COMPETENCY-BASED LEARNING MATERIAL
Sector: CONSTRUCTION
Qualification Title: CARPENTRY NC II
Unit of Competency: INSTALL FORMWORK COMPONENTS
Module Title: INSTALLING FORMWORK COMPONENTS
Technical Education and Skills Development AuthorityJacobo Z. Gonzales Memorial School of Arts and Trades
San Antonio, Biñan City
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 1 of 38Developed by:Glenn F.
SalandananRevision # ____
HOW TO USE THIS COMPETENCY BASED LEARNING MATERIAL
Welcome to the module in Installing Formwork Components. This module contains training materials and activities for you to complete.
You are required to go through a series of learning activities in order to complete each learning outcome of the module. In each learning outcome are Information Sheets, Self-Checks, Operation Sheets and Job Sheets. Follow these activities on your own. If you have questions, don't hesitate to ask your facilitator for assistance.
The goal of this course is the development of practical skills. To gain these skills, you must learn basic concepts and terminology. For the most part, you'll get this information from the Information Sheets and multimedia materials
This module was prepared to help you achieve the required competency, in "Installing Formwork components".
This will be the source of information for you to acquire knowledge and skills in this particular competency independently and at your own pace, with minimum supervision or help from your instructor.
Remember to:Work through all the information and complete the activities in each section.Read information sheets and complete the self-check. Suggested references
are included to supplement the materials provided in this module.Most probably your trainer will also be your supervisor or manager. He/she is
there to support you and show you the correct way to do things.You will be given plenty of opportunity to ask questions and practice on the
job. Make sure you practice your new skills during regular work shifts. This way you will improve both your speed and memory and also your confidence.
Use the Self-checks, Operation Sheets or Job Sheets at the end of each section to test your own progress.
When you feel confident that you have had sufficient practice, ask your Trainer to evaluate you. The results of your assessment will be recorded in your Progress Chart and Accomplishment Chart.
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 2 of 38Developed by:Glenn F.
SalandananRevision # ____
UNIT OF COMPETENCY : INSTALL FORMWORK COMPONENTS
MODULE TITLE : INSTALLING FORMWORKS
MODULE DESCRIPTOR : This module covers the knowledge, skills and attitude in selecting and preparing materials and tools for installing formworks, Laying-out/assembling scaffolds and braces, setting/fixing form panels of building components.
NOMINAL DURATION : 32 hrs.
CERTIFICATE LEVEL : NATIONAL CERTIFICATE LEVEL II
PREREQUISITE :
SUMMARY OF LEARNING OUTCOMES:
Upon completion of this module, the trainee/student must be able to:
LO 1. Select and prepare materials and tools for installing formworks
LO 2. Lay-out/assemble scaffolds and braces
LO 3. Set/fix form panels of building components
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 3 of 38Developed by:Glenn F.
SalandananRevision # ____
ASSESSMENT CRITERIA:
1. Plans and details are correctly identified and interpreted according to job requirements
2. Materials, hand and power tools and equipment are selected and prepared consistent with job requirements
3. Materials are re-checked for defects and in accordance with plans and specifications
4. Housekeeping is performed according to safety regulations
5. Work areas are cleared for safe laying-out and assembling of scaffolds and braces
6. Scaffolds and braces are assembled with tolerance of + 3mm for all measurements and squareness, plumbness and levelness
7. Connectors, locks and screws are properly secured according to job requirements
8. Formworks components/form panels are laid-out, set/fixed with tolerance of ± 3 mm for measurement, alignment, squareness, levelness and plumbness with form oil
9. Braces are properly installed to support the formworks according to job requirements
10. Formworks components/form panels are re-checked for squareness, levelness and plumbness
11. Appropriate PPE is used according to job requirements and safety regulations
12. Unexpected situations are responded to in line with company rules and regulations
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 4 of 38Developed by:Glenn F.
