Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
j l
C00 / 4094-7
SAFETY PROCEDURES FOR THE 25-kW SOLAR PHOTOVOLTAIC
ARRAY AT MEAD, NEBRASKA
S. E. Forman
E. E. Landsman
Massachusetts Institute of Technology
Lincoln Laboratory
Lexington, Massachusetts 02173
7 April 1978
Prepared For
THE U.S. DEPARTMENT OF ENERGY
UNDER CONTRACT NO. EY-76-C-02-4094
This report was prepared as an account of work sponsored by the United States Government. Neither the Uni ted States nor the United States Department of Energy, nor any of their employees, nor any of their contractors, subcontractors, or their employees, makes any warranty, expressed or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product or process disclosed, or represents that its use would not infringe privately owned rights.
..
"
SAFETY PROCEDURES FOR THE 25-kW SOLAR PHOTOVOLTAIC
.ARRAY AT MEAD, NEBRASKA
S. E. Forman
E • E. Landsman
C00-4094-7
7 April 1978
Massachusetts Institute of Technology Lincoln Laboratory
Lexington, Massachusetts 02173
ABSTRACT
Since the 25-kW solar photovoltaic agricultural field test system
at the University of Nebraska is a unique electrical power system, special
safety rules and regulations are needed to govern its operation. Field
inspection and maintenance operations require the handling of electrically
active elements during daylight hours. This report serves to enumerate the
methods and techniques necessary to perform these operations in a safe manner
and to make field personnel more safety conscious as well.
iii
,II
ABSTRACT
LIST OF FIGURES
BACKGROUND AND GLOSSARY OF TERMS
GENERAL INSTRUCTIONS
SAFETY PROCEDURES
CONTENTS
I. Physical Inspection and Cleaning of Array Front Surface
II. Electrical Work on Back Surface of Array Frames
III. Locating an Open Module in a Pair or Quad
IV. Removing a Defective Panel EXCEPT for Completely Open-Circuited Panels
V. Removing a Completely Open-Circuited Panel
VI. Locating a Ground-to-Frame
VII. Locating an Open Panel in a String
VIII. Alternative Method to Find an Open Panel or Bad Interconnects
V
iii
vii
l
4
5
5
7
9
11
13
16
18
19
LIST OF FIGURES Page
Fig. 1. Aerial view of Mead, Nebraska, photovoltaic array. viii
Fig_. 2. Close-up view of photovoltaic array showing two 2 rows of frames and photovoltaic modules.
vii
<: .... .... .....
jcP2s1-11nl
Fig. 1. Aerial view of Mead, Nebraska, photovoltaic array .
•
BACKGROUND AND GLOSSARY OF TERMS
As part of the DOE's demonstration program for terrestrial photovoltaic
modules, MIT/Lincoln Laboratory has designed and built a 25-kW experimental
test facility at the University of Nebraska Field Station in Mead, Nebraska.
At the time of its incept~on in July 1977, it was the largest active
photovoltaic power source in the world. An aerial view of the site is
shown in Figure 1.
The lifetime goal for the photovoltaic modules which make up the array
is 20 years. In order to assess whether this goal is being met, it is necessary
to periodically inspect the modules in the field, to remove modules from the
array for more detailed analysis in the laboratory, to make measurements which
locate electrically defective modules, to wash and clean the modules, and
to perform various other general maintenance and testing operations on the
modules. Since the modules represent active electrical elements and many
of the aforementioned operations must be performed in daylight hours, it
is necessary to develop a set of safety guidelines for the personnel involved
in performing the operations.
The Nebraska test site is a "first of its kind" type of facility and,
therefore, many of the safety rules and regulations associated with its
operation are unique. For example, the solar cells in the photovoltaic modules
are encapsulated in clear silicone rubber as opposed to being covered with
glass or hard plastic. In some instances, components of the modules were
inadequately covered by the silicone rubber and eventually became exposed due
to weathering. This type of hazard can be found only through inspection and
touching, and special rules must be developed so that there is no danger of
electrical shock to the inspector. In addition, this system uses batteries
for energy storage. Special guidelines for the handling of batteries in an
enclosed trailer are also needed. The basic intent of this report is to list
all the possibly hazardous operations which need to be performed on the array
subsystem and to ensure that each operation has a set of safety guidelines so
that each may be carried out with no danger.
