CFR SA’S PROJECTS FOR DEVELOPING THE ROMANIAN
RAILWAY INFRASTRUCTURE
Meeting AECOM, AM SOP-T, CFR, JASPERS
Bucharest, February 22, 2013
2
The modernization of CFR SA’s railway infrastructure will enable the achievement of the following technical parameters: • running speeds of 160 km/h for passenger trains and of 120
km/h for freight trains• electrified double line• introduction of ERTMS and of traffic control systems. In this way, the railway infrastructure will be compliant
with the technical parameters set down in the international agreements AGC, AGTC and TER.
MODERNIZATION OF RAILWAY LINES
3
Forecast benefits of the railway line modernization• Increase in the freight and passenger traffic • Decrease in the travelling time• Increase in the quality of the freight and passenger transport
services• Decrease in the pollution caused by the railway transport• Decrease in the fuel consumption • Decrease in the operating costs• Decrease in the rolling stock and infrastructure maintenance
costs.
4
PAN-EUROPEAN TRANSPORT CORRIDORS SITUATED ON THE ROMANIAN TERRITORY
Length of Corridor IV – 1,364 km
Length of Corridor IX – 551 km
5
CFR SA’s projects, completed and in progress
• Modernization of the railway sections included in Corridor IV
MODERNIZATION OF RAILWAY SECTIONS
7
Railway infrastructure projects under preparation
• Modernization of the railway sections included in the Northern and Southern branches of
Corridor IV• Modernization of tunnels, bridges and culverts
• Development of intermodal transport• Increase in traffic safety
8
MODERNIZATION OF THE Km 614 – GURASADA SECTION
Km 614 – Gurasada (102 km)Estimated value: EUR 1,336,936,721 without VAT Status: Feasibility Study under completion, EA obtained, Technical Design and Detail Engineering under completion Financing proposal: Cohesion Funds (SOP-T 2007 – 2013 and 2014 - 2020) + the State Budget Execution duration: 2013- 2018
9
MODERNIZATION OF THE GURASADA – SIMERIA SECTION
Gurasada – Simeria (42 km)Estimated value: EUR 632,951,759 Financing proposal: Cohesion Funds (SOP-T 2007 – 2013 and 2014 - 2020) + the State BudgetStatus: Feasibility Study, Technical Design and Detail Engineering under approval, EA obtainedExecution duration: 2013- 2018
10
MODERNIZATION OF THE BRASOV - SIGHISOARA SECTION
Brasov - Sighisoara (130 km)Estimated value: EUR 1,739,712,000Financing proposal: Cohesion Funds (SOP-T 2014 - 2020) + the State Budget Status: Feasibility Study completed, Technical Design completed, EA under completionExecution duration: 2014 – 2019
11
Brasov - Predeal (26 km)Estimated value: EUR 200,488,000 Financing proposal: Cohesion Funds (SOP-T 2014 - 2020) + the State BudgetStatus: Feasibility Study under evaluationExecution duration: 2015 – 2019
MODERNIZATION OF THE BRASOV – PREDEAL SECTION
12
MODERNIZATION OF THE CRAIOVA – CALAFAT SECTION
Craiova – Calafat (108 km) Estimated value: EUR 566,563,000 Financing proposal: Cohesion Funds (SOP-T 2014 - 2020) + the State BudgetStatus: Feasibility Study completed and approved by CFR, EA under completionDesigning: scheduled for 2014 - 2017Execution duration: 2018 – 2020 if the financing is supplied
13
MODERNIZATION OF THE CRAIOVA – CARANSEBES SECTION
Craiova – Caransebes (227 km)Estimated value:
EUR 1,620,000,000 Financing proposal: Cohesion Funds (SOP-T 2014 - 2020) + the State BudgetStatus: Assessment Study completedDesigning: FS 2013 – 2015, TD and DE 2016 – 2017 if the financing is supplied Proposed execution duration: 2018 – 2020 if the financing is supplied
14
MODERNIZATION OF THE ARAD – CARANSEBES SECTION
Caransebes – Arad (155 km)Estimated value: EUR 670,000,000Financing proposal: Cohesion Funds (SOP-T 2014 - 2020) + the State BudgetStatus: Assessment Study completedDesigning: FS 2013 – 2015, TD and DE 2016 – 2017 if the financing is supplied Execution duration: 2018 – 2020 if the financing is supplied
15
MODERNIZATION OF THE RAILWAY STATIONS – STAGE IV
Modernization of 5 railway stations: Baia Mare, Satu Mare, Miercurea Ciuc, Targu Jiu and Targoviste
Value: EUR 43,000,000
Financing proposal: SOP-T 2014 - 2020 + the State Budget
Execution duration: 2014-2016
16
Bridges Tunnels CulvertsTotal
structures
94 19 60 173
Bridge and tunnel rehabilitation works on
the TEN-T Railway Network Stage II
Rehabilitation works for 173 railway bridges, culverts and tunnels
Investment value: EUR 256 million
Financing proposal: SOP-T 2014 - 2020 + the State Budget
Status: FS completed
Project preparation: FS 2013-2015, TD 2016-2017
Execution duration: 2018 - 2020
17
PROJECTS FOR INCREASING TRAFFIC SAFETY Stage II
Modernization of railway level-crossings – 154 level-crossings
Value: EUR 28,063,659
Financing proposal: SOP-T 2014 - 2020 + the State Budget
Execution duration: 2014-2020 Modernization of the electro-dynamic interlocking systems in 17 railway stations
Value: EUR 103,986,000
Financing proposal: SOP-T 2014 - 2020 + the State Budget
Execution duration: 2014-2020
THE RAILWAY LINE BUCURESTI NORD – HENRI COANDA INTERNATIONAL AIRPORT
Railway/underground common station
Estimated value: EUR 417,878,890
Financing proposal: SOP-T 2007-2013 or 2014 - 2020 +
the State Budget
FS review: 2013
Preparation and execution: 2013-2015
Status: FS completed
The Henri Coanda International Airport
THE RE-OPENING OF THE RAILWAY TRAFFIC ON THE NEW BRIDGE ON ARGES RIVER BETWEEN VIDRA AND GRADISTEA RAILWAY STATIONS
Estimated value: EUR 57,000,000
Financing proposal: SOP-T 2007-2013 or 2014 - 2020 + the State Budget
FS review: 2013
Preparation and execution: 2013-2015
Status: FS completed
CONSTRUCTION OF INTERMODAL TERMINALS
Estimated value: EUR 118 million
Financing proposal: SOP-T 2007-2013 and 2014 - 2020
+ the State Budget
Status: Feasibility Studies launched
Execution duration: 2013 – 2016
MODERNIZATION OF THE RAILWAY RING OF THE MUNICIPALITY OF BUCHAREST
Estimated value: EUR 500,000,000
Financing proposal: SOP-T 2014 - 2020 + the State
Budget
Status: Opportunity Study prepared
Execution duration: 60 months if financing is ensured
THE HIGH SPEED RAILWAY LINE
PROJECT PROPOSED FOR PUBLIC – PRIVATE PARTNERSHIP• The High Speed Railway Line is an integral part of the TEN-T comprehensive network as a sustainable solution for ensuring mobility at EU level • The extension of the Paris - Vienna high speed line by means of the connection Vienna – Budapest – Szeged• Estimated value: EUR 11 billion• Status: Launching of the Prefeasibility Study proposed to be financed from SOP-T 2007-2013 or 2014-2020
THANK YOU FOR YOUR ATTENTION!