SalandananRevision # ____
LEARNING OUTCOME NO. 1 Select and prepare materials and tools for installing formworks
CONTENTS:• Materials, power and hand tools and equipment uses and specifications • Properties of Wood• Housekeeping
ASSESSMENT CRITERIA1. Plans and details are correctly identified and interpreted according to job
requirements2. Materials, hand and power tools and equipment are selected and prepared
consistent with job requirements3. Materials are re-checked for defects and in accordance with plans and
specifications4. Appropriate PPE is used according to job requirements5. Unexpected situations are responded to in line with company rules and
regulations6. Housekeeping is performed according to safety regulations
CONDITIONS: You must be provided with the following:
1. WORKPLACE LOCATION2. TOOLS AND EQUIPMENT
• Claw Hammer• Pencil/Marking pen• Pull-Push Rule• Nylon String• Steel Square• Try-square• Hand Saw• Chalk Line
3. TRAINING MATERIALSLeaning PackagesBond paperBall pens
• Personal Protective Equipment
• Portable Circular Saw• Plan and working drawings• Lumber• Nails• Plywood
ManualsRelated References
ASSESSMENT METHOD
Portfolio
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 5 of 38Developed by:Glenn F.
SalandananRevision # ____
Learning ExperienceSELECT AND PREPARE MATERIALS AND TOOLS FOR INSTALLING
FORMWORKS
Learning Activities Special Instructions
Read Information Sheet No. 3.1-1 on Materials, power and hand tools and equipment uses and specifications
Refer to Information Sheets No. 1.1-2 and 1.1-4
Read Information Sheet No. 3.1-2 on Properties of wood
Refer to Information Sheet No. 2.1-3
Read Information Sheet No. 3.1-3 on Housekeeping
Answer Self-Check No. 3.1-3Compare your answer to the answer key
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 6 of 38Developed by:Glenn F.
SalandananRevision # ____
INFORMATION SHEET NO. 3.1-1MATERIALS, POWER AND HAND TOOLS AND EQUIPMENT USES
AND SPECIFICATIONS
Review Information Sheet No. 1.1-2 on Material Specifications, Information Sheet No. 1.1-4 on Tools, Materials and Equipment for Staking out Building Lines
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 7 of 38Developed by:Glenn F.
SalandananRevision # ____
INFORMATION SHEET NO. 3.1-2PROPERTIES OF WOOD
Read Information Sheet No. 2.1-3 on Mechanical Properties of Wood.
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 8 of 38Developed by:Glenn F.
SalandananRevision # ____
INFORMATION SHEET NO. 3.1-3HOUSEKEEPING
LEARNING OBJECTIVE:Upon completing this section, you should be able to KNOW and APPLY
HOUSEKEEPING at all times.
Formwork construction because of its constantly changing work environment, restricted access through frames and formwork supports and a large volume of material and waste, requires ongoing monitoring of housekeeping practices.
A. Access
Clear access is important for the safe movement of materials, equipment and persons on site. Designated access ways must be provided. Persons must be instructed to use the access ways and keep them clear of any excess wastes, plant or materials. In some situations, it may be necessary to use hazard taping or other visual methods to clearly show where access ways are located. This is particularly important where access is required through formwork frames.
Emergency access and egress must be considered and provided to all parts of the workplace where persons are required to work.
B. Material storage
1. Materials must be stored so as to minimize manual tasks hazards, trip hazards and the potential for falling objects.
2. It is preferable to lay wall forms flat on the ground instead of leaning them against structures or other forms.
3. Timbers, or another effective means, must be provided under the forms where slings are to be placed under the forms for crane lifting.
4. Wall forms must be stacked in such a way that they cannot move away or rotate from the surface they are placed against.
5. Incorrect materials delivery and storage can create significant manual handling tasks. Safe work practices to minimize exposure to these risks include:• ensuring the formwork materials are delivered as close as possible to the
job• designing and designating a small section of the formwork as a loading
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 9 of 38Developed by:Glenn F.
SalandananRevision # ____
platform to load ply and other components• ensuring mechanical aids are used to handle loads wherever possible• storing loads on trolleys to minimize double handling or on raised
platforms to minimize manual lifting from ground level• having adequate storage space or lay down area to safely store materials
and equipment and to minimize double handling
C. Storing and Disposing of Waste Materials at the Workplace
Waste material storage and removal for formwork may include the provision of garbage skips and wheel barrows that are moved as work progresses. However, garbage skips should only be positioned where the supporting structure has adequate strength to support the total weight of the bin and likely contents.
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 10 of 38Developed by:Glenn F.
