CEESP Project Management. Unit Eight

Embed Size (px)

Citation preview

  • 7/29/2019 CEESP Project Management. Unit Eight

    1/41

    Project Management

    Purchasing Management

    Lecturer: Javier Daz lvarez

    Electrical EnergyConversion andPower Systems

    Universidadde Oviedo

  • 7/29/2019 CEESP Project Management. Unit Eight

    2/41

    Purchasing Management Plan Procurements

    Conduct Procurements

    Administer Procurements

    Close Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    3/41

    Purpose

    Determine what to procure, when, how and from whom

    3

    Plan Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    4/41

    We need to use:

    Baselines

    Scope Cost

    Schedule

    Requirements documentation

    Teaming agreements

    Risk Register

    4

    Plan Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    5/41

    Types of Contracts. Fixed Price

    Firm fixed price (FFP). A lump-sum contract under which the

    seller furnishes goods or services at a fixed price. The sellerbears all risk, but is compensated with the greatest profitpotential. FFP is the most common contract type, because it isbest suited for situations with reasonably definite

    specifications and relatively certain costs

    5

    Plan Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    6/41

    Types of Contracts. Fixed Price

    Fixed price incentive (FPI). A contract in which the buyer pays

    the contractor for the actual allowable cost incurred, not toexceed a ceiling price defined in the contract, and thecontractor can earn more or less profit depending on its abilityto meet defined cost or performance criteria. Some sharing of

    risk with this contract type exists, but in general, the seller istaking more risk than the buyer. This type of contract is usedprimarily for high-value projects involving long performanceperiods (for example, shipbuilding and major systems

    development projects)

    6

    Plan Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    7/41

    Types of Contracts. Fixed Price

    Fixed price with economic price adjustment (FP-EPA). A

    contract used when a long-term (multiyear) agreement existswith accommodation to account for the fluctuations ininflation, commodity prices, or other external price increases.This contract type is designed to protect both the buyer and

    the seller from external influences outside their control.

    7

    Plan Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    8/41

    Types of Contracts. Fixed Price

    8

    Plan Procurements

    Contract Type Actual Costs Profilt Incentive

    FPF. Firm

    Fixed Price

    No, lump-sum

    payment

    Defined by the ability to meet

    defined cost and performance

    criteria

    No

    FPI. FixedPrice Incentive

    Yes, actual cost noto exceed a

    ceiling price

    Defined by the ability to meetdefined cost and performance

    criteria

    Yes, given forsuperior

    performance

    FP-EPA. Fixed

    Price withEconomic Price

    Adjustment

    No, lump-sum

    payment adjustedfor inflation rates

    or other exteral

    monetary factors

    Dictated by the ability to meet

    defined cost and performancecriteria and the adjustments

    made per the external factors

    No

  • 7/29/2019 CEESP Project Management. Unit Eight

    9/41

    Types of Contracts. Cost Reimbursement

    Cost plus incentive fee (CPIF). A CPIF contract allows overrun

    or underrun sharing of cost through a predetermined formulafor fee adjustment. The maximun and minimum fees limit thefee in this contract type. If the actual cost is less than theexpected cost, the buyer and seller share the savings. If the

    actual cost exceeds the expected cost, the buyer and sellershare the overrun. This contract type is used predoinantly forprojects with long performance periods and substantialhardware development and test requirements

    9

    Plan Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    10/41

    Types of Contracts. Cost Reimbursement

    Cost plus fixed fee (CPFF): A CPFF contract provides for the

    reimbursement of allowable costs plus a fixed fee paidproportionately as the contract progresses. Because thesellers fee is fixed, there is no motivation to control costs.Therefor, most risk remains with the buyer. This contract type

    is used predominantly for reserch and development projects inwhich the effort required remains uncertain until the project iswell under way.

    10

    Plan Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    11/41

    Types of Contracts. Cost Reimbursement

    Cost plus award fee (CPAF). A CPAF contrct reimburses for

    actual costs, but the fee is largely based on the sellersperformance against subjective criteria built into the contract.The buyer determines how well the seller has met thosecriteria.

    11

    Plan Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    12/41

    Types of Contracts. Cost Reimbursement

    Cost plus percentage of cost (CPPC): A CPPC contract provides

    for the reimbursement of allowable costs of servicesperformed plus an agreed-upon percentage of the actual costas profit. The seller is only obligated to make its best effort tofulfill the contract within the estimated amount; the buyer

    funds all overruns. It is not allowed in the USA.

