22
CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN CONNECTION WITH THE APPROVAL OF THE OUTPATIENT PAVILION PROJECT AT THE UNIVERSITY OF CALIFORNIA, SAN DIEGO I. CERTIFICATION OF THE FINAL ENVIRONMENTAL IMPACT REPORT The University of California (University), as the lead agency pursuant to the California Environmental Quality Act (CEQA), has prepared a Final Environmental Impact Report (Final EIR) for the Outpatient Pavilion (OPP) Project (Project). This Project will be developed at the University of California, San Diego (UC San Diego). The Board of Regents of the University of California (The Regents) hereby issues these Findings and concurrently approves the Project. The proposed OPP Project consists of a four level facility that would house hospital- licensed services to support the existing Thornton Hospital and Jacobs Medical Center. The overall limits of work for the proposed project encompass approximately 4.1 acres. This project site includes the project development area and the construction staging area. The project site is currently developed with a 169,884 SF surface parking lot (Campus Lot P-751). The proposed project will remove approximately 156 parking spaces, leaving Campus Lot P-751 with approximately 179 parking spaces. The four level (three-story with a basement), approximately 75-foot tall OPP would include approximately 156,000 gross square feet (GSF) of new construction, including operating rooms, outpatient care bays, clinical facilities, patient intake facilities, staff support spaces, and mechanical/electrical facilities. The proposed OPP would provide pain management, urology, orthopedics, spine, sports medicine, breast, and stem cell clinics. In addition, the proposed project would provide outpatient, orthopedic and breast imaging, as well as rehabilitation facilities. In accordance with the UC San Diego standard for all new construction and major renovation projects on campus, the OPP building would be a high- performance, energy efficient facility that would achieve a Leadership in Energy and Environmental Design (LEED) “Silver” certification or higher. The key objectives of the OPP Project are focused on advancing the UC San Diego Medical Center goals established in the 2004 Long Range Development Plan (LRDP), as related to constructing new facilities to consolidate clinical research activities around certain specialty areas and to facilitate the translation of laboratory discoveries into improved diagnosis and treatment capabilities. Such objectives include developing a medical facility that would house hospital-licensed services to support the existing Thornton Hospital and Jacobs Medical Center by housing disease-specific centers and consolidating all outpatient, ancillary, professional and support services to improve outpatient care delivery. The Final EIR has been assigned State Clearinghouse (“SCH”) Number 2014061078. The Final EIR consists of one volume. The Final EIR contains an Introduction with Errata, responses to comments, the Mitigation Monitoring and Reporting Program, the revised Draft EIR with ATTACHMENT 7

CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN ...regents.universityofcalifornia.edu/regmeet/july15/gb8attach7.pdf · 2010, replaced the UC San Diego 2004 LRDP EIR as the basis

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN ...regents.universityofcalifornia.edu/regmeet/july15/gb8attach7.pdf · 2010, replaced the UC San Diego 2004 LRDP EIR as the basis

CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS

IN CONNECTION WITH THE APPROVAL

OF THE OUTPATIENT PAVILION PROJECT AT THE

UNIVERSITY OF CALIFORNIA, SAN DIEGO

I. CERTIFICATION OF THE FINAL ENVIRONMENTAL IMPACT REPORT

The University of California (University), as the lead agency pursuant to the California

Environmental Quality Act (CEQA), has prepared a Final Environmental Impact Report (Final

EIR) for the Outpatient Pavilion (OPP) Project (Project). This Project will be developed at the

University of California, San Diego (UC San Diego). The Board of Regents of the University of

California (The Regents) hereby issues these Findings and concurrently approves the Project.

The proposed OPP Project consists of a four level facility that would house hospital-

licensed services to support the existing Thornton Hospital and Jacobs Medical Center. The

overall limits of work for the proposed project encompass approximately 4.1 acres. This project

site includes the project development area and the construction staging area. The project site is

currently developed with a 169,884 SF surface parking lot (Campus Lot P-751). The proposed

project will remove approximately 156 parking spaces, leaving Campus Lot P-751 with

approximately 179 parking spaces. The four level (three-story with a basement), approximately

75-foot tall OPP would include approximately 156,000 gross square feet (GSF) of new

construction, including operating rooms, outpatient care bays, clinical facilities, patient intake

facilities, staff support spaces, and mechanical/electrical facilities. The proposed OPP would

provide pain management, urology, orthopedics, spine, sports medicine, breast, and stem cell

clinics. In addition, the proposed project would provide outpatient, orthopedic and breast

imaging, as well as rehabilitation facilities. In accordance with the UC San Diego standard for all

new construction and major renovation projects on campus, the OPP building would be a high-

performance, energy efficient facility that would achieve a Leadership in Energy and

Environmental Design (LEED) “Silver” certification or higher.

The key objectives of the OPP Project are focused on advancing the UC San Diego

Medical Center goals established in the 2004 Long Range Development Plan (LRDP), as related

to constructing new facilities to consolidate clinical research activities around certain specialty

areas and to facilitate the translation of laboratory discoveries into improved diagnosis and

treatment capabilities. Such objectives include developing a medical facility that would house

hospital-licensed services to support the existing Thornton Hospital and Jacobs Medical Center

by housing disease-specific centers and consolidating all outpatient, ancillary, professional and

support services to improve outpatient care delivery.

The Final EIR has been assigned State Clearinghouse (“SCH”) Number 2014061078. The

Final EIR consists of one volume. The Final EIR contains an Introduction with Errata, responses

to comments, the Mitigation Monitoring and Reporting Program, the revised Draft EIR with

ATTACHMENT 7

Page 2: CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN ...regents.universityofcalifornia.edu/regmeet/july15/gb8attach7.pdf · 2010, replaced the UC San Diego 2004 LRDP EIR as the basis

errata shown in strike out / underline format, and EIR appendices. The Final EIR assesses the

potential environmental effects of implementation of the OPP Project, identifies the means to

eliminate or reduce potentially significant adverse impacts, and evaluates a reasonable range of

alternatives to the Project. The Final EIR also responds to comments on the Draft EIR, explains

changes made to the text of the Draft EIR, and includes a Mitigation Monitoring and Reporting

Program that outlines the substance and timing of mitigation measures required for the Project.

Pursuant to Public Resources Code section 21081 and CEQA Guidelines section 15090,

the Regents certifies that it completed the following activities prior to approving the OPP

Project: the Regents has received the Final EIR; the Regents has reviewed and considered the

information contained in the Final EIR and received through public comments; and the Regents

has considered all additional written and oral statements received prior to or at its public hearing

on the Final EIR and on the OPP Project. The Regents additionally certifies that the Final EIR

was completed in compliance with CEQA and that the Final EIR reflects the University’s

independent judgment and analysis. The conclusions presented in these Findings are based on the

Final EIR and other evidence in the administrative record.

