13
Ch 2 Project time management

ch 2 Time Manegment

Embed Size (px)

Citation preview

8/7/2019 ch 2 Time Manegment

http://slidepdf.com/reader/full/ch-2-time-manegment 1/13

Ch 2

Project time management

8/7/2019 ch 2 Time Manegment

http://slidepdf.com/reader/full/ch-2-time-manegment 2/13

2.1 Time Management definitions

Wikipedia define Time management: refers to a range of skills, tools,

and techniques used to manage time when accomplishing specific tasks,

 projects and goals. This set encompasses a wide scope of activities, and

these include planning, allocating, setting goals, delegation, analysis of 

time spent, monitoring, organizing, scheduling, and prioritizing. Initially

time management referred to just business or work activities, but

eventually the term broadened to include personal activities as well. A

time management system is a designed combination of processes, tools,techniques, and methods.

PMBOK define Project Time Management:- includes the processes

required to ensure timely completion of the project.

Project Management for Development Organizations define time

management: The project schedule is the organization of all project

activities by time and by their logical dependencies and each with a start

date and a finish date.

So every time we plane project we had to pass throw a lot of action's (that

need an implementation) each action had specific characteristic's: action

time, the labor need for, start and finish of the action..etc the define

activity process is to identify this characteristic, and estimate thischaracteristic, this action's lead to produce a project deliverable's .

The action's arranging by time with process call sequencing activities that

identifying the dependency of actions.

The estimation of project duration need to assign duration for eachactivity and developing the schedule at this time we need to be accurate

8/7/2019 ch 2 Time Manegment

http://slidepdf.com/reader/full/ch-2-time-manegment 3/13

as possible as we can (always we had a degree of uncertainty) in

estimation this depend on estimation method and the experience.

Accurate estimation safe money ….and safe time because it affect on the

whole project duration and the quantity of labor, material, equipment andworking hour's

2.2Activity definition:

Five steps must be prepared before start defining actions:

Step # 1 : work breakdown structure must be done because the first piece

of information needed for this The creation of the project schedule

requires the team to define the conditions that will project step comes

from the WBS that has all the activities identified for the track when each

activity should begin and finish.

Step # 2 : scope statement must be situated the main point in planning

 process is to set the goal's to knew what to do and ,and that contain

developing the time line of the project

Step # 3 : historical information ( experience ) from past similar project

that was a feedback used to improve accuracy of estimation.

Step # 4 : constrains affect on define activities because each time and

each place had specific constrains that control the project and the option

will be limited.

Step # 5 : assumption's will made in any project that will identify thedegree of risk so assumption must be real and based on accurate info

 because it use in planning purpose but the assumption's become more

accurate later and later because after each project feedback will used in

the next project amount of risk will decrease.

2.3How to define activity:

8/7/2019 ch 2 Time Manegment

http://slidepdf.com/reader/full/ch-2-time-manegment 4/13

Decomposition : mean to divide the project to a subdivision's easy to deal

with and more manageable components in order to provide better 

management control the final outputs here are described as activities(action steps) rather than as deliverables (tangible items) some application

, the WBS and the activity list are developed concurrently.

Template: is to use the activity list of previous project as template in the

next project and the activity list for a WBS element from the current

 project may be usable as a template for other, similar WBS elements.

Results:

Activity list: finally activity should be listed including all activity that will

done in implementation phase and the description of each activity ,and

activity arrange as an extension to be sure than no addition activity the

activity list understandably.

Supporting detailed: Supporting detail for the activity list should be

documented and organized as needed to facilitate its use by other project

management processes. Supporting detail should always include

documentation of all identified assumptions and constraints. The amount

of additional detail varies by application area.

Work breakdown structure updates: that the deliverable descriptions need

to be clarified or corrected. Any such updates are needed, the project team

may identify missing deliverables or may determine In using the WBS to

identify which activities must be reflected in the WBS and related

documentation such as cost estimates These updates are often called

(refinements)and are most likely when the project involves new or 

unproven technology.

2.4 Activity Sequencing:

8/7/2019 ch 2 Time Manegment

http://slidepdf.com/reader/full/ch-2-time-manegment 5/13

Activity sequencing pass throw seven steps:

Step #1: activity list: Explained earlier Step #2: constraint: Explained earlier 

Step #3: assumption’s: Explained earlier 

Step #4: product description: Explained in past chapter’s

Step #5: Discretionary dependencies: it mean to recognition dependency

of activities so the important of it comes from any error limit option’s of 

team management the recognition based on:

*Experience in application area

*Some unusual aspect of the project where a specific sequence is desired

Step #6: External dependencies: between project activities and non- project activities External dependencies are those that involve a

relationship.

