Brief Overview Diamir Bhasha Dam and Mohmand DamJul 05, 2018  · 3 Location: The project is located on Indus River, about 315 km upstream of Tarbela Dam, 165 km downstream of the

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Brief Overview Diamir Bhasha Dam and Mohmand DamJul 05, 2018  · 3 Location: The project is located on Indus River, about 315 km upstream of Tarbela Dam, 165 km downstream of the

Best Equity HouseTop 25 Listed Companies

Corporate Finance House

of the Year

Best Domestic

Equity House

www.jamapunji.pk

Analyst:Tahir Abbas

[email protected]

+92 21 3246 2589

www.arifhabibltd.com

Brief Overview Diamir Bhasha Dam and Mohmand Dam

05-Jul-2018

REP-300

Page 2: Brief Overview Diamir Bhasha Dam and Mohmand DamJul 05, 2018  · 3 Location: The project is located on Indus River, about 315 km upstream of Tarbela Dam, 165 km downstream of the

2

• The Honorable Supreme Court of Pakistan (CJP) has issued directives for immediate construction of Diamir Bhasha

and Mohmand dams.

• While Chief Justice Mr. Saqib Nisar has announced a donation of PKR 1mn for the cause, he also formed a

committee under the chairmanship of Water and Power Development Authority (WAPDA) Chief to monitor the

progress of work as well as an account to collect funds for the project.

• The committee is set to present a report on the subject within 3 weeks.

Supreme Court Deems Construction of Dams Vital for Pakistan

Page 3: Brief Overview Diamir Bhasha Dam and Mohmand DamJul 05, 2018  · 3 Location: The project is located on Indus River, about 315 km upstream of Tarbela Dam, 165 km downstream of the

3

Location:

The project is located on Indus River, about 315 km upstream of Tarbela Dam, 165 km downstream of the

Northern Areas Capital Gilgit and 40 km downstream of Chilas.

Diamir Bhasha Dam

Page 4: Brief Overview Diamir Bhasha Dam and Mohmand DamJul 05, 2018  · 3 Location: The project is located on Indus River, about 315 km upstream of Tarbela Dam, 165 km downstream of the

4

Diamir Bhasha Dam

Location Cont..

Page 5: Brief Overview Diamir Bhasha Dam and Mohmand DamJul 05, 2018  · 3 Location: The project is located on Indus River, about 315 km upstream of Tarbela Dam, 165 km downstream of the

5

• This will be a Roller Compacted Concrete (RCC) Dam

• Height of the Dam will be 272m

• Gross storage capacity is expected to be 8.1 MAF (Million Acre Feet)

• Live storage capacity will be around 6.1 MAF

• Gross power generation capacity is estimated at 4,500MW

• Expected completion time is 14 years

• Estimated cost of the project is USD 15bn

Diamir Bhasha Dam

Salient Features

Diamir Bhasha Dam – Snapshot

Dam Type Roller Compacted Concrete (RCC)

Height of Dam 272 m

Gross Storage Capacity 8.1 MAF

Live Storage Capacity 6.4 MAF

Power Generation 4,500 MW

Execution by WAPDA

Expected Completion 14 years

Estimated Cost (USD) 15bn

Source: WAPDA and AHL Research

Page 6: Brief Overview Diamir Bhasha Dam and Mohmand DamJul 05, 2018  · 3 Location: The project is located on Indus River, about 315 km upstream of Tarbela Dam, 165 km downstream of the

6

Status• Land acquisition in progress (initial stages)

Funding

• Government has previously negotiated the funding of Diamir Basha Dam with World Bank

• World Bank has two funds to finance development projects including:

1. International Development Agency (IDA)

2. International Bank for Reconstruction and Development (IBRD)

• The share of Pakistan in IDA fund is around USD 500mn

• While the funding from IBRD requires a certain criteria of federal foreign exchange reserves

• To recall, Pakistan had obtained USD 500mn each from IDA and IBRD for Tarbela 4th extension project

