27
CHARU KANDPAL THDC INSTITUTE OF HYDROPOWER ENGINEERING AND TECHNOLOGY Summer Training Report TEHRI HYDRO POWER PLANT

Charu Kandpal Final Report on HEP

  • Upload
    -

  • View
    241

  • Download
    5

Embed Size (px)

DESCRIPTION

Summer Training Report of Tehri Hydro Development Corporation

Citation preview

  • CHARU KANDPAL

    THDC INSTITUTE OF HYDROPOWER

    ENGINEERING AND TECHNOLOGY

    Summer Training Report

    TEHRI HYDRO POWER PLANT

  • TEHRI HYDRO POWER PLANT Summer Training Report

    1 | P a g e Charu Kandpal THDC Institute of Hydropower Engineering and Technology 2014-15

    Table of Contents

    Serial Number

    Topics Page Number

    Submission Details 2 Acknowledgement 3 Introduction 4 Energy Scenario In India 5 Types of Power plants 7 Features of Tehri Dam 9 Components of Tehri HEP 11 Power Generation 15 Excitation System 16 Braking System 18 Governor System 19 Gas Insulated Switchyard 21 Computerized Control Room 23 References 25 Epilogue 26

  • TEHRI HYDRO POWER PLANT Summer Training Report

    2 | P a g e Charu Kandpal THDC Institute of Hydropower Engineering and Technology 2014-15

    Submission Details

    Name of the organization- Tehri Hydro Development Corporation

    Location of Power House- Bhagirathi Puram, Tehri Garhwal

    Duration of Training- July 23rd, 2014 to august 2nd, 2014

    Title of Report- Tehri Hydro Power Plant

    Submitted To- Er. S.K. Arya

    Name- Charu Kandpal

    College- THDC Institute of Hydr0power Engineering and Technology

    University- Uttarakhand Technical University

    Branch- Electrical Engineering

    Roll No. - 110970105019

    Guides:

    1) Er. D. P. Kothiyal

    2) Er. P. C. Pandey

    3) Er. Rakesh Panwar

    4) Er. Sachin Vyas

    5) Er. Arpan Kumar

    6) Er. Shrikant Pant

    7) Er. Rahul Joshi

  • TEHRI HYDRO POWER PLANT Summer Training Report

    3 | P a g e Charu Kandpal THDC Institute of Hydropower Engineering and Technology 2014-15

    Acknowledgement

    I would like to sincerely thank Mr. Seemant Pant, Deputy General Manager THDC India Limited, for his immense support that has

    made this training possible. I would also like to thank Mr. S.K.Arya, Senior Manager (O&M) for their great supervision as a mentor.

    I would like to whole heartedly thank all the guides for their true

    effort they put in to make us understand principles behind working

    of all sections in brief.

    Charu Kandpal

    THDC Institute of Hydropower Engineering and Technology

    Uttarakhand Technical University

  • TEHRI HYDRO POWER PLANT Summer Training Report

    4 | P a g e Charu Kandpal THDC Institute of Hydropower Engineering and Technology 2014-15

    ntroduction

    THDC-

    TEHRI HYDRO DEVELOPMENT CORPORATION, or THDC, is

    a joint venture of the Central Government and Uttar Pradesh State

    Government.

    Tehri Dam-

    The Tehri Dam is a multi-purpose rock and earth-fill embankment dam at

    the confluence of Bhagirathi and Bhilangna River at Tehri in Uttarakhand, India. Tehri Hydro

    Power Projects comprises of three phases.

    Phase 1. Tehri HEP (4X250MW) was completed in 2006.

    Phase 2. Koteshwar HEP (4X100MW) was completed in 2012.

    Phase 3. (4X250MW) Pumped storage Plant of hydroelectricity generation is under

    construction.

