 mm in diameter and has beveled butting edge at the lower end. It isconnected to the drill rod and pushed by static force into the bottom of the hole. When the

    tube is almost full, it is withdrawn from the hole, removed from the drill rod, sealed at bothends with paraffin, and shipped to PT. Soilens soil laboratory in Bandung for testing.

    When ready for test, the samples are ejected from the tubes cut into required length and

    subjected to various laboratory tests.

    3.4 Water Level Observations

    The elevation of ground water level in the bore holes varies from 0.85 to 0.90 m below theexisting ground surface. The ground water level in each bore hole was recorded every

    morning and evening, 24 hours after completion of the drilling through the end of the

    whole field work. Table 1 shows the water level elevation in each borehole.

    The ground water conditions observed during drilling may not represent the groundwater

    conditions during construction. The ground water conditions will fluctuate with wet anddry seasonal. We recommend that the water levels be verified just before construction.

    3.5 Dutch Cone Penetration Test

    One unit of 2-ton capacity Dutch Cone Penetration Test equipment with accessories wasused for the sounding test at site. The test was carried out in accordance with the ASTM D

    3441. The cone penetration test consists of pushing into the soil, at a sufficiently slow rate,

  • 7/24/2019 Cirebon Power Plant_R0

    7/213

    Final Report, Part I : Power Block Area Revision-00

    Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007

    For Cirebon Electric Power PT, Jakarta Job No. 2350

    PT. SOILENS, Bandung Page 3

    a series of cylindrical rods with a beconus at the base for measuring the cone resistance andfriction resistance every 20 cm intervals.

    The results of cone and friction resistance then plotted on a graph, showing the variation

    with depth of cone resistance, ratio of local friction to cone resistance and total friction.The tests results are presented in Appendix A.3.

    Based on the test results, cone and total resistance of 1000 kg/cm2were achieved at depthsof 18.60 meter to 19.60 meter, respectively, from the existing ground surface.

    3.6 Coordinate and Elevation of the Investigated Points

    The coordinates and elevations of the investigated pointa are listed in Table 1. Theinvestigated point positions were determined using an existing Benchmark as the

    reference.

    Table 1 : Coordinates and elevations of the investi gated points

    Coordinate

    NoInvestigated

    PointEast North

    Elevation

    (m)

    Depth

    (m)

    Depth to

    ground waterlevel

    (m)1 BH-12 236341.460 9251052.930 +1.271 30.45 1.20

    2 BH-13 236372.437 9250950.349 +0.215 30.45 0.50

    3 BH-14 236423.346 9251056.548 +0.168 30.45 1.05

    4 BH-15 236348.007 9251021.005 +1.366 30.45 1.00

    5 BH-16 236364.924 9250977.719 +0.538 45.45 1.30

    6 BH-17 236381.312 9250984.099 +0.542 30.45 0.607 BH-18 236463.391 9251046.875 +0.343 30.45 0.70

    8 BH-19 236471.427 9251026.786 +0.129 30.45 0.50

    9 BH-20 236483.486 9251054.908 +0.214 30.45 0.60

    10 BH-21 236491.524 9251034.819 +0.269 30.00 1.40

    11 BH-22 236501.668 9251076.970 +0.316 30.45 1.50

    12 BH-23 236520.071 9251030.966 +0.753 30.45 1.43

    13 BH-24 236531.464 9251081.660 +0.851 30.45 0.75

    14 BH-25 236483.989 9251018.008 +0.287 30.45 -

    15 BH-26 236525.001 9251052.003 +0.683 45.45 0.80

    16 CPT-21 236441.635 9251010.844 +0.312 14.60

    17 CPT-22 236421.819 9251031.058 +0.154 11.60

    18 CPT-23 236388.279 9250994.324 +1.251 12.80

    19 CPT-24 236483.486 9251054.908 +0.214 12.60

    20 CPT-25 236526.253 9251060.528 +0.552 11.40

    21 CPT-26 236531.564 9251081.660 +0.851 12.20

    22 CPT-27 236552.636 9251024.704 +0.843 12.80

    23 CPT-28 236571.259 9251066.558 +0.894 12.40

    24 CPT-31 236471.424 9251110.377 +0.284 15.40

    4. SUBSURFACE CONDITIONS

    4.1 Geology

    Generally, the project site lies on the Alluvial Formations, consisting of homogeneous orinterlaminated fined grained soils, mainly clays and silts, intercalated with coarse grained

  • 7/24/2019 Cirebon Power Plant_R0

    8/213

    Final Report, Part I : Power Block Area Revision-00

    Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007

    For Cirebon Electric Power PT, Jakarta Job No. 2350

    PT. SOILENS, Bandung Page 4

    soils of fine to medium grained sands and occasionally coarse grained sands and gravels.This Alluvial Formation is unconformably underlain by the Undifferentiated Young

    Volcanic Product Formation, comprising of fine to coarse grained volcanistic materials

    (Achdan et.al & Djuri, GRDC 1992 & 1995)

    The flat to lowland topography (not elevated level terrain) of the project site indicates the

    presence of reworked sedimentrary soils due to the Holocene (thousands year ago) Recent stream action, introduced principally by the Cimanuk River. The coarse grained

    soils are generally uncemented (occasionally very weak or slightly cemented) sedimentary

    rounded-altered fragments, derived from the pre-existing Undifferentiated Young ProductFormation

    4.2 Seismicity

    The purpose of study on seismic risk of the project site, was performed based on the

    following references :

    ( 1 ) Seismic Zones for building construction, Beca Carter Holling & Ferner Ltd. andthe Indonesian Counterpart Team, New Zealand Steering Committee, Vol 2 & 3,

    1987.( 2 ) Kertapati E.K. et al., Earthquake Ground Shaking Hazard Map of Indonesia, scale

    1 : 5.000.000, 1999.

    ( 3 ) Standar Nasional Indonesia, SNI 03-1723-2002, Tata cara perencanaan ketahanangempa untuk bangunan gedung, BSN.

    ( 4 ) Preliminary Map of Seismic Risk Zones of Indonesia, compiled by PT. SOILENS(August 30, 2005), scale : 1 : 5.000.000.

    Referring to the the above reference the site is located in the zone with a base rock max.

    horizontal acceleration of 0.10 g for 500-year return period earthquakes. The seismicoccurrence risk is considered by the following expression :

    N

    TNT

    R )1

    1(1, = ..(1)

    Where:

    RN,T = Seismic occurrence risk

    N = the life time of the structures, years

    T = earthquake mean return period, years

    For earthquake mean return period of 500 years and building life time of 50 years, the

    anticipated occurrence risk is approximately 10 %. The map of Seismic zone of Indonesiapresented in Appendix A.4

    4.3 Stratigraphy

    The conditions of the subsurface soils in the project site was determined from visualdescription of the core samples, SPT N-values, laboratory tests and CTP. The lateral and

    vertical extents of the soil stratum was deduced from subsurface cross sections made fromthe boring and CPT log as shown in Appendix A.5 thus the stratigraphy may not be

    accurate in between the boreholes or CPT points.

    As shown in the soil sections, the subsurface soil is found to be generally discontinuous inlateral extend and with irregular shapes extending throughout the project site. The subsoil

  • 7/24/2019 Cirebon Power Plant_R0

    9/213

    Final Report, Part I : Power Block Area Revision-00

    Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007

    For Cirebon Electric Power PT, Jakarta Job No. 2350

    PT. SOILENS, Bandung Page 5

    at the site can be classified into 4 (four) unit based on the physical appearance andengineering properties:

    (1) Layer-1 : Very soft to soft of Clay or Silty Clay, with SPT N-values of less than

    1 to 5(2) Layer-2 : Medium stiff to very stiff Clay or Silty Clay, with SPT N-values of >5

    to 30(3) Layer-3 : Medium dense to dense Sand or Silty Sand, with SPT N-values of more

    than 30

    The description and the distribution of the above Unit are briefed as below:

    (a) Layer-1

    The subsoil in the upper unit is the top soil that consisted of cohesive soil of clay/silty claylayer. The top soil is distributed almost of all over the site and was confirmed in all the

    exploratory boreholes and CPT sounding as shown in the soil profiles.

    The colors of the upper unit are grey to brownish grey, high plasticity. The consistency isvery soft to soft, with SPT N-value of less than 1 to 5, average of 2. The thickness of

    Layer-1varies from 8 to 14 m.

    (b) Layer-2

    Layer-2consists of clay/silt and sand layer, of low to high plasticity. The thickness of this

    layer is vary from 3 m to 14 m. This unit is brownish grey to blackish grey in color. SPTN-values vary from >5 to 30, average of 16.

    (c)

    Layer-3

    Layer-3 consisted of Clay/Silty Clay/Silty Sand of 3 to 20 m in thickness. The color of

    this layer is brownish grey to blackish grey. The SPT N-values of this layer vary from 30

    to 81, average of 40.

