    CHECKLIST FOR CONTROL & INSTRUMENTATION COMMISSIONING

    (NEW & R&M PROJECTS)

    CORPORATE OS-C&I

    1. POWER SUPPLY

    SLN

    O

    DESCRIPTION REMARKS

    1. UPS

    Complete configuration of UPS including chargers,

    inverters, and static switch, battery and distributionboxes erected and commissioned.

    Inverter and charger pairs are in service.

    Cables glanded and connected properly.

    All spare gland holes sealed. (Cabling may not becompleted in distribution panels.)

    Proper tags on panels like inverter A, charger B etc andall breakers provided.

    Incoming (415Vac) feeders are identified.

    Check general condition of UPS room is satisfactory.

    (Civil works like walls, flooring and tiling completed.Air condition satisfactory. Room is clean.)

    Earthing completed as per drawing.

    Check displays for voltage, frequency and current of

    inverters and chargers to judge healthiness.

    Check condition of battery and battery room.Check polarities of battery terminal marked.

    Number of cells as per design available in each battery

    bank.

    Check signed protocols are available for UPS

    commissioning.

    Note down name plate details of inverter, charger and

    cells.

  • 7/29/2019 Checklist of c&i for Full Load Operation

    2/9

    2. CHARGERS

    Complete configuration of chargers including battery and

    distribution boxes erected and commissioned.

    Check displays for voltage, frequency and current of

    chargers and ensure float voltage is set for proper battery

    and at panel ends.

    Check condition of cleanliness of charger, battery and

    battery room.

    Check polarities of battery terminal marked.

    Number of cells as per design available in each battery

    bank.Check signed protocols are available for chargers

    commissioning

    Note down name plate details of chargers and cells.

    2.0 CER / CCR

    CCR civil works completed (walls, flooring , ceiling andtiles)

    A/C is available and marinating temperature.

    General cleanliness of CCR is OK.

    Unused panel cutouts are sealed.

    Mounting arrangement of panels is OK.

    CER civil works completed (walls, flooring and tiles).A/C is available and marinating temperature.

    General cleanliness of CER is OK.

    Unused panel cutouts are sealed.

    Mounting of panels is OK

    Lighting sufficient

    Signed protocols are available for workstations, LVS andemergency push buttons commissioning.

  • 7/29/2019 Checklist of c&i for Full Load Operation

    3/9

    3 DCS

    General condition of DCS panels satisfactory.

    Proper tags of available on all panels.

    Signal cables properly glanded, supported and dressed

    inside panels.

    Power cables properly glanded, supported and dressed

    inside panels,

    Screen is sleeved and connected to identified terminals.

    Redundant power to panels as per drawing wired andavailable.

    Communication cables dressed, supported andconnected.

    Redundant communication network connected to each

    controller.

    All hardware like redundant controllers is available in

    controller panels.

    No faults are persisting on controllers, communication

    and other modules.

    Panel to panel interconnection cables are properly routed

    and terminated.

    Status of commissioned controllers is available on

    workstations.Switches, hubs, converters are mounted as per drawing

    and all cables are tagged.

    Complete configuration of DCS network completed or

    pending jobs.

  • 7/29/2019 Checklist of c&i for Full Load Operation

    4/9

    4. OPERATOR/ENGINEER WORKSTATIONS ANDLVS

    Workstations, UPS and LVS are available and

    functional.

    PCs have proper mounting arrangement.

    All servers, PCs and UPS are tagged as per their

    function.

    Annunciation provided on LVS is working.

    Emergency push buttons for boiler, turbine and

    auxiliaries installed and commissioned.

    SOE commissioned and simulations done for all inputs

    Lighting sufficient

  • 7/29/2019 Checklist of c&i for Full Load Operation

    5/9

    5. CABLING, JUNCTION BOXES.

    Cable gallery

    General house keeping is good

    Trays are not overloaded.

    Cables are not hanging from trays

    Cables are dressed properly

    There is no mixing of power and signal cables.

