Upload
abhishekkumar
View
217
Download
0
Embed Size (px)
Citation preview
7/31/2019 CE-474 EIA(1)
1/104
Dr. Dharmendra
Assistant Professor
Department of Civil Engineering
Office Location: Environmental Laboratory
Civil Department
(Ground Floor)
7/31/2019 CE-474 EIA(1)
2/104
CE-474 (a) ENVIRONMENTAL IMPACT ASSESSMENT
L T P
3 1 0
Environment and its components, Concept of Ecological imbalances, carrying capacity and sustainable
development. Evolution of environmental impact assessment (EIA), Current screening process in India. A
step-by-step procedure for developing EIA. Elements of Environmental Analysis. Public consultation, Post
monitoring, Data collection for Air Quality Impact analysis, Water Quality Impact Analysis and energy
impact analysis. Impact Assessment Methodologies-Matrices, overlays, network analysis. Case studies of
Industrial EIA and Water resources projects. Brief introduction about Environment legislation and
Environmental Audit.
Books:
1. Environmental Impact Assessment for Developing Countries: Asit K. Biswas
2. Environmental Impact Analysis Handbook : G.J. Rau and C.D. Wooten
3. Environmental Impact Assessment by C.W. Canter
4.Environmental Impact Assessment Theory and practice Peter Wathern
7/31/2019 CE-474 EIA(1)
3/104
7/31/2019 CE-474 EIA(1)
4/104
Course Plan
Contd CHAPTER 5
Introduction to data collection.
What data to be collected and its significance such as
Air environment
Water environment
Land environment
Biodiversity
How data should be collected, interpreted and
presented?
CHAPTER 6
Impact assessment
Introduction to Impact analysis.
Criteria for predicting the significance of impacts. Basis thumb rule to evaluate the project feasibility.
Method to assess the impact of a project
on ground and surface water.
Method to assess the project impact on eco-
sensitive areas.
Project feasibility with respect to land use
pattern.
Estimation of assimilative capacity of the
river.
Mass balance and thumb rule to estimate theresource consumption and emission potential
of different industrial sector.
Thumb rule to estimate the pollution potential
based on fuel and raw material analysis.
Thumb rule to estimate the stack height.
Thumb rule to estimate the water demand,
wastewater discharge, load and treatmentprocess efficiency.
Thumb rule to estimate the seismic location.
Estimation of site suitability with respect
meteorological parameter.
Thumb rule to assess social issues
7/31/2019 CE-474 EIA(1)
5/104
Course Plan
Contd CHAPTER 7
Mitigation and Environmental
management plant (EMP)
Introduction to impact mitigation and
impact management.
Identification of state of art technologiesfor resource consumption and pollution
prevention.
Structural and non-structural mitigation
measures in certain industrial projects.
Introduction to Environmental
management plan.
What good EMP should contain.
CHAPTER 8
Public consultation
Introduction to public consultation.
How one should prepare for the
public consultation.
Loopholes of public hearing in India
CHAPTER 9
Post monitoring
Weakness in post monitoring
Structural weakness
Legal weakness
How to strengthen post monitoring
7/31/2019 CE-474 EIA(1)
6/104
Environment
Our natural environment climate, soils, oceans, biological life(plants, animals, bacteria) that can both nurture us and behazards to us.
The built environment that we have created to protect and
house ourselves and to provide a modified infrastructure withinwhich we can prosper
The economic environment that sustains our built environmentand allows the organization of the means of production
The social, cultural and legal environments within which weconduct ourselves and our interactions with others.
These environments are themselves diverse, continuallyevolving and have strong interdependence.
7/31/2019 CE-474 EIA(1)
7/104
Introduction
What is EIA?
What are the core value of EIA?
Evolution and history of EIA
Why is it important?
How can you intervene in the process?
7/31/2019 CE-474 EIA(1)
8/104
Definitions of EIA:
A study of probable changes in various socio-economic andbiophysical characteristics and the environment, which mayresult from a proposed or impending action (Jain, Urban,Stacey, 1977).
An activity that aims at establishing quantitative values forselected parameters, which indicate the quality ofenvironment before, during, and after the proposedactivitiesHeer, Hagerty (1977).
An instrument to identify and assess the potential
environmental impacts of a proposed project, evaluatealternatives, and design appropriate mitigation,management, and monitoring measures (World Bank)
7/31/2019 CE-474 EIA(1)
9/104
Different names for the same report
An EIA report may be known by several other
names such as:
Environmental impact assessment (EIA)
Environment impact statement (EIS)
Environmental statement (ES)
Environmental assessment report (EAR) Environmental effects statement (EES)
7/31/2019 CE-474 EIA(1)
10/104
EIAThree core values
Integrity: The EIA process should be fair,
objective, unbiased and balanced.
Utility: The EIA process should provide
balanced, credible information for decision
making.
Sustainability: The EIA process should result in
environmental safeguards.
7/31/2019 CE-474 EIA(1)
11/104
Evolution and history of EIA
Development of EIA
Pre-1970 Project review based on the technical/engineering andeconomic analysis.
Limited consideration given to environmental consequences.
Early/mid1970s
EIA introduced by NEPA in 1969 in US. Basic principle: Guidelines, procedures including public
participation requirement instituted.
Standard methodologies for impact analysis developed (e.g.
matrix, checklist and network).
Canada, Australia and New Zealand became first countries to
follow NEPA in 1973-1974. Unlike Australia, which legislatedEIA, Canada and New Zealand established administrative
procedures.
Major public inquires help to shape the process development.
7/31/2019 CE-474 EIA(1)
12/104
Evolution and history of EIA
Development of EIA
Late 1970 and
early 1980s More formalized guidance.
Other industrial and developing countries introduced formal EIA
requirements (France, 1976; Philippines, 1977) began to use
the process informally or experimentally ( Netherlands, 1978) oradopted elements, such as impact statements or reports, as
part of development applications for planning permission
(German states [lander], Ireland).
Use of EA by developing countries (Brazil, Philippines, China,
Indonesia)
Strategic Environment Assessment (SEA), risk analysisincluded in EA processes.
Greater emphasis on ecological modeling, prediction and
evaluation methods.
Provision for public involvement.
Coordination of EA with land use planning processes.
7/31/2019 CE-474 EIA(1)
13/104
Evolution and history of EIA
Development of EIAMid 1980s to end
of decade In Europe, EC Directive on EIA establishes basic principle and
procedural requirements for all member states.
Increasing efforts to address cumulative effects.
World Bank and other leading international aid agencies
establish EA requirements. Spread of EIA process in Asia.