    4.4 Soil Profile Based on The UBC 1997

    The Uniform Building Code (UBC) 1997 classifies soil profile for earthquake design into 6types as follows:

    Table 2: Soil Profile based on UBC 1997AVERAGE SOIL PROPERTIES FOR TOP 100 FEET (3048 MM) OF SOIL

    PROFILESOIL

    PROFILE

    TYPE

    SOIL PROFILENAME/GENERIC

    DESCRIPTIONShear wave Velocity, Vs,

    (m/s)

    Standard Penetration

    Test, N (or Nchforcohessionless soil

    layers), (blows/foot)

    Undrained Shear

    Strength, Su, (kPa)

    SA Hard Rock >5,000

    SB Rock 760 to 1,500- -

    SCVery Dense Soil

    and Soft Rock360 to 760 >50 100

    SD Stiff Soil Profile 180 to 360 15 to 50 50 to 100SE

    1 Soft Soil Profile

  • 7/24/2019 Cirebon Power Plant_R0

    10/213

    Final Report, Part I : Power Block Area Revision-00

    Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007

    For Cirebon Electric Power PT, Jakarta Job No. 2350

    PT. SOILENS, Bandung Page 6

    The top layer consist of more than 30 m of soft clay with PI>20, wn >40 percent andaverage undrained shear strength (su) 99 kPa. The soil profile type SEor stif f Soil Profile

    can thus be classified for this site based on UBC 1997.

    5. LABORATORY TESTING

    5.1 Description of Tests

    Selected samples were tested to determine the classification and engineering characteristicsof the soil. All tests were performed in accordance to relevant ASTM standards.

    The laboratory testing program was formulated with the following objectives in mind :

    To provide data so that soil deposits may be adequately identified and classified.These also provide means of correlation with strength parameters resulting in a better

    understanding of the physical behavior of the soils and facilitate the choice of design

    parameters. To obtain relevant strength data to form the basis for foundation design, etc.

    The laboratory test on undisturbed soil samples included the followings:

    1. Index Properties Test:

    Bulk and dry density (ASTM D1557) Water content (ASTM D2216)

    Specific gravity (ASTM C127)

    Atterberg limit (ASTM D4318) Sieve and hydrometer (ASTM D2487)

    Porosity and void ratio (ASTM D2216)

    2. Mechanical Properties Tests:

    Unconsolidated undrained triaxial test (ASTM D2850)

    Consolidation test (ASTM D2435) Unconfined compression test (ASTM D2166)

    The results of laboratory tests are presented in Appendix B. Selected properties andparameters are discussed in the following paragraphs.

    5.2 Engineering Properties of the Undisturbed Samples

    The engineering properties of the subsoil were interpreted from results of the laboratorysoil test and are summarized in Appendix B. The following sections discuss the

    engineering properties of each unit as introduced in Section 4.3

    5.2.1 Physical Properties

    (a) Layer-1

    Layer-1 in general consisted of very soft clay layer. The bulk densities (m) vary from 24.1

    to 27.5 kN/m3, and dry densities (d) vary from 6.4 to 13.8 kN/m3, which is a normal range

    for clay.

  • 7/24/2019 Cirebon Power Plant_R0

    11/213

    Final Report, Part I : Power Block Area Revision-00

    Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007

    For Cirebon Electric Power PT, Jakarta Job No. 2350

    PT. SOILENS, Bandung Page 7

    The natural moisture water contents of the Layer-1 are generally in the range of 35 % to115 %. The majority of the moisture water contents are relatively closed to their liquid

    limits indicating normaly consolidated of very soft to very soft clay.

    The plasticity index and liquid limits of this unit indicate that the majority of the subsoilcan be classified as high plasticity clay (CH) according ASTM standard. The large clay

    content in soil passing No. 200 sieve was believed as the main reason for high liquidlimits. The liquid limits of the Layer-1 vary from 37 to 124 % thus classify the clay as

    high plasticity.

    The index properties and grain size distribution of Layer-1are summarized below with theaverage values in the bracket:

    Natural water content, % 35 115 (63)

    Liquid limit, % 37 124 (82)

    Plastic limit, % 20 43 (33) Plasticity index, % 15 83 (48)

    Bulk density, kN/m3 13.8 18.6 (16.1)

    Grainsize distribution:

    Gravel, % 0 12

    Sand, % 0 70 (20)

    Silt, % 12 41(23)

    Clay, % 15 84 (56)

    (b)Layer-2

    Layer-2consist of clay, and silt layers. The bulk densities of this unit vary from 16.5 to18.0 kN/m3, and dry densities vary from 10.5 to 13.2 kN/m3. Its natural moisture water

    contents generally fall in the range of 37 % to 58 %.

    The plasticity index and liquid limits of this unit indicate that the majority of the subsoil

    can be classified as clay (CH) or Silt (MH) according ASTM standard. The large claycontent in soil passing No. 200 sieve was believed as the main reason for high liquid

    limits. The liquid limits of the Layer-2 are vary from 72 to 88 % thus classify the clay as

    high plasticity.

    The index properties and grain size distribution of Layer-2are summarized below with the

    average values in the bracket:

    Natural water content, % 37 58 (44)

    Atterberg limits

    Liquid limit, % 72 88 (79)

    Plastic limit, % 32 42 (36)

    Plasticity index, % 30 55 (44)

    Bulk density, kN/m3 16.5 18.0 (17.1)

    Grainsize distribution:

    Gravel, % 0

    Sand, % 2 7 (5)

  • 7/24/2019 Cirebon Power Plant_R0

    12/213

    Final Report, Part I : Power Block Area Revision-00

    Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007

    For Cirebon Electric Power PT, Jakarta Job No. 2350

    PT. SOILENS, Bandung Page 8

    Silt, % 13 41(25)

    Clay, % 52 81 (69)

    (c)

    Layer-3

    Layer-3consist of sand and clay respectively. No undisturbed samples was collected thus

    no laboratory test results from this layer.

    5.2.2 Strength Parameters

    The undrained shear strengths (cu) and internal friction angle () of the cohesive soil takenfrom Layer-1, and Layer-2 were determined from the laboratory Unconsolidated

    Undrained (UU) Triaxial test and from the laboratory unconfined compression test. The

    undrained shear strength of Layer-3 were derived based on SPT N values with correlation

    of su= 6N, N is average SPT N values.The following range of undrained shear strengths with the recommended average values in

    bracket:

    Table 3: Un-drained shear strengths of the subsoil and friction angle of the soil

    Description Layer-1 Layer-2 Layer-3

    SPT N-values Less 1-5 >5 30 >30

    Un-drained shear strength (cu),kN/m2 2-43 (16) 13-98(54) >150

    Internal friction angle (), degrees 0.3-8.5(3.1) 1.6-9.0(5.8) 0

    Note : (1) Undrained shear strengths are predicted from SPT N-values

    5.2.3 Compressibility Characteristic

    The pre-consolidation pressures (Pc) in Layer-1 is much lower than the computed effective

    overburden pressures, therefore the soil is under normally consolidated. For Layer-2 thepre-consolidation pressure (Pc) is higher than the effective overburden pressure, therefore

    these units are over consolidated.

    The consolidation properties for cohesive subsoil obtained from the laboratory tests and

    the recommended average values are summarized in Table 4.

    Table 4: Compressibility Characteristic of the Subsoil

    Description Layer-1 Layer-2

    Compression Index, cc 0.29-1.51(0.78) 0.34-0.47(0.38)

    Preconsolidation Pressure (Pc),kPa 17-550(116) 247-646(413)

  • 7/24/2019 Cirebon Power Plant_R0

    13/213

    Final Report, Part I : Power Block Area Revision-00

    Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007

    For Cirebon Electric Power PT, Jakarta Job No. 2350

    PT. SOILENS, Bandung Page 9

    6. ANALYSIS AND RECOMMENDATIONS

    6.1 Plant Site Preparation

    6.1.1 Areal Fill

    To form the final grading level of the proposed development, low lying area will beraised to an elevation of +5.00 m MSL to keep the site should always be dry and free

    from any flooding during the plant life time. The fill thickness will range of 3.63 to4.87 m. Based on the laboratory tests, the original soil layers is to weak to carry the

    proposed fill height. Failure will occur as the safety factor against failure of the original

    soil layer, based on the conservative estimate is less than 1.0.

    Reclamation could be done using sand obtained from along the coastal area. Before

    reclamation over the proposed plant area we have to remove any organic material.Analysis on ultimate bearing capacity for each borehole point gives the following

    results:

    Table 5: Ultimate bearing capacity calculation results

    Borholecu

    (kN/m2)

    qult

    (kN/m2)

    Fill

    thickness(m)

    p

    (kN/m2)

    SF against

    bearing capacityfailure

    BH-12 10 51.4 3.73 61.54 0.83

    BH-13 13 66.8 4.78 78.87 0.85

    BH-14 8 41.1 4.83 79.69 0.51

    BH-15 5 25.7 3.63 59.89 0.43

    BH-16 12 61.7 4.46 73.59 0.84

    BH-17 10 51.4 4.45 73.42 0.70

    BH-18 10 51.4 4.65 76.72 0.66

    BH-19 41 210.7 4.87 80.35 2.62

    BH-20 47 241.5 4.78 78.87 3.06

    BH-21 11 56.5 4.73 78.04 0.72

    BH-22 14 71.9 4.68 77.20 0.93

    BH-23 13 66.8 4.25 70.12 0.95

    BH-24 9 46.3 4.20 69.30 0.67

    BH-25 2 10.3 4.71 77.71 0.13

    BH-26 2 10.3 4.32 69.79 0.15

    Note:

    1. cu = undrained shear strength

    2. qult = ultimate bear ing capacity = 5.14 cu.

    3. p = fill pressure = fill thickness x fill density (16.5 kN/m2)

    4. SF = Safety Factor =

    p

    ultq

    6.1.2 Areal Settlement

    Settlement analysis due to areal fill is carried out for points at the center of the fill.

