Upload
teguh-wiradinata
View
215
Download
0
Embed Size (px)
Citation preview
7/24/2019 Cirebon Power Plant_R0
1/213
JOB NO. 2338
CIREBON ELECTRIC POWER PT
J A K A R T A
SOIL INVESTIGATION
FOR
POWER BLOCK AREA
CIREBON THERMAL POWER PLANT PROJECT
CIREBON, WEST JAVA
I N D O N E S I A
FINAL REPORT
AUGUST 2007
01 10/08/2007 All Issued Final Report, R0 Ir. Padmono, PE Ir.Iman Mulyana Ir.Wirastusrini, PE
No Date Page Description Prepared by Checked by Approved by
7/24/2019 Cirebon Power Plant_R0
2/213
Final Report, Part I : Power Block Area Revision-00
Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007For Cirebon Electric Power PT, Jakarta Job No. 2350
PT. Soilens, Bandung Page i
TABLE OF CONTENTS
Cover
Executive Summary
Table of Contents.......i
1 INTRODUCTION..1
2 SCOPE AND PURPOSE.......1
3 FIELD INVESTIGATIONS...............1
3.1.Drillings...........1
3.2.Standard Penetration Tests......2
3.3.Undisturbed Samplings.......2
3.4.Water Level Observations.......2
3.5.Dutch Cone Penetration Test......2
3.6.Coordinate and Elevation of the Investigated Points.........3
4 SUBSURFACE CONDITIONS.............3
4.1.Geology...3
4.2.Seismicity............4
4.3.Stratigraphy.........4
4.4.Soil Profile based on the UBC 1997.......6
5 LABORATORY TESTING...........6
5.1.Description of Test..........6
5.2.Engineering Properties of the Undisturbed Samples......6
5.2.1. Physical Properties......6
5.2.2. Strength Parameters.....8
5.2.3. Compressibility Characteristics...........8
6 ANALYSIS AND RECOMMENDATIONS...............9
6.1.Plant Site Preparation............9
6.1.1.Areal Fill..........96.1.2.Areal Settlements.....9
6.1.3.Vertical Drain and Deep Mixing...........11
6.1.4.Provisions Against Secondary Settlement.11
6.2.Liquefaction........11
6.2.1. General .......11
6.2.2. Liquefaction Analysis.11
6.2.3. Results of Analysis......12
6.3.Foundations.....12
6.3.1. General Foundation Criteria........136.3.2. Shallow Foundation....13
7/24/2019 Cirebon Power Plant_R0
3/213
Final Report, Part I : Power Block Revision-00
Cirebon Thermal Power Plant Project, Cirebon, West Java August, 2007For Cirebon Electeric Power PT, Jakarta Job No. 2340
PT. Soilens, Bandung Page ii
TABLE OF CONTENTS
6.3.3. Deep Foundation.....13
6.3.3.1. Axially Loaded PC-Piles...14
6.3.3.2.Negative Skin Friction on Piles....14
6.3.3.3. Laterally Loaded Piles..15
6.3.3.4. Allowable Pile Capacity...15
6.3.3.5. Pile Spacing..16
6.3.3.6. Pile Driving Procedures .......16
6.3.3.7. Full Scale Vertical Pile Loading Test.......17
6.3.3.8. Lateral Load Test......196.3.3.9. Pile Dynamic Analyzer (PDA) Test.....19
6.4. Chemical Properties of Water Samples..........21
6.5. Hydrology...........22
6.6. Inspection and Monitoring......22
Plates :
PLATE 1.1 to PLATE 1.15 : Areal Settlements Analysis
PLATE 2.1 to PLATE 2.2 : Vertical Drain Calculation and Spacing
PLATE 3.1 to PLATE 3.13 : Liquefaction Analysis
PLATE 4.1 to PLATE 4.15 : Axial Spun Presstresed Concrete Pile Capacity
PLATE 5.1 to PLATE 5.5 : Lateral Pile Capacity Curves Pinned Pile Head
PLATE 6.1 to PLATE 6.5 : Lateral Pile Capacity Curves Fixed Pile Head
PLATE 7.1 to PLATE 7.5 : Lateral Pile Response Pinned Pile Head
PLATE 8.1 to PLATE 8.5 : Lateral Pile Response Fixed Pile Head
PLATE 9.1 to PLATE 9.3 : Allowable PC Pile Capacity
Appendices:
Appendix A.1 : Project Location Map
Appendix A.2 : Boring Log
Appendix A.3 : Graph of 2 ton DCPTAppendix A.4 : Map of Seismic Risk Zones of Indonesia
Appendix A.5 : General Cross Section
Appendix B.1 : Laboratory Test Table
Appendix B.2 : Consolidation Curves
Appendix B.3 : Unconsolidated Undrained Triaxial Test
Appendix B.4 : Consolidated Undrained Triaxial Test
Appendix B.5 : Grainsize Analysis
7/24/2019 Cirebon Power Plant_R0
4/213
Final Report, Part I : Power Block Revision-00
Cirebon Thermal Power Plant Project, Cirebon, West Java August, 2007For Cirebon Electeric Power PT, Jakarta Job No. 2340
PT. Soilens, Bandung Page iii
TABLE OF CONTENTS
Appendix C.1 : Term and SymbolsAppendix C.2 : Equipment and Procedures
Appendix C.3 : Conversion Factors
Appendix C.4 : Analytical Procedures
7/24/2019 Cirebon Power Plant_R0
5/213
Final Report, Part I : Power Block Area Revision-00
Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007
For Cirebon Electric Power PT, Jakarta Job No. 2350
PT. Soilens, Bandung Page 1
1. INTRODUCTION
This geotechnical engineering report is carried out by PT. Soilens for Cirebon Electric
Power PT. It contains the discussion on engineering properties of the groundrecommendations of foundations system and solution of the anticipated geotechnical
problem for the Power Block area as part of Cirebon Power Plant Project.
This final report presents a comprehensive sub-surface information of the proposed plant
site and a geotechnical assessment for the site preparation, and foundation of variousstructures to be constructed. This includes analyses of areal settlements, soil improvement,
liquefaction analysis, deep pile foundation and other relevant information for design of the
proposed plant.
The analysis of axial compressive and tension pile capacities were performed using
PLEAXI computer program. The analysis of lateral pile capacities were performed using
Lpile Plus V5 computer program based on p-y method.
This work is carried out under the PO No.: 7017-CI-004 dated June 28, 2007 from
Cirebon Electric Power PT. to PT.SOILENS.
2 SCOPE AND PURPOSE
The purpose of the investigation is to explore the soil at the proposed plant site and toprovide recommendations in relation to the foundation design. The scope of the
investigations included:
(1) Soil drilling of 15 points, with a total depth of 480 m, performing standard
penetration test, collecting undisturbed samples, and continuous coring.(2) Performing Dutch Cone Penetration Test of 2 ton capacity at 8 points(3) A laboratory testing program on undisturbed and disturbed samples to evaluate the
engineering characteristics of the sub surface strata encountered.
(4) Performing engineering analysis to evaluate and to provide site specific geotechnicalinformation, should include recommendation on most suitable foundation type for
each facility, recommendation on soil improvement, area settlement and others.However, detail analysis and calculations of foundation design in relation to the
foundation arrangement and configuration, and working load is beyond the scope of
works of this report.
The lay-out of the project and the location of the investigated points are shown in
Appendix A.1.
3 FIELD INVESTIGATIONS
3.1 Drillings
The field investigations were carried out by a team consisting of Iman Mulyana as TeamLeader, Ujang, Mamay, Omay, E. Slamet, Unang M, Iyang as Drilling Master, Untung as
CPT Master and Arif S. as Assistant Geologist.
The drillings were carried out using 6 (six) Long Year drilling machine with Long Year
535-RQ pumping unit. The bore holes were advanced by continuous coring using NX-
size, single tube core barrels apparatus with outer diameter of 73 mm. All drillings weresupervised by the Assistant Geologist, who also maintained a continuous logging on the
7/24/2019 Cirebon Power Plant_R0
6/213
Final Report, Part I : Power Block Area Revision-00
Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007
For Cirebon Electric Power PT, Jakarta Job No. 2350
PT. SOILENS, Bandung Page 2
core samples. These core samples were placed in wooden boxes, each containing 5 meterlong of samples, and stored at the site. The undisturbed soil samples were carried out on
cohesive soil at approximately 5 meter interval or at every change in soil layer.
The detailed classification of the soil samples after refinements in relation to the laboratorytest results are presented in boring logs included in Appendix A.2.
The information on the logs also includes the field test results and locations of samples.The samples were brought to PT.SOILENS Soil Laboratory in Bandung where the tests
were performed.
3.2 Standard Penetration Tests (SPT)
The standard penetration test was performed in accordance to the ASTM Standard method
D1586. The test consists of driving a standard split spoon sampler into the soil at requireddepth in a bore hole.
A hammer of 63.5 kg weight falling freely from a height of 75 cm on the drill rod is used
to drive the sampler. The number of hammer blows to drive the second and the third 15 cmof penetration are called the SPT N-value which represents the number of blows per 30 cm
of penetration. The standard penetration test was performed at 2.0 meter interval. Inaddition, pocket penetrometer tests were also performed on cohesive soil samples that
indicated plastic behavior. The SPT results presented in the boring log enclosed in this
report.
3.3 Undisturbed Samplings
The undisturbed samples were taken from cohesive soil at depth interval of approximately
5 meters. This is done by taking samples from bore hole by means of seamless thin walledsteel tube commonly known as shelby tube.
The tube is 76.2 mm in diameter and has beveled butting edge at the lower end. It isconnected to the drill rod and pushed by static force into the bottom of the hole. When the
tube is almost full, it is withdrawn from the hole, removed from the drill rod, sealed at bothends with paraffin, and shipped to PT. Soilens soil laboratory in Bandung for testing.
When ready for test, the samples are ejected from the tubes cut into required length and
subjected to various laboratory tests.
