Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
May 6, 2020
KANSAS CITY INTERNATIONAL AIRPORTNEW TERMINAL PROJECT
March 2020 Monthly Report
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
2,374FOUNDATION PILES DRILLED151KC METRO AREA
FIRMS ENGAGED
PEOPLE HAVE COMPLETED JOBSITE SAFETY TRAINING1,739 87 KCMO-CERTIFIED
M/WBE FIRMS ENGAGED
PROJECT UPDATE BY THE NUMBERS
Pictured below: New Terminal construction progress as of March 31, 2020.
*As of March 31, 2020
Edgemoor March Monthly Report | 1Kansas City International Airport New Terminal Project
Construction is vital to our communities. As such, the KCI New Terminal project, and numerous construction projects being built by other contractors across Kansas City, have been deemed essential infrastructure by the City of Kansas City, Missouri government (Order 20-01) and are continuing to safely operate in accordance with local health guidelines while a Stay-at-Home order is in effect. Protecting our workforce and enabling our trade partners to put their crews to work in a safe, controlled, and healthy environment is paramount. Given the current guidance from national industry and health authorities, such as the Occupational Safety and Health Association (OSHA) and Centers for Disease Control (CDC), as well as local health agencies, it is safe to keep our jobsite and project office open so long as we follow proper protocols for physical distancing, hand hygiene, and cleaning work areas.
The Edgemoor Team is taking every precaution to minimize the risk of infection on the New Terminal jobsite and has implemented these and other preventative strategies as part of our overall COVID-19 management plan:
1. Reinforce the importance of physical/social distancing, hand hygiene, and respiratory etiquette with the workforce, including:
• Frequent hand washing
• Avoiding touching nose, mouth, and eyes
• Avoiding handshaking or other close contact
• Covering mouth and nose with a tissue or elbow when coughing or sneezing
• Maintaining a safe, 6-foot distance from others
2. Educate workforce on the symptoms of COVID-19
3. Require individuals who are sick to stay home
4. Encourage high-risk individuals to stay home
5. Perform cleaning of frequently touched surfaces, portable toilets, and shared tools on the site
6. Implement measures for physical/social distancing including spreading out work as much as possible, deploying a rotational telework plan for management staff, and encouraging workforce to minimize close contact (within 6 feet of others) to the greatest extent possible
7. Immediate notification to Edgemoor / CWC leadership task force is required if anyone on the project has:
• Tested positive for COVID-19
• Had close contact with someone known to have tested positive for COVID-19
Protocols have been established in accordance with CDC and OSHA recommendations to address a confirmed case of COVID-19 on the jobsite or in the office, including isolating the individual, investigating and informing those who may be impacted, and disinfecting impacted areas.
This situation is ever-evolving and we are actively monitoring new developments. The Edgemoor Team remains fully committed to operating in accordance with the guidelines set forth by national industry and health authorities and local health agencies.
COVID-19 RESPONSE
Pictured above: A worker on the jobsite wearing a face covering in response to COVID-19.
Pictured above: Signage on the jobsite reminding workers to remain at least six feet apart per CDC guidelines.
Edgemoor March Monthly Report | 2Kansas City International Airport New Terminal Project
PROJECT BUDGET
Nearly sixteen percent (16%) of Edgemoor’s project budget has been spent as of March 31, 2020. The Total Project Cost of $1.5 Billion includes Edgemoor’s Revised Guaranteed Maximum Price (GMP) of $1.357 Billion. The Final GMP submitted by the Edgemoor Team on April 2 is currently under review by the Kansas City Aviation Department and their Owner’s Representative, Paslay Management Group (PMG).
EDGEMOOR CONTRACT VALUE
$1.357B$214.8M (16%)
SPENT TO
DATE
PROJECT SCHEDULE
Schedule Critical Path: As of the end of March, the next item on the schedule critical path is completion of the auger cast pile drilling by April 24, 2020.
Weather Days: During the month of March, Clark | Weitz | Clarkson (CWC) used six (6) of the Terminal schedule’s weather days due to rain that delayed work site-wide and specific activities related to concrete placement in the headhouse. Thirty-six (36) of 60 total weather days remain in the schedule.
UPCOMING MILESTONES
Pictured below: Graphic of numbered buildings in the New Terminal, identified for construction sequencing.
• Parking garage construction starts
SUMMER ‘20
• Terminal steel erection starts
• Passenger traffic moves to eastern access roadways
SPRING ‘20
• New Terminal opensMARCH ‘23
• Terminal precast & roofing starts
FALL ‘20
DEVELOPER PLEDGE
The graphs below illustrate the progress toward project goals of creating opportunities for minority and women-owned business and of inclusive workforce participation.
All data is through March 31, 2020, and the source is the City’s B2GNow reporting system.
There are a total of 188 subcontractors and sub-consultants engaged on the project by Edgemoor and CWC. Of these companies, 151 are based in the Kansas City Metro Area and 87 are KCMO-certified M/WBE firms. Through March, 295,587 workforce hours–roughly 5% of the expected 5.9 Million total hours–have been logged on the project.
WORKFORCE PARTICIPATION
GOAL2.75%
GOAL20.00%
MINORITIES18.25%
WOMEN4.70%
CONSTRUCTION SREVICES
16.42% MBE
M/WBE SUBCONTRACTOR PARTICIPATION
GOAL20.00%
12.88% WBE
PROFSSIONAL SERVICES GOAL
15.00%10.10% WBE
20.29% MBE
GOAL20.00%
GOAL15.00%
Pictured: United Rentals equipment yard adjacent to the Logistics Trailer Complex. As part of the TWEP Supplier Support Program,
all rentals are at project-wide rates, negotiated by CWC.
Pictured above: 32 KC SPP graduated on March 5.
Pictured above: The second Workforce Training Program class.
During March the project team:
• Held its second Workforce Training Program Class. Sixteen participants were sponsored by eight subcontractors on the project. The class began on March 9. Due to COVID-19 restrictions, the remaining two weeks of class were canceled; however, all participants received stipends as if they had completed the entire program. Graduation was not held. All trainees became apprentices with their unions and began work for their subcontractors by April 3, 2020. The third class is scheduled to begin in July, although timing will be depend on COVID-19 and associated restrictions in place at that time.
• Graduated its third Strategic Partnership Program class. Thirty-two MBE/WBE/SLBE/SDVOSB/VOSB businesses participated in the third KC Strategic Partnership Program. Capstone Project Presentations were held on February 13. Graduation was held on March 5. To date, there are a total of 12 KC SPP graduated firms that have been awarded contracts on the project. The fourth KC Strategic Partnership Program class will begin on September 10.
• Continues to offer extended childcare hours. Four out of five childcare center partners have continued to operate in light of COVID-19. All workers were reminded of the extended childcare hours program, which could be used to accommodate childcare constraints due to school closures.
• Continues to offer bus passes to all workers seeking to utilize the KCATA 529 KCI Limited Express route. Due to COVID-19 restrictions, the KCATA has begun offering free ridership to all patrons in the Kansas City area. Ridership data acquired from the KCATA shows 27 passes issued, a total of nine active riders, and a total of 142 trips made. Due to low ridership on the route, alternative transportation options are currently being discussed to support those workers that heavily rely on the route for transportation to and from the work site. The current pickup/drop off location for the 529 KCI Limited Express is at 12th and Charlotte in downtown Kansas City.
• Interviewed candidates for the Ombudsman job listing. Nineteen resumes were submitted in response to the job listing. Interested applicants were firms and individuals. Phone interviews were conducted with all nineteen applicants, which resulted in five applicants being viewed as qualified candidates. Video conference
TERMINAL WORKFORCE ENHANCEMENT PROGRAMS (TWEP)
interviews with the top candidates are currently being conducted. It is anticipated that an offer will be made the week of April 27.
• Continues to see a thriving On-Site Health Care Program. Since 2019, Mobile Medical Corporation has provided full-time Emergency Medical Technician/Paramedic services during all project work hours. The firm has participated in Monthly Safety Stand Downs, provided educational materials to employees, and assisted in safety orientation by addressing topics such as emergency response and COVID-19. To date, there have been 14 work-related visits and 27 wellness visits by project workers.
• Continues to see a thriving Supplier Support Program. Intended to leverage CWC’s purchasing power to enable MBE/WBE/SDVOSB/SLBE/VOSB firms to more effectively complete for work on the project, this program allows those firms to rent or purchase equipment at pre-negotiated rates. There have been six M/WBE firms that have taken advantage of this program.
Edgemoor March Monthly Report | 5Kansas City International Airport New Terminal Project
As of March 31, 2020, the value of executed subcontracts was approximately $614 million or 63%* of total anticipated subcontracted work. The Appendix E Procurement Log presents a summary of awarded, under review, and current procurement packages.
PROJECT PROCUREMENT
During March, the design-build team delivered the 100% Terminal Design Development, 60% Parking Garage, and 100% Landside and Airside Civil packages.
PROJECT DESIGN
$81M
$901M
PROFESSIONAL SERVICES92%
CONSTRUCTION SERVICES60%
AWARDED CONTRACTS AS %
OF TOTAL BUDGET
TERMINAL DESIGN PHASES
Program Validation
Concept Design
Schematic Design
Design Development
Construction Documents
30%0% 60% 90% 100%
BUDGET FOR SUBCONTRACTED WORK
CONSTRUCTION SERVICES
$901M
PROFESSIONAL SERVICES
$81M
TOTAL BUDGET$982M
*In the February 2020 report, the value of executed subcontracts was incorrectly reported as $681 million. The correct value of executed subcontracts for February 2020 was $613 million. In addition, awarded contracts as a percentage of total budget for Construction Services should have been reported in February as 60% rather than 55%.
Edgemoor March Monthly Report | 6Kansas City International Airport New Terminal Project
PROCUREMENT OPPORTUNITIES
RFP’s to be issued in June –
• Drywall, Framing, and Ceilings
• Rough Carpentry
• Doors, Frames, and Hardware
• Loading Dock Equipment
UPCOMING OPPORTUNITIES:
BIDS UNDER REVIEW:• Airside Civil
• Systems Integration
• Fire Protection (Sprinklers)
• Metal Stairs
• Roofing
• Overhead Coiling Doors
• Spray Fireproofing
• BIM - FM (Building Information Model to Facilities Management)
• Landside Parking Lots
• Masonry
• Louvers (Furnish Only)
• Joint Sealants & Air Barrier
• Misc. Metals
During March, construction activities included continuing slab on grade concrete placement at the south end of Concourse B and beginning slab on grade placement at the north end of Concourse A. Slab on Grade concrete placement continued at the south end of Concourse B.
Demolition:
• Crushing of the Terminal A concrete is complete• Bridge abutment removal is occurring along with
utility corridor excavation. Upon completion of the abutment removal, the demolition scope will be complete
Airside Civil:
• Storm and sanitary sewer lines are being installed under connector Buildings 7 and 8
• Pavement is being removed around the New Terminal footprint to allow for utility excavations
• Construction of a new Ground Service Equipment (GSE) fueling tank near Terminal C is ongoing
Landside Civil:• Construction of the eastern access roadways is
ongoing. These roadways are scheduled to be activated for the traveling public at the end of April
• New access to the FAA and Police parking lot will be completed after the eastern access roadways switchover
• Chilled water line relocation work is complete
• Installation of relocated electrical and data duct banks is ongoing
• Evergy installation of electrical service lines ongoing
• Construction of the new waterline will begin when signed drawings are received from the Water Services Department
New Terminal:
• Auger cast foundation pile placement for the New Terminal and elevated roadway is nearing completion with 2,374 of 2,724 total piles installed
• Foundation concrete, and MEP work across Concourses A and B and in selected parts of the headhouse (Buildings 10A-12A) is ongoing
• Slab on grade concrete placement in Buildings 1, 2, 13 and 14 is ongoing
• Crews are backfilling New Terminal foundation walls to provide a working pad for steel erection
• Steel erection is scheduled to begin on April 6
Pictured above: Crew smoothing concrete on new eastern access roadways. This photo was taken before COVID-19 protocols went into effect.
PROJECT CONSTRUCTION
Pictured above: Data and electrical conduit at the south end of Concourse A.
Pictured above: Preparation for slab on grade placement. This photo was taken before COVID-19 protocols went into effect.
Edgemoor March Monthly Report | 7Kansas City International Airport New Terminal Project
No significant corrective action was taken or proposed during the month of March, and there are no material disputes with respect to the work.
Below are current items the team is tracking closely and that require attention from all stakeholders. Each issue includes a description of steps the project team is taking to mitigate impacts that could occur as a result of these issues. We will provide updates on all items noted in the monthly reports until each is noted as resolved.
