19
Church Street Jr PS and Jesse Ketchum Jr & Sr PS Program Area Review Team Public Meeting May 3, 2017

Church Street Jr PS and Jesse Ketchum Jr & Sr PS Program ...€¦ · 1st Meeting – February 24, 2017 2nd Meeting – March 6, 2017 3rd Meeting – March 22, 2017 Report considered

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Church Street Jr PS and Jesse Ketchum Jr & Sr PS Program ...€¦ · 1st Meeting – February 24, 2017 2nd Meeting – March 6, 2017 3rd Meeting – March 22, 2017 Report considered

Church Street Jr PS and Jesse Ketchum Jr & Sr PS

Program Area Review Team

Public Meeting

May 3, 2017

Page 2: Church Street Jr PS and Jesse Ketchum Jr & Sr PS Program ...€¦ · 1st Meeting – February 24, 2017 2nd Meeting – March 6, 2017 3rd Meeting – March 22, 2017 Report considered

Welcome Parents and Community Members

Agenda6:30 to 8:30

1. 6:30 to 6:45 - Open House and Kiosk Information

2. 6:45 to 7:15 Presentation Why are we here? Review of current situation Timeline of Review Schools involved in the Program Area Review Options discussed at Program Review Team (PART) meetings Next Steps

3. 7:15 to 7:45 - Questions and Answers

4. 7:45 – 8:30 – Open House

Church Street Jr PS and Jesse Ketchum Jr & Sr PS PART – Public Meeting

Page 3: Church Street Jr PS and Jesse Ketchum Jr & Sr PS Program ...€¦ · 1st Meeting – February 24, 2017 2nd Meeting – March 6, 2017 3rd Meeting – March 22, 2017 Report considered

3

Why are we here?

TDSB’s Long-Term Program and Accommodation Strategy (LTPAS) is a 10 year plan and is reviewed annually to allow for flexibility and responsiveness to a changing environment

Church Street Jr PS was identified as a school which is currently over-capacity and will continue to be short classrooms

A series of working meetings have been conducted by TDSB staff and the Program Area Review Team (PART) to review data and discuss impacts of any proposed changes

The overall goal for today is to receive broader feedback from the parents and community members impacted by the potential changes

Opportunities to Provide FeedbackPublic Meeting – May 3, 2017Paper and Online Survey (Online survey due May 7, 2017)Planning & Priorities Committee Meeting – June 14, 2017

Church Jr Street PS and Jesse Ketchum Jr & Sr PS PART – Public Meeting

Page 4: Church Street Jr PS and Jesse Ketchum Jr & Sr PS Program ...€¦ · 1st Meeting – February 24, 2017 2nd Meeting – March 6, 2017 3rd Meeting – March 22, 2017 Report considered

4

Church Jr Street PS and Jesse Ketchum Jr & Sr PS PART – Public Meeting

Current Situation

Church Street Jr PSThe school has a utilization rate of 104% and is short 2 classrooms. Portables are

scheduled to be placed at the school site this summer to address the shortage of two classrooms and the continued growth in enrolment

Within the next 10 years, Church Street Jr PS enrolment is expected to grow to 133% utilization and be short 7 classrooms

Jesse Ketchum Jr & Sr PS

The school’s utilization rate is 75% and has extra classroom space

Page 5: Church Street Jr PS and Jesse Ketchum Jr & Sr PS Program ...€¦ · 1st Meeting – February 24, 2017 2nd Meeting – March 6, 2017 3rd Meeting – March 22, 2017 Report considered

5

Overview and Timeline of ReviewStudy Identified

The Long Term Program & Pupil Accommodation StrategyBoard Approval – June 2015 & June 2016

Staff Review ProcessLocal Feasibility Team (LFT)

Trustees, Superintendent, Principals and Planning Staff1st Meeting – February 24, 2017

2nd Meeting – March 6, 20173rd Meeting – March 22, 2017

Report considered by Central Accommodation Team - March 23, 20174th Meeting – April 4, 2017

TDSB Final Approval ProcessTrustees, Superintendent and Executive Staff

Report considered by Central Accommodation Team – May 2017Report considered by Planning and Priorities – June 14, 2017

Report considered by Board – June 21, 2017

Public Review Process Program Area Review Team (PART)

Trustees, Superintendent, Principals, School Representative, Design and Planning Staff

1st PART Working Meeting – April 10, 20172nd PART Working Meeting – April 20, 2017

2nd PART Working Meeting continued - April 25, 2017Public Meeting – May 3, 2017

3rd PART Working Meeting – May 8, 2017

Step 1

Step 2

Step 3(we are here)