3.4 Water Level Observations
The elevation of ground water level in the bore holes varies from 0.85 to 0.90 m below theexisting ground surface. The ground water level in each bore hole was recorded every
morning and evening, 24 hours after completion of the drilling through the end of the
whole field work. Table 1 shows the water level elevation in each borehole.
The ground water conditions observed during drilling may not represent the groundwater
conditions during construction. The ground water conditions will fluctuate with wet anddry seasonal. We recommend that the water levels be verified just before construction.
3.5 Dutch Cone Penetration Test
One unit of 2-ton capacity Dutch Cone Penetration Test equipment with accessories wasused for the sounding test at site. The test was carried out in accordance with the ASTM D
3441. The cone penetration test consists of pushing into the soil, at a sufficiently slow rate,
7/24/2019 Cirebon Power Plant_R0
7/213
Final Report, Part I : Power Block Area Revision-00
Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007
For Cirebon Electric Power PT, Jakarta Job No. 2350
PT. SOILENS, Bandung Page 3
a series of cylindrical rods with a beconus at the base for measuring the cone resistance andfriction resistance every 20 cm intervals.
The results of cone and friction resistance then plotted on a graph, showing the variation
with depth of cone resistance, ratio of local friction to cone resistance and total friction.The tests results are presented in Appendix A.3.
Based on the test results, cone and total resistance of 1000 kg/cm2were achieved at depthsof 18.60 meter to 19.60 meter, respectively, from the existing ground surface.
3.6 Coordinate and Elevation of the Investigated Points
The coordinates and elevations of the investigated pointa are listed in Table 1. Theinvestigated point positions were determined using an existing Benchmark as the
reference.
Table 1 : Coordinates and elevations of the investi gated points
Coordinate
NoInvestigated
PointEast North
Elevation
(m)
Depth
(m)
Depth to
ground waterlevel
(m)1 BH-12 236341.460 9251052.930 +1.271 30.45 1.20
2 BH-13 236372.437 9250950.349 +0.215 30.45 0.50
3 BH-14 236423.346 9251056.548 +0.168 30.45 1.05
4 BH-15 236348.007 9251021.005 +1.366 30.45 1.00
5 BH-16 236364.924 9250977.719 +0.538 45.45 1.30
6 BH-17 236381.312 9250984.099 +0.542 30.45 0.607 BH-18 236463.391 9251046.875 +0.343 30.45 0.70
8 BH-19 236471.427 9251026.786 +0.129 30.45 0.50
9 BH-20 236483.486 9251054.908 +0.214 30.45 0.60
10 BH-21 236491.524 9251034.819 +0.269 30.00 1.40
11 BH-22 236501.668 9251076.970 +0.316 30.45 1.50
12 BH-23 236520.071 9251030.966 +0.753 30.45 1.43
13 BH-24 236531.464 9251081.660 +0.851 30.45 0.75
14 BH-25 236483.989 9251018.008 +0.287 30.45 -
15 BH-26 236525.001 9251052.003 +0.683 45.45 0.80
16 CPT-21 236441.635 9251010.844 +0.312 14.60
17 CPT-22 236421.819 9251031.058 +0.154 11.60
18 CPT-23 236388.279 9250994.324 +1.251 12.80
19 CPT-24 236483.486 9251054.908 +0.214 12.60
20 CPT-25 236526.253 9251060.528 +0.552 11.40
21 CPT-26 236531.564 9251081.660 +0.851 12.20
22 CPT-27 236552.636 9251024.704 +0.843 12.80
23 CPT-28 236571.259 9251066.558 +0.894 12.40
24 CPT-31 236471.424 9251110.377 +0.284 15.40
4. SUBSURFACE CONDITIONS
4.1 Geology
Generally, the project site lies on the Alluvial Formations, consisting of homogeneous orinterlaminated fined grained soils, mainly clays and silts, intercalated with coarse grained
7/24/2019 Cirebon Power Plant_R0
8/213
Final Report, Part I : Power Block Area Revision-00
Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007
For Cirebon Electric Power PT, Jakarta Job No. 2350
PT. SOILENS, Bandung Page 4
soils of fine to medium grained sands and occasionally coarse grained sands and gravels.This Alluvial Formation is unconformably underlain by the Undifferentiated Young
Volcanic Product Formation, comprising of fine to coarse grained volcanistic materials
(Achdan et.al & Djuri, GRDC 1992 & 1995)
The flat to lowland topography (not elevated level terrain) of the project site indicates the
presence of reworked sedimentrary soils due to the Holocene (thousands year ago) Recent stream action, introduced principally by the Cimanuk River. The coarse grained
soils are generally uncemented (occasionally very weak or slightly cemented) sedimentary
rounded-altered fragments, derived from the pre-existing Undifferentiated Young ProductFormation
4.2 Seismicity
The purpose of study on seismic risk of the project site, was performed based on the
following references :
( 1 ) Seismic Zones for building construction, Beca Carter Holling & Ferner Ltd. andthe Indonesian Counterpart Team, New Zealand Steering Committee, Vol 2 & 3,
1987.( 2 ) Kertapati E.K. et al., Earthquake Ground Shaking Hazard Map of Indonesia, scale
1 : 5.000.000, 1999.
( 3 ) Standar Nasional Indonesia, SNI 03-1723-2002, Tata cara perencanaan ketahanangempa untuk bangunan gedung, BSN.
( 4 ) Preliminary Map of Seismic Risk Zones of Indonesia, compiled by PT. SOILENS(August 30, 2005), scale : 1 : 5.000.000.
Referring to the the above reference the site is located in the zone with a base rock max.
horizontal acceleration of 0.10 g for 500-year return period earthquakes. The seismicoccurrence risk is considered by the following expression :
N
TNT
R )1
1(1, = ..(1)
Where:
RN,T = Seismic occurrence risk
N = the life time of the structures, years
T = earthquake mean return period, years
For earthquake mean return period of 500 years and building life time of 50 years, the
anticipated occurrence risk is approximately 10 %. The map of Seismic zone of Indonesiapresented in Appendix A.4
4.3 Stratigraphy
The conditions of the subsurface soils in the project site was determined from visualdescription of the core samples, SPT N-values, laboratory tests and CTP. The lateral and
vertical extents of the soil stratum was deduced from subsurface cross sections made fromthe boring and CPT log as shown in Appendix A.5 thus the stratigraphy may not be
accurate in between the boreholes or CPT points.
As shown in the soil sections, the subsurface soil is found to be generally discontinuous inlateral extend and with irregular shapes extending throughout the project site. The subsoil
7/24/2019 Cirebon Power Plant_R0
9/213
Final Report, Part I : Power Block Area Revision-00
Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007
For Cirebon Electric Power PT, Jakarta Job No. 2350
PT. SOILENS, Bandung Page 5
at the site can be classified into 4 (four) unit based on the physical appearance andengineering properties:
(1) Layer-1 : Very soft to soft of Clay or Silty Clay, with SPT N-values of less than
1 to 5(2) Layer-2 : Medium stiff to very stiff Clay or Silty Clay, with SPT N-values of >5
to 30(3) Layer-3 : Medium dense to dense Sand or Silty Sand, with SPT N-values of more
than 30
The description and the distribution of the above Unit are briefed as below:
(a) Layer-1
The subsoil in the upper unit is the top soil that consisted of cohesive soil of clay/silty claylayer. The top soil is distributed almost of all over the site and was confirmed in all the
exploratory boreholes and CPT sounding as shown in the soil profiles.
The colors of the upper unit are grey to brownish grey, high plasticity. The consistency isvery soft to soft, with SPT N-value of less than 1 to 5, average of 2. The thickness of
Layer-1varies from 8 to 14 m.
(b) Layer-2
Layer-2consists of clay/silt and sand layer, of low to high plasticity. The thickness of this
layer is vary from 3 m to 14 m. This unit is brownish grey to blackish grey in color. SPTN-values vary from >5 to 30, average of 16.
(c)
Layer-3
Layer-3 consisted of Clay/Silty Clay/Silty Sand of 3 to 20 m in thickness. The color of
this layer is brownish grey to blackish grey. The SPT N-values of this layer vary from 30
to 81, average of 40.
4.4 Soil Profile Based on The UBC 1997
The Uniform Building Code (UBC) 1997 classifies soil profile for earthquake design into 6types as follows:
Table 2: Soil Profile based on UBC 1997AVERAGE SOIL PROPERTIES FOR TOP 100 FEET (3048 MM) OF SOIL
PROFILESOIL
PROFILE
TYPE
SOIL PROFILENAME/GENERIC
DESCRIPTIONShear wave Velocity, Vs,
(m/s)
Standard Penetration
Test, N (or Nchforcohessionless soil
layers), (blows/foot)
Undrained Shear
Strength, Su, (kPa)
SA Hard Rock >5,000
SB Rock 760 to 1,500- -
SCVery Dense Soil
and Soft Rock360 to 760 >50 100
SD Stiff Soil Profile 180 to 360 15 to 50 50 to 100SE
1 Soft Soil Profile
7/24/2019 Cirebon Power Plant_R0
10/213
Final Report, Part I : Power Block Area Revision-00
Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007
For Cirebon Electric Power PT, Jakarta Job No. 2350
PT. SOILENS, Bandung Page 6
The top layer consist of more than 30 m of soft clay with PI>20, wn >40 percent andaverage undrained shear strength (su) 99 kPa. The soil profile type SEor stif f Soil Profile
can thus be classified for this site based on UBC 1997.
5. LABORATORY TESTING
5.1 Description of Tests
Selected samples were tested to determine the classification and engineering characteristicsof the soil. All tests were performed in accordance to relevant ASTM standards.
The laboratory testing program was formulated with the following objectives in mind :
To provide data so that soil deposits may be adequately identified and classified.These also provide means of correlation with strength parameters resulting in a better
understanding of the physical behavior of the soils and facilitate the choice of design
parameters. To obtain relevant strength data to form the basis for foundation design, etc.