1990s Requirement to consider trans-boundary effects under Espoo
convention.
Increase use of GIS and other information technologies.
Sustainability principal and global issues receive increased
attention.
India also adopted the EIA formally.
Formulation of EA legislation by many developing countries.
Rapid growth in EA training.
7/31/2019 CE-474 EIA(1)
14/104
History of EIA in India
In 1984 Gas leak tragedy in Bhopal Indian Govt. formed EPA in 1994 & EIAmandatory for certain projects.
On 27 January
1994
The MoEF, under the EPA 1986,
promulgated the EIA notification makingenvironmental clearance mandatory for
expansion or modernisation of any activity or
for setting up new projects.
The EIA notification has been amended 13
times in the past 12 years. While most of the
amendments diluted the environmental
clearance process, there were some, which
also strengthened it.
7/31/2019 CE-474 EIA(1)
15/104
Why is it important?
To understand the short term and long term impact of project.
To identifies the likely environmental, economical and social
burden of the project for decision makers.
The long-term objective of EIA is to promote sustainable
development by ensuring the balance between environment
and development.
Opportunity to the local people to understand the project so
that they can participate and intervene in project
development.
7/31/2019 CE-474 EIA(1)
16/104
The EIA process1. Screening: First stage of EIA, which determines whether the proposed project,
requires an EIA and if it requires EIA, then the level of assessment required.2. Scoping: This stage identifies the key issues and impact that should be further
investigated. This stage also defines the boundary and time limit of the study.
3. Impact analysis: This stage of EIA identifies and predicts likely environmental and social
impact of the proposed project and evaluates the significance.
4. Mitigation: This step in EIA recommends the actions to reduce and avoid the potentialadverse environmental consequences of development activities.
5. Reporting: This stage presents the result of EIA in a form of a report to the decision-
making body and other interested parties.
6. Review of EIA: It examines the adequacy and effectiveness of the EIA report and
provides information necessary for the decision-making.7. Decision-making: It decides whether the project is rejected, approved or needs further
change.
8. Post monitoring: This stage comes into play once the project is commissioned.
7/31/2019 CE-474 EIA(1)
17/104
Types of EIA
Broadly EIA classified into two types: Rapid EIA
This is carried out for projects that are likely to cause limited adverseimpacts. In rapid EIA, data or information is collected for only one season(other than monsoon). Therefore, the time frame for undertaking rapidEIA is much shorter (3 months).
Comprehensive EIA As the name suggests, this is conducted over a year as it involves
collection of data/information for three seasons (other than monsoons).
It is usually conducted for projects that are likely to cause more or a seriesof adverse impacts.
However, in India, there are no clear guidelines on the type of projects forwhich comprehensive EIA should be conducted. As per the new EIAnotification, the authority in charge of issuing environmental clearances(either the Union ministry for environment and forests (MoEF) or thestate level body) decides whether the project proponent has to conduct arapid or a comprehensive EIA.
7/31/2019 CE-474 EIA(1)
18/104
Public participation in different
countriesEurope The views of NGOs and affected people are considered during
screening, scoping and EIA review.
Japan Provisions of public feedback at screening, scoping and draft
environmental impact statement.
Canada People are consulted during screening, scoping and hearing.Netherlands and
Denmark
Consultation and public participation is a regulatory requirement
US Publish a notice of intent in the Federal register and asks public to
comment.
India Commonly called thePublic
Consultation
legal provision, peopleare consulted at the latter stage of the EIA process once the draft
EIA report has been prepared. There is no public consultation in
the initial phase.
7/31/2019 CE-474 EIA(1)
19/104
How can you intervene in the
process? Local communities can intervene during the public hearing
process.
Relevant issues can be raised.
Loopholes/gaps/inadequacies in the EIA report can be pointed
out.
Legal options can also be exercised.
A properly presented rigorous analysis of the EIA report can
be presented to the court.
A critical analysis of the EIA report can also be sent to the
National Environmental Appellate Authority for a final appeal
in case the project is given a clearance.
7/31/2019 CE-474 EIA(1)
20/104
CHAPTER 2
Environmental clearance process in India
Central level
State level
Function of Central and State Expert Appraisal Committees
The union Ministry of environment and forests brought out the new EIAnotification in 2006.
In the new notification (dated 14th September 2006),the process of
screening and scoping has been made mandatory.
7/31/2019 CE-474 EIA(1)
21/104
EIA at project
Old notification
Six stages:
(1) Project concept
(2) Pre-feasibility(3) Feasibility
(4) Design andengineering
(5) Implementation and(6) Monitoring and
evaluation.
New notification
Four Stage
Stage first - screening (only
for category B projectsand activities),
Stage second - scoping
(applicable for A and B1
type project), Stage third - public
consultation, Stage
fourth project appraisal.
7/31/2019 CE-474 EIA(1)
22/104
Project concept and site selection
Proposal of project
Project A, Get clearance from
MOEFProject B, Get clearance from
state
Submission of Form & relevant information to Expert
Appraisal Committee (Both for project A&B)
Screening(Applicable for B category project
EIA not required
(Called B2 project)
EIA required
(called B1 project)
Scoping
(For both A & B category project)
Impact assessment
Draft EIA followed by public consultation
Submission to appraisal committee and decision
Not approved
Approved
Post monitoring
Fig:EIA processin India
7/31/2019 CE-474 EIA(1)
23/104
Bodies involved in the assessment
process
Environment quality experts: Experts in measurement andmonitoring, as well as analysis and interpretation ofenvironmental parameters
Sectoral experts: Experts in management of processes and
operations in the relevant industrial sectors EIA process experts: Experts in conducting eias and preparing
Environmental Management Tools (emps)
Risk assessment experts
Life science experts in floral and faunal management Forestry and wildlife experts
Environmental economics experts
7/31/2019 CE-474 EIA(1)
24/104
Function of Central and State Expert
Appraisal Committees
The function of the expert appraisal
committee is to evaluate the project feasibility
at the central level for A category project
before granting environmental clearance.
However similar function is rest with state
level SEAC. The function of EAC and SEAC are
given below
7/31/2019 CE-474 EIA(1)
25/104
Function of Central and State EAC
Cont..
The EAC and SEAC expert appraisal committees at the central and state orthe Union territory level are responsible to screen, scope and appraiseprojects or activities
The authorized members of the EAC and SEAC, may inspect any siteconnected with the project or activity in respect of which the priorenvironmental clearance for the purposes of screening or scoping or
appraisal. EAC and SEAC will decide the Terms of Reference (ToR) on the basis of the
information furnished in the prescribed application i.e. form1/form 1Aincluding Terns of Reference proposed by the applicant.
