48
CHAPTER 4 EXPERIMENTAL SET-UP 4.1 Experimental Cell Design and Construction 4.2 Instrumentation and Monitoring Program 4.3 Leachate Recirculation Strategy The engineering design, construction, supervision and instrumentation of the full-scale experimental cell constituted a significant part of this thesis, which laid down the required groundwork for the subsequent investigations. This chapter provides a detailed description of the experimental cell including its instrumentation and the related monitoring program. It also outlines and justifies the strategy of leachate recirculation employed in the test. 4-1

CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

CHAPTER

4EXPERIMENTAL SET-UP

4.1 Experimental Cell Design and Construction

4.2 Instrumentation andMonitoring Program

4.3 Leachate Recirculation Strategy

The engineering design, construction, supervision and instrumentation of the full-scale

experimental cell constituted a significant part of this thesis, which laid down the required

groundwork for the subsequent investigations. This chapter provides a detailed

description of the experimental cell including its instrumentation and the related

monitoring program. It also outlines and justifies the strategy of leachate recirculation

employed in the test.

4-1

Page 2: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Chapter 4

4.1 EXPERIMENTAL CELL DESIGN AND CONSTRUCTION

4.1.1 General

The experimental cell is located in Browning-Ferris Industries Inc. (BFI) ’s Lyndhurst

Sanitary Landfill site which is about 35km south-east of Melbourne city centre as

shown in the location plan (Figure 4.1).

The existing pit used for landfilling, in common with many landfill sites in the same

south-eastern sand belt region of Melbourne, was created by previous sand mining

operations. The geology comprises a sequence of Tertiary age sands and clays of 15 to

35m depth underlain by granite rock.

The natural groundwater level is shallow at about 6m below original ground level,

which is at approximately 12m AHD (Australian Height Datum). The regional

hydraulic gradient is falling towards the west.

The site is at a latitude of 38.02o S. Historic climatic data from a meteorological station

located 15km north of the landfill reveal that the mean annual Class-A pan evaporation

(1227 mm) exceeds the mean annual rainfall (874 mm).

The cell commissioned for the full-scale experiment is Cell 3 at the north-western

corner of the site as shown in the aerial photograph (Plate 4.1 – Appendix A). Table 4.1

summarises the progress of the experiment up to December 1997.

4-2

Page 3: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Experimental Set-up

4-3

Page 4: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Chapter 4

Table 4.1 - Progress of Experiment

4.1.2 Size of Experimental Cell

The cell covers a footprint area of approximately 180m x 75m (about 1.4 hectares) as

shown in the as-constructed survey plan (Figure 4.2). This cell size is regarded as

typical compared with other operational cells in the same landfill.

The final capping level rises from +15m AHD at the north-western corner up to +20m

AHD at the south-eastern corner as the landscape slopes up south-easterly (Figure 4.2).

The surface of the base liner is at +4m AHD. The thickness of fill thus varies from 10m

to 15m (excluding the 1m final capping).

Based on survey data, the as-constructed volume of the experimental cell is 180,400 m3.

Total tonnage of MSW as recorded by weighbridge is 100,800 tonnes. The filling of the

cell took about two years to complete (Table 4.1).

In plan, the cell is divided into two sections of roughly equal areas. The western half

has been designated as the control section for dry landfilling and the eastern half as the

test section for leachate recirculation (Figure 4.2).

Plate 4.2 (Appendix A) shows a general view of the completed experimental cell taken

from the north-western corner.

4-4

Page 5: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Experimental Set-up

4-5

Page 6: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Chapter 4

4.1.3 Waste Composition

As the composition of waste is one of the most vital factors that influence

biodegradation and hence the enhancement strategy, it is important to be able to

quantify and qualify the types of waste being investigated in the experiment. This

information would also be essential to allow any findings to be cross-referenced with

other similar studies.

Although the Lyndhurst Landfill is also licensed to accept prescribed wastes (as defined

in SEPP 1991) and contaminated soil, for the purpose of this bioreactor experiment,

only domestic garbage and non-hazardous/ non-toxic waste from the commercial/

industrial waste stream were used in the experimental cell.

A record of all the wastes placed in the experimental cell was kept according to their

waste streams. It is shown graphically in Figure 4.3. The ratio of domestic to

commercial/ industrial waste stream is 1:1.6. The filling thus constitutes a higher

proportion of commercial/ industrial waste as this forms the bulk of the waste source of

Lyndhurst Landfill.

Figure 4.3 – Record of Waste Disposed According to Waste Streams

4-6

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

Dec-93 Mar-94 Jun-94 Sep-94 Dec-94 Mar-95 Jun-95 Sep-95 Dec-95

Cum

mul

ativ

e To

nnag

e

Domestc Waste Stream

Commercial & IndustrialWaste Stream

Page 7: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Experimental Set-up

In terms of composition, both domestic waste and industrial/ commercial waste streams

from metropolitan Melbourne have been studied recently (Waste Management Council,

1995). Their compositions according to the survey are listed in Table 4.2. These figures

should provide a close representation of the wastes disposed in the experimental cell.

