Building Auotmation System_2015 March_EA Training

Embed Size (px)

DESCRIPTION

Building Automation Costs

Citation preview

  • BMS_Cost. A BAS system will have a capital cost of USD 100 to 150 per

    sensor or control point and usually contribute 15% to 20% of the total HVAC cost.

    The payback period is usually 2 to 4 years but it is recommended to check the economics that is unique to each project.

    The BAS does not guarantee saving its own. The mechanical and electrical system need to be equipped with design features that introduce overall efficiency and safety

    The saving is largely depend on the operators skill, duty hours and the energy cost.

  • Operating cost

    It is necessary to decrease energy cost without discomfort to the user

    Is it possible with a DDC?

    Load shedding

    Optimum start/stop

    Reduction of speeds

    Tight shut off of building(Lead to Sick building syndrome, Looses productivity and human health)

    Constructi

    on, 11%Financing,

    14%

    Alterations, 25%

    Operation, 50%

    Building Cost over 40 Years

  • Operating cost Case Study 1

    Gross area 1.2million sqft(=111,483 sqm)

    AC area 1.0million sqft(92,900 sqm)

    Tenant area 0.7 million sqft(65 000 sqm)

    House for 8000 people + 2000 Visitors

    Electricity/month 40million (about 1.7m kwh, max demand 5.5MVA), Installed capacity 11.2MVA

    5.5MVA/111,483sqm(=49VA/m2)

    Water /month 1.2million (About 500m3 per day)

    For 10 years

    Capex -20%

    Opex -80%

    AC, 37%

    Tenant, 20%

    Landloard, 18%

    AHU, 15%

  • Operating Cost Case study 2

    24 Storey Office building for Bank and tenants

    Approx Gross floor area 40000m2

    Air-condition area 28500m2

    Car parks 6000m2

    Electricity/month max demand 1600kVA, 600,000kWh

    1600kVA/40000m2 (=40VA/m2)

    Installed capacity, Electrical 2500kVA x 2 Nos

  • Energy share Case Study 2

    SLEMA Annual Sessions - 2010

    47%

    2%

    28%

    16%

    1%2%

    4%

    Air-Conditioning

    Fire & WaterSupplyLighting & Power -NormalCentral UPS

    Lifts

    Serv Bld - Ltg, Pow& Ventilation

    46%

    2%

    27%

    16%

    1%2%

    6%

    Air-Conditioning

    Fire & Water Supply

    Lighting & Power -NormalCentral UPS

    Lifts

    Serv Bld - Ltg, Pow& Ventilation

    46%

    2%

    28%

    16%

    1%2%

    5%

    Air-Conditioning

    Fire & Water Supply

    Lighting & Power - Normal

    Central UPS

    Lifts

    Serv Bld - Ltg, Pow &Ventilation

    Mar 2010 Apr 2010

    May 2010

  • Case Study 1

    1,700,000 kWh per month

    (1,700,000kWh/111,483m2)x12=182 kWh/m2 per year

    Case study 2

    600,000 kWh per month

    (600000kWh/40000m2) x 12 = 180 kWh/m2 per year

    Useful Data from BSRIA

    BSRIA(Building Services Research and Information Association)