The laboratory test on undisturbed soil samples included the followings:
1. Index Properties Test:
Bulk and dry density (ASTM D1557) Water content (ASTM D2216)
Specific gravity (ASTM C127)
Atterberg limit (ASTM D4318) Sieve and hydrometer (ASTM D2487)
Porosity and void ratio (ASTM D2216)
2. Mechanical Properties Tests:
Unconsolidated undrained triaxial test (ASTM D2850)
Consolidation test (ASTM D2435) Unconfined compression test (ASTM D2166)
The results of laboratory tests are presented in Appendix B. Selected properties andparameters are discussed in the following paragraphs.
5.2 Engineering Properties of the Undisturbed Samples
The engineering properties of the subsoil were interpreted from results of the laboratorysoil test and are summarized in Appendix B. The following sections discuss the
engineering properties of each unit as introduced in Section 4.3
5.2.1 Physical Properties
(a) Layer-1
Layer-1 in general consisted of very soft clay layer. The bulk densities (m) vary from 24.1
to 27.5 kN/m3, and dry densities (d) vary from 6.4 to 13.8 kN/m3, which is a normal range
for clay.
7/24/2019 Cirebon Power Plant_R0
11/213
Final Report, Part I : Power Block Area Revision-00
Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007
For Cirebon Electric Power PT, Jakarta Job No. 2350
PT. SOILENS, Bandung Page 7
The natural moisture water contents of the Layer-1 are generally in the range of 35 % to115 %. The majority of the moisture water contents are relatively closed to their liquid
limits indicating normaly consolidated of very soft to very soft clay.
The plasticity index and liquid limits of this unit indicate that the majority of the subsoilcan be classified as high plasticity clay (CH) according ASTM standard. The large clay
content in soil passing No. 200 sieve was believed as the main reason for high liquidlimits. The liquid limits of the Layer-1 vary from 37 to 124 % thus classify the clay as
high plasticity.
The index properties and grain size distribution of Layer-1are summarized below with theaverage values in the bracket:
Natural water content, % 35 115 (63)
Liquid limit, % 37 124 (82)
Plastic limit, % 20 43 (33) Plasticity index, % 15 83 (48)
Bulk density, kN/m3 13.8 18.6 (16.1)
Grainsize distribution:
Gravel, % 0 12
Sand, % 0 70 (20)
Silt, % 12 41(23)
Clay, % 15 84 (56)
(b)Layer-2
Layer-2consist of clay, and silt layers. The bulk densities of this unit vary from 16.5 to18.0 kN/m3, and dry densities vary from 10.5 to 13.2 kN/m3. Its natural moisture water
contents generally fall in the range of 37 % to 58 %.
The plasticity index and liquid limits of this unit indicate that the majority of the subsoil
can be classified as clay (CH) or Silt (MH) according ASTM standard. The large claycontent in soil passing No. 200 sieve was believed as the main reason for high liquid
limits. The liquid limits of the Layer-2 are vary from 72 to 88 % thus classify the clay as
high plasticity.
The index properties and grain size distribution of Layer-2are summarized below with the
average values in the bracket:
Natural water content, % 37 58 (44)
Atterberg limits
Liquid limit, % 72 88 (79)
Plastic limit, % 32 42 (36)
Plasticity index, % 30 55 (44)
Bulk density, kN/m3 16.5 18.0 (17.1)
Grainsize distribution:
Gravel, % 0
Sand, % 2 7 (5)
7/24/2019 Cirebon Power Plant_R0
12/213
Final Report, Part I : Power Block Area Revision-00
Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007
For Cirebon Electric Power PT, Jakarta Job No. 2350
PT. SOILENS, Bandung Page 8
Silt, % 13 41(25)
Clay, % 52 81 (69)
(c)
Layer-3
Layer-3consist of sand and clay respectively. No undisturbed samples was collected thus
no laboratory test results from this layer.
5.2.2 Strength Parameters
The undrained shear strengths (cu) and internal friction angle () of the cohesive soil takenfrom Layer-1, and Layer-2 were determined from the laboratory Unconsolidated
Undrained (UU) Triaxial test and from the laboratory unconfined compression test. The
undrained shear strength of Layer-3 were derived based on SPT N values with correlation
of su= 6N, N is average SPT N values.The following range of undrained shear strengths with the recommended average values in
bracket:
Table 3: Un-drained shear strengths of the subsoil and friction angle of the soil
Description Layer-1 Layer-2 Layer-3
SPT N-values Less 1-5 >5 30 >30
Un-drained shear strength (cu),kN/m2 2-43 (16) 13-98(54) >150
Internal friction angle (), degrees 0.3-8.5(3.1) 1.6-9.0(5.8) 0
Note : (1) Undrained shear strengths are predicted from SPT N-values
5.2.3 Compressibility Characteristic
The pre-consolidation pressures (Pc) in Layer-1 is much lower than the computed effective
overburden pressures, therefore the soil is under normally consolidated. For Layer-2 thepre-consolidation pressure (Pc) is higher than the effective overburden pressure, therefore
these units are over consolidated.
The consolidation properties for cohesive subsoil obtained from the laboratory tests and
the recommended average values are summarized in Table 4.
Table 4: Compressibility Characteristic of the Subsoil
Description Layer-1 Layer-2
Compression Index, cc 0.29-1.51(0.78) 0.34-0.47(0.38)
Preconsolidation Pressure (Pc),kPa 17-550(116) 247-646(413)
7/24/2019 Cirebon Power Plant_R0
13/213
Final Report, Part I : Power Block Area Revision-00
Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007
For Cirebon Electric Power PT, Jakarta Job No. 2350
PT. SOILENS, Bandung Page 9
6. ANALYSIS AND RECOMMENDATIONS
6.1 Plant Site Preparation
6.1.1 Areal Fill
To form the final grading level of the proposed development, low lying area will beraised to an elevation of +5.00 m MSL to keep the site should always be dry and free
from any flooding during the plant life time. The fill thickness will range of 3.63 to4.87 m. Based on the laboratory tests, the original soil layers is to weak to carry the
proposed fill height. Failure will occur as the safety factor against failure of the original
soil layer, based on the conservative estimate is less than 1.0.
Reclamation could be done using sand obtained from along the coastal area. Before
reclamation over the proposed plant area we have to remove any organic material.Analysis on ultimate bearing capacity for each borehole point gives the following
results:
Table 5: Ultimate bearing capacity calculation results
Borholecu
(kN/m2)
qult
(kN/m2)
Fill
thickness(m)
p
(kN/m2)
SF against
bearing capacityfailure
BH-12 10 51.4 3.73 61.54 0.83
BH-13 13 66.8 4.78 78.87 0.85
BH-14 8 41.1 4.83 79.69 0.51
BH-15 5 25.7 3.63 59.89 0.43
BH-16 12 61.7 4.46 73.59 0.84
BH-17 10 51.4 4.45 73.42 0.70
BH-18 10 51.4 4.65 76.72 0.66
BH-19 41 210.7 4.87 80.35 2.62
BH-20 47 241.5 4.78 78.87 3.06
BH-21 11 56.5 4.73 78.04 0.72
BH-22 14 71.9 4.68 77.20 0.93
BH-23 13 66.8 4.25 70.12 0.95
BH-24 9 46.3 4.20 69.30 0.67
BH-25 2 10.3 4.71 77.71 0.13
BH-26 2 10.3 4.32 69.79 0.15
Note:
1. cu = undrained shear strength
2. qult = ultimate bear ing capacity = 5.14 cu.
3. p = fill pressure = fill thickness x fill density (16.5 kN/m2)
4. SF = Safety Factor =
p
ultq
6.1.2 Areal Settlement
Settlement analysis due to areal fill is carried out for points at the center of the fill.
Stress distribution at each soil layer is calculated based on the elasticity theory using
Bousinesqs equations. The settlement to occur is estimated using Terzaghis onedimensional compression model with soil parameters obtained form oedometer test in
7/24/2019 Cirebon Power Plant_R0
14/213
Final Report, Part I : Power Block Area Revision-00
Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007
For Cirebon Electric Power PT, Jakarta Job No. 2350
PT. SOILENS, Bandung Page 10
the laboratory. The results of the settlement calculation presented in PLATE 1.1 toPLATE 1.2, summarized in Table 6.
Table 6: Summarized areal settlement analysis results
Borhole Fill (m)Unit Weight
(kN/m3)
Average Load(kN/m
2)
Settlement(mm)
Time required toreach 90 %
consolidationsettlements
(Years)
BH-12 3.73 16.5 61.53 1164 6.8
BH-13 4.79 16.5 78.95 1577 1.6
BH-14 4.83 16.5 79.73 1770 8.1
BH-15 3.63 16.5 59.96 1056 4.6BH-16 4.46 16.5 73.62 1414 6.9
BH-17 4.46 16.5 73.56 1798 2.4
BH-18 4.66 16.5 76.84 820 8.1
BH-19 4.87 16.5 80.37 754 5.7
BH-20 4.79 16.5 78.97 1209 8.1
BH-21 4.73 16.5 78.06 1323 5.7
BH-22 4.68 16.5 77.29 1198 5.7
BH-23 4.25 16.5 70.09 1169 5.7
BH-24 4.15 16.5 66.38 1782 4.6
BH-25 4.71 16.5 77.76 1033 3.8
BH-26 4.32 16.5 71.23 915 6.0
Under the fill layer of about 3.7 to 4.8 meter the proposed plant site will undergo arealsettlement. That is due to consolidation process of the upper soft layer of about 12 meter
thick under the fill weight.
Because of very soft original soil layer, we do not recommend filling the area with very
high fill in straight until elevation of +6.5 m MSL. With average undrained shearstrength of about 16 kN/m2 the ultimate bearing capacity of the original layer will beonly 82 kN/m2. The maximum fill height that can be supported by the original layer
without failure is hfill=qult/(fill x SF). Using SF (Safety Factor) of 1.5 and fill 16.5kN/m2then hfill= 3.3 meter.