After being weighted according to the above 1:1.6 ratio, the overall waste composition

was estimated. It is shown in Figure 4.4. Note that the percentages are expressed in

terms of wet mass.

Table 4.2 - Compositions of Waste from Metropolitan

Melbourne (WMC, 1995)

Components Domestic Waste (%) Commercial/ Industrial Waste (%)Residual 20% 10%Plastics 6% 12%Garden 16% 5%Kitchen/Food 25% 17%Paper 19% 22%Metals 3% 5%Textiles 2% 10%Inert 3% 4%Glass 6% -Domestic - 2%Timber/Wood - 11%Others - 2%Total 100% 100%

Figure 4.4 Figure 4.5

4-7

Inert (building /daily covers /

residual)47%

Paper12%

Plastic9%

Garden/food23%

Glass1%

Metal3%Textlle

5%

Waste Composition Based on Test Cell Samples

(By Dry Mass)

Inert + Residual

18%

Paper21%

Plastic10%

Garden / Food / Timber

36%

Textile7%

Metal4%

Glass4%

Waste Composition Based on Waste streams & WMC 1995 Data (By Wet Mass)

Page 8: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Chapter 4

Additional waste composition information was also determined by collecting continuous

waste samples from seven augered holes immediately after final capping. These holes

were drilled to install access tubes for subsequent moisture monitoring (refer Section

4.2.1 for locations and details). The samples were dried to determine their gravimetric

moisture (refer Section 4.1.4) prior to sorting. The composition as sorted is presented in

Figure 4.5. In contrast to Figure 4.4, it is expressed in terms of dry mass.

It is impossible to make a direct comparison between the compositions in Figure 4.4

and Figure 4.5, as the moisture contents of individual components are not available.

Nevertheless, by assuming a reasonable moisture content for each component, the two

compositions tend to agree reasonably well. The dry mass composition is always pre-

ferred as it is independent of moisture content.

As the control and test sections were filled up simultaneously and the ratio of domestic

waste to commercial/ industrial waste was maintained fairly consistently (Figure 4.3),

the composition of waste in the experimental cell (in macroscopic scale) can be

considered to be reasonably uniform. For the same reason, the wastes in the control and

test sections can be treated as identical, at least within the context of this experiment.

4.1.4 Waste Moisture Content

The variations of moisture content (immediately after final capping) with depth for the

seven sampling holes mentioned above are plotted in Figure 4.6. The moisture content

range and distribution of all the samples are plotted in Figure 4.7. The volumetric

values in the figures were calculated based on a bulk density of 0.83 tonne/ m3 (refer

Section 4.1.6).

The results of the moisture content analysis are summarised in Table 4.3. Thus, for the

purpose of the water balance analysis in Chapter 6, the mean value of 27% (volumetric)

is taken to be the overall as-capped moisture content of the waste.

4-8

Page 9: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Experimental Set-up

Figure 4.6 – Variation of Moisture Content with Depth in the Seven Sampling Holes:(a) By Dry Mass; (b) By Wet Mass; (c) By Volume

4-9

(a) As-capped Waste Moisture Content with Depth - by dry mass

0%

50%

100%

150%

200%1

to 2

m

2 to

3 m

3 to

4 m

4 to

5 m

5 to

6 m

6 to

7 m

7 to

8 m

8 to

9 m

9 to

10

m

10 to

11

m

11 to

12

m

Depth

Moi

stur

e C

onte

nt AT1

AT2

AT3

AT4

AT5

AC1

AC2

(b) As-capped Waste Moisture Content with Depth - by wet mass

0%

10%

20%

30%

40%

50%

60%

70%

1 to

2 m

2 to

3 m

3 to

4 m

4 to

5 m

5 to

6 m

6 to

7 m

7 to

8 m

8 to

9 m

9 to

10

m

10 to

11

m

11 to

12

m

Depth

Moi

stur

e C

onte

nt AT1

AT2

AT3

AT4

AT5

AC1

AC2

(c) As-capped Waste Moisture Content with Depth - by volume

0%

10%

20%

30%

40%

50%

60%

1 to 2

m

2 to 3

m

3 to 4

m

4 to 5

m

5 to 6

m

6 to 7

m

7 to 8

m

8 to 9

m

9 to 1

0 m

10 to

11 m

11 to

12 m

Depth

Moi

stur

e C

onte

nt AT1

AT2

AT3

AT4

AT5

AC1

AC2

Page 10: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Chapter 4

Figure 4.7 – Moisture Content Range and Distribution of MSW:(a) By Dry Mass; (b) By Wet Mass; (c) By Volume