    Stress distribution at each soil layer is calculated based on the elasticity theory using

    Bousinesqs equations. The settlement to occur is estimated using Terzaghis onedimensional compression model with soil parameters obtained form oedometer test in

  • 7/24/2019 Cirebon Power Plant_R0

    14/213

    Final Report, Part I : Power Block Area Revision-00

    Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007

    For Cirebon Electric Power PT, Jakarta Job No. 2350

    PT. SOILENS, Bandung Page 10

    the laboratory. The results of the settlement calculation presented in PLATE 1.1 toPLATE 1.2, summarized in Table 6.

    Table 6: Summarized areal settlement analysis results

    Borhole Fill (m)Unit Weight

    (kN/m3)

    Average Load(kN/m

    2)

    Settlement(mm)

    Time required toreach 90 %

    consolidationsettlements

    (Years)

    BH-12 3.73 16.5 61.53 1164 6.8

    BH-13 4.79 16.5 78.95 1577 1.6

    BH-14 4.83 16.5 79.73 1770 8.1

    BH-15 3.63 16.5 59.96 1056 4.6BH-16 4.46 16.5 73.62 1414 6.9

    BH-17 4.46 16.5 73.56 1798 2.4

    BH-18 4.66 16.5 76.84 820 8.1

    BH-19 4.87 16.5 80.37 754 5.7

    BH-20 4.79 16.5 78.97 1209 8.1

    BH-21 4.73 16.5 78.06 1323 5.7

    BH-22 4.68 16.5 77.29 1198 5.7

    BH-23 4.25 16.5 70.09 1169 5.7

    BH-24 4.15 16.5 66.38 1782 4.6

    BH-25 4.71 16.5 77.76 1033 3.8

    BH-26 4.32 16.5 71.23 915 6.0

    Under the fill layer of about 3.7 to 4.8 meter the proposed plant site will undergo arealsettlement. That is due to consolidation process of the upper soft layer of about 12 meter

    thick under the fill weight.

    Because of very soft original soil layer, we do not recommend filling the area with very

    high fill in straight until elevation of +6.5 m MSL. With average undrained shearstrength of about 16 kN/m2 the ultimate bearing capacity of the original layer will beonly 82 kN/m2. The maximum fill height that can be supported by the original layer

    without failure is hfill=qult/(fill x SF). Using SF (Safety Factor) of 1.5 and fill 16.5kN/m2then hfill= 3.3 meter.

    Therefore, 2 stages of filling should be performed to avoid failure on the original softlayer. First stage is filling the proposed plant area to +3.50 m MSL, and wait until

    settlement finishes within about 3 years. After the first-stage settlement then the second

    filling until elevation of +6.50 m MSL can be done and wait until the second settlementfinishes within next three years before plant construction.

  • 7/24/2019 Cirebon Power Plant_R0

    15/213

    Final Report, Part I : Power Block Area Revision-00

    Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007

    For Cirebon Electric Power PT, Jakarta Job No. 2350

    PT. SOILENS, Bandung Page 11

    6.1.3 Vertical Drain and Deep Mixing

    Waiting 3 years for site preparation is not an attractive choice for a project with tight

    schedule like this power plant project. To speed up consolidation process of the top 11

    m layer installation of vertical drains over the proposed plant site together withsurcharging (filling) can be a good solution in terms of cost efficiency and construction

    ease. We propose using synthetic band-shaped drain (wick-drain) of 100 mm wide and6 mm thick for vertical drains installed until about 11 m depth below the existing

    ground surface. By using drain spacing of about 1.5 m in triangular pattern the

    consolidation process of the original soft layer can be expected to be finished withinabout 3 month. The two stages of filling then can be finished within about six month.

    PLATE 2 shows drain spacing calculation using Baron theory for vertical drains.

    Other method of ground improvement should be considered of the time available for site

    preparation is less than 6 (six) months. Deep mixing or deep compaction to mix reagents

    such as cement powder or lime with in-situ soil can be considered for groundimprovement. This type of improvement will increase the strength and reduce the

    compressibility of the soft layer. However, Contractor specialist in this field should becontacted for further assessment.

    6.1.4 Provisions Against Secondary Settlement

    Although consolidation settlement has been finished, the designer of the plant should beaware of the remaining secondary settlement that is still to be experienced by the project

    site during the lifetime of the plant due to creep of the original soft soil layer. Such asettlement is estimated to be in the order of ten percent of the consolidation settlement,

    i.e. about 15 to 20 cm, during the plant lifetime. For example, connection between pipe

    resting directly on the ground and structure resting on pile should take intoconsideration this remaining settlement. Otherwise, problem will arise after some years

    of construction because of this settlement, which may not be of the same magnitude atevery point.

    6.2 Liquefaction

    6.2.1 General

    The basic cause of liquefaction is the built-up of excess pore pressure caused by

    earthquake induced vibrations. The excess pore pressure can cause loose cohesionlessmaterial to lose strength, and results in large settlements of the structures supported on

    this material; or in the case of the pile foundations, the soil may lose its ability to

    provide lateral resistance for the piles during liquefaction.

    6.2.2 Liquefaction Analysis

    For the analysis of liquefaction, all borings containing sand material are analyzed todetermine whether this material is subject to liquefaction under 0.08 g and 0.10 g peak

    ground accelerations (PGA) and earthquake magnitude of 6.9 Richter Scale. The

    analysis is performed using the methods of Seed & Idris and Ishihara, using thefollowing equation:

    d

    o

    od

    org

    PGA...65.0)( ''

    = ......(1)

  • 7/24/2019 Cirebon Power Plant_R0

    16/213

    Final Report, Part I : Power Block Area Revision-00

    Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007

    For Cirebon Electric Power PT, Jakarta Job No. 2350

    PT. SOILENS, Bandung Page 12

    d

    o

    l

    oFS

    )(

    )(

    '

    '

    = .......(2)

    Where :

    d

    o

    )('

    = average cyclic stress ratio developed during the earthquake

    PGA = peak ground acceleration at the ground surface in g

    g = acceleration of gravity, m/s2

    o = total stress at depth of interest, ton/m2or kN/m2

    '

    o = effective stress (total stress minus pore water pressure) at depth, ton/m2or

    kN/m

    2

    rd = reduction in acceleration with depth= 1-0.008 Z

    Z = depth below ground surface, m

    l

    o

    )('

    = cyclic stress ratio required to induce liquefaction.

    FS = factor of safety.

    Figure 1 : Liquefaction curves criterion for fines5 %, 15 % and 35 %

    Specifically, the

    analysis consists of firstselecting the sands, silty

    sands and clayey sandslayers occurring below

    the water table that are

    characterized byrelatively low standard

    penetration test valuesthat may be susceptible

    to liquefaction. The

    standard penetrationtest values are then

    normalized, the cyclic

    shear stress isdetermined, and all

    material having a factorof safety less than 1.0 is

    concluded to beliquefiable.

    6.2.3 Result of Analyses

    Based on the analyses described in Section 6.2.2, for peak ground acceleration (PGA) of

    0.08 g and 0.10 g with earthquake magnitude of 6.90 Richter Scale, the sand is not

    potentially liquefiable with a safety factor of more than 1.0. The results of analysis arepresented in PLATE 3.1to PLATE 3.13.

  • 7/24/2019 Cirebon Power Plant_R0

    17/213

    Final Report, Part I : Power Block Area Revision-00

    Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007

    For Cirebon Electric Power PT, Jakarta Job No. 2350

    PT. SOILENS, Bandung Page 13

    6.3 Foundations

    6.3.1 General Foundation Criteria

    To have a good performance foundation of any structure must satisfy two independent

    design criteria.

    It must have an acceptable factor of safety against bearing type failure under a

    maximum design load. Settlements during the structure lifetime must not be a magnitude that will cause

    structural damage, or impair the operational efficiency of the facility.

    Selection of the foundation type to satisfy the criteria depends on the nature andmagnitude of dead and live loads, the base area of the structure and the settlement

    tolerances. Where more than one foundation type satisfies these criteria, the cost,scheduling, material availability and local practice will influence on the final selection of

    the type of foundation.

    6.3.2 Shallow Foundation

    We do not recommend the use of shallow foundation for any important and settlement

    sensitive structure because of the low bearing capacity of the original layer and therelatively large settlement that still to be experienced by the project site.

    6.3.3 Deep Foundation

    6.3.3.1 Axially Loaded PC-Piles

    The most reasonable and acceptable foundation for any important and settlement

    sensitive structure to be constructed here is driven pile. This is because driven pile is easyand fast to install and can transfer working load to a competent layer at deeper layer

    stratum by by-passing the top soft layer, resulting in very small experienced settlement

    The assessment of axial pile capacity is based on Pre stressed Concrete Spun Pile (PC-Pile) of 300 mm, 350 mm, 400 mm, 450 mm and 500 mm outside diameter, with 60

    mm, 65 mm, 75 mm, 80 mm and 90 mm wall thickness, respectively.

