www.energy.gov/EM 1 Approved for Public Release; Further Dissemination Unlimited CHBWV Project Update Scott Anderson Deputy General Manager Quarterly Public Meeting February 24, 2016

CHBWV Project Update€¦ · Approved for Public Release; Further Dissemination Unlimited 1 CHBWV Project Update Scott Anderson Deputy General Manager Quarterly Public Meeting

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: CHBWV Project Update€¦ · Approved for Public Release; Further Dissemination Unlimited  1 CHBWV Project Update Scott Anderson Deputy General Manager Quarterly Public Meeting

www.energy.gov/EM 1Approved for Public Release; Further Dissemination Unlimited

CHBWV Project Update

Scott AndersonDeputy General Manager

Quarterly Public MeetingFebruary 24, 2016

Page 2: CHBWV Project Update€¦ · Approved for Public Release; Further Dissemination Unlimited  1 CHBWV Project Update Scott Anderson Deputy General Manager Quarterly Public Meeting

www.energy.gov/EM 2Approved for Public Release; Further Dissemination Unlimited

Safety Performance

• As of January 28, 2016, CHBWV and subcontractors worked approximately

1,809,622 work hours (1,179 days) without a lost-time work accident or illness.

10-Plex Office Installation

Grouting Activities in the Main Plant

Process Building (MPPB)

Water Line Directional Boring

Page 3: CHBWV Project Update€¦ · Approved for Public Release; Further Dissemination Unlimited  1 CHBWV Project Update Scott Anderson Deputy General Manager Quarterly Public Meeting

www.energy.gov/EM 3

• Five High-Level Waste (HLW) canisters loaded into a Vertical Storage Cask

(VSC) and relocated to the HLW Interim Storage Pad – November 10, 2015

• Three additional VSCs were relocated to the HLW Interim Storage Pad in

2015 (November 30 - December 22) Each VSC contains 5 canisters for a total of 20 HLW canisters

VSC loaded for Transport

Milestone 1: High-Level Waste

Accomplishments

1st Cask Placed on the Interim

Storage Pad

1st Cask Loaded onto Vertical Cask

Transporter

Page 4: CHBWV Project Update€¦ · Approved for Public Release; Further Dissemination Unlimited  1 CHBWV Project Update Scott Anderson Deputy General Manager Quarterly Public Meeting

www.energy.gov/EM 4Approved for Public Release; Further Dissemination Unlimited

• Planning for remaining VSCS

• 16 VSCs have already been fabricated (4 have been loaded)

• NAC International will resume on-site construction of VSCs in April 2016

• Complete relocation of remaining VSCs in 2016

• High-Level Waste (HLW) campaign resumes April 25, 2016

• Resume at rate of one VSC per week to Interim Storage Pad

• Increase to rate of two VSCs to Interim Storage Pad per week starting June

2016

• Employ a two shift/day; four day/ week operations schedule

• First 6 VSCs loaded, welded and relocated on a single shift for training and

proficiency

• Additional craft and support labor hiring ongoing

Milestone 1: 2016 Look Ahead

Page 5: CHBWV Project Update€¦ · Approved for Public Release; Further Dissemination Unlimited  1 CHBWV Project Update Scott Anderson Deputy General Manager Quarterly Public Meeting

www.energy.gov/EM 5Approved for Public Release; Further Dissemination Unlimited

• Degraded Containers Placed

• on Dunnage

Degraded Container Over-packed and Shipped to Nevada

National Security Site (NNSS)

Asbestos Debris Shipped to Ohio

Milestone 2: Waste Operations

Accomplishments

Page 6: CHBWV Project Update€¦ · Approved for Public Release; Further Dissemination Unlimited  1 CHBWV Project Update Scott Anderson Deputy General Manager Quarterly Public Meeting

www.energy.gov/EM 6Approved for Public Release; Further Dissemination Unlimited

First of Its Kind – The Shipment of Vitrification Components

CHBWV received Special Package Authorization

from the US Nuclear Regulatory Commission

(NRC) to ship the melter, primarily by rail, for

disposal to Waste Control Specialist (WCS) in

Andrews, Texas in October 2016.