SalandananRevision # ____
LEARNING OUTCOME NO. 2 Lay-out/assemble scaffolds and braces
CONTENTS:• Types of scaffolds• Different scaffold fittings and their uses• Scaffolds safety rules• Assemble scaffolding
ASSESSMENT CRITERIA1. Work areas are cleared for safe laying-out and assembling of scaffolds and
braces2. Scaffolds and braces are assembled with tolerance of +3mm for all
measurements and squareness, plumbness and levelness3. Connectors, locks and screws are properly secured according to job
requirements4. Appropriate PPE is used according to job requirements5. Unexpected situations are responded to in line with company rules and
regulations
CONDITIONS: You must be provided with the following:
1. WORKPLACE LOCATION2. TOOLS AND EQUIPMENT
• Claw Hammer• Pencil/Marking pen• Pull-Push Rule• Nylon String• Steel Square• Try-square• Hand Saw• Chalk Line
3. TRAINING MATERIALS• Leaning Packages• Bond paper• Ball pens
• Personal Protective Equipment
• Portable Circular Saw• Plan and working drawings• Lumber• Nails• Plywood
• Manuals• Related References
ASSESSMENT METHOD
Portfolio
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 11 of 38Developed by:Glenn F.
SalandananRevision # ____
Learning ExperienceLAY-OUT/ASSEMBLE SCAFFOLDS AND BRACES
Learning Activities Special Instructions
Read Information Sheet No. 3.2-1 on Types of scaffolds
Answer Self-Check No. 3.2-1Compare your answer to the answer key
Read Information Sheet No. 3.2-2 on Different scaffold fittings and their uses
Answer Self-Check No. 3.2-2Compare your answer to the answer key
Read Information Sheet No. 3.2-3 on Scaffolds safety rules
Answer Self-Check No. 3.2-3Compare your answer to the answer key
Read Information Sheet No. 3.2-4 on Assemble scaffolds
Perform Operation Sheet No. 3.2-4 on Assemble scaffolds
Evaluate your own work using the Performance Criteria ChecklistPresent your work to your trainer for evaluationKeep a copy of your work for the next activities
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 12 of 38Developed by:Glenn F.
SalandananRevision # ____
INFORMATION SHEET NO. 3.2-1TYPES OF SCAFFOLDS
LEARNING OBJECTIVE:Upon completing this section, you should be able to KNOW the definition of
SCAFFOLDS and SCAFFOLDINGS and RECOGNIZE the different MATERIALS and TYPES of SCAFFOLDING
Scaffold–A temporary structure from which persons can gain access to a place in order to carry out building operation
Scaffolding–Method of construction of scaffolds is called scaffolding.
Scaffold can be made of the following materials:
a. Tubular steel • 3 times heavier than aluminum alloy
tubes but far stronger• longer span can be used • galvanized steel tubes and ungalvanized
steel tubes are types of steel scaffolds
b. Tubular aluminum alloy• Needs protective treatment when used
in contact with damp line, wet cement and sea water
• Coating the tube with bituminus paint before using it as protective treatment
c. Timber• Extensively used in the developing
countries • Members are lashed together with wire
or rope instead of coupling fittings used with metal scaffolds
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 13 of 38Developed by:Glenn F.
SalandananRevision # ____
Following are the types of scaffolds
Single Scaffolds Double Scaffolds Ladder Scaffolds
Cantilever ScaffoldsSuspended Scaffolds
Steel or Tubular Scaffolds
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 14 of 38Developed by:Glenn F.
SalandananRevision # ____
SELF- CHECK NO. 3.2-1
Check your mastery in types of scaffolds by completing the tasks below.
Identification: Identify the types of scaffold used based from the following statement. Choose from the answers below by writing the letter of your answer on the space provided before the number.
a. Tubular steel b. Tubular aluminum alloyc. Timber
1. Coated with bituminus paint before using it as protective treatment
2. Three (3) times heavier than aluminum alloy tubes but far stronger
3. Longer span can be used
4. Members are lashed together with wire or rope instead of coupling fittings used with metal scaffolds
5. Extensively used in the developing countries
6. Needs protective treatment when used in contact with damp line, wet cement and sea water
7. Galvanized steel tubes and ungalvanized steel tubes are types of scaffolds
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 15 of 38Developed by:Glenn F.
SalandananRevision # ____
ANSWER KEY 3.2-1
Check your answer with the answer key below. If you fail to get it right, refer back to corresponding resources until you make it perfect.