    This dam is Asias largest & worlds 3rd. largest rock fill dam. The area of the

    reservoir is around 44 km2 and the catchment area expands to over 7511

    km2 The complex will afford irrigation to an area of 270,000 hectares

    (670,000acres), irrigation stabilization to an area of 600,000 hectares

    (1,500,000acres). and a supply of 270 million gallons of drinking water per day

    to the industrialized areas of Delhi, Uttar Pradesh and Uttarakhand ,

    thereby supplying drinking water to over ten million people

    I

  • TEHRI HYDRO POWER PLANT Summer Training Report

    5 | P a g e Charu Kandpal THDC Institute of Hydropower Engineering and Technology 2014-15

    nergy Scenario in India

    Coal dominates the energy mix in India, contributing to 55% of the total primary energy

    production. Over the years, there has been a marked increase in the share of natural gas in

    primary energy production from 10% in 1994 to 13% in 1999. There has been a decline in the

    share of oil in primary energy production from 20% to 17% during the same period.

    Coal Power:

    India has huge coal reserves, at least 84,396 million tons of proven recoverable reserves

    (at the end of 2003). These amounts to almost 8.6% of the world reserves and it may last for

    about 230 years at the current Reserve to Production (R/P) ratio. In contrast, the world's

    proven coal reserves are expected to last only for 192 years at the current R/P ratio.

    Natural Gas:

    Natural gas accounts for about 8.9 per cent of energy consumption in the

    country. The current demand for natural gas is about 96 million cubic meters per day (mcmd) as

    against availability of 67 mcmd. By 2007, the demand is expected to be around 200 mcmd.

    Natural gas reserves are estimated at 660 billion cubic meters.

    Hydro Power:

    India is endowed with a vast and viable hydro potential for power generation of

    which only 15% has been harnessed so far. The share of hydropower in the country's total

    generated units has steadily decreased and it presently stands at 25% as on 31st May 2004. It is

    assessed that exploitable potential at 60% load factor is 84,000 MW.

    E

  • TEHRI HYDRO POWER PLANT Summer Training Report

    6 | P a g e Charu Kandpal THDC Institute of Hydropower Engineering and Technology 2014-15

    Nuclear Power:

    Nuclear Power contributes to about 2.4 per cent of electricity generated in India.

    India has ten nuclear power reactors at five different nuclear power stations. More nuclear

    reactors have also been approved for construction.

    Figure 1: Energy Production by Different Sectors in India

  • TEHRI HYDRO POWER PLANT Summer Training Report

    7 | P a g e Charu Kandpal THDC Institute of Hydropower Engineering and Technology 2014-15

    ypes of Power Plants

    Power Plant:

    A power plant or a power generating station is basically an industrial location

    that is utilized for the generation and distribution of electric power in mass scale. Since for the

    purpose of bulk power generation, only thermal, nuclear and hydro power comes handy,

    therefore a power generating station can be broadly classified in the 3 below mentioned types.

    Thermal Power Station:

    It uses coal as the primary fuel to boil the water available to superheated steam for driving the steam turbine. The steam turbine is then mechanically coupled to an alternator rotor, the rotation of which results in the generation of electric power.

    Nuclear Power Station:

    In nuclear power plant, the radioactive fuels are made to undergo fission reaction within the nuclear reactors. The fission reaction propagates like a controlled chain reaction and is accompanied by unprecedented amount of energy produced, which is manifested in the form of heat. This heat is then transferred to the water present in the heat exchanger tubes. As a result, super-heated steam at very high temperature is produced.

    Hydro-Electric Power Station:

    In Hydro-electric plants the energy of the falling water is utilized to drive the turbine which in turn runs the generator to produce electricity. Rain falling upon the earths surface has potential energy relative to the oceans towards which it flows. This energy is converted to shaft work where the water falls through an appreciable vertical distance. The hydraulic power is therefore a naturally available renewable energy given by the equation:

    Where g = acceleration due to gravity = 9.81 m/sec 2

    T

  • TEHRI HYDRO POWER PLANT Summer Training Report

    8 | P a g e Charu Kandpal THDC Institute of Hydropower Engineering and Technology 2014-15

    = density of water = 1000 kg/m 3

    H = height of fall of water i.e. gross head

    This power is utilized for rotating the alternator shaft, to convert it to equivalent electrical

    energy.