    The ultimate soil bearing capacity in compression and tension is calculated based on the

    laboratory and field tests, by using the following equation :

    Pult-cmp = fs.As+ qp.Ap.......................(3)

    Where :Pult-comp = ultimate pile capacity in compression, kNfs = unit skin friction to pile, kN/m

    2

    = . cu, for cohesive soil

    = ko.po.tan(), for cohesionless soil

    = adhesion factor

    = 0.50. 50.0)(

    o

    u

    p

    cfor

    o

    u

    p

    c1.0

    = 0.50.25.0

    )(

    o

    u

    p

    cfor

    o

    u

    p

    c >1.0

    ko = coefficient of lateral earth pressure

    = 1 sin

  • 7/24/2019 Cirebon Power Plant_R0

    18/213

    Final Report, Part I : Power Block Area Revision-00

    Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007

    For Cirebon Electric Power PT, Jakarta Job No. 2350

    PT. SOILENS, Bandung Page 14

    cu = undrained shear strength, kN/m2

    Po = effective overburden vertical stress at depth under consideration,

    kN/m2

    As = outside surface area of pile, m

    2

    qp = unit end bearing capacity, kN/m2

    = 9.cu, for cohesive soil= po.Nq, for cohesionless soil

    Nq = dimensionless bearing capacity factor

    Ap = cross section area of pile, m2

    The shear strength (cu) of rock can be derived based on unconfined compression test with

    correlation of2

    uu

    qc = . If there is no laboratory test results, the un-drained shear

    strength derived based on SPT N-values using correlation of c u = 6N. The maximum

    values of cu is 250 kPa for compressive and 100 kPa for tension. The analysis wasperformed by using computer program of PLEAXI. To aid the designer in designing a

    foundation, the graph of pile capacities for each borehole point is provided in this report.The designer can select which borehole point close to a particular structure or to a

    particular pile location so pile capacity can be obtained from the graph for that borehole.

    The graphs showing the ultimate and allowable soil bearing capacity in compression and

    tension against the embedment depth below plant site elevation of +5.0 m MSL are

    shown in PLATE 4.1 to PLATE 4.15 enclosed in this report. The allowablecompressive capacity of spun piles are designed for a safety factor of 2 and the estimated

    settlement of about 25.4 mm. The allowable tension capacities are designed for a safetyfactor of 3.

    6.3.3.2 Negative Skin Friction on Piles.

    Due to the site fill over the existing consolidated soil layers at the plant site, we

    recommend to include the negative skin friction in calculating allowable

    compressive bearing capacity. The magnitude of negative skin frictionPNactingon bored pile is presented in Table 7.

    The unit negative skin friction is calculated as suggested by Bjerrum using the following

    equations:

    For cohesive soil : fs = 0.25 po..............................................................(4)

    For cohesionless soil : )4

    3tan(...

    2

    1oss pkf = .........(5)

    Where :

    fs = unit negative skin frictionpo = effective overburden pressure

    ks = coefficient of lateral earth pressure

    = internal friction angle of cohesionless soil

    The ultimate negative skin friction then to be calculated by using the following equation:

    PN = .D.LN.fs.......(6)

    Where :

  • 7/24/2019 Cirebon Power Plant_R0

    19/213

    Final Report, Part I : Power Block Area Revision-00

    Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007

    For Cirebon Electric Power PT, Jakarta Job No. 2350

    PT. SOILENS, Bandung Page 15

    PN = ultimate negative skin friction on pileD = diameter of pile

    LN = length of pile to neutral point

    fs = unit negative skin friction.The negative skin friction on pile summarized as follows:

    Table 7: Negative skin friction on pile (PN)

    No Pile TypePile Dimension/

    Diameter

    Negative Friction (PN)

    (kN)

    1 Spun Pile dia. 300 mm 165

    2 Spun Pile dia. 350 mm 190

    3 Spun Pile dia. 400 mm 215

    4 Spun Pile dia. 450 mm 245

    5 Spun Pile dia. 500 mm 270

    6.3.3.3 Laterally Loaded Piles

    The analysis of the lateral capacity of the piles is performed by using Lpile Pluscomputer program developed by Ensoft. Lpile Plus uses a finite difference approximation

    to solve the non-linear spring-beam/column model of pile-soil interaction. The stress-

    strain response of the pile is modeled as a simple elastic material with E-pile assumed to

    be b9600 kg/cm2. Where bis the characteristics compressive strength of concrete

    of 500 kg/cm2for pc-pile.

    The results of analyses for single piles are presented as curves of the lateral load versuspile head deflection and the lateral load versus maximum bending moment on the

    following Plate :

    PLATE 5.1 to PLATE 5.5 for Pinned/Free Pile Head

    PLATE 6.1 to PLATE 6.5 for Fixed Pile Head

    The pile response due to lateral load presented in curves on the following plate :

    PLATE 7.1 to PLATE 7.5 for Pinned/Free Pile Head

    PLATE 8.1 to PLATE 8.5 for Fixed Pile Head

    6.3.3.4 Allowable Pile Capacity

    (a).

    Axial Compressive CapacityTo determine the allowable axial pile capacity in compression the equation (4)should be used.

    s

    ult

    compallF

    PP

    comp

    = ........................................................(4)

    Where :Pall-comp = allowable soil bearing capacity in compression, kN

    Pult-comp = ultimate soil bearing capacity, kN

    FS = factor of safety, 2.0

    Based on our experience a safety factor of 2.0 may be used in equation (4) to getthe allowable compressive capacity.

  • 7/24/2019 Cirebon Power Plant_R0

    20/213

    Final Report, Part I : Power Block Area Revision-00

    Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007

    For Cirebon Electric Power PT, Jakarta Job No. 2350

    PT. SOILENS, Bandung Page 16

    (b). Axial Tension Capacity

    To determine the allowable axial pile capacity in tension the equation (5)should

    be used.

    s

    ult

    tensionallF

    PP tension= ..........................................................(5)

    Where :Pall-tension= allowable pile capacity in tension, kN

    Pult-tension= ultimate pile capacity in tension, kNFS = factor of safety, 3

    Finally, the maximum allowable load both in compression and tension should be

    checked against the allowable capacity of the pile material.

    (c). Lateral Pile Capacity

    We recommend using allowable lateral load based on a tolerable butt deflectionof 10 mm for pinned head and 6 mm for fixed head.

    During design phase the lateral pile capacity presented in this report should be

    checked against the capacity of pile material to resist bending moment and shearstress. This can be done by checking the interaction graph of axial load versus

    bending moment issued by the pile manufacturer.

    The pile penetration or length below plant elevation, allowable compressive,

    tension and lateral pile capacity are presented in PLATE 9.1 to PLATE 9.3. It

    should be noted that the allowable static axial pile capacities presented in thistable can be increased by 30 % to determine the transient load such as wind or

    seismic.

    6.3.3.5 Pile Spacing

    Axial loading of group piles should be determined as the product of group efficiency

    (reduction factor), number of piles in the group and the capacity of a single pile. Werecommend that for piles with center to center spacing of 3 pile diameters, the reduction

    factor of 1.0 be used. The reduction factor of 0.70 for piles with a center to center spacingless than 3 pile diameters should be used. Center to center piles spacing less than a 2.5

    pile diameter is not recommended.

    For lateral loading, analyses based on Fleming show that no reduction in lateral capacitydue to pile group effects is envisaged provided the pile spacing is 4.5 pile diameter or

    greater (center to center). In case pile spacing is less than 4.5 pile diameter in a group, werecommend reduction factor of 0.70 to analyze the lateral group capacity.

    6.3.3.6 Pile Driving Procedures

    (a). Driving Records

    Probe piles should be installed first before any production pile. Observation on

    probe pile should be performed at every area near the boring points to know the

    sufficient length of embedment, final blows per 25 cm penetration, and totalblows of each probe pile.

  • 7/24/2019 Cirebon Power Plant_R0

    21/213

    Final Report, Part I : Power Block Area Revision-00

    Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007

    For Cirebon Electric Power PT, Jakarta Job No. 2350

    PT. SOILENS, Bandung Page 17

    After driving the probe piles, pile load tests on several piles at represented areashould be carried out to know pile behavior under loading and pile load capacity

    at certain short-term settlement.

    Driving of working piles are performed after issuing pile driving criteria for pilesat each represented area. The following data shall be recorded in the pile driving

    record sheet.

    (1) General data including project name, job number, pile driving record, date

    and time of pile driving commencement and completion, pile number,

    structures name, ground surface elevation and others.(2) Data of pile including pile identification number, pile diameter, pile length,

    pile tip elevation, and others(3) Data of hammer including total weight of hammer ram weight, ram stroke,

    rate energy per blow, hammer cushion.

    We recommend that pile driving be performed from center to edge of the group toavoid or to limit possible heaving. A continuous heave measurement for all the

    piles should be performed throughout the pile driving. Re-driving of piles shouldbe done if heave exceeds 25.4 mm.

    We recommend using pile shoes to improve drive-ability and also to provide

    protection at the pile tip.

    (b). Pile Driving Criteria

    The pile driving acceptance criteria should be based on the following :

    (1).

    Drive the pile to target level as defined by the nearest boring logs or pile testresults.

    (2). If the pile comes to refusal above target level, continue driving until a blowcount of 100 blows/250 mm penetration or final set of 25 mm/10 blows. The

    pile is then required to be driven for final setting in 2 t imes, without anyreduction in the driving resistance. If the resistance is not maintained at 25

    mm/10 blows it is judged that the hard layer is thin and the pile is liable to

    break through this layer. Therefore, the pile should be driven further to thetarget level.

    (c). Use minimum pile driving equipment of K-35 with hammer weight of 35 kN or

    equivalent for driving the pile with pile weight of 25 to 65 kN and requiredbearing capacity of 1000 to 1750 kN.

    (d). Use minimum pile driving equipment of K-45 hammer weight of 45 kN orequivalent for driving pile with pile weight of 35 to 85 kN and required bearing

    capacity of 650 kN to 2000 kN.