1. B2. A3. A4. C5. C6. B7. A
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 16 of 38Developed by:Glenn F.
SalandananRevision # ____
INFORMATION SHEET NO. 3.2-2DIFFERENT SCAFFOLD FITTINGS AND THEIR USES
LEARNING OBJECTIVE:Upon completing this section, you should be able to RECOGNIZE the
DIFFERENT SCAFFOLD FITTINGS and their USES.
Scaffold fittings
1. Double Coupler–It joins ledgers and standards.2. Swivel Coupler–Composed of two single couplers and used to join two
scaffolds at any angle.3. Putlog Coupler–Used to join putlogs with transom.4. Base Plate–Used at the base of the standards.5. Split joint Pin–It’s a connection fitting used to join scaffold tubes.6. Reveal Pin–It fit in to the end of a tube to form an adjustable strut.7. Putlog end–A flat plate used at the end of a scaffold to convert it in to a putlog.
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 17 of 38Developed by:Glenn F.
SalandananRevision # ____
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 18 of 38Developed by:Glenn F.
SalandananRevision # ____
SELF- CHECK NO. 3.2-2
Check your mastery in different scaffold fittings and their uses by completing the tasks below.
Identification: Identify the types of scaffold fitting from the following statement. Choose your answer from the fittings below by writing the answer on the space provided before the number.
DOUBLE COUPLERSWIVEL COUPLERPUTLOG COUPLER
BASE PLATESPLIT JOINT PIN
REVEAL PINPUTLOG END
_____________________1. A flat plate used at the end of a scaffold to convert
it in to a putlog.
_____________________2. Used at the base of the standards.
_____________________3. It joins ledgers and standards.
_____________________4. Composed of two single couplers and used to join
two scaffolds at any angle.
_____________________5. It fit in to the end of a tube to form an adjustable
strut.
_____________________6. It’s a connection fitting used to join scaffold tubes.
_____________________7. Used to join putlogs with transom.
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 19 of 38Developed by:Glenn F.
SalandananRevision # ____
ANSWER KEY 3.2-2
Check your answer with the answer key below. If you fail to get it right, refer back to corresponding resources until you make it perfect.
1. Putlog end2. Base Plate3. Double Coupler4. Swivel Coupler5. Reveal Pin6. Split joint Pin7. Putlog Coupler
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 20 of 38Developed by:Glenn F.
SalandananRevision # ____
INFORMATION SHEET NO. 3.2-3SCAFFOLDS SAFETY RULES
LEARNING OBJECTIVE:Upon completing this section, you should be able to APPLY SAFETY RULES
in ERECTING SCAFFOLDS at all times
These safety rules cover generalized situations only and should not be used to replace any other additional safety and precautionary measures that may be necessary to cover the many usual or unusual conditions encountered during installation or dismantling.
1. Follow safe practice of the safety rules and comply with OH&S laws and other federal, state and local rules, codes and regulations pertaining to scaffolding during any use of the equipment.
2. The potentially hazardous nature of scaffolding assembly makes it important that all personnel assigned to this work be instructed in theses safety rules, safe practices and procedures and be under the supervision of an experienced person. Ensure that these Safety rules are posted and that all assemblers and users of the scaffold are aware of and follow them.
3. Report any unsafe conditions to supervisors. Do not work or allow persons to work on scaffolds when sick or suffering from dizziness, unsteadiness or any other physical symptom which could affect their ability to work safe.
4. Inspect all equipment before use. Never use any equipment which is damaged, defective, or deteriorated in any way.
5. Inspect assembled scaffold frequently and be sure that it is maintained in a safe condition, ensure that the scaffold connection have not become loosened and that components have not been improperly released or removed.
6. Maintain all equipment in good repair. Never use corroded or excessively rusted equipment; the strength of such equipment is not known.
7. Consult your scaffolding supplier when in doubt. Never take chances.8. Always read these safety rules in conjunction with all safety regulations.9. Always place scaffolds on a sound, stable surface and assure that it is
adequate to support the intended scaffold loads. Never place scaffolds on unstable where loose objects could tip, break or become dislodged.