The Regents certifies that this Final EIR properly tiers from the certified Program EIR

prepared for the UC San Diego 2004 LRDP EIR SCH No. 2003081023; and the certified EIR

prepared for the East Campus Bed Tower EIR (2010 ECBT EIR), SCH No. 2009081053,

pursuant to Public Resources Code sections 21068.5 and 21093 and CEQA Guidelines sections

15152 and 15385, and complies with all relevant requirements for tiered CEQA documents. The

UC San Diego 2004 LRDP EIR analyzed the 2004 LRDP for the UC San Diego campus, as later

amended by the 2010 ECBT EIR. Technical analyses presented in the 2010 ECBT EIR updated

the long-term traffic and cumulative construction emissions (air quality) analyses presented in

the UC San Diego 2004 LRDP EIR. As a result, the 2010 ECBT EIR, which was certified in July

2010, replaced the UC San Diego 2004 LRDP EIR as the basis of long-term traffic and

cumulative construction emissions analyses for all future campus projects proposed under the

2004 LRDP.

The OPP Project is consistent with and fits within the scope of development considered

in the UC San Diego 2004 LRDP EIR and the 2010 ECBT EIR. The Final EIR certified here

considers all additional, relevant information that has become available since the University’s

certification of the UC San Diego 2004 LRDP EIR and the 2010 ECBT EIR; examines the

project-specific impacts of the OPP Project, including all impacts that either were not examined

as significant impacts in the UC San Diego 2004 LRDP EIR and the 2010 ECBT EIR or are

susceptible to substantial reduction or avoidance; and imposes all feasible and applicable

mitigation measures to reduce potentially significant environmental impacts. The UC San Diego

2004 LRDP EIR and the 2010 ECBT EIR, from which this Final EIR tiers, is available for

review at http://physicalplanning.ucsd.edu/environmental/lrdpeir.html and at UC San Diego

Physical and Community Planning, Torrey Pines Center South, 10280 North Torrey Pines Road,

Suite 355, La Jolla, California 92037-1032, (858) 534-3860.

Page 3: CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN ...regents.universityofcalifornia.edu/regmeet/july15/gb8attach7.pdf · 2010, replaced the UC San Diego 2004 LRDP EIR as the basis

II. FINDINGS

Having received, reviewed, and considered the Final EIR and other information in the

administrative record, The Regents hereby adopts the following Findings and Statement of

Overriding Considerations for the OPP Project in compliance with CEQA, the CEQA

Guidelines, and the University’s procedures for implementing CEQA. The Regents adopts these

Findings and Statement of Overriding Considerations in conjunction with its approval of the

OPP Project, as set forth in Section III, below.

A. ENVIRONMENTAL REVIEW PROCESS

1. CEQA Process and Preparation of the EIR

On June 24, 2014, the University released a Notice of Preparation (NOP) announcing the

preparation of the Draft EIR which described the proposed OPP Project and the scope of the

Draft EIR.

The University issued the Draft EIR for the OPP Project on April 15, 2015 and circulated

it for public review and comment for a 45-day period ending on June 1, 2015. Three comment

letters on the Draft EIR were received from various federal, state, and local agencies. One

member of the public provided comments at the May 20, 2015 public hearing on the draft EIR.

The Final EIR contains all of the comment letters received during the public comment

period. The Final EIR also contains responses to those comments, which the University prepared

in accordance with CEQA, the CEQA Guidelines, and the University’s procedures for

implementing CEQA. The Regents has reviewed the comments received and the responses

thereto and finds that the Final EIR provides adequate, good faith, and reasoned responses to

those comments.

2. Absence of Significant New Information

CEQA Guidelines section 15088.5 requires that a lead agency recirculate an EIR for

additional review and comment when significant new information is added to the EIR after the

public comment period but before certification. Such information can include changes in the

project or environmental setting, but that information is not significant unless the EIR is changed

in a manner that deprives the public of a meaningful opportunity to comment upon a substantial

adverse environmental effect of the project or a feasible way to mitigate or avoid such an effect

that the project’s proponent declines to implement.

The Regents finds that no significant new information was added to the Draft EIR after

the public review period. The Regents specifically finds that: no new significant environmental

impact would result from the OPP Project or from the implementation of a mitigation measure;

no substantial increase in severity of an environmental impact would result, or if such an increase

would result, the University has adopted mitigation measures to reduce the impact to a level of

Page 4: CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN ...regents.universityofcalifornia.edu/regmeet/july15/gb8attach7.pdf · 2010, replaced the UC San Diego 2004 LRDP EIR as the basis

insignificance; the University has not declined to adopt any feasible project alternative or

mitigation measures considerably different from others previously analyzed that would clearly

lessen the environmental impacts of the OPP Project; and the Draft EIR is not so fundamentally

and basically inadequate in nature that it precluded meaningful public review.

Having reviewed the information in the Draft EIR, Final EIR, and administrative record,

The Regents finds that no new significant information was added to the EIR following public

review, and recirculation of the EIR is therefore unnecessary and not required by CEQA.

B. IMPACTS AND MITIGATION MEASURES

As required by CEQA and the CEQA Guidelines, the following section summarizes the

environmental impacts of the Project identified in the Final EIR and includes The Regent’s

Findings regarding those impacts and any mitigation measures set forth in the Final EIR, adopted

by The Regents, and incorporated as requirements of the Project. These Findings summarize the

determinations of the Final EIR with respect to the Project’s impacts before and after mitigation

and do not attempt to describe the full analysis of each environmental impact considered in the

Final EIR. Instead, the Findings provide a summary of each impact, describe the applicable

mitigation measures identified in the Final EIR and adopted by The Regents, and state The

Regent’s Findings regarding the significance of each impact with the adopted mitigation

measures. The Final EIR contains a full explanation of each impact, mitigation measure, and the

analysis that led the University to its conclusions on those impacts. These Findings hereby

incorporate by reference the discussion and analysis in the Final EIR, which support the Final

EIR’s determinations regarding the Project’s environmental impacts and mitigation measures. In

making these Findings, The Regents ratifies, adopts, and incorporates by reference the Final

EIR’s analysis, determinations, and conclusions relating to environmental impacts and mitigation

measures, except to the extent that any such determinations and conclusions are specifically and

expressly modified by these Findings.

In adopting the mitigation measures described below, The Regents intends to adopt each

of the mitigation measures recommended in the Final EIR. Accordingly, in the event that a

mitigation measure recommended in the Final EIR has been inadvertently omitted from these

Findings, that mitigation measure is hereby adopted and incorporated by reference in the

Findings. Additionally, in the event that the description of mitigation measures set forth below

fails accurately to capture the substance of a given mitigation measure due to a clerical error (as

distinct from specific and express modification by The Regents through these Findings), the

language of the mitigation measure as set forth in the Final EIR shall govern.

With respect to mitigation measures that were suggested in comments by the public or

other public agencies but not included in the Final EIR, the responses to comments explain that

the suggested mitigation measures either are already part of the OPP Project and associated

CEQA documentation or are infeasible or ineffectual and thus not recommended for adoption for

the reasons outlined in the responses to comments. The Regents hereby adopts and incorporates

Page 5: CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN ...regents.universityofcalifornia.edu/regmeet/july15/gb8attach7.pdf · 2010, replaced the UC San Diego 2004 LRDP EIR as the basis

by reference the reasons stated in the responses to comments as the basis for finding these

suggested mitigation measures unnecessary or inappropriate for inclusion as Project

requirements.