1
I CP2 67-16691
~ ·
N
Fig . 2. · ff s a nd photovoltaic modul, Clos e -up of photovoltaic array showing two rows o r ame
• •
•
•
Prior to enumerating specific safety guidelines, a glossary is provided
to establish the terminology needed to describe various elements of a
photovoltaic system.
1. Module
2. Pair
3. Quad
As-manufactured assembly of encapsulated photovoltaic cells arranged on a substrate.
Two modules wired in parallel.
Four modules wired in parallel. (The word "panel" may be used interchangeably with pair or quad.)
4. String A number of panels electrically connected in series. (Pairs and quads are never mixed.)
5. Frame Metal structure to which one or more strings are attached. (The frame and its strings are often referred to as an array or array frame.)
6. Row Group of frames aligned to form a row. (This is often called an array group or a subfield.)
7. Field One or more rows of frames
8. Field Control Panel Electrical panel that controls the operational behavior of the field and various subsets of the field, i.e., frames and strings.
9. Frame Junction Box
10. Array Test Box
Electrical junction box attached to the rear side of each frame. Each string on the frame is wired directly to this box.
An electrical test box which can be used to isolate up to three strings from ground and also make various electrical measurements.
As shown in Figure 2, the field consists of two rows, each having fourteen
array frames. The front row contains modules from Solarex Corporation, and
the back row contains modules from Sensor Technology, Inc. Two Solarex modules
wired in parallel constitute a pair; ten pairs in series make up a string.
Four Sensor Tech modules wired in parallel are called a quad; nine quads
in a series make up a string.
Two-and-one-half Solarex strings are located on each array frame in the
front row. Three Sensor Tech strings are located on each of the fourteen array
frames in the back row.
3
GENERAL INSTRUCTIONS
The purpose of this report is to enumerate a set of safety procedures
which must be followed in performing various operations at the Nebraska test
facility involving handling of active electrical components and wiring.
If at any time during the execution of the safety regulations described herein
any confusion or doubt arises as to the meaning or intent of the instructions
to be followed, a supervisory person should be contacted immediately.
Prior to working on any section or sections of the field, such areas
should be placed in the open-circuit mode at the field control panel and so
designated by signs that state: People at Work - Do Not Touch. The toggle
switches for specific areas to be worked on should be locked in the open
position - using the special switch panel locking cover which will be
provided at the site.
The following test equipment should be assembled prior to beginning work
on the photovoltaic installation:
1. One or more array test boxes that include separate meters to measure:
Leakage-current to ground String open-circuit voltage String short-circuit current
2. Multimeter for voltage, current, and resistance measurements.
3. Six, 2-foot-long, insulated wires with alligator clips at each end to ground panels or wires.
4. Log book containing ranges of values for particular measurements to be made.
As an overall precaution, no wiring should be considered safe until
checked personally with an appropriate measuring instrument. All entries
in the log book should be accompanied with the date, the time of day, and the
signature of the person making the entry.
4
SAFETY PROCEDURES
I. Physical Inspection and Cleaning of Array Front Surface
A. Place those sections of the field to be worked on in the open-circuit
mode via the field control panel in the trailer.
CAUTION: A high voltage exists within module strings.
Avoid contact with modules.
B. Ground the array test box to the metal support frame being worked on
by attaching the clip lead to the frame.
c. Verify that test box is set at open-circuit for all strings.
D. Pull all connectors from junction box of frame being worked on.
NOTE: There should be no arcing when disconnecting connectors.
If arcs occur, notify supervisor before proceeding.
Cap open junction box connectors.
E. Attach the connectors from each string on the frame to the test box
via mating connectors that are in place on test box. Match string
numbers when possible (i.e., unless they are not noted on connectors
at the frame junction box).
F. Test all strings for leakage-current to ground.
NOTE: If meter dial registers more than 10 microamps, STOP, do not
proceed with inspection.
Notify supervisor.
Return all ground test switches to the OPEN position.
G. Measure and record in the log book the open-circuit voltage, short
circuit current, and ground currents for all strings being worked on.