Therefore, 2 stages of filling should be performed to avoid failure on the original softlayer. First stage is filling the proposed plant area to +3.50 m MSL, and wait until
settlement finishes within about 3 years. After the first-stage settlement then the second
filling until elevation of +6.50 m MSL can be done and wait until the second settlementfinishes within next three years before plant construction.
7/24/2019 Cirebon Power Plant_R0
15/213
Final Report, Part I : Power Block Area Revision-00
Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007
For Cirebon Electric Power PT, Jakarta Job No. 2350
PT. SOILENS, Bandung Page 11
6.1.3 Vertical Drain and Deep Mixing
Waiting 3 years for site preparation is not an attractive choice for a project with tight
schedule like this power plant project. To speed up consolidation process of the top 11
m layer installation of vertical drains over the proposed plant site together withsurcharging (filling) can be a good solution in terms of cost efficiency and construction
ease. We propose using synthetic band-shaped drain (wick-drain) of 100 mm wide and6 mm thick for vertical drains installed until about 11 m depth below the existing
ground surface. By using drain spacing of about 1.5 m in triangular pattern the
consolidation process of the original soft layer can be expected to be finished withinabout 3 month. The two stages of filling then can be finished within about six month.
PLATE 2 shows drain spacing calculation using Baron theory for vertical drains.
Other method of ground improvement should be considered of the time available for site
preparation is less than 6 (six) months. Deep mixing or deep compaction to mix reagents
such as cement powder or lime with in-situ soil can be considered for groundimprovement. This type of improvement will increase the strength and reduce the
compressibility of the soft layer. However, Contractor specialist in this field should becontacted for further assessment.
6.1.4 Provisions Against Secondary Settlement
Although consolidation settlement has been finished, the designer of the plant should beaware of the remaining secondary settlement that is still to be experienced by the project
site during the lifetime of the plant due to creep of the original soft soil layer. Such asettlement is estimated to be in the order of ten percent of the consolidation settlement,
i.e. about 15 to 20 cm, during the plant lifetime. For example, connection between pipe
resting directly on the ground and structure resting on pile should take intoconsideration this remaining settlement. Otherwise, problem will arise after some years
of construction because of this settlement, which may not be of the same magnitude atevery point.
6.2 Liquefaction
6.2.1 General
The basic cause of liquefaction is the built-up of excess pore pressure caused by
earthquake induced vibrations. The excess pore pressure can cause loose cohesionlessmaterial to lose strength, and results in large settlements of the structures supported on
this material; or in the case of the pile foundations, the soil may lose its ability to
provide lateral resistance for the piles during liquefaction.
6.2.2 Liquefaction Analysis
For the analysis of liquefaction, all borings containing sand material are analyzed todetermine whether this material is subject to liquefaction under 0.08 g and 0.10 g peak
ground accelerations (PGA) and earthquake magnitude of 6.9 Richter Scale. The
analysis is performed using the methods of Seed & Idris and Ishihara, using thefollowing equation:
d
o
od
org
PGA...65.0)( ''
= ......(1)
7/24/2019 Cirebon Power Plant_R0
16/213
Final Report, Part I : Power Block Area Revision-00
Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007
For Cirebon Electric Power PT, Jakarta Job No. 2350
PT. SOILENS, Bandung Page 12
d
o
l
oFS
)(
)(
'
'
= .......(2)
Where :
d
o
)('
= average cyclic stress ratio developed during the earthquake
PGA = peak ground acceleration at the ground surface in g
g = acceleration of gravity, m/s2
o = total stress at depth of interest, ton/m2or kN/m2
'
o = effective stress (total stress minus pore water pressure) at depth, ton/m2or
kN/m
2
rd = reduction in acceleration with depth= 1-0.008 Z
Z = depth below ground surface, m
l
o
)('
= cyclic stress ratio required to induce liquefaction.
FS = factor of safety.
Figure 1 : Liquefaction curves criterion for fines5 %, 15 % and 35 %
Specifically, the
analysis consists of firstselecting the sands, silty
sands and clayey sandslayers occurring below
the water table that are
characterized byrelatively low standard
penetration test valuesthat may be susceptible
to liquefaction. The
standard penetrationtest values are then
normalized, the cyclic
shear stress isdetermined, and all
material having a factorof safety less than 1.0 is
concluded to beliquefiable.
6.2.3 Result of Analyses
Based on the analyses described in Section 6.2.2, for peak ground acceleration (PGA) of
0.08 g and 0.10 g with earthquake magnitude of 6.90 Richter Scale, the sand is not
potentially liquefiable with a safety factor of more than 1.0. The results of analysis arepresented in PLATE 3.1to PLATE 3.13.
7/24/2019 Cirebon Power Plant_R0
17/213
Final Report, Part I : Power Block Area Revision-00
Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007
For Cirebon Electric Power PT, Jakarta Job No. 2350
PT. SOILENS, Bandung Page 13
6.3 Foundations
6.3.1 General Foundation Criteria
To have a good performance foundation of any structure must satisfy two independent
design criteria.
It must have an acceptable factor of safety against bearing type failure under a
maximum design load. Settlements during the structure lifetime must not be a magnitude that will cause
structural damage, or impair the operational efficiency of the facility.
Selection of the foundation type to satisfy the criteria depends on the nature andmagnitude of dead and live loads, the base area of the structure and the settlement
tolerances. Where more than one foundation type satisfies these criteria, the cost,scheduling, material availability and local practice will influence on the final selection of
the type of foundation.
6.3.2 Shallow Foundation
We do not recommend the use of shallow foundation for any important and settlement
sensitive structure because of the low bearing capacity of the original layer and therelatively large settlement that still to be experienced by the project site.
6.3.3 Deep Foundation
6.3.3.1 Axially Loaded PC-Piles
The most reasonable and acceptable foundation for any important and settlement
sensitive structure to be constructed here is driven pile. This is because driven pile is easyand fast to install and can transfer working load to a competent layer at deeper layer
stratum by by-passing the top soft layer, resulting in very small experienced settlement
The assessment of axial pile capacity is based on Pre stressed Concrete Spun Pile (PC-Pile) of 300 mm, 350 mm, 400 mm, 450 mm and 500 mm outside diameter, with 60
mm, 65 mm, 75 mm, 80 mm and 90 mm wall thickness, respectively.
The ultimate soil bearing capacity in compression and tension is calculated based on the
laboratory and field tests, by using the following equation :
Pult-cmp = fs.As+ qp.Ap.......................(3)
Where :Pult-comp = ultimate pile capacity in compression, kNfs = unit skin friction to pile, kN/m
2
= . cu, for cohesive soil
= ko.po.tan(), for cohesionless soil
= adhesion factor
= 0.50. 50.0)(
o
u
p
cfor
o
u
p
c1.0
= 0.50.25.0
)(
o
u
p
cfor
o
u
p
c >1.0
ko = coefficient of lateral earth pressure
= 1 sin
7/24/2019 Cirebon Power Plant_R0
18/213
Final Report, Part I : Power Block Area Revision-00
Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007
For Cirebon Electric Power PT, Jakarta Job No. 2350
PT. SOILENS, Bandung Page 14
cu = undrained shear strength, kN/m2
Po = effective overburden vertical stress at depth under consideration,
kN/m2
As = outside surface area of pile, m
2
qp = unit end bearing capacity, kN/m2
= 9.cu, for cohesive soil= po.Nq, for cohesionless soil
Nq = dimensionless bearing capacity factor
Ap = cross section area of pile, m2
The shear strength (cu) of rock can be derived based on unconfined compression test with
correlation of2
uu
qc = . If there is no laboratory test results, the un-drained shear
strength derived based on SPT N-values using correlation of c u = 6N. The maximum
values of cu is 250 kPa for compressive and 100 kPa for tension. The analysis wasperformed by using computer program of PLEAXI. To aid the designer in designing a
foundation, the graph of pile capacities for each borehole point is provided in this report.The designer can select which borehole point close to a particular structure or to a
particular pile location so pile capacity can be obtained from the graph for that borehole.
The graphs showing the ultimate and allowable soil bearing capacity in compression and
tension against the embedment depth below plant site elevation of +5.0 m MSL are
shown in PLATE 4.1 to PLATE 4.15 enclosed in this report. The allowablecompressive capacity of spun piles are designed for a safety factor of 2 and the estimated
settlement of about 25.4 mm. The allowable tension capacities are designed for a safetyfactor of 3.
6.3.3.2 Negative Skin Friction on Piles.
Due to the site fill over the existing consolidated soil layers at the plant site, we
recommend to include the negative skin friction in calculating allowable
compressive bearing capacity. The magnitude of negative skin frictionPNactingon bored pile is presented in Table 7.
The unit negative skin friction is calculated as suggested by Bjerrum using the following
equations:
For cohesive soil : fs = 0.25 po..............................................................(4)
For cohesionless soil : )4
3tan(...
2
1oss pkf = .........(5)
Where :
fs = unit negative skin frictionpo = effective overburden pressure
ks = coefficient of lateral earth pressure
= internal friction angle of cohesionless soil
The ultimate negative skin friction then to be calculated by using the following equation:
PN = .D.LN.fs.......(6)
Where :
7/24/2019 Cirebon Power Plant_R0
19/213
Final Report, Part I : Power Block Area Revision-00
Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007
For Cirebon Electric Power PT, Jakarta Job No. 2350
PT. SOILENS, Bandung Page 15
PN = ultimate negative skin friction on pileD = diameter of pile
LN = length of pile to neutral point
fs = unit negative skin friction.The negative skin friction on pile summarized as follows:
Table 7: Negative skin friction on pile (PN)
No Pile TypePile Dimension/
Diameter
Negative Friction (PN)
(kN)
1 Spun Pile dia. 300 mm 165
2 Spun Pile dia. 350 mm 190
3 Spun Pile dia. 400 mm 215
4 Spun Pile dia. 450 mm 245
5 Spun Pile dia. 500 mm 270
6.3.3.3 Laterally Loaded Piles
The analysis of the lateral capacity of the piles is performed by using Lpile Pluscomputer program developed by Ensoft. Lpile Plus uses a finite difference approximation
to solve the non-linear spring-beam/column model of pile-soil interaction. The stress-
strain response of the pile is modeled as a simple elastic material with E-pile assumed to
be b9600 kg/cm2. Where bis the characteristics compressive strength of concrete
of 500 kg/cm2for pc-pile.