The application for the project may by rejected regulatory authority on therecommendation of the EAC and SEAC at central and state level
respectively. In case of such rejection, the decision together with reasons shall be
communicated to the applicant.
7/31/2019 CE-474 EIA(1)
26/104
Function of Central and State EAC
Cont..
The EAC and SEAC are responsible to scrutiny application and otherdocuments like the final EIA report, outcome of the public consultationsincluding public hearing proceedings, submitted by the applicant to theregulatory authority concerned for the grant of environmental clearance.
The project proponent is also be invited for furnishing necessary clarificationsin person or through an authorized representative.
The regulatory authority shall normally accept the recommendations of thecentral and state level expert appraisal committee concerned.
In cases of disagreement with the recommendations of the EAC and SEAC, theregulatory authority shall request for reconsideration within forty-five days ofthe receipt of the recommendations of the EAC and SEAC.
The decision of the regulatory authority after considering the views of the
central and state level expert appraisal committee concerned shall be finaland conveyed to the applicant.
State Level Environment Impact
7/31/2019 CE-474 EIA(1)
27/104
State Level Environment Impact
Assessment Authority (SEIAA)
Environment Impact Assessment Authority (SEIAA) Its is compose ofthree members which includes member secretary, chairman and onemore person.
Main function of SEIAA is to grant environmental clearance based on therecommendation of SEAC. Decision of the Authority on the basis ofconsensus.
SEIAA is an independent body; members/chairman have fixed term, cannot be removed except for cause
Three (3) member SEIAA to be notified by MOEF after every three years
Chairman and other member shall be experts/professionals fulfilling theeligibility criteria given in Appendix VI.
Chairman shall be an expert in EIA process.
Member Secretary shall be a serving officer of the state governmentfamiliar with environmental laws.
No funding from MoEF
7/31/2019 CE-474 EIA(1)
28/104
Forms of impact assessment
There are various forms of impact assessment such
as health impact assessment (HIA) and social impact
assessment (SIA) that are used to assess the health
and social consequences of development so thatthey are taken into consideration along with the
environmental assessment.
One of the forms of impact assessment is strategic
environment assessment, which is briefly discussedbelow:
7/31/2019 CE-474 EIA(1)
29/104
Strategic EIA
Strategic environment assessment (SEA) refers to
systematic analysis of the environmental effects of:
development policies, plans, programmes and other
proposed strategic actions. This process extends the aims and principles of EIA
upstream in the decision-making process, beyond
the project level , major alternatives are still open.
SEA represents a proactive approach to integrating
environmental considerations into the higher levels
of decision-making.
7/31/2019 CE-474 EIA(1)
30/104
Difference in EIA and SEAEnvironment impact assessment Strategic environment assessment
Takes place at end of decision-making cycle
Reactive approach to development proposal
Identifies specific impacts on the
environmentConsiders limited number of feasible
Alternatives
Limited review of cumulative effects
Emphasis on mitigating and minimizing
impacts
Narrow perspective, high level of detail
Well-defined process, clear beginning and
end
Focuses on standard agenda, treats
symptoms of environmental deterioration
Takes place at earlier stages of decisionmaking cycle
Pro-active approach to developmentproposals
Identifies environmental implications, issues
of sustainable developmentConsiders broad range of potential
alternatives
Early warning of cumulative effects
Emphasis on meeting environmental
objectives, maintaining natural systems
Broad perspective, lower level of detail toprovide a vision and overall framework
Multi-stage process, overlapping components,
policy level is continuing, iterative
Focuses on sustainability agenda, gets at
sources of environmental deterioration
7/31/2019 CE-474 EIA(1)
31/104
Different forms of impact assessment
Macro Impact Assessment
1. Environmental Impact
Assessment
2. Social Impact assessment
3. Technology Impact Assessment
4. Policy Impact Assessment
Micro Impact Assessment
1. Economic and Fiscal Impact
assessment
2. Demographic Impact
assessment
3. Health Impact assessment
4. Ecology Impact assessment
5. Risk Impact assessment
6. Climate Impact assessment
7. Development Impact
assessment
7/31/2019 CE-474 EIA(1)
32/104
Social Impact Assessment
It can be defined as the processes of assessing or eliminating
the social consequences in advance.
The social consequences particularly in the context of
appropriate national, state or provincial environmental policy
legislation.
Social impacts include all social and cultural consequences to
human population of any public and private action.
Cultural impacts involve change to norms, values, and beliefs
of individuals that guide and rationalize their cognition of
themselves and their society.
7/31/2019 CE-474 EIA(1)
33/104
Social Impact Assessment
Cont
The SIA process provides direction in1. Understanding, managing and controlling change.
2. The prediction of likely impacts from change strategies ordevelopment projects that are to be implemented
3. The identification, development and implementation of
mitigation strategies in order to minimise potential impacts.4. The development and implementation of monitoring programs to
identify unanticipated social impacts that may develop as a resultof social change.
5. The development and implementation of mitigation mechanisms
to deal with unexpected impacts as they develop.6. The evaluation of social impacts caused by earlier developmentprojects, technological change, specific technology andgovernment policy.
7/31/2019 CE-474 EIA(1)
34/104
Guidelines & Principles of SIA
1. Public involvement: Develop and implement an effective publicinvolvement plan to involve all potentially affected publics.
2. Identification of alternative: Described the proposed action orpolicy change and reasonable alternatives.
3. Profile baseline conditions: This will include developing andunderstanding of the relationship between the social andbiophysical environment; historical background of the area;contemporary issues; political and social structures; culture;attitudes and social-psychological condition; as well as basicpopulation characteristics.
4. Scoping: identify the full range of possible social impactsthrough a variety of means including discussion or interviewswith numbers of all potentially affected.
5. Projection of estimated effects: Evaluate all possible impacts todetermine the probable impacts.
7/31/2019 CE-474 EIA(1)
35/104
CHAPTER 3
Screening
Role of screening
Current screening process in India
What information is missing in screening forms?
Case studies
7/31/2019 CE-474 EIA(1)
36/104
Screening
It is the first step of the environmental impact
assessment, which helps to assess the
environmental impacts of an industrial, or
development project and decides whether anenvironmental impact assessment is required
for the project or not.
7/31/2019 CE-474 EIA(1)
37/104
Project concept and site selection
Proposal of project
Project A, Get clearance from
MOEFProject B, Get clearance from
state
Submission of Form & relevant information to Expert
Appraisal Committee (Both for project A&B)
Screening
(Applicable for B category project
EIA not required
(Called B2 project)
EIA required
(called B1 project)
Scoping
(For both A & B category project)
Impact assessment
Draft EIA followed by public consultation
Submission to appraisal committee and decision
Not approved
Approved
Post monitoring
Fig:EIA processin India
7/31/2019 CE-474 EIA(1)
38/104
What information is missing in screening
forms?