(Log book contains range of acceptable values.)
NOTE: Notify supervisor if discrepancies occur.
H. Place all strings in shorted condition in the test box.
I. Proceed with inspection and/or cleaning.
5
J. After completing inspection and/or cleaning, return strings to open
circuit mode and remove string connectors from test box.
K. Remove frame junction box caps and reconnect string connectors
to proper points on junction box.
NOTE: No arcing should occur.
L. Verify that strings are working properly by noting the open-circuit
voltage and short-circuit current of the frame worked on via field
control panel in the trailers.
6
•
II. Electrical Work on Back Surface of Array
A. Preparation
1. Place those sections of the field to be worked on in the open
circuit mode via the field control panel in the trailer.
CAUTION: A high voltage exists within module strings.
Avoid contact with modules.
2. Ground the array test box to the metal support frame being worked
on by attaching the clip lead to the frame.
3. Verify that test box is set at open-circuit for all strings.
4. Pull all connectors from junction box of frame being worked on.
NOTE: There should be no arcing when disconnecting connectors.
If arcs occur, notify supervisor before proceeding.
Cap open junction box connectors.
5. Attach the connectors from each string on the frame to the
test box via mating connectors that are in place on test box. Match
string numbers when possible (i.e., unless they are not noted on
connectors at the frame junction box).
6. Test all strings for leakage-current to ground.
NOTE: If meter dial registers more than 10 microamps, STOP, do not
proceed with inspection.
Notify supervisor.
Return all ground switches to the OPEN position.
7. Measure and record in the log book the open-circuit voltage,
short-circuit current, and ground currents for all strings being
worked on. (Log book contains range of acceptable values.)
NOTE: Notify supervisor if discrepancies occur.
8. Place all strings in shorted condition in the test box.
7
B. Connect a ground as close as electrically possible to each wire
connected to the work site, but not at the work site.
OBJECTIVE: Guarantee that all wires are grounded even if disconnected
during the work.
NOTE: A. Grounding connections may, under some conditions, draw
an arc. Thus, keep eyes and skin away from the point of
electrical contact.
B. When frame grounding, always attach lead to frame first,
then to the point being grounded.
C. Measure voltage directly from the work sites to the frame. Proceed
with planned operation unless dangerous voltages are noted (over 50 volts).
D. Upon completing planned operation, remove ground carefully as an arc
may be drawn.
NOTE: Remove lead from grounded point first, then remove lead from frame
ground.
E. Open-circuit all strings.
F. Remove string connectors from test box.
G. Reconnect string connectors to proper points on frame junction box.
NOTE: There should be no arcing.
8
>
III. Locating an Open Module in a Pair or Quad
A. Preparation
1. Place those sections of the field to be worked on in the open
circuit mode via the field control panel in the trailer.
CAUTION: A high voltage exists within module strings.
Avoid contact with modules.
2. Ground the array test box to the metal support frame being worked
on by attaching the clip lead to the frame.
3. Verify that test box is set at open-circuit for all strings.
4. Pull all connectors from junction box of frame being worked on.
NOTE: There should be no arcing when disconnecting connectors.
If arcs occur, notify supervisor before proceeding.
Cap junction box connectors.
5. Attach the connectors from each string on the frame to the
test box via mating connectors that are in place on test box.
Match string numbers when possible (i.e., unless they are not noted
on connectors at the frame junctio~ box).
6. Test all strings for leakage current to ground.
NOTE: If meter dial registers more than 10 microamps, STOP, do not
proceed with inspection.
Notify supervisor.
Return all ground switches to the OPEN position.
B. With strings open circuited and test box ground switches in open
condition, measure short-circuit current of panels in question with a
multi-meter switched to a current scale greater than the short-circuit
current of a string.
NOTE: Accidental shorts of measuring leads to the support frame should
produce no arcing.
9
C. A short-circuit current that is an integer fraction less than one,
related to the number of modules in parallel, indicates an open module in
a panel.
EXAMPLE: I is 3/4 normal in a 4-module set or 1/2 normal in a SC
2-module set. See table of expected values in the log book.
D. Upon identifying the defective panel, cast a shadow over each module
in the panel separately to locate the one that produces no change in
measured short-circuit current and note its serial number.
