Certification PilotMay 5, 2010

Walton FehrUS Department of Transportation

ITS Joint Program Office

IntelliDrive Connectivity and the Future of Surface

Transportation

2

Safety Pilot Roadmap (rev 14)

CY 2010 CY 2011 CY 2012Q1

Independent Evaluation of Testing Activities

CY 2013Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

V2V Regulatory Decision Point

Model Deployment Ramp-up and Preliminary Testing

Input to Industry standards based upon test results

Device Updates

Light Vehicle Driver Clinics & Performance

Testing

Driv

er C

linic

sM

odel

Dep

loym

ent

Eva

luat

ion

V2V Benefits Assessment

Initial Integrated Safety System Light Vehicle Builds

Vehicle Updates

Model Deployment Full Scale Testing

Aftermarket Device Development

Transit Vehicle Roadeo

Heavy Vehicle

Ray Resendes, Mike Schagrin

3

Certification FrameworkTim McGuckin, OmniAir Team

4

DRAFT

Certification Pilot Roadmap Draft (based on rev 13 of safety pilot roadmap and published Sources Sought Notice DTFH61-10-R-00026))

CY 2010 CY 2011

1st Device ProcurementQPL

Established

WC Orlando

Issue Device Solicitation

Awards

M A M J J A S O N M A M J J A S O ND J F D

Qualification Testing /

Tech. Eval.

Spec. Development

Recommendation for the IntelliDrive Certification Organizational Structure and Process Pilot

Update Qualification

Tests

Cert. Pilot SOW

Cert. Pilot Development

Qualification Test SOW

OmniAir proposal including subs

Auth. to proceed

Spec. Review

Develop Qualification Tests

Proposal/Device Submission

1st SpecUpdate

2nd SpecUpdate

Device Procurement for Field Test

Certification Pilot

5

Goal of this Pilot

• Pilot IntelliDrive System management processes at the same time we pilot IntelliDrive technology and applications.

• Have useful tools in place to assist the technology and application pilot.

• Include both the communication medium and the application elements in the pilot. (These would likely have separate certification processes in a full deployment.)

6

Certification FrameworkTim McGuckin, OmniAir Team

7

Safety Pilot Roadmap (rev 14)

CY 2010 CY 2011 CY 2012Q1

Independent Evaluation of Testing Activities

CY 2013Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

V2V Regulatory Decision Point

Model Deployment Ramp-up and Preliminary Testing

Input to Industry standards based upon test results

Device Updates

Light Vehicle Driver Clinics & Performance

Testing

Driv

er C

linic

sM

odel

Dep

loym

ent

Eva

luat

ion

V2V Benefits Assessment

Initial Integrated Safety System Light Vehicle Builds

Vehicle Updates

Model Deployment Full Scale Testing

Aftermarket Device Development

Transit Vehicle Roadeo

Heavy Vehicle

Ray Resendes, Mike Schagrin

8

Task Alignment, Part 1

• Spec Development leads to qualification test development

• Qualification test development is finished in time to be applied to the material from the 1st Device Procurement

• Qualification test is exercised on 1st devices

9

Task Alignment, Part 2

• Certification management structure is developed

• Qualification test is updated

• Entire process – management and qualification is applied to the 2nd device material