1. Environmental Resource Areas with No Impacts as a Result of the Project

The Final EIR determined that the OPP Project would cause no impacts in the following

environmental resource areas, and no mitigation is proposed for these impacts: impacts to

aesthetics (see Draft EIR pages 4-3 through 4-4; damage scenic resources); impacts to

agricultural resources (see Draft EIR pages 4-14 through 4-15; all impacts); impacts to biological

resources (see Draft EIR pages 4-15 through 4-16; impacts affecting federally protected

wetlands; impacts affecting the movement of any native resident, migratory fish or wildlife

species; impacts affecting any local policies or ordinances protecting biological resources;

impacts affecting the provisions of an adopted Habitat Conservation Plan, Natural Community

Plan or other approved conservation plan); impacts to cultural resources (see Draft EIR pages 4-

16 through 4-17; all impacts); impacts to hazards and hazardous materials (see Draft EIR page 4-

9; result in airport safety hazard); impacts to land use and planning (see Draft EIR pages 4-21

through 4-23; result in land use incompatibilities; conflict with any applicable habitat

conservation plan or natural community conservation plan); impacts to mineral resources (see

Draft EIR page 4-23; all impacts); impacts to population and housing (see Draft EIR pages 4-24

through 4-25; displace substantial numbers of existing housing or people); impacts to recreation

(see Draft EIR page 4-25; include recreation facilities or require the construction or expansion of

recreational facilities); impacts to transportation and traffic (see Draft EIR pages 3-89; impacts

affecting air traffic patterns); and impacts to utilities, service systems and energy (see Draft EIR

pages 4-25 through 4-30; exceed wastewater treatment requirements; adequate wastewater

capacity; require or result in the construction of new water or wastewater treatment facilities or

expansion of existing facilities; create other utility and service systems impacts).

FINDING: The Regents finds that the Project would have no impacts to the

environmental resource areas listed above. Therefore, no mitigation is proposed or

required.

2. Less-Than-Significant Impacts for Which No Mitigation Is Required

The Final EIR found that the following impacts from the implementation of the OPP

Project would be less than significant without mitigation, and no mitigation is proposed for these

impacts: impacts to aesthetics (see Draft EIR pages 4-3 through 4-4; adverse effect on a scenic

vista; degrade the existing visual character); impacts to air quality (see Draft EIR pages 3-13

through 3-19; exceedance of air quality standards and exposure of sensitive receptors to pollutant

concentrations); impacts to biological resources (see Draft EIR pages 4-15; impacts to species

identified as candidate, sensitive, or special status; impacts affecting any riparian habitat or other

sensitive natural community); impacts to geology and soils (see Draft EIR pages 4-19 through 4-

21; all impacts); impacts to global climate change (see Draft EIR pages 3-110 through 3-118; all

Page 6: CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN ...regents.universityofcalifornia.edu/regmeet/july15/gb8attach7.pdf · 2010, replaced the UC San Diego 2004 LRDP EIR as the basis

impacts); impacts to hazards and hazardous materials (see Draft EIR pages 4-4 through 4-10;

transport, use, or disposal of hazardous materials; release of hazardous materials; emit or handle

hazardous materials near a school; create wildland fire risk); impacts to hydrology and water

quality (see Draft EIR pages 3-32 through 3-34; direct alteration of existing drainage or

hydrology); impacts to land use and planning (see Draft EIR pages 4-21 through 4-23; conflict

with any land use plan, policy, or regulation); impacts from noise (see Draft EIR pages 4-10

through 4-12; expose sensitive receptors to excessive noise levels; increase ambient noise levels;

impacts to population and housing (see Draft EIR pages 4-24 through 4-25;directly or indirectly

induce substantial population growth); impacts to public services (see Draft EIR pages 3-56

through 3-58; impacts to fire protection and emergency services); impacts to recreation (see

Draft EIR page 4-25; increase the use of existing parks or recreational facilities); impacts to

transportation and traffic (see Draft EIR pages 3-78 through 3-88; direct conflict with circulation

plans, direct conflict with alternative circulation plans); and impacts to utilities, service systems

and energy (see Draft EIR pages 4-25 through 4-30; require or result in the construction of new

storm water drainage facilities or expansion of existing facilities; sufficient water supplies

available; served by a landfill with sufficient capacity; comply with applicable solid waste

regulations).

FINDING: The Regents finds that all of the aforementioned environmental impacts

would be less than significant without mitigation. Therefore, no mitigation is proposed or

required.

3. Potentially Significant Impacts Reduced to Less-Than-Significant Impacts

Through the Incorporation of Mitigation Measures

Pursuant to Public Resources Code section 21081(a)(1) and CEQA Guidelines section

15091(a)(1), the following potentially significant impacts identified in the Final EIR will be

reduced to less-than-significant impacts through the implementation of the mitigation measures

hereby incorporated into the Project.

i. Aesthetics

OPP Impact: The proposed Project could create a substantial new source of lighting that

could adversely affect nighttime views in the Project area. (Draft EIR pages 4-4 through

4-5.)

LRDP Aes-2B: If a proposed project includes outdoor lighting, lighting plans shall be

reviewed during the project planning process to ensure that the UC San Diego Outdoor

Lighting Policy and the UC San Diego Outdoor Lighting Design Guidelines or equivalent

measures have been applied in the lighting plan so that:

Direct lighting is shielded from residential areas, sensitive biological habitat, and

other light sensitive receptors;

Page 7: CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN ...regents.universityofcalifornia.edu/regmeet/july15/gb8attach7.pdf · 2010, replaced the UC San Diego 2004 LRDP EIR as the basis

Lighting is directed to the specific location intended for illumination (e.g., roads,

walkways, or recreation fields);

Non-essential lighting and stray light spillover is minimized; and

Low intensity lamps are used except when high intensity illumination is required,

such as for a recreational field.

ii. Hazards and Hazardous Materials

OPP Impact: Munitions and explosives of concern (i.e., lead and arsenic) and munitions

debris associated with historic small arms training at Camp Matthews, as well as

contamination from diesel fuel, could be encountered during construction of the proposed

OPP Project. (Draft EIR pages 4-5 through 4-10).

LRDP Haz-4A: During project planning, EH&S Environmental Affairs shall be

consulted in order to identify if any past contamination, underground storage tanks

(USTs), aboveground storage tanks (ASTs), or other contamination could potentially

occur in areas to be impacted. EH&S Environmental Affairs will consider the cases on

file at the County Department of Environmental Health (DEH), the list of Camp

Matthews tanks (Table 4.6-5), the historic burn ash site (see Figure 4.6-1), and

information on historic uses in the area to be impacted such as old maps and photos. If

EH&S Environmental Affairs determines that there is limited potential for contamination

to occur on site, no additional mitigation is necessary. If it is determined that

contamination has potential to exist on a project site, Haz-4B shall be implemented.

LRDP Haz-4B: If contamination exists on a proposed project site and if it poses a risk to

human health or the environment, actions shall be taken prior to any construction,

pursuant to applicable regulations, to remove or otherwise remediate the contamination

through appropriate measures such as natural attenuation, active remediation, and

engineering controls. Assessment and remediation activities shall incorporate the

following conditions:

i. All assessment and remediation activities shall be conducted in accordance with a

work plan which is approved by the regulatory agency having oversight of the

activities.

ii. It may be necessary to excavate existing soil within the project site, or to bring fill

soils into the site from off-site locations. At sites that have been identified as being

contaminated or where soil contamination is suspected, appropriate sampling is

required prior to disposal of excavated soil. Contaminated soil shall be properly

disposed at an approved off-site facility. Fill soils also shall be sampled to ensure

that imported soil parameters are within acceptable levels.