COVID-19March Update: As described earlier in this report, the Edgemoor Team is taking every precaution to minimizethe risk of infection on the New Terminal jobsite and has implemented a COVID-19 management plan. In coordination with the unions, CWC will implement a 4-day per week construction schedule, starting on April 13. As of March 31, 2020, CWC had received direct notice from one of its subcontractors, Schindler Elevator Corporation, that there was an impact to their supply chain for moving walkway procurement. This impact led to an additional three weeks of material lead-times. Any impacts to project costs or schedule as a result of COVID-19 will be tracked and reported to KCAD. Any impacts to time/cost/schedule/delays will be addressed in accordance with the Development Agreement, inclusive of any subsequent amendments thereto, if any.
POTENTIAL CONTAMINATED SOILSAugust 2019-February 2020: While removing pavement in the New Terminal footprint, workers noted a strong fuel odor in the vicinity of the existing aviation fuel line. Testing of soil samples from the area detected very low levels of contaminants in the soil. These levels are below the State’s Default Target Levels (DTL), and, as such, the soil may remain where it is. The team has established monitoring and storage protocols for any potentially contaminated soils and water in coordination with KCAD and in accordance with KCMO and Missouri Department of Natural Resources (MDNR) requirements. This item will remain on the list until below-grade excavation activities are complete and final test results from any soils or water, segregated due to potential contamination, have been received.
March Update: Contaminated soil continues to be encountered around the fuel lines that are being removed, and the soil is being tested and triaged with the intent of reusing the material on site. No contaminated soil or water has reached levels of contamination that would require disposal off-site, and monitoring is ongoing.
ITEMS WE ARE TRACKING
Pictured: Signage on the jobsite reminding workers of COVID-19 guidelines.
KANSAS CITY AVIATION DEPARTMENT AND AIRLINE PARTNERSDuring March, the team conducted previews of the 100% Design Development and 60% Parking Garage designs to kick-off the stakeholder reviews of these packages. In smaller group meetings, among many design topics reaching conclusion, the team worked to finalize plans for severe weather shelters within the New Terminal. The team held a review of the draft Final GMP documents with KCAD and the Airlines on April 2.
FEDERAL AGENCIES (FAA, CBP, TSA)The Edgemoor Team is working closely with several Federal agencies on New Terminal design and construction activities:
FAA: The team is making progress on the redesign of the North Courtyard, which is the site selected by the EA Mitigation Commission to commemorate the 1971-present airport terminal system. The next quarterly update meeting with the FAA will be held on April 9.
TSA: The team continues to work through TSA’s design review process for the BHS, Security Screening Check-Point (SSCP), and leasable and non-leasable TSA spaces in the New Terminal.
CBP: The team is responding to comments from CBP on the 30% design package and preparing for the next design submission.
MUNICIPAL ARTS COMMISSION (MAC)On March 3, design team members from SOM and BNIM, the firms responsible for the Terminal and Parking Garage designs, respectively, presented to the Project Advisory Artists, sharing the overall project design and highlighting public art locations for their consideration. The Executive Working Group quickly retooled plans for public outreach meetings during March and prepared an online presentation and survey. The survey invites public feedback on art in the New Terminal and will be available April 6-20.
AIRPORT USERSThe switch to the New Terminal eastern access roadways will occur at the end of April, and KCAD is planning media outreach to notify and explain this change to airport users.
PROJECT WORKFORCECWC held its monthly Safety Stand Down on March 4, but Safety Stand Downs have since been discontinued due to COVID-19. As of the end of March, 1,739 people have completed safety orientation. CWC is working diligently with subcontractors to maintain a safe and healthy job site.
COMMUNITY OUTREACHOn March 18, the Edgemoor Team joined KCAD and PMG to provide a project update to the City Council Transportation, Infrastructure & Operations Committee.
Also during March, in response to the closing of schools and many businesses as a result of COVID-19, the Edgemoor Team hosted a food and household supply drive to support the Morningstar Youth & Family Life Center in Kansas City, MO. Morningstar generously provides free resources to the surrounding community through tutoring, food, clothing, job skills training, and counseling.
Edgemoor’s Quarterly Project Update is issued to the community via email and at kci-edgemoor.com. Click the hyperlink above to view the Spring 2020 update. The team also provides updates on Twitter and Facebook @kciedgemoor.
STAKEHOLDER COMMUNICATIONS
Pictured above: The Edgemoor Team gathered food and household supplies for Morningstar Youth & Family Life Center to help community members effected by COVID-19.
Edgemoor March Monthly Report | 9Kansas City International Airport New Terminal Project
PROJECT GOVERNANCE
During March, the Project Management Committee (PMC) and Steering Committee (SC) reviewed and approved the following costs:
• Addition of security exit control devices on the Arrivals level (use of Design Evolution Contingency)
• Mechanical and Plumbing procurement (use of Design Evolution Contingency)
• Reroute of a portion of an existing stormwater box culvert (use of Design Evolution Contingency)
• Increase size of replacement water main from 12” to 16” diameter (use of Design Evolution Contingency)
• Redesign of the North Courtyard to comply with EA Mitigation Commission scope (use of Owner Contingency)
• Point-to-point hearing induction units for assistance to hearing impaired travelers (use of Owner Contingency)
• Various smaller-scale items for which PMC and SC approved the use of Design Evolution or Owner Contingency
The PMC provides direction on major decisions for the project and is composed of one representative each from KCAD, Edgemoor and the airlines:
• KCAD: David Long, Deputy Director
• Edgemoor: Geoff Stricker, Senior Managing Director
• Airlines: William Manning, Airline Technical Representative
The SC oversees the PMC and is required to approve PMC decisions regarding issues that materially affect airline operations, project schedule, or project scope, or that affect the payments required of the airlines under the Airline Use and Lease Agreement. The SC is composed of one Airline Representative and the Director of the Kansas City Aviation Department.
• Airlines: Kyle O’Neal, Southwest Airlines
• KCAD: Pat Klein, Director
Pictured: View of concrete columns in what will be the lower level of the New Terminal headhouse.
TEAM MEMBER PROFILE
Your background is impressive with multiple degrees and 18 years of experience building a national reputation in education and nonprofit development. How did you end up in construction and how does your experience apply to TWEP.
This program is basically my career come-full-circle. It is the perfect blend of my background in charter school development, nonprofit development, and economic and financial education. I’ve worked with major private foundations established by America’s most entrepreneurial families (Waltons and Kauffmans) to build charter schools in Little Rock and Kansas City, and have worked with the Cray Foundation to further expand my career in the entrepreneurship, and economic and financial education sectors. I was an educator who saw education through a business lens, and I developed a national reputation in that arena.
I was working on my EMBA at Rockhurst in 2017 when I heard publicity about plans at KCI and how it could open up opportunities for minority and women-owned businesses. With the encouragement of a dear friend, I considered starting a new business for myself in the construction arena, and I wanted to learn the industry. I started my own company, Rhys Ivy, a name which represents my daughter’s middle name, Rhys; Ivy is the Greek symbol for wealth. It was time to learn the vernacular of construction, so I became a member of the second graduating class of the KC Strategic Partnership Program in 2018. It was a valuable crash course on the construction industry.
3 Questions with Latoya Goree, Executive DirectorCompany: Clark | Weitz | ClarksonProject Scope: Terminal Workforce Enhancement Programs
In my new role, I am putting my past experience to work. I was skilled at running multiple organizations at once. When this opportunity came up two and a half months ago, I didn’t skip a beat. I left my prior job on a Friday and started on Monday as Executive Director of TWEP. Since the very beginning, I felt very supported by Edgemoor and CWC – we understand each other’s vision for TWEP.
What is your vision for TWEP?
The TWEP agreement that Edgemoor developed for the New Terminal at KCI is, among so many other things, supportive of small businesses by providing financial opportunities through low-interest loans and helping smaller construction companies with bonding support. The agreement helps the workforce with transportation and childcare, as well as training and long-term career development.
When I moved to Kansas City in 2010 to open the Ewing Marion Kauffman School, my personal philosophy was that hard work, dedication, and a sense of urgency are the driving forces behind success, and your socioeconomic background does not determine your destiny. On opening day of the New Terminal at KCI, I hope to see the smiling faces of small business owners–minorities, women and veterans–who have strengthened their businesses by taking full advantage of as many of the 15 Terminal Workforce Enhancement Programs as were available to them and are there to celebrate their own company’s success.
With the COVID-19 challenges, how has your work been impacted?
The New Terminal project is moving ahead, and work has not stopped. Edgemoor and CWC have done a great job of implementing measures to keep our workers safe. In the case of the Workforce Training program, which had just begun its second class and was one week into the training during the onset of COVID-19 in KCMO, the guest instructors were not going to be available during the quarantine period. Even though we had to cancel the remaining classes, all of our trainees were designated as apprentices with their unions and began work with their new employers as planned.
Edgemoor March Monthly Report | 11Kansas City International Airport New Terminal Project
ACRONYMS & DEFINITIONS
BHS Baggage Handling System
CBP Customs and Border Protection
CWC Clark | Weitz | Clarkson, A Joint Venture (Project Design-Builder)
DTL Default Target Levels
FAA Federal Aviation Administration
GMP Guaranteed Maximum Price
GSE Ground Service Equipment
ICS Individual Carrier System (type of BHS)
KCAD Kansas City Aviation Department
KCATA Kansas City Area Transportation Authority
KCI Kansas City International Airport
KCMO Kansas City, Missouri
MAC Municipal Arts Commission
MBE Minority-Owned Business Enterprise
MCI Airport Code for KCI Airport (Mid-Continent International)
MDNR Missouri Department of Natural Resources
PMC Project Management Committee
PMG Paslay Management Group (Owner’s Representative)
RFP Request for Proposals
SC Steering Committee
SD Schematic Design
SOM Skidmore, Owings & Merrill LLP (Project Lead Designer)
SSCP Security Screening Check-Point
TSA Transportation Security Administration
TWEP Terminal Workforce Enhancement Programs
VSR Vehicle Road Service
WBE Woman-Owned Business Enterprise
Appendix A
Edgemoor March Monthly Report | 12Kansas City International Airport New Terminal Project
STORED MATERIALS
The Pay Application for the period through March 31, 2020 included a cumulative gross value of $12,529,511 in stored materials located at the steel subcontractor fabrication plant. The request was accompanied by all documentation required for stored materials.
Appendix B
Edgemoor March Monthly Report | 13Kansas City International Airport New Terminal Project
SUBMITTALS LOG
Appendix C
KCI Outstanding Submittal Item Report Update (Owner)
Number Coordinator Description Type Date Sent Due DateDays in
Review
O-010001-058 Tammy HoushC-0139 - Concurrence Request - Aviation Fuel
Above Ground Manifold at ConnectorConcurrence 1/17/2020 1/31/2020 70
O-010001-101 Tammy HoushC-0184 Concurrence Request - Apron Pavement
Removal for Airside UtilitiesConcurrence 2/14/2020 2/28/2020 42
O-010001-067 Tammy HoushC-0144 Concurrence Request - RFI O-0134 CUP
Water Infiltration Through Existing Lighting ConduitsConcurrence 2/24/2020 3/9/2020 32
O-010001-081 Tammy HoushC-0133 Concurrence Request for Trade Parking
Lot ImprovementsConcurrence 2/25/2020 3/10/2020 31
O-010001-089 Tammy HoushC-0174 - Concurrence Request - G2A - RMC
Temporary Water Main RerouteConcurrence 2/25/2020 3/10/2020 31
O-010001-097 Tammy HoushC-0189.1 Concurrence Request - Gas Line Crimp,
Tie in, and Cut and CapConcurrence 2/25/2020 3/10/2020 31
O-010001-098 Tammy HoushC-0190 Concurrence Request - KCI Landside RCB
InstallationConcurrence 2/25/2020 3/10/2020 31
O-013100-027 Greg KingProcurement Garage Glazing Package RFP Docs
- Add’n 1Procurement 2/25/2020 3/10/2020 31
O-010001-106 Tammy HoushC-0199 Concurrence Request - KCAD-FD
0002 Replacement of Existing 400A-480/277V Panelboard
Concurrence 2/28/2020 3/13/2020 28
O-010001-083 Tammy HoushC-0167 Concurrence Request - Excavate and Haul
Excess Material to Apron StockpileConcurrence 3/2/2020 3/16/2020 25
O-013100-029 Greg KingProcurement Garage Glazing Package RFP Doc -
Add’n 2Procurement 3/2/2020 3/16/2020 25
O-010001-099 Tammy HoushC-0192 Concurrence Request - G2A - RMC -
Pothole for Existing Utilities Along Bonn Cir.Concurrence 3/3/2020 3/17/2020 24
O-010001-105 Tammy HoushC-0196 Concurrence Request - Procure Street
Light Pole Anchor Bolts - Group 2B, 3, & 4Concurrence 3/3/2020 3/17/2020 24
O-010001-125 Tammy HoushC-0219 Concurrence Request - Parking Garage -
Glass & Glazing ProcurementConcurrence 3/10/2020 3/24/2020 17
O-010001-102 Tammy HoushC-0111 Concurrence Request - CWC Office
Janitorial Cleaning ServicesConcurrence 3/11/2020 3/25/2020 16
O-013200-011 Tammy Housh Submittal Log - Garage Information Only 3/12/2020 3/26/2020 15
O-220529-001 Komal Patel Terminal- Plumbing Hanger & Support Product Data Product Data 3/12/2020 3/26/2020 15
O-221300-005 Komal PatelTerminal - CUP Boiler Floor Drain FD-11 Product
DataProduct Data 3/12/2020 3/26/2020 15
O-235213-001 Komal Patel Terminal- MP- Electric Boiler Product Data Product Data 3/12/2020 3/26/2020 15
O-010001-137 Tammy HoushC-0230 Concurrence Request - Entire Parking
Garage ProcurementConcurrence 3/18/2020 4/1/2020 9
O-010001-066 Tammy HoushC-0142 Concurrence Request - Remove 20,000
Gal UST / GSE Fuel TankConcurrence 3/24/2020 4/7/2020 3
O-010001-071 Tammy HoushC-0148 Concurrence Request For Expenditure:
200 LF 8” Natural Gas Line Extension & Cut & Cap 10” Line
Concurrence 3/24/2020 4/7/2020 3
O-010001-110 Tammy Housh
C-0202 Concurrence Request - Additional Pavement Between Bridge Approach Slabs and Limits of Roundabout Construction at Terminal B
and Terminal C
Concurrence 3/24/2020 4/7/2020 3
Edgemoor March Monthly Report | 14Kansas City International Airport New Terminal Project
SUBMITTALS LOG (CONT.)
