    PRACTICAL SCADA SYSTEMS

    CHAPTER ONE: INTRODUCTION TO SCADA

    SYSTEMS

    Topics:

    Principles and components of modern SCADA systems Master stations and remote terminal units

    Objectives:

    To understand how SCADA components are integrated together

    To define the difference between PLC/SCADA/DCS

    1.1 INTRODUCTION AND BRIEF HISTORY OF SCADA

    This manual is designed to provide a thorough understanding of the

    fundamental concepts and the practical issues of SCADA systems.Particular emphasis has been placed on the practical aspects of SCADA

    systems with a view to the future. Formulae and details that can be foundin specialized manufacturer manuals have been purposely omitted in favorof concepts and definitions.

    This chapter provides an introduction to the fundamental principles andterminology used in the field of SCADA. It is a summary of the main

    subjects to be covered throughout the manual.

    SCADA (supervisory control and data acquisition) has been around as long

    as there have been control systems. The first 'SCADA' systems utilizeddata acquisition by means of panels of meters, lights and strip chartrecorders. The operator manually operating various control knobs

    exercised supervisory control. These devices were and still are used to dosupervisory control and data acquisition on plants, factories and powergenerating facilities. The following figure shows a sensor to panel system.

    Sensors

    Actuators

    Figure 1.1 Sensors to Panel old days SCADA System

    Chapter 1 Introduction To SCADA Systems Page 1

  • 8/11/2019 Ch1 - Introduction to SCADA Systems

    2/15

  • 8/11/2019 Ch1 - Introduction to SCADA Systems

    3/15

    PRACTICAL SCADA SYSTEMS

    SensorsPLC or DCS

    PLC or DCS

    PLC or DCS

    Network

    Figure 1.2 PC to PLC or DCS

    The advantages of the PLC / DCS SCADA system are:

    The computer can record and store a very large amount of data The data can be displayed in any way the user requires Thousands of sensors over a wide area can be connected to the

    system

    The operator can incorporate real data simulations into the system

    Many types of data can be collected from the RTUs

    The data can be viewed from anywhere, not just on siteThe disadvantages are:

    The system is more complicated than the sensor to panel type

    Different operating skills are required, such as system

    analysts and programmer

    With thousands of sensors there is still a lot of wire to deal with The operator can see only as far as the PLC

    As the requirement for smaller and smarter systems grew, sensors were

    designed with the intelligence of PLCs and DCSs. These devices are knownas lEDs (intelligent electronic devices). The lEDs are connected on afieldbus, such as Profibus, Devicenet or Foundation Fieldbus to the PC.They include enough intelligence to acquire data, communicate to other

    devices, and hold their part of the overall program. Each of these supersmart sensors can have more than one sensor on-board. Typically, an IED

    could combine an analog input sensor, analog output, PID control,

    communication system and program memory in one device.

    IED's

    Field Bus

    Figure 1.3 PC to IEDs using fieldbus

    Chapter 1 Introduction To SCADA Systems Page 3

  • 8/11/2019 Ch1 - Introduction to SCADA Systems

    4/15

  • 8/11/2019 Ch1 - Introduction to SCADA Systems

    5/15

    PRACTICAL SCADA SYSTEMS

    RTU (and PLC) interface

    Scalability

    Security

    Access to data

    Database

    Networking Client/server distributed processing

    These features are discussed and descriped in deep details later in thesemanual.

    SCADA software can be divided into two types, proprietary or open.Companies develop proprietary software to communicate to their

    hardware. These systems are sold as 'turn key' solutions. The mainproblem with this system is the overwhelming reliance on the supplier ofthe system. Open software systems have gained popularity because of the

    interoperability they bring to the system. Interoperability is the ability tomix different manufacturers' equipment on the same system.

    Citect and WonderWare Intouch are just two of the open software

    packages available in the market for SCADA systems. Some packages arenow including asset management integrated within the SCADA system.

    1.3.4 Communication Networks

    Here comes the telemetry part to the picture, communication networks

    are the means by which data is transferred from RTUs (PLC or DCS) at

    remote site to the SCADA software stations. The communication networkmay be as short as 10 meters or as long as thousands of kilometers.