Page 8: CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN ...regents.universityofcalifornia.edu/regmeet/july15/gb8attach7.pdf · 2010, replaced the UC San Diego 2004 LRDP EIR as the basis

iii. Caution shall be taken during excavation activities near existing groundwater

monitoring wells, so that they are not damaged. Existing groundwater monitoring

wells may have to be abandoned and reinstalled if they are located in an area that is

undergoing redevelopment.

LRDP Haz-4C: In the event that USTs, not identified in consultation with EH&S, or

undocumented areas of contamination are encountered during construction or

redevelopment activities, work shall be discontinued until appropriate health and safety

procedures are implemented. Either the San Diego County Department of Environmental

Health (DEH) or the RWQCB, depending on the nature of the contamination, must be

notified regarding the contamination. Each agency and program within the respective

agency has its own mechanism for initiating an investigation. The appropriate program

(e.g., the DEH Local Oversight Program for tank release cases, the DEH Voluntary

Assistance Program for non-tank release cases, the RWQCB for non-tank cases involving

groundwater contamination) will be selected based the nature of the contamination

identified. The contamination remediation and removal activities will be conducted in

accordance with pertinent regulatory guidelines, under the oversight of the appropriate

regulatory agency.

FINDING: The Regents finds that the implementation of the OPP Project would

result in potential impacts related to encountering unknown contaminated sites and

the associated release of hazardous materials (Final EIR Section 4.1). LRDP

Mitigation Measures Haz-4A Haz-4B and Haz-4C are hereby adopted and

incorporated into the Project. The Regents finds that implementation of LRDP

Mitigation Measures Haz-4A Haz-4B and Haz-4C, combined with the UC San Diego

Site Development Guidelines and Procedures that will be included with the

contractor specifications for the OPP Project, will reduce this potentially significant

impact to a less-than-significant impact and that the Project will not, therefore,

result in a significant hazard to the public or environment.

OPP Impact: The proposed Project could impair the implementation of or physically

interfere with an adopted emergency response plan or emergency evacuation plan. (Draft

EIR page 4-9).

LRDP Haz-6A: In the event that the construction of a project requires a lane or roadway

closure, prior to construction the contractor and/or Facilities Design and Construction

(FD&C) shall ensure that the UC San Diego Director of Fire and Life Safety is notified.

If determined necessary by the UC San Diego Director of Fire and Life Safety, local

emergency services will be notified of the closure by the Director of Fire and Life Safety.

FINDING: The Regents finds that the implementation of the OPP Project would

result in the potential need for temporary traffic lane closures in the Project site

Page 9: CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN ...regents.universityofcalifornia.edu/regmeet/july15/gb8attach7.pdf · 2010, replaced the UC San Diego 2004 LRDP EIR as the basis

vicinity during the construction phase (Final EIR Section 4.1). LRDP Mitigation

Measure Haz-6A is hereby adopted and incorporated into the Project. The Regents

finds that implementation of LRDP Mitigation Measures Haz-6A will reduce this

potentially significant impact to a less-than-significant impact and that the Project

will not, therefore, result in a significant hazard to the public or environment. All

other hazards impacts are less than significant and no mitigation is required (see

pages 4-5 and 4-10 of the Final EIR).

iii. Hydrology and Water Quality

OPP Impact HYD-1: Operation of the proposed OPP Project has the potential to violate

water quality standards or waste discharge requirements and degrade water quality. (Draft

EIR page 3.2-43.)

OPP MM HYD-1: The proposed Project would create and/or replace 5,000 square feet

or greater of impervious surface; therefore, a Post-Construction Storm Water

Management Checklist shall be completed prior to construction of the Project. The

checklist shall be provided to the UC San Diego project manager who will ensure the

information is uploaded to the SWRCB’s SMARTS online program. The checklist can be

found at: http://blink.ucsd.edu/safety/environment/outdoor/storm/post-construction.html

(Draft EIR page 3-43.)

FINDING: The Regents finds that the OPP Project would result in the potential for

an operational water quality impact (see Final EIR Section 3). Project-specific

Mitigation Measure HYD-1 is hereby adopted and incorporated into the Project.

The Regents finds that implementation of OPP Mitigation Measure HYD-1, as well

as compliance with all applicable storm water permits and plans and incorporation

of post-construction treatments and source control measures, will reduce this

potentially significant impact to a less than significant impact and will ensure that

violation of water quality standards or waste discharge requirements will not occur.

All other hydrology and water quality impacts are less than significant and no

mitigation is required (see pages 3-25 through 3-45 of the Final EIR).

iv. Noise

OPP Impact: Construction noise from the louder equipment used to build the OPP

Project could temporarily expose nearby receptors at the Moores Cancer Center and

Thornton Hospital to elevated noise levels (i.e., above the 75-dBA CNEL threshold from

the 2004 LRDP EIR) that could disrupt communications and routine activities. (Draft

EIR pages 4-12 through 4-13).

Page 10: CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN ...regents.universityofcalifornia.edu/regmeet/july15/gb8attach7.pdf · 2010, replaced the UC San Diego 2004 LRDP EIR as the basis

LRDP MM NOI-2A: UC San Diego shall implement the following measures to

minimize short-term noise levels caused by construction activities. Measures to reduce

construction/demolition noise to the maximum extent feasible shall be included in

contractor specifications and shall include, but not be limited to, the following:

i. The construction contractor shall be required to work in such a manner so as not

to exceed a 12-hour average sound level of 75 dBA at any noise sensitive land use

(dormitories/residential/lodging, contemplative spaces, libraries, inpatient medical

care facility [beds present], and on-campus classrooms) between 7:00 a.m. and

7:00 p.m. Monday through Saturday.

ii. Construction equipment shall be properly outfitted and maintained with

manufacturer recommended noise-reduction devices to minimize construction-

generated noise.

iii. Stationary construction noise sources such as generators or pumps shall be located

at least 100 feet from noise-sensitive land uses as feasible.

iv. Laydown and construction vehicle staging areas shall be located as far from noise

sensitive land uses as feasible.

v. All neighboring land uses that would be subject to construction noise shall be

informed at least two weeks prior to the start of each construction project,

whenever possible.

vi. Loud construction activity such as jackhammering, concrete sawing, asphalt

removal, pile driving, and large-scale grading operations occurring within 100

feet of a residential or academic building shall not be scheduled during any finals

week of classes to the extent feasible or consider adjusting the hours or days of

construction.

vi. Loud construction activity, such as jackhammering, concrete sawing, asphalt

removal, pile driving, and large-scale grading operations, occurring within 100

feet of an academic or residential use shall be scheduled during holidays, class

breaks, and/or summer session, to the extent feasible.

viii. Loud construction activity located within 100 feet of a residential building or

inpatient medical care facility shall be restricted to occur between the 10 hours of

7:00 a.m. and 7:00 p.m. Monday through Friday. (Draft EIR pages 4-10 through

4-13.)