The results of analyses for single piles are presented as curves of the lateral load versuspile head deflection and the lateral load versus maximum bending moment on the
following Plate :
PLATE 5.1 to PLATE 5.5 for Pinned/Free Pile Head
PLATE 6.1 to PLATE 6.5 for Fixed Pile Head
The pile response due to lateral load presented in curves on the following plate :
PLATE 7.1 to PLATE 7.5 for Pinned/Free Pile Head
PLATE 8.1 to PLATE 8.5 for Fixed Pile Head
6.3.3.4 Allowable Pile Capacity
(a).
Axial Compressive CapacityTo determine the allowable axial pile capacity in compression the equation (4)should be used.
s
ult
compallF
PP
comp
= ........................................................(4)
Where :Pall-comp = allowable soil bearing capacity in compression, kN
Pult-comp = ultimate soil bearing capacity, kN
FS = factor of safety, 2.0
Based on our experience a safety factor of 2.0 may be used in equation (4) to getthe allowable compressive capacity.
7/24/2019 Cirebon Power Plant_R0
20/213
Final Report, Part I : Power Block Area Revision-00
Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007
For Cirebon Electric Power PT, Jakarta Job No. 2350
PT. SOILENS, Bandung Page 16
(b). Axial Tension Capacity
To determine the allowable axial pile capacity in tension the equation (5)should
be used.
s
ult
tensionallF
PP tension= ..........................................................(5)
Where :Pall-tension= allowable pile capacity in tension, kN
Pult-tension= ultimate pile capacity in tension, kNFS = factor of safety, 3
Finally, the maximum allowable load both in compression and tension should be
checked against the allowable capacity of the pile material.
(c). Lateral Pile Capacity
We recommend using allowable lateral load based on a tolerable butt deflectionof 10 mm for pinned head and 6 mm for fixed head.
During design phase the lateral pile capacity presented in this report should be
checked against the capacity of pile material to resist bending moment and shearstress. This can be done by checking the interaction graph of axial load versus
bending moment issued by the pile manufacturer.
The pile penetration or length below plant elevation, allowable compressive,
tension and lateral pile capacity are presented in PLATE 9.1 to PLATE 9.3. It
should be noted that the allowable static axial pile capacities presented in thistable can be increased by 30 % to determine the transient load such as wind or
seismic.
6.3.3.5 Pile Spacing
Axial loading of group piles should be determined as the product of group efficiency
(reduction factor), number of piles in the group and the capacity of a single pile. Werecommend that for piles with center to center spacing of 3 pile diameters, the reduction
factor of 1.0 be used. The reduction factor of 0.70 for piles with a center to center spacingless than 3 pile diameters should be used. Center to center piles spacing less than a 2.5
pile diameter is not recommended.
For lateral loading, analyses based on Fleming show that no reduction in lateral capacitydue to pile group effects is envisaged provided the pile spacing is 4.5 pile diameter or
greater (center to center). In case pile spacing is less than 4.5 pile diameter in a group, werecommend reduction factor of 0.70 to analyze the lateral group capacity.
6.3.3.6 Pile Driving Procedures
(a). Driving Records
Probe piles should be installed first before any production pile. Observation on
probe pile should be performed at every area near the boring points to know the
sufficient length of embedment, final blows per 25 cm penetration, and totalblows of each probe pile.
7/24/2019 Cirebon Power Plant_R0
21/213
Final Report, Part I : Power Block Area Revision-00
Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007
For Cirebon Electric Power PT, Jakarta Job No. 2350
PT. SOILENS, Bandung Page 17
After driving the probe piles, pile load tests on several piles at represented areashould be carried out to know pile behavior under loading and pile load capacity
at certain short-term settlement.
Driving of working piles are performed after issuing pile driving criteria for pilesat each represented area. The following data shall be recorded in the pile driving
record sheet.
(1) General data including project name, job number, pile driving record, date
and time of pile driving commencement and completion, pile number,
structures name, ground surface elevation and others.(2) Data of pile including pile identification number, pile diameter, pile length,
pile tip elevation, and others(3) Data of hammer including total weight of hammer ram weight, ram stroke,
rate energy per blow, hammer cushion.
We recommend that pile driving be performed from center to edge of the group toavoid or to limit possible heaving. A continuous heave measurement for all the
piles should be performed throughout the pile driving. Re-driving of piles shouldbe done if heave exceeds 25.4 mm.
We recommend using pile shoes to improve drive-ability and also to provide
protection at the pile tip.
(b). Pile Driving Criteria
The pile driving acceptance criteria should be based on the following :
(1).
Drive the pile to target level as defined by the nearest boring logs or pile testresults.
(2). If the pile comes to refusal above target level, continue driving until a blowcount of 100 blows/250 mm penetration or final set of 25 mm/10 blows. The
pile is then required to be driven for final setting in 2 t imes, without anyreduction in the driving resistance. If the resistance is not maintained at 25
mm/10 blows it is judged that the hard layer is thin and the pile is liable to
break through this layer. Therefore, the pile should be driven further to thetarget level.
(c). Use minimum pile driving equipment of K-35 with hammer weight of 35 kN or
equivalent for driving the pile with pile weight of 25 to 65 kN and requiredbearing capacity of 1000 to 1750 kN.
(d). Use minimum pile driving equipment of K-45 hammer weight of 45 kN orequivalent for driving pile with pile weight of 35 to 85 kN and required bearing
capacity of 650 kN to 2000 kN.
6.3.3.7 Full Scale Vertical Pile Loading Test
The design capacities in this report for properly installed conventional piles are based on
considerable experience with load tests as well as the application of geotechnical design
methods. It is recommended performing full scale pile loading tests for the axial anduplift modes to confirm the calculated ultimate to determine the safe loads capacities ofthe piles.
7/24/2019 Cirebon Power Plant_R0
22/213
Final Report, Part I : Power Block Area Revision-00
Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007
For Cirebon Electric Power PT, Jakarta Job No. 2350
PT. SOILENS, Bandung Page 18
The test piles should be installed with the same procedures and details which will be usedfor production piles. This is especially important with bored piles where the performance
can be significantly influenced by the installation procedures. The test pile lengths should
be similar to the expected lengths of the production piles. If at all possible, the static loadtesting procedures and capacities should be such that the load test is carried out to a soil
failure. Having failure criteria will allow the penetration of the production piles to bemodified based on the load test results and the calculated pile-soil adhesion factors.
The tests should follow ASTM D1143 and ASTM D3689 procedure. The test should be
carried out on 2(two) of the first piles. This will enable an early evaluation and make itpossible to verify weather the pile system actually complies the contractors
specifications. The pile load testing program should consider the following :
The load shall be applied to the test pile by a hydraulic jack acting against a reaction
beam, which is anchored by two or four reaction piles or loaded platform with concrete
blocks.Reaction pile or counter loads and hydraulic jack each should have a capacity of
minimum 4 times the pile design load.
Vertical movement of the test pile and reaction piles are measured using at least 3 dial
gauges, each having a 50 mm travel and be accurate to 0.01 mm. The dial gauges should
be supported independently from the test pile and reaction piles.
The loads shall be applied in accordance with the cyclic loading procedure of the
respective ASTM standard. The entire test area must be sheltered from direct sunlight, wind and rain. The
shelter must be sufficiently lighted as to allow night monitoring.
The resultant of the load components must act along the longitudinal centerline ofthe test pile.
An effort is to be made to have the dial gages calibrated prior to the test in anacceptable testing laboratory and the certificate is to be submitted for records.
During test loading, read dial gages at 0, 1, 2, 5, 10, 15 and 30 minutes after each
load increment, and 30 minutes intervals thereafter with max. 2 hours. Opticalreadings shall be taken on the reaction of anchor piles as well as the test pile before
each load increment is changed. During 24 hours hold, readings may be taken every3 hours after the first 2 hours.
The final report shall contain the following :
Identification, location and description of the test pile Description of the test apparatus, loading system and deflection measurement
procedure Tabulated field data
Time-settlement curve
Load-settlement curve Remarks explaining unusual events or data, and movement of reaction piles
Inspection logs for the test pile Calibration certificate of dial gauges and pressure gauges, indicating the serial
number of the gauges and date the calibration was performed
Pile loading test shall be performed minimum 21 days after pile driving. We suggestperforming minimum 2(two) static loading tests on plant site.
7/24/2019 Cirebon Power Plant_R0
23/213
Final Report, Part I : Power Block Area Revision-00
Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007
For Cirebon Electric Power PT, Jakarta Job No. 2350
PT. SOILENS, Bandung Page 19
6.3.3.8 Lateral Load Test
It is recommended to perform lateral load test to confirm the calculated ultimate capacity
to determine the safe loads capacities of the piles. The tests should follow ASTM D3966
procedure.
The impact point for the lateral test load shall be as close as possible to the site elevation.
The impact point shall be finalized at the job site taking into account the loading device tobe actually utilized at the time of load test. The following requirement and boundary
limitation shall be applied for performing the lateral load test :
In the static loading, unless failure occurs first, the test pile shall be loaded to themaximum test load of 200 % of the design load in accordance with the standard
loading procedure stipulated in ASTM D3966, Section 6.1
In the dynamic (cyclic) loading, unless failure occurs first, the test pile shall be
loaded to the maximum test load of 200 % design load in accordance with thestandard loading procedure stipulated in ASTM D3966, Section 6.3
6.3.3.9 Pile Dynamic Analyzer (PDA Tests)
(a) We recommend performing Pile Dynamic Analyzer (PDA) Test to evaluate theultimate pile capacity at the time of testing. Based on the PDA test results,
CAPWAP analysis should be performed to provide refined estimates of static
capacity, assessment of soil resistance distribution, and soil quake and dumpingparameters for wave equation input.