    6.3.3.7 Full Scale Vertical Pile Loading Test

    The design capacities in this report for properly installed conventional piles are based on

    considerable experience with load tests as well as the application of geotechnical design

    methods. It is recommended performing full scale pile loading tests for the axial anduplift modes to confirm the calculated ultimate to determine the safe loads capacities ofthe piles.

  • 7/24/2019 Cirebon Power Plant_R0

    22/213

    Final Report, Part I : Power Block Area Revision-00

    Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007

    For Cirebon Electric Power PT, Jakarta Job No. 2350

    PT. SOILENS, Bandung Page 18

    The test piles should be installed with the same procedures and details which will be usedfor production piles. This is especially important with bored piles where the performance

    can be significantly influenced by the installation procedures. The test pile lengths should

    be similar to the expected lengths of the production piles. If at all possible, the static loadtesting procedures and capacities should be such that the load test is carried out to a soil

    failure. Having failure criteria will allow the penetration of the production piles to bemodified based on the load test results and the calculated pile-soil adhesion factors.

    The tests should follow ASTM D1143 and ASTM D3689 procedure. The test should be

    carried out on 2(two) of the first piles. This will enable an early evaluation and make itpossible to verify weather the pile system actually complies the contractors

    specifications. The pile load testing program should consider the following :

    The load shall be applied to the test pile by a hydraulic jack acting against a reaction

    beam, which is anchored by two or four reaction piles or loaded platform with concrete

    blocks.Reaction pile or counter loads and hydraulic jack each should have a capacity of

    minimum 4 times the pile design load.

    Vertical movement of the test pile and reaction piles are measured using at least 3 dial

    gauges, each having a 50 mm travel and be accurate to 0.01 mm. The dial gauges should

    be supported independently from the test pile and reaction piles.

    The loads shall be applied in accordance with the cyclic loading procedure of the

    respective ASTM standard. The entire test area must be sheltered from direct sunlight, wind and rain. The

    shelter must be sufficiently lighted as to allow night monitoring.

    The resultant of the load components must act along the longitudinal centerline ofthe test pile.

    An effort is to be made to have the dial gages calibrated prior to the test in anacceptable testing laboratory and the certificate is to be submitted for records.

    During test loading, read dial gages at 0, 1, 2, 5, 10, 15 and 30 minutes after each

    load increment, and 30 minutes intervals thereafter with max. 2 hours. Opticalreadings shall be taken on the reaction of anchor piles as well as the test pile before

    each load increment is changed. During 24 hours hold, readings may be taken every3 hours after the first 2 hours.

    The final report shall contain the following :

    Identification, location and description of the test pile Description of the test apparatus, loading system and deflection measurement

    procedure Tabulated field data

    Time-settlement curve

    Load-settlement curve Remarks explaining unusual events or data, and movement of reaction piles

    Inspection logs for the test pile Calibration certificate of dial gauges and pressure gauges, indicating the serial

    number of the gauges and date the calibration was performed

    Pile loading test shall be performed minimum 21 days after pile driving. We suggestperforming minimum 2(two) static loading tests on plant site.

  • 7/24/2019 Cirebon Power Plant_R0

    23/213

    Final Report, Part I : Power Block Area Revision-00

    Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007

    For Cirebon Electric Power PT, Jakarta Job No. 2350

    PT. SOILENS, Bandung Page 19

    6.3.3.8 Lateral Load Test

    It is recommended to perform lateral load test to confirm the calculated ultimate capacity

    to determine the safe loads capacities of the piles. The tests should follow ASTM D3966

    procedure.

    The impact point for the lateral test load shall be as close as possible to the site elevation.

    The impact point shall be finalized at the job site taking into account the loading device tobe actually utilized at the time of load test. The following requirement and boundary

    limitation shall be applied for performing the lateral load test :

    In the static loading, unless failure occurs first, the test pile shall be loaded to themaximum test load of 200 % of the design load in accordance with the standard

    loading procedure stipulated in ASTM D3966, Section 6.1

    In the dynamic (cyclic) loading, unless failure occurs first, the test pile shall be

    loaded to the maximum test load of 200 % design load in accordance with thestandard loading procedure stipulated in ASTM D3966, Section 6.3

    6.3.3.9 Pile Dynamic Analyzer (PDA Tests)

    (a) We recommend performing Pile Dynamic Analyzer (PDA) Test to evaluate theultimate pile capacity at the time of testing. Based on the PDA test results,

    CAPWAP analysis should be performed to provide refined estimates of static

    capacity, assessment of soil resistance distribution, and soil quake and dumpingparameters for wave equation input.

    (b) It is noted that the soil is greatly disturbed when a pile is driven into the soil. As

    the soil surrounding the pile recovers from the installation disturbance, a timedependent change in capacity often occurs. In this case we suggested to perform

    PDA in two time for the same pile as follows:

    Immediately after pile driving, and

    21 days after pile driving.

    The hammer for pile dynamic analysis should be warmed up before re-drivebegins by applying at least 20 blows to another pile. The maximum amount of

    penetration required during re-drive should be 152.4 mm (6 inches) or the

    maximum total hammer blows required will be 50, whichever occurs first.

    (c) Equipment and Methodology Prepared the top of the pile head, prior to testing, by grinding the concrete

    surface to a smooth and flat condition.

    Drilled and plugged the concrete test pile in order to attach two strain

    transducers and two piezo-electric accelerometers to the pile shaft at a distanceof 1.5 to 2.0 times the pile diameter below pile head.

    The instrument then is connected to the PDA Collector computer by aninsulated multi-wire cable. The PDA computer should be located some

    distance away from the instrumented test pile

    Dynamic measurements then are obtained from the strain transducers andpiezo-resistive accelerometers by striking the pile head on four separate

    occasions using a driving hammer as a drop weight. Each blow should be

  • 7/24/2019 Cirebon Power Plant_R0

    24/213

    Final Report, Part I : Power Block Area Revision-00

    Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007

    For Cirebon Electric Power PT, Jakarta Job No. 2350

    PT. SOILENS, Bandung Page 20

    cushioned by a purpose made plywood packer placed directly on top of thesmooth pile head.

    Analog signal from transducers be conditioned, digitized, stored and processed

    by PDA. Selected output from PDA typically included values such as :

    the measured force and calculated maximum stress

    transferred energy to the pile

    calculated ram stroke

    static pile capacity and others

    (d) The following main Pile Driving Analyzer data input should be checked and beadjusted to the actual pile and soil condition in the project

    Pile length below gages Pile cross section area at the gauges

    Pile elastic modulus Unit weight of pile material Pile wave speed

    Case damping factor Unit indicator

    Display scale and transducer calibrations

    (e) Methodology of CAPWAP Analysis

    The CAPWAP computer program is a rigorous numerical analysis procedure

    which uses the PDA measured force and velocity data to solve for soilresistance parameters.

    A model of each pile should be divided into segments of approximately one

    meter in length and trial soil resistance be assigned every second embeddedpile element and one extra resistance at the pile base, to model the base

    response.

    The soil model for each soil element contained a static resistance represented

    by an elasto-plastic spring with an ultimate resistance and a limiting elastic

    displacement, termed the quake

    The soil damping modeled as a viscous dashpot with a damping factor which

    related the magnitude of the dynamic soil resistance to the pile velocity.

    The selected PDA measured pile top velocity for the test pile then is imposedas an input to the CAPWAP analysis and trial values is assigned to all soil

    model parameters. The required pile top force then computed and thesolution compared with the measured force obtained from the selected

    hammer blow. The agreement between computed and measured pile top forceshould be progressively improved by an iteration process in order to modify

    the soil model parameters, total capacity and its distribution along theembedded pile shaft, damping factors and quakes until no further significant

    improvement could be obtained in the model. The final soil parameters then

    are deemed to represent a best match dynamic soil model for the test pile.These soil parameters and pile model, finally be analyzed to calculate both

    shaft and base resistance, total mobilized capacity, and the static load-settlement response of both the pile head and the pile base.

  • 7/24/2019 Cirebon Power Plant_R0

    25/213

    Final Report, Part I : Power Block Area Revision-00

    Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007

    For Cirebon Electric Power PT, Jakarta Job No. 2350

    PT. SOILENS, Bandung Page 21

    (f) Detail procedures of PDA Test, apparatus to be applied, analysis, and reportingshall be in accordance with the requirement of ASTM D4945.

    (g) All components of the apparatuses for obtaining dynamic measurement and the

    apparatuses for recording shall be calibrated at least once a year.

    (h) The PDA test and analysis should be performed by qualified and experienced

    Engineer(s). We recommend performing 4 (four) points of PDA test for thisproject. Regardless of the project size, we consider that Engineer may adjust the

    number and locations of dynamically tested piles based on design or construction

    issues that arise

    6.4 Chemical Properties of Soil and Water Samples

    Chemical test, i.e., pH, chloride content, and sulfate content were performed on soil andwater samples obtained from borings to know the aggressivity of the soil against concrete

    structure. The results of analysis are summarized in Table 8.

    Table 8: Chemical properties of soil samples.

    Test ResultNo Test

    in ppm in %

    1 pH 7.8-8.1(7.9)

    2 Chloride (Cl) content 6409-13032(8987) 0.64-1.30(0.90)

    3 Sulfate Content 3452-5546(4844) 0.35-0.55(0.48)

    Table 9: Chemical properties of water samples.

