21
RWE Power 31.01.2013 PAGE 1 Dr. Karl Josef Wolf RWE Power AG CCS at RWE: Struggling for solutions, acknowledging the obstacles

CCS at RWE: Struggling for solutions, acknowledging the obstacles

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

RWE Power 31.01.2013 PAGE 1

Dr. Karl Josef Wolf RWE Power AG

CCS at RWE: Struggling for solutions, acknowledging the obstacles

PAGE 2 RWE Power 31.01.2013

Content

1. Lessons learned from the Hürth IGCC Project

2. RWE´s current CCS activities

3. CO2 Utilization: a way out ?

4. CO2 Storage in Germany: a far way to go

5. Summary

PAGE 3 RWE Power 31.01.2013

Key data of RWE´s Hürth IGCC CCS plant

Basic technology: IGCC (Integrated Gasification Combined Cycle) Capacity: 513 MWgross, 306 MWnet

CO2 capture rate: > 90% of produced CO2

CO2 storage: ~ 2.6 m t/a in deep saline formations of Northern Germany equal to approx. 100 Mt in 40 years of operation

Main objective: Demonstrate the full CCS chain Project timeframe: 2006-2010 Status: Project put on hold after up-front pre-engineering

PAGE 4 RWE Power 31.01.2013

No public acceptance in planned storage regions

PAGE 5 RWE Power 31.01.2013

Lessons Learned from the Hürth project

Total project costs far higher then expected (>> 2 bil. €). IGCC is probably not the cheapest CCS option for lignite power plants

Deploying CCS without being able to rely on a European wide pipeline infrastructure is economically not feasible

The problem of public acceptance is difficult to resolve. Conventional power plants even with CCS are in a different ballpark then Renewables

Demoprojects demonstrating the full CCS chain have to be brought into run. The basic challenges revealed by the RWE IGGC project still remain

CCS will not be an option, as long as there is no supporting and CCS friendly legal framework existing

PAGE 6 RWE Power 31.01.2013

1. Lessons learned from the Hürth IGCC Project

2. RWE´s current CCS activities

3. CO2 Utilization: a way out ?

4. CO2 Storage in Germany: a far way to go

5. Summary

PAGE 7 RWE Power 31.01.2013

Solvent regeneration

CO2-capture Flue gas cooling, SO2-pre scrubbing CO2

Desorber

Flue gas

Absorber Prescrubber

CO2-lean flue gas

NaOH solution tank Solvent tank

CO2 capture pilot plant at Niederaussem

Flue gas: 1.550 m3N/h Availability 97%

CO2 product: 7,2 tCO2/day; capture rate 90% Budget of RWE for phases I/II: 15 Mio. € Absorber height corresponds to full scale 40% funding by the Federal Ministry of Operating hours (as of 6/2012): > 20000 h Economics and Technology

PAGE 9 RWE Power 31.01.2013

RWE‘s pilot plant at Aberthaw

Pilot plant modules supplied by Cansolv Combined capture of SO2 and CO2

Treated gas volume 10,000 Nm3/hr CO2 product = 50 t/day (= 3 MWe)

Modules erected late 2011 Cold commissioning during 2012 ‘First capture’ January 2013 100% RWE budget > £12M R&D programme to last to mid-2014

PAGE 10 RWE Power 31.01.2013

1. Lessons learned from the Hürth IGCC Project

2. RWE´s current CCS activities

3. CO2 Utilization: a way out ?

4. CO2 Storage in Germany: a far way to go

5. Summary

PAGE 11 RWE Power 31.01.2013

CO2 in power production: Courses of action

CO2 mitigation CO2 utilization CO2 storage

Mitigation based on efficiency increase is promoted further

RWE is involved in the „Ketzin“ project in Germany

One of RWE‘s main research focuses

then then

PAGE 12 RWE Power 31.01.2013

Direct use liquefaction/compression

Chemistry Project Dream Production

Biotechnology Cooperation with BRAIN AG

Power Plant

chem. Energy storage Project CO2RRECT

CO2

CO2

CO2

Flue gas

Scrubbing

Promising Routes for Utilization of CO2

However, the overall potential for CO2 Usage in Germany is < 10 MT/a. Reward for CCU in form of free Allocated EUAs is not given.

