Upload
debjyoti-das
View
217
Download
0
Embed Size (px)
Citation preview
7/30/2019 Chapter 4: Erection Methods of Cable Stayed Bridge
1/5
18
CHAPTER 4
ERECTION METHODS
4.1 GENERAL
The erection procedure depends on the structural system of the bridge, the site
conditions, dimensions of the shop-fabricated bridge units, equipments and other
factors characteristic of a particular project. The techniques and methods of
erecting cable-stayed bridges are as varied and numerous as the ingenuity and
number of erector contractors. It is common practice for the design engineer to
suggest a method of erection, because erection method not only affects the
stresses in the structure during construction but may have an effect on the final
stresses in the completed structure.
4.2 ERECTON METHODS
The methods of erection for cable stayed bridges can be broadly described by
three general methods as follows:
4.2.1 Staging Method
The staging method of erection is most often used where there is a low clearance
requirement to the underside of the structure and temporary bents will not
interfere with any traffic below the bridge. Its advantage is its accuracy in
maintaining required geometry and grade and its relatively low cost for low
clearance. The staging erection method is explained through a case study as
follows.
Erection Methods
Staging Method Push-out Method Cantilever Method
7/30/2019 Chapter 4: Erection Methods of Cable Stayed Bridge
2/5
7/30/2019 Chapter 4: Erection Methods of Cable Stayed Bridge
3/5
20
impractical. In this method, large sections of bridge deck are pushed out over the
piers on rollers or sliding Teflon bearings. The deck is pushed out from both
abutments toward the center, or, in some instances, from one abutment all the
way to the other abutment. Assembling the components in an erection bay at one
or both ends of the structure and progressively pushing the components out into
the span as they are completed can simplify construction and reduce costs. The
push-out erection method is explained through a case study as follows.
4.2.2.1 Push-out method: Julicher Strasse Bridge
Here the erection problem was that the federal railway operation, which consisted
of six electrified tracks under the eastern side span and the marshalling yard
under the center span, could not be interrupted. The push-out concept was
selected as the most feasible for the site conditions.
An area behind the west abutment of approximately 61 m by 39 m was utilized
as the assembly shop. Erection units were approximately 16 m in length and
were assembled from six subunits and, as much as possible, were
automatically welded at the assembly site.
The erection procedure is shown in Fig. 4.2. It should be noted that in the final
position the reaction load of the towers is borne by the permanent piers VIII andXI. However, during the push-out operation the tower reaction must be
resisted by a lateral-beam diaphragm which in turn transmits the load to the
longitudinal box girders. For this reason the cable stays are only partially
tensioned. The jacking mechanism at the saddle is used to compensate for the
cantilever deflection of the leading edge of the pushed out section.
When the leading edge of the bridge reaches pier VIII [Fig. 4.2(d)], the bearing
is elevated approximately 100 mm by jacks. As a result of this action the
bearing pressure at pier VII is relieved. As the structure is pushed out farther,
the bearing pressure at pier VIII will increase. It was determined that the
allowable bearing pressure was reached when the leading edge extended
approximately 7.3 m past pier IX. At this point the bearing at pier VIII is
7/30/2019 Chapter 4: Erection Methods of Cable Stayed Bridge
4/5
21
lowered to its original position. This procedure is then repeated until the
structure is in its final position.
4.2.3 Cantilever Method
Because of their self-anchored cable systems, the cantilever method has been
widely used for the girder erection of cable-stayed bridges. The cantilevermethod is considered as the natural and logical solution for constructing the
cable-stayed bridges of large span, where new girder segments are installed and
then supported by new cable stays in each erection stage, and the construction
process keeps going stage-by-stage until the bridge is completed. Since no
auxiliary supports are needed for constructing the bridge girder in the cantilever
method, a lot of construction cost and time can be saved. There are two basic
alternates in the cantilever method. One is named herein the single cantilever
method and the other is the double cantilever method. In the former the side
span girders of the bridge are erected on auxiliary piers and afterwards the
stiffening girder in main span is erected by one-sided free cantilevering until the
span centre or the anchor pier on the far end is reached. In the latter, the bridge
girder is erected from both side of the tower towards the anchor piers and the
Figure 4.2: Push-out method: Erection sequences of Julicher Strasse Bridge
7/30/2019 Chapter 4: Erection Methods of Cable Stayed Bridge
5/5
22
main span centre by double-sided free cantilevering. The cantilever erection
method is explained through the erection procedure of a harp type cable stayed
bridge as follows.
4.2.3.1 Cantilever method: Harp type cable stayed bridge
The Pylons are erected.
The first pair of girder segments B1 is installed.
The stayed cables C1 are installed and stressed initially to elevate the girders
and relieve their bending moments.
The pair of girder segments B2 is installed.
The stayed cables C2 are installed and stressed.
The girder segments B3 are installed.
The stayed cables C3 are installed and stressed.
Girder segments B4 is installed and the bridge is closed at the main span
centre.
Figure 4.3: Cantilever method: Erection sequences of a harp cable stayed bridge