(b) It is noted that the soil is greatly disturbed when a pile is driven into the soil. As
the soil surrounding the pile recovers from the installation disturbance, a timedependent change in capacity often occurs. In this case we suggested to perform
PDA in two time for the same pile as follows:
Immediately after pile driving, and
21 days after pile driving.
The hammer for pile dynamic analysis should be warmed up before re-drivebegins by applying at least 20 blows to another pile. The maximum amount of
penetration required during re-drive should be 152.4 mm (6 inches) or the
maximum total hammer blows required will be 50, whichever occurs first.
(c) Equipment and Methodology Prepared the top of the pile head, prior to testing, by grinding the concrete
surface to a smooth and flat condition.
Drilled and plugged the concrete test pile in order to attach two strain
transducers and two piezo-electric accelerometers to the pile shaft at a distanceof 1.5 to 2.0 times the pile diameter below pile head.
The instrument then is connected to the PDA Collector computer by aninsulated multi-wire cable. The PDA computer should be located some
distance away from the instrumented test pile
Dynamic measurements then are obtained from the strain transducers andpiezo-resistive accelerometers by striking the pile head on four separate
occasions using a driving hammer as a drop weight. Each blow should be
7/24/2019 Cirebon Power Plant_R0
24/213
Final Report, Part I : Power Block Area Revision-00
Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007
For Cirebon Electric Power PT, Jakarta Job No. 2350
PT. SOILENS, Bandung Page 20
cushioned by a purpose made plywood packer placed directly on top of thesmooth pile head.
Analog signal from transducers be conditioned, digitized, stored and processed
by PDA. Selected output from PDA typically included values such as :
the measured force and calculated maximum stress
transferred energy to the pile
calculated ram stroke
static pile capacity and others
(d) The following main Pile Driving Analyzer data input should be checked and beadjusted to the actual pile and soil condition in the project
Pile length below gages Pile cross section area at the gauges
Pile elastic modulus Unit weight of pile material Pile wave speed
Case damping factor Unit indicator
Display scale and transducer calibrations
(e) Methodology of CAPWAP Analysis
The CAPWAP computer program is a rigorous numerical analysis procedure
which uses the PDA measured force and velocity data to solve for soilresistance parameters.
A model of each pile should be divided into segments of approximately one
meter in length and trial soil resistance be assigned every second embeddedpile element and one extra resistance at the pile base, to model the base
response.
The soil model for each soil element contained a static resistance represented
by an elasto-plastic spring with an ultimate resistance and a limiting elastic
displacement, termed the quake
The soil damping modeled as a viscous dashpot with a damping factor which
related the magnitude of the dynamic soil resistance to the pile velocity.
The selected PDA measured pile top velocity for the test pile then is imposedas an input to the CAPWAP analysis and trial values is assigned to all soil
model parameters. The required pile top force then computed and thesolution compared with the measured force obtained from the selected
hammer blow. The agreement between computed and measured pile top forceshould be progressively improved by an iteration process in order to modify
the soil model parameters, total capacity and its distribution along theembedded pile shaft, damping factors and quakes until no further significant
improvement could be obtained in the model. The final soil parameters then
are deemed to represent a best match dynamic soil model for the test pile.These soil parameters and pile model, finally be analyzed to calculate both
shaft and base resistance, total mobilized capacity, and the static load-settlement response of both the pile head and the pile base.
7/24/2019 Cirebon Power Plant_R0
25/213
Final Report, Part I : Power Block Area Revision-00
Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007
For Cirebon Electric Power PT, Jakarta Job No. 2350
PT. SOILENS, Bandung Page 21
(f) Detail procedures of PDA Test, apparatus to be applied, analysis, and reportingshall be in accordance with the requirement of ASTM D4945.
(g) All components of the apparatuses for obtaining dynamic measurement and the
apparatuses for recording shall be calibrated at least once a year.
(h) The PDA test and analysis should be performed by qualified and experienced
Engineer(s). We recommend performing 4 (four) points of PDA test for thisproject. Regardless of the project size, we consider that Engineer may adjust the
number and locations of dynamically tested piles based on design or construction
issues that arise
6.4 Chemical Properties of Soil and Water Samples
Chemical test, i.e., pH, chloride content, and sulfate content were performed on soil andwater samples obtained from borings to know the aggressivity of the soil against concrete
structure. The results of analysis are summarized in Table 8.
Table 8: Chemical properties of soil samples.
Test ResultNo Test
in ppm in %
1 pH 7.8-8.1(7.9)
2 Chloride (Cl) content 6409-13032(8987) 0.64-1.30(0.90)
3 Sulfate Content 3452-5546(4844) 0.35-0.55(0.48)
Table 9: Chemical properties of water samples.
Test ResultNo Test
in ppm in %
1 pH 6.1-6.9(6.6)
2 Chloride (Cl) content 15310-18515(17595) 1.53-1.85(1.76)
3 Sulfate Content 1766-1924(1817) 0.18-0.19(0.18)
The pH data indicates that the soils in the area are normal. The degradation of concrete iscaused by chemical agents in the soil or groundwater that react with concrete to either
dissolve the cement paste or precipitate larger which cause cracking and flaking. The
concentration of the water-soluble sulfate in the soils is a good indicator of the potential forchemical attack of concrete. Sulfate concentration in soil can be used to evaluate the need
for protection of concrete based on the information in the table below:
Table 10: Sulfate Attack Potential
Sulfate ion concentration, ppm Aggressiveness
>20,000 Very Severe
2,000 to 20,000 Severe
1,000 to 2,000 Moderate
7/24/2019 Cirebon Power Plant_R0
26/213
Final Report, Part I : Power Block Area Revision-00
Cirebon Thermal Power Plant Project, Cirebon, West Java August 13, 2007
For Cirebon Electric Power PT, Jakarta Job No. 2350
PT. SOILENS, Bandung Page 22
The American Concrete Institute Code 218 recommends that for these conditions Type Vcement be used with a water cement ratio of less than 0.45. Other types of cement with fly
ash up to 10 % may be used if the maximum water cementitious materials ratio is reduced
to 0.4 or lowerBecause of the location of the project adjacent to a salt water and possibility of moisture
containing significant volumes of chlorides which could then be deposited on concreteexposed to wetting and drying cycles, considerations should be given to provide corrosion
protection to minimize chloride attack to the exposed concrete structures near or on the sea.
Chloride inhibitors are available as admixtures during concrete mixing.
6.5 Hydrology
To ensure easy drain of rain water runoff from the plant site, drainage ditch should beconstructed along the proposed road, around the buildings, the edges of the embankment or
excavation onto slopes. A vegetation cover should be established as soon as possible on theembankment and or excavation slopes to minimize erosion from the surface run-off. Run-off coefficient of 0.70 to 0.90 should be used for calculating design discharge on paved
area, and 0.50 for flat grassed areas with about 50 percent area impervious. We alsorecommend providing the area with impermeable surface drainage ditch, i.e., lined ditch, to
easily drain the surface water to a lower elevation.
6.6 Inspection and Monitoring
Geotechnical aspects of foundation construction and/or installation should be monitored by
a geotechnical engineer or his/her representative. Critical phases of the construction where
geotechnical inspection is crucial to success of the project are : During plant site reclamation, and soil improvements.
During pile load testing, for making change in situ driving criteria and depth
requirements to account for subsurface conditions.
During production pile driving to monitor depth requirements and potential hard driving
zones and others.
7/24/2019 Cirebon Power Plant_R0
27/213
01
164
621
164
62
0
621
164
0.1
0.3
0.6
1.0
1.6
2.3
3.3
4.6
6.8
116
233
349
466
582
698
815
931
1048
Ir.Wirastusrini,PE
LOAD-SETT
LEMENTS
TIME-SETTLEMENTS
Settlements(mm)
LayerThickness(m)
SettlementTime(years)
SettlementsbyFill(mm)
AverageLoad(kN/m
2)
61.53
1164
UnitWeight,
(kN/m
3)
Approvedby
Preparedby
Checkedby
Ir.Padmono,PE
Ir.KabulS.MSC
JobNo.
2358
16.5
3.73
AREASE
TTLEMENTANALYSISBH-12
PLATE1.1
PT.SOILENS
CIREBONTH
ERMALPOWERPLANTPR
OJECT
0150
300
450
600
750
900
1050
1200
1350
1500
1650
1800
1950
2100
2250
2400
0
10
20
30
40
50
60
70
80
90
100
11012
0
130
FILLLOAD,kN/m
2
SETTLEMENTS,MM
0 75 150
225
300
375
450
525
600
675
750
825
900
975
1050
1125
1200
0.00
0.60
1.20
1.80
2.40
3.00
3.60
4.20
4.80
5.40
6.00
6.60
7.20
TIME,Years
SETTLEMENTS,MM
7/24/2019 Cirebon Power Plant_R0
28/213
01
577
791
577
79
0
791
577
0.0
0.1
0.1
0.2
0.4
0.5
0.7
1.0
1.5
158
315
473
631
789
946
1104
1262
1419
Ir.Wirastusrini,PE
LOAD-SETT
LEMENTS
TIME-SETTLEMENTS
Settlements(mm)
LayerThickness(m)
SettlementTime(years)
SettlementsbyFill(mm)
AverageLoad(kN/m
2)
78.95
1577
UnitWeight,
(kN/m
3)
Approvedby
Preparedby
Checkedby
Ir.Padmono,PE
Ir.KabulS.MSC
JobNo.