    An important point to be noted is that, the hydro-electric plants are of much lower capacity

    compared to their thermal or nuclear counterpart. For this reason hydro plants are generally

    used in scheduling with thermal stations, to serve the load during peak hours. They in a way

    assist the thermal or the nuclear plant to deliver power efficiently during periods of peak hours.

  • TEHRI HYDRO POWER PLANT Summer Training Report

    9 | P a g e Charu Kandpal THDC Institute of Hydropower Engineering and Technology 2014-15

    eatures of Tehri Dam

    Reservoir

    Full Reservoir Level (F.R.L) EL 830 M

    Maximum Level During Design Flood EL 835 M

    Dead Storage Level (D.S.L) EL 740 M

    Water Spread at F.R.L 42 Sq. KM

    Water Spread at D.S.L 18 Sq. KM

    Dam

    Type Earth and Rock Fill Dam

    Top Level 839.5 M

    Height 260.5 M

    Width at Riverbed 1125 M

    Length at Top 592 M

    Spillway

    Chute Spillway

    Crest Level EL 815 M

    Waterways 3 bays of 10.5 M each

    Type and No. Of Gates Radial Gates, 3 Nos

    Right Bank Shaft Spillway

    Type and No. of Gates Ungated, 2 Nos

    Crest Level 830.2 M

    Diameter of Shaft 12 M

    Left Bank Shaft Spillway

    Type and No. Of Gates Radial Gated, 2 Nos

    Crest Level EL 815 M

    Diameter of Shaft 12 M

    Intermediate Level Outlet

    Number One

    Size (Diameter) 8.5 M

    F

  • TEHRI HYDRO POWER PLANT Summer Training Report

    10 | P a g e Charu Kandpal THDC Institute of Hydropower Engineering and Technology 2014-15

    Penstocks

    Numbers 4

    Size 5.75 M dia. Each

    Total Length 1040 M

    Power House

    Machine Hall

    Type Underground

    Location Left Bank, Underground

    Number & Units 4, 250 MW each

    Head Maximum: 231.5 M Minimum: 127.5 M Designed: 188.0 M

    Transformer Hall

    Type Underground

    Size 16118.529 M

    Step Up Transformer

    Capacity 306 MVA

    Number 4

    Voltage Ratio 15.75/420 KV

    Switchyard

    Type Indoor SF-6 Switchgear

    Tail Race Works

    Number and Size of Tail Race Tunnel 2 Nos, 9.0 M dia. Each

    Length of Tunnels 862.5 M, 747.5 M

    Insert Level of Outlet EL 598 M

    Installed Capacity

    Total 2400 MW

    Tehri- I 1000 MW

    Tehri- II 1000 MW

    Koteshwar 400 MW

  • TEHRI HYDRO POWER PLANT Summer Training Report

    11 | P a g e Charu Kandpal THDC Institute of Hydropower Engineering and Technology 2014-15

    omponents of Tehri HEP

    Earth and Rock Fill Dam:

    The dam is earth and rock fill type & its height is 260.5m. The length at the top is 592 m & width is 25.5 m. The elevation of the top of the dam is 842 m.

    Figure 2: Tehri Earth and Rock Fill Dam

    Head Race Tunnel-

    There are 04 Numbers of HRTs on the Right Bank of the reservoir having

    circular shape, 8.5 m diameter. The lengths of HRTs are 779 m, 855 m, 997 m &1033 m. It takes

    water from reservoir and supplies it to power house machines for generation. HRT-1 and

    HRT-2 carry the later to Hydro power plant (HPP). HRT-3 and HRT-4 carry the water to the

    pump storage plant (PSP) which is still an ongoing project and is not functional right now.

    C

  • TEHRI HYDRO POWER PLANT Summer Training Report

    12 | P a g e Charu Kandpal THDC Institute of Hydropower Engineering and Technology 2014-15

    Penstocks:

    Water enters through the different penstocks to the different generating units.

    Each penstock comprises upper horizontal, vertical & lower horizontal reach including upper &

    lower bend. The diameter of penstock is 5.75 m.

    Inlet Valves:

    One Butterfly Inlet Valve (BIV) at mouth of the each penstock and one machine inlet

    valve (MIV) before the spiral casing are installed. The valve remains close in case of unit

    shutdown.

