20
Done by : 1 - Abdul-Azez Saeed Hafedh 430106898 2 - Abdulmajeed Mohammed Ba-Gunaid 430104658 3 - Ahmed Saeed Basager 430107147 4 - Ahmed Omer Bin-Madhi 430107597 CAPITAL BUDGETING

Capital budgeting

  • Upload
    tyanne

  • View
    17

  • Download
    0

Embed Size (px)

DESCRIPTION

Capital budgeting. Done by : 1- Abdul- A zez Saeed Hafedh 430106898 2- Abdulmajeed Mohammed Ba- Gunaid 430104658 3- Ahmed Saeed Basager 430107147 - PowerPoint PPT Presentation

Citation preview

Page 1: Capital budgeting

Done by:

1 -Abdul-Azez Saeed Hafedh 430106898

2 -Abdulmajeed Mohammed Ba-Gunaid 430104658

3 -Ahmed Saeed Basager 430107147

4 -Ahmed Omer Bin-Madhi 430107597

CAPITAL BUDGETING

Page 2: Capital budgeting

* Capital Budgeting is the process of determining which real investment projects should be accepted and given an

allocation of funds from the firm.

• *Capital budgeting is the process of analyzing additions to • fixed assets .

• *Capital budgeting is important because, more than anything else, fixed asset investment decisions chart a

company's • course for the future .

WHAT IS CAPITAL BUDGETING

Page 3: Capital budgeting

Independent: -- A project whose acceptance (or rejection) does not prevent the acceptance of other projects under consideration.

   Dependent:-- A project whose acceptance depends on the acceptance of one or more other projects.

   Mutually exclusive: -- A project whose acceptance precludes the acceptance of one

or more alternative projects .

KINDS OF PROJECTS THAT CAPITAL BUDGETING RANKS

Page 4: Capital budgeting

Net present value(NPV)

It is the present value of an investment project’s net cash flows minus the project’s initial cash outflow .  

NPV Equation: CF1 CF2 CFn (  1+k)1 (1+k)2 (1+k)n

NPV (L)= 18.79NPV (s)= 19.98

Page 5: Capital budgeting

Rational behind NPV method:

NPV = PV inflows – Cost

This is net gain in wealth, so accept project if NPV > 0.

Choose between mutually exclusive projects on basis of higher positive NPV. Adds most value.

Page 6: Capital budgeting

Questions about NPV

1 -which franchise or franchises should be accepted if they are independent ,

dependent or Mutually exclusive?

2 -Would the NPVs change if the cost of capital changed?

Page 7: Capital budgeting

Define the term Internal Rate Of Return (IRR)? and What is each franchise's IRR?

The internal rate of return (IRR) is that discount rate which forces the NPV of a project to equal zero

Franchise L's IRR is 18.1%

franchise S, IRRS is 23.6%

Page 8: Capital budgeting

How is the IRR on a project related to the YTM on a bond?

The IRR is to a capital project what the YTM is to a bond .

It is the expected rate of return on the project, just as the YTM is the promised

rate of return on a bond.

Page 9: Capital budgeting

What is the logic behind the IRR method? According to IRR, which franchises should be accepted if they are independent? Mutually exclusive?

IRR measures a project's profitability in the rate of return sense: if a project's IRR equals its cost of capital, then its cash flows are just sufficient to provide investors with their required rates of return. An IRR greater than r implies an economic profit, which accrues to the firm's shareholders, while an IRR less than r indicates an economic loss, or a project that will not earn enough to cover its cost of capital.Projects' IRRs are compared to their costs of capital, or hurdle rates. Since franchises L and S both have a hurdle rate of 10 percent, and since both have IRRs greater than that hurdle rate, both should be accepted if they are independent. However, if they are mutually exclusive, franchise S would be selected, because it has the higher IRR

Page 10: Capital budgeting

Would the franchises' IRRs change if the cost of capital changed?

IRRs are independent of the cost of capital. Therefore, neither IRRS nor IRRL would change if r changed. However, the acceptability of the franchises could change--L would be rejected if r were above 18.1%, and S would also be rejected if r were above 23.6%.

Page 11: Capital budgeting

Which franchise or franchises should be accepted if they are independent? Mutually exclusive? Explain

If projects are independent, the two methods always lead to the same accept/reject decisions.

If projects are mutually exclusive If k > crossover point, the two methods lead to the same decision and there is no conflict.

If k < crossover point, the two methods lead to different accept/reject decisions.

Page 12: Capital budgeting

What is the underlying cause of ranking conflicts between NPV and IRR?

When you are analyzing a single conventional project, both NPV and IRR will provide you the same indicator about whether to accept the project or not. However, when comparing two projects, the NPV and IRR may provide conflicting results. It may be so that one project has higher NPV while the other has a higher IRR. This difference could occur because of the different cash flow patterns in the two projects.

Page 13: Capital budgeting

The following example illustrates this point

Page 14: Capital budgeting

What is the "reinvestment rate assumption”, and how does it affect the NPV versus IRR conflict?

NPV method assumes CFs are reinvested at k, the opportunity cost of capital.

IRR method assumes CFs are reinvested at IRR.

Assuming CFs are reinvested at the opportunity cost of capital is more realistic, so NPV method is the best. NPV method should be used to choose between mutually exclusive projects.

Page 15: Capital budgeting

Which method is the best? Why?

Whether NPV or IRR gives better rankings depends on which has the better reinvestment rate assumption. Normally, the NPV's assumption is better.

,because IRR does not account for

changing discount rates, so it's just not enough for longer-term projects with discount rates that are expected to vary.

Page 16: Capital budgeting

Definition of 'Modified Internal Rate Of Return - MIRR' ? find the MIRR for franchise L

and S? MIRR is that discount rate which equates the

present value of the terminal value of the inflows, compounded at the cost of capital, to the present value of the costs.

MIRRL = 16.5%. We could calculate MIRRS similarly: = 16.9%. Thus, franchise S is ranked higher than L. This result is consistent with the NPV decision.

Page 17: Capital budgeting

What are the MIRR's advantages and disadvantages vis-a-vis the regular IRR? What are the MIRR's advantages and disadvantages vis-a-vis the NPV?

MIRR is a better rate of return measure than IRR for two reasons:

(1) it correctly assumes reinvestment at the project's cost of capital rather than at its IRR.

(2) MIRR avoids the problem of multiple IRRs--there can be only one MIRR for a given project

Page 18: Capital budgeting

MIRR does not always lead to the same decision as NPV when mutually exclusive projects are being considered. In particular, small projects often have a higher MIRR, but a lower NPV, than larger projects. Thus, MIRR is not a perfect substitute for NPV, and NPV remains the single best decision rule. However, MIRR is superior to the regular IRR, and if a rate of return measure is needed, MIRR should be used

Page 19: Capital budgeting

What does Profitability Index (PI) measure ? what are the PIs of franchise L and S ?

An index that attempts to identify the relationship between the costs and benefits of a proposed project through the use of a ratio calculated as:

Page 20: Capital budgeting

A ratio of 1.0 is logically the lowest acceptable measure on the index. Any value lower than 1.0 would indicate that the project's PV is less than the initial investment. As values on the profitability index increase, so does the financial attractiveness of the proposed project.

PIs of franchise L and S :For L = 1.19For S = 1.2