10.Lift and lower components carefully and safely. Use tag lines where appropriate to the handling method. Never allow excessive quantities of components to be stockpiled on partially complete scaffolds. Stock only sufficient components consistent with the progress of the work. Lower dismantled components as soon as possible. Never drop components deliberately.
11. The tieing of the scaffold to the structure is of great importance to the
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 21 of 38Developed by:Glenn F.
SalandananRevision # ____
stability and safety of the scaffold. Assure that the structure to which the scaffold is tied or anchored is capable of safely supporting all loads imposed by the scaffold.
12.Free standing scaffolds other than wall scaffolds must be restrained from tipping by guying or other means or otherwise stabilized as appropriate, recognizing that stability is essential to the safety of the scaffold.
13. Install guardrails, midrails, and toeboards at all openings, open sides, and ends of every work platform
14.Never use ladders or makeshift devices on tops of scaffold to increase the height. Never place plank on or stand on guardrails and mid-rails.
15.Power lines near scaffolds are dangerous. Use extreme caution and consult the electrical company to have the lines de-energized, insulated, or otherwise rendered safe. Never allow any installation or use of scaffolds until this is completed.
16.Proper care and precautions must be taken when using cantilevers to prevent tripping of the scaffold
17.For mobile scaffolds following these additional safety rulesa) Never ride mobile scaffolds.b) Remove all materials and equipment from the scaffold before moving.c) Lock castor and outrigger brakes when scaffold is not being moved.d) Do not attempt to move mobile scaffold without sufficient help and roll on
even surfaces only.e) The maximum platform height of a mobile scaffold must not be exceeded.
All OH &S laws must comply when using mobile scaffold.f) Move the scaffold using the bottom frame. Never attempt to move the
scaffold when on top.g) If mobile scaffolds are used outdoors, care must be taken to assure that
they cannot become unstable due to wind or other conditions.18.Do not overload scaffolds. Refer to and do not exceed the scaffold load
capacities.
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 22 of 38Developed by:Glenn F.
SalandananRevision # ____
SELF- CHECK NO. 3.2-3
Check your mastery in scaffolds safety rules by completing the tasks below.
Identification: Read the statement carefully. Supply the missing word or group of words by writing it on the space provided. Choose your answer from the list below.
ComponentsInspectLaddersOH&S
Overload
Power lines Stable
Supervisors Tieing
Toeboards
1. Always place scaffolds on a sound, __________ surface.
2. Do not _______________ scaffolds.
3. _____________ near scaffolds are dangerous.
4. _____________ assembled scaffold frequently.
5. Report any unsafe conditions to _____________.
6. Install guardrails, midrails, and _____________ at all openings.
7. Never use _____________ or makeshift devices on tops of scaffold.
8. The ___________ of the scaffold to the structure is of great importance to the
stability and safety of the scaffold.
9. Follow safe practice of the safety rules and comply with ___________ laws.
10.Lift and lower ______________ carefully and safely.
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 23 of 38Developed by:Glenn F.
SalandananRevision # ____
ANSWER KEY 3.2-3
Check your answer with the answer key below. If you fail to get it right, refer back to corresponding resources until you make it perfect.
1. Stable2. Overload3. Power lines4. Inspect5. Supervisors6. Toeboards7. Ladders8. Tieing9. OH&S10.Components
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 24 of 38Developed by:Glenn F.
SalandananRevision # ____
INFORMATION SHEET NO. 3.2-4ASSEMBLE SCAFFOLDING
LEARNING OBJECTIVE:Upon completing this section, you should be able to ERECT SCAFFOLDS.
Procedures in Assembling Scaffolds
Step 1 Attach side brace B to two frames A• Pull L-shape lock pin at each end of side brace to the disengaged position. • While holding L-shape pin in disengaged position, place U-channel on
each end of side brace B around leg of frame A at desired platform height.• Release lock pin and be sure that pin fully engages into hole in frame A
leg.Step 2 Attach second brace B to two frames A. Repeat instructions in Step 1.
WARNING:• Both side braces must be positioned at the same height on the frames so
that the platform will be level.• Be sure all 4 L-shape lock pins are fully engaged in holes of frames.• Be sure all 4 L-shape lock pins are in the locked position.
Step 3 Install platform C on side braces B so that the platform is fully seated within inner channel on top of side braces.