    When the unit is started then after sensing the starting command, MIV opens first to build up

    the pressure in spiral casing and roll the turbine.

    Figure 3: Head Race Tunnel

    Figure 4: Butterfly Inlet Valve

  • TEHRI HYDRO POWER PLANT Summer Training Report

    13 | P a g e Charu Kandpal THDC Institute of Hydropower Engineering and Technology 2014-15

    Turbine:

    Four Vertical Francis turbines are installed having net head of 188 meter.

    Water from the spiral casing enters through the 28 guide vanes and strikes the 14 blades of the

    runner, which is coupled to the main shaft. The shaft is coupled to the rotor of the generator at

    the other end. The opening of guide vanes depends upon the generation requirement. Water

    strikes the blades of the runner and fall axially in the draft tube. For keeping shaft vertically,

    Turbine guide bearing is installed which is of rotating sump self-cooled type.

    Generator:

    It is 278 MVA, 0.9pf, 50HZ, 3 Phase generator which generates power at a

    voltage of 15.75 KV. A generator has two parts, Stator and Rotor. Power generated is

    transmitted through isolated phase bus duct to transformer gallery from where it is stepped up

    to 400 KV by GSU transformers. Two bearings named as Thrust bearing and upper guide

    bearing are installed for sustaining the outward thrust of rotor and keeping shaft verticality.

    Both the bearings are of water cooled type. The direction of rotation is anticlockwise when

    viewed from the top.

    Figure 5: Main Inlet Valve

  • TEHRI HYDRO POWER PLANT Summer Training Report

    14 | P a g e Charu Kandpal THDC Institute of Hydropower Engineering and Technology 2014-15

    Transformer Gallery:

    Eight in numbers, 306 MVA, 15.75/ 400KV GSU 3 Phase transformers are

    installed in transformer gallery (TG) for the four units. Other four set of transformers are

    installed for upcoming Pumped Storage Plant (PSP). 15.75 KV is generated from the each unit

    and this power is stepped up to 400 KV here and sent to switchyard through oil filled cables.

    These generating transformers are provided with makeup valve which is filled with water that

    cools the oil that is being used to cool the transformer. These transformers are also equipped

    with micro wave detector which detects the microwave that generated In case of some spark

    and raises the alarm. Transformer oil conditioner is used to purify the oil which is used to cool

    the transformer and eliminates different gases from the oil that got mixed during the cooling

    process.

    Figure 6: Turbine and Generator in a HPP

  • TEHRI HYDRO POWER PLANT Summer Training Report

    15 | P a g e Charu Kandpal THDC Institute of Hydropower Engineering and Technology 2014-15

    ower Generation

    Water enters from reservoir through HRT-1 and HRT-2. Each HRT further divides

    into two penstocks which are equipped with a butterfly valve. Hence four penstocks

    lead to four turbines. This water rotates the turbine blades and turbine rotates the

    excited rotor. This leads to change in flux and according to faradays law electricity is

    generated.

    Water from turbine enters the draft tubes and there after tail race tunnel TRT-1

    and TRT-2. These TRTs takes the water to mainstream.

    P

    Figure 7: Tehri HPP and PSP power generation scheme

  • TEHRI HYDRO POWER PLANT Summer Training Report

    16 | P a g e Charu Kandpal THDC Institute of Hydropower Engineering and Technology 2014-15

    xcitation System

    The basic principle of power generation is when a magnetic field is moved across a

    stationary conductor, voltage is induced in the conductor. Voltage will be induced even if

    conductor is rotated and magnetic field is kept stationary, Generators consist of two circuits an

    electric circuit and a magnetic circuit; one is rotating with respect to other. The magnetic circuit

    of a generator is called exciter.

    In modern generators magnetic field is produced by an electromagnet. The

    intensity of magnetic field can be varied by varying the amount of DC current

    applied to electromagnet. Generator output voltage is affected by the following

    factors:

    1) Intensity of the flux in the rotating magnetic excitation field. This can be

    varied by varying the DC current applied to the electromagnets.