4-10

(b) Moisture Content Distribution- by wet mass

0%

10%

20%

30%

40%

10% -2

0%

20%-30

%

30%-40

%

40%-50

%

50%-60

%

60% to

70%

Moisture Content Range

Rela

tive

frequ

ency

(c) Moisture Content Distribution- by volume

0%

10%

20%

30%

40%

50%

< 15%

15%-25

%

25%-35

%

35%-45

%>45

%

Moisture Content Range

Rela

tive

frequ

ency

(a) Moisture Content Distribution- by dry mass

0%

10%

20%

30%

40%

50%

0 - 20

%

20 - 4

0%

40 - 6

0%

60 - 8

0%

80 - 1

00%

100 -

120%

120 -

140%

140 -

160%

160 -

180%

Moisture Content Range

Rela

tive

frequ

ency

Page 11: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Experimental Set-up

Table 4.3 - Results of Waste Moisture Content AnalysisMoisture Content (%)

By dry mass By wet mass By volumeMaximum 173 63 53Minimum 15 13 11Mean 55 32 27Std. Deviation 38 13 11

4.1.5 Daily/ Interim Covers

Due to licensing requirements as well as operational needs to control litter, birds and

odour during filling, daily cover was used in a manner similar to other operational cells.

The licence requires a 150mm layer of earth material as daily cover during waste

disposal. In addition, each completed vertical lift (of 2m) should be covered by an

interim cover of 300mm earth material. This requirement was applied to the

experimental cell.

In common with other sand-pit landfills in the region, semi-dry to dry slimes were used

for daily and interim covers in the experimental cell. The slimes were generally a

clayey sandy silt material left behind from previous sand washing (Yuen and Styles,

1995). They spread reasonably well at “spadable” dryness. While still moist, they

exhibit low permeability to both gas and odour. As they dry out, they crack to form

agglomerates. This would allow a reasonable permeability, which is desirable for

moisture movement induced by later leachate recirculation.

To reduce the barrier effects of the daily and interim covers for later recirculation,

permeability was improved by stripping and mixing the earth material with waste

before placing the next lift.

Figure 4.8 provides a record of all cover material (excluding final capping) placed in

the experimental cell. The cumulative waste volume is also plotted. From the figure, it

can be deduced that the cover material occupies about 15% of the total waste volume.

4-11

Page 12: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Chapter 4

This figure compares well with the amount as stipulated by the licence requirement

which is 17% as calculated based on the above configuration.

Figure 4.8 – Record of Cover Material against Total waste Volume

4.1.6 Density and Porosity of Waste

The waste was compacted in vertical layers by a Caterpillar 826C landfill compactor

with an operating weight of 32 tonnes. It is the same compaction method employed in

other operational cells.

Table 4.4 lists all the weight and volume components and the procedure used to

calculate the in-situ density of waste. The bulk density, accounting also for the

daily/interim earth covers, is 0.83 tonne/m3.

Based on this density and the bulk moisture content (55% by dry mass) determined in

Section 4.1.4, the dry density and porosity of the MSW was calculated, which are 0.54

tonne/m3 and 0.55 respectively. The literature suggests a porosity range between 0.5 to

0.6 (e.g. Korfiatis et al., 1984; Oweis et al., 1990; Zeiss and Major, 1992). In this case

0.55 reflects that the MSW in the experimental cell is reasonably well-compacted.Table 4.4 - Calculation of in-situ waste densityItem Description Volume Weight Density

4-12

0

20,000

40,000

60,000

80,000

100,000

120,000

140,000

160,000

Dec-93 Mar-94 Jun-94 Sep-94 Dec-94 Mar-95 Jun-95 Sep-95 Dec-95

Cum

mul

ativ

e Vo

lum

e (m

3) MSW

Daily / Interim Covers

Page 13: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Experimental Set-up

(m3) (tonne) (tonne/m3)a Volume between top of liner and top of capping 180,400

b Volume of 1m thick final cap 13,500

c Volume of daily/interim covers 24,750

d Volume of leachate collection drainage layer 4,160

e Net volume of MSW ( = a - b - c - d ) 137,950

f Total MSW weight as recorded by weighbridge 100,820

g Total weight of daily interim covers as recorded 34,650

h As placed in-situ density of MSW ( = f / e)(excluding daily/interim covers, drainage & cap) 0.73

i As placed in-situ density of combined MSW & cover material (= [f + g] / [a-b-d] ) 0.83

4.1.7 Cell Containment System

In common with all other operational cells, the experimental cell is lined with a 1m

thick side and base clay liner. The compacted clay has a specified hydraulic

conductivity of less than 10-9 m/s. The construction of the liner was subject to a quality

assurance program as required by the licence.

