cernprogress

Embed Size (px)

Citation preview

  • 8/3/2019 cernprogress

    1/5

    ..c

    No Time for DowNTime

    When youre trying to understand the building blocks o matter, the origin o

    the universe and everything in between, system downtime is not an option. CERN,

    the European Organization or Nuclear Research, explores these complex, epic

    issues using the worlds largest and most powerul particle accelerator, the Large

    Hadron Collider (LHC).

    CERNs goal is to recreate the Big Bang with the LHC, using its thousand

    15-meter magnets to re particles into each other. With particles colliding at

    the speed o light, the Technical Inrastructure Monitoring (TIM) system tracking

    LHC operations must be reliable. Thats why CERN adopted Progress

    SonicMQ

    ,

    the industrys most robust and resilient enterprise messaging system, as the

    communications inrastructure or TIM.

    T h e C h a l l e n g e

    Ensure the Technical Infrastructure

    Monitoring system is reliable

    T h e S o l u T i o n

    A high-performing, continuously

    available messaging system

    T h e R e S u l T

    Real-time insight into Large Hadron

    Collider operations; zero downtime

    for the monitoring infrastructure; over

    150 systems monitored with 50,000

    measuring points delivering nearly

    2.6 million values a day

    How CerNmakes progress

  • 8/3/2019 cernprogress

    2/5

    2

    ..c

    a Complex TeCHNiCal iNfrasTruCTure

    Located west o Lake Geneva, CERN is spread out over Swiss and

    French territory. The most important systems, such as the Large Hadron

    Collider, are underground. The LHC is in a circular tunnel with a circumerence

    o 27 km, the latest addition to CERNs existing linear and circular accelerators.

    In the LHC tunnel, more than 1,000 super conducting magnets, each

    15 meters long, will accelerate elementary particlesprotons or heavy

    ionsthrough a vacuum lled tunnel to 99.99% o the speed o light. When

    these particles are red into each other in opposing trajectories, their impacts

    involve extremely high energy levels. Physical conditions similar to those

    immediately ater the Big Bang are created or ractions o a second.

    Its no surprise that it takes a highly complex technical inrastructure

    to run this huge research laboratory and its scientic systems. These includes

    the power supplythe LHC needs as much electricity as all o the households

    in the city o Geneva combinedventilation o underground systems,

    rerigeration or the super conducting magnets, high-perormance vacuum

    pumps, water pumps, air conditioners, re alarms, communication systems

    and access control.

    Currently, over 100 technical inrastructure systems with about25,000 individual measuring points generate around 1.3 million individual

    items o inormation daily. When the LHC becomes ully operational, over 150

    systems with 50,000 measuring points will be delivering around 2.6 million

    values a day.

    This inrastructure is monitored round the clock by the CERN Control

    Centre (CCC), built or the LHC on the French CERN site in Prvessin. The data

    to be monitored is collected, evaluated, stored and distributed using CERNs

    Technical Inrastructure Monitoring system (TIM). Using TIM, the status oany equipmentany vacuum pump, relay or valvecan be checked online

    at any time. This inrastructure inormation is kept completely separate rom

    physics data and experimental results, which are managed in dedicated IT

    systems in a separate control center.

  • 8/3/2019 cernprogress

    3/5

    3

    ..c

    moNiToriNg wiTH Tim

    The inormation provided by the inrastructure systems is merged in

    TIM and provided to users via a graphical user interace, ensuring a consistent

    look and eel. A logging system integrated in TIM automatically stores selected

    data or urther evaluation and subsequent checking. This is useul or post-

    mortem analysis o severe equipment malunctions.

    Just as important, TIM automatically inorms the central LHC Alarm

    Service (LASER) o problems with the technical inrastructure that may be o

    interest to the dierent site services. In total, TIM contains about 20,0000

    denitions o potential ault situations.

    TIM collects data rom a broad range o dierent, widely distributed

    systems and also orwards control instructions to those systems, explains

    Jan Stowisek, a CERN engineer responsible or the TIM system. We have

    thereore implemented a fexible data acquisition mechanism that supports

    a large number o protocols and can be expanded by additional protocols

    i required.

    CERN started implementing TIM in 2003. It used J2EE because a

    number o systems at CERN were already based on this technology. Using

    similar hardware and sotware platorms or multiple systems signicantlyreduced support costs.

    For its communication inrastructure, TIM uses Progress Sotwares

    messaging middleware, SonicMQ, based on JMS. As an asynchronous,

    messaging-oriented solution, JMS is much better suited or the challenges

    TIM aces than a connection-oriented client-server approach such as those

    supported by RMI or CORBA. It is the only communication protocol between

    the data acquisition, processing and distribution layers.

    Also, JMS allows a clear separation o these layers, which means

    that the implementation o one layer is independent o the implementation

    o the other system components, explains Jan Stowisek. This is very

    convenient or maintenance work. For instance, we can perorm maintenance

  • 8/3/2019 cernprogress

    4/5

    4

    ..c

    on the application server without having to restart any o the client

    applications. JMS is also used or communication with the LASER

    alarm system.