    Test ResultNo Test

    in ppm in %

    1 pH 6.1-6.9(6.6)

    2 Chloride (Cl) content 15310-18515(17595) 1.53-1.85(1.76)

    3 Sulfate Content 1766-1924(1817) 0.18-0.19(0.18)

    The pH data indicates that the soils in the area are normal. The degradation of concrete iscaused by chemical agents in the soil or groundwater that react with concrete to either

    dissolve the cement paste or precipitate larger which cause cracking and flaking. The

    concentration of the water-soluble sulfate in the soils is a good indicator of the potential forchemical attack of concrete. Sulfate concentration in soil can be used to evaluate the need

    for protection of concrete based on the information in the table below:

    Table 10: Sulfate Attack Potential

    Sulfate ion concentration, ppm Aggressiveness

    >20,000 Very Severe

    2,000 to 20,000 Severe

    1,000 to 2,000 Moderate

  • 7/24/2019 Cirebon Power Plant_R0

    26/213

    Final Report, Part I : Power Block Area Revision-00

    Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007

    For Cirebon Electric Power PT, Jakarta Job No. 2350

    PT. SOILENS, Bandung Page 22

    The American Concrete Institute Code 218 recommends that for these conditions Type Vcement be used with a water cement ratio of less than 0.45. Other types of cement with fly

    ash up to 10 % may be used if the maximum water cementitious materials ratio is reduced

    to 0.4 or lowerBecause of the location of the project adjacent to a salt water and possibility of moisture

    containing significant volumes of chlorides which could then be deposited on concreteexposed to wetting and drying cycles, considerations should be given to provide corrosion

    protection to minimize chloride attack to the exposed concrete structures near or on the sea.

    Chloride inhibitors are available as admixtures during concrete mixing.

    6.5 Hydrology

    To ensure easy drain of rain water runoff from the plant site, drainage ditch should beconstructed along the proposed road, around the buildings, the edges of the embankment or

    excavation onto slopes. A vegetation cover should be established as soon as possible on theembankment and or excavation slopes to minimize erosion from the surface run-off. Run-off coefficient of 0.70 to 0.90 should be used for calculating design discharge on paved

    area, and 0.50 for flat grassed areas with about 50 percent area impervious. We alsorecommend providing the area with impermeable surface drainage ditch, i.e., lined ditch, to

    easily drain the surface water to a lower elevation.

    6.6 Inspection and Monitoring

    Geotechnical aspects of foundation construction and/or installation should be monitored by

    a geotechnical engineer or his/her representative. Critical phases of the construction where

    geotechnical inspection is crucial to success of the project are : During plant site reclamation, and soil improvements.

    During pile load testing, for making change in situ driving criteria and depth

    requirements to account for subsurface conditions.

    During production pile driving to monitor depth requirements and potential hard driving

    zones and others.

  • 7/24/2019 Cirebon Power Plant_R0

    27/213

    01

    164

    621

    164

    62

    0

    621

    164

    0.1

    0.3

    0.6

    1.0

    1.6

    2.3

    3.3

    4.6

    6.8

    116

    233

    349

    466

    582

    698

    815

    931

    1048

    Ir.Wirastusrini,PE

    LOAD-SETT

    LEMENTS

    TIME-SETTLEMENTS

    Settlements(mm)

    LayerThickness(m)

    SettlementTime(years)

    SettlementsbyFill(mm)

    AverageLoad(kN/m

    2)

    61.53

    1164

    UnitWeight,

    (kN/m

    3)

    Approvedby

    Preparedby

    Checkedby

    Ir.Padmono,PE

    Ir.KabulS.MSC

    JobNo.

    2358

    16.5

    3.73

    AREASE

    TTLEMENTANALYSISBH-12

    PLATE1.1

    PT.SOILENS

    CIREBONTH

    ERMALPOWERPLANTPR

    OJECT

    0150

    300

    450

    600

    750

    900

    1050

    1200

    1350

    1500

    1650

    1800

    1950

    2100

    2250

    2400

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    11012

    0

    130

    FILLLOAD,kN/m

    2

    SETTLEMENTS,MM

    0 75 150

    225

    300

    375

    450

    525

    600

    675

    750

    825

    900

    975

    1050

    1125

    1200

    0.00

    0.60

    1.20

    1.80

    2.40

    3.00

    3.60

    4.20

    4.80

    5.40

    6.00

    6.60

    7.20

    TIME,Years

    SETTLEMENTS,MM

  • 7/24/2019 Cirebon Power Plant_R0

    28/213

    01

    577

    791

    577

    79

    0

    791

    577

    0.0

    0.1

    0.1

    0.2

    0.4

    0.5

    0.7

    1.0

    1.5

    158

    315

    473

    631

    789

    946

    1104

    1262

    1419

    Ir.Wirastusrini,PE

    LOAD-SETT

    LEMENTS

    TIME-SETTLEMENTS

    Settlements(mm)

    LayerThickness(m)

    SettlementTime(years)

    SettlementsbyFill(mm)

    AverageLoad(kN/m

    2)

    78.95

    1577

    UnitWeight,

    (kN/m

    3)

    Approvedby

    Preparedby

    Checkedby

    Ir.Padmono,PE

    Ir.KabulS.MSC

    JobNo.

    2358

    16.5

    4.79

    AREASE

    TTLEMENTANALYSISBH-13

    PLATE1.2

    PT.SOILENS

    CIREBONTH

    ERMALPOWERPLANTPR

    OJECT

    0200

    400

    600

    800

    1000

    1200

    1400

    1600

    1800

    2000

    2200

    2400

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    11012

    0

    130

    FILLLOAD,kN/m

    2

    SETTLEMENTS,MM

    0200

    400

    600

    800

    1000

    1200

    1400

    1600

    1800

    2000

    2200

    2400

    0.00

    0.20

    0.4

    0

    0.60

    0.80

    1.00

    1.20

    1.40

    1.60

    1.80

    2.00

    TIME,Years

    SETTLEMENTS,MM

  • 7/24/2019 Cirebon Power Plant_R0

    29/213

    01

    770

    801

    770

    80

    0

    801

    770

    0.1

    0.3

    0.7

    1.2

    1.9

    2.7

    3.9

    5.4

    8.1

    177

    354

    531

    708

    885

    1062

    1239

    1416

    1593

    Ir.Wirastusrini,PE

    LOAD-SETT

    LEMENTS

    TIME-SETTLEMENTS

    Settlements(mm)

    LayerThickness(m)

    SettlementTime(years)

    SettlementsbyFill(mm)

    AverageLoad(kN/m

    2)

    79.73

    1770

    UnitWeight,

    (kN/m

    3)

    Approvedby

    Preparedby

    Checkedby

    Ir.Padmono,PE

    Ir.KabulS.MSC

    JobNo.

    2358

    16.5

    4.83

    AREASE

    TTLEMENTANALYSISBH-14

    PLATE1.3

    PT.SOILENS

    CIREBONTH

    ERMALPOWERPLANTPR

    OJECT

    0200

    400

    600

    800

    1000

    1200

    1400

    1600

    1800

    2000

    2200

    2400

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    11012

    0

    130

    FILLLOAD,kN/m

    2

    SETTLEMENTS,MM

    0200

    400

    600

    800

    1000

    1200

    1400

    1600

    1800

    2000

    2200

    2400

    0.00

    1.00

    2

    .00

    3.00

    4.00

    5.00

    6.00

    7.00

    8.00

    9.00

    TIME,Years

    SETTLEMENTS,MM

  • 7/24/2019 Cirebon Power Plant_R0

    30/213

    01

    056

    601

    056

    60

    0

    601

    056

    0.0

    0.2

    0.4

    0.7

    1.1

    1.5

    2.2

    3.1

    4.6

    106

    211

    317

    422

    528

    634

    739

    845

    950

    Ir.Wirastusrini,PE

    LOAD-SETT

    LEMENTS

    TIME-SETTLEMENTS

    Settlements(mm)

    LayerThickness(m)

    SettlementTime(years)

    SettlementsbyFill(mm)

    AverageLoad(kN/m

    2)

    59.96

    1056

    UnitWeight,

    (kN/m

    3)

    Approvedby

    Preparedby

    Checkedby

    Ir.Padmono,PE

    Ir.KabulS.MSC

    JobNo.

    2358

    16.5

    3.63

    AREASE

    TTLEMENTANALYSISBH-15

    PLATE1.4

    PT.SOILENS

    CIREBONTH

    ERMALPOWERPLANTPR

    OJECT

    0200

    400

    600

    800

    1000

    1200

    1400

    1600

    1800

    2000

    2200

    2400

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    11012

    0

    130

    FILLLOAD,kN/m

    2

    SETTLEMENTS,MM

    0200

    400

    600

    800

    1000

    1200

    1400

    1600

    1800

    2000

    2200

    2400

    0.00

    0.50

    1.0

    0

    1.50

    2.00

    2.50

    3.00

    3.50

    4.00

    4.50

    5.00

    TIME,Years

    SETTLEMENTS,MM

  • 7/24/2019 Cirebon Power Plant_R0

    31/213

    01

    414

    741

    414

    74

    0

    741

    414

    0.1

    0.3

    0.6

    1.0

    1.6

    2.3

    3.3

    4.6

    6.9

    141

    283

    424

    566

    707

    848

    990

    1131

    1273

    Ir.Wirastusrini,PE

    LOAD-SETT

    LEMENTS

    TIME-SETTLEMENTS

    Settlements(mm)

    LayerThickness(m)

    SettlementTime(years)

    SettlementsbyFill(mm)

    AverageLoad(kN/m

    2)

    73.62

    1414

    UnitWeight,

    (kN/m

    3)

    Approvedby

    Preparedby

    Checkedby

    Ir.Padmono,PE

    Ir.KabulS.MSC

    JobNo.