NOTE: Modules wired backwards can produce strange results in the above
steps. For pairs, the short-circuit current will be zero if one module
is wired backwards. For quads the short-circuit current will be reduced
from the normal value and shadowing each module in the quad will produce
meter response.
10
IV. Removing a Defective Panel EXCEPT for Completely Open-Circuited Panels
A. Identify panel to be removed per Section III.
B. Preparation
1. Place those sections of the field to be worked on in the
open-circuit mode via the field control panel in the trailer.
CAUTION: A high voltage exists within module strings.
Avoid contact with modules.
2. Ground the array test box to the metal support frame
being worked on by attaching the clip lead to the frame.
3. Verify the test box is set at open-circuit for all strings.
4. Pull all connectors from junction box of frame being
worked on.
NOTE: There should be no arcing when disconnecting connectors.
If arcs occur, notify supervisor before proceeding.
Cap junction box connectors.
5. Attach the connectors from each string on the frame to the
test box via mating connectors that are placed on test box. Match
string numbers when possible (i.e., unless they are not noted on
connectors at the frame junction box).
6. Test all strings for leakage-current to ground.
NOTE: If meter dial registers more than 10 microamps, STOP, do not
proceed with inspection.
Notify supervisor.
Return all ground switches to the OPEN position.
7. Measure and record in the log book the open-circuit voltage,
short-circuit current, and ground currents for all strings being
worked on. (Log book contains range of acceptable values.)
8. Place all strings in shorted condition in the test box.
11
C. Ground both sides of panel to be removed to array frame.
NOTE: 1. If defective panel is at the end of a series string
of panels, it is necessary to ground at the adjacent panel and
at the other end of the string.
OBJECTIVE: Remove defective panel while leaving all ground wires
in place so that no remaining wires can become hot electrically.
2. When grounding a panel to the frame, always attach lead wire
to the frame first, then to the point on the panel being grounded.
3. Grounding connections may draw an arc; thus keep eyes, skin, and
clothing away from the point of electrical contact.
D. Measure voltage directly from the work sites to the array frame.
Proceed if voltages do not exceed 50 volts.
E. Remove panel's electrical mating plugs. Remove defective panel.
F. Install new panel and mate electrically.
G. Remove ground leads.
NOTE: Remove lead from panel first and then from frame.
CAUTION: Arcing as noted in step C-3 may occur.
H. Test all strings for leakage-current to ground.
NOTE: If meter dial registers more than 10 microamps, STOP, do not
proceed with inspection.
Notify supervisor.
Return all ground switches to the OPEN position.
I. Measure and record in the log book the open-circuit voltage,
short-circuit current, and ground currents for all strings being
worked on. (Log book contains range of acceptable values.)
NOTE: Notify supervisor if discrepancies occur. Also record serial
numbers of removed panel and newly installed panel.
J. Remove string connectors from test box.
K. Reconnect string connectors to proper points on frame junction box.
NOTE: No arcing should occur.
L. Verify proper operation of strings by noting open-circuit voltage
and short-circuit current via field control panel in the trailer. 12
p
V. Removing Completely Open-Circuited Panel
(Cause may be a bad diode, which rarely occurs.)
A. Identify panel to be removed per Section III.
B. Preparation
1. Place those.sections of the field to be worked on in the
open-circuit mode via the field control panel in the trailer.
CAUTION: A high voltage exists within module strings.
Avoid contact with modules.
2. Ground the array test box to the metal support frame being
worked on by attaching the clip lead to the frame.
3. Verify that test box is set at open-circuit for all strings.
4. Pull all connectors from junction box of frame being worked on.
NOTE: There should be no arcing when disconnecting connectors.
If arcs occur, notify supervisor before proceeding.
Cap open junction box connectors.
5. Attach the connectors from each string on the frame to the
test box via mating connectors that are in place on test box. Match
string numbers when possible (i.e., unless they are not noted on
connectors at the frame junction box).
6. Test all strings for leakage-current to ground.
NOTE: If meter dial registers more than 10 microamps, STOP, do not
proceed with inspection.
Notify supervisor.
Return all ground test switches to the OPEN position.