Appendix C
KCI Outstanding Submittal Item Report Update (Owner) (cont.)
*Data from March 27, 2020.Submittal Responses Pending:0-14 Days: 27 15-30 Days: 11 30+ Days: 9
Number Coordinator Description Type Date Sent Due DateDays in
Review
O-010001-111 Tammy HoushC-0203 Concurrence Request - – Group 2B
Temporary FAA Access Rock Shoulder for WB-67 Off-Tracking
Concurrence 3/24/2020 4/7/2020 3
O-010001-112 Tammy HoushC-0205 Concurrence Request - Group 2B IFC
True UpConcurrence 3/24/2020 4/7/2020 3
O-010001-113 Tammy HoushC-0206 Concurrence Request - Southwest Airlines
- Tenant ImprovementConcurrence 3/24/2020 4/7/2020 3
O-010001-115 Tammy HoushC-0208 Concurrence Request - Refeeding of
Existing Roadway Light PoleConcurrence 3/24/2020 4/7/2020 3
O-010001-116 Tammy HoushC-0210 Concurrence Request - VSR Road
Modification for Turning RadiusConcurrence 3/24/2020 4/7/2020 3
O-010001-118 Tammy HoushC-0211 Concurrence Request - Unforeseen
Conditions - Abandoned VaultConcurrence 3/24/2020 4/7/2020 3
O-010001-119 Tammy HoushC-0212 Concurrence Request - Added Floor Drains
to Chase WallsConcurrence 3/24/2020 4/7/2020 3
O-010001-120 Tammy HoushC-0214 Concurrence Request - Kitchenette - Mop
Sink Back of HouseConcurrence 3/24/2020 4/7/2020 3
O-010001-122 Tammy HoushC-0216 Concurrence Request - Add Grease Waste
BackupConcurrence 3/24/2020 4/7/2020 3
O-010001-123 Tammy HoushC-0217 Concurrence Request - Add Floor Drain for
Ice Maker (KCAD Custodial)Concurrence 3/24/2020 4/7/2020 3
O-010001-126 Tammy HoushC-0220 - Concurrence Request - Added Floor
Drains in VT Maintenance RoomsConcurrence 3/24/2020 4/7/2020 3
O-010001-127 Tammy HoushC-0222 Concurrence Request - Fire Protection
UndergroundConcurrence 3/24/2020 4/7/2020 3
O-010001-128 Tammy HoushC-0233 Concurrence Request - KCAD-FD-0015 -
Cut & Cat Hydrant Lines West Side of Bldg 3 Grade Beam Excavation
Concurrence 3/24/2020 4/7/2020 3
O-010001-130 Tammy HoushC-0225 Concurrence Request - Cut & Cap to
A,B,C,D & E and Remove Fuel on Existing MainConcurrence 3/24/2020 4/7/2020 3
O-010001-131 Tammy HoushC-0226 Concurrence Request - Additional Fuel
Removal from Low Points in LinesConcurrence 3/24/2020 4/7/2020 3
O-010001-133 Tammy HoushC-0227 Concurrence Request - Natural Gas Line Crimp, Tie-in, and Cut & Cap the Existing Main
Concurrence 3/24/2020 4/7/2020 3
O-010001-134 Tammy HoushC-0172 Concurrence Request - Design Services -
Evergy Switchgear EnclosureConcurrence 3/24/2020 4/7/2020 3
O-010001-139 Tammy HoushC-0236 Concurrence Request - Grading Credit for
RenascentConcurrence 3/24/2020 4/7/2020 3
O-010001-140 Bruce MellingerC-0237 Concurrence Request - HRD Wage
Determination AmendmentConcurrence 3/24/2020 4/7/2020 3
O-010000-038 Diane EvansTerminal Bldg. Design Development (100%
Submission) For Record OnlyFor Record 3/25/2020 3/25/2020 2
O-010000-039 Diane Evans Garage (60% Submission) For Record Only For Record 3/25/2020 3/25/2020 2
O-010000-040 Diane Evans Civil Group 4 Parking Lot (90% Sub) For Record Only For Record 3/25/2020 3/25/2020 2
O-236416-001 Komal Patel Terminal- Chiller Product Data Product Data 3/26/2020 4/9/2020 1
Edgemoor March Monthly Report | 15Kansas City International Airport New Terminal Project
Item No. Date Report No. Location Discrepancy Resolution Date
Resolved
10 8/15/19CTR:0336100-40-C1
Connector Road permanent pavement section, 10’ South of North end of section
Concrete sample failed to meet mix design compressive strength of 4,500 psi. Average 28-day compressive strength result: 3,870 psi.
47 2/3/20 FC:0336100-164Terminal B Roundabout paving, outer lane; Sta
3+15 to 4+35
Concrete sample C2 exceeded mix design specification for slump. 5"
maximum slump specified; 6.25" slump tested.
Concrete sample exceeded the mix design compressive strength
of 4,500 psi. Average 28-day compressive strength result:
6,520 psi.
3/2/20
48 2/8/20 FC:0336100-169Terminal B Roundabout paving, inside lane; Sta
4+75 to 2+25
Concrete sample C3 exceeded mix design specification for slump. 5"
maximum slump specified; 6.25" tested.
Concrete sample exceeded the mix design compressive strength
of 4,500 psi. Average 28-day compressive strength result:
7,150 psi.
3/9/20
49 2/11/20 FC:0336100-171Terminal B Roundabout paving, outer lane; Sta
5+35 to 1+65
Concrete sample C1 exceeded mix design specification for slump. 5"
maximum slump specified; 7" tested.
Concrete sample exceeded the mix design compressive strength
of 4,500 psi. Average 28-day compressive strength result:
6,950 psi.
3/10/20
50 2/17/20 FC:0336100-174Terminal B Roundabout paving, inside lane; Sta
2+10 to 2+75
Concrete sample C1 exceeded mix design specification for slump. 5"
maximum slump specified; 5.75" tested.
51 2/18/20 FC:0336100-175Terminal B Roundabout
paving, outer lane at inflow; Sta 2+10 to 2+75
Concrete sample C1 exceeded mix design specification for slump. 5"
maximum slump specified; 5.5" tested.
52 2/28/20 FC:0336100-1842A Duct Bank conduit
encasement; Sta 218+00 to 219+00
Concrete sample C1 exceeded mix design specification for slump. 3"
maximum slump specified; 3.75" tested.
53 3/2/20 FC:0336100-185Isolation Valve Vault-1
structure walls
Concrete sample C1 exceeded mix design specification for slump. 6"
maximum slump specified; 7.25" tested.
Concrete sample exceeded the mix design compressive strength
of 5,000 psi. Average 28-day compressive strength result:
5,740 psi.
3/30/20
54 3/6/20 FDR:0336100-189Storm sewer backfill at FAA tower North Drive entrance
at Sta 3+10
Density tests S3 & S5 failed to meet specifications for moisture content and
compaction.
Failing areas retested and met project specifications for
compaction and moisture content. See FDR:0336100-
202.
3/26/20
55 3/6/20 FC:0336100-189Isolation Valve Vault-1
structure roof slab
Concrete sample C2 exceeded mix design specification for slump. 5"
maximum slump specified; 10" tested.
Concrete sample exceeded the mix design compressive strength
of 5,000 psi. Average 28-day compressive strength result:
5,320 psi.
56 3/6/20 FC:0336100-189Isolation Valve Vault-1
structure roof slab
Concrete sample C2 did not meet mix design specification for air content. 5% to 8% specified; 3.2% tested. Average
28-day compressive strength: 5,320 psi.
57 3/11/20 FC:0336100-192
Terminal C Roundabout paving, West Outflow,
Inside Lane Sta 6+36 to 7+50
Concrete sample C1 exceeded mix design specification for slump. 5"
maximum slump specified; 5.25" tested.
Concrete sample exceeded the mix design compressive strength
of 4,500 psi. Average 28-day compressive strength result:
5,460 psi.
58 3/20/20 PRR:0336100-198Existing Cookingham Dr.
widening subgradeProofroll of subgrade exhibited rutting
and pumping greater than 1".
Failing areas remediated and passed a subsequent proofroll on 4/1/2020. See
PRR:0336100-206.
Civil Discrepancy LogItems identified and resolved within a reporting period will not be included on this list.
MATERIALS TESTING & INSPECTIONS LOG
Appendix D
Edgemoor March Monthly Report | 16Kansas City International Airport New Terminal Project
Item No. Date Report No. Location Discrepancy Resolution Date
Resolved
59 3/25/20 PRR:0336100-201Existing Cookingham Dr. widening subgrade from
Sta 5+00 to 5+75
Proofroll of subgrade exhibited rutting and pumping greater than 1".
Failing areas remediated and passed a subsequent proofroll on 4/1/2020. See
PRR:0336100-206.
60 3/25/20 FC:0336100-2012A Duct Bank conduit
encasement; 0' to 30' East of Sta 228+45
Concrete sample C2 exceeded mix design specification for air content. Air content tested at 8.0 percent, and 4.5 to 7.5 percent air content is specified. Average 28-day compressive strength:
5,370 psi.
61 3/31/20 PRR:0336100-205North Drive subgrade from
Sta 1+00 to Sta 2+59Proofroll of subgrade exhibited rutting
and pumping greater than 1".
Failing areas remediated and passed a subsequent proofroll on 4/1/2020. See
PRR:0336100-206.
Civil Discrepancy Log (cont.)Items identified and resolved within a reporting period will not be included on this list.
MATERIALS TESTING & INSPECTIONS LOG (CONT.)
Appendix D
Edgemoor March Monthly Report | 17Kansas City International Airport New Terminal Project
Data provided by Intertek-PSI, Materials Testings and Inspections Consultant for the New Terminal project.
Discrepancies and resolutions reported through: 3/31/20.
Terminal Discrepancy Log - SubgradeItems will remain on this log until resolved.
MATERIALS TESTING & INSPECTIONS LOG (CONT.)
Appendix D
Discrepancies and resolutions reported through: 3/31/20.
Edgemoor March Monthly Report | 18Kansas City International Airport New Terminal Project
Item No. Date Report No. Location Discrepancy Resolution Date
Resolved
10 12/2/19 FDR:0336101-126Terminal Y, Building 1 Low-
volume-change material (LVC)
Nuclear field density test results S18 through S22 failed to meet compaction
specification.
Failing areas retested and met compaction specification on
3/3/2020. See FDR:0336101-300 & FDR:0336101-347.
3/3/20
15Terminal Y, Building 2 trench backfill at grid line YS17.9
18 inches of recycled concrete placed within the LVC zone. Geotechnical report states the building slab should have a minimum
of 18" of the approved LVC material placed beneath it (Type 5 Baserock).
Area was re-worked as part of electrical conduit installation. PSI observed the required thickness of LVC material had been placed
at the detailed location. See FDR:0336101-391.
3/17/20
25 2/10/20 FDR:0336101-276 Terminal Y, Building 5 LVCNuclear density test results S1 through S4 failed to meet compaction specification.
Failing areas retested and met compaction specification on
3/24/2020. See FDR:0336101-409.
3/24/20
30 3/4/20 FDR:0336101-352Building 13 electrical trench
backfill at grid location XN20/W8.5
Nuclear density test result S6 failed to meet compaction specification.
Failing area retested and met compaction specification on
2/18/2020. See FDR:0336101-300.
3/13/20
31 3/7/20 FDR:0336101-363Building 2 electrical trench
backfill at grid location W30/YS17
Nuclear density test result S9 failed to meet compaction specification.