7/31/2019 CE-474 EIA(1)
39/104
CHAPTER 4
Why scoping is important
Role of scoping
Regulatory provision for scoping in India Decision criteria to undertake rapid or
comprehensive EIA
Scoping guidelines for defining the Term ofreference for projects (TOR).
7/31/2019 CE-474 EIA(1)
40/104
Why scoping is important?
The scoping phase is the backbone of theenvironmental impact assessment process
It involves trying to find answers to questions like
1-what are the issues to be addressed,
2- how to proceed,
3- what extent of analysis is needed,
4- what infrastructure is needed5- and what kind of people should be involved in the
assessment.
7/31/2019 CE-474 EIA(1)
41/104
Role of scoping
Ideally, the role of scoping is to determine three key issues,
namely,
Justification of the project (both scenarios with and
without the project, extent of benefit to the local
communities due to the project)
Site alternatives (assessment of different sites with
respect to stress on biophysical environment and its
cumulative effects)
Design alternatives (type of technology, structural andnon-structural mitigation measures to reduce significant
impacts).
l i i f i
7/31/2019 CE-474 EIA(1)
42/104
Regulatory provisions for scoping
in India As per the new notification, the ToR for scoping would be
decided by the expert appraisal committee at the central-level
or the state-level expert appraisal committee based on
information furnished in the application Form1/Form 1A,
ToR prepared by the project proponent and a report of the sitevisit(if the appraisal committee deems a requirement of a site
visit to the area).
The expert committee has to convey the ToR for the EIA study
to the project proponent within 60 days of the receipt of Form1. Otherwise, the ToR suggested by the applicant shall be
deemed as the final ToR approved for the EIA studies.
7/31/2019 CE-474 EIA(1)
43/104
Scoping guidelines for defining the Term of
reference for projects (TOR).
Issues to beconsidered
Description Extent of investigation/best practice in scoping
Site alternative The provision of site
alternatives is never considered
in the EIA process because site
selection is driven by
availability of raw materials andother economic factors. There
are hardly any considerations of
environmental and social
impacts while locating a project.
In order to locate a project, the
siting guideline should be
properly followed (see annexure
1.2 for siting guidelines).
Final decision on the site should be made
based on the detailed investigation of
environmental, social and economic issues
related with each sites.
Environmental issues: Type of landuse pattern, water potential and
competitive users, pollution potential
with respect to assimilation capacity of
the area/medium, and proximity to
sensitive areas.
Social issues: Population density,
impact on local resources, impact on
public amenities and infrastructure,
scenario with and without the project,
proximity of human habitation.
Cont
7/31/2019 CE-474 EIA(1)
44/104
Annexure 1.2: Siting Guidelines
The following guidelines should be taken into account while identifying a suitable
site for setting up an industry.
No forest land shall be converted for non forest activity for the siting of an
industry [Ref: Forest(Conservation)Act, 1980]:
No prime agricultural land shall be converted into an industrial site
Within the acquired site the industry unit must be located at the lowestelevation to remain hidden from general vision:
Land acquired shall be sufficiently large to provide space for appropriate
treatment of waste water after maximizing possible reuse and recycling
reclaimed (treated) wastewater shall be used to raise a green belt and to
create a water body aesthetics recreation and if possible for aquaculture. The
green belt shall be 1/2 km wide around the boundary limits of the industry.
For an industry having an odour problem it shall be a kilometer wide:
The green belt between two adjoining large scale industries shall be one
kilometer.
Si i G id li
7/31/2019 CE-474 EIA(1)
45/104
Siting Guidelines
Contd.. Enough space should be provided for storage of solid wastes,
so that these would be available for possible reuse:
Lay out and the from of the industry coming up in an area
must conform to the landscape of the area without affecting
the scenic features of that place:
The associated township of the industry must be created at a
place having physiographic barriers between the industry and
the township:
Each industry is required to maintain three ambient air qualitymeasuring stations within 120 degree angle between the
stations:
7/31/2019 CE-474 EIA(1)
46/104
Areas to be avoided
Ministry of environment and forests, government of india has
notified the following areas for prohibiting and restricting
specified industrial activites in the country:
Murud Jangira Disst. Maharashtra , (Notification,189)
Doon Valley in uttar Pradesh. (Notification, 1989) Antop Hill in Bombay (Notification, 1980)
Dahanu Taluka in Maharashtra (Notification, 1996)
Namaligarh East of Kaziranga (Notification, 1996)
Specified Areas of Aravali Range. (Notification, 1992)
Matheran and surrounding region in the state of Maharashtra declared as theMatheran Eco-sensitive Zone (Notification Dt. 4th Feb 03)
Coastal Regulation Zone (CRZ)-500 meters from the high tide line (HTL)
towards the landward side. (Section 9 for details on CRZ Rules, 1991 &
Amendments).
7/31/2019 CE-474 EIA(1)
47/104
Guidelines for defining the Term of
reference for projects (TOR). Contd..
Issues to be
considered
Description Extent of investigation/best practice
in scoping
Technology The technology used for manufacturing has a huge impact
on the environment.
Therefore it should be selected after considering all
possible alternatives.
For instance in , most of the industries still use outdatedtechnologies when compared to global trends.
In a country like India, where regulatory
mechanism for industrial pollution is weak,
the best way to reduce the industrial pollution
is by allowing only state of art technology for
instance in Chlor-alkali sector, the state of art
technology is membrane cell technology andfor aluminium smelter state of art is pre-
baked technologyImpact on sensitive
locations (forests,
wildlife sanctuaries,
national parks,
archaeological sites etc.)
This impact is very high in case the project is located close to a sensitive area.
In case of industrial, irrigation and mining projects, there are several examples of
how the impacts on biodiversity were ignored for setting up a project. An excellent
example is of the Himachal-based cement plant of Gujarat Ambuja Cements
Limited (GACL). The production unit and the mines are located in extremely eco-
sensitive areas there are 19 protected forest blocks in the region. The production
unit is close to the Darlaghat Wildlife Sanctuary, the mines are close to the
Majathal Sanctuary. However, for setting this plant, the Darlaghat sanctuary was
denotified by the government.
Similarly, the construction work of Durgawati water resource project continues on
the forestland. Expert committee in their report mentioned that the state
government had denotified 160 acres of forestland including 5.44 acres in the
Kaimur Wildlife Sanctuary through a notification on November 5, 2004 for setting
up this project.