Figure 4.9 – Details of Final Capping

4-13

Top soil

Sand

Waste

Compacted Clay

Grass

300mm200mm500mm

Page 14: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Chapter 4

Immediately upon completion of filling, a final capping was laid, the details of which

are shown in Figure 4.9. The capping falls gently on a 1 on 7.5 gradient towards its

north-western corner (refer Figure 4.2).

4.1.8 Leachate Collection System

A more efficient leachate drainage system different from other operational cells is used.

It aims to provide a better control of the hydraulic head on the base liner during

leachate recirculation. The system comprises a 300mm thick drainage layer of 20/40mm

basalt gravel immediately above the liner, with 90mm diameter slotted collector pipes

installed at 15m centres. These then drain to a 150mm diameter header pipe falling at a

0.16% gradient into a leachate collection sump (Figure 4.10).

To enable both leachate quantity and quality from the control and test sections to be

monitored separately, each of the two sections has its own collection system. The two

systems are isolated by a compacted clay bund wall constructed on top of the base liner

as shown in Figure 4.10.

Figure 4.10 – Schematic Plan showing Leachate Collection System

4-14

Collector drain

15 m

CONTROL AREA RECIRCULATION AREA

Leachatesump

Header pipe

Compacted clay bermN

( N.T.S. )

Page 15: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Experimental Set-up

4.1.9 Gas Extraction System

An active extraction system employing a small suction is used to collect gas. To enable

both flow rate and composition in the control and test sections to be monitored

independently, two isolated gas fields (Figure 4.11) are employed. Each field comprises

nine collection wells spaced approximately 25m apart connecting to a manifold station

(Plate 4.3 in Appendix A). As the amount of gas that can be extracted from each well

may vary, each well has a separate control valve for vacuum adjustment at the manifold

station.

The details of the gas wells in the control section are shown in Figure 4.12. For the test

section, the wells are designed also for leachate injection (see also Section 4.1.10).

Construction details are shown in Figure 4.13.

Further discussion on the gas collection system is provided in Section 8.2.

Figure 4.11 – Schematic Plan Showing Gas Extraction Wells and Combined Leachate injection/ Gas Extraction Wells

4-15

Legends :

Combined Leachate Sub-surface injection/ Gas Collection Well Infiltration Trench

for RecirculationGas Collection Well

057

053

Control Area Recirculation AreaN

(N.T.S.)Plan

050 049 048

051052053

054055056

057 059058

062061060

065064063

Page 16: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Chapter 4

Figure 4.12 – Details of Gas Extraction Wells

Figure 4.13 – Details of Combined Gas Extraction/

4-16

G.L.

To gas manifold

63mm dia.HDPE pipe

450 mm dia.borehole

45mmgravel pack

3.5m

plu

g(c

ompa

cted

cla

y)

4m to top of liner

Perf

orat

ed p

ipe

sect

ion

0.5m

Suction

G.L.

Perf

orat

ed p

ipe

sect

ion

0.5m

To gas manifold

63mm dia.HDPE pipe

450 mm dia.borehole

45mmgravel pack

3.5m

plu

g(c

ompa

cted

cla

y)

4m to top of liner

Suction

From header tank Leachate

Page 17: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Experimental Set-up

Leachate Injection Well4.1.10 Leachate Recirculation System

A wide range of recirculation options was considered. They included surface irrigation,

surface ponding, buried drip irrigation tubing, in-ground piping grid, sub-surface

infiltration trench/field, and vertical recharge well.

With potential problems such as odour control and wind-blown misting, surface

application of leachate by spray irrigation or ponding was ruled out at an early stage.

The use of buried drip irrigation tubing or an in-ground piping grid was also excluded.

This decision was based on previous trials which indicated that there are numerous

difficulties in maintaining the connection of the system as the landfill subsides.

A combination of sub-surface horizontal infiltration trenches and deep vertical injection

wells was finally selected for this experiment. Both devices were constructed after final

capping to avoid interruption to waste filling. The integrated system is shown schemat-

ically in Figure 4.14. The design, including the sizing and spacing of wells and

trenches, was based on a numerical model simulation as discussed later in Section 7.2.1.

The details of a sub-surface horizontal infiltration trench are shown in Figure 4.15.

There are eight infiltration trenches (RT1 to RT8) strategically placed between each

pair of wells (Figure 4.14).

As described previously in Section 4.9 (Figure 4.13), the nine leachate injection wells

(RW1 to RW9 in Figure 4.14) also serve to extract gas in the test section.

Leachate is pumped from the collection sump (Plate 4.4 in Appendix A) into three

storage/header tanks (Plate 4.5) with a total capacity of 27,000 litres. From there the

leachate feeds the wells and trenches by gravity via a system of pipework and valves

(Plate 4.6). The system has been designed to allow flexibility to inject either an

individual well/trench or a group of selected wells/trenches.