Failing area retested and met compaction specification on
3/11/2020. See FDR:0336101-375.
3/11/20
32 3/24/20 FDR:0336101-409 Building 5 LVCNuclear density test results S7 & S10 failed
to meet compaction specification.
Failing area retested and met compaction specification on
3/25/2020. See FDR:0336101-413.
3/25/20
33"3/30/2020 4/27/2020"
"PRR:0336101-425 PRR:0336101-503"
Building 10B building pad subgrade proofroll
Pumping and rutting in excess of 1" observed in the building pad subgrade.
34 3/30/20 PRR:0336101-429Building 11A building pad
subgrade proofrollPumping and rutting in excess of 1"
observed in the building pad subgrade.
Terminal Discrepancy Log - Auger Cast PilesItems will remain on this log until resolved.
Item No. Date Report No. Location Discrepancy Resolution Accepted
by CityDate
Resolved
1 11/27/19 N/ATerminal Y, Buildings 1-6, auger cast piles placed by 11/5/2019
See attached Non-Conforming Auger Cast Piles reports for Buildings 1 through 6. Detailed piles are out of compliance for one or more of the following
criteria: horizontal pile placement, top of pile reinforcing steel and grout elevation. The design
engineer, Berkel, has proposed fixes that have been reviewed by SOM. Pile fixes are in progress as pile
caps and grade beams are being placed.
2 12/30/19 N/ATerminal X, Buildings 12A-14,
auger cast piles placed by 12/9/2019
See attached Non-Conforming Auger Cast Piles reports for Buildings 12A through 14. Detailed
piles are out of compliance for one or more of the following criteria: horizontal pile placement, top of
pile reinforcing steel and grout elevation. The design engineer, Berkel, has proposed fixes that have been reviewed by SOM. Pile fixes are in progress as pile
caps and grade beams are being placed.
3 10/29/19 USR:0336101-74Terminal Y, auger cast pile
5-127 at grid line YN5/W32
Pile 5-127 encountered auger refusal at a drill depth of 28 feet. Final length of pile is 20.4 feet, design
length of pile is 27.97 feet.
Sealed letter from W. Morgan NeSmith with Berkel accepting as-built conditions. Letter dated 12/6/2019.
4 10/29/19 USR:0336101-74Terminal Y, auger cast pile
5-127 at grid line YN5/W32
Six (6) feet of reinforcing steel removed from the lower end of the cage. Design length of cage for type to reinforcing is 23.25 feet, observed was
length 17.25 feet.
Sealed letter from W. Morgan NeSmith with Berkel accepting as-built conditions. Letter dated 12/6/2019.
5 11/2/19 USR:0336101-82Terminal Y, auger cast pile 2-38
at grid line YS21/W30.7
Reinforcing steel cage did not reach design elevation. Top of cage was 6 inches higher
than design elevation. As-built drawings with recommendations have been submitted.
Reinforcing steel elevation observed to be ok prior to pile cap concrete
placement on 12/12/2019.
6 11/20/19 USR:0336101-112Terminal Y, auger cast pile 6-37
at grid line YN20/W31
Pile 6-37 encountered auger refusal at a drill depth of 48 feet. Final length of pile is 45.8 feet, design
length of pile is 46.6 feet.
Sealed letter from W. Morgan NeSmith with Berkel accepting as-built conditions. Letter dated 12/6/2019.
7 11/21/19 USR:0336101-114Terminal Y, auger cast pile 6-50
at grid line YN17/W30
Pile 6-50 encountered auger refusal at a drill depth of 45 feet. Final length of pile was 43.3 feet, design
length of pile is 53.08 feet.
Additional pile (6-78) installed at grid line YN17/W30 to meet loading
capacities per the recommendation by W. Morgan NeSmith with Berkel. Pile
installed on 12/2/2019.
8 11/21/19 USR:0336101-114Terminal Y, auger cast pile 6-18
at grid line YN15/W31
Pile 6-18 encountered auger refusal at a drill depth of 34 feet. Final length of pile is 34.3 feet, design
length of pile is 46.58 feet.
Additional piles (6-79 and 6-80) installed at grid line YN15/W31 to meet loading capacities per the recommendation by W. Morgan
NeSmith with Berkel. Piles installed on 12/2/2019 and 12/3/2019.
9 11/22/19 USR:0336101-116Terminal X, auger cast pile 14-
97 at grid line XN23/W6
Pile 14-97 has final length of 37.7 feet. Per the pile schedule dated 10/23/19, design length the pile
14-97 is 42.42 feet. Updated pile schedule dated 11/26/19 has a design length of 38.02 feet for the
detailed pile.
Sealed letter from W. Morgan NeSmith with Berkel stating the
tip elevation for the detailed pile is installed at the correct elevation.
Letter dated 12/6/2019.
10 11/22/19 USR:0336101-116Terminal X, auger cast pile 14-
99 at grid line XN22/W6
Pile 14-99 has final length of 36.7 feet. Per the pile schedule dated 10/23/19, design length the pile
14-99 is 42.42 feet. Updated pile schedule dated 11/26/19 has a design length of 38.02 feet for the
detailed pile.
Sealed letter from W. Morgan NeSmith with Berkel stating the
tip elevation for the detailed pile is installed at the correct elevation.
Letter dated 12/6/2019.
11 11/22/19 USR:0336101-116Terminal X, auger cast pile 14-
84 at grid line XN21/W7
Pile 14-84 has final length of 36.7 feet. Per the pile schedule dated 10/23/19, design length the pile
14-84 is 39.42 feet. Updated pile schedule dated 11/26/19 has a design length of 38.02 feet for the
detailed pile.
Sealed letter from W. Morgan NeSmith with Berkel stating the
tip elevation for the detailed pile is installed at the correct elevation.
Letter dated 12/6/2019.
MATERIALS TESTING & INSPECTIONS LOG (CONT.)
Appendix D
Edgemoor March Monthly Report | 19Kansas City International Airport New Terminal Project
Terminal Discrepancy Log - Auger Cast Piles (cont.)Items will remain on this log until resolved.
MATERIALS TESTING & INSPECTIONS LOG (CONT.)
Appendix D
Edgemoor March Monthly Report | 20Kansas City International Airport New Terminal Project
Item No. Date Report No. Location Discrepancy Resolution Accepted
by CityDate
Resolved
12 11/25/19 USR:0336101-119
Terminal X, auger cast piles 14-43, 14-18 & 13-25 at grid lines XN21/W9, XN21/W10 & XN20/
W9, respectively
Detailed piles had the lower 4 feet of reinforcing steel cage removed due pile length. Design
length of cage for Type 2 reinforcing is 23.25 feet, observed length was 19.25 feet.
Sealed letter from W. Morgan NeSmith dated 12/6/2019
acknowledges the modified cage, and email from the structural engineer with Berkel, Richard
Guenther, states the shorter cage is acceptable.
13 11/26/19 USR:0336101-121
Terminal X, auger cast piles 14-42, 14-17, 13-80, 13-47 at grid lines XN21/W9, XN21/W10, XN15/W8 & XN15/W9,
respectively
Detailed piles had the lower 4 feet of reinforcing steel cage removed due pile length. Design
length of cage for Type 2 reinforcing is 23.25 feet, observed length was 19.25 feet.
Sealed letter from W. Morgan NeSmith dated 12/6/2019
acknowledges the modified cage, and email from the structural engineer with Berkel, Richard
Guenther, states the shorter cage is acceptable.
14 11/26/19 USR:0336101-121
Terminal X, auger cast piles 13-86, 13-64, 13-61, 12A-1 & 12A-5 at grid lines XN13/W8, XN12.5/W8.5, XN12/
W9, XN11/W10 & XN9.7/W10, respectively
Per the pile schedule dated 11/26/19, the detailed piles are designated as end bearing piles. It
appeared drilling was terminated at 80 feet w/out refusal at each pile.
Sealed letter from W. Morgan NeSmith with Berkel stating all the detailed piles extend to shale at
elevation 920'.
15 11/26/19 USR:0336101-121Terminal X, auger cast pile 13-
26 at grid line XN20/W9.
Ground surface elevation for pile 13-26 does not appear to match with the elevation provided by Berkel. The working surface is approximately 2
feet below working pad elevation of 999.75', top of reinforcing steel cage is extending above pile cutoff
elevation.
Sealed letter from W. Morgan NeSmith with Berkel stating the pile was placed on a slope with the surrounding grade built up
to provide a flat surface to install the pile. As-built drawings state the pile is installed at the correct
recommendation.
16 12/2/19 USR:0336101-125
Terminal X, auger cast piles 13-79, 13-50, 14-40 & 14-15 at grid lines XN15/W8, XN15/W9, XN21/W9 & XN21/W10,
respectively
Detailed piles had the lower 4 feet of reinforcing steel cage removed due pile length. Design
length of cage for Type 2 reinforcing is 23.25 feet, observed length was 19.25 feet.
Sealed letter from W. Morgan NeSmith dated 12/6/2019
acknowledges the modified cage, and email from the structural engineer with Berkel, Richard
Guenther, states the shorter cage is acceptable.
17 12/5/19 USR:0336101-133Terminal X, auger cast piles 13-13 & 13-11 at grid line
XN16/W9.5
Detailed piles have a design length of 44.4 feet per the pile schedule dated 11/26/2019. The observed
pile length is approximately 26 feet.
Sealed letter from W. Morgan NeSmith with Berkel stating the
updated pile lengths are correct and will be reflected in the next set of
drawings. Updated drawings dated 1/10/20 reflect this change. Design
length is 25.42 feet.
18 12/6/19 USR:0336101-135Terminal X, auger cast piles 13-14 & 13-12 at grid line
XN16/W9.5
Detailed piles have a design length of 44.4 feet per the pile schedule dated 11/26/2019. The observed pile length is 26.6 feet. Representatives with Berkel stated the design length of the piles had changed.
Sealed letter from W. Morgan NeSmith with Berkel stating the
updated pile lengths are correct and will be reflected in the next set of
drawings. Updated drawings dated 1/10/20 reflect this change. Design
length is 25.42 feet.
19 12/23/19 USR:0336101-159Terminal X, auger cast pile
9-218 at grid line XS19/W7
Pile 9-218 encountered auger refusal at tip elevation 943.2'. Design tip elevation is 938'. Installed length of pile is 47.8 feet; design length of pile is 53 feet.
Final pile length is approximately 5.2 feet short.
Sealed letter from W. Morgan NeSmith with Berkel stating the
condition of the shorter pile has been reviewed and will be included in the
next round of as-built analysis. Email from the structural engineer with
Berkel, Richard Guenther, stating the as-built location of the detailed pile does not cause major concern and Berkel is ok to install the adjacent
pile.
Terminal Discrepancy Log - Auger Cast Piles (cont.)Items will remain on this log until resolved.
MATERIALS TESTING & INSPECTIONS LOG (CONT.)
Appendix D
Discrepancies and resolutions reported through: 3/31/20.
Edgemoor March Monthly Report | 21Kansas City International Airport New Terminal Project
Item No. Date Report No. Location Discrepancy Resolution Accepted
by CityDate
Resolved
20 1/14/20 USR:0336101-203Terminal X, auger cast pile 12A-
51 at grid line W7.5/W11.5
Per the pile schedule dated 1/14/2020, the detailed pile is designated as an end bearing pile. It
appeared drilling was terminated at 84 feet w/out refusal at pile.
Sealed letter from W. Morgan NeSmith with Berkel stating the
detailed piles appear to have been drilled into underlying shale capable of providing sufficient resistance to
limit pile movements.
21 1/15/20 USR:0336101-207Terminal X, auger cast pile 12A-
52 at grid line W7.5/W11.5
Per the pile schedule dated 1/14/2020, the detailed pile is designated as an end bearing pile. It
appeared drilling was terminated at 80 feet w/out refusal at pile.
Sealed letter from W. Morgan NeSmith with Berkel stating the
detailed piles appear to have been drilled into underlying shale capable of providing sufficient resistance to
limit pile movements.
22 4/1/20 USR:0336101-430Building 11B auger cast pile 11B-119 at grid line W3/XN4
Pile 11B-119 encountered auger refusal at tip elevation 939.2'. Design tip elevation is 924'.
Installed length of pile is 44.8 feet; design length of pile is 59.92 feet. An email from Richard Guenther with Berkel dated 4/1/2020 indicates the pile is ok
as installed.
MATERIALS TESTING & INSPECTIONS LOG (CONT.)
Appendix D
Terminal Discrepancy Log - Pile Caps & Grade BeamsItems will remain on this log until resolved.
Item No. Date Report No. Location Discrepancy Resolution Date
Resolved
1 12/10/19 RSI:0336101-141Building 1 pile cap & pilaster
at grid line YS27/W29
"4F Special-1 Pilaster" reinforcing steel placed per field use shop drawing detail on sheet R1.02 dated
11/25/2019. Reinforcing steel differs from city approved structural drawings dated 10/21/2019.
