CHINCHERO INTERNATIONAL AIRPORT
CUSCO - PERU
February 2014
2
BACKGROUND AND STRATEGIC STUDIES
� Entrusted to PROINVERSION – At the beginning of 2010, the Ministry of Transport
and Communications commissioned PROINVERSION to start the private investment
promotion process to transfer to the private sector, through a Public - Private
Partnership (PPP) the construction and operation to the New International Airport of
Chinchero – Cusco (AICC).
� Project Feasibility – PROINVERSION hired the services of an international company
specialist in airport matters:
• Initial strategic studies of the project were prepares articulating and validating
existing reports from the 1980s. Studies concluded that the construction and
operation of the AICC are completely feasible from a technical and operational
point of view and that some operational improvements could be achieved
compare to the airport currently operated.
• Due to the change in the funding scheme to a co-financing by the State
concession, in 2013, the consulting firm has developed the feasibility studies
according to the Peruvian legislation, which were approved by the Ministry of
Transport and Communications at September 30th, 2013.
3
CURRENT SITUATION
The International Airport Alejandro Velasco Astete (AIVA) is the second major
airport in Peru. It served 2.1 million passengers from January to November
2013.
The entrance of tourist to Cusco has grown significantly over the last 10 years.
Tourists arrivals tolodgings in Cusco (Mpax)
Source: MINCETUR
DomesticForeign
CURRENT SITUATION
• Orographic and meteorological restrictions of the AIVA airport limit its
technical capacity.
• Operations (landings and departures) are performed by a single threshold.
• The AIVA airport is surrounded by commercial and residential buildings.
• Residents constantly complain about airport noise.
4
Therefore, with the official announcement, the State
seeks to address:
► Sustainted growth expectation of traffic in Peru and
in Cusco.
► The tourism potential to be develop, which is at risk
of not being addressed by the limitations of the
AIVA airport
► The difficult inclusion of the AIVA airport in the
urban zone of Cusco, which involves operational,
safety complications and compatibility with the
citizens’ demandas.
CURRENT SITUATION
CHINCHERO INTERNATIONAL AIRPORT
Play
Lobitos
� Location: Chinchero and Huayllabamba
districts, Urubamba province, Cusco region.
� Description: Design, build, finance, operate
and transfer (DBFOT) of the new Chinchero
Internacional Airport.
� Estimated investment (VAT not includes):
• Total investment amount (includes
future interventions): US$ 658 Million
• Necessary investment to start
operations: US$ 538 Million
� Concession period: 40 years.
� Contest type: Integral Projects Contest
� Financing scheme: Co-financing by the
State
� Award Date: February 28th, 2014
CONTEST CALL
AIRPORT SITE LOCATION
7
Touristic Route
Chinchero is a mid-way stop between Cusco city and the Sacred Valley.
Driving distance from Cusco to Chinchero: 29
km, equivalent to 30 - 45 minutes by car or bus.
N
E
S
O
8
PASSENGER TRAFFIC FORECAST FOR CUSCO
Passenger Traffic Forecast of the AICC by type of flight
1.9 2.0 2.2 2.3 2.5 2.7 2.9 3.0 3.2 3.1 3.2 3.3 3.4 3.6 3.7 3.9 3.9 4.0 4.0 4.2 4.3 4.5 4.7 4.9 5.1
0.2 0.3 0.3 0.4 0.4 0.4 0.5 0.5 0.5 0.5 0.50.5
0.50.6
0.60.6
1.9 2.1 2.2 2.4 2.5 2.7 2.9 3.0 3.2 3.3 3.5 3.6 3.8 4.0 4.24.3 4.4 4.4 4.5 4.6
4.85.0
5.25.4
5.7
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
2025
2026
2027
2028
2029
2030 …
2035 …
2040 …
2045 …
2050 …
2055 …
2060
Pasajeros rutas internacionales
Pasajeros rutas domésticas
CAGRInternacional: 30.2%
Doméstico: 4.8%Total: 5.6%
CAGRInternacional: 0.8%
Doméstico: 0.8%Total: 0.8%
Foreign Passengers
Domestic Passengers
9
� 40,000 m2 passenger terminal with IATA Level of Service “B” (eco-friendly design)
� 16.8 Million m3 of earth moving works
� 4,000 x 45 m ILS CAT 1 RWY 16-34 (ICAO ref. code 4-E)
� 4,000 m parallel TWY
� 13 positions initial aircraft parking capacity (140,000 m2)
� 4.5 Mpax initial airport capacity
MINIMUM TECHNICAL REQUIREMENTS
SCHEDULE OF THE CONTEST 1/
Play
Lobitos
ACTIVITY DATE
Last day for the submission of Envelope N° 1 Up to 01/31/2014
Comments to Envelope N°1 Up to two (2) Working Days after the
submission of Envelope N° 1
Amendments to Envelope N°1 Up to three (3) Working Days after the
delivery of comments to Envelope N° 1
Communication of the Bidder's Shortlisting As from the seven (7) Working Days from
the submission of Envelope N° 1
Delivery of the Final Contract Version to the
Comptroller General's Office and Shortlisted Bidders.
03/07/2014
Deadline for consortium modification 04/08/2014
Submission of Envelopes N° 2 and N° 3 04/22/2014
Publications of Results of the Evaluation of Envelope
N°2
04/25/2014
Opening of Envelope N° 3 and Award 04/25/2014
Closing Date Shall be informed by Circular Letter
10
1/ This dates has been taken from Annex N°2 Process sch edule.
SHORT-LISTING REQUIREMENTS
AIRPORT
MANAGEMENT AND
OPERATION CAPACITY
AIRPORT
MANAGEMENT AND
OPERATION CAPACITY
INFRASTRUCTURE
CONSTRUCTION
CAPACITY +
AIRPORT MANAGEMENT
AND OPERATION
CAPACITY
INFRASTRUCTURE
CONSTRUCTION
CAPACITY +
AIRPORT MANAGEMENT
AND OPERATION
CAPACITY
OR
TECHNICAL - OPERATIONAL FINANCIAL
MINIMUM EQUITY
US$ 140 MILLION
MINIMUM EQUITY
US$ 140 MILLION
MINIMUM ANUAL
TURNOVER
US$ 48 MILLIONS
MINIMUM ANUAL
TURNOVER
US$ 48 MILLIONS
+
12
3-D VIEW OF THE FUTURE AIRPORT
CONTAC INFORMATION
Giancarlo Villafranqui Head of Airport Projectss
Teléfono (51-1) 200-1200 extensión 1206
E-mail [email protected]