FINDING: The Regents finds that the construction of the OPP Project would result

in temporary noise levels that would exceed the 75-dBA CNEL threshold identified

in the 2004 LRDP EIR (see Final EIR Section 4.1). The applicable provisions of

LRDP Mitigation Measure NOI-2A (provisions (i) through (v)) are hereby adopted

and incorporated into the Project. The Regents finds that implementation of the

applicable provisions of LRDP Mitigation Measure NOI-2A will reduce this

potentially significant impact to a less than significant impact and that construction

Page 11: CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN ...regents.universityofcalifornia.edu/regmeet/july15/gb8attach7.pdf · 2010, replaced the UC San Diego 2004 LRDP EIR as the basis

of the Project will not, therefore, result in temporarily elevated noise levels that

could disrupt communication and routine activities.

OPP Impact: Construction activities at the OPP Project site could cause vibrations at

adjacent properties. (Draft EIR page 4-13.)

LRDP MM NOI-4A: For major construction activity involving heavy earth moving

equipment within 200 feet, and pile driving within 600 feet, of sensitive land uses (e.g.,

vibration sensitive laboratory equipment), prior to the initiation of construction activities,

the UC San Diego Environmental Planner and the Facilities Design and Construction

department shall approve a construction vibration mitigation program developed by a

qualified person experienced in the fields of environmental noise and vibration

assessment to be implemented by the construction contractor. The construction vibration

mitigation program shall include measures to reduce vibration resulting from construction

activities to the maximum extent practicable. Notification and monitoring of construction

activities shall include, but not be limited to, the following:

i. Vibration monitoring shall be performed during construction to establish the level

of vibration produced by high impact activities. Monitoring shall be conducted

when any construction would occur within 50 feet of a vibration sensitive land use.

Monitoring shall be conducted using a portable vibration-monitoring instrument

that provides a calibrated record of local ground movement/accelerations. If

construction vibration exceeds 2.0 in/sec, alternative work methods and equipment

shall be used. Baseline vibration levels at specified locations shall be established

prior to construction.

ii. Building occupants shall be notified at least two weeks prior to the start of

construction that would occur within 50 feet of any vibration sensitive land use.

FINDING: The Regents finds that construction of the OPP Project would include

activities that have the potential to lead to vibration impacts to existing vibration-

sensitive equipment at nearby sites (see Final EIR Section 4.1). LRDP Mitigation

Measure NOI-4A is hereby adopted and incorporated into the Project. The Regents

finds that implementation of LRDP Mitigation Measure NOI-4A will reduce this

potentially significant impact to a less than significant impact and that construction

of the Project will not, therefore, result in a significant amount of vibration. All

other noise impacts are less than significant and no mitigation is required (see pages

4-10 through 4-13 of the Final EIR).

v. Public Services—Cumulative

OPP Impact FIRE-1: The proposed OPP Project would contribute considerably to

cumulative demands for fire protection services in the University City area that may

Page 12: CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN ...regents.universityofcalifornia.edu/regmeet/july15/gb8attach7.pdf · 2010, replaced the UC San Diego 2004 LRDP EIR as the basis

trigger the need for new facilities potentially resulting in adverse physical impacts. (Draft

EIR pages 3-58 through 3-60.)

OPP MM FIRE-1: The project shall pay its proportionate share of the cost of mitigating

the environmental impacts associated with the construction and operation of a new UC

San Diego-area fire station. UC San Diego's proportionate share of funding would be

determined by the percentage of new population generated by the project compared to the

additional population in the community (as defined by the 2011 Citygate study) that

could be served within five minutes by a new fire station. UC San Diego may meet its

proportional share contribution obligation by contributing either land or money or some

combination thereof.

FINDING: The Regents finds that the OPP Project would result in a considerable

contribution to cumulatively significant public services impacts related to fire

protection services (see Final EIR Section 3.3). Because no specific location has been

selected for a potential UC San Diego-area fire station, the nature and magnitude of

associated environmental impacts associated with a new fire station are unknown at

this time. OPP Mitigation Measure FIRE-1 is hereby adopted and incorporated into

the Project. The Regents finds that implementation of OPP Mitigation Measure

FIRE-1 will mitigate the Project’s contribution to this cumulatively significant

public services impact to a level that is not cumulatively considerable. All other

public services impacts are less than significant and no mitigation is required (see

pages 3.3-49 through 3.3-61 of the Final EIR).

vi. Transportation and Traffic

OPP Impact: Construction activities at the OPP Project site could potentially result in

temporary inadequate emergency access. (Draft EIR page 3-88)

LRDP MM TRA-1B: If a campus construction project or a specific campus event

requires an on-campus lane or roadway closure, or could otherwise substantially interfere

with campus traffic circulation, the contractor or other responsible party will provide a

traffic control plan for review and approval by UC San Diego. The traffic control plan

shall ensure that adequate emergency access and egress is maintained 12 and that traffic

is allowed to move efficiently and safely in and around the campus. The traffic control

plan may include measures such as signage, detours traffic control staff, a temporary

traffic signal, or other appropriate traffic controls. If the interference would occur on a

public street, UC San Diego (or its contractor) shall apply for all applicable permits from

the appropriate jurisdiction.

Page 13: CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN ...regents.universityofcalifornia.edu/regmeet/july15/gb8attach7.pdf · 2010, replaced the UC San Diego 2004 LRDP EIR as the basis

FINDING: The Regents finds that construction of the OPP Project would result in

the potential for inadequate emergency access to the Thornton Hospital Emergency

Department (see Final EIR Section 3.4). LRDP Mitigation Measure TRA-1B is

hereby adopted and incorporated into the Project. The Regents finds that

implementation of LRDP Mitigation Measure TRA-1B will reduce this potentially

significant impact to a less than significant impact and will ensure that access to the

Thornton Hospital Emergency Department would not be compromised or blocked

due to road closures during construction of the OPP Project.

OPP Impact: The project would have a direct significant impact at the Genesee Avenue /

Campus Point Drive intersection in the Near-term condition (Draft EIR pages 3-89

through 3-98)

OPP MM TRA-1: As part of the I-5 Managed Lanes / Voigt Drive Direct Access Ramps

project, Campus Point Drive at Genesee Avenue will be realigned and widened to

provide additional lanes on both the northbound and southbound approaches.

Implementation of this improvement will mitigate the Project’s impact to less than

significant.

FINDING: The Regents finds that construction of the OPP Project would result in

the potential for regional decreases in traffic level of service in the near-term

condition (see Final EIR Section 3.4). OPP Mitigation Measure TRA-1 is hereby

adopted and incorporated into the Project. The Regents finds that implementation

of OPP Mitigation Measure TRA-1 will reduce this potentially significant impact to

a less than significant impact and will ensure that regional decreases in level of

service in the near-term condition will be corrected prior to the long-term buildout

condition is reached. All other transportation and traffic impacts are less than

significant and no mitigation is required (see pages 3.63 through 3.98 of the Final

EIR).

4. Significant and Unavoidable Adverse Impacts and Related Mitigation Measures

Pursuant to Public Resources Code section 21081(b) and CEQA Guidelines section

15093, where the lead agency identifies significant adverse environmental impacts that cannot

feasibly be mitigated to a less-than-significant level, the lead agency may nonetheless approve

the project if it finds that specific economic, legal, social, technological, or other benefits of the

project outweigh the unavoidable significant environmental impacts.