2 12/11/19 RSI:0336101-144Building 1 pile caps at grid lines YS25 & YS26.3/W30
Pile caps reinforcing steel placed per field use shop drawings detail "Pile Cap PC2-16G" on
sheet R1.01 dated 11/25/2019. Reinforcing steel differs from city approved structural drawings
dated 10/21/2019.
3 12/11/19 RSI:0336101-144Building 2 grade beams and pile caps at grid lines YS23/W29-30.2 & W29/YS23-22.8
Grade beam dimensions and reinforcing steel placed per field use shop drawings details on
sheet R2.03 & R2.02, dated 11/1/2019 & drawing RW-01 (RFI C-0264) dated 11/5/2019. Shop drawings differ from city approved structural
drawings dated 10/21/2019.
4 12/12/19 RSI:0336101-146
Building 1 transfer grade beam pile caps at grid lines W30.8/YS24.5 & W31.3/
YS25.5
Pile caps reinforcing steel placed per field use shop drawings detail "Pile Cap PC2-16G" on
sheet R1.01 dated 11/25/2019. Reinforcing steel differs from city approved structural drawings
dated 10/21/2019.
5 12/12/19 RSI:0336101-146Building 2 grade beams at
grid lines YS23/W30.2-30.7 & YS20.8-23/W30.7
Grade beam dimensions and reinforcing steel placed per field use shop drawings details on
sheet R2.03 & R2.02, dated 11/1/2019 & drawing RW-01 (RFI C-0264) dated 11/5/2019. Shop drawings differ from city approved structural
drawings dated 10/21/2019.
6 12/12/19 RSI:0336101-146Building 2 pile caps at grid lines W30.7/YS23, 22 & 21
Pile caps "PC2-12" did not have #4 side bands spaced at 8" on center as indicated on typical
detail 2 on ST-3001 and field use shop drawing sheet R2.01. (1) #4 band observed at top of pile cap. Approved RFI C-0304 dated 12/19/2019
states caps with only bottom reinforcing mats and that are 43" or shallower do not require side bars. Per the City of KCMO requirements, RFI's must be signed and sealed by the EOR prior to their
acceptance.
7 12/13/19 RSI:0336101-148Building 2 grade beams at
grid lines YS20.8-18/W30.7 & YS18/W30.7-30.6
Grade beam dimensions and reinforcing steel placed per field use shop drawings details on
sheet R2.03, dated 11/1/2019 & drawing RW-01 (RFI C-0264) dated 11/5/2019. Shop drawings & RFI differ from city approved structural drawings
dated 10/21/2019.
8 12/17/19 RSI:0336101-153Building 1 transfer grade
beam at grid lines W30/YS25-26.3, W29/YS25.5-27
Column haunches & additional haunch reinforcing indicated on structural drawings detail 6 on ST-
3010 and rebar shop drawings Sections A & B on R1.02 was not placed at column locations, only
indicated TGB reinforcing steel placed.
9 12/17/19 RSI:0336101-153Building 1 transfer grade beam at grid lines W29/
YS25.5
(3) Bottom #7 form saver bars in pile cap not placed due to top of pile elevation blocking their
placement.
10 12/17/19 RSI:0336101-153Building 1 circular penetration in transfer grade beam at grid
lines W29/YS26
Additional reinforcing placed around penetration per Detail 3 on ST-3010. However, the #5's on each face are not "Z" bars as indicated in the
detail.
Edgemoor March Monthly Report | 22Kansas City International Airport New Terminal Project
MATERIALS TESTING & INSPECTIONS LOG (CONT.)
Appendix D
Terminal Discrepancy Log - Pile Caps & Grade Beams (cont.)Items will remain on this log until resolved.
Edgemoor March Monthly Report | 23Kansas City International Airport New Terminal Project
Item No. Date Report No. Location Discrepancy Resolution Date
Resolved
11 12/17/19 RSI:0336101-153Building 1 pilaster reinforcing
at grid lines W29/YS27
"4F Special-1 Pilaster" dimensions and reinforcing steel placed per field use shop drawing details
on sheet R1.02 dated 11/25/2019. Reinforcing steel differs from city approved structural drawings
dated 10/21/2019.
12 12/19/19 RSI:0336101-156Building 2 grade beam at grid
lines W29-30.7/YS18
Grade beam dimensions and reinforcing steel placed per approved RFI C-0264 dated
12/18/2019, and field use shop drawings details on R2.01 & R2.03. Reinforcing steel and dimensions differ from city approved structural
drawings.
13 12/19/19 RSI:0336101-156Building 2 pilaster at grid lines
W29/YS18
"4F Special-1 Pilaster" dimensions and reinforcing steel placed per field use shop drawing details
on sheet R2.02 dated 11/30/2019. Reinforcing steel differs from city approved structural drawings
dated 10/21/2019.
15 12/20/19 RSI:0336101-157
Building 1 transfer grade beams at grid lines W32/
YS23.9-25.1 & W30.8/YS24.5 to W31.3/YS25.5
Column haunches & additional haunch reinforcing indicated on structural drawings detail 6 on
ST-3010 and rebar shop drawings Section B on R1.02 & Sections C & D on R1.03 was not placed at column locations, only indicated TGB reinforcing
steel placed.
16 12/27/19 RSI:0336101-165Building 1 pile cap at grid line
W31/YS31
Pile cap shape and reinforcing placed per approved RFI C-0299 dated 12/19/2019. Per the City of KCMO requirements, RFI's must be signed and sealed by the EOR prior to their acceptance.
17
12/30/19 RSI:0336101-168Building 14 pile caps and
pilasters at grid lines XN22/W7 & 7.9
As indicated by JE Dunn, top of pilaster elevation is 2’-0” below top of slab elevation at the detailed
interior pile cap locations. Per detail 2 on ST-3041, top of pilaster elevation should be 1’-0” below top of slab. JE Dunn stated they had
verbal approval from the EOR to lengthen pilaster reinforcing 1’-0” to achieve the correct elevation. RFI-C0351 in review with SOM addressing this
condition.12/31/19 RSI:0336101-171
Building 14 pile caps and pilasters at grid lines XN23/
W7 & 7.9
18 1/2/20 RSI:0336101-173Building 2 MER foundation
wall at grid line W29/YS18-19
Per JE Dunn: Approval to thicken MER foundation wall at the detailed location was provided approximately 20 minutes after concrete
placement. An additional row of #7 vertical bars were wet set into the grade beam. Spacing
matched original wall reinforcing. This was done in order to exclude the grade beam at the top of
wall as indicated in Detail 9/ST-3020. RFI C-0348 addressing this change is in review with SOM.
20 1/3/20 RSI: 0336101-176Building 2 MER Foundation Wall at W29/YS18.9 to 19
Wall widened to 28” with an additional row of #7’s vertical and #5’s horizontal. See Item No. 18 for
additional details.
21 1/3/20 RSI:0336101-176Building 2 MER foundation
wall at grid line W29/YS18.9-20.5
Curtain wall precast embeds cast-in-placed at top of MER wall placed without approved drawings or details. Sketch provided by Ben Bunge with CWC
dated 12/17/2019 used for reference.
23 1/6/20 RSI:0336101-181Building 12A transfer grade
beam at grid line W10/XN10-11
Column haunches & additional haunch reinforcing indicated on structural drawings detail 6 on
ST-3010 and rebar shop drawing Section G on R13.03 was not placed at column location, only
indicated TGB reinforcing steel placed.
MATERIALS TESTING & INSPECTIONS LOG (CONT.)
Appendix D
Terminal Discrepancy Log - Pile Caps & Grade Beams (cont.)Items will remain on this log until resolved.
Edgemoor March Monthly Report | 24Kansas City International Airport New Terminal Project
Item No. Date Report No. Location Discrepancy Resolution Date
Resolved
24 1/7/20 RSI:0336101-183Building 3 pile cap at grid line
W29/YS13
"4F Special Pilaster" reinforcing steel placed per field use shop drawing detail on sheet R2.05 dated
12/3/2019. Reinforcing steel differs from city approved structural drawings dated 10/21/2019.
25 1/7/20 RSI:0336101-183Building 2 MER foundation
wall at grid line W29/YS19.5-21.5
Curtain wall precast embeds cast-in-placed at top of MER wall placed without approved drawings or details. Sketch provided by Ben Bunge with CWC
dated 12/17/2019 used for reference.
26 1/7/20 RSI: 0336101-184Building 14 PC3-12B at
XN21/W6
Missing side bars. Similar condition to Item No. 6. RFI C-0303 dated 12/19/2019 referenced. Needs
to be sealed by EOR.
27 1/8/20 RSI:0336101-188Building 2 pile cap at grid line
W32/YS23
Pile cap shape and reinforcing placed per approved RFI C-0299 dated 12/19/2019. Per the City of KCMO requirements, RFI's must be signed and sealed by the EOR prior to their acceptance.
28 1/8/20 RSI:0336101-188Terminal Y, pilaster at grid lines
W32/YS22 & 23
"4F Pilaster" reinforcing steel placed per field use shop drawing detail on sheet R2.08 dated 12/9/2019. Reinforcing steel differs from city
approved structural drawings dated 10/21/2019.
29 1/9/20 RSI:0336101-192Building 1 pile cap at grid line
W29/YS25.7
No form savers in pile cap for the bottom (3) #7 bars per Section 1 on R1.02. JE Dunn stated the form savers had been eliminated due to a change in pile cap elevation. No documentation provided
for this change.
31 1/9/20 RSI:0336101-193 Building 13 MER Pit
MER pit slab dowels not placed. JE Dunn indicated slab dowels would be installed per
approved shop drawings with "Stay Form Box" placed within MER walls. Structural drawings
indicate cast-in-place dowels.
32 1/9/20 RSI:0336101-193Building 14 pile cap at grid line
W6/XN26
Pile caps "PC3-12B" did not have #4 side bands spaced at 8" on center as indicated on typical
detail 2 on ST-3001 and field use shop drawing sheet R14.01. RFI C-0304 dated 12/19/2019 approves the detailed change. Per the City of
KCMO requirements, RFI's must be signed and sealed by the EOR prior to their acceptance.
33 1/15/20 RSI:0336101-208Building 2 pile caps at grid
lines W31 & 32/YS21
Pile cap shape and reinforcing placed per approved RFI C-0299 dated 12/19/2019. Per the City of KCMO requirements, RFI's must be signed and sealed by the EOR prior to their acceptance.
34 1/15/20 RSI:0336101-208Building 2 pilasters at grid
lines W31 & 32/YS21
"4F" and "4E" Pilaster reinforcing changed from field use reinforcing shop drawing details on R2.01 dated 11/30/2019 and structural drawings dated
10/21/2019. (24) #11 vertical bars placed.
35 1/15/20 RSI:0336101-208Building 2 transfer grade beam at grid line W29/
YS14.5-15.5
Column haunch & additional haunch reinforcing indicated on structural drawings detail 6 on ST-
3010 and rebar shop drawing Section A on R2.05 was not placed at column location, only indicated
TGB reinforcing steel placed.
37 1/21/20 RSI:0336101-217Building 3 transfer grade
beam at grid line W29/YS12
Column haunch & additional haunch reinforcing indicated on structural drawings detail 6 on ST-
3010 and rebar shop drawing Section B on R2.05 was not placed at column location, only indicated
TGB reinforcing steel placed.
38 1/23/20 RSI:0336101-226Building 2 transfer grade beam at grid line W29.8/YS13.5 to W30.4/YS12.5
Column haunch & additional haunch reinforcing indicated on structural drawings detail 6 on ST-
3010 and rebar shop drawing Section B on R2.06 was not placed at column location, only indicated
TGB reinforcing steel placed.
MATERIALS TESTING & INSPECTIONS LOG (CONT.)
Appendix D
Terminal Discrepancy Log - Pile Caps & Grade Beams (cont.)Items will remain on this log until resolved.
Edgemoor March Monthly Report | 25Kansas City International Airport New Terminal Project
Item No. Date Report No. Location Discrepancy Resolution Date
Resolved
39 1/28/20 RSI:0336101-234Building 2 transfer grade beam at grid line W31/
YS12.8-14.1
Column haunch & additional haunch reinforcing indicated on structural drawings detail 6 on
ST-3010 was not placed at column location, only indicated TGB reinforcing steel placed.
40 1/28/20 RSI:0336101-234Building 3 MER grade beams at grid lines W29.2-30.6/YS10
& W30.6/YS9.6-10
Grade beam dimensions and reinforcing steel placed per approved RFI C-0264 dated
12/18/2019. RFI not signed and sealed. Reinforcing steel and dimensions differ from city
approved structural drawings.
42 1/30/20 RSI:0336101-245Building 2 pilaster at grid line
W31/YS21
Pilaster reinforcing placed per approved shop drawing Section E on R2.01. Reinforcing differs
from detail 4E on ST-3041 on city approved drawings.