    2) Rate at which flux lines cut by the conductor. This is not variable since the

    generators operator at the rated constant speed.

    3) Length of the conductor (Not variable).

    The excitation system is intended for providing the following functions:

    Start up, field flashing and switching to the system by precise synchronizing.

    Operation of the generator at loads varying from no load to maximum load for the

    generator.

    Operation in the synchronous condenser mode both with inductive and capacitive load.

    Field forcing at the set voltage response and de excitation at disturbances in the power

    grid causing voltage rise or drop in the system.

    E

  • TEHRI HYDRO POWER PLANT Summer Training Report

    17 | P a g e Charu Kandpal THDC Institute of Hydropower Engineering and Technology 2014-15

    Rotor field suppression by the field circuit breaker at protection operation with

    simultaneous inversion of the rectifying unit.

    Operation on joint control maintaining even distribution of the reactive load between

    machines.

    Limiting the ratio of ceiling field current to nominal field current by two (2) per unit

    without time delay as well limiting of over load by the time-inverse characteristics.

    Limiting minimum field current with set point depending on generator active power in

    the mode of VAR load demand from the grid.

    Protection of the generator for loss of excitation/asynchronous run.

    Protection of generator transformer from damage at frequency drops under no load

    conditions by lowering the voltage regulator setting suitably.

    Compensation for step-up transformer impedance.

    Startup of pumped storage units by back-to-back method and for electrical braking

    operation of the units.

  • TEHRI HYDRO POWER PLANT Summer Training Report

    18 | P a g e Charu Kandpal THDC Institute of Hydropower Engineering and Technology 2014-15

    raking System

    1) To stop the machine, first wicket gates are closed.

    2) It is then left in the idle condition, so that the speed reduces to 50%. 3) Dynamic brakes: When the speed is reduced to 50% dynamic brakes are

    applied. For this, first the

    4) 11KV incomer line is stepped down to 230V which after passing through

    circuit breakers followed by field breakers is supplied to the rotor in

    opposite direction (opposite to the direction of excitation) and the 3

    phase AC is shorted, which applies the force in opposite direction and

    helps in reducing the speed.

    5) Dynamic brakes are applied until machine reduces to 4 percent.

    6) Mechanical brakes are applied when the speed reduces to 4% after application of

    Dynamic brakes.

    B

    Figure 8: Mechanical Brake

  • TEHRI HYDRO POWER PLANT Summer Training Report

    19 | P a g e Charu Kandpal THDC Institute of Hydropower Engineering and Technology 2014-15

    overnor and oil pressure System

    Governor System:

    The main purpose of governor system is to maintain the rotational speed of the

    rotor within permissible limits. It consist of Electrohydraulic Transducers, which takes

    input from electronic transducers installed in unit control boards and performs desirable

    action by sending it to servomotor. It also takes signals from servomotor and in case of

    any malfunctioning, it sends signal to electronic transducer to take mandatory action

    according to the scenario.

    For controlling the speed of a turbine a signal proportional to the speed is to be fed to

    the control system. The pressure is maintained constant by a separate unit called as oil

    pressure unit.

    For achieving automatic control, a portion of the system output is fed back to the

    system and this signal is called feedback. The governor then automatically adjusts the

    flow to control the prime movers power.

    Oil Pressure Unit:

    Application of oil pressure system:

    1) The heat generated by the moving parts can be carried away

    by the oil which can be transmitted to exchanger.

    2) Various devices (big or small) like operating server motors for

    the wicket gates and opening and closing of the spherical valve of MIV

    (Main inlet valve) can be operated using a simple energy source.

    3) The oil acts as a lubricant which can increase the component life and hydraulic

    actuators have a good response.