    12

    Plan Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    13/41

    Types of Contracts. Cost Reimbursement

    13

    Plan Procurements

    Contract Type Actual

    Costs

    Profit Incentive

    CPIF. Cost plus

    incentive fee

    Yes Allows overrrun or underrun sharing of

    expenses through a predetermined

    formula.

    Maximun and minimum fee limits the

    fee in the contract

    Yes

    CPFF. Cost plus fixed

    fee

    Yes Fixed fee paid as the contrct progresses No

    CPAF. Cost plus award

    fee

    Yes Dictated by the sellers ability to serve

    the subjective criteria dictated withinthe contract and awarded accordint to

    the buyers determination that the

    criteria have been satisfied

    Yes

    CPPC. Cost plus

    percentage of cost

    Yes Calculated from percentage of actual

    cost

    No

  • 7/29/2019 CEESP Project Management. Unit Eight

    14/41

    BuyersRisk

    Sellers

    Risk

    14

    Plan ProcurementsType of Contrat

    CPPC

    CPFF

    CPIF

    CPAF

    FPI

    FP-EPA

    FFP

  • 7/29/2019 CEESP Project Management. Unit Eight

    15/41

    Purchasing Management Plan Procurements

    Conduct Procurements

    Administer Procurements Close Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    16/41

    Purpose

    Obtain quotes or bids, select a seller, and award a contract

    16

    Conduct Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    17/41

    Statement of work

    It describes the procurement item in sufficient detail so that

    prospective sellers can determine whether they are capable ofproviding the item. It is a narrative description of the productsor services to be supplied under contract.

    It is important that the SOW be as clear, complete, and concise

    as possible.

    17

    Conduct Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    18/41

    Some tools (I):

    Bidder conferences and advertising: Conferences with

    prospective sellers are often held to ensure that sellers have aclear, common understanding of the procurement product.Responses to questions must be incorporated into theprocurement documents as amendments so all prospective

    sellers remain on equal standing. Advertising also is used toexpand existing lists of potential sellers where appropriate

    18

    Conduct Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    19/41

    Some tools (II-a):

    Proposal evaluation techniques:

    Wighting system: method of quantifying qualitative data to minimizethe effect of personal prejudice. Most systems involve:

    Assigning a numerical weight to each of the evaluation criteria

    Rating the proposed sellers on each criterion

    Multiplying the weight by the rating Totaling the resultant products to compute an overall score

    Screening system: establishment of minimum performancerequirements for one or more of the evaluation criteria. This methodmeans that a prospective seller may be required to propose a projectmanager with specific qualifications befor the remainder of theproposal would be considered

    19

    Conduct Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    20/41

    Some tools (II-b): Seller rating system: tied to evaluation criteria, the seller rating

    system is an organizational tool that evaluates considerations likeseller past performance, quality ratings, and compliance.

    20

    Conduct Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    21/41

    Some tools (III):

    Independent estimates: preparation of the procuring

    organizations own estimate as a reference point against whichcontractor proposals are ompared. Significant differences mayindicate that the Statement of Work (SOW) was not adequateor that the prospetive seller either misunderstood or failed to

    respond to the SOW. These estimates are often referred to asshould cost estimates.

    Expert judgment: the expertise to review proposals can comefrom many differente parts in the organization

    21

    Conduct Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    22/41

    Some tools (IV):

    Contract negotiations: clarification and mutual agreement on

    the contract structure and requirements. Subjects ofteninclude responsibilities and authorities, applicable terms andlaw, technical and business management approaches, contractfinancing, and price. Contract negotiation may be a separate

    process with inputs and outputs for complex procurementitems.

    22

    Conduct Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    23/41

    Negotiation stages:

    Protocol: Introductions are made and the atmosphere is set.

    Probing: Negotiators identify issues of concern, as well as thestrengths and weaknesses of the other party.

    Scratch bargaining: The actual bargaining occurs andconcessions are made.

    Closure: Positions are summed up and final concessions aremade.

    Agreement: The final agreement is documented.

    23

    Conduct Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    24/41

    Negotiation tactics (I):

    Deadline: imposing a deadline for reaching an agreement.

    Surprise: taking the other party by surprise with newinformation.

    Limited authority: claiming an inability to finalize theagreement just reached (a stalling tactic).

    Missing man: claiming that the person with final authority isabsent.

    Fair and reasonable: Offering comparisions to other situations,

    for example, to show that the price offered is reasonable Strategic delay: Requesting a recess to divert attention from

    the present discussion or to regroup.

    24

    Conduct Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    25/41

    Negotiation tactics (II):

    Reasoning together: Collaborating to resolve problems for

    everyones benefit. Withdrawal: Making a false attack on an issue and the retrating

    (to diver attention from a weakness).