4-17

Page 18: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Chapter 4

Figure 4.14 – Integrated Leachate Recirculation System

4-18

A c c e s s R o a d

B a s e l i n e r

C a p p i n g

L e a c h a t e I n j e c t i o n /G a s C o l l e c t i o n w e l l

S u b - s u r f a c e I n f i l t r a t i o n T r e n c h

F e e d e r p i p e

S e c t i o n A - A( N . T . S . )

C O N T R O L A R E A R E C I R C U L A T I O N A R E A

N

( N . T . S . )

L e g e n d s :

L e a c h a t e I n j e c t i o n /G a s C o l l e c t i o n W e l l

S u b - s u r f a c eI n f i l t r a t i o n T r e n c h

F e e d e r P i p e

A

AP l a n

R W 1

R W 9R W 8R W 7

R W 6R W 5R W 4

R W 3R W 2

R T 1

R T 2

RT

3R

T5

RT

6R

T4

RT

7

RT

8

Page 19: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Experimental Set-up

Figure 4.15 – Details of Sub-Surface Horizontal Infiltration Trench

4-19

G.L.

Final Capping

Feeder pipe

Leachet from header tank

90mm dia. slottedPVC pipe

600mm

600m

m

45mm gravel pack

(N.T.S.)

Waste

Page 20: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Chapter 4

4.2 INSTRUMENTATION AND MONITORING PROGRAM

The design of the right instrumentation is crucial to enable the collection of reliable

data for later analysis. The following factors and constraints have been taken into

consideration in the design: costs (both capital and running costs), compatibility with

the landfill environment, reliability, and simplicity.

Table 4.5 lists all the items that are being monitored in the study with the corresponding

method/ instrumentation employed. Figure 4.16 shows the location of instrumentation

schematically in plan. It can be divided into four monitoring groups: Control A, Control

B, Test A and Test B.

Table 4.5 - Instrumentation/ Method Employed To Collect Data

Items Required Monitoring

Instrumentation/ Method

Waste Moisture Distribution Profile

Using neutron probe to measure moisture changes via in-situ access tubes

Climatic Data Automatic weather station

Surface Runoff Collection by surface channels & measurement by flume with water level auto-logger

Landfill Settlement Level survey on settlement plates

Waste Temperature Stainless steel sheathed thermocouples

Leachate Level Measure leachate levels in the sumps and open wells by a water level

sensor

Leachate Volume Combining the use of an ultrasonic flowmeter and tank measurement

Leachate Quality Collect and test leachate samples from both leachate sumps and open

wells

Landfill Gas Composition Portable non-dispersive infra-red absorption landfill gas analyser. Portable gas chromatograph (GC)

Landfill Gas Flow Rate Pre-calibrated orifice plate

Groundwater Quality Collect and analyse groundwater samples from adjacent monitoring bores

4-20

Page 21: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Experimental Set-up

Figure 4.16 – Location Plan Showing Instrumentation of Experimental Cell

4.2.1 In-situ Municipal Solid Waste Moisture Monitoring

Based on a parallel investigation as described later in Chapter 5, the combined use of a

neutron probe and in-situ access tubes has been identified as a practicable tool for mon-

itoring moisture of in-situ MSW. Seven in-situ access tubes each of 12m long have

been installed as shown in Figure 4.17. They are used to monitor: seasonal moisture

change in the control section (AC1 and AC2); moisture change adjacent to a recircula-

tion well (AT1 to AT3); and moisture change adjacent to a trench in the test section

(AT4 and AT5). The installation details of the access tubes are described in Section

5.5.1.

4-21

(N.T.S.)PlanLegends :

Neutron Probe Access Tube Open Well Flume

Temperature Probe Leachate Collection Sump Catch Pit

Settlement Plate Surface Channel Automatic Weather Station

Control Section Recirculation SectionN

FallFall

To stormwaterdischarge

Control A Control BTest A

Test B

Page 22: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Chapter 4

4-22

Page 23: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Experimental Set-up

Figure 4.17 – In-situ Access Tubes for Monitoring Moisture Changes

4-23

C o n t r o l A r e a R e c i r c u l a t i o n A r e a

N

( N . T . S . )P l a nL e g e n d s :

C o m b i n e d L e a c h a t e S u b - S u r f a c e I n f i l t a r t i o n T r e n c h i n j e c t i o n / G a s C o l l e c t i o n W e l lG a s C o l l e c t i o n W e l l N e u t r o n P r o b e A c c e s s T u b e

A A

B BA C 1 A C 2

A T 1A T 2A T 3

A T 5 A T 4

Neutron Probe Access Tubes

SECTION A - A (N.T.S)