    2358

    16.5

    4.46

    AREASE

    TTLEMENTANALYSISBH-16

    PLATE1.5

    PT.SOILENS

    CIREBONTH

    ERMALPOWERPLANTPR

    OJECT

    0200

    400

    600

    800

    1000

    1200

    1400

    1600

    1800

    2000

    2200

    2400

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    11012

    0

    130

    FILLLOAD,kN/m

    2

    SETTLEMENTS,MM

    0200

    400

    600

    800

    1000

    1200

    1400

    1600

    1800

    2000

    2200

    2400

    0.00

    0.75

    1.5

    0

    2.25

    3.00

    3.75

    4.50

    5.25

    6.00

    6.75

    7.50

    TIME,Years

    SETTLEMENTS,MM

  • 7/24/2019 Cirebon Power Plant_R0

    32/213

    01

    798

    741

    798

    74

    0

    741

    798

    0.0

    0.1

    0.2

    0.4

    0.5

    0.8

    1.1

    1.6

    2.4

    180

    360

    539

    719

    899

    1079

    1259

    1438

    1618

    AREASE

    TTLEMENTANALYSISBH-17

    PLATE1.6

    PT.SOILENS

    CIREBONTH

    ERMALPOWERPLANTPR

    OJECT

    UnitWeight,

    (kN/m

    3)

    Approvedby

    Preparedby

    Checkedby

    Ir.Padmono,PE

    Ir.KabulS.MSC

    JobNo.

    2358

    16.5

    4.46

    Ir.Wirastusrini,PE

    LOAD-SETT

    LEMENTS

    TIME-SETTLEMENTS

    Settlements(mm)

    LayerThickness(m)

    SettlementTime(years)

    SettlementsbyFill(mm)

    AverageLoad(kN/m

    2)

    73.56

    1798

    0200

    400

    600

    800

    1000

    1200

    1400

    1600

    1800

    2000

    2200

    2400

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    11012

    0

    130

    FILLLOAD,kN/m

    2

    SETTLEMENTS,MM

    0200

    400

    600

    800

    1000

    1200

    1400

    1600

    1800

    2000

    2200

    2400

    0.00

    0.25

    0.5

    0

    0.75

    1.00

    1.25

    1.50

    1.75

    2.00

    2.25

    2.50

    TIME,Years

    SETTLEMENTS,MM

  • 7/24/2019 Cirebon Power Plant_R0

    33/213

    0

    820

    77

    820

    77

    0

    77

    820

    0.1

    0.3

    0.7

    1.2

    1.9

    2.7

    3.9

    5.4

    8.1

    82

    164

    246

    328

    410

    492

    574

    656

    738

    Ir.Wirastusrini,PE

    LOAD-SETT

    LEMENTS

    TIME-SETTLEMENTS

    Settlements(mm)

    LayerThickness(m)

    SettlementTime(years)

    SettlementsbyFill(mm)

    AverageLoad(kN/m

    2)

    76.84

    820

    UnitWeight,

    (kN/m

    3)

    Approvedby

    Preparedby

    Checkedby

    Ir.Padmono,PE

    Ir.KabulS.MSC

    JobNo.

    2358

    16.5

    4.66

    AREASE

    TTLEMENTANALYSISBH-18

    PLATE1.7

    PT.SOILENS

    CIREBONTH

    ERMALPOWERPLANTPR

    OJECT

    0150

    300

    450

    600

    750

    900

    1050

    1200

    1350

    1500

    1650

    1800

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    11012

    0

    130

    FILLLOAD,kN/m

    2

    SETTLEMENTS,MM

    0150

    300

    450

    600

    750

    900

    1050

    1200

    1350

    1500

    1650

    1800

    0.00

    0.80

    1.60

    2.40

    3.20

    4.00

    4.80

    5.60

    6.40

    7.20

    8.00

    8.80

    TIME,Years

    SETTLEMENTS,MM

  • 7/24/2019 Cirebon Power Plant_R0

    34/213

    0

    754

    80

    754

    80

    0

    80

    754

    0.1

    0.2

    0.5

    0.8

    1.3

    1.9

    2.7

    3.8

    5.7

    75

    151

    226

    302

    377

    452

    528

    603

    679

    Ir.Wirastusrini,PE

    LOAD-SETT

    LEMENTS

    TIME-SETTLEMENTS

    Settlements(mm)

    LayerThickness(m)

    SettlementTime(years)

    SettlementsbyFill(mm)

    AverageLoad(kN/m

    2)

    80.37

    754

    UnitWeight,

    (kN/m

    3)

    Approvedby

    Preparedby

    Checkedby

    Ir.Padmono,PE

    Ir.KabulS.MSC

    JobNo.

    2358

    16.5

    4.87

    AREASE

    TTLEMENTANALYSISBH-19

    PLATE1.8

    PT.SOILENS

    CIREBONTH

    ERMALPOWERPLANTPR

    OJECT

    0100

    200

    300

    400

    500

    600

    700

    800

    900

    1000

    1100

    1200

    1300

    1400

    1500

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    11012

    0

    130

    FILLLOAD,kN/m

    2

    SETTLEMENTS,MM

    0100

    200

    300

    400

    500

    600

    700

    800

    900

    1000

    1100

    1200

    1300

    1400

    1500

    0.00

    0.60

    1.2

    0

    1.80

    2.40

    3.00

    3.60

    4.20

    4.80

    5.40

    6.00

    TIME,Years

    SETTLEMENTS,MM

  • 7/24/2019 Cirebon Power Plant_R0

    35/213

    01

    209

    791

    209

    79

    0

    791

    209

    0.1

    0.3

    0.7

    1.2

    1.9

    2.7

    3.9

    5.4

    8.1

    121

    242

    363

    484

    605

    725

    846

    967

    1088

    Ir.Wirastusrini,PE

    LOAD-SETT

    LEMENTS

    TIME-SETTLEMENTS

    Settlements(mm)

    LayerThickness(m)

    SettlementTime(years)

    SettlementsbyFill(mm)

    AverageLoad(kN/m

    2)

    78.97

    1209

    UnitWeight,

    (kN/m

    3)

    Approvedby

    Preparedby

    Checkedby

    Ir.Padmono,PE

    Ir.KabulS.MSC

    JobNo.

    2358

    16.5

    4.79

    AREASE

    TTLEMENTANALYSISBH-20

    PLATE1.9

    PT.SOILENS

    CIREBONTH

    ERMALPOWERPLANTPR

    OJECT

    0200

    400

    600

    800

    1000

    1200

    1400

    1600

    1800

    2000

    2200

    2400

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    11012

    0

    130

    FILLLOAD,kN/m

    2

    SETTLEMENTS,MM

    0200

    400

    600

    800

    1000

    1200

    1400

    1600

    1800

    2000

    2200

    2400

    0.00

    0.80

    1.60

    2.40

    3.20

    4.00

    4.80

    5.60

    6.40

    7.20

    8.00

    8.80

    TIME,Years

    SETTLEMENTS,MM

  • 7/24/2019 Cirebon Power Plant_R0

    36/213

    01

    323

    781

    323

    78

    0

    781

    323

    0.1

    0.2

    0.5

    0.8

    1.3

    1.9

    2.7

    3.8

    5.7

    132

    265

    397

    529

    662

    794

    926

    1058

    1191

    Ir.Wirastusrini,PE

    LOAD-SETT

    LEMENTS

    TIME-SETTLEMENTS

    Settlements(mm)

    LayerThickness(m)

    SettlementTime(years)

    SettlementsbyFill(mm)

    AverageLoad(kN/m

    2)

    78.06

    1323

    UnitWeight,

    (kN/m

    3)

    Approvedby

    Preparedby

    Checkedby

    Ir.Padmono,PE

    Ir.KabulS.MSC

    JobNo.

    2358

    16.5

    4.73

    AREASE

    TTLEMENTANALYSISBH-21

    PLATE1.10

    PT.SOILENS

    CIREBONTH

    ERMALPOWERPLANTPR

    OJECT

    0200

    400

    600

    800

    1000

    1200

    1400

    1600

    1800

    2000

    2200

    2400

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    11012

    0

    130

    FILLLOAD,kN/m

    2

    SETTLEMENTS,MM

    0200

    400

    600

    800

    1000

    1200

    1400

    1600

    1800

    2000

    2200

    2400

    0.00

    0.60

    1.2

    0

    1.80

    2.40

    3.00

    3.60

    4.20

    4.80

    5.40

    6.00

    TIME,Years

    SETTLEMENTS,MM

  • 7/24/2019 Cirebon Power Plant_R0

    37/213

    01

    198

    771

    198

    77

    0

    771

    198

    0.1

    0.2

    0.5

    0.8

    1.3

    1.9

    2.7

    3.8

    5.7

    120

    240

    359

    479

    599

    719

    839

    958

    1078

    Ir.Wirastusrini,PE

    LOAD-SETT

    LEMENTS

    TIME-SETTLEMENTS

    Settlements(mm)

    LayerThickness(m)

    SettlementTime(years)

    SettlementsbyFill(mm)

    AverageLoad(kN/m

    2)

    77.29

    1198

    UnitWeight,

    (kN/m

    3)

    Approvedby

    Preparedby

    Checkedby

    Ir.Padmono,PE

    Ir.KabulS.MSC

    JobNo.