    HigHly available CommuNiCaTioNsiNfrasTruCTure

    The initial TIM prototype was based on OpenJMS as a messaging

    middleware and JBoss as an application server. However, because a large

    volume o data needs to be processed, CERN required a highly available and

    high-perormance solution.

    Considering the signicant investments made at CERN, ailures o the

    control systems could have serious consequences and result in a substantial

    nancial burden. Unplanned downtime is unacceptable or such costly

    systems, considering that physicists rom all over the world who come to

    CERN or only a ew days would be interrupted in their experiments.

    We tested SonicMQ and were convinced by its availability eatures,

    especially with regard to clustering and load balancing, and its fexible

    conguration options, explained CERN Project Manager Anna Suwalska. We

    also received excellent support by Progress Sotware sta during our tests

    and during our subsequent design work or the solution.

    In its operational conguration, TIM currently uses a cluster o

    two SonicMQ brokers to ensure optimal availability. A third broker installed

    on a separate server manages the cluster. On the hardware side, the TIM

    application servers and JMS brokers are hosted on HP Proliant servers. An

    additional server is standing by to take over immediately should one o the

    primary servers ail.

    The scalability o the SonicMQ messaging solution is also critical

    or TIM. Currently, only the smaller CERN accelerators are being used or

    experiments. However, oncethe LHC is ready or operation, the amount o

    data to be processed will be ar greater. For this reason, urther servers can

    be added to the TIM inrastructure when necessary. SonicMQ now orms the

    W tstd ScMQ d

    wr cvcd by ts

    vbty ftrs,spcy wt rrd

    t cstr d d

    bc, d ts

    fxb cfrt

    pts. W s

    rcvd xct

    spprt by Prrss

    Sftwr stff dr

    r tsts d dr r

    sbsqt ds wrk

    fr t st.

    Anna Suwalska

    CERN Project Manager

  • 8/3/2019 cernprogress

    5/5

    backbone o TIM and, thus, o a large part o the technical inrastructure.

    A wide variety o inormation comes together on this bus and is distributed

    to various client systems.

    The solution is very reliable, explained CCC Technical Inrastructure

    Operations Manager Peter Sollander. Our success with TIM and LASER

    shows that J2EE technology is not just or eCommerce applications, but that it

    is also suitable or industrial process control, summarized Jan Stowisek.

    progress sofTware

    Progress Sotware Corporation (NASDAQ: PRGS) is a global sotware company that enables enterprises to

    be operationally responsive to changing conditions and customer interactions as they occur. Our goal is to

    enable our customers to capitalize on new opportunities, drive greater eciencies, and reduce risk. Progress

    oers a comprehensive portolio o best-in-class inrastructure sotware spanning event-driven visibility

    and real-time response, open integration, data access and integration, and application development and

    managementall supporting on-premises and SaaS/cloud deployments. Progress maximizes the benets

    o operational responsiveness while minimizing IT complexity and total cost o ownership.

    worlDwiDe HeaDquarTers

    Progress Sotware Corporation, 14 Oak Park, Bedord, MA 01730 USA

    Tel: +1 781 280-4000 Fax: +1 781 280-4095 On the Web at: ..c

    For international oce locations and contact inormation, please reer to:

    ..c/dd

    2009 Progress Sotware Corporation and/or its subsidiaries or aliates. All rights reser ved. Progress and SonicMQ are trademarks

    or registered trademarks o Progress So tware Corporation or one o its aliates or subsidiaries in the U.S. and other countries. Any

    other trademarks contained herein are the property o their respective owners. Specications subject to change without notice.

    Rev. 09/09 | 6252-127876

    5

    CerN

    CERN (European Organization or Nuclear Research) was ounded in Geneva on 29 September, 1954, and currently

    has 20 member states. With more than 3,000 people, CERN is the worlds largest particle physics research acility.In addition, over 6000 guest scientists (called Users) rom around the world are taking part in research in the

    elds o particle and high-energy physics at CERN. The results primarily serve basic research and the development

    o physical theories. CERN has built the worlds largest particle accelerator, the LHC (Large Hadron Collider), with a

    circumerence o 27 km. The LHC became operational in 2007. www.cern.ch

    progress soNiCmq

    SonicMQ is the most robust and reliable enterprise-class messaging system. In addition to i ts unparalleled

    availability and perormance, it eatures unusually powerul management options and a new level o scalability or

    large and complex enterprise-class implementations. SonicMQ guarantees continuous availability with its Sonic

    Continuous Availability Architecture

    , or which patents are pending. Together with advanced cluster technologies,

    dynamic routing architecture ensures that SonicMQ installations can be expanded with great fexibility.

    The management and implementation inrastructure provided by SonicMQ simplies work related to mission-

    critical corporate communication systems signicantly and reduces overall operating costs. Comprehensive support

    or authentication, authorization and encryption unctions keeps messages and systems secureboth inside and

    outside the rewall.