AT1AT2

3 m

Liner

Final CappingAT3

3 m

Deep Injection WellRW5

3 m

Page 24: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Chapter 4

4.2.2 Climatic Data

An automatic weather station is installed on top of the experimental cell (Figure 4.16

and Plate 4.7). It is equipped with a data logger and the following sensors (with meas-

urement height and instrument accuracy in bracket):

Rain gauge (0.3m; 0.2mm tipping bucket)

Air temperature sensor (1.4m; +0.2o )

Relative humidity sensor (1.4m; +5%)

Anemometer (2.0m; +0.1 km/hr)

Solar radiation sensor (2.0m; +0.1 kJ/m2)

4.2.3 Surface Runoff

All runoff from the experimental cell catchment is collected by two surface channels

running along the north and north-western edges as show in Figure 4.16. Through two

catch pits, all flow is then diverted to a single main channel. A flume equipped with

two water level probes (one as backup) and a real-time logger is installed in-line with

the main channel to measure flow rate (Plate 4.8).

The flume belongs to the RBC (Replogle, Bos and Clemmens) family of long throated

flumes (Bos et al., 1984) which are designed for measurement of flow in open channels

with minimum head loss and reasonable sediment and debris passage without affecting

performance. They allow accurate measurement of head loss at the sill, ensure that crit-

ical flow occurs in the throat, and give an accuracy of about 2% over the range of meas-

ured discharge. They require only one measurement of flow depth at a point upstream

of the sill, which simplifies the operation compared to other types of flume. Their full

hydraulic design details are given by Bos et al. (1984).

4-24

Page 25: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Experimental Set-up

The flume is of a trapezoidal cross-section with dimensions as shown in Figure 4.18. It

has a maximum flow capacity of 80 litres/sec. It has been calibrated in a hydraulic

laboratory channel (Plate 4.9) and the calibrated curve in Figure 4.19 is used to relate

measured flow depth data to flow rate. The water level is scanned every 30 seconds and

recorded if it varies by more than 3mm from the previous measurement.

Figure 4.18 – Details of RBC Long Throated Flume Employed in Experimental Cell

4-25

700mm 300mm 300mm 300mm

Approach Transition Throat Exit

225mm100mm225mm

350mm

100mm

A

ALongitudinal Section Section A-A

Flow

0

50

100

150

200

250

300

0 10 20 30 40 50 60 70 80 90

Discharge (l/s)

Stag

e He

ight

(m

m)

First Calibration Points

Second Calibration Points

Page 26: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Chapter 4

Figure 4.19 – Flume Calibration Curve Relating Stage Height and Flow Rate

4.2.4 Landfill Settlement

Figure 4.20 shows in plan three groups of settlement monitoring plates, two in the

control section (Control A and Control B) and one in the test section (Test A). Each

group is composed of a series of five settlement plates installed approximately at +4m

AHD (i.e. surface of liner), +6m AHD, +8m AHD, +10m AHD, and +18m AHD (i.e.

ground level) respectively. Instead of just monitoring the subsidence at surface level,

the additional settlement data collected at various levels would provide some additional

information on subsidence behaviour along a vertical profile.

Construction details of a typical in-ground settlement plate are given in Figure 4.21.

The plates were pre-placed on the nominated levels during filling. Upon completion of

the cell, they were relocated in plan by a positioning survey. Boreholes were then sunk

to provide access for the installation of connection rod and sleeve. The level of each

plate is monitored by surveying the top level of the connection rod.

Originally two groups of settlement plates were pre-placed in the test section.

Unfortunately one group was placed too close to the south-eastern corner. Following

cell completion they are located underneath a slope (refer to Figure 4.2), and it is

virtually impossible to mobilise a machine there to bore the required holes.

Subsequently this group of plates was abandoned, which resulted in only one group in

the test section.

4.2.5 In-situ Waste Temperature

Four groups of temperature probes were installed as shown in Figure 4.22 (Control A

and Control B, Test A and Test B). Each group comprises three probes aligned along a

4-26

Page 27: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Experimental Set-up

vertical profile (at 3m below ground surface, at mid-depth, and at 3m above liner

surface) in order to delineate any temperature variation with depth.

Figure 4.20 – Location Plan Showing Settlement Plates

4-27

( N . T . S . )P l a n

C o n t r o l A r e a R e c i r c u l a t i o n A r e aN

S P 1 S P 2 S P 3 S P 4 S M 1 S P 5 S P 6 S P 7 S P 8 S M 2

S P 9 S P 1 0 S P 1 1 S P 1 2 S M 3

C o n t r o l A : C o n t r o l B :

T e s t A :

L e v e l C o n t r o l A C o n t r o l B T e s t A ( a p p r o x i m a t e )S P 1 S P 5 S P 9 4 m A H D ( l i n e r s u r f a c e )S P 2 S P 6 S P 1 0 6 m A H DS P 3 S P 7 S P 1 1 8 m A H DS P 4 S P 8 S P 1 2 1 0 m A H DS M 1 S M 2 S M 3 1 8 m A H D ( g r o u n d s u r f a c e )

S e t t l e m e n t P l a t e G r o u p

Page 28: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Chapter 4

Figure 4.21 – Details of Settlement Plate

Figure 4.22 – Location Plan Showing Temperature Probes

Each probe is composed of a stainless steel sheathed type K thermocouple. The buried

thermocouple is connected to a surface terminal plug via a special compensating cable

protected by a sealed duct. As each probe is subject to a potentially corrosive

4-28

A A

1200 mm

1200

mm

Plan(N.T.S.)