    2358

    16.5

    4.68

    AREASE

    TTLEMENTANALYSISBH-22

    PLATE1.11

    PT.SOILENS

    CIREBONTH

    ERMALPOWERPLANTPR

    OJECT

    0150

    300

    450

    600

    750

    900

    1050

    1200

    1350

    1500

    1650

    1800

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    11012

    0

    130

    FILLLOAD,kN/m

    2

    SETTLEMENTS,MM

    0150

    300

    450

    600

    750

    900

    1050

    1200

    1350

    1500

    1650

    1800

    0.00

    0.60

    1.2

    0

    1.80

    2.40

    3.00

    3.60

    4.20

    4.80

    5.40

    6.00

    TIME,Years

    SETTLEMENTS,MM

  • 7/24/2019 Cirebon Power Plant_R0

    38/213

    01

    169

    701

    169

    70

    0

    701

    169

    0.1

    0.2

    0.5

    0.8

    1.3

    1.9

    2.7

    3.8

    5.7

    117

    234

    351

    468

    585

    701

    818

    935

    1052

    Ir.Wirastusrini,PE

    LOAD-SETT

    LEMENTS

    TIME-SETTLEMENTS

    Settlements(mm)

    LayerThickness(m)

    SettlementTime(years)

    SettlementsbyFill(mm)

    AverageLoad(kN/m

    2)

    70.08

    1169

    UnitWeight,

    (kN/m

    3)

    Approvedby

    Preparedby

    Checkedby

    Ir.Padmono,PE

    Ir.KabulS.MSC

    JobNo.

    2358

    16.5

    4.25

    AREASE

    TTLEMENTANALYSISBH-23

    PLATE1.12

    PT.SOILENS

    CIREBONTH

    ERMALPOWERPLANTPR

    OJECT

    0200

    400

    600

    800

    1000

    1200

    1400

    1600

    1800

    2000

    2200

    2400

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    11012

    0

    130

    FILLLOAD,kN/m

    2

    SETTLEMENTS,MM

    0200

    400

    600

    800

    1000

    1200

    1400

    1600

    1800

    2000

    2200

    2400

    0.00

    0.60

    1.2

    0

    1.80

    2.40

    3.00

    3.60

    4.20

    4.80

    5.40

    6.00

    TIME,Years

    SETTLEMENTS,MM

  • 7/24/2019 Cirebon Power Plant_R0

    39/213

    01

    782

    661

    782

    66

    0

    661

    782

    0.0

    0.2

    0.4

    0.7

    1.1

    1.5

    2.2

    3.1

    4.6

    178

    356

    535

    713

    891

    1069

    1247

    1426

    1604

    AREASE

    TTLEMENTANALYSISBH-24

    PLATE1.13

    PT.SOILENS

    CIREBONTH

    ERMALPOWERPLANTPR

    OJECT

    UnitWeight,

    (kN/m

    3)

    Approvedby

    Preparedby

    Checkedby

    Ir.Padmono,PE

    Ir.KabulS.MSC

    JobNo.

    2358

    16

    4.15

    Ir.Wirastusrini,PE

    LOAD-SETT

    LEMENTS

    TIME-SETTLEMENTS

    Settlements(mm)

    LayerThickness(m)

    SettlementTime(years)

    SettlementsbyFill(mm)

    AverageLoad(kN/m

    2)

    66.38

    1782

    0200

    400

    600

    800

    1000

    1200

    1400

    1600

    1800

    2000

    2200

    2400

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    110

    120

    FILLLOAD,kN/m

    2

    SETTLEMENTS,MM

    0200

    400

    600

    800

    1000

    1200

    1400

    1600

    1800

    2000

    2200

    2400

    0.00

    0.60

    1

    .20

    1.80

    2.40

    3.00

    3.60

    4.20

    4.80

    5.40

    TIME,Years

    SETTLEMENTS,MM

  • 7/24/2019 Cirebon Power Plant_R0

    40/213

    01

    033

    781

    033

    78

    0

    781

    033

    0.0

    0.1

    0.3

    0.6

    0.9

    1.3

    1.8

    2.5

    3.8

    103

    207

    310

    413

    517

    620

    723

    826

    930

    AREASE

    TTLEMENTANALYSISBH-25

    PLATE1.14

    PT.SOILENS

    CIREBONTH

    ERMALPOWERPLANTPR

    OJECT

    UnitWeight,

    (kN/m

    3)

    Approvedby

    Preparedby

    Checkedby

    Ir.Padmono,PE

    Ir.KabulS.MSC

    JobNo.

    2358

    16.5

    4.71

    Ir.Wirastusrini,PE

    LOAD-SETT

    LEMENTS

    TIME-SETTLEMENTS

    Settlements(mm)

    LayerThickness(m)

    SettlementTime(years)

    SettlementsbyFill(mm)

    AverageLoad(kN/m

    2)

    77.76

    1033

    0200

    400

    600

    800

    1000

    1200

    1400

    1600

    1800

    2000

    2200

    2400

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    11012

    0

    130

    FILLLOAD,kN/m

    2

    SETTLEMENTS,MM

    0200

    400

    600

    800

    1000

    1200

    1400

    1600

    1800

    2000

    2200

    2400

    0.00

    0.40

    0.8

    0

    1.20

    1.60

    2.00

    2.40

    2.80

    3.20

    3.60

    4.00

    TIME,Years

    SETTLEMENTS,MM

  • 7/24/2019 Cirebon Power Plant_R0

    41/213

    0

    915

    71

    915

    71

    0

    71

    915

    0.1

    0.2

    0.5

    0.9

    1.4

    2.0

    2.9

    4.0

    6.0

    92

    183

    275

    366

    458

    549

    641

    732

    824

    AREASE

    TTLEMENTANALYSISBH-26

    PLATE1.15

    PT.SOILENS

    CIREBONTH

    ERMALPOWERPLANTPR

    OJECT

    UnitWeight,

    (kN/m

    3)

    Approvedby

    Preparedby

    Checkedby

    Ir.Padmono,PE

    Ir.KabulS.MSC

    JobNo.

    2358

    16.5

    4.32

    Ir.Wirastusrini,PE

    LOAD-SETT

    LEMENTS

    TIME-SETTLEMENTS

    Settlements(mm)

    LayerThickness(m)

    SettlementTime(years)

    SettlementsbyFill(mm)

    AverageLoad(kN/m

    2)

    71.23

    915

    0150

    300

    450

    600

    750

    900

    1050

    1200

    1350

    1500

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    11012

    0

    130

    FILLLOAD,kN/m

    2

    SETTLEMENTS,MM

    0150

    300

    450

    600

    750

    900

    1050

    1200

    1350

    1500

    0.00

    0.60

    1.20

    1.80

    2.40

    3.00

    3.60

    4.20

    4.80

    5.40

    6.00

    6.60

    TIME,Years

    SETTLEMENTS,MM

  • 7/24/2019 Cirebon Power Plant_R0

    42/213

    Input

    C h

    2.9

    E-07m/s=

    9.1

    5m/yearCoff.ofconsolid

    ationforhorizontalflow

    ToactivateIterationgotothemenu

    T

    120days=

    1.0E

    +07sec.

    Consolidationtime

    extra

    options

    calculation

    d

    0.0

    65m

    65mm

    Theequivalentdiameter

    andactivateiteratio

    U h

    0.9

    5ratio

    95%

    Degreeofconsolidationrequired

    t

    12.0

    0m

    Draindepth

    A

    10,0

    00m

    Area

    Outputm

    1.

    77

    D

    1.7

    7

    m

    4,0

    52

    Numberofdrains

    D D

    1.6

    9

    m

    48,6

    19m

    Totalamount

    D

    1.5

    7

    m

    U

    t(days)

    0%

    0

    10%

    4

    20%

    9

    30%

    14

    40%

    20

    50%

    28

    60%

    37

    70%

    48

    80%

    64

    90%

    92

    99%

    184

    Calculationprogramf

    ord

    eterminingdraindistanceaccordingBarron

    Triangularpattern

    Squarepattern

    Draininflu

    encezone

    PT.SOILENS

    PLATE2.1

    2358

    PadmonoPE

    KabulS.MSCE

    WirastusriniPE

    CIREBONTHERMALPOWERPLANTPROJECT,W

    ESTJAVA

    DRAINSPACINGCALC

    ULATIONFORDETERMININGDRAINDISTANCE

    JobNo

    Preparedby

    Checkedby

    Approvedby

    0.00.10.20.30.40.50.60.70.80.91.0 0

    14

    28

    42

    56

    70

    84

    98

    112

    126

    140

    154

    168

    182

    196

    210

    224

    238

    252

    266

    280

    Times(days)

    ConsolidationDegree,%

  • 7/24/2019 Cirebon Power Plant_R0

    43/213

    CheckedbyK

    abulS,

    MSCE

    PLATE2.2

    ApprovedbyW

    irastusrini,PE

    DRAINSPACINGvs

    TIMEREQUIREDTOREACH95%

    SETTLEMENTS

    JobNo.

    2358

    PT.SOILENS

    PreparedbyP

    admono,P

    E

    CIREBONTHERMA

    LPOWERPLANTPROJECT,

    WESTJAVA

    0.00

    0.25

    0.50

    0.75

    1.00

    1.25

    1.50

    1.75

    2.00

    2.25

    2.50

    2.75

    3.00