• Pakistan faces challenges with respect to obtaining financing for Diamir Basha Dam amid its location in Gilgit

Baltistan along with depleting foreign exchange reserves

• Government has allocated PKR 24bn during FY18-19 for the acquisition of land

• Whereas the Government of Pakistan is also negotiating with China regarding the financing of the project

Diamir Bhasha Dam

Page 7: Brief Overview Diamir Bhasha Dam and Mohmand DamJul 05, 2018  · 3 Location: The project is located on Indus River, about 315 km upstream of Tarbela Dam, 165 km downstream of the

7

Key Challenges

• Area of the dam would form part of both KPK (Kohistan) and Gilgit Baltistan which would lead towards differences

between the province and administrative territory with land ownership being a major hurdle

• In particular, it would not be an easy task to move heavy machinery in an area like Gilgit Baltistan

• Financing of the project from World Bank / Asia Development Bank and other donors is difficult amid location

Impact on the Economy and Sectors

• The project would create cement demand of ~5.0mn tons (over a span of 10 years) or 0.5mn tons per annum, which

is around 2% of the annual North demand

• Likewise, the steel consumption is expected at 1.4mn over 10 years or (0.14mn per annum) which is 4% of annual

rebar demand

• This will also create thousands of jobs for both skilled and un-skilled workers over the duration of the project

• It is expected to add 4,500MW (15% of current capacity) of clean and cheap electricity to the national grid

Diamir Bhasha Dam

Page 8: Brief Overview Diamir Bhasha Dam and Mohmand DamJul 05, 2018  · 3 Location: The project is located on Indus River, about 315 km upstream of Tarbela Dam, 165 km downstream of the

8

Location:Construction of this project is proposed at the Swat River about 5 km upstream Munda Head Works in Mohmand AgencyFATA, Khyber Pakhtunkhwa

Mohmand Dam

Overview

Page 9: Brief Overview Diamir Bhasha Dam and Mohmand DamJul 05, 2018  · 3 Location: The project is located on Indus River, about 315 km upstream of Tarbela Dam, 165 km downstream of the

9

• Mohmand Dam was previously referred to as Munda Dam

• Height of the Dam will be 213m

• Gross storage capacity is expected to be 1.2 MAF

• Live storage capacity is around 0.6 MAF

• Gross power generation capacity will be 800MW

• Expected completion time is 6 years

• Estimated cost of the project is USD 2.6bn

Mohmand Dam

Salient Features

Mohmand Dam – Snapshot

Dam Type Concrete Faced Rock fill

Height of Dam 213 m

Storage Capacity 1.293 MAF

Live Storage Capacity 0.676 MAF

CCA 16,737 Acres

Power Generation 800 MW

Execution by WAPDA

Expected Completion 6 years

Estimated Cost (USD) 2.6bn

Source: WAPDA and AHL Research

Page 10: Brief Overview Diamir Bhasha Dam and Mohmand DamJul 05, 2018  · 3 Location: The project is located on Indus River, about 315 km upstream of Tarbela Dam, 165 km downstream of the

10

Status• Land acquisition in progress (initial stages)

Funding

• Negotiation with International and local donors along with WAPDA’s internal cash flow generation

• Allocation of PKR 2bn during FY18-19 for the acquisition of land

Key Challenges

• The area of Mohmand Agency FATA requires major upgradation of road network and setting up of base camp

• Difficult to mobilize heavy machinery

• Financing of the project

Mohmand Dam

Page 11: Brief Overview Diamir Bhasha Dam and Mohmand DamJul 05, 2018  · 3 Location: The project is located on Indus River, about 315 km upstream of Tarbela Dam, 165 km downstream of the

11

Impact on the Economy and Sector

• The project would create cement demand of ~1.5mn tons over span of 6 years or 0.25mn tons per annum, which is

around 1% of North region annual demand

• Likewise, the consumption of steel is expected at 0.34mn over 6 years or 0.05mn tons per annum, which is 1% of

annual rebar demand

• Employment opportunities in FATA region

• It is expected to add 800MW (3% of current capacity) of clean and cheap electricity to the national grid