    Coaxial cables are laid as per drawing and well

    protected.

    Fiber optic cables are laid as per drawing and wellprotected.

    CABLING NEAR INSTRUMENTS, JUNCTION

    BOXES AND BRANCH TRAYS

    Junction boxed are mounted as per drawing and tagged.

    Branch trays are complete upto the junction box and

    instrument.

    Cables are away from hot surface

    Cables glanded at JB and instruments.

    There is no mixing of power and signal cables

    Junction boxes are earthed

  • 7/29/2019 Checklist of c&i for Full Load Operation

    6/9

    6. LOCAL INSTRUMENTS

    Local instruments, E/P converters etc are properly

    mounted on frames

    Instruments, thermocouples and RTDs are tagged.

    Cable are glanded and cable entry sealed

    Cables are tagged.

    Canopies are provided where necessary.

    Copper tubes are neatly laid and supported.

    No leakage in instruments which are charged.

    Root valves and isolation valves provided as per

    scheduleCalibration reports of all instruments available

    Complete schedule of flow elements, transmitters,

    gauges available with site

    Calibration report of flow elements (with curves)

    available.

  • 7/29/2019 Checklist of c&i for Full Load Operation

    7/9

    7. ACTUATORS

    Actuators have free access and platform for working

    General condition of actuator (painting, body condition)is good

    Cables are tagged, glanded and connected securely.

    Actuator tags are available

    All gland holes, covers on the actuator are sealed toprevent water entry.

    Actuator schedule, commissioning report, power supplyfeeder details with fuse rating , full open/close timing

    availableAir pressure regulator, air lock and other accessories are

    provided as per drawing for pneumatic actuators.

    Positioner, feedback transmitters and solenoid valves areproperly covered and sealed. Cables are glanded and

    sealed.

    Check for Instrument air leakage

  • 7/29/2019 Checklist of c&i for Full Load Operation

    8/9

    8. SWAS & OXYGEN ANALYZER

    General cleanliness of SWAS room OK

    Wet Panel erection, panel condition OK

    Sample conditioning equipment (coolers, pressure

    regulators, cation columns etc) for all samples tagged.

    No leakages in lines charged.

    Sample temperature within limits

    Pressure, temperature and flow indicators provided and

    working

    Grab samples available

    Sample table drains taken out through pipe to designatedplace and not left open any where

    Chiller Unit commissioned and working.

    Insulation of sample lines, cold water lines as required

    are completed.

    Lighting inside panel and in the room sufficient

    Analyzer panel general condition OK

    Analyzers installed and have proper tags

    No leakages of sample or reactants

    Room temperature maintained by AC

    Analyzer readings are available on DCS workstation

    Oxygen probes are located at identified location as perP&ID

    Flue gas oxygen analyzers installed and commissioned at

    all locations as per P&ID.

    Oxygen analyzers readings available at UCB

  • 7/29/2019 Checklist of c&i for Full Load Operation

    9/9

    9. DOCUMENTATION1. Following signed commissioning protocols are

    available with site commissioning:

    Chargers and battery commissioning

    UPS commissioning

    Charging of panels and power supply change over

    Boiler Protection

    Oil and coal elevations & scanners commissioning

    P&I checks of boiler auxiliaries (ID/FD/PA/SGWC/Air

    Heater (including fire protection) etc.)

    Commissioning of servers, change over

    Commissioning of redundant networksEHC, P&I, TSI, ATRS ATT of turbine

    Auto synchronizer

    P&I of turbine auxiliaries (BFP, CEP, Heaters etc)

    Commissioning of BOP equipments (if C&I is involved)

    2. Calibration reports of all instruments, alarm and trip

    settings, PID settings (pending fine tuning), and

    calibration curves for flow elements shall be documentedand available.

    3. Calibration report of TSI with procedure

    4. SFD, FCD, jumper settings available

    5. Drawings of FSSS, EHC, turbine protections, alarmand SOE list available

    6. DCS manuals.