While the Project would contribute only incrementally to cumulatively significant

construction emissions of ozone, PM10, and PM2.5 in the air basin, the Final EIR nonetheless

identifies a significant and unavoidable adverse environmental impact associated with

construction emissions resulting from the approval of the Project. The UC San Diego 2004

Page 14: CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN ...regents.universityofcalifornia.edu/regmeet/july15/gb8attach7.pdf · 2010, replaced the UC San Diego 2004 LRDP EIR as the basis

LRDP EIR and 2010 ECBT EIR fully analyzed this impact, including the identification and

imposition of all feasible mitigation measures that could reduce the severity of this impact. The

University has determined that these analyses adequately addressed the cumulative impact and

remain valid. For this reason and pursuant to CEQA Guidelines section 15152(f)(1), the

University was not required to analyze this impact in detail; the Final EIR, nonetheless, provides

a discussion of the cumulative impact of construction emissions of ozone, PM10, and PM2.5. For

the detailed description of this impact, please see the relevant sections of the Final EIR and

Mitigation Monitoring and Reporting Program, as well as the UC San Diego 2004 LRDP EIR

and 2010 ECBT EIR.

i. Air Quality—Cumulative

OPP Impact: The proposed OPP Project would generate cumulatively considerable

construction emissions (ozone, PM10 and PM2.5) that would result in a significant and

unavoidable air quality impact (consistency with air quality standards—cumulative

construction emissions). (Draft EIR pages 3-19 through 3-21).

LRDP MM AIR-CB: Any development on the UC San Diego campus shall include in

all construction contracts the measures specified below to reduce PM10 and PM2.5 air

pollutant emissions.

All on-site unpaved roads and off-site unpaved access roads shall be effectively

stabilized of dust emissions using water, chemical stabilizer/suppressant, or other

stabilization techniques.

All land clearing and grading and demolition activities shall be effectively controlled

of fugitive dust emissions utilizing application of water or by presoaking.

Street sweeping shall be performed regularly on roads surrounding the construction

site that carry construction traffic or collect construction-related dust or dirt.

Revegetate exposed earth surface following construction.

Limit traffic speeds on unpaved roads to 15 mph.

To the extent that equipment is available and cost effective, the campus shall

encourage contractors to use alternate fuels and retrofit existing engines in

construction equipment.

Minimize idling time to a maximum of 10 minutes when construction equipment is

not in use.

To the extent practicable, manage operation of heavy-duty equipment (e.g., restrict

operations, operate only when necessary) to reduce emissions. (Draft EIR pages 3.1-

19 and 3.1-22).

LRDP MM AIR-CC: Campus construction contracts/specifications shall include

language that requires medium- and large-sized construction fleets to comply with the

Page 15: CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN ...regents.universityofcalifornia.edu/regmeet/july15/gb8attach7.pdf · 2010, replaced the UC San Diego 2004 LRDP EIR as the basis

requirements of the California Air Resources Board’s current regulation for In-use Off-

road Diesel Vehicles (Section 2449, Title 13, Article 4.8, California Code of Regulations,

as modified).

FINDING: The Regents finds that the OPP Project would contribute incrementally

to a previously identified, cumulatively significant air quality impact during Project

construction (see Final EIR Section 3.1). Based on the detailed analyses in the UC

San Diego 2004 LRDP EIR and 2010 ECBT EIR and the tiered analysis in the Final

EIR, The Regents finds that this cumulative impact was adequately addressed in the

UC San Diego 2004 LRDP EIR and 2010 ECBT EIR, and CEQA Guidelines section

15152(f)(1) directs that this impact is not considered significant for the purposes of

the Final EIR. Additional detailed analysis of this impact is, therefore, not required

in the Final EIR, and pursuant to the conclusions of the prior CEQA analyses and

the Final EIR, LRDP Mitigation Measures AIR-CB (as amended) and AIR-CC are

hereby adopted and incorporated into the Project to reduce the severity of this

cumulative impact. Implementation of these mitigation measures will reduce the

impact, but not to a level that is less than cumulatively considerable for ozone, PM10,

and PM2.5. The implementation of LRDP Mitigation Measures AIR-CB and AIR-

CC thus does not ensure that the significant impact will be reduced to a level that is

less than cumulatively considerable. The Regents have not identified any additional

mitigation that would further reduce the contribution of the OPP Project to the

significant impact. Therefore, the implementation of the OPP Project may

contribute to a cumulative impact related to construction emissions (ozone, PM10,

and PM2.5) that is significant and unavoidable, but because this impact was

adequately addressed in the UC San Diego 2004 LRDP EIR and 2010 ECBT EIR

from which the Final EIR tiers, it is not considered significant for the purposes of

the Project. Even if the impact were considered significant, however, The Regents

finds this impact to be acceptable because the benefits of the Project outweigh the

cumulative environmental impact for the reasons set forth in the Statements of

Overriding Considerations adopted by The Regents in association with the

certifications of the UC San Diego 2004 LRDP EIR and 2010 ECBT EIR from which

the Project’s EIR tiers. The Regents further finds that the OPP Project will have the

specific benefits listed below. The Regents therefore reaffirms the Statements of

Overriding Considerations—as applied to the Project’s contribution to cumulative

construction emissions of ozone, PM10 and PM2.5—adopted in association with the

certifications of the UC San Diego 2004 LRDP EIR and 2010 ECBT EIR from which

the Project’s EIR tiers.

Project-Specific Benefits:

A. The Project will help advance the UC San Diego Medical Center goals established in the

2004 LRDP, specifically the construction of new facilities to consolidate clinical research

Page 16: CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN ...regents.universityofcalifornia.edu/regmeet/july15/gb8attach7.pdf · 2010, replaced the UC San Diego 2004 LRDP EIR as the basis

activities around certain specialty areas and to facilitate the translation of laboratory

discoveries into improved diagnosis and treatment capabilities.

B. The Project will develop a medical facility that would house hospital-licensed services to

support the existing Thornton Hospital and Jacobs Medical Center by housing disease-

specific centers and consolidating all outpatient, ancillary, professional and support

services to improve outpatient care delivery.

C. The Project will provide in-fill development in the existing East Campus Health Sciences

neighborhood, surrounded by existing infrastructure and medical center facilities, in close

proximity to existing housing, schools, and commercial development which is likely to

reduce and/or shorten vehicle trips.

D. The Project will incorporate sustainable design principles to achieve Leadership in

Energy and Environmental Design (LEED) New Construction (LEED-NC) “Silver”

certification or higher, thereby reducing energy consumption, conserving natural

resources, and minimizing GHG production.

E. The Project will provide hundreds of new permanent jobs over the long-term. Health care

and biotechnology jobs have been bright spots in the recovering economy, and are

projected to be a consistent source of economic and job growth well into the future.

F. The Project will provide employment opportunities for highly trained workers. The

Project will create the need for a substantial number of additional technical specialists

such as laboratory researchers, technicians, post-doctoral fellows, as well as physicians

and other skilled and technical specialties, that typically pay far beyond the median wage

in San Diego County. Physicians and biomedical researchers require extensive graduate

education and work fellowships, and licensure requirements before being able to practice

medicine. These and other technical specialists who will be employed by the Project

represent the “highly trained workers” mentioned in the CEQA Guidelines section

15091(a)(3).