Mohmand Dam

Page 12: Brief Overview Diamir Bhasha Dam and Mohmand DamJul 05, 2018  · 3 Location: The project is located on Indus River, about 315 km upstream of Tarbela Dam, 165 km downstream of the

Disclaimer

12

Analyst Certification: The research analyst(s) is (are) principally responsible for preparation of this report. The views expressed in this research report accurately reflect the personal views of the analyst(s)

about the subject security (ies) or sector (or economy), and no part of the compensation of the research analyst(s) was, is, or will be directly or indirectly related to the specific recommendations and views

expressed by research analyst(s) in this report. In addition, we currently do not have any interest (financial or otherwise) in the subject security (ies). Furthermore, compensation of the Analyst(s) is not

determined nor based on any other service(s) that AHL is offering. Analyst(s) are not subject to the supervision or control of any employee of AHL’s non-research departments, and no personal engaged in

providing non-research services have any influence or control over the compensatory evaluation of the Analyst(s).

Equity Research Ratings

Arif Habib Limited (AHL) uses three rating categories, depending upon return form current market price, with Target period as Dec’18 for Target Price. In addition, return excludes all type of taxes. For more

details kindly refer the following table;

Equity Valuation Methodology

AHL Research uses the following valuation technique(s) to arrive at the period end target prices;

Discounted Cash Flow (DCF)

Dividend Discounted Model (DDM)

Sum of the Parts (SoTP)

Justified Price to Book (JPTB)

Reserved Base Valuation (RBV

Risks

The following risks may potentially impact our valuations of subject security (ies);

Market risk

Interest Rate Risk

Exchange Rate (Currency) Risk

Rating Description

BUY Upside* of subject security(ies) is more than +10% from last closing of market price(s)

HOLD Upside* of subject security(ies) is between -10% and +10% from last closing of market price(s)

SELL Upside* of subject security(ies) is less than -10% from last closing of market price(s)

Page 13: Brief Overview Diamir Bhasha Dam and Mohmand DamJul 05, 2018  · 3 Location: The project is located on Indus River, about 315 km upstream of Tarbela Dam, 165 km downstream of the

Disclaimer

13

This document has been prepared by Research analysts at Arif Habib Limited (AHL). This document does not constitute an offer or solicitation for the purchase or sale of any security. This publication is

intended only for distribution to the clients of the Company who are assumed to be reasonably sophisticated investors that understand the risks involved in investing in equity securities. The information

contained herein is based upon publicly available data and sources believed to be reliable. While every care was taken to ensure accuracy and objectivity, AHL does not represent that it is accurate or

complete and it should not be relied on as such. In particular, the report takes no account of the investment objectives, financial situation and particular needs of investors. The information given in this

document is as of the date of this report and there can be no assurance that future results or events will be consistent with this information. This information is subject to change without any prior notice. AHL

reserves the right to make modifications and alterations to this statement as may be required from time to time. However, AHL is under no obligation to update or keep the information current. AHL is

committed to providing independent and transparent recommendation to its client and would be happy to provide any information in response to specific client queries. Past performance is not necessarily a

guide to future performance. This document is provided for assistance only and is not intended to be and must not alone be taken as the basis for any investment decision. The user assumes the entire risk of

any use made of this information. Each recipient of this document should make such investigation as it deems necessary to arrive at an independent evaluation of an investment in the securities of companies

referred to in this document (including the merits and risks involved), and should consult his or her own advisors to determine the merits and risks of such investment. AHL or any of its affiliates shall not be in

any way responsible for any loss or damage that may be arise to any person from any inadvertent error in the information contained in this report.

© 2018 Arif Habib Limited: Corporate Member of the Pakistan Stock Exchanges. No part of this publication may be copied, reproduced, stored or disseminated in any form or by any means without the prior

written consent of Arif Habib Limited.