Preventive approach - Not to locate projects close to
sensitive areas such as national park, wildlife and
protected area buffer zones (Part of National Park and
Wild Life habitats)In case of hydropower projects, Small hydropower
project is one alternative solution to reduce magnitude
of impact. In case of hydropower project EIA shouldfocus more to identify the impact on biodiversity,
submergence, siltation, downstream ecology, social
impacts and disaster management.
7/31/2019 CE-474 EIA(1)
48/104
Issues to be considered
Impact of change in land
use patterns
Cumulative load
Impact on water resources
Impact during pre-
construction stage.
Impact on biodiversity
Impact on air by pointsource emissions
Toxic emissions
Impact of water pollution
Sediment impact
Impact of solid/hazardous
wastes generation and
handling
Impact of noise
Blasting
Transportation issues
Risk Assessment team and
monitoring infrastructure
7/31/2019 CE-474 EIA(1)
49/104
CHAPTER 5
Introduction to data collection.
What data to be collected and its significance such as
Air environment
Water environment
Land environment
Biodiversity
How data should be collected, interpreted andpresented?
7/31/2019 CE-474 EIA(1)
50/104
Data collection
Data collection is done basically with two
intentions:
To get an idea of the existing social, environmental
and economic scenario in and around theproposed plants location,
To get an idea of possible implications of settingup the plant in the region
7/31/2019 CE-474 EIA(1)
51/104
What data is needed?
While data is required for all projects:
Different projects require different kinds of data
for an effective environmental assessment
depending on their location and the nature of theiroperations.
Industrial projects (manufacturing industries),
mining projects,
infrastructure projects,
hydroelectric and irrigation projects
thermal power plants
7/31/2019 CE-474 EIA(1)
52/104
Infrastructure projects
This includes highways/ airports/ bridges/
pipelines/ ports/ railway networks
In the case of pipelines, railway networks, roads and
highways, the study area is usually taken as a 2 kmcorridor (1 km on each side) along the entire length of the
project.
In addition, the study area includes a 5-km radius area
surrounding key areas in the network like large towns,cities etc.
In the case of airports/ports, the study area is a 10-km
radius
7/31/2019 CE-474 EIA(1)
53/104
Location
Topography (flat/hilly)
Existence of other industries/development projects
within the study area (Number of projects/distance of
these projects from the proposed project)
Details of population in the area distance of the
nearest human habitation, villages in the study area
and their population.
In the case of selected key areas, data correspondingto a 1-km radius, 2-km radius and a 5-km radius
should be collected
Location
7/31/2019 CE-474 EIA(1)
54/104
Location
Contd... Existence of eco-sensitive areas in the study area and
their distance from the proposed project
wildlife sanctuaries
national parks forests/wetlands and mangroves
archaeological sites/sites of historical importance
habitats for migratory birds
estuary or sea lakes and reservoirs or dams)
7/31/2019 CE-474 EIA(1)
55/104
Land use studies
Existing land use patterns in the study area.
Data from different sources such as from census
records, local land records, agricultural census as well
as Indian Remote Sensing satellite imagery should be
collected and analysed.
Existing land use patterns in the land for which
Right of Use/ownership has to be acquired forsetting up the project
Land use studies
7/31/2019 CE-474 EIA(1)
56/104
Land use studies
Contd... Data on land use should be collected under the
following categories: Urban (this can be built-up land, notified industrial area or mixed
land use)
Forestland
Agricultural land(with some indication of productivity
information on whether single-cropped land/double-cropped
land/triple cropped land should be collected)
Fallow land
Scrubs/grazing land
Water bodies
Wetlands (mangroves/salt plans/mudflats)
Wasteland (this refers to rocky/marshy/salt affected/water
logged/gullied land)
7/31/2019 CE-474 EIA(1)
57/104
Soil
Type of soil within the study area (composition/
characteristics).
Characteristics such as pH, nitrogen/ phosphorous/
potassium/ calcium/ magnesium/ sodium, sodiumabsorption ratio (SAR), electrical conductivity,
available water storage capacity, infiltration rate,
porosity, texture, permeability, percentage of sand,
silt and clay in the soil etc. should be collected Availability and characteristics of topsoil in the
study area (depth of topsoil, composition)
Soil
7/31/2019 CE-474 EIA(1)
58/104
Soil
Contd...
Soil and slope stability reports on studies
done in the area.
This is particularly important in case of
projects located in hilly and mountainous
terrains, where risks of landslides can be high.
It is also important in case of large-scale
projects located in seismically active zones
7/31/2019 CE-474 EIA(1)
59/104
Geology & Climate
Geology Data on the seismic zone in which the project location
falls and the maximum observed seismic intensity in
the region
Physiography and general geology of the area
Climatology and meteorology Month-wise data on atmospheric pressure, temperature
and relative humidity. Wind speed and wind direction dataat the project site. A wind rose diagram (providing month-
wise or at least annual data) has to be constructed
Hydrogeology and local water
7/31/2019 CE-474 EIA(1)
60/104
Hydrogeology and local water
regime Drainage patterns in the area details of
rivers/tributaries/streams/aquifers draining the
region in the study area
Details of canal and river crossings Water consumption by the project
Detailed water quality study in surface water
bodies in the study area
Detailed groundwater quality study
7/31/2019 CE-474 EIA(1)
61/104
Quarrying and landfilling
Data on the approximate quantity of material
excavated during construction, for instance during
dredging (along with information on the type of
material that is excavated)
(Note: This might be substantial for instance in
the case of construction of tunnels etc.)
Data on the approximate quantity of the material
that might be used for landfilling (for instance silt
from nearby areas) low-lying areas
7/31/2019 CE-474 EIA(1)
62/104
Air
Ambient air quality data on suspended
particulate matter (SPM), respirable suspended
particulate matter (RSPM), sulphur dioxide (SO2),
and different oxides of nitrogen (NOX), dust fall,
carbon monoxide and hydrocarbons
Data should be calculated on a 24-hour basis
number of vehicles passing/hour should be noted,
along with information on the type of vehicle(heavy motor vehicles/light motor vehicles/two-
three wheelers)
Noise
7/31/2019 CE-474 EIA(1)
63/104
Noise
Information on the possible sources of
noise from the proposed project noise
levels, duration of noise
Data on the ambient noise levels
collected near residential areas,
commercial areas and silent zones. 24-hour data is to be collected
7/31/2019 CE-474 EIA(1)
64/104
Biodiversity
Vegetation If there are forests in the study area, a detailed study of what
kinds of forests exist (teak/sal/mixed etc.) has to be done.