Waste

SECTION A-A

G.L.

12 mm steel plate (pre-placed during filling) Base Level

50mm PVCsleeve

20mm galvanisedsteel pipe

(N.T.S.)

450mm dia.drillhole

Gravel backfill

Cap

C o n t r o l A r e a R e c i r c u l a t i o n A r e aN

T P 7 T P 8 T P 9

T P 1 0 T P 1 1 T P 1 2

T P 1 T P 2 T P 3 T P 4 T P 5 T P 6

( N . T . S . )P l a n

C o n t r o l A : C o n t r o l B :

T e s t A :

T e s t B :

L e v e l C o n t r o l A C o n t r o l B T e s t A T e s t BT P 1 T P 4 T P 7 T P 1 0 A t 3 m b e l o w g r o u n d s u r f a c eT P 2 T P 5 T P 8 T P 1 1 A t m i d - d e p t hT P 3 T P 6 T P 9 T P 1 2 A t 3 m a b o v e l i n e r s u r f a c e

T e m p e r a t u r e P r o b e G r o u p

Page 29: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Experimental Set-up

environment, only the sensor tip of the thermocouple is exposed in the waste (Plate

4.10).

Using a compatible portable digital thermometer (Fluke model 51), temperatures are

read from the thermocouples manually by connecting to the surface terminal plugs.

4.2.6 Saturated Leachate Level/ Leachate Sampling

There are two open wells and a leachate collection sump in each of the two sections

where the saturated leachate level can be monitored (Figure 4.23). From these wells and

sumps, leachate samples are also collected for monthly analysis.

Each open well was installed down to the liner surface and is constructed of a 50mm

continuously perforated PVC pipe surrounded with gravel packing. Leachate levels in

the sumps and wells are measured manually by using a portable water level sensor

probe which has an instrument accuracy of + 10mm.

Figure 4.23 - Location Plan Showing Leachate Sumps and Open Wells

4-29

Control Area Recirculation Area

N

(N.T.S.)Plan

Sump 3A Sump 3B

Open Well OW1

Open Well OW4

Open Well OW3

Open WellOW2

Page 30: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Chapter 4

4.2.7 Volume of Leachate Collected and Recirculated

A clamp-on type portable transit-time ultrasonic flowmeter (Plate 4.11) is used to

measure both flow volume and flow rate during recirculation trials of individual wells

and trenches. It is also used to calibrate the volume of each of the header/storage tanks

to allow an accurate record of daily leachate recirculation obtained by volumetric tank

measurement.

4.2.8 Landfill Gas Composition and Flow Rate

The flow rate of an individual well is measured through a pre-calibrated orifice plate

located at the manifold station (see Plate 4.12). Methane and oxygen concentrations are

routinely monitored by a portable non-dispersive infra-red absorption gas analyser

(ADC model LFG 20, see Plate 4.13). A portable gas chromatograph (GC) with a

micro-thermal conductivity detector is also used to provide more accurate

measurements and to detect other gases including nitrogen (refer Plate 4.14). Gas

sampling points at individual well heads are also provided.

4.2.9 Groundwater Quality

It is important in this study to demonstrate that the groundwater system is not signific-

antly affected by the recirculation operation. As part of the overall landfill monitoring

program, routine groundwater quality analysis is being conducted by an independent ac-

credited laboratory.

4-30

Page 31: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Experimental Set-up

A total of eight observation bores were installed in and around the periphery of the

landfill site. They are shown in Figure 4.24. BH8 and BH9 are the two closest

observation bores most relevant to the experimental cell. As the groundwater hydraulic

gradient is falling gently in a westerly direction, BH9 can be taken to represent the up-

gradient groundwater and BH8 the down-gradient.

Up to the end of 1997, the experimental cell was the only landfilling activity conducted

at the north-western corner of the site. Hence the groundwater data obtained from both

BH8 and BH9 can be considered to be unbiased of any adjacent landfilling effects.

Groundwater samples have been taken from both bores at three-monthly intervals since

January 1995. The water level and in-situ groundwater temperature are also measured.

