Casestudy Lighting

Embed Size (px)

Citation preview

  • 7/29/2019 Casestudy Lighting

    1/19

    CASE STUDYLighting Commercial

    Alison HughesPresented by Denis van Es

    Energy Research Centre

    University of Cape Town

  • 7/29/2019 Casestudy Lighting

    2/19

    OverviewExamples of current projects

    Problems encounteredDiscussion

  • 7/29/2019 Casestudy Lighting

    3/19

    ERC have M&Vd 10 Commercial lighting projectsCommercial offices / retail outlets

    offices : 120 Plein Street (Parliamentbuildings, Cape Town)

    target = 0.46 MWretail : Supermarket chain

    target = 1.358 MW

  • 7/29/2019 Casestudy Lighting

    4/19

    Lighting projects are largely energy efficiency, theyreduce demand whenever the lights are on

    but

    they can alter the hours of operation of the lights

    NONE of our DSM projects alter the hours of use

    Energy efficiency projects have a target MW reduction indemand but no specific peak reduction target

  • 7/29/2019 Casestudy Lighting

    5/19

    Lighting projects can be either a retrofit or installation of asavings device

    Retrofit - magnetic to electronic ballast

    change of luminaire typereduction in the number of fittings

    Savings device - connected in circuitalter the lighting hourslower the power drawn by the fittings

    On completion lighting must comply with OccupationalHealth and Safety Act ( www.acts.co.za )

  • 7/29/2019 Casestudy Lighting

    6/19

    Voltage Reduction Unit

    Installed in a range of stores in mallsthroughout South Africa (158 stores)

    Unit connected into lighting circuit

    Lowers voltage and therefore also theenergy demand of lamps

    Only works with magnetic ballasts

    Energy saving of roughly 30%

    Lowers light outputNo change in the hours of use or thenumber of lights

    Examples

  • 7/29/2019 Casestudy Lighting

    7/19

    National Supermarket Chain98 stores throughout thecountry participating(Approximately 46 000 Lightfittings)

    Replacing magnetic withelectronic ballasts

    No change in the hours of useor the number or type of lights

    Anticipate 20 percent savings

  • 7/29/2019 Casestudy Lighting

    8/19

    M&V of lighting projectsScoping document

    Site visit to confirm

    Lights currently in place

    Current maintenance of lights

    Light levels

    M&V Plan

    There may be a large number of sites and often they arewidespread,

    do you need to visit all or can you use a sample?

    If there are a large number of sites, it may take a long

    time to collect the tariff information

  • 7/29/2019 Casestudy Lighting

    9/19

    Baseline and post interventionsite visits

    Typically meters are not installed on site asonly instantaneous measurements are

    neededApproach differs depending on whether thereis a single or multiple sites

    ANDwhether it is a retrofit or installation of asavings device

  • 7/29/2019 Casestudy Lighting

    10/19

    Determining the baseline wherepower saving devices are installed

    If there are several sites determine the numberof sites to visit

    Is it possible to establish an average e.g.average power saved for each deviceinstalled

    It may be possible to measure the baseline and

    post intervention measurements during thesame site visit

    Monitoring of light levels is very important with

    these devices

  • 7/29/2019 Casestudy Lighting

    11/19

    Determining the baseline wherethere is a retrofitIf there are multiple sites determine the number of sites at which

    you need to take measurements to get a representative sampleOn site

    Count the number of lights of each type

    It often helps to have a site plan handy

    Determine the average number of lights not working (inmost commercial sites lights are well maintained)

    Measure selected circuits

    Establish current hours of operation

    If it is a retail store, lights often remain on outside ofnormal store trading hours

    Light levels in the stores

  • 7/29/2019 Casestudy Lighting

    12/19

    RMS meter (portable)Volts, amperes, power factor, power

    Important to match current clamp to loadRecord

    the DB number,

    The circuit number you are measuring,

    the number and type of lights on the circuit,

    the number of lights not working on the circuit

    Metered data is used to establish the average

    W/fitting of each type of light on siteIt may not be possible to isolate circuits of a particulartype of fitting on site

    Lux measurements

    Metered Data

  • 7/29/2019 Casestudy Lighting

    13/19

    Example of baseline measurements takenat National Supermarket Chain

    80

    90

    100

    110

    120

    130

    140

    150

    200 205 210 215 220 225 230 235 240 245

    Volts

    Watts

  • 7/29/2019 Casestudy Lighting

    14/19

    Example of measurements taken at UCT

    50

    70

    90

    110

    130

    150170

    200 210 220 230 240

    volts

    Watts

    Low loss magnetic

    Low power factor

    Electronic

    Electronic

  • 7/29/2019 Casestudy Lighting

    15/19

    Savings CalculationsLights are either on or off

    On = saving

    Off = no saving

    Establish tariff municipal or ESKOMMunicipal revised in July

    ESKOM revised in January

    Baseline and Post implementationDemand = Number of lights* watts per fitting

    Energy = demand1 * number of hours1 + demand (afterhours) 2*number of hours2

    (this calculation is performed for weekdays, Saturdays,Sundays and Public holidays)

  • 7/29/2019 Casestudy Lighting

    16/19

    Typical Monthly Savings Sheet

    Hours

    per

    mnth Savings Savings Tariff

    kW

    savings Savings TariffSavings

    kVA

    Total

    Savings

    days

    hrs/

    day days

    hrs/

    day days

    hrs/

    day days

    hrs/

    day days

    hrs/

    day hrs (W) (kWh)

    R/

    kWh (R) kVAR/

    kVA (R) (R)

    Store A 19 9.5 4 6 3 5 3 4 1 5 236.5 3820 903.4 0.31 280.06 4.39 0 0 280.06

    Store B 19 10 4 9.15 3 4.5 3 4.5 1 4 257.6 1040 267.9 0.27 72.33 1.45 0 0 72.33

    Store C 19 10 4 10 3 5 3 5 1 4 264.0 1880 496.3 0.29 143.93 2.39 0 0 143.93

    Store D 19 9.75 4 9.5 3 5 3 5 1 4 257.3 1100 283.0 0.31 87.72 1.56 0 0 87.72

    Total 1950.6 R 584.05

    Sunday

    Pub

    HolidayWeekday Saturday Sunday

    Weekday

    Pub

    Holiday

  • 7/29/2019 Casestudy Lighting

    17/19

    Example of baseline and actualdemand profile

    0

    100

    200

    300

    400

    500

    600

    5 7 9 11 13 15 17 19 21

    Hours (5:00am - 21:00)

    kW

    weekday baseline

    weekday post

    intervention

    Saturday baseline

    Saturday post

    intervention

    Sunday

    Baseline

    Sunday post intervention

  • 7/29/2019 Casestudy Lighting

    18/19

    Problems EncounteredWhat is the baseline if many fittings are defective

    What is the baseline if power reduction units are alreadyin place

    Tariffs hard to obtain

    Retail retrofits may have a long installation period(years), in this case do you begin with savings reportsbefore the installation is completed

    If there is a long delay between the proposal by theESCo and the project approval, sites may have changedor been upgraded

  • 7/29/2019 Casestudy Lighting

    19/19

    Can you use manufacturers data

    Data is not collected in NMEC friendly format, there isno half hourly metered data

    If the intervention causes the light levels to drop,where is the cut off

    Savings do not occur over 24 hours and often do notcoincide with peak