Usually, this data is available with the Forest Department.
The following data is collected for each type of
forest:
Location/topography where the forests are located
Percentage area of the total study area occupied by each
forest type
Type of soil
Crown density of the forests
7/31/2019 CE-474 EIA(1)
65/104
Fauna
Detailed inventorisation of fauna found in the study area
data on wildlife/ butterflies/ mammals/ birds/ reptiles/
amphibians/ migratory birds and animals/ phytoplankton/
zooplankton should be collected
Presence of nesting/breeding grounds/ watering holes
Classification of animals under various schedules of the
Wildlife Act (1972)
Physiochemical characteristics of all the local water bodies -
temperature, light penetration, turbidity, pH, dissolved
oxygen, phosphates, nitrates and sulphates
Demography and socio-economic
7/31/2019 CE-474 EIA(1)
66/104
Demography and socio-economic
data Population
Population density
Number of villages, distance and direction from the
proposed project Number of households
Male/female population
Ethnic profile: percentage of people belonging toscheduled castes, scheduled tribes and other
vulnerable communities out of the total population
Demography and socio-economic
7/31/2019 CE-474 EIA(1)
67/104
Demography and socio-economic
data Contd... Demographic profile of the people being displaced:
percentage of displaced people belonging to
scheduled castes, scheduled tribes and other
vulnerable communities.
Literacy rates, educational status, and educational
infrastructure
Data on employment: How many to be employed,
what percentage from local communities, what kindof employment (daily wage/contract/permanent,
proportion of workers/middle management/upper
management)
Demography and socio-economic
7/31/2019 CE-474 EIA(1)
68/104
Demography and socio-economic
data Contd... Occupation: Occupation should be collected on
various categories like agricultural workers (agrarian
labourers), cultivators, occupied in fisheries/
livestock/ fishing and allied activities, mining and
quarrying workers, manufacturing and processing in
household industry, construction workers,
manufacturing and processing in industry (other than
household industry), trade and commerce workers,transport, storage communication workers, marginal
labour, other service workers and non-workers. Also
data on child employment.
Demography and socio-economic
7/31/2019 CE-474 EIA(1)
69/104
Demography and socio-economic
data Contd... Infrastructure facilities: Details of schools, colleges,
hospitals, private doctors, veterinary hospitals, roads,
aanganwadis, electrification, source of drinking
water, source of irrigation water, and sewage
management in the region.
Also, data on whether the project plans to improve
these facilities. If so, how.
Details of influx into the study area due to theproject: No of people entering, time period of influx
(temporary/permanent), facilities available to deal
with the influx
Demography and socio-economic
7/31/2019 CE-474 EIA(1)
70/104
Demography and socio-economic
data Contd...
Land holdings: Details of average size of land
holdings, number of families owning land (if at
all) within a particular bracket (landless, land
less than 0.5 acres, between 0.5-1 acres,between 1-2 acres etc.)
Income levels: Classification required (less
than Rs 3,600/month per household, betweenRs 3,601-6,400 per household etc.)
Demography and socio-economic
7/31/2019 CE-474 EIA(1)
71/104
Demography and socio economic
data Contd...
Fuel requirement
Health status: Details of common ailments in
the local community and their month-wise
frequency
Details of the compensation/rehabilitation
package being offered
7/31/2019 CE-474 EIA(1)
72/104
How should data be collected?
1. Method followed for data collection:
I. There are well-established rules for collecting
different kinds of data, and these rules should be
followed in order to ensure reliability of thedata.
II. For instance, in order to collect accurate data on
water flow, measurements have to be taken at
various points in the river.
Data collection
7/31/2019 CE-474 EIA(1)
73/104
Data collection
Cont
2. Time of data collection:I. The time period over which data collection takes place is
very important, and often crucial in making decisions on
possible environmental impact.
II. For instance, unless water flow data is collected during
the lean period, typically peak summer, the data loses
relevance since it will not be able to give an accurate
picture of water stress.
III. To give another example, data on wind speeds should be
collected throughout the day to get a good picture of the
wind profile of the area.
Data collection
7/31/2019 CE-474 EIA(1)
74/104
Data collection
Cont
3. Place of data collection:I. The point where data is collected is important in many cases.
II. For instance, in the case of industries which discharge vast
quantities of wastewater in local water bodies, data on water
flow and water quality has to be collected downstream of the
proposed point of discharge if any decision on whether the
existing assimilative capacity of the river is capable of
handling the effluents has to be made.
III. Similarly, stations for monitoring air should be located
downwind with respect to the most prevalent wind direction
to get a good picture of air quality.
7/31/2019 CE-474 EIA(1)
75/104
Data related to air
The important parameters of air quality are:
suspended particulate matter (SPM)
respirable suspended particulate matter (RSPM)
sulphur dioxide (SO2)
different oxides of nitrogen (NOX).
Apart from these, some other parameters (like
hydrocarbons, chlorine) might have to bemonitored, depending on the nature of the
project.
What are the common air
7/31/2019 CE-474 EIA(1)
76/104
What are the common air
pollutants that are measured?
1. SPM:I. This refers to solid and liquid particles suspended in the
air.
II. The size of these particles can hugely vary from 200
micron to as low as 0.01 micron.
III. SPM can accumulate in the lungs and bronchi and cause
breathing problems to those affected.
IV. Particles suspended in the air scatter and absorb
sunlight.
V. They can produce a haze, reduce visibility and can also
reduce the amount of solar energy reaching the earth.
Common air pollutants.....measur..
7/31/2019 CE-474 EIA(1)
77/104
Common air pollutants.....measur..
Contd...2. RSPM:
I. This refers to particulate matter less than 10 micrometers in size.
II. These are more harmful than SPM emissions, since they can penetrate the
lungs.
3. SO2:I. This is a heavy, pungent and colourless gas.
II. Industrial sources include burning of coal (particularly imported coal), pet coke and oil as
well as other industrial processes like smelting and petroleum refining.
III. These emissions can cause pulmonary damage.
IV. They can injure the bronchial tubes leading to the lungs, as well as the delicate tissue of the
lungs themselves.
V. They can cause irritation to the eyes, nose and throat.
VI. They can also damage leaves and stems of plants. SO2 emissions can also affect the pH
balance of water.
VII. These emissions form sulphuric acid with water. This acid attacks metal, concrete, granite
and other structural materials.
Common air pollutants.....measur..
7/31/2019 CE-474 EIA(1)
78/104
Common air pollutants.....measur..
Contd...