45 2/6/20 RSI:0336101-264Building 2 grade beam at grid
line W32/YS15
At the detailed grade beam to transfer grade beam construction joint, the formsavers were set 5" to the east causing the grade beam tying in to the pilaster to be flush with the face of wall. PSI observed JE Dunn extending grade beam steel
with U-bands at 10" O.C. which allows the vertical wall reinforcing to fall within the added grade beam reinforcing. RFI C-0420 approves the detailed fix. Per the City of KCMO requirements, RFI's must be signed and sealed by the EOR prior to their
acceptance.
46 2/7/20 FC:0336101-269Buildings 13 & 14 pile caps & grade beams at grid lines W9/
XN12 & W9/XN20
Concrete samples C2 & C3 exceeded mix design specification for slump. 8" maximum slump
specified; 8.25" & 9" tested, respectively.
Concrete samples exceeded the mix design compressive strength
of 5,000 psi. Average 28-day compressive strength results: 7,800 psi & 7,470 psi, respectively. See
CTR:0336101-269-C2 & C3.
3/6/20
47 2/11/20 FC:0336101-278Building 3 MER foundation
wall at grid lines W30.6/YS6.5-8.5
Concrete sample C1 exceeded mix design slump specification. 8.5" slump tested; 8" maximum
specified.
Concrete sample exceeded the mix design compressive strength
of 5,000 psi. Average 28-day compressive strength result: 7,560 psi. See CTR:0336101-278-C1.
3/10/20
48 2/11/20 RSI:0336101-278Building 2 MER grade beam at
W29/YS18.2-18.8
Wall widened to 28” thick per approved RFI C-0348 in order to eliminate grade beam
placement at the top of wall. Per the City of KCMO requirements, RFI's must be signed and
sealed by the EOR prior to their acceptance.
49 2/15/20 RSI:0336101-291Building 2 MER Foundation Wall at W29/YS18.2-18.8
Wall widened to 28” thick per approved RFI C-0348 in order to eliminate grade beam
placement at the top of wall indicated in Detail 9/ST-3020. No grade beam reinforcing steel placed at top of wall. Per the City of KCMO requirements, RFI's must be signed and sealed by the EOR prior
to their acceptance.
50 2/18/20 RSI:0336101-298Building 2 pilaster at grid line
W29/YS24
"4K Special Pilaster" reinforcing steel placed per field use shop drawing detail on sheet R1.05 dated
11/25/2019. Reinforcing steel differs from city approved structural drawings dated 10/21/2019.
51 2/19/20 FC:0336101-302 Building 2 MER slab-on-grade
Concrete sample C1 exceeded mix design slump specifications. 8.5" slump tested; 8" maximum specified. 7-day compressive strength result:
4,870 psi.
Concrete sample exceeded the mix design compressive strength
of 4,000 psi. Average 28-day compressive strength result: 7,560
psi.
3/18/20
52 2/19/20 RSI:0336101-302Buildings 1 bathroom slab-
on-grade and Building 2 MER slab-on-grade
Post-installed #4 slab dowels into interior pile caps placed without observation from PSI. Per
NCR-033000-001, SOM has no objections to the installed work.
MATERIALS TESTING & INSPECTIONS LOG (CONT.)
Appendix D
Terminal Discrepancy Log - Pile Caps & Grade Beams (cont.)Items will remain on this log until resolved.
Edgemoor March Monthly Report | 26Kansas City International Airport New Terminal Project
Item No. Date Report No. Location Discrepancy Resolution Date
Resolved
53 2/19/20 RSI:0336101-302Building 2 pilaster at grid lines
W31/YS12
"4E Pilaster" on 6/R2.06 and 4E on ST-3041 indicate (40) #8 vertical dowels in pilaster. (24) #11
vertical dowels placed.
55 2/20/20 DFR:0336101-307Building 1 transfer grade
beam haunches
Post-installed reinforcing at transfer grade beam haunches placed without observation from PSI.
Per NCR-033000-002, SOM has no objections to the installed work.
56 2/20/20 RSI:0336101-307Building 2 grade beam
intersecting pilaster at grid line W29/YS24
No form savers present for bottom (4) #9 and lower (2) #8 side bars as indicated on Elevation 6 on R1.05. In lieu of form savers for the lower bars, (14) #9 bars, 8'-6" in length, with a 2'-6" 90 degree leg were used to tie the grade beam reinforcing into the pilaster. Added bars placed
within the upper half of the grade beam.
57 2/21/20 RSI:0336101-311Building 4 pile cap at grid line
W32/YS5
(40) #8 vertical pilaster dowels indicated on Section 4 on R3.06 & 4F on ST-3041 for "4F Pilaster". (26) #11 pilaster dowels placed.
58 2/21/20 FC:0336101-312Building 11A pile cap at grid
line W11/XN4
Concrete sample C1 exceeded mix design slump specifications. 10" slump tested; 8" maximum
specified.
Concrete sample exceeded the mix design compressive strength
of 5,000 psi. Average 28-day compressive strength result: 8,050 psi. See CTR:0336101-312-C1.
3/20/20
59 2/26/20 FC:0336101-325Building 3 MER foundation wall at grid lines W29-29.5/
YS4
Concrete sample C2 exceeded mix design slump specifications. 10.5" slump tested; 8" maximum
specified.
Concrete sample exceeded the mix design compressive strength
of 5,000 psi. Average 28-day compressive strength result: 6,810 psi. See CTR:0336101-325-C2.
3/25/20
60 2/26/20 DFR:0336101-325
Building 1 post-installed slab dowels at interior isolated pile caps and perimeter pilasters located within grid lines W29-
32/YS27.7-31
The city approved structural drawings do not indicate post-installed slab dowels at piles caps
and pilasters. Dowels were installed per approved shop drawings dated 11/25/2019.
61 2/26/20 DFR:0336101-325Building 1 perimeter pilasters at W32/YS31, W29/YS31 &
W29/YS29
At the detailed pilasters, only a portion of the dowels could be installed due to concrete from the pilaster not extending far enough for dowel
installation. Shop drawings indicate 12" on center spacing for the dowels.
62 2/27/20 RSI:0336101-330Building 4 grade beam at grid
line W32/T0-YN3
Due to a change in the stem wall at the detailed location, the east (interior) vertical wall dowels
fall outside the horizontal grade beam reinforcing. Detail 3 on ST-3020 indicate these dowels should be placed within the grade beam steel. PSI was
provided and email chain from the EOR stating this condition was acceptable in this instance. Formal
RFI to follow.
63 3/2/20 RSI:0336101-341Building 3 pilaster at grid line
W30/YS12
(40) #8 vertical pilaster dowels indicated on Section 6 on R2.06 & 4E on ST-3041 for "4F Pilaster". (24) #11 pilaster dowels placed.
64
"3/3/2020 3/5/2020 3/7/2020 3/11/2020 3/13/2020 3/17/2020"
"RSI:0336101-345 RSI:0336101-354 RSI:0336101-361 RSI:0336101-373 RSI:0336101-381 RSI:0336101-389"
Building 7 MER grade beams, pile caps & foundation walls
Building 7 MER has been redesigned and differs significantly from city approved structural
drawings. Grade beams, pile cap size & foundation wall layout and reinforcing was placed per approved shop drawings dated 2/19/2020.
MATERIALS TESTING & INSPECTIONS LOG (CONT.)
Appendix D
Terminal Discrepancy Log - Pile Caps & Grade Beams (cont.)Items will remain on this log until resolved.
Edgemoor March Monthly Report | 27Kansas City International Airport New Terminal Project
Item No. Date Report No. Location Discrepancy Resolution Date
Resolved
65 3/4/20 DFR:0336101-351
Building 12A post-installed horizontal foundation wall
dowels at grid lines W9/XN5-XN8 & column at W10/XN11
City approved structural drawings do not indicate post-installed dowels at the detailed locations.
Sheet R12.01 & Sections 3/R12.04 on approved shop drawings dated 2/26/2020 detail post-
installed dowels.
66 3/4/20 DFR:0336101-351
Building 12A post-installed grade beam dowels at grid
location W9.75/XN12 & W9.25/XN12
City approved structural drawings do not indicate post-installed dowels at the detailed locations.
Sheet R12.01 "GB20x30-1" Grade Beam Reinforcing detail on approved shop drawings dated 2/26/2020 detail post-installed dowels.
67 3/5/20 RSI:0336101-354Building 5 pilaster at grid lines
W32/YN6
Pilaster reinforcing placed per Section 4 on R5.02 on approved shop drawings dated 1/19/2020.
Reinforcing differs from detail 4F on ST-3041 on city approved drawings dated 10/21/2019.
68 3/5/20 RSI:0336101-354Building 5 transfer grade
beam at grid line W32/YN7
Column haunch & additional haunch reinforcing indicated on structural drawings detail 6 on ST-
3010 and rebar shop drawing Section A on R5.01 was not placed at column location, only indicated
TGB reinforcing steel placed.
69 3/6/20 RSI:0336101-358Building 2 pilaster at grid line
W29/YS14
"4K Special Pilaster" reinforcing steel placed per field use shop drawing detail on sheet R2.09
dated 12/9/2019. Reinforcing steel differs from detail 4K on ST-3041 on city approved structural
drawings dated 10/21/2019.
70 3/6/20 DFR:0336101-358
Building 3 post-installed column haunch reinforcing at grid locations W32/YS12 & 14, W31/YS13 & 14, W30/
YS13 & 14, W29/YS12 & 15
RFI C-0462 dated 2/27/2020 approves post-installed column haunch reinforcing. City
approved drawings dated 10/21/2019 detail column haunch reinforcing as cast-in-place.
71 3/6/20 DFR:0336101-359
Building 14 post-installed slab dowels at interior pile caps at
grid lines XN24 & XN25 at W7, W8 & W9
Building 14 approved shop drawings dated 12/03/2019 detail post-installed slab dowels at the detailed locations. City approved drawings dated 10/21/2019 detail these slab dowels as
cast-in-place.
72 3/7/20 RSI:0336101-361Building 11A grade beams at grid lines W10/XS1.7-XN3.8
Grade beam dimensions and reinforcing steel placed per field use shop drawings details on sheet R11.01 & R11.05, dated 01/29/2020 &
drawing RW-01 (RFI C-0264) dated 11/5/2019. Shop drawings differ from city approved structural
drawings dated 10/21/2019.
73 3/10/20 DFR:0336101-370Building 14 post-installed slab dowels at exterior pilasters at grid lines W6 & W10/XN26
Building 14 approved shop drawings dated 12/03/2019 detail post-installed slab dowels at the detailed locations. City approved drawings dated 10/21/2019 detail these slab dowels as
cast-in-place.
74 3/10/20 DFR:0336101-370
Building 12A post-installed horizontal foundation wall
dowels into columns at grid lines W9/XN9 & XN8
City approved structural drawings do not indicate post-installed dowels at the detailed locations.
Sheet R12.01 & Sections 3/R12.04 on approved shop drawings dated 2/26/2020 detail post-
installed dowels.
75 3/11/20 FC:0336101-373Building 5 transfer grade
beam at grid line W30/YN6.6-YN8
Concrete sample C2 exceeded mix design slump specifications. 8.5" slump tested; 8" maximum
specified.
76 3/11/20 RSI:0336101-373Building 5 transfer grade
beams at grid lines W31/YN6-YN7.5, W30/YN6.6-YN8
Column haunch & additional haunch reinforcing indicated on structural drawings detail 6 on
ST-3010 was not placed at column location, only indicated TGB reinforcing steel placed.
MATERIALS TESTING & INSPECTIONS LOG (CONT.)
Appendix D
Terminal Discrepancy Log - Pile Caps & Grade Beams (cont.)Items will remain on this log until resolved.
Edgemoor March Monthly Report | 28Kansas City International Airport New Terminal Project
Item No. Date Report No. Location Discrepancy Resolution Date
Resolved
77 3/11/20 RSI:0336101-374Building 9 interior pile caps at
grid lines W7 & W8/XS12
Pile cap shape and reinforcing placed per approved RFI C-0299 dated 12/19/2019. Per the City of KCMO requirements, RFI's must be signed and sealed by the EOR prior to their acceptance.
78 3/13/20 RSI:0336101-381Building 4 pilaster at grid line
W29/YN4
"1C Special Pilaster" reinforcing steel placed per field use shop drawing detail on sheet R4.04 dated
1/23/2020. Reinforcing steel differs from city approved structural drawings dated 10/21/2019.
79 3/13/20 DFR:0336101-381
Building 1 post-installed slab dowels at grid locations YS24/W30 & W31, YS25/W29, W30
& W31 & YS26/W31
Building 1 approved shop drawings dated 11/25/2019 detail post-installed slab dowels at the detailed locations. City approved drawings dated 10/21/2019 detail these slab dowels as
cast-in-place.
