www.pontoenergia.pt

WHO

BundleUp is an Horizon 2020 project with only Portuguese participants

“Development of energy eficiency projectswith bankability requirements”

Page 3: BundleUP Joint procurement for energy efficiency in public

www.pontoenergia.pt

GoParity is an online P2P impact investing platform that connects citizens to sustainability projectswith as little as 20€.

CREATINGIMPACTWITH RETURN

Page 4: BundleUP Joint procurement for energy efficiency in public

www.pontoenergia.pt

BusinessModel

INVESTORS

NO FEES

PROJECTS

UPFRONT FEE+

ONGOING FEE

LOAN

CAPITAL AND INTEREST

4% TO 6% PER YEAR

Page 5: BundleUP Joint procurement for energy efficiency in public

www.pontoenergia.pt

WHERE WE ARE

>2000users

>1M €transactions

16 projectsfunded

Page 6: BundleUP Joint procurement for energy efficiency in public

www.pontoenergia.pt

FUNDINGHard to find funding through

traditional means

SCALEMany projects are too small to attract professional investors

BUREAUCRACYRestrictive procedures make the

process costly and time-consuming

WHY

Several projects with great potential for savings and economic viability do not reach the implementation stage

Page 7: BundleUP Joint procurement for energy efficiency in public

www.pontoenergia.pt

PROJECTS

Consumption equivalent to 150 GWH/year

M€ OF FUNDING

Average Payback of 5,7 years

CITIES

Which account to more than 20% of portuguese population

56 49 13

STARTING POINT

Page 8: BundleUP Joint procurement for energy efficiency in public

www.pontoenergia.pt

Page 9: BundleUP Joint procurement for energy efficiency in public

www.pontoenergia.pt

Page 10: BundleUP Joint procurement for energy efficiency in public

www.pontoenergia.pt

• PML 1 – Potential project identified

(building or infrastructure apparently suitable for energy efficiency or RES intervention)

• PML 2 – RES and/or Efficiency potential quantified

(via audit, study or certification)

• PML 3 – Investment estimated and business model chosen

• PML 4 – Technical project developed

• PML 5 – Investment-Ready

(Business case confirmed)

• PML 6 – Investment offer or tendering requirements created

(ready to sign or launch tender)

PROJECT MATURITY LEVEL

Page 11: BundleUP Joint procurement for energy efficiency in public

www.pontoenergia.pt

METHODOLOGY

Potential assessment and budget estimation

Business and financing models assessment

Support in obtaining technical and economic-financial proposals

Contracting and funding support

Investment forms• Own Equity/Capitals• Loan• External Investor (off-balance sheet)

Page 12: BundleUP Joint procurement for energy efficiency in public

www.pontoenergia.pt

PROMOTERS

Private or Public Organizationswith energy efficiency projects

EXPERTS

Energy efficiency or renewable energy services companies

INVESTORS

Financial institutions, funds, private investors or family offices

One-stop-shop: a place where all stakeholders can make their energy efficiency projects happen

VALUE PROPOSITION

Page 13: BundleUP Joint procurement for energy efficiency in public

www.pontoenergia.pt

LOANS

“OFF-BALANCE SHEET”

EXTERNAL INVESTORS

INVESTMENT FROM THE PROMOTER

OWN FUNDS

DEBT

INVESTMENT TYPES/FORMS

Page 14: BundleUP Joint procurement for energy efficiency in public

www.pontoenergia.pt

• Installment payment agreements

• “Group of contracting entities”

• Standard contracts for EE in public administraiton (”EcoAP”)

• Aquisition of energy efficiency services/equipment

LEGAL FRAMEWORK

Providing contracting support is a vital part of BundleUp activities, which counts with SRS Layers for thelegal framework definition. At this moment, there are four general solutions identified, even thoughsome projects could have other approaches:

Page 15: BundleUP Joint procurement for energy efficiency in public

www.pontoenergia.pt

CURRENT PIPELINE

Funding and Energy| All BundleUp projects identified

PARTNER INVESTMENT Yearly Savings (GWh/year)

Yearly Savings (€/year)

Energy EfficiencyInvestment

Savings GWh(EE+PV)

PV Investment

Page 16: BundleUP Joint procurement for energy efficiency in public

www.pontoenergia.pt

WHERE WE ARE

• Beta-version platform

• Legal framework

• Project harmonization (batch 1)

• Investor meetings (15 concluded)

• Tendering templates

FIRST PROJECTS COMING TO LIFE!

Page 17: BundleUP Joint procurement for energy efficiency in public

www.pontoenergia.pt

Energy Savings

143,81 GWh/year

= =

3 617 861 trips from Lisbon to

Oporto per year

Equivalent to

planting 3 379 535 trees per year

=

67 590 Ton C02 per year

Convertions rates from DGEG, Pordata and VW Portugal

PROJECT IMPACT

If all BundleUp pipeline projects were successfully implemented

Page 18: BundleUP Joint procurement for energy efficiency in public

www.pontoenergia.pt

AdEPorto - Agência de Energia do Porto, a non profit

organization, was founded by the Municipality of Porto in 2007.