4. NOX:I. These arereddish brown gases with a characteristic odour.
II. Industrial sources of nitrogen oxides are generally combustion of fuels.
III. Other sources are internal combustion engines as well as natural
processes.IV. The various oxides of nitrogen can have an adverse impact on air quality
as well as on human health.
V. Nitrous oxide reduces the oxygen carrying capacity of blood, and can be
fatal in high concentration.
VI. Emissions of nitrogen oxides cause increased respiratory infections inchildren (mainly bronchitis).
VII. Nitrogen dioxide and water combine to form nitric acid. In addition, the
oxides of nitrogen combine with water on mucous membranes to form
mild acid solutions.
How is data on concentration of
7/31/2019 CE-474 EIA(1)
79/104
How is data on concentration of
air pollutants collected? Air pollutants are expressed in parts per million (ppm) or micrograms per
cubic meter (g/m3).
In order to convert concentration of air pollutants from ppm to g/m3, the
following formula is used:
1 ppm = 44.64 x M x 273 / (273 + T) x (P2 / P1), where
M = Molecular weight of the pollutant
T = Temperature of the gas in C
P2 = Pressure of the gas
P1 =Pressure of the gas at standard temperature (0C) and pressure (1 bar
or 100 kilo Pascal) Molecular weight is calculated based on the atomic weights of the
constituent gases. For example, molecular weight of CO2 is 44 (12 x 1 + 16
x 2)
Inversions, mixing heights and
7/31/2019 CE-474 EIA(1)
80/104
Inversions, mixing heights and
stable layers Understanding the concept of inversion, mixing heights and stability layers
is very important in predicting the impact of air pollutants released by the
project on ambient air quality.
They play a key role in determining how dispersion of the pollutants will
take place.
This data also helps in deciding the optimum height of stacks such thatdispersion takes place effectively and without polluting regions near
human habitation.
In the atmosphere, temperature normally changes with height as
expressed by the formula:
dT/dZ = -(n-1)/nR,
Where : T = Temperature
Z = Height
n = 1 for isothermal conditions, 1.4 for adiabatic conditions
When n is greater than 1.4 (super
7/31/2019 CE-474 EIA(1)
81/104
adiabatic condition),
When n lies between 1 and 1.4 (sub
adiabatic condition) it leads to
instability.
When n is lesser than 1, the
atmospheric conditions are highly
stable.
In all such cases, the rate at which
temperature changes with height is
referred to as Environmental LapseRate (ELR)
When the rate of change of
temperature with height is positive
(n
7/31/2019 CE-474 EIA(1)
82/104
Radiation inversion Subsidence inversion Double inversion
Mi i d h
7/31/2019 CE-474 EIA(1)
83/104
Mixing depths
The vertical extent to which the mixingtakes place varies diurnally, from season
to season, and is also affected by
topographical features.
The greater the vertical extent, the larger
the volume of atmosphere available for
dispersion of the pollutants. The depth of the mixing layer is known as
the Mean Mixing Depth. Atmospheric
conditions influence the way thermal
plumes behave.
Behaviour of plumes under different
conditions
Case 1- Looping: This occurs when n > 1.4
and atmospheric conditions are unstable
Case 2Coning: This occurs when n isbetween 1 and 1.4 and atmospheric
conditions are unstable
Case 3Fanning: This occurs when n < 1,
and inversion takes place
Case 4Lofting: This occurs when the
inversion layer lies below the stack height Case 5Fumigation: This occurs when
the inversion layer lies above the stack
height
Case 6Trapping: This occurs when
double inversion layers occur
Case 7: Neutral: This occurs when n = 1,and atmospheric conditions are stable
7/31/2019 CE-474 EIA(1)
84/104
Figure : Behaviour of plumes under different conditions
M it i f t k i i
7/31/2019 CE-474 EIA(1)
85/104
Monitoring of stack emissions
The determination of concentration of various pollutants present inemissions from a stack consists essentially of sampling iso-kinetically.
Iso-kinetic sampling means that the kinetic energy of the gas stream in the
stack should be equal to the kinetic energy of the gas stream flowing
through the sampler .
NOTE:
Samples must be collected without physical or chemical alteration and
without altering the flow pattern or concentration of the pollutant.
Samples must be obtained at a point of average gas density and average
pollutant concentration. Therefore, selection of suitable locations for
sampling is very important.
St k M it i P d
7/31/2019 CE-474 EIA(1)
86/104
Stack Monitoring Procedure
The sampling port is to be located at 8 diameters from the inlet of the stack(or from any bends, expansions or flow disturbances) and 2 diameters from
the exit of the stack.
It should be of 7-10 cm in size and a strong platform should be constructed
about 1 m below the sampling ports.
The stack monitoring equipment (thermocouple for measuringtemperature, pitot tube for measuring pressure, dry gas meter for
measuring the total gas flow, collection filter for filtering the gases, vacuum
pump for drawing gas etc.) will be shifted to the platform.
Insert the thermocouple into the stack and record the temperature of the
gas.
Insert the pitot tube upside down and record the static pressure of the gas
(PU = BA + PS, where PU is the absolute stack pressure in mm Hg, BA is the
barometric pressure in mm Hg and PS is the static pressure in the stack in
mm Hg)
Stack Monitoring Procedure
7/31/2019 CE-474 EIA(1)
87/104
g
Cont...
The inner diameter of the stack is recorded and points are marked (seeannexure: Guidelines for locating sampling points).
The velocity at each of these points is calculated using the formula given
below, and then the average velocity is calculated.
VS = 33.5 x 0.96 x [(TS x H) / (M x PU)]0.5,
where TS = Stack gas temperature inC,
H is the pressure difference measured with the pitot tube in mm of water,
M is the molecular weight of the stack gas measured with the help of Orsat
apparatus, and
PU is the absolute stack pressure
7/31/2019 CE-474 EIA(1)
88/104
Guidelines for ambient air quality
7/31/2019 CE-474 EIA(1)
89/104
q y
monitoring Air pollution should be monitored during the winter months.
The minimum number of sampling stations should be six.
While selecting stations, various factors like population
density, concentration of industries, and intensity of traffic
should be taken into account.
Monitoring stations should be located downwind of the most
prevalent wind direction
The stations should not be located near buildings
Samples are generally taken for a period of 24-hours
R t ti f d t
7/31/2019 CE-474 EIA(1)
90/104
Representation of data
When many samples are taken (say over a period ofa month), ambient air quality is typically represented
by the following figures:
Maximum value: This is the maximum emission value
recorded
Minimum value: This is the minimum emission value
recorded
Average value: This is the average emission value recorded
98 percentile: This is a value such that at most 2 per cent of
the observations are higher than this value.