Milestone 2: 2016 Look Ahead

Page 7: CHBWV Project Update€¦ · Approved for Public Release; Further Dissemination Unlimited  1 CHBWV Project Update Scott Anderson Deputy General Manager Quarterly Public Meeting

www.energy.gov/EM 7Approved for Public Release; Further Dissemination Unlimited

• Off-Gas Cell (OGC) – Completed stabilization of embedded pipe penetration (foam) and grouted

sump

• Off-Gas Blower Room (OGBR) – Completed dewatering and grouting of below-grade pump niches

and stabilized embedded pipe penetrations

• Acid Recovery Cell (ARC) and Acid Recovery Pump Room (ARPR) – Completed stabilization of

embedded pipe penetration

• Uranium Process Cell (UPC) – Reconnected utilities and returned pumps to service for processing

wastewater in tanks; collected waste water sample for analysis

MPPB Deactivation

Off-Gas Cell Embedded Wall

Penetration Stabilization OGBR Floor and Niche Grouting

Milestone 3: Facility Disposition

Accomplishments

Page 8: CHBWV Project Update€¦ · Approved for Public Release; Further Dissemination Unlimited  1 CHBWV Project Update Scott Anderson Deputy General Manager Quarterly Public Meeting

www.energy.gov/EM 8Approved for Public Release; Further Dissemination Unlimited

High-Level Waste Trench

Pipe Removal

Downdraft Table Loadout in Vit Cell

Continue equipment removal in the

Vitrification Facility in preparation for

demolition activities to begin FY2017

Milestone 3: 2016 Look Ahead

Page 9: CHBWV Project Update€¦ · Approved for Public Release; Further Dissemination Unlimited  1 CHBWV Project Update Scott Anderson Deputy General Manager Quarterly Public Meeting

www.energy.gov/EM 9Approved for Public Release; Further Dissemination Unlimited

NDA Inspection and Repair

• Installed new water line to locker rooms

• Shipped S-09 Stormwater Outfall soils for off-site

disposal (11 of 11 intermodals)

• Completed biennial NRC-Licensed Disposal Area

(NDA) inspection

• Removed Enkamat from Buttermilk Creek

• Installed erosion markers in spillway Enkamat Removal

Water Line Installation

Milestone 4: Site Operations

Page 10: CHBWV Project Update€¦ · Approved for Public Release; Further Dissemination Unlimited  1 CHBWV Project Update Scott Anderson Deputy General Manager Quarterly Public Meeting

www.energy.gov/EM 10Approved for Public Release; Further Dissemination Unlimited

Personnel Relocation

• Relocated approximately 35 DOE, NYSERDA and

CHBWV personnel from Administrative Office

Building

• Human Resource Turn-Around, Nurse’s station,

4-Plex and comfort station delivered and set-up

• Final personnel relocation planned for March

2016

4-Plex Office Space Set-up Complete

10-Plex Office Complex Set-up Underway

Milestone 4: Site Operations

Page 11: CHBWV Project Update€¦ · Approved for Public Release; Further Dissemination Unlimited  1 CHBWV Project Update Scott Anderson Deputy General Manager Quarterly Public Meeting

www.energy.gov/EM 11

Surveillance &

Maintenance and Site

Services

$29 million/48%

HLW

Canister

Relocation

$10 million/

16%

D&D

$11million/

18%

Waste

Disposition

$11 million/

18%

FY2016 Funding Allocation - $61M

Page 12: CHBWV Project Update€¦ · Approved for Public Release; Further Dissemination Unlimited  1 CHBWV Project Update Scott Anderson Deputy General Manager Quarterly Public Meeting

www.energy.gov/EM 12Approved for Public Release; Further Dissemination Unlimited

Questions?