2358
16.5
4.79
AREASE
TTLEMENTANALYSISBH-13
PLATE1.2
PT.SOILENS
CIREBONTH
ERMALPOWERPLANTPR
OJECT
0200
400
600
800
1000
1200
1400
1600
1800
2000
2200
2400
0
10
20
30
40
50
60
70
80
90
100
11012
0
130
FILLLOAD,kN/m
2
SETTLEMENTS,MM
0200
400
600
800
1000
1200
1400
1600
1800
2000
2200
2400
0.00
0.20
0.4
0
0.60
0.80
1.00
1.20
1.40
1.60
1.80
2.00
TIME,Years
SETTLEMENTS,MM
7/24/2019 Cirebon Power Plant_R0
29/213
01
770
801
770
80
0
801
770
0.1
0.3
0.7
1.2
1.9
2.7
3.9
5.4
8.1
177
354
531
708
885
1062
1239
1416
1593
Ir.Wirastusrini,PE
LOAD-SETT
LEMENTS
TIME-SETTLEMENTS
Settlements(mm)
LayerThickness(m)
SettlementTime(years)
SettlementsbyFill(mm)
AverageLoad(kN/m
2)
79.73
1770
UnitWeight,
(kN/m
3)
Approvedby
Preparedby
Checkedby
Ir.Padmono,PE
Ir.KabulS.MSC
JobNo.
2358
16.5
4.83
AREASE
TTLEMENTANALYSISBH-14
PLATE1.3
PT.SOILENS
CIREBONTH
ERMALPOWERPLANTPR
OJECT
0200
400
600
800
1000
1200
1400
1600
1800
2000
2200
2400
0
10
20
30
40
50
60
70
80
90
100
11012
0
130
FILLLOAD,kN/m
2
SETTLEMENTS,MM
0200
400
600
800
1000
1200
1400
1600
1800
2000
2200
2400
0.00
1.00
2
.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
TIME,Years
SETTLEMENTS,MM
7/24/2019 Cirebon Power Plant_R0
30/213
01
056
601
056
60
0
601
056
0.0
0.2
0.4
0.7
1.1
1.5
2.2
3.1
4.6
106
211
317
422
528
634
739
845
950
Ir.Wirastusrini,PE
LOAD-SETT
LEMENTS
TIME-SETTLEMENTS
Settlements(mm)
LayerThickness(m)
SettlementTime(years)
SettlementsbyFill(mm)
AverageLoad(kN/m
2)
59.96
1056
UnitWeight,
(kN/m
3)
Approvedby
Preparedby
Checkedby
Ir.Padmono,PE
Ir.KabulS.MSC
JobNo.
2358
16.5
3.63
AREASE
TTLEMENTANALYSISBH-15
PLATE1.4
PT.SOILENS
CIREBONTH
ERMALPOWERPLANTPR
OJECT
0200
400
600
800
1000
1200
1400
1600
1800
2000
2200
2400
0
10
20
30
40
50
60
70
80
90
100
11012
0
130
FILLLOAD,kN/m
2
SETTLEMENTS,MM
0200
400
600
800
1000
1200
1400
1600
1800
2000
2200
2400
0.00
0.50
1.0
0
1.50
2.00
2.50
3.00
3.50
4.00
4.50
5.00
TIME,Years
SETTLEMENTS,MM
7/24/2019 Cirebon Power Plant_R0
31/213
01
414
741
414
74
0
741
414
0.1
0.3
0.6
1.0
1.6
2.3
3.3
4.6
6.9
141
283
424
566
707
848
990
1131
1273
Ir.Wirastusrini,PE
LOAD-SETT
LEMENTS
TIME-SETTLEMENTS
Settlements(mm)
LayerThickness(m)
SettlementTime(years)
SettlementsbyFill(mm)
AverageLoad(kN/m
2)
73.62
1414
UnitWeight,
(kN/m
3)
Approvedby
Preparedby
Checkedby
Ir.Padmono,PE
Ir.KabulS.MSC
JobNo.
2358
16.5
4.46
AREASE
TTLEMENTANALYSISBH-16
PLATE1.5
PT.SOILENS
CIREBONTH
ERMALPOWERPLANTPR
OJECT
0200
400
600
800
1000
1200
1400
1600
1800
2000
2200
2400
0
10
20
30
40
50
60
70
80
90
100
11012
0
130
FILLLOAD,kN/m
2
SETTLEMENTS,MM
0200
400
600
800
1000
1200
1400
1600
1800
2000
2200
2400
0.00
0.75
1.5
0
2.25
3.00
3.75
4.50
5.25
6.00
6.75
7.50
TIME,Years
SETTLEMENTS,MM
7/24/2019 Cirebon Power Plant_R0
32/213
01
798
741
798
74
0
741
798
0.0
0.1
0.2
0.4
0.5
0.8
1.1
1.6
2.4
180
360
539
719
899
1079
1259
1438
1618
AREASE
TTLEMENTANALYSISBH-17
PLATE1.6
PT.SOILENS
CIREBONTH
ERMALPOWERPLANTPR
OJECT
UnitWeight,
(kN/m
3)
Approvedby
Preparedby
Checkedby
Ir.Padmono,PE
Ir.KabulS.MSC
JobNo.
2358
16.5
4.46
Ir.Wirastusrini,PE
LOAD-SETT
LEMENTS
TIME-SETTLEMENTS
Settlements(mm)
LayerThickness(m)
SettlementTime(years)
SettlementsbyFill(mm)
AverageLoad(kN/m
2)
73.56
1798
0200
400
600
800
1000
1200
1400
1600
1800
2000
2200
2400
0
10
20
30
40
50
60
70
80
90
100
11012
0
130
FILLLOAD,kN/m
2
SETTLEMENTS,MM
0200
400
600
800
1000
1200
1400
1600
1800
2000
2200
2400
0.00
0.25
0.5
0
0.75
1.00
1.25
1.50
1.75
2.00
2.25
2.50
TIME,Years
SETTLEMENTS,MM
7/24/2019 Cirebon Power Plant_R0
33/213
0
820
77
820
77
0
77
820
0.1
0.3
0.7
1.2
1.9
2.7
3.9
5.4
8.1
82
164
246
328
410
492
574
656
738
Ir.Wirastusrini,PE
LOAD-SETT
LEMENTS
TIME-SETTLEMENTS
Settlements(mm)
LayerThickness(m)
SettlementTime(years)
SettlementsbyFill(mm)
AverageLoad(kN/m
2)
76.84
820
UnitWeight,
(kN/m
3)
Approvedby
Preparedby
Checkedby
Ir.Padmono,PE
Ir.KabulS.MSC
JobNo.
2358
16.5
4.66
AREASE
TTLEMENTANALYSISBH-18
PLATE1.7
PT.SOILENS
CIREBONTH
ERMALPOWERPLANTPR
OJECT
0150
300
450
600
750
900
1050
1200
1350
1500
1650
1800
0
10
20
30
40
50
60
70
80
90
100
11012
0
130
FILLLOAD,kN/m
2
SETTLEMENTS,MM
0150
300
450
600
750
900
1050
1200
1350
1500
1650
1800
0.00
0.80
1.60
2.40
3.20
4.00
4.80
5.60
6.40
7.20
8.00
8.80
TIME,Years
SETTLEMENTS,MM
7/24/2019 Cirebon Power Plant_R0
34/213
0
754
80
754
80
0
80
754
0.1
0.2
0.5
0.8
1.3
1.9
2.7
3.8
5.7
75
151
226
302
377
452
528
603
679
Ir.Wirastusrini,PE
LOAD-SETT
LEMENTS
TIME-SETTLEMENTS
Settlements(mm)
LayerThickness(m)
SettlementTime(years)
SettlementsbyFill(mm)
AverageLoad(kN/m
2)
80.37
754
UnitWeight,
(kN/m
3)
Approvedby
Preparedby
Checkedby
Ir.Padmono,PE
Ir.KabulS.MSC
JobNo.
2358
16.5
4.87
AREASE
TTLEMENTANALYSISBH-19
PLATE1.8
PT.SOILENS
CIREBONTH
ERMALPOWERPLANTPR
OJECT
0100
200
300
400
500
600
700
800
900
1000
1100
1200
1300
1400
1500
0
10
20
30
40
50
60
70
80
90
100
11012
0
130
FILLLOAD,kN/m
2
SETTLEMENTS,MM
0100
200
300
400
500
600
700
800
900
1000
1100
1200
1300
1400
1500
0.00
0.60
1.2
0
1.80
2.40
3.00
3.60
4.20
4.80
5.40
6.00
TIME,Years
SETTLEMENTS,MM
7/24/2019 Cirebon Power Plant_R0
35/213
01
209
791
209
79
0
791
209
0.1
0.3
0.7
1.2
1.9
2.7
3.9
5.4
8.1
121
242
363
484
605
725
846
967
1088
Ir.Wirastusrini,PE
LOAD-SETT
LEMENTS
TIME-SETTLEMENTS
Settlements(mm)
LayerThickness(m)
SettlementTime(years)
SettlementsbyFill(mm)
AverageLoad(kN/m
2)
78.97
1209
UnitWeight,
(kN/m
3)
Approvedby
Preparedby
Checkedby
Ir.Padmono,PE
Ir.KabulS.MSC
JobNo.
2358
16.5
4.79
AREASE
TTLEMENTANALYSISBH-20
PLATE1.9
PT.SOILENS
CIREBONTH
ERMALPOWERPLANTPR
OJECT
0200
400
600
800
1000
1200
1400
1600
1800
2000
2200
2400
0
10
20
30
40
50
60
70
80
90
100
11012
0
130
FILLLOAD,kN/m
2
SETTLEMENTS,MM
0200
400
600
800
1000
1200
1400
1600
1800
2000
2200
2400
0.00
0.80
1.60
2.40
3.20
4.00
4.80
5.60
6.40
7.20
8.00
8.80
TIME,Years
SETTLEMENTS,MM
7/24/2019 Cirebon Power Plant_R0
36/213
01
323
781
323
78
0
781
323
0.1
0.2
0.5
0.8
1.3
1.9
2.7
3.8
5.7
132
265
397
529
662
794
926
1058
1191
Ir.Wirastusrini,PE
LOAD-SETT
LEMENTS
TIME-SETTLEMENTS
Settlements(mm)
LayerThickness(m)
SettlementTime(years)
SettlementsbyFill(mm)
AverageLoad(kN/m
2)
78.06
1323
UnitWeight,
(kN/m
3)
Approvedby
Preparedby
Checkedby
Ir.Padmono,PE
Ir.KabulS.MSC
JobNo.