Step 4 Rotate the platform clips into the engaged position. Step 5 Install 4 castors D into legs of frame A and pin with lock pins E.Step 6 Install 4 outriggers into legs of bottom frame.Step 7 While standing on first platform, insert third frame A into top of first mobile
scaffold frame. Then insert fourth frame A into top of first mobile scaffold frame.
Step 8 Attach second side brace B to two frames A ensuring the L-shape lock pin attach end of side brace is engaged. And repeat other side.
Step 9 Install platform as per Step 3 and 4.Step 10 Install guardrail.
WARNING:• Recheck all side brace lock pins for full engagement before accessing
platform.• Recheck platform to be sure it is properly seated within side brace channel
and the platform clips are fully engaged before accessing.• When accessing platform, climb over top of frame ladder – DO NOT
SWING AROUND SIDE FRAME.
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 25 of 38Developed by:Glenn F.
SalandananRevision # ____
OPERATION SHEET NO. 3.2-4
Title: Assemble Scaffolds
Performance Objective: Given the necessary materials, you should be able to assemble scaffolds
Supplies and Materials: Working Drawing/ Mudsill (boards)
Tools and Equipment: • H-frame• Cross bracing• Connectors• Screw jacks
• Catwalk• Spirit level• Plumb bob
PPE
Steps/Procedure:
1. Prepare the site for the assembly. Work area should be cleared for safe lay-
outing and assembling of scaffolds and braces
2. Ready all the equipment, tools and materials.
3. Assemble the scaffolds based on your trainer’s instruction.
4. Carefully follow the assembling procedure.
5. Check the squareness, plumbness and levelness of the scaffolds.
6. Acknowledge your teacher to check your work if you are done with the task.
7. Perform housekeeping after the operation.
Precautions:
1. Always observe scaffold safety rules while working/performing.2. Appropriate body protection must be worn during the performance of the
task.Assessment Method:
PortfolioDemonstration
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 26 of 38Developed by:Glenn F.
SalandananRevision # ____
PERFORMANCE CRITERIA CHECKLISTOPERATION SHEET NO. 3.2-4
Name of Trainee:_____________________________ Date: __________________
CRITERIACRITERIA YESYES NONO
1. Did I clear the work area first before laying out and assembling scaffolds and braces for safety?
2. Are all scaffolds and braces laid-out and assembled with ±3 mm tolerance for:
• All measurements?
• Squareness?
• Plumbness?
• Levelness?
3. Did I use proper and correct personal protective equipment when assembling scaffolds and braces?
4. Did I secure all the connectors, braces, locks and screws properly?
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 27 of 38Developed by:Glenn F.
SalandananRevision # ____
LEARNING OUTCOME NO. 3 Set/fix formworks components/form panels
CONTENTS:• Formwork components assembly
ASSESSMENT CRITERIA1. Formworks components/form panels are laid-out, set/fixed with tolerance of
±3 mm for measurement, alignment, squareness, levelness and plumbness with form oil
2. Braces are properly installed to support the formworks according to job requirements
3. Formworks components/form panels are re-checked for squareness, levelness and plumbness
4. Appropriate PPE is used according to job requirements and safety regulations
5. Unexpected situations are responded to in line with company rules and regulations
CONDITIONS: You must be provided with the following:
1. WORKPLACE LOCATION2. TOOLS AND EQUIPMENT
• Claw Hammer• Pencil/Marking pen• Pull-Push Rule• Nylon String• Steel Square• Try-square• Hand Saw• Chalk Line
3. TRAINING MATERIALS• Leaning Packages• Bond paper• Ball pens
• Personal Protective Equipment
• Portable Circular Saw• Plan and working drawings• Lumber• Nails• Plywood
• Manuals• Related References
ASSESSMENT METHODPortfolio
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 28 of 38Developed by:Glenn F.
SalandananRevision # ____
Learning ExperienceSET/FIX FORMWORKS COMPONENTS/FORM PANELS
Learning Activities Special Instructions
Read Information Sheet No. 3.3-1 on Formwork components assembly
Perform Operation Sheet No. 3.3-1a on Install column form
Evaluate your own work using the Performance Criteria ChecklistPresent your work to your trainer for evaluationKeep a copy of your work for the next activities
Perform Operation Sheet No. 3.3-1b on Install beam form
Evaluate your own work using the Performance Criteria ChecklistPresent your work to your trainer for evaluationKeep a copy of your work for the next activities
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 29 of 38Developed by:Glenn F.