    G

  • TEHRI HYDRO POWER PLANT Summer Training Report

    20 | P a g e Charu Kandpal THDC Institute of Hydropower Engineering and Technology 2014-15

    Figure 10: Oil pumping unit with motor

    Figure 9: Oil and air pressure units

  • TEHRI HYDRO POWER PLANT Summer Training Report

    21 | P a g e Charu Kandpal THDC Institute of Hydropower Engineering and Technology 2014-15

    as Insulated Switchyard

    After generation of power at 15.75 KV it is stepped up to 400 KV by transformers installed at

    elevation EL 605 M. Then it is passed through GIS before sending it to power grid. GIS needed

    very less space for a switchyard than in comparison of building it in an open space.

    a) 3 phase AC wave is first passed through the surge arrestors which arrests the

    high peaks in the wave. Basically it is the capacitor which charges and discharges in

    order to remove those high peaks.

    b) Current transformers are there for the protection. Their rating is 500A/1A. c)

    Isolators give option to switch between the bus bars.

    d) Circuit breakers are also there, which contains Nitrogen gas to pressurize the

    oil. Nitrogen pushes the piston as a result the circuit is completed and the conduction

    starts. Circuit breakers here are hydraulic type. The pressure of SF6 in circuit breaker is

    6.9MPa.

    e) Bus Coupler: - It connects the power generated to the transfer line. B11 is

    connected to B12 & B21 is connected to B22.

    f) Insulation: - For insulation SF6 is used. AS soon as the line charges, spark is

    generated, SF6 quenches the spark. SF6 is used because Fluorine ions have high electro

    negativity which quickly recombines to form SF6.

    g) L1 line trap is provided for the hotline communication.

    h) Here capacitive voltage transformers are used because it works well on high

    voltage and are economical.

    G

  • TEHRI HYDRO POWER PLANT Summer Training Report

    22 | P a g e Charu Kandpal THDC Institute of Hydropower Engineering and Technology 2014-15

    In GIS red cylinder contains Nitrogen whereas blue cylinders contain SF6. Nitrogen is used here

    to take vacant space created by motor whenever breaks are applied. As breakers are removed or

    applied by a motor and Nitrogen fills it very fast and it is cheap.

    Figure 11: Gas Insulated Switchyard

  • TEHRI HYDRO POWER PLANT Summer Training Report

    23 | P a g e Charu Kandpal THDC Institute of Hydropower Engineering and Technology 2014-15

    omputerized Control Room

    It uses SCADA i.e. Supervisory Control and Data Acquisition system. It has full control on

    starting, running and stopping of a machine. Amount of energy produced, Shutdown of a

    machine, starting of a machine etc. is ensured by SCADA system of ALSTOM installed in

    CCR.

    Start Sequence:

    C START

    1) Check Start Condition

    2) Open Start Page

    3) TM START

    1) MIV open

    2) Gen. Cooling Water ON

    3) Gen. Space Heaters OFF

    4) Field Beaker ON

    5) Governor Start

  • TEHRI HYDRO POWER PLANT Summer Training Report

    24 | P a g e Charu Kandpal THDC Institute of Hydropower Engineering and Technology 2014-15

    If Speed> 95%

    Excitation ON

    If Voltage>80%

    Spinning Mode

    Check

    Synchronization

    and close circuit

    breaker

    END

  • TEHRI HYDRO POWER PLANT Summer Training Report

    25 | P a g e Charu Kandpal THDC Institute of Hydropower Engineering and Technology 2014-15

    eferences

    1) A report on Energy Scenario of India, Bureau of energy efficiency, India

    (BEE)

    2) Official Site of THDC, www.thdc.gov.in

    3) Technical Directories of THDC India Limited

    4) Official site of ALSTOM (www.alstom.com)

    5) Wikipedia Tehri dam Portal

    R

  • TEHRI HYDRO POWER PLANT Summer Training Report

    26 | P a g e Charu Kandpal THDC Institute of Hydropower Engineering and Technology 2014-15

    pilogue

    This industrial training has helped me in improving my practical knowledge about

    electrical machines and electrical apparatus. With state of the art gigantic structure this

    is a source of power for the country. I realized how it is easy to waste energy easily and

    how difficult and costly it is to make. GIS, SCA Transformers was such an important part

    of learning.

    The ability of staff to let us understand the working principle of machines and

    their familiar behavior was unforgettable. TEHRI HEP was a phenomenal experience for

    me to get trained in such a place full of engineering and technology.

    E