    Many communication technologies have been implemented successfully in

    modern automation systems such as landlines (copper wires and fiberoptics), microwave, radio and even satellite. These technologies vary intheir architectures, speeds, and most important, prices. Details on these

    communication methods are discussed in the next chapter.

    1.4 SCADA SYSTEM BOUNDERIES

    When speaking about SCADA systems, it's very important to define whatis exactly meant by the word "SCADA system", because people mean a lotof things with this word.

    To conclude what they say, we can say it is a matter of boundaries. Eachdefinition include different components of the automation system, for

    example, some people mean with "SCADA system" all automationcomponents and equipments starting from field devices and PLCs throughthe communication network and ending with the SCADA software. Otherpeople exclude the field devices, other people mean only with that word

    the SCADA software.

    Chapter 1 Introduction To SCADA Systems Page 5

  • 8/11/2019 Ch1 - Introduction to SCADA Systems

    6/15

    PRACTICAL SCADA SYSTEMS

    1.5 COMPARISON OF THE TERMS SCADA, DCS, PLC ANDSMART INSTRUMENT

    1.5.1 SCADA System

    A SCADA (or supervisory control and data acquisition) system means asystem consisting of a number of remote terminal units (or RTUs)collecting field data connected back to a master station via a

    communications system. The master station displays the acquired dataand also allows the operator to perform remote control tasks.

    The accurate and timely data (normally real-time) allows for optimizationof the operation of the plant and process. A further benefit is moreefficient, reliable and most importantly, safer operations. This all results in

    a lower cost of operation compared to earlier non-automated systems.

    There is a fair degree of confusion between the definition of SCADAsystems and process control system. SCADA has the connotation of

    remote or distant operation. The inevitable question is how far 'remote' is,typically this means over a distance such that the distance between the

    controlling location and the controlled location is such that direct-wirecontrol is impractical (i.e. a communication link is a critical component of

    the system).

    A successful SCADA installation depends on utilizing proven and reliabletechnology, with adequate and comprehensive training of all personnel in

    the operation of the system.

    There is a history of unsuccessful SCADA systems - contributing factors to

    these systems includes inadequate integration of the various componentsof the system, unnecessary complexity in the system, unreliable hardwareand unproven software. Today hardware reliability is less of a problem,

    but the increasing software complexity is producing new challenges. Itshould be noted in passing that many operators judge a SCADA systemnot only by the smooth performance of the RTUs, communication links

    and the master station (all falling under the umbrella of SCADA system)but also the field devices (both transducers and control devices). The fielddevices however fall outside the scope of SCADA in this manual and will

    not be discussed further. A diagram of a typical SCADA system is givenopposite.

    Chapter 1 Introduction To SCADA Systems Page 6

  • 8/11/2019 Ch1 - Introduction to SCADA Systems

    7/15

    PRACTICAL SCADA SYSTEMS

    Figure 1.4 Diagram of a typical SCADA system

    On a more complex SCADA system there are essentially five levels orhierarchies:

    Field level instrumentation and control devices

    Marshalling terminals and RTUs Communications system

    The master station(s)

    The commercial data processing department computer system

    The RTU provides an interface to the field analog and digital signalssituated at each remote site. The communications system provides the

    pathway for communications between the master station and the remotesites. This communication system can be radio, telephone line, microwaveand possibly even satellite. Specific protocols and error detection

    philosophies are used for efficient and optimum transfer of data.

    Chapter 1 Introduction To SCADA Systems Page 7

  • 8/11/2019 Ch1 - Introduction to SCADA Systems

    8/15

    PRACTICAL SCADA SYSTEMS

    The master station (and submasters) gather data from the various RTUs

    and generally provide an operator interface for display of information andcontrol of the remote sites. In large telemetry systems, submaster sitesgather information from remote sites and act as a relay back to the

    control master station.

    SCADA technology has existed since the early sixties and there are now

    two other competing approaches possible - distributed control system(DCS) and programmable logic controller (PLC). In addition there hasbeen a growing trend to use smart instruments as a key component in all

    these systems. Of course, in the real world, the designer will mix andmatch the four approaches to produce an effective system matchinghis/her application.