7. Measure and record in log book open-circuit voltage, short
circuit current, and ground currents for all strings being worked
on. (Log book contains range of acceptable values.)
NOTE: Notify supervisor if discrepancies occur.
8. Place all strings in shorted condition in the test box.
13
C. Open-circuit the string to be worked on.
D. Ground both sides of panel to be removed to array frame.
NOTE: If defective panel is at the end of a series string of panels,
it is necessary to ground at the adjacent panel and at the
other end of the string.
OBJECTIVE: Remove defective panel while leaving all ground
wires in place so that no remaining wires can become hot
electrically.
NOTE: 1. When grounding a panel to the frame, always attach
lead wire to the frame first, then to the point on
the panel being grounded.
2. Grounding connections may draw an arc; thus
keep eyes, skin, and clothing away from the point of
electrical contact.
E. Short-circuit string being worked on.
NOTE: All strings connected to test box should now be shorted.
F. Unmate defective panel electrically.
G. Remove defective panel.
H. Install new panel and mate electrically.
I. Remove ground leads.
NOTE: Remove leads from panel first and then from frame.
CAUTION: Arcing as noted in Step D-2 may occur.
J. Read and record in log book short-circuit current and open-circuit
voltage per test box meter. New module is functioning satisfactorily if
reading is within range of values in log book.
NOTE: Notify supervisor if discrepancies occur.
K. Test all strings for leakage-current-to-ground.
L. Return all ground test switches to OPEN position.
14
,
. ,.,
)
' •.
M. Return strings to open-circuit mode and remove string·
connectors from test box.
' N. Remove frame junction box caps and reconnect string
connectors to proper points on junction box.
NOTE: No arcing should occur.
O. Verify that strings are working properly by noting the
open-circuit voltage and short-circuit current of the frame
worked on via field control panel in the trailer •
15
VI. Locating a Ground-to-Frame
A. Preparation
1. Place those sections of the field to be worked on in the open
circuit mode via the field control panel in the trailer.
CAUTION: A high voltage exists within module strings.
Avoid contact with modules.
2. Ground the array test box to the metal support frame being
worked on by attaching the clip lead to the frame.
3. Verify that test box is set at open-circuit for all strings.
4. Pull all connectors from junction box of frame being worked
on.
NOTE: There should be no arcing when disconnecting connectors.
If arcs occur, notify supervisor before proceeding.
Cap junction box connectors.
5. Attach the connectors for each string on the frame to the
test box via mating connectors that are placed on test box. Match
string numbers when possible (i.e., unless they are not noted on
connectors at the frame junction box).
6. Test all strings for leakage-current to ground to verify that
frame ground exists. The ground will cause values of leakage-current
greater than 10 microamps.
NOTE: Return all ground switches to the OPEN position.
B. Measure string voltage (V) between positive and negative test points s
on the test box using a voltmeter.
C. Using a voltmeter, measure voltages from positive-to-ground and
negative-to-ground on test box (V+ and V ).
16
D. V+ plus V_ should equal Vs. The ratio (V+/V_) should indicate how
far from either end of the string the ground is.
EXAMPLE: If V = 230 and V = -89 and there are nine panels in the s string, the ground is in the middle of the fourth panel from the
negative side. To zero in, check voltage on both sides of unit 4
to ground. If voltages are of opposite polarity to ground (i.e.,
voltage changes sign) defective panel has been located. Ratio of
either V+ or V to Vs will indicate the approximate position of the
ground in the panel.
E. Remove defective panel per Section IV.
17
VII. Locating an Open Panel in a String
A. Short-circuit suspected string at field control panel. (Minus
side of string is assumed permanently grounded.)
NOTE: String is not open if a current is indicated at field control
panel.
B. Measure voltages within string to ground.
NOTE: When voltage changes sign the the open is passed.
CAUTION: Connect one voltmeter lead to ground first and then connect
the other voltmeter lead to the point to be measured.
DANGER: Be careful not to accidentally make bodily contact with any
terminals.
18
•
VIII. Alternative Method to Find Open Panel or Bad Interconnects
A. Follow Section III, but measure panel short-circuit current between
negative side of panel to negative side of adjacent panel. No short
circuit current will be present if an open exists.
NOTE: The same test can be made between positive sides •
19