    Unreasonable: Making the other partys request appear

    unreasonable. Suggesting arbitration: Attempting to scare the other party

    into agreement.

    Fait accompli (hecho consumado): Claiming that a topic ofdispute has already been decided or accomplished and cannotbe changed

    25

    Conduct Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    26/41

    Contract document (I):

    SOW

    Schedule basline Performance reporting

    Period of performance

    Place of performance

    Pricing

    Roles and responsibilities

    Payment terms

    Place of delivery

    Inflation adjustments

    26

    Conduct Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    27/41

    Contract document (II):

    Handling changes

    Warranties Limitations of liability

    Insurance

    Inspections

    Delays

    Terminations

    Subontracts

    Peformance bonds

    Fees and retainage

    27

    Conduct Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    28/41

    Contract document (III):

    Penalties

    Incentives Support

    Acceptance criteria

    Subcontractor approvals

    Disputes resolution

    28

    Conduct Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    29/41

    Purchasing Management

    Plan Procurements

    Conduct Procurements

    Administer Procurements Close Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    30/41

    Purpose

    Manage the contract and the relationship with the seller.

    Ensuring that the sellers performance meets contractualrequirements

    30

    Administer Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    31/41

    Some tools (I):

    Changes and change control. All contracts should define theprocess by which any changes to the contract (project) can beaccommodated and should include the paperwork, trackingsystmes and approvals necessary for authorizing changes.

    Reviews, audits, inspections, and reporting. Processes

    designed to assess progress in terms of both process anddeliverables.

    Claims administration. It deals with those changes wheredisagreements exist and there is a lack of resolution. Claims

    can be generated when cost of a change, existence of achange, or the nature of the change is at issue. They should bedetailed in a disputes clause within the contract.

    31

    Administer Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    32/41

    Some tools (II):

    Records management system. It refers to the specificprocesses for maintaining contractually requireddocumentation within the project management informationsystem.

    Undefined work. It becomes an issue when time is of the

    essence. The parties would like to proceed with the project,but the price and other important terms and conditions of thecontract have not been specified or agreed to.

    32

    Administer Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    33/41

    Standard Clauses of Contracts (I)

    Changes

    Control who initiates a change request Determine how change is funded

    Identify final approval authority

    Require configuration control

    Warranties Establish a level of quality

    Express warranty: explicitly stated

    Implied warranty: stated as usable

    Doctrine of waiver

    Relinquishing of one partys rights because of a lack of enforcementof those rights

    33

    Administer Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    34/41

    Standard Clauses of Contracts (II)

    Delays

    Identify who caused it and the impact Bonds

    Performance bond

    Payment bond

    Breach Failure to perform a contractua obligation

    Material breach is more serious than a contract breach

    34

    Administer Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    35/41

    Standard Clauses of Contracts (III)

    Damages

    Punitive damage Damages awarded over and above what will compensate for cost

    Activities that punish (or make example) of defendant

    Not normally awarded under contract law

    Compensatory Damages awarded to cover the loss and nothing more

    Force majeure

    The Act of God clause

    35

    Administer Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    36/41

    Elements of a Legally Enforceable Contract

    Agreement must be voluntary

    People who sign must have legal capacity to do so Cause must be sufficient to contract

    Purpose must be legal and must not violate public policy

    36

    Administer Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    37/41

    Purchasing Management

    Plan Procurements

    Conduct Procurements

    Administer Procurements Close Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    38/41

    Purpose

    Complete the contract and all open issues

    Settle the contract

    38

    Close Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    39/41

    Topics

    Organizing for contract management:

    Centralized contracting

    Decentralized contracting

    Privity of contract

    Dealing with foreign currencies and their exchanges

    39

    Close Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    40/41

    Centralized contracting

    A single function within the company is responsible for theentire contracting process for all projects.

    Advantages

    More economical

    Easier to control overall contracting efforts

    Higher degree of contracting specialization Orders can be consolidated across several projects

    Disadvantages:

    The contracting office can become a bottleneck if several projectshave heavy needs at once

    Less attention is given to the especial needs of individual projects

    40

    Close Procurements

  • 7/29/2019 CEESP Project Management. Unit Eight

    41/41

    Decentralized contracting (more used in projectizedorganization)

    Each project manager controls the contracting process for hisor her project.

    Advantages

    Project Manager has more control

    Contracting personnel are more familiar with project needs More flexible and adaptable to project needs

    Disadvantages:

    Duplicationn of contracting efforts across projects Higher costs

    No standard contracting policies

    41

    Close Procurements