Step 4

Church Jr Street PS and Jesse Ketchum Jr & Sr PS PART – Public Meeting

Page 6: Church Street Jr PS and Jesse Ketchum Jr & Sr PS Program ...€¦ · 1st Meeting – February 24, 2017 2nd Meeting – March 6, 2017 3rd Meeting – March 22, 2017 Report considered

Schools involved in the Program Area Review

6

Church Jr Street PS and Jesse Ketchum Jr & Sr PS PART – Public Meeting

Jesse Ketchum Jr & Sr PS

Church Street Jr PS

Page 7: Church Street Jr PS and Jesse Ketchum Jr & Sr PS Program ...€¦ · 1st Meeting – February 24, 2017 2nd Meeting – March 6, 2017 3rd Meeting – March 22, 2017 Report considered

What options will solve Church Street Jr PS long-term classroom shortage?

Need a 4 classroom solution in 2018

Need a 7 classroom solution in 2026

Grade Range

Change?

Boundary Change?

Retrofits?

7

Church Jr Street PS and Jesse Ketchum Jr & Sr PS PART – Public Meeting

Page 8: Church Street Jr PS and Jesse Ketchum Jr & Sr PS Program ...€¦ · 1st Meeting – February 24, 2017 2nd Meeting – March 6, 2017 3rd Meeting – March 22, 2017 Report considered

8

Options Discussed at Program Area Review Team (PART) Meetings

Church Jr Street PS and Jesse Ketchum Jr & Sr PS PART – Public Meeting

Page 9: Church Street Jr PS and Jesse Ketchum Jr & Sr PS Program ...€¦ · 1st Meeting – February 24, 2017 2nd Meeting – March 6, 2017 3rd Meeting – March 22, 2017 Report considered

9

LFT Proposed Boundary Change

Church Jr Street PS and Jesse Ketchum Jr & Sr PS PART – Public Meeting

Page 10: Church Street Jr PS and Jesse Ketchum Jr & Sr PS Program ...€¦ · 1st Meeting – February 24, 2017 2nd Meeting – March 6, 2017 3rd Meeting – March 22, 2017 Report considered

10

Boundary Change Options

Option A:

For the 2018/2019 school year, JK registrants and new families moving into the proposed boundary change area will register at Jesse Ketchum Jr & Sr PS. Existing 2017/2018 Church Street Jr PS students have the option to remain at Church Street Jr PS 1 Kindergarten class at Jesse Ketchum Jr & Sr PS in 2018/2019

5 classes by 2021

Option B:

For the 2018/2019 school year, all Church Street Jr PS students living within the boundary change area will be moving to Jesse Ketchum Jr & Sr PS (currently 82 students) 4 classes at Jesse Ketchum Jr & Sr PS in 2018/2019

5 classes by 2021

Church Jr Street PS and Jesse Ketchum Jr & Sr PS PART – Public Meeting

Page 11: Church Street Jr PS and Jesse Ketchum Jr & Sr PS Program ...€¦ · 1st Meeting – February 24, 2017 2nd Meeting – March 6, 2017 3rd Meeting – March 22, 2017 Report considered

11

Grade Range Change Option

Church Street Jr PS becomes a JK to Grade 5 school in 2018/2019 and will feed into Jesse Ketchum Jr and Sr PS at grade 6 1 class at Jesse Ketchum Jr & Sr PS in 2018/2019

2 classrooms by 2019

Church Jr Street PS and Jesse Ketchum Jr & Sr PS PART – Public Meeting

Page 12: Church Street Jr PS and Jesse Ketchum Jr & Sr PS Program ...€¦ · 1st Meeting – February 24, 2017 2nd Meeting – March 6, 2017 3rd Meeting – March 22, 2017 Report considered

12

Internal Retrofits at Church Street Jr PS

TDSB staff identified potential internal retrofits creating two additional classrooms at Church Street Jr PS for the 2018/2019 school year Relocate the kitchen/lunch room currently in Room 105 to Seminar Room 109

and convert Room 105 into a regular classroom

Convert Kindergarten Room 106 into 2 classrooms

Church Jr Street PS and Jesse Ketchum Jr & Sr PS PART – Public Meeting

The Program Area Review Team will continue to explore additional retrofits opportunities.