2358
16.5
4.73
AREASE
TTLEMENTANALYSISBH-21
PLATE1.10
PT.SOILENS
CIREBONTH
ERMALPOWERPLANTPR
OJECT
0200
400
600
800
1000
1200
1400
1600
1800
2000
2200
2400
0
10
20
30
40
50
60
70
80
90
100
11012
0
130
FILLLOAD,kN/m
2
SETTLEMENTS,MM
0200
400
600
800
1000
1200
1400
1600
1800
2000
2200
2400
0.00
0.60
1.2
0
1.80
2.40
3.00
3.60
4.20
4.80
5.40
6.00
TIME,Years
SETTLEMENTS,MM
7/24/2019 Cirebon Power Plant_R0
37/213
01
198
771
198
77
0
771
198
0.1
0.2
0.5
0.8
1.3
1.9
2.7
3.8
5.7
120
240
359
479
599
719
839
958
1078
Ir.Wirastusrini,PE
LOAD-SETT
LEMENTS
TIME-SETTLEMENTS
Settlements(mm)
LayerThickness(m)
SettlementTime(years)
SettlementsbyFill(mm)
AverageLoad(kN/m
2)
77.29
1198
UnitWeight,
(kN/m
3)
Approvedby
Preparedby
Checkedby
Ir.Padmono,PE
Ir.KabulS.MSC
JobNo.
2358
16.5
4.68
AREASE
TTLEMENTANALYSISBH-22
PLATE1.11
PT.SOILENS
CIREBONTH
ERMALPOWERPLANTPR
OJECT
0150
300
450
600
750
900
1050
1200
1350
1500
1650
1800
0
10
20
30
40
50
60
70
80
90
100
11012
0
130
FILLLOAD,kN/m
2
SETTLEMENTS,MM
0150
300
450
600
750
900
1050
1200
1350
1500
1650
1800
0.00
0.60
1.2
0
1.80
2.40
3.00
3.60
4.20
4.80
5.40
6.00
TIME,Years
SETTLEMENTS,MM
7/24/2019 Cirebon Power Plant_R0
38/213
01
169
701
169
70
0
701
169
0.1
0.2
0.5
0.8
1.3
1.9
2.7
3.8
5.7
117
234
351
468
585
701
818
935
1052
Ir.Wirastusrini,PE
LOAD-SETT
LEMENTS
TIME-SETTLEMENTS
Settlements(mm)
LayerThickness(m)
SettlementTime(years)
SettlementsbyFill(mm)
AverageLoad(kN/m
2)
70.08
1169
UnitWeight,
(kN/m
3)
Approvedby
Preparedby
Checkedby
Ir.Padmono,PE
Ir.KabulS.MSC
JobNo.
2358
16.5
4.25
AREASE
TTLEMENTANALYSISBH-23
PLATE1.12
PT.SOILENS
CIREBONTH
ERMALPOWERPLANTPR
OJECT
0200
400
600
800
1000
1200
1400
1600
1800
2000
2200
2400
0
10
20
30
40
50
60
70
80
90
100
11012
0
130
FILLLOAD,kN/m
2
SETTLEMENTS,MM
0200
400
600
800
1000
1200
1400
1600
1800
2000
2200
2400
0.00
0.60
1.2
0
1.80
2.40
3.00
3.60
4.20
4.80
5.40
6.00
TIME,Years
SETTLEMENTS,MM
7/24/2019 Cirebon Power Plant_R0
39/213
01
782
661
782
66
0
661
782
0.0
0.2
0.4
0.7
1.1
1.5
2.2
3.1
4.6
178
356
535
713
891
1069
1247
1426
1604
AREASE
TTLEMENTANALYSISBH-24
PLATE1.13
PT.SOILENS
CIREBONTH
ERMALPOWERPLANTPR
OJECT
UnitWeight,
(kN/m
3)
Approvedby
Preparedby
Checkedby
Ir.Padmono,PE
Ir.KabulS.MSC
JobNo.
2358
16
4.15
Ir.Wirastusrini,PE
LOAD-SETT
LEMENTS
TIME-SETTLEMENTS
Settlements(mm)
LayerThickness(m)
SettlementTime(years)
SettlementsbyFill(mm)
AverageLoad(kN/m
2)
66.38
1782
0200
400
600
800
1000
1200
1400
1600
1800
2000
2200
2400
0
10
20
30
40
50
60
70
80
90
100
110
120
FILLLOAD,kN/m
2
SETTLEMENTS,MM
0200
400
600
800
1000
1200
1400
1600
1800
2000
2200
2400
0.00
0.60
1
.20
1.80
2.40
3.00
3.60
4.20
4.80
5.40
TIME,Years
SETTLEMENTS,MM
7/24/2019 Cirebon Power Plant_R0
40/213
01
033
781
033
78
0
781
033
0.0
0.1
0.3
0.6
0.9
1.3
1.8
2.5
3.8
103
207
310
413
517
620
723
826
930
AREASE
TTLEMENTANALYSISBH-25
PLATE1.14
PT.SOILENS
CIREBONTH
ERMALPOWERPLANTPR
OJECT
UnitWeight,
(kN/m
3)
Approvedby
Preparedby
Checkedby
Ir.Padmono,PE
Ir.KabulS.MSC
JobNo.
2358
16.5
4.71
Ir.Wirastusrini,PE
LOAD-SETT
LEMENTS
TIME-SETTLEMENTS
Settlements(mm)
LayerThickness(m)
SettlementTime(years)
SettlementsbyFill(mm)
AverageLoad(kN/m
2)
77.76
1033
0200
400
600
800
1000
1200
1400
1600
1800
2000
2200
2400
0
10
20
30
40
50
60
70
80
90
100
11012
0
130
FILLLOAD,kN/m
2
SETTLEMENTS,MM
0200
400
600
800
1000
1200
1400
1600
1800
2000
2200
2400
0.00
0.40
0.8
0
1.20
1.60
2.00
2.40
2.80
3.20
3.60
4.00
TIME,Years
SETTLEMENTS,MM
7/24/2019 Cirebon Power Plant_R0
41/213
0
915
71
915
71
0
71
915
0.1
0.2
0.5
0.9
1.4
2.0
2.9
4.0
6.0
92
183
275
366
458
549
641
732
824
AREASE
TTLEMENTANALYSISBH-26
PLATE1.15
PT.SOILENS
CIREBONTH
ERMALPOWERPLANTPR
OJECT
UnitWeight,
(kN/m
3)
Approvedby
Preparedby
Checkedby
Ir.Padmono,PE
Ir.KabulS.MSC
JobNo.
2358
16.5
4.32
Ir.Wirastusrini,PE
LOAD-SETT
LEMENTS
TIME-SETTLEMENTS
Settlements(mm)
LayerThickness(m)
SettlementTime(years)
SettlementsbyFill(mm)
AverageLoad(kN/m
2)
71.23
915
0150
300
450
600
750
900
1050
1200
1350
1500
0
10
20
30
40
50
60
70
80
90
100
11012
0
130
FILLLOAD,kN/m
2
SETTLEMENTS,MM
0150
300
450
600
750
900
1050
1200
1350
1500
0.00
0.60
1.20
1.80
2.40
3.00
3.60
4.20
4.80
5.40
6.00
6.60
TIME,Years
SETTLEMENTS,MM
7/24/2019 Cirebon Power Plant_R0
42/213
Input
C h
2.9
E-07m/s=
9.1
5m/yearCoff.ofconsolid
ationforhorizontalflow
ToactivateIterationgotothemenu
T
120days=
1.0E
+07sec.
Consolidationtime
extra
options
calculation
d
0.0
65m
65mm
Theequivalentdiameter
andactivateiteratio
U h
0.9
5ratio
95%
Degreeofconsolidationrequired
t
12.0
0m
Draindepth
A
10,0
00m
Area
Outputm
1.
77
D
1.7
7
m
4,0
52
Numberofdrains
D D
1.6
9
m
48,6
19m
Totalamount
D
1.5
7
m
U
t(days)
0%
0
10%
4
20%
9
30%
14
40%
20
50%
28
60%
37
70%
48
80%
64
90%
92
99%
184
Calculationprogramf
ord
eterminingdraindistanceaccordingBarron
Triangularpattern
Squarepattern
Draininflu
encezone
PT.SOILENS
PLATE2.1
2358
PadmonoPE
KabulS.MSCE
WirastusriniPE
CIREBONTHERMALPOWERPLANTPROJECT,W
ESTJAVA
DRAINSPACINGCALC
ULATIONFORDETERMININGDRAINDISTANCE
JobNo
Preparedby
Checkedby
Approvedby
0.00.10.20.30.40.50.60.70.80.91.0 0
14
28
42
56
70
84
98
112
126
140
154
168
182
196
210
224
238
252
266
280
Times(days)
ConsolidationDegree,%
7/24/2019 Cirebon Power Plant_R0
43/213
CheckedbyK
abulS,
MSCE
PLATE2.2
ApprovedbyW
irastusrini,PE
DRAINSPACINGvs
TIMEREQUIREDTOREACH95%
SETTLEMENTS
JobNo.
2358
PT.SOILENS
PreparedbyP
admono,P
E
CIREBONTHERMA
LPOWERPLANTPROJECT,
WESTJAVA
0.00
0.25
0.50
0.75
1.00
1.25
1.50
1.75
2.00
2.25
2.50
2.75
3.00