    Figure 1.5 SCADA system

    Chapter 1 Introduction To SCADA Systems Page 8

  • 8/11/2019 Ch1 - Introduction to SCADA Systems

    9/15

    PRACTICAL SCADA SYSTEMS

    1.5.2 Distributed control system (DCS)

    In a DCS, the data acquisition and control functions are performed by anumber of distributed microprocessor-based units situated near to the

    devices being controlled or the instrument from which data is being

    gathered. DCS systems have evolved into systems providing verysophisticated analog (e.g. loop) control capability. A closely integrated set

    of operator interfaces (or man machine interfaces) is provided to allow foreasy system configurations and operator control. The data highway isnormally capable of fairly high speeds (typically 1 Mbps up to 10 Mbps).

    Figure 1.6 - Distributed Control System

    1.5.3 Programmable logic controller (PLC)

    Since the late 1970s, PLCs have replaced hardwired relays with acombination of ladder-logic software and solid state electronic input and

    output modules. They are often used in the implementation of a SCADA

    RTU as they offer a standard hardware solution, which is veryeconomically priced.

    Chapter 1 Introduction To SCADA Systems Page 9

  • 8/11/2019 Ch1 - Introduction to SCADA Systems

    10/15

    PRACTICAL SCADA SYSTEMS

    Figure 1.7 - Programmable Logic Controller (PLC) system

    Another device that should be mentioned for completeness is the smartinstrument which both PLCs and DCS systems can interface to.

    1.5.4 Smart instrument

    Although this term is sometimes misused, it typically means an intelligent

    (microprocessor based) digital measuring sensor (such as a flow meter)with digital data communications provided to some diagnostic panel or

    computer based system.

    Figure 1.8 - Typical example of a smart instrument

    Chapter 1 Introduction To SCADA Systems Page 10

  • 8/11/2019 Ch1 - Introduction to SCADA Systems

    11/15

    PRACTICAL SCADA SYSTEMS

    1.6 REMOTE TERMINAL UNITS

    An RTU (sometimes referred to as a remote telemetry unit) as the title

    implies, is a standalone data acquisition and control unit, generallymicroprocessor based, which monitors and controls equipment at some

    remote location from the central station. Its primary task is to control andacquire data from process equipment at the remote location and to

    transfer this data back to a central station. It generally also has thefacility for having its configuration and control programs dynamically

    downloaded from some central station. There is also a facility to beconfigured locally by some RTU programming unit. Although traditionallythe RTU communicates back to some central station, it is also possible to

    communicate on a peer-to-peer basis with other RTUs. The RTU can alsoact as a relay station (sometimes referred to as a store and forwardstation) to another RTU, which may not be accessible from the centralstation.

    Small sized RTUs generally have less than 10 to 20 analog and digital

    signals, medium sized RTUs have 100 digital and 30 to 40 analog inputs.RTUs, having a capacity greater than this can be classified as large.

    1.7 PLCS USED AS RTUS

    A PLC or programmable logic controller is a computer based solid statedevice that controls industrial equipment and processes. It was initially

    designed to perform the logic functions executed by relays, drum switches

    and mechanical timer/counters. Analog control is now a standard part ofthe PLC operation as well.

    The advantage of a PLC over the RTU offerings from variousmanufacturers is that it can be used in a general-purpose role and caneasily be set up for a variety of different functions.

    The actual construction of a PLC can vary widely and does not necessarilydiffer much from generalizing on the discussion of the standard RTU. PLCs

    are popular for the following reasons:

    Economic solution: PLCs are a more economic solution than ahardwired relay solution manufactured RTU

    Versatility and flexibility: PLCs can easily have their logic or

    hardware modified to cope with modified requirements for control

    Ease of design and installation: PLCs have made the design and

    installation of SCADA systems easier because of the emphasis onsoftware

    More reliable: When correctly installed, PLCs are a far more reliable

    solution than a traditional hardwired relay solution or short runmanufactured RTUs.