All retrofit proposals must be submitted to the TDSB facilities team for structural evaluation and cost estimates

Page 13: Church Street Jr PS and Jesse Ketchum Jr & Sr PS Program ...€¦ · 1st Meeting – February 24, 2017 2nd Meeting – March 6, 2017 3rd Meeting – March 22, 2017 Report considered

13

User Groups within Church Street Jr PS

Church Street School Day Care Service – 2 exclusive classrooms Native Learning Centre (TDSB Secondary School) – 3 exclusive classrooms Parenting and Family Literacy Centre (PFLC) – 1 exclusive classroom

Total Classrooms: 6

Church Jr Street PS and Jesse Ketchum Jr & Sr PS PART – Public Meeting

Page 14: Church Street Jr PS and Jesse Ketchum Jr & Sr PS Program ...€¦ · 1st Meeting – February 24, 2017 2nd Meeting – March 6, 2017 3rd Meeting – March 22, 2017 Report considered

14

Portables at Church Street Jr PS

Two portables at Church Street Jr PS are required for the 2017/2018 school year The portables will be used to address the shortage of classrooms and to be

used as flex space to accommodate students if enrolment exceeds projections Under the staff recommended scenario, portables will be required until 2026

or until there is absolute confidence portables will not be required in the future.

Church Jr Street PS and Jesse Ketchum Jr & Sr PS PART – Public Meeting

Page 15: Church Street Jr PS and Jesse Ketchum Jr & Sr PS Program ...€¦ · 1st Meeting – February 24, 2017 2nd Meeting – March 6, 2017 3rd Meeting – March 22, 2017 Report considered

15

Capital Request for Construction of Classroom Additions

The Ministry requires a business case that suggests the neighbouring schools are at capacity when considering approval for funding for classroom construction

Jesse Ketchum Jr & Sr PS would be considered to be a nearby school with available space to accommodate some of the Church Street Jr PS students, therefore acquiring capital would be a challenge

Church Jr Street PS and Jesse Ketchum Jr & Sr PS PART – Public Meeting

Page 16: Church Street Jr PS and Jesse Ketchum Jr & Sr PS Program ...€¦ · 1st Meeting – February 24, 2017 2nd Meeting – March 6, 2017 3rd Meeting – March 22, 2017 Report considered

2018 2026

Option 1 Boundary Change Boundary change in 2018‐19 for JK registrants and new families living within the new boundary.  Plus a two classroom retrofit. 

4               Boundary Change 

+ Retrofit + Portable 

7                 Boundary Change + 

Retrofit 

Option 2 Boundary Change 

Includes Option 1 but would also include current Church Street Jr PS students living within the new boundary. These students would move to Jesse Ketchum Jr & Sr PS. 

4               Boundary Change 

7                 Boundary Change + 

Retrofit 

Option 3 Grade Range Change

A grade range change in 2018‐19 for Church Street Jr PS to become a JK to Grade 5 school. Plus a two classroom retrofit.  In 2018‐19, Church Street Jr PS Grade 6 students would move to Jesse Ketchum School for Grade 6. 

3               Grade Range 

Change + Retrofit

4                 Grade Range 

Change + Retrofit

Other PART Ideas included: Additional Retrofits, User Groups: Relocation or reduction of exclusive space, Request to the Ministry of Education for funding for classroom additions

Local Feasibilty Team (Staff) Recommended Option:

Program Area Review Team (PART) Request for Further Options to Explore:

Number of Classroom Solution

Summary of Options

16

Church Jr Street PS and Jesse Ketchum Jr & Sr PS PART – Public Meeting

2018 – Church Street Jr PS is short 4 classrooms2026 – Church Street Jr PS is short 7 classrooms

Page 17: Church Street Jr PS and Jesse Ketchum Jr & Sr PS Program ...€¦ · 1st Meeting – February 24, 2017 2nd Meeting – March 6, 2017 3rd Meeting – March 22, 2017 Report considered

17

Next Steps

Church Jr Street PS and Jesse Ketchum Jr & Sr PS PART – Public Meeting

Program Area Review Team (PART) to review and consider feedback from this evening

Program Area Review Team (PART) to develop a set of recommendations and report

Program Area Review Team (PART) submits report summarizing recommendations to Central Accommodation Team (CAT) - May 2017

Planning & Priorities will consider Staff’s Report along with the PART ReportPrior to the Board meeting. Planning & Priorities is the opportunity for the public to depute to trustees– June 14, 2017

If staff recommendations are approved by Board of Trustees, affected Superintendents and Principals will notify staff and students and proceed with the addressing details regarding the transition. - June 2017

Page 18: Church Street Jr PS and Jesse Ketchum Jr & Sr PS Program ...€¦ · 1st Meeting – February 24, 2017 2nd Meeting – March 6, 2017 3rd Meeting – March 22, 2017 Report considered

18

Questions Town Hall Question Period until 7:45

Open House - 7:45 to 8:30

Church Jr Street PS and Jesse Ketchum Jr & Sr PS PART – Public Meeting

Page 19: Church Street Jr PS and Jesse Ketchum Jr & Sr PS Program ...€¦ · 1st Meeting – February 24, 2017 2nd Meeting – March 6, 2017 3rd Meeting – March 22, 2017 Report considered