SalandananRevision # ____
INFORMATION SHEET NO. 3.3-1FORMWORK COMPONENTS ASSEMBLY
LEARNING OBJECTIVE:Upon completing this section, you should be able to APPLY the STEPS IN
ASSEMBLING FORMWORK COMPONENTS
The method and sequence of erecting formwork may vary depending on the availability of lifting equipment and whether reinforcing cages are available. Forms are usually handled manually, by small derrick, or by crane. The erect formwork activity includes the process of lifting, positioning, and aligning the different formworkelements. This activity also includes the process of applying the form release agent or coating that prevents bonding of concrete to forms. The concrete life cycle starts after the erect formwork activity is finished with placing inserts and reinforcement activity.
A. Constructing a Wall/Column FormConstruct column forms from the lowest point to the highest point. Follow
these steps when constructing a concrete form:
1. Ensure to get the column form inside dimensions and height.
2. Ensure that the following materials are available:
• Sheathing• Yokes• Battens
• Yoke locks• No. 4 reinforcing material• Tie wire
3. Build the footing form (refer to Information sheet no. 2.2-1).
4. Build the column-form sides (refer to Information sheet 2.2-1).
4.1 Fasten the column sides. After the four sides of the column form have been constructed, fasten them together and set them in place.
NOTE: The column form should have a clean-out hole in the bottom to remove construction debris. The pieces of lumber removed from the clean-out hole should be nailed to the form so they can be replaced right before placing concrete in the column.
4.2 Install the yoke locks.
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 30 of 38Developed by:Glenn F.
SalandananRevision # ____
4.2.1 Sheathing-type yoke lock. Fasten this type of lock to the yokes with nails or screws.
4.2.2 Bolt-type yoke lock. Drill holes where the yokes intersect and insert bolts, washers, and nuts.
4.2.3 Tighten until they are snug. If available, wing nuts work the best.
4.2.4 Scab-type yoke lock. Cut scabs out of scrap 2- by 4-inch lumber and secure with wood fasteners.
B. Constructing an Overhead Form
1. Construct a concrete-overhead-beam form
1.1 Set the form bottom.
1.1.1 Make the width of the soffit out of 2-inch material, exactly like that of the member being formed, and its length equal to the distance between the columns or the spans.
1.1.2 Cut the two ends of the form bottom at a 45-degree angle to produce a chamfer at the junction of the beam bottom and column.
1.2 Nail the chamfer strips with beveled ends to the beam-form bottom, flush with the outside edge.
NOTE: Chamfer strips are small pieces of wood (about 1 inch by 1 inch).
1.3 Cut the studs to the length called for in the specifications.
1.4 Cut and fasten the sheathing.
1.4.1 Use either 1-inch tongue and groove lumber or plywood.
1.4.2 Cut the sheathing should be cut to the length called for in the specifications and fasten it to the studs to create both side panels.
1.4.3 Nail sheathing sides so that they overlap the bottom piece of the form.
1.5 Cut and install the temporary spreaders.
1.5.1 Cut the temporary spreaders to the beam as stated in the specifications.1.5.2 Install the temporary spreaders by using double-headed forming nails.
1.6 Install the shoring.
1.6.1 Use a large quantity of shoring to offset the downward hydrostatic pressure placed on the form bottom. Commercial adjustable-metal forms are available and are probably the best and easiest type of shoring to use on beam and girder forms (Figure 052-236-1165-2). Heavy timber such as 4- by 4-inch lumber is normally available and works fine. 1.6.2 Install shoring so that the beam form remains level.
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 31 of 38Developed by:Glenn F.
SalandananRevision # ____
Beam and Girder Form
C. Constructing a Concrete-Slab Form
1. Construct a wooden-form slab
1.1 Construct the formwork. Measure and mark the side-form material to the required lengths.
1.1.1 Make two pieces the actual length of the slab and two pieces length of the slab plus two times the thickness of the material.1.1.2 Nail the form sides together at the corners.