80 3/13/20 RSI:0336101-382Building 11A pile caps at grid lines XS1/W11 & W12, XS2/
W11 & XN1 & XN2/W12
Pile cap shape and reinforcing placed per approved RFI C-0299 dated 12/19/2019. Per the City of KCMO requirements, RFI's must be signed and sealed by the EOR prior to their acceptance.
81 3/16/20 RSI:0336101-386Building 13 pilaster at grid
lines W9/XN15
"4E Pilaster" reinforcing steel placed per field use shop drawing Section B on R13.07 dated 12/9/2019. Reinforcing steel differs from city
approved structural drawings dated 10/21/2019.
82 3/17/20 RSI:0336101-390Building 9 interior pile caps at grid lines XS19/W8-9, XS18/W8 & W7, XS20/W8 & W7
Pile cap shape and reinforcing placed per approved Building 9 shop drawings dated
3/11/2020. Shop drawings updated per SSK-061 dated 3/9/2020. Reinforcing differs from city
approved structural drawings dated 10/21/2019.
83 3/20/20 DFR:0336101-396Building 1 post-installed slab
dowels at grid locations YS27/W29 & W32
Building 1 approved shop drawings dated 11/25/2019 detail post-installed slab dowels at the detailed locations. City approved drawings dated 10/21/2019 detail these slab dowels as
cast-in-place.
84 3/20/20 DFR:0336101-397
Building 14 post-installed slab dowels at pile caps and pilasters located within grid
lines XN21-XN23/W5.9-W10
Building 14 approved shop drawings dated 12/3/2019 detail post-installed slab dowels at the detailed locations. City approved drawings dated 10/21/2019 detail these slab dowels as
cast-in-place.
85 3/21/20 RSI:0336101-399Building 4 pilaster at grid line
W28/YS3
"7C" pilaster is detailed to have cross sectional dimensions of 72" X 72" per Detail 7 on ST-4001.
Approved rebar shop drawings 7/R4.06 dated 1/23/2020 detail the "7C" pilaster as 66" X 66".
86 3/23/20 FC:0336101-403Building 2 SOG between grid lines YS18.5 to slab step at
YS25
Concrete samples C3 & C4 exceeded mix design slump specifications. 8" maximum slump
specified, 10" & 8.5" tested, respectively.
87 3/23/20 DFR:0336101-403Building 2 MER post-installed slab dowels at stair landing at
grid line YS18
RFI C-0300 dated 12/12/2019 approves the use of post-installed dowels at the detailed location. However, the RFI does not specify embedment
depth. No additional RFI provided for the detailed location.
88 3/23/20 DFR:0336101-404
Building 13 MER post-installed slab dowels at column block-outs at grid lines XN17, XN18
& XN19/W9
Building 13 approved shop drawings dated 12/9/2019 detail post-installed slab dowels at the detailed locations. City approved drawings dated 10/21/2019 detail these slab dowels as
cast-in-place.
89 3/23/20 DFR:0336101-404
Building 13 MER post-installed slab dowels at column block-outs at grid lines XN17, XN18
& XN19/W9
Hilti HIT-RE 500 epoxy used to due free moisture in the drilled holes. Hilti HIT-HY200 is the only
epoxy approved by the EOR for use thus far. No RFI or submittal provided for the substitution.
MATERIALS TESTING & INSPECTIONS LOG (CONT.)
Appendix D
Terminal Discrepancy Log - Pile Caps & Grade Beams (cont.)Items will remain on this log until resolved.
Edgemoor March Monthly Report | 29Kansas City International Airport New Terminal Project
Item No. Date Report No. Location Discrepancy Resolution Date
Resolved
90 3/23/20 DFR:0336101-404
Building 12A post-installed wall dowels into columns
located at grid lines XN11/W9 & XN11/W8
Building 12A approved shop drawings dated 2/26/2020 detail post-installed wall dowels at the detailed locations. City approved drawings dated 10/21/2019 detail these slab dowels as cast-in-
place.
91 3/24/20 RSI:0336101-407Building 4 pilaster at grid line
W28/YS4
"7C" pilaster is detailed to have cross sectional dimensions of 72" X 72" per Detail 7 on ST-4001.
Approved rebar shop drawings 7/R4.06 dated 1/23/2020 detail the "7C" pilaster as 66" X 66".
92 3/25/20 DFR:0336101-411
Building 1 post-installed slab dowels at interior isolated pile caps and perimeter pilasters located within grid lines W29-
32/YS25-28
The city approved structural drawings do not indicate post-installed slab dowels at piles caps
and pilasters. Dowels were installed per approved shop drawings dated 11/25/2019.
93 3/25/20 RSI:0336101-412
Building 11A grade beams at grid lines W9.9/XN3.3-XN3.5, XN3.3/W9-W9.9, W9/XN3-
XN3.3
Grade beam dimensions and reinforcing steel placed per approved RFI C-0264 dated
12/18/2019, and field use shop drawings details on R11.01, R11.04 & R13.06. Reinforcing steel
and dimensions differ from city approved structural drawings.
94 3/25/20 FC:0336101-412Building 14 slab-on-grade within grid lines XN19.5-
XN23.5/W6-W10
Concrete sample C4 exceeded mix design slump specifications. 8.5" slump tested; 8" maximum
specified.
95 3/26/20 RSI:0336101-416Building 10A pile cap at grid
line W9/XS5
Pile cap shape and reinforcing placed per approved RFI C-0299 dated 12/19/2019. Per the City of KCMO requirements, RFI's must be signed and sealed by the EOR prior to their acceptance.
96 3/26/20 DFR:0336101-416
Buildings 12A & 13 post-installed transfer grade beam
haunch reinforcing at grid lines XN12/W9 (East & West face) &
XN12/W8 (West face)
RFI C-0462 dated 2/27/2020 approves post-installed column haunch reinforcing. City
approved drawings dated 10/21/2019 detail column haunch reinforcing as cast-in-place.
97 3/27/20 RSI:0336101-419Building 5 MER interior grade beams on grid lines YN11 &
W30.8
Grade beam dimensions and reinforcing steel placed per field use shop drawings details on
sheet R6.02 & R6.03, dated 1/20/2020 & drawing RW-01 (RFI C-0264) dated 11/5/2019. Shop drawings differ from city approved structural
drawings dated 10/21/2019.
98"3/27/2020 4/13/2020"
"RSI:0336101-419 RSI:0336101-468"
Building 5 MER pilaster at grid line W29/YN12
"4O Pilaster" reinforcing steel placed per field use shop drawing on R6.02 dated 1/20/2020.
4M pilaster indicated on city approved structural drawings dated 10/21/2019.
99 3/27/20 FC:0336101-420Building 11A foundation walls at grid lines XN3.3-XN4/W9.8,
W9.2-W9.8/XN3.3, W10-W11/XN4
Concrete sample C4 exceeded mix design slump specifications. 8.5" slump tested; 8" maximum specified.
100 3/27/20 RSI:0336101-420
Buildings 9A & 10A pile caps at grid lines XS18/W5.9,
XS15/W7, XS10 & XS11/W8 & XS10/W9
Pile cap shape and reinforcing placed per approved RFI C-0299 dated 12/19/2019. Per the City of KCMO requirements, RFI's must be signed and sealed by the EOR prior to their acceptance.
101 3/30/20 RSI:0336101-423Buildings 5 & 6 interior grade
beam on grid line W30.8/YN11.5-YN16.5
Grade beam dimensions and reinforcing steel placed per field use shop drawings details on
sheet R6.01 & R6.03, dated 1/20/2020 & drawing RW-01 (RFI C-0264) dated 11/5/2019. Shop drawings differ from city approved structural
drawings dated 10/21/2019.
102 3/30/20 RSI:0336101-424Building 10A grade beams within grid lines XS9.25-
XS9.5/W9.5-W10
Grade beams added in this area were placed per an email provided by Nick Kramer with JE Dunn on 3/26/2020. Updated drawing differs from city approved structural drawings dated 10/21/2020.
MATERIALS TESTING & INSPECTIONS LOG (CONT.)
Appendix D
Terminal Discrepancy Log - Pile Caps & Grade Beams (cont.)Items will remain on this log until resolved.
Edgemoor March Monthly Report | 30Kansas City International Airport New Terminal Project
Discrepancies and resolutions reported through: 3/31/20.
Item No. Date Report No. Location Discrepancy Resolution Date
Resolved
103 3/31/20 RSI:0336101-427Building 4 pilaster at grid line
W28/YS4
At the grade beam and pilaster/pile cap intersection, the lower layers of female formsavers
were not installed into the pile cap as detailed. JE Dunn proposed a fix "Building 4 missed formsavers" that was provided to PSI on
3/31/2020. The proposed fix matches what PSI observed in the field. Formal RFI forthcoming.
104 3/31/20 RSI:0336101-427Building 3 MER grade beam at
grid lines W29/YS8.2-YS8.8
Over a span of approximately 5 feet, the lower layer of grade beam reinforcing did not achieve the
required 3 inches of clear cover.
PROCUREMENT LOG
Below please find the KCI Airport New Terminal procurement packages as of March 31, 2020.
Group # RFP Issued to Bidders Scope of Work Award
(Prime Contractor)
0 January 2018 through July 2018
Asbestos Survey WorkGeotechnical InvestigationHazmat Testing and ReportTerminal Mechanical and Plumbing (Design Build)Terminal Electrical (Design Build)Parking Garage (Design Build)Site Utility ModelingSite Office BuildoutStructural Peer Review
Anlab EnvironmentalTSi GeotechnicalOlssonU.S. EngineeringCapital ElectricJ.E. DunnSK DesignVariousCagley
0 April 2019 TWEP Needs Evaluation Amazing Traditions
2 September 2018
DemolitionCut/Cap UtilitiesMaintenance of TrafficEarly Earthwork
RenascentGenesisIBCFour J
2A December 2019
Asphalt and Concrete Paving for Early WorkSafety CarpentryConstruction CleaningUtility Relocations (Storm, Sanitary, Water)Aviation Fuel – Phase 1 (Relocate)Aviation Fuel – Phase 2 (Complete)Earthwork for Terminal FoundationsMedical ClinicBadging SystemLogistics Trailer Complex
Julius KaazHartlineRitewayRodriguezUSE/AMC JVBy MCI Fuel ConsortiumJ.A. Lillig ExcavationMobile MedicalFCUniversial
2B May 2019 Eastern Access RoadwaysEastern Access Roadways Electrical
KissickCapital Electric
2C May 2019
SurveyingBreak TentDumpstersShuttle ServiceTemporary ToiletsConstruction Trailers
TrekkBig TopUnder Review by CWCBy KCADUnder Review by KCADAries/AT&S
3 December 2018April 2019
Auger Cast Test PilesDeep Foundations – Auger Cast Piles (Design-Build)
CBS PilingBerkel
3A January 2019 Baggage Handling System (Design-Build) Vanderlande
3B June 2019 Terminal Electrical Gear Capital Electric
4 July 2019
Terminal Cast in Place Concrete Substructure and Slab on GradeTerminal Cast in Place Concrete SuperstructureTerminal Cast in Place Slab on Metal DeckStructural Steel / Metal DeckVertical and Horizontal TransportationFoundation Waterproofing
J.E. DunnJ.E. DunnMusselmanADF-CSCA JVSchindlerS&W
4A July 2019 Underslab Electrical Capital Electric
4B July 2019 Underground Plumbing U.S. Engineering
5 August 2019 Curtain Wall and Punched Windows Physical Security
6B September 2019 Architectural PrecastConcrete Masonry
OmegaN/A
6A October 2019 Landside Civil & Elevated Roadways Clarkson/Realm
TWEP November 2019 Child Care Extra Hours Services Multiple Providers
DUNN November 2019 Parking Garage Architectural & Structural Precast Fabrication Coreslab Structures
DUNN February 2020 Parking Garage Glass/Glazing Under Review by KCAD
7A February 2020 Airside Civil Under Review by CWC
7B February 2020 Systems Integration Under Review by CWC
Appendix E
Edgemoor March Monthly Report | 31Kansas City International Airport New Terminal Project
PROCUREMENT LOG (CONT.)
*Not all packages are listed here.
Appendix E
Edgemoor March Monthly Report | 32Kansas City International Airport New Terminal Project
Group # RFP Issued to Bidders Scope of Work Award
(Prime Contractor)
7C February 2020
Fire Protection (Sprinklers)Metal StairsRoofing (including Rough Carpentry for Roofing)Overhead Coiling DoorsSpray Fireproofing
Under Review by CWC
BIM-FM February 2020 BIM to FM Integration Under Review by CWC
7D March 2020
Landside Surface ParkingMasonryMisc. MetalsLouvers (Furnish Only)Joint Sealants & Air Barrier
Bids due April 17
8A June 2020
Drywall, Framing, and CeilingsRough CarpentryDoors, Frames, and HardwareLoading Dock Equipment
TBD
CONSTRUCTION PHASING PLAN
Below please find the current Construction Phasing Plan.