The water samples are tested for the following parameters:

(a) Physical indicators – pH, alkalinity, conductivity, TDS, redox potential

(b) Organic indicators – COD, TOC

(c) Nitrogen – nitrate, total Kjeldahl nitrogen, ammonia

(d) Sulphate

(e) Chloride

(f) Phosphate

(g) Cyanide

(h) Phenolic substances

(i) Azure A

(j) Metal and heavy metals – Ca, Fe, Mg, Cu, K, Na, Pb, Hg, Cr, Ca, Se.

The results of the independent groundwater monitoring from January 1995 to December

1997 are presented in Appendix K.

4.2.10 Monitoring Program

The scheduled frequency of monitoring for each item is shown in Table 4.6.

4-31

Page 32: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Chapter 4

Table 4.6 - Monitoring ScheduleItems Required Monitoring Frequency

Waste Moisture Distribution Profile Test section: during recirculation trials

Control section: quarterlyClimatic Data Continuous

Surface Runoff Continuous

Landfill Settlement Monthly

Waste Temperature Monthly

Leachate Level Monthly

Leachate Volume Daily

Leachate Quality Monthly

Landfill Gas Composition Bi-monthly initially then monthly

Landfill Gas Flow Rate Bi-monthly initially then monthly

Groundwater Quality and Level Quarterly

4-32

Page 33: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Experimental Set-up

Figure 4.24 – Location of Groundwater Monitoring Bores

4.3 LEACHATE RECIRCULATION STRATEGY

4-33

Page 34: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Chapter 4

The leachate recirculation strategy adopted in this experiment has taken the following

factors and limitations into consideration:

(i) The leachate produced in other operational cells, which also accept

contaminated soils and hazardous industrial wastes, commonly contains high

concentrations of heavy metals and toxic chemicals. This source is considered

not suitable for recirculation as it may inhibit microbial growth. For this reason,

only leachate collected from within the experimental cell was used for

recirculation. Hence, there was a limited supply of suitable leachate for

recirculation. As the leachate from within the cell dried up in the recirculation,

stormwater was then injected to provide the required moisture.

(ii) This experiment did not consider alternative concepts such as the sequential

batch bioreactor employing the exchange of leachate between an acidogenic cell

and a methanogenic cell (e.g. Chugh 1996), and the high rate flushing bioreactor

to remove nitrogen, inorganic salts and the residual organic carbon (e.g. Walker

et al. 1997).

(iii) While small-scale experiments have suggested that it is desirable to have a high

moisture content and flow to encourage leachate contact (Section 2.3.3 (ix)), a

full-scale recirculation of this kind may create practical problems. As leachate

may accumulate and the pooling of leachate within the containment system

would impose an excessive head on the liner if the leachate is not removed

quickly enough. This sort of hydrological condition is undesirable. Hence in a

real landfill, there is a balance to be drawn between biodegradation requirements

and the hydrological capacity of the cell.

(iv) It is well recognised that excessive moisture at the initial stage of landfill

development would intensify acid production that may “sour” the system and

hinder the onset of methanogenesis (Section 2.3.3(i)). Because no external pH

buffer was used in the experiment (as explained in Section 3.1), any excessive

moisture introduced to the experimental cell could be undesirable.

4-34

Page 35: CHAPTER - MyWebPages · Web viewTo reduce the barrier effects of the daily and interim covers for later recirculation, permeability was improved by stripping and mixing the earth

Experimental Set-up

In order to avoid any potential inhibitory effects on the overall process, and to prevent

overloading the hydrological capacity of the containment system, this experiment has

adopted the strategy of recirculating leachate gradually.

The leachate intake rate of each injection device varies substantially due largely to the

heterogeneity of waste (refer Section 7.2.2 (iii)). To avoid an uneven delivery and

distribution, the feeding of a group of devices simultaneously from the header tanks

was discouraged. Instead, every trench and well was fed separately in turn. Thus a

routine recirculation involved firstly the pumping of leachate from the sump to fill up

the header tanks, and then the adjustment of the valve system to deliver leachate via

gravity to feed a single trench or well until the tanks were drained. In this way, the

volume injected into each device could be measured.

This practice of intermittent injection to each device also provides another advantage. It

allows sufficient time for both saturated and unsaturated flow to propagate from the

device into the surrounding waste to wet the potential zone of influence without

overloading the leachate collection system and liner. As there are eight trenches and

nine wells, this strategy allows sufficient time for each individual device to “recover”

before the next injection round.

There were three main stages of recirculation. Initially, leachate was collected from

within the test section sump and recirculated. After drying up the test sump, leachate

was then pumped from the control section into the test section. When all leachate from

both sections was exhausted, external storm water was then introduced. A total of 2.5

million litres of leachate was injected through the recirculation system during the period

from July 1996 to October 1997. The progress and volume of recirculation are

discussed further under the water balance study in Section 6.3.4.

4-35