Presently it aggregates 9 municipalities of Porto Metropolitan

Area – North of Douro River.

Also holds 21 other associate member institutions, both private

and public, ranging different activities: energy, water, R&D,

professional associations, and academia.

AdEPorto

18

POPULATION > 1 MILHÃO (10% PT)TERRITORY > 800 km2 (1% PT)ELECT. USE 2016 = 5.378 GWh (11% PT)

Page 19: BundleUP Joint procurement for energy efficiency in public

www.pontoenergia.pt

PORTO MUNICIPALITY

• Population:237 591 hab• Area: 41,42 km2

• Density: 5 736 hab/km2

(PT: 115 hab/km2)

• World Heritage Historic Centre

• Best European Destination:2012, 2014 and 2017

19

Page 20: BundleUP Joint procurement for energy efficiency in public

www.pontoenergia.pt 20

➢ Covenant of Mayors Signatory:

• First approved Portuguese SEAP (2011);

• 45% CO2 reduction Target (2020);

• Municipal Council decided for joining the

Covenant of Mayors for Climate and Energy;

• Renewed target of 50% CO2 reduction (2030)

and adaptation strategy.

PORTO MUNICIPALITY

Page 21: BundleUP Joint procurement for energy efficiency in public

www.pontoenergia.pt 21

PORTO MUNICIPALITY

➢ (A few) Project Highlights:

• PV Porto (1st Phase): 1MWp decentralized PV

• Public Lighting: Full LED system

• Municipal Fleet:100% EV goal (≈300 vehicles)

• Public transportation: New electric buses until 2020

• Social Housing: Deep renovation + RES

Page 22: BundleUP Joint procurement for energy efficiency in public

www.pontoenergia.pt 22

PV PORTO

• Decentralized System;

• Renewable electricity;

• Available Municipal buildings:

o Schools, services, sports, cultural...

o Different voltage levels (MV and LV)

o Energy use mainly in daytime hours

• EV charging + Storage pilots;

1st Phase target: 1MWp

Page 23: BundleUP Joint procurement for energy efficiency in public

www.pontoenergia.pt 23

PV PORTO – INSTALLATION EXAMPLECENTRAL MAINTENANCE BUILDING

Power to Install 210 kWp

Investment 178 500 €

Annual Income 37 718€

Payback 5,0 years

Generated Energy 308 250 kWh

Grid Injection Approx. 0%

Avoided CO2/year] 111 ton

CAR PARKING BUILDUING

Power to Install 82 kWp

Investment 98 400 €

Annual Income 17 980€

Payback 5,7 years

Generated Energy 106 108 kWh

Grid Injection Approx. 0%

Avoided CO2/year] 38 ton

• 60 EV Chargers• Charge Management Control

• 45 EV Chargers• Charge Management Control

Page 24: BundleUP Joint procurement for energy efficiency in public

www.pontoenergia.pt 24

PV PORTO - 1st PHASEBuildings 34

Power to Install 1 013 kWp

Investment 933 850 €

Annual Maintenance 10 130 €

Annual Income 183 458 €

Payback 5,2 years

Generated Energy 1 476 650 kWh

Grid Injection 16%

Avoided CO2/year 531 ton

• Clean electricity;

• Reducing CO2 emissions;

• Raising awareness;

• Lower energy costs;

• Gamification on Schools;

Page 25: BundleUP Joint procurement for energy efficiency in public

www.pontoenergia.pt 25

PV PORTO – NEXT STEPS

25

• On-site validation of power plant installation potential;

• Electrical infrastructure sizing;

• Existing structural elements load bearing characteristics;

• Evaluate EV chargers interconnection;

• Evaluate local storage possibilities;

• Final PV system dimensioning, cost and tenders;

Initial Studies

On-site Evaluation

Final design and

tendering Public Procuremen

tDeployment

Mar/2019 Apr/2019 Aug/2019 Nov/2019

2st Phase target: + 2MWp (2020)

Page 26: BundleUP Joint procurement for energy efficiency in public

www.pontoenergia.pt 26

PV PORTO AND BUNDLE UP (PONTO ENERGIA)

• Support from peers and partners;

• Identifying bundling and market opportunities;

• Identifying potential market players;

• Proposing alternative financing schemes;

• Technical/Legal support;

Page 27: BundleUP Joint procurement for energy efficiency in public

www.pontoenergia.pt

THANK YOU

N U N O B J @ G O P A R I T Y . C O M

R U I P I M E N T A @ A D E P O R T O . E U

W W W . P O N T O E N E R G I A . P T / / W W W . B U N D L E U P . E U