    Chapter 1 Introduction To SCADA Systems Page 11

  • 8/11/2019 Ch1 - Introduction to SCADA Systems

    12/15

    PRACTICAL SCADA SYSTEMS

    Sophisticated control: PLCs allow for far more sophisticated control

    (mainly due to the software capability) than RTUs.

    Physically compact: PLCs take up far less space than alternative

    solutions.

    Easier troubleshooting and diagnostics: Software and clear cut

    reporting of problems allows easy and swift diagnosis ofhardware/firmware/software problems on the system as well asidentifying problems with the process and automation system.

    PLC software: The ladder-logic approach to programming is popularbecause of its perceived similarity to standard electrical circuits.

    Two vertical lines supplying the power are drawn at each of thesides of the diagram with the lines of logic drawn in horizontal lines.

    1.8 THE MASTER STATION

    The central site/master station can be pictured as having one or moreoperator stations (tied together with a local area network) connected to acommunication system consisting of modem and radio

    receiver/transmitter. It is possible for a landline system to be used inplace of the radio system; in this case the modem will interface directly to

    the landline. Normally there are no input/output modules connecteddirectly to the master stations although there may be an RTU located inclose proximity to the master control room. The features that should be

    available are: Operator interface to display status of the RTUs and enable

    operator control

    Logging of the data from the RTUs Alarming of data from the RTU As discussed earlier, a master

    station has two main functions:

    Obtain field data periodically from RTUs and submaster stations

    Control remote devices through the operator station.

    There are various combinations of systems possible, as indicated in the

    diagram below.

    Chapter 1 Introduction To SCADA Systems Page 12

  • 8/11/2019 Ch1 - Introduction to SCADA Systems

    13/15

    PRACTICAL SCADA SYSTEMS

    Figure 1.9 - Various approaches possible for the master station

    It may also be necessary to set up a submaster station. This is to controlsites within a specific region. The submaster station has the following

    functions:

    Acquire data from RTUs within the region

    Log and display this data on a local operator station Pass data back to the master station Pass on control requests from the master station to the RTUs in its

    region

    Chapter 1 Introduction To SCADA Systems Page 13

  • 8/11/2019 Ch1 - Introduction to SCADA Systems

    14/15

    PRACTICAL SCADA SYSTEMS

    Figure 1.10 - Typical structure of the master station

    The master station has the following typical functions:

    Establishment of communications

    Configure each RTU Initialize each RTU with input/output parameters

    Download control and data acquisition programs to the RTU

    Operation of the communications link

    If a master slave arrangement, poll each RTU for data and write to

    RTU

    Chapter 1 Introduction To SCADA Systems Page 14

  • 8/11/2019 Ch1 - Introduction to SCADA Systems

    15/15

    PRACTICAL SCADA SYSTEMS

    Log alarms and events to hard disk (and operator display if

    necessary)

    Link inputs and outputs at different RTUs automatically

    Diagnostics

    Provide accurate diagnostic information on failure of RTU andpossible problems

    Predict potential problems such as data overloads

    1.9 SYSTEM IMPLEMENTATION

    When first planning and designing a SCADA system, consideration should

    be given to integrating new SCADA systems into existing communicationnetworks in order to avoid the substantial cost of setting up newinfrastructure and communications facilities. This may be carried out

    through existing LANs, private telephone systems or existing radiosystems used for mobile vehicle communications. Careful engineering

    must be carried out to ensure that overlaying of the SCADA system on toan existing communication network does not degrade or interfere with theexisting facilities.

    If a new system is to be implemented, consideration must be given to thequality of the system to be installed. No company has an endless budget.

    Weighing up economic considerations against performance and integrityrequirements is vital in ensuring a satisfactorily working system at the endof the project. The availability of the communications links and the

    reliability of the equipment are important considerations when planningperformance expectations of systems.

    All the aforementioned factors will be discussed in detail in the book. Theywill then be tied together in a systematic approach to allow the reader todesign, specify, install and maintain an effective telemetry and dataacquisition system that is suitable for the industrial environment into

    which it is to be installed.

    Chapter 1 Introduction To SCADA Systems Page 15