Step #7: Mandatory dependencies: Mandatory dependencies are those

which are inherent in the nature of the work being done. They often

involve physical limitations (on a construction project it is impossible to

erect the superstructure until after the foundation has been built; on an

electronics project, a prototype must be built before it can be tested).

Mandatory dependencies are also called.

2.4.1How to sequence the activities:

2.4.1.1Precedence diagram method (PDM:(

Method that represent the activities as nodes connecting with an

arrows represent the relationship between this activity and most

scheduling software requires to user to input the data as a

 precedence diagram form, and in PDM each element describe as

follows.

8/7/2019 ch 2 Time Manegment

http://slidepdf.com/reader/full/ch-2-time-manegment 6/13

 Network Logic Diagram Drawn Using the Precedence Diagramming Method .

Shapes of Relationship in PDM are:

1-Finish-to-start—the “from” activity must finish before the “to” activity

can start

2-Finish-to-finish—the “from” activity must finish before the “to”

activity can finish.

3-Start-to-start—the “from” activity must start before the “to” activity

can start

4-Start-to-finish—the “from” activity must start before the “to” activity

can finish.

8/7/2019 ch 2 Time Manegment

http://slidepdf.com/reader/full/ch-2-time-manegment 7/13

2.4.1.2Arrow diagramming method (ADM:(

This is a method of constructing a project network diagram using arrows

to represent the activities and connecting them at nodes to show the

dependencies.

Although less prevalent than PDM, is still the technique of choice insome application areas. ADM uses only finish-to-start dependencies and

may require the use of dummy activities to define all logical relationships

correctly.

ADM can be done manually or on a computer 

8/7/2019 ch 2 Time Manegment

http://slidepdf.com/reader/full/ch-2-time-manegment 8/13

 Arrow Diagram Method 

2.5 Activity list updates

In much the same manner that the activity definition process may

generate updates to the WBS, preparation of the project network diagram

may reveal instances where an activity must be divided or otherwise

redefined in order to diagram the correct logical relationships.

Activity estimation time:

2.5.1Estimation of activity time need to make:

1-Activity list: Explained earlier 

2-Constraints: Explained earlier 

3-Assumptions: Explained earlier 

4-Resource requirements: amount of resource affect on the time of any

activity for example two person can achieve some activity in specific

time however one of them will need double time and one person with

apart time work need more time so assigning the resources and leveling it

affect on the time needed for activity

5-Resource capabilities: the productivity of any unit of resource affect on

the time estimation which need an accurate estimation for the

 productivity of each unit for example old equipment or old staff member 

need time more than the new equipment or young staff member toachieve the specific work .

8/7/2019 ch 2 Time Manegment

http://slidepdf.com/reader/full/ch-2-time-manegment 9/13

6- Historical information: Historical information on the likely durations

of many categories of activities is often available from one or more of the

following sources:

1- Feedback from previous projects helps estimation time for project

 by comparing and interpolating two projects with area and member 

of the team which work 

2- Commercial duration estimating databases: historical information

is often available commercially. These databases tend to be

especially useful when activity durations are not driven by the

actual work content for example how long it takes concrete to cure;

how long does a government agency usually take to respond tocertain types of requests.

3- Project team knowledge: experience of team member facilitate the

estimation process from previous project they work in.

2.5.2 How to estimate time needed for any

project:

1- Expert judgment: it’s guided by historical information should be

used whenever possible. If such expertise is not available, the

estimates are uncertain and risky

2-Analogous estimating: some activities repeated in more than one

 project so estimating activity using previous data from previous

 project will be accurate enough It is frequently used to estimate

 project duration when there is a limited amount of detailed

information about the project.

3- Simulation: involves calculating multiple durations with different

sets of assumptions. The most common is Monte Carlo Analysis

2.6 Schedule development

Developing the schedule need to prepare:

8/7/2019 ch 2 Time Manegment

http://slidepdf.com/reader/full/ch-2-time-manegment 10/13

1- Project network diagram: explained earlier 

2- Activity duration estimates: explained earlier 

3- Resource requirements: explained earlier 

4- Assumptions: explained earlier 

5- Resource pool description: Knowledge of what resources

will be available at what times and in what patterns is necessary

for schedule development. The amount of detail and the level of 

specificity in the resource pool description will vary.

