3
® © Concrete Canvas Ltd. 2018 The information contained herein is offered free of charge and is, to the best of our knowledge, accurate. However, since the circumstances and conditions in which such information and the products discussed therein can be used may vary and are beyond our control, we make no warranty, express www.concretecanvas.com [email protected] +44 (0) 345 680 1908 www ® i # Project Info *Geosynthetic Cementitious Composite Mat JAN 1 01 / 01 / 18 CC8 TM Batched Rolls 250m 2 Transverse layers Falkirk Wheel, Falkirk, Scotland AMCO CC8 TM used to line drainage channels running adjacent to a busy rail line to prevent erosion and scour. Completed CC lined channel in Falkirk, Scotland In January 2018, Concrete Canvas ® GCCM* (CC) was used to line a 100m long dilapidated drainage channel running adjacent to a busy rail line at the famous Falkirk Wheel in Scotland. AMCO, who have previously installed CC on many other Network Rail projects in the region, were the principle contractor for the project. The project presented several challenges for the contractor and client. Firstly, the site was located in a remote area with no access for heavy machinery. Therefore, all materials were delivered to the site with small tracked vehicles and the contractor was limited to simple hand tools for the installation. The ground was also saturated due to recent heavy snowfall which made alternatives such as poured concrete very difficult. Ultimately, CC was chosen as it is available in portable batched rolls, which don’t require any heavy machinery, while its flexible nature meant it could easily accommodate the channel without additional excavation and preparation. 50 batched rolls of CC8 TM were delivered to site and the channels excavated by the installation crew using shovels. The material was cut to length on site with utility knives to reduce material wastage and deployed transversely across the width of the channel. The CC layers were then overlapped by 100mm, shingled in the direction of water flow, and screwed together at 200mm intervals with stainless steel screws. Following each day’s work, the CC was hydrated from a nearby stream using a pump and hose with a diffused spray nozzle. To prevent water ingress beneath the material, the edges of the CC were terminated into hand dug anchor trenches on either side of the channel, with the material pinned and backfilled.

CC Channel Lining - Falkirk Wheel, Scotland - AMCO Network Rail · Falkirk Wheel, Falkirk, Scotland AMCO CC8TM used to line drainage channels running adjacent to a busy rail line

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: CC Channel Lining - Falkirk Wheel, Scotland - AMCO Network Rail · Falkirk Wheel, Falkirk, Scotland AMCO CC8TM used to line drainage channels running adjacent to a busy rail line

®

© Concrete Canvas Ltd. 2018The information contained herein is offered free of charge and is, to the best of our knowledge, accurate. However, since the circumstances and conditions in which such information and the products discussed therein can be used may vary and are beyond our control, we make no warranty, express

[email protected]+44 (0) 345 680 1908 www®

i

#

Project Info

*Geosynthetic Cementitious Composite Mat

JAN

1 01 / 01 / 18

CC8TM Batched Rolls

250m2

Transverse layers

Falkirk Wheel, Falkirk, Scotland

AMCO

CC8TM used to line drainage channels running adjacent to a busy rail line to prevent erosion and scour.

Completed CC lined channel in Falkirk, Scotland

In January 2018, Concrete Canvas® GCCM* (CC) was used to line a 100m long dilapidated drainage channel running adjacent to a busy rail line at the famous Falkirk Wheel in Scotland. AMCO, who have previously installed CC on many other Network Rail projects in the region, were the principle contractor for the project.

The project presented several challenges for the contractor and client. Firstly, the site was located in a remote area with no access for heavy machinery. Therefore, all materials were delivered to the site with small tracked vehicles and the contractor was limited to simple hand tools for the installation. The ground was also saturated due to recent heavy snowfall which made alternatives such as poured concrete very diffi cult. Ultimately, CC was chosen as it is available in portable batched rolls, which don’t require any heavy machinery, while its fl exible nature meant it could easily accommodate the channel without additional excavation and preparation.

50 batched rolls of CC8TM were delivered to site and the channels excavated by the installation crew using shovels. The material was cut to length on site with utility knives to reduce material wastage and deployed transversely across the width of the channel. The CC layers were then overlapped by 100mm, shingled in the direction of water fl ow, and screwed together at 200mm intervals with stainless steel screws. Following each day’s work, the CC was hydrated from a nearby stream using a pump and hose with a diff used spray nozzle. To prevent water ingress beneath the material, the edges of the CC were terminated into hand dug anchor trenches on either side of the channel, with the material pinned and backfi lled.

Page 2: CC Channel Lining - Falkirk Wheel, Scotland - AMCO Network Rail · Falkirk Wheel, Falkirk, Scotland AMCO CC8TM used to line drainage channels running adjacent to a busy rail line

© Concrete Canvas Ltd. 2018The information contained herein is offered free of charge and is, to the best of our knowledge, accurate. However, since the circumstances and conditions in which such information and the products discussed therein can be used may vary and are beyond our control, we make no warranty, express

[email protected]+44 (0) 345 680 1908 www®

®

© Concrete Canvas Ltd. 2018The information contained herein is offered free of charge and is, to the best of our knowledge, accurate. However, since the circumstances and conditions in which such information and the products discussed therein can be used may vary and are beyond our control, we make no warranty, express

[email protected]+44 (0) 345 680 1908 www®

®

Railway line runs adjacent to the Falkirk Wheel

Batched rolls delivered using JCB tracked mini dumper

CC able to accomodate existing security fencing

Unlined channel prior to installation

Anchor trenches excavated with hand shovels

CC lined channel diverted water into two large culverts

Page 3: CC Channel Lining - Falkirk Wheel, Scotland - AMCO Network Rail · Falkirk Wheel, Falkirk, Scotland AMCO CC8TM used to line drainage channels running adjacent to a busy rail line

© Concrete Canvas Ltd. 2018The information contained herein is offered free of charge and is, to the best of our knowledge, accurate. However, since the circumstances and conditions in which such information and the products discussed therein can be used may vary and are beyond our control, we make no warranty, express

[email protected]+44 (0) 345 680 1908 www®

®

© Concrete Canvas Ltd. 2018The information contained herein is offered free of charge and is, to the best of our knowledge, accurate. However, since the circumstances and conditions in which such information and the products discussed therein can be used may vary and are beyond our control, we make no warranty, express

[email protected]+44 (0) 345 680 1908 www®

Completed project

In total, 250m2 of CC8TM were installed by a team of four in inclement weather conditions in three days. The ease and speed of installation resulted in a significantly reduced time on site and a reduction in the overall project cost. Due to these factors, the contractor and client deemed the installation a success and the material will continue to be specified for similar rail schemes in the region.