1.2 Place and secure the formwork.
1.2.1 Place the formwork at the specified location.
1.2.2 Square the forms by using the diagonal method.
1.2.3 Drive the stakes at all the corners and approximately 3 feet along the entire perimeter of the form.
1.2.4 Level the formwork, then nail the forms to the stakes.
1.3 Cut and place polyethylene plastic in the bottom of the form as a vapor barrier.
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 32 of 38Developed by:Glenn F.
SalandananRevision # ____
OPERATION SHEET NO. 3.3-1a
Title: Install Column Forms
Performance Objective: Given the necessary materials, you should be able to install column forms
Supplies and Materials: Working Drawing/ PlanLumber, plywood, fasteners
Tools and Equipment: • Hammer• Marking Tools• Measuring Tools• Steel Square• Try-square• Hand Saw
• Chalk Line• Water Hose
Level• Plumb Bob• PPE• Circular Saw
Steps/Procedure:
1. Prepare the necessary tools, equipment and materials to be used.
2. From the given working drawing, stake-out building lines and batter boards (refer to Job Sheet No. 1.2-1 on staking out building lines)
3. Fabricate the column-form sides (refer to Operation Sheet No. 2.2-4 and 2.3-2 regarding the fabrication of formworks)
4. Erect scaffolding. Observe safety in installing scaffoldings.
5. Install column-form panels reinforcement.
6. Fasten the column sides. After the four sides of the column form have been constructed, fasten them together and set them in place. Check the plumbness, levelness and squareness using appropriate tools.
7. Install column-form reinforcement
8. Install ties.
9. Provide bracing for column-form sides
10. Place secondary and main reinforcement
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 33 of 38Developed by:Glenn F.
SalandananRevision # ____
Working Drawing of Column Footing Detail
Assessment Method:PortfolioDemonstration
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 34 of 38Developed by:Glenn F.
SalandananRevision # ____
PERFORMANCE CRITERIA CHECKLISTOPERATION SHEET NO. 3.3.1a
Name of Trainee:_____________________________ Date: __________________
CRITERIACRITERIA YESYES NONO
1. Did I secure the formworks using braces for stability?
2. Did I always check/recheck the squareness, measurement, levelness and plumbness of installed formwork components?
3. Did I use proper and correct personal protective equipment when working in installing formworks?
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 35 of 38Developed by:Glenn F.
SalandananRevision # ____
OPERATION SHEET NO. 3.3-1b
Title: Install Beam Forms
Performance Objective: Given the necessary materials, you should be able to install column forms
Supplies and Materials: Working Drawing/ PlanLumber, plywood, fasteners
Tools and Equipment: • Hammer• Marking Tools• Measuring Tools• Steel Square• Try-square• Hand Saw
• Chalk Line• Water Hose
Level• Plumb Bob• PPE• Circular Saw
Steps/Procedure:
1. Prepare the necessary tools, equipment and materials to be used.
2. Fabricate the beam-form sides (refer to Operation Sheet No. 2.2-4 and 2.3-2 regarding the fabrication of formworks)
3. Set the form bottom. The width of the soffit is based on the drawing, exactly like that of the member being formed on the column form, and its length equal to 3 feet (36 inches)
4. Nail the beam-form bottom, flushed with the column form opening.
5. Nail sheathing sides so that they overlap the bottom piece of the form.
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 36 of 38Developed by:Glenn F.
SalandananRevision # ____
6. Cut and install the temporary spreaders as stated in the specifications. Install the temporary spreaders by using 2-inch nails.
7. Install the shoring so that the beam form remains level. Use a large quantity of shoring to offset the downward hydrostatic pressure placed on the form bottom.
Assessment Method:PortfolioDemonstration
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 37 of 38Developed by:Glenn F.
SalandananRevision # ____
PERFORMANCE CRITERIA CHECKLISTOPERATION SHEET NO. 3.3.1b
Name of Trainee:_____________________________ Date: __________________
CRITERIACRITERIA YESYES NONO
1. Did I secure the formworks using braces for stability?
2. Did I always check/recheck the squareness, measurement, levelness and plumbness of installed formwork components?
3. Did I install the shoring so that the beam form remains level?
4. Did I use proper and correct personal protective equipment when working in installing formworks?
JZGMSATQA
SYSTEM
Carpentry NC IIINSTALLING FORMWORK
COMPONENTS
Date Developed:Aug. 1, 2011
Document No. Issued by:
Page 38 of 38Developed by:Glenn F.
SalandananRevision # ____