6- Calendars: Project and resource calendars identify periods

when work is allowed. Project calendars affect all resources,

Resource calendars affect a specific resource or category of resources .

7- Constraints: explained earlier 

There are two major categories of constraints that must be

considered during schedule development:

• Imposed dates: Completion of certain deliverables by a specifieddate may be required by the project sponsor, the project customer,

or other external factors.

• Key events or major milestones: Completion of certain

deliverables by a specified date may be requested by the project

sponsor, the project customer, or other stakeholders. Once

scheduled, these dates become expected and often may be moved

only with great difficulty.

8- Leads and lags: Any of the dependencies may require

specification of a lead or a lag in order to accurately define the

relationship.

2.6.1 How to develop a schedule for any project:

1-Mathematical analysis: Mathematical analysis involves calculating

theoretical early and late start and finish dates for all project

activities without regard for any resource pool limitations.

8/7/2019 ch 2 Time Manegment

http://slidepdf.com/reader/full/ch-2-time-manegment 11/13

The data that we get from this process are not a schedule but indicate

the period of time which activity should scheduled

Most common mathematical analysis techniques are:

• Critical Path Method (CPM): it focusing on CPM is on

calculating float in order to determine which activities have the

least scheduling flexibility.

• Graphical Evaluation and Review Technique (GERT):

allows for probabilistic treatment of both network logic and

activity duration estimates

Program Evaluation and Review Technique (PERT): usessequential network logic and a weighted average duration

estimate to calculate project duration.

2- Duration compression:

Duration compression is a special case of mathematic analysis that

looks for ways to shorten the project schedule without changing the

 project scope .

Duration compression includes techniques such as:

• Crashing:

In which cost and schedule trade-offs are analyzed to determine

how to obtain the greatest amount of compression for the least

incremental cost. Crashing does not always produce a viable

alternative and often results in increased cost.

• Fast tracking:

Doing activities in parallel that would normally be done insequence , Fast tracking often results in rework and usually

increases risk.

3- Simulation: explained earlier.

4- Resource leveling heuristics:

Mathematical analysis often produces a preliminary schedule that

requires more resources during certain time periods than are available,

or requires changes in resource levels that are not manageable.Heuristics such as “allocate resources to critical path activities first”

8/7/2019 ch 2 Time Manegment

http://slidepdf.com/reader/full/ch-2-time-manegment 12/13

can be applied to develop a schedule that reflects such constraints.

Resource leveling often results in a project duration that is longer than

the preliminary schedule.

5- Project management software:Project management software is widely used to assist with schedule

development. These products automate the calculations of 

mathematical analysis and resource leveling and thus allow for rapid

consideration of many schedule alternatives. They are also widely

used to print or display the outputs of schedule development.

Result:

Project schedule: The project schedule includes at least planned startand expected finish dates for each detail activity

The project schedule may be presented in summary form (the “master 

schedule”)

or in detail. Although it can be presented in tabular form, it is more

often presented graphically using one or more of the following

formats:

• Project network diagrams: with date information added these charts

usually show both the project logic and the project’s critical path

activities

• Bar charts: also called Gantt charts, show activity start and end dates

as well as expected durations, but do not usually show dependencies.

They are relatively easy to read and are frequently used in

management presentations.

• Milestone charts: similar to bar charts, but identifying the Scheduled

start or completion of major deliverables and key external interfaces

• Time-scaled network diagrams: are a blend of project network 

diagrams and bar charts in that they show project logic, activity

durations, and schedule information.

Supporting detail: Supporting detail for the project schedule includes

at least documentation of all identified assumptions and constraints.

The amount of additional detail varies by application area. For 

example:

8/7/2019 ch 2 Time Manegment

http://slidepdf.com/reader/full/ch-2-time-manegment 13/13

• On a construction project: it will most likely include such items as

resource histograms, cash flow projections, and order and delivery

schedules.

• On an electronics project: it will most likely include resourcehistograms only. Information frequently supplied as supporting detail

includes, but is not limited to:

• Resource requirements by time period, often in the form of a

resource histogram.

• Alternative schedules

• Schedule reserves or schedule risk assessments

Schedule management plan: A schedule management plan defines

how changes to the schedule will be managed. It may be formal or 

informal, highly detailed or broadly framed based on the needs of the

 project. It is a subsidiary element of the overall project plan

Resource requirement updates: Resource leveling and activity list

updates may have a significant effect on preliminary