G. The Project will provide an economic stimulus to San Diego County. The Project will

cost approximately $140 million, providing significant construction wages for hundreds

of workers. Wages earned by construction workers will be spent locally; this multiplier

effect has the potential to create jobs in other sectors of the economy. Similarly, the

Project will require construction materials from local suppliers, which will put additional

money into the local economy and produce sales tax revenues for local governments.

C. MITIGATION MONITORING AND REPORTING PROGRAM

Public Resources Code section 21081.6 requires the lead agency, when making the

findings required by Public Resources Code section 21081(1)(a), to adopt a mitigation

monitoring and reporting program that incorporates all of the changes made to the project or any

conditions of project approval adopted to mitigate or avoid significant effects on the

environment. The University has prepared a Mitigation Monitoring and Reporting Program that

requires the University to monitor all of the mitigation measures adopted and made fully

enforceable through these Findings and the approval of the OPP Project. The Regents finds that

Page 17: CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN ...regents.universityofcalifornia.edu/regmeet/july15/gb8attach7.pdf · 2010, replaced the UC San Diego 2004 LRDP EIR as the basis

the Mitigation Monitoring and Reporting Program has been designed to ensure compliance with

the mitigation requirements during project implementation.

The Mitigation Monitoring and Reporting Program defines the responsibility and

anticipated timing for implementation of mitigation measures within the University’s

jurisdiction. The University will ensure the accomplishment of mitigation measures through

administrative controls over the Project’s implementation, and the University will monitor and

enforce the implementation of mitigation measures through verification in periodic mitigation

monitoring reports and through periodic inspections by appropriate University personnel. The

Mitigation Monitoring and Reporting Program is included in the Final EIR as Section II.

D. PROJECT ALTERNATIVES

Section 5 of the Draft EIR evaluated a range of alternatives to the OPP Project. The

EIR’s analysis examined the feasibility of each alternative, the environmental impacts of each

alternative, and each alternative’s ability to meet the Project objectives described in Section 5 of

the Draft EIR. In compliance with CEQA and the CEQA Guidelines, the alternatives analysis

included an analysis of a no-project alternative and also identified the environmentally superior

alternative.

FINDING: The Regents certifies that it has independently reviewed and considered

the information on alternatives provided in the Draft and Final EIR and in the

administrative record. For the reasons set forth below, The Regents finds that the

alternatives either fundamentally fail to meet the Project objectives or fail to avoid or

substantially lessen the Project’s significant impacts.

1. Project Objectives

The Regents finds that the objectives for the OPP Project are as described in Section

2.3.3 of the Draft EIR. The overall purpose of the Project is to advance the UC San Diego

Medical Center goals established in the 2004 LRDP, as related to constructing new facilities to

consolidate clinical research activities around certain specialty areas and to facilitate the

translation of laboratory discoveries into improved diagnosis and treatment capabilities.

The specific objectives of the OPP Project are as follows:

Advancing the UC San Diego Medical Center goals established in the 2004 LRDP,

specifically the construction of new facilities to consolidate clinical research activities

around certain specialty areas and to facilitate the translation of laboratory discoveries

into improved diagnosis and treatment capabilities.

Developing a medical facility that would house hospital-licensed services to support

the existing Thornton Hospital and Jacobs Medical Center by housing disease-

specific centers and consolidating all outpatient, ancillary, professional and support

services to improve outpatient care delivery.

Page 18: CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN ...regents.universityofcalifornia.edu/regmeet/july15/gb8attach7.pdf · 2010, replaced the UC San Diego 2004 LRDP EIR as the basis

Incorporating sustainable design principles to achieve Leadership in Energy and

Environmental Design (LEED) “Silver” certification or higher, thereby reducing

energy consumption, conserving natural resources, and minimizing GHG production.

2. Alternatives to the Project

The Draft EIR evaluated two alternatives to the Project that were determined to have the

potential to meet most of the Project objectives, reduce impacts when compared to the Project,

and/or be potentially feasible: the No Project Alternative and the Reduced Project Alternative.

a) No Project Alternative

In accordance with CEQA and the State CEQA Guidelines, the Final EIR evaluates

the “No Project Alternative,” which compares the effects of approving the proposed

Project with the effects of not approving it.

Under the No Project Alternative, the proposed OPP Project facility would not be

developed. The project site would remain in its existing condition, mainly as the

south parking lot associated with the Perlman Medical Office Building. The No

Project Alternative would not preclude future development consistent with the land

use designation of the site in the LRDP, which is Medical Use.

The No Project Alternative would not result in any construction or operational

pollutant emissions, and the Project’s contribution to cumulative air quality impacts

(oxides of nitrogen [NOx] and reactive organic gases [ROG], herein collectively

referred to as ozone; and particulate matter [PM]) associated with construction would

be avoided. Under this alternative, the direct impacts to water quality would be

avoided, as would cumulative hydrology and water quality impacts, because

additional impervious surfaces would not be constructed. The proposed Project’s

cumulatively considerable contribution to existing fire protection impacts in the City

of San Diego would be avoided under the No Project Alternative because there would

be no effects on public services in the community. The No Project Alternative would

result in no impacts to traffic or emergency access because traffic and circulation

patterns would not be altered from existing conditions. With no development

occurring under this alternative, the proposed Project would have no impact on global

climate change; emissions of GHG during construction and operation would be

avoided, and it would not conflict with an applicable plan, policy or regulation

adopted for the purpose of reducing emissions of GHGs.

FINDING: Pursuant to Public Resources Code §21081(a)(3) and CEQA Guidelines

§15091(a)(3), The Regents finds that specific economic, legal, social, technological, or other

considerations render the No Project Alternative infeasible. The No Project Alternative is

not feasible because it would not achieve any of the Project objectives identified by the

Page 19: CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN ...regents.universityofcalifornia.edu/regmeet/july15/gb8attach7.pdf · 2010, replaced the UC San Diego 2004 LRDP EIR as the basis

University in Section 5 of the Draft EIR, including the key goals of developing a medical

facility that supports the existing Thornton Hospital and Jacobs Medical Center and

augmenting the 2004 LRDP’s goals of consolidating clinical research activities around

certain specialty areas and facilitating the translation of laboratory discoveries into

improved diagnoses and treatment. The Regents therefore rejects this alternative as

infeasible for the reasons listed above.

b) Reduced Project Alternative

Under the Reduced Project Alternative, the OPP facility would be developed but in a

modified configuration that would reduce the gross square footage of the building by

approximately 25 percent. The structure would have two stories above grade and

would include a basement level as opposed to the three above grade stories planned

under the proposed Project.

Similar to the proposed Project, the Reduced Project Alternative would result in less

than significant impacts related to the exceedance of air quality standards and

exposure of sensitive receptors to substantial pollutant concentrations. With the 25

percent reduction in the building size, the Reduced Project Alternative would require

less time to construct and fewer construction materials as compared to the proposed

Project, thereby decreasing both the Project’s less than significant direct air quality

impacts and severity of the Project’s contribution to the cumulative air quality

impacts associated with construction emissions of criteria air pollutants. However,

cumulative emissions of ozone, PM10 and PM2.5 under the Reduced Project

Alternative would not be reduced substantially enough and cumulative air quality

impacts would remain significant and unavoidable. The Reduced Project Alternative

would have a potentially significant water quality impact similar to the proposed

Project, because the amount of impervious surface added to the site would be similar.