PAGE 13 RWE Power 31.01.2013 *pictures courtesy of Bayer AG

CO2 from a lignite-fired power plant for polyurethane production

CO2

power

Scrubbing and supply of CO2

*Process Development and converting of CO2

*Production and testing of

polyurethanes from CO2

Fundamental research

Eco-efficiency analysis

„Dream Production“: from CO2 to polyurethanes

PAGE 14 RWE Power 31.01.2013

Carbon Capture and CO2 utilization projects at the Niederaussem Coal Innovation Centre

PCC CO2 for polymers “Dream Production“

CCU using microorganisms

Higher Efficiency Lower Emissions

Carbon Capture CO2 Utilization

Electrolysis for H2 generation Catalyst Development for

Power to Gas applications

PAGE 15 RWE Power 31.01.2013

1. Lessons learned from the Hürth IGCC Project

2. RWE´s current CCS activities

3. CO2 Utilization: a way out ?

4. CO2 Storage in Germany: a far way to go

5. Summary

PAGE 16 RWE Power 31.01.2013

Onshore CO2 Storage-Potential in Germany limited

Federal Institute for Geosciences and Natural Resources - CCS Study 2010 Suitable storage regions

in North-West and North-East Germany Storage potential:

Deep saline aquifers: 9 ± 3 bn. t Natural gas fields: 2.75 bn. t

Estimated storage potential sufficient for the CO2 emissions of large industrial installations for more than one power plant generation, but far up in the north

incr

easi

ng s

tora

ge

capa

city

Natural gas fields Large CO2 sources

Not suitable for CO2 storage

PAGE 17 RWE Power 31.01.2013

Carbon Storage Law (KSpG) – status quo

η = 65 % η = 65 %

KSpG took effect on 17/08/2012 and transposes EU directive 2009/31/EC into German law

The KSpG only permits a limited number of demo storage facilities (max. 1.3Mt/a per project) to be erected until 2017 for CCS research (max. 4Mt/a in total)

Federal states are responsible for permitting CO2 storage projects

The opt-out clause allows federal states to declare CO2 storage in certain areas inadmissible

Liability for storage side 40 years starting on the day of decommissioning (EU directive only demands 20 years)

The KSpG does not contain any agreement regarding the EEZ

KSpG to be reviewed in 2018 taking into account experiences gained in national and international projects

PAGE 18 RWE Power 31.01.2013

Assessment of the CCS law (KSpG)

η = 65 % η = 65 %

The EU CCS directive primarily deals with safety requirements for CO2 storage and access options to the CO2 transport infrastructure. It forms a good basis.

The KSpG puts obstacles in the way of projects in Germany that can hardly be overcome, including:

Opt-out clause: Certain areas can be excluded from CO2 storage. Sets a precedent for other infrastructure projects, energy-policy questions and laws.

Missing agreement concerning transport of CO2 to foreign or German EEZ. It is extremely difficult to assess whether approval will be granted for a CO2 pipeline in practice.

The approvals process for CCS could have been accelerated. For other infrastructure projects, these accelerators exist (e.g. in the Energy Line Extension Act (EnLAG)).

Liability issues

It is very unlikely that there will be a CCS demonstration project in Germany on the basis of the KSpG current .

PAGE 19 RWE Power 31.01.2013

1. Lessons learned from the Hürth IGCC Project

2. RWE´s current CCS activities

3. CO2 Utilization: a way out ?

4. CO2 Storage in Germany: a far way to go

5. Summary

PAGE 20 RWE Power 31.01.2013

Summary

The IGCC Project in Hürth (2006-2010) very early uncovered the challenges CCS development in Germany is still facing today

Facing currently unsurmountable problems with CO2-Transport & Storage, RWE focuses its efforts on Carbon Capture und on Utilization

RWE is developing a number of options for CCU. However, the potential for CCU is limited. A reward in form of free EUA allowances is not given

The current legal framework in Germany does rather hinder than promote the development of CCS

Public acceptance still the biggest issue to be resolved but can only be achieved if political support is granted. EU-wide Demoprojects are strongly needed to support this process

RWE Power 31.01.2013 PAGE 21

Thank you very much !