M t l i l D t
7/31/2019 CE-474 EIA(1)
91/104
Meteorological Data
Climatology Data Indian Bureau of Mines (IBM) and the Indian Meteorological Department (IMD)
Rainfall:
Rainfall (in mm) = Volume of rainfall collected (in mm3) / (Area of the aperture
of the gauge in mm2)
Index of wetness = Actual rainfall in a given year at a given place / Normalannual rainfall of that place
Arithmetical mean method: P = (P1 + P2 + P3+ . Pn)/ n
Thiessens mean method: P = (A1P1 + A2P2 + A3P3+ . An Pn)/ A
Isohyetal method: P = (A1P1 + A2P2 + A3P3+ . An Pn)/ (A1 + A2 + A3+ .An)
Data related to noise
7/31/2019 CE-474 EIA(1)
92/104
Data related to noise
Noise survey should be done in the study areacovering the following three zones, and data
should be collected for 24 hours at each
location: Residential zones
Commercial zones
Silent zones
Noise pollution parameters
7/31/2019 CE-474 EIA(1)
93/104
Noise pollution parameters
L10 = Noise level exceeded 10 per cent of the time
L50 = Noise level exceeded 50 per cent of the time
L90 = Noise level exceeded 90 per cent of the time
Leq (Lequivalent) = This is the equivalent continuous sound level
during the period of measurement. It is calculated as follows:
Leq = L50 + [(L10 L90)2/60)]
Lday = Leq measured over a period of time during 6 am to 9 pm
Lnight
= Leq
measured over a period of time during 9 pm to 6
am
Day-Night Sound Level (Ldn) = 10 log {1/24 [15 (10Lday/10) + 9
(10(Lnight + 10)/10)]}
Data related to water
7/31/2019 CE-474 EIA(1)
94/104
Data related to water
Surface water (rivers, lakes, streams and ponds) Eg. river, first the width of the river is measured.
This width is divided into convenient equal portions (thus
dividing the river into various channels), say divisions of 10 m
width each (with the width of the last channel depending on
the width of the river).
Flow is calculated at each of these channels
The velocity of the water at each channel is also measured with
the help of a rotometer.
The formula for calculating flow is as follows:
Q (in m3/sec) = Depth of the channel (in m) x Width of the channel
(in m) x Velocity of the channel (m/sec)
Groundwater
7/31/2019 CE-474 EIA(1)
95/104
Groundwater
Porosity = Total volume of voids in the aggregate(Vs)/Total volume of the aggregate (V) x 100
Type of rock formation Porosity
Granite, Quartzite 1.5%
Slate, Shale 4%
Limestone 5-10%
Sandstone 10-15%
Sand and Gravel 20-30%
Only Gravel 25%
Only Sand 35%
Clay and Soil 45%
Permeability: This is defined as the ability of a rock to
l h h i i d i f
7/31/2019 CE-474 EIA(1)
96/104
let water pass though it. It is measured in terms of
coefficient of permeability.
Type of rock formation Average value of
permeability coefficient in
cm/sec
Granite, Quartzite 0.6 x 10 -5
Slate, Shale 4 x 10 -5
Limestone 4 x 10 -5
Sandstone 0.004
Sand and Gravel 0.4
Only Gravel 4.0Only Sand 0.04
Clay and Soil 0.04 x 10 -5
Velocity of groundwater
7/31/2019 CE-474 EIA(1)
97/104
Velocity of groundwater
Slichters formula: Groundwater velocity va (inm/day) is given by:
va= KID102/
where K is a constant (approximately 400)
I is the slope of the hydraulic gradient line
D10 is the effective size of the particles in the
aquifer in mm and is the viscosity of water depending on the
temperature
Velocity of groundwater
7/31/2019 CE-474 EIA(1)
98/104
Velocity of groundwater
Hazens formula: Groundwater velocity va (in m/day)is given by:
va= KID102/60 x (1.8T + 42)
where K (approximately 1,000) is a constant I andD10 is same as and
T is the temperature of water in degrees celsius
Measuring of groundwater yields (Q in m3/sec):
Q = x va x Area of the aquifer in m2
where is the porosity of the soil medium
Data related to Biodiversity
7/31/2019 CE-474 EIA(1)
99/104
Data related to Biodiversity
The main purpose of ecological studies is thefollowing:
To assess the nature and distribution of vegetation
in and around the project site To assess the distribution of animal life spectra
To understand the productivity of water bodies
To assess the biodiversity and to understand theresource potential of the region
To ascertain migratory routes of flora and fauna
and possibility of breeding grounds
Raunkiaers classification of the
7/31/2019 CE-474 EIA(1)
100/104
life form spectrum
Data collected on flora should be categorisedinto the following groups
Phanerophytes: Shrubs and trees
Therophytes:Annuals including ferns Hydrophytes: Water plants except phytoplankton
Hemicryptophytes: Plants with perennial shoots
and buds close to the surface Geophytes: Plants, with penetrating parts buried
deep in the substratum
To assess biodiversity in flora, the following data
7/31/2019 CE-474 EIA(1)
101/104
collection methods can be used:
Belt transect studies: This is done to determine thedistribution pattern of the dominant species in the region.
Girth, height and canopy of the dominant species with 25
m on each side of every nodal point are measured and
tabulated. Plot quadrate method: This technique is used only when a
part of a large area is sampled.
Relative Basal Area: Basal area is a term commonly used for
woody trees it refers to the cross-sectional area of all treesof a certain species.
Bt = (D12
+ D22 + D3
2+ .. Dn2
)/4/10 cm2/hectare
To assess biodiversity in flora
7/31/2019 CE-474 EIA(1)
102/104
To assess biodiversity in flora
Relative Density: Density is the number ofspecies in a specified area.
Suppose there are n teak trees in a 10-hectare
quadrant, the density for teak trees (Dt) would be n/10.
Suppose there are N tree species in the quadrant,
with densities of D2, D3..DN respectively, the
relative density of teak trees (Drt) would be:
Drt = Dt/(Dt + D2 + D3+ .DN) x 100
Data related to Biodiversity
7/31/2019 CE-474 EIA(1)
103/104
Data related to Biodiversity
Apart from classifying the species under theabove-mentioned categories, for each listed
species, information on its economic importance
should be collected. For instance, classification under categories like
fruit, fruit vegetables, leafy vegetables, cereals,
millets, pulses, timber, fodder and forage, fuel,
medicinal plants, ethnobiological use, flowers,poisonous plants, sacred plants, oil seeds, aquatic
weed, terrestrial weed, silk, fibre, tanning etc. can
be done.
Fauna
7/31/2019 CE-474 EIA(1)
104/104
Fauna