1. CONSTRUCT TEMPORARY AOA FENCING ANDLOW PROFILE AIRCRAFT BARRICADES ASSHOWN ON THIS SHEET.
2. RELOCATE UTILITIES IN THE WORK AREA ANDPREPARE THE NECESSARY AREAS FOR PHASE 6.
3. BEGIN CONSTRUCTION OF PROPOSED TERMINALBUILDING.
4. CONSTRUCT PROPOSED CENTRAL UTILITYPLANT AND ASSOCIATED UTILITIES.
5. CONSTRUCT NEW AIRPORT ACCESS ROADS INPREPERATION FOR PHASE 6 WORK.
6. CUT, CAP AND RELOCATE LANDSIDE UTILITIES INTHE WORK AREA AND PREPARE THENECESSARY AREAS FOR PHASE 6 WORK.
PHASE 5MONTHS 4-9
MAJOR WORK ITEMS
LEGEND
EMPLOYEE PARKING AREAEP
CS
TEMPORARY AOA FENCE
TERMINAL CONSTRUCTION
PROPOSED FUTURE TERMINALBUILDING
TAXILANE OBJECT FREE AREA(OFA)OFA
LOW PROFILE BARRICADE
AIRCRAFT ROUTE
AIRPORT VEHICLE ROUTE
CONTRACTOR ACCESS ROUTE
TAXIWAY OBJECT FREEAREA
TOFA
CLOSED TERMINAL GATE
PUBLIC PASSENGER ACCESS
ARFF ARFF ROUTE
PREVIOUSLY CONSTRUCTEDCONTRACTOR ACCESS ROAD
EXISTING AOA FENCE
CONTRACTOR STAGING AREA
TAXIWAY SAFETY AREATSA
RON PARKING
CA
AVR
PUB
1. THE INSTALLATION OF THE TEMPORARY AOAFENCE ADJACENT TO TAXIWAY L REQUIRESTAXIWAY L TO BE LIMITED TO ADG III AIRCRAFT(MAX. 118' WINGSPAN) OPERATIONS. ADG IV ANDLARGER AIRCRAFT SHALL UTILIZE TAXIWAYS A, B,C, AND D.
2. PHASE 5 WORK INCLUDED IN GROUP 2AINCLUDES MAJOR WORK ITEM NO. 1 ONLY.
3. PHASE 5 WORK INCLUDED IN SCHEMATIC DESIGNINCLUDES MAJOR WORK ITEMS NO. 2 THROUGHNO. 8.
GENERAL NOTES
N
0
SCALE IN FEETHORIZONTAL SCALE 1"=300'
300 600300
PREVIOUSLY CONSTRUCTEDROADWAY
PROPOSED ROADWAY
CONSTRUCTION TRAILER
PREVIOUSLY CONSTRUCTEDGSE FUEL ISLAND
CONSTRUCTION FENCE
N
0
A
5/10/2018 1:57:57 PM
123456789101112
© Copyright Skidmore, Owings & Merrill LLP
OWNER
Skidmore, Owings & Merrill LLP14 Wall Street, New York, NY 10005
KEYPLAN
DATE DESCRIPTION
DRAWING TITLE
DRAWING NUMBER
NOT FOR CONSTRUCTION
533 Mexico City Avenue, Kansas City, MO 64153
KANSAS CITY INTERNATIONALAIRPORT NEW TERMINALKANSAS CITY, MO 64153
B
C
D
E
F
G
H
I
J
K
L
SEAL
PROJECT NUMBER - 6218KANSAS CITY AVIATION DEPARTMENT (KCAD)
DEVELOPER
CONTRACTOR
ARCHITECT & STRUCTURAL ENGINEER
DESIGN TEAM
533 Mexico City Avenue, Kansas City, MO 64153
MARK E. WILLIAMS, P.E. - AIRSIDE CIVILMO. LIC. NO. 2005023336
SCHEMATIC DESIGNPACKAGE
THE PROFESSIONAL WHOSE SIGNATURE AND SEALAPPEARS HEREON ASSUMES RESPONSIBILITY ONLY FORWHAT APPEARS ON THIS PAGE, AND DISCLAIMS(PURSUANT TO SEC. 327.411 RSMO) RESPONSIBILITY FORALL OTHER DOCUMENTS NOT SEALED BY THEUNDERSIGNED PROFESSIONAL.
Garver, LLCMO State Certificate of Authority# 20080130907410 NW Tiffany Springs PKWY
Kansas City, MO 64153P: 816-298-6465
Draw Architecture - Collaborating ArchitectWellner Architects - Collaborating ArchitectHJM Architects Inc. - Collaborating ArchitectFSC Inc. - Fire Protection / Code / Life SafetyLand3 Studio - LandscapeGarver - Airside CivilEntro - Signage / WayfindingOlsson - Traffic PlanningBNP - Baggage HandlingMichele & Associates - ADAThornton Tomasetti - Protective DesignSK Design Group - Glycol / Landside UtilitiesTrekk Design Group - Airside Storm DrainageARUP - Aircraft Parking / Gate Eqp. / AIS / ICTTaliaferro & Browne Inc. - Landside CivilCustom Engineering Inc. - CP Electrical / Landside Lighting3T Design & Development - Landside UtilitiesHG Consulting Group - PermittingSK Design Group - Glycol / Landside UtilitiesLightworks - Lighting / Landside LightingDubois Consultants - Struc. Terminal and CUPLeigh & O'Kane - Roadway StructureArgus Consulting - Hydrant Fuel SystemTranssolutions - Terminal PlanningPremier Engineering - DemolitionICF - ConcessionsLerch Bates - VHT ConsultantsCityfi - Smart Technology
14 SEPTEMBER 2018 ISSUED FOR PERMIT
Suite 200
CONSTRUCTION SAFETY AND PHASING PLAN - PHASE 51 SCALE: 1" = 300'
CONSTRUCTION SAFETYAND PHASING PLAN -PHASE 5
CSPP-0005
GATE
Appendix F
Edgemoor March Monthly Report | 33Kansas City International Airport New Terminal Project
Low Interest Loan Program
Pay Without DelayList of participating firms through March 31, 2020:
Lead Bank Loan
Original Note Date
Contract Line of Credit
Maturity Date
Total Origination Fee % (varies by
loan size)
Contractor Portion of Origination
Fee
Edgemoor Origination Fee
% (varies by loan size)
Edgemoor Origination
Fee
Loan #1 3/27/2019 $155,000.00 3/27/2020 4.75% 1.00% 3.75% $5,812.50
Loan #2 7/20/2018 $96,000.00 7/20/2019 5.00% 1.00% 4.00% $3,840.00
Loan #3 7/20/2018 $60,000.00 7/20/2019 5.00% 1.00% 4.00% $2,400.00
Loan #4 7/20/2018 $60,000.00 7/20/2019 5.00% 1.00% 4.00% $2,400.00
Loan #5 7/20/2018 $504,000.00 7/20/2019 4.25% 1.00% 3.25% $16,380.00
Loan #6 8/5/2019 $600,000.00 8/5/2020 4.25% 1.00% 3.25% $19,500.00
Loan #7 12/10/2019 $250,000.00 08/05/2020 2.50% 1.00% 1.50% $3,750.00
Loan #8 1/10/2020 $2,000,000.00 1/10/2021 2.50% 1.00% 1.50% $30,000.00
Total through March 31, 2020: $3,725,000.00 $84,082.50
PROFESSIONAL SERVICES01. 3T-Design & Development, LLC 02. Amazing Traditions, LLC03. Anlab Environmental04. Bare Business Basics 05. Custom Engineering, Inc. 06. Draw Architecture & Urban Design, LLC07. DuBois Consultants, Inc.08. From the Ground Up Photography, Inc.09. FSC, Inc.10. Hg Consult, Inc.11. HJM Architects, Inc.12. KEM Consulting LLC13. Land3 Studio, Inc.14. Leigh & O’Kane, LLC15. Lightworks, Inc.16. Michele & Associates17. Parson & Associates, LLC18. Premier Engineering Consultants, LLC19. Priority Engineers, Inc.20. SK Design Group, Inc. 21. Taliaferro & Browne, Inc.22. Tech. Services to Go, Inc.23. TREKK Design Group, LLC24. Wellner Architects, Inc.
Appendix G
TERMINAL WORKFORCE ENHANCEMENT PROGRAMS REPORTING
Edgemoor March Monthly Report | 34Kansas City International Airport New Terminal Project
CONSTRUCTION SERVICES01. AGP, Inc. 02. Alexander Mechanical Corp.03. Alpha Energy & Electric, Inc.04. American Fire Sprinkler Corp.05. Axiom Construction06. Compass Roofing07. Dye Electric, LLC08. Enterprise Control Systems, Inc.09. Exceptional Waste Solutions, LLC10. Four J Environmental, LLC 11. Freedom Interior Solutions, LLC12. Genesis Environmental Solutions, Inc.13. Hartline Construction, LLC14. IBC Traffic, Inc.15. Image Staffing, LLC16. Infinite Energy Construction, Inc.17. J.A. Lillig Excavating, Inc.18. J.A. Lillig Grading, LLC19. Julius Kaaz Construction Co., Inc.20. K. Ramos Interiors, LLC21. Maher Oil Co.22. Midwest Contracting Services, LLC23. MJ Builders LLC24. New Horizons, LLC25. Pro Metals, LLC26. Richardson Hauling Inc.27. Riteway Maintenance & Supply, LLC28. Rodriguez Mechanical Contractors, Inc.29. SE3, LLC30. SheDigs IT, LLC31. T-Shirt King, Inc.32. Tanner & Son Trucking, Co, LLC33. Three Feathers Construction & Sales, LLC34. Universal Construction Company35. Vazquez Commercial Contracting, LLC
Edgemoor March Monthly Report | 35Kansas City International Airport New Terminal Project
Small Business Incubator Space
This program will be implemented upon completion of the Logistics Trailer Complex, located north of the project co-location office, and installation of a trailer to be used for this program. There are no participants as of this report date.
General Contractor Training Program
The General Contractor Training Program will be developed and implemented in the first half of 2020. No costs were incurred during the month of March 2020.
Appendix G
TERMINAL WORKFORCE ENHANCEMENT PROGRAMS REPORTING (CONT.)
Project Transportation - KCI Express Limited Route
East
Vill
age
Tran
sit C
ente
r
Boar
dwal
k Sq
uare
Pa
rk &
Rid
e
KCI J
ob S
ite
Park
& R
ide
Term
inal
C
KC
I Air
port
MAP a b c dNORTHBOUND
A.M
.
6:02 6:27 6:45 6:50
KCI J
ob S
ite
Park
& R
ide
Term
inal
C
KC
I Air
port
Boar
dwal
k Sq
uare
Pa
rk &
Rid
e
East
Vill
age
Tran
sit C
ente
r
MAP c d b aSOUTHBOUND
P.M
.
3:45 3:51 4:09 4:34
Monday–Friday Schedule
529KCI Express Limited
Barry
I-29
I-2956th
64th
72nd
I-29
c
Zona Rosa
Barry
Prai
rie V
iew
Con
gres
s
Barry Woods
Crossing
152 Hwy.152 Hwy.
I-29
Board
walk
Prairie View
201
229south
229north
Boardwalk Square
Park & Ride
234529
b b
a
Bike Share StationEstación de bicicletas
compartidasNon-Stop Service
Servicio sin interrupciones
Express/LimitedService
Expreso/LimitadoServicio
Major Transfer HubUbicación de transferencia
Schedule Time PointHora de llegada parada
de autobús
a
Streetcar RouteRuta del tranvía
Transfer OptionsOpciones de transbordo
000LEG
END
LEY
END
A
FREE Park & RideAparcamiento gratis para
viajeros de autobús
Terminal C
KCI Airport
DowntownKansas City, MO
c
d
d
Terminal B
New Terminal Construction
CookinghamBern St.
Pase
o
Cha
rlotte
11th12th
Paris St.
Mex
ico
City
Ave
.
152 Hwy.
aEast Village
Transit Center
Project Childcare Facilities
• Emmanuel Child Care | 2416 Swope Parkway and 4736 Prospect Avenue
• KD Learning Center | 3501 Woodland Avenue and 2105 Prospect Avenue (starting October 2020)
• Sweet Chariot Childcare | 2901 Flora Avenue
• Talented Tots Learning Center | 2901 Williamsburg Terrace
• United Inner Cities Childcare | St. Mark Center (12th & Garfield) and Metro Center (38th & Troost)
Pictured: Cranes mobilized for New Terminal foundation work. This photo was taken before COVID-19 protocols went into effect.
533 Mexico City AveKansas City, MO 64153
KANSAS CITY INTERNATIONAL AIRPORT NEW TERMINAL PROJECT
Edgemoor Monthly Report
@kciedgemoor @buildkci
kci-edgemoor.com buildkci.com
@kciedgemoor @buildkci