The Reduced Project Alternative would have fewer employees, but would still

increase the need for public services compared to existing conditions and would not

avoid the cumulatively considerable contribution to existing fire protection and

emergency medical services impacts to the City. Similar to the proposed project, the

Reduced Project Alternative would result in less than significant impacts to potential

conflicts with circulation plans, alternative transportation plans, and Long-term

cumulative impacts and there would be no impact to air traffic patterns; the

potentially significant impact related to emergency access Near-term cumulative

impact would be similar under this alternative. With the 25 percent smaller building

size, impacts to global climate change would be reduced compared to the proposed

Project and would remain less than significant.

FINDING: Pursuant to Public Resources Code §21081(a)(3) and CEQA Guidelines

§15091(a)(3), The Regents finds that specific economic, legal, social, technological, or other

Page 20: CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN ...regents.universityofcalifornia.edu/regmeet/july15/gb8attach7.pdf · 2010, replaced the UC San Diego 2004 LRDP EIR as the basis

considerations render the Reduced Project Alternative infeasible. Despite the removal of

the third above grade story, associated reductions in program components and faculty and

staff population, the Reduced Project Alternative would still meet the key objective of

supporting the development and construction of new facilities to consolidate clinical

research activities around certain specialty areas and to facilitate the translation of

laboratory discoveries into improved diagnosis and treatment capabilities; however, this

important objective would not be met as fully as it would have been with development of a

larger facility. The Reduced Project Alternative would not fully support the development

of a medical facility geared towards housing disease-specific centers and consolidating all

outpatient, ancillary, professional and support services to support Thornton Hospital and

Jacobs Medical Center to improve outpatient care delivery, as the breast care and stem cell

clinics, infusion, and pharmacy components of the building would be removed. The

cumulative air quality impacts of the proposed Project would remain significant and

unavoidable under the Reduced Project Alternative. Furthermore, although the Reduced

Project Alternative would incrementally reduce some of the Project’s significant

environmental impacts, those relatively minimal reductions in adverse impacts would be

outweighed by the potentially detrimental results of a decrease in the Project’s building

size and the associated smaller growth potential. While the Reduced Project Alternative

generally would achieve the basic Project objectives, the smaller growth potential

associated with the alternative would not fulfill those objectives as completely as a larger

building because several important services and facilities would be removed. Therefore,

The Regents rejects this alternative because it would generate significant and unavoidable

environmental impacts (only slightly reduced in intensity compared to the Project) while

failing to completely fulfill many of the essential Project objectives.

FINDING: While The Regents finds that the No-Project Alternative is the

environmentally superior alternative because it would avoid many of the significant

environmental impacts of the development that would occur under the OPP Project, The

Regents also finds that the No-Project Alternative is infeasible pursuant to Public

Resources Code §21081(a)(3) and CEQA Guidelines §15091(a)(3) because it would not

meet any of the basic project objectives. CEQA Guidelines Section 15126.6(e)(2) requires

that if the environmentally superior alternative is the No Project Alternative, the EIR shall

identify an environmentally superior alternative among the other alternatives. Therefore,

the Final EIR identified the Reduced Project Alternative as the environmentally superior

alternative. The Reduced Project Alternative would not avoid any of the significant

environmental impacts of the development that would occur under the OPP Project. The

Reduced Project Alternative, however, would reduce the magnitude of the impacts

associated with air quality, hydrology and water quality, public services, traffic, and global

climate change. The Reduced Project Alternative, however, is infeasible because it would 1)

fail to completely fulfill all three of the key Project objectives, and 2) generate significant

and unavoidable environmental impacts (construction-related air emissions) which would

only be slightly reduced in intensity compared to the Project; these and other relatively

Page 21: CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN ...regents.universityofcalifornia.edu/regmeet/july15/gb8attach7.pdf · 2010, replaced the UC San Diego 2004 LRDP EIR as the basis

minimal reductions in adverse impacts would be outweighed by the potentially detrimental

results of a decrease in the Project’s building size and the associated smaller growth

potential. For these reasons, The Regents rejects the environmentally superior alternative

as infeasible. When compared to those alternatives, the OPP Project provides the best

available and feasible balance between maximizing attainment of the Project objectives and

minimizing significant environmental impacts.

III. RECORD OF PROCEEDINGS

The record of proceedings upon which The Regents bases these Findings consists of all

the documents and evidence relied upon by the University in preparing the proposed OPP Project

and the associated EIR. The custodian of the record of proceedings is: Catherine J. Presmyk,

Assistant Director, Environmental Planning, UC San Diego Physical and Community Planning,

Torrey Pines Center South, 10280 North Torrey Pines Road, Suite 355, La Jolla, California

92037-1032, (858) 534-3860.

IV. SUMMARY

Based on the foregoing Findings and the information contained in the record, The

Regents has made one or more of the following Findings with respect to the significant

environmental effects of the proposed Outpatient Pavilion Project as described in the Final EIR:

Changes or alterations have been required for, or incorporated into, the Project that

avoid or substantially lessen the significant environmental effects on the environment.

Changes or alterations that are wholly or partially within the responsibility and

jurisdiction of another public agency have been, or can and should be, adopted by that

other public agency.

Specific economic, legal, social, technological, or other considerations make

infeasible certain mitigation measures and alternatives.

Based on the foregoing Findings and the information contained in the record, it is hereby

determined that:

All significant effects on the environment due to approval of the Outpatient Pavilion

Project have been eliminated or substantially lessened to the extent feasible for the

reasons set forth in Section II of these Findings.

Any remaining significant effects on the environment found to be unavoidable are

acceptable due to the factors described in Section III, above.

V. APPROVALS

The Regents hereby takes the following actions:

Page 22: CALIFORNIA ENVIRONMENTAL QUALITY ACT FINDINGS IN ...regents.universityofcalifornia.edu/regmeet/july15/gb8attach7.pdf · 2010, replaced the UC San Diego 2004 LRDP EIR as the basis

1) The Regents certifies the Final EIR, as described in Section I, above.

2) The Regents hereby adopts as conditions of approval of the Outpatient Pavilion

Project all mitigation measures within the responsibility and jurisdiction of the

University set forth in Section II of the Findings, above.

3) The Regents hereby adopts the Mitigation Monitoring and Reporting Program for

the Project accompanying the Final EIR and discussed in Section II.C of the

Findings, above.

4) The Regents hereby adopts the Findings in their entirety as set forth in Sections I -

V, above, and reaffirms the Statement of Overriding Considerations adopted in

association with certification of the UC San Diego 2004 LRDP EIR and 2010

ECBT EIR from which the Project’s EIR tiers.

5) Having certified the Final EIR, independently reviewed and analyzed the Final EIR,

incorporated mitigation measures into the Project, and adopted the Mitigation

Monitoring and Reporting Program and the foregoing Findings, The Regents hereby

approves the design of the Outpatient Pavilion Project.