Upload
akhilesh-dwivedi
View
215
Download
0
Embed Size (px)
Citation preview
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
1/35
+ Written comments on this Paper are invited and will be received upto 31 st
December, 2004.
* Advisor to Govt. of Bahrain, Bahrain.
Paper No.507
“BRIDGING” THE ARABIAN–GULF BETWEEN
QATAR AND BAHRAIN-CONCEPTUAL DESIGN &
CONSTRUCTION”+
By
DR.V.K. RAINA*
CONTENTS
Page
1. Introduction ... ... 463
2. Geometrical and Functional Requirements ... ... 4723. Structural Capacity Requirements .. ... 473
4. Materials and Workmanship Requirements ... ... 474
5. Bridge Locations and Type ... ... 475
6. Conceptual Design Philosophy .. ... 476
7. Conceptual Design ... ... 478
8. Construction and Erection Concept ... ... 481
9. Prefabrication Yards ... ... 484
1. INTRODUCTION
1.1. The Challenge
This most mighty of ‘bridges’, a 40 km. long Sea-Link, will connect
Bahrain with Qatar, cutting through the Arabian Gulf waters that are one
of the most highly charged with the attacking chlorides, sulphates and
moluscs–the tripple killers of structure–durability in the Gulf waters.
Above all, its alignment, effecting the location and extent of the
navigation channels, the effect of associated dredging for these channels,
the location and extent of island–embankmants, their effect on the delicate
balancing of water and salt exchange across, the unobstructed migration
of shrimps and minimum disturbance to the fresh water acquifers mid-sea,
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
2/35
DR. RAINA ON464
in order to have an almost zero impact on environment, are only some of
the terrible challenges to be met in designing and constructing this trulyunique civil engineering feat of the century!
Hence evolvement and fixing of the various technical requirements
and parameters of design for this classical structure are a class of their
own that call for unstinted clinical attention of the best minds there are
in bridge structure location, design and construction in such trying
circumstances.
1.2. The Project
For a ‘large’ project of this nature, a decision on the number and
scope of contracts constituting it may be critical to the eventual success
of the project. Having multiple contracts will give the Employer more
control than under a single contract for the entire project, and it may be
more economic by maximising competitive pricing. On the other hand,
multiple contracts will require more interface managemeent from the Client’s
organisation.
The contract “packaging” could perhaps be divided into the following
contracts:
· Contract No 1: Coast-to-Coast Fixed Link (39.94 km. long)
·
Contract No 2: Qatar Land Works· Contract No 3: Bahrain Land Works
The ‘offshore’ part of the Works could perhiaps be done on “Design-
and-Build” basis (for reasons of ‘clearer risk allocation’ and ‘speedier
construction – since Design-Build allowes an overlap between Design
and Construction activities’), while the “on-shore” works - where the
‘risk allocation’ is simpler - need not necessarily be of a “Design-and-
Build” nature and therefore could be done as item rate constructioncontracts. However, no final decision has been taken as yet.
The characteristcs and scope of each contract will determine the
party responsible for the design of the Works. A brief description of the
scope might then be as follows:
Contract No. 1, The Causeway __ Coast-to-Coast (i.e. offshore) part
of the Work:
The characteristics and overall scope of Contract No.1 may be
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
3/35
“BRIDGING” THE ARABIAN-GULF BETWEEN QATAR AND BAHRAIN CONCEPTUALDESIGN & CONSTRUCTION
465
summarised as follows:
· A total causeway length of 39,940 m from coast to coast;
· A dual carriageway road on the causeway with two lanes in
each direction;
· Six embankments in the causeway alignment with individual
lengths between 500 m and 6,245 m, and with a total embankment
length of approximately 17,990 m;
·
Five bridges with individual lengths between 1,320 m and10,070 m, including high-level navigation spans in two of the
five bridges, and with a total bridge length of approximately
21,950 m;
· Miscellaneous works including ancillary buildings, utilities
and services from coast to coast;
· Dredging from two navigation channels;
· Two extended embankments for the purposes of rest areas,
and
· Two fill depots for surplus dredged material.
Contracts No. 2 & 3, the Land Works (i.e. on-shore) parts of the
work:
The Land Works under Contracts No. 2 and 3 will comprise all
works on land in each country from the “Coast-to-Coast Fixed Link”interface up to and including tie-ins with existing infrastructures. These
Contracts could include the following:
· Directional interchanges in Qatar and Bahrain
· Road Works
· Border and Tolling facilities
· An Operation and Maintenance complex in Qatar
· Miscellaneous works, including ancillary buildings, fencing,parking areas, utilities and services, and
· Landscaping
1.3. Materials & Quantities:
The construction of the Causeway will require import of considerable
quantities of materials. Most of the materials will be imported directly to
the work sites through temporary harbours established near the landfalls
of the Causeway. Some materials will require land transport or combined
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
4/35
DR. RAINA ON466
land/sea transport. The bulk parts of the materials will be imported from
other countries as available resources both in Qatar and Bahrain arelimited.
Table 1 provides a summary of main construction material quantities.
The table summarises permanent materials as per theoretical bulit-in
volumes. In addition are quantities for temporary works which for some
of the materials (e.g. stone and sand fill) can reach approximately 10 per
cent of the volumes for the permanent materials.
For the permanent materials an add-on for waste and tolerances
should be made to reach the actual required quantity of the respective
materials. This could add a volume of as much as 20-25 per cent for some
of the material categories (e.g. blinding layers and sand fill).
TABLE-1. MAIN QUANTITIES AND POTENTIAL SOURCES OF MATERIALS
Material Unit Quantity Potential Source
Stone fill m3 ~ 5,630,000 UAE, Iran, Oman
Sand fill, offshore 1) m3 ~10,400,000 Locally dredged material
Sand fill, onshore 2) m3 ~ 850,000 Local sources
Geotextile m2 ~ 691,000 Europe, Far East, USA
Structural concrete m3 ~ 650 ,000 Coarse aggregates from UAE
Fine aggregates either locally
dredge’d sea sand or desertsand from Saudi Arabia
Cement from Qatar, Europe,
Far East or USA
Reinforcement & tonnes ~ 116,000 Europe, Far East, USA, Qatar
prestressing
Cable stay tendons tonnes ~ 840 Europe, Far East, USA
Structural steel tonnes ~ 2,200 Europe, Far East, USA
Road base m3 ~ 274,000 UAE, Oman
Asphalt m2 ~ 1,418,000 Coarse aggregates from UAE,
Oman Bitumen from sources
in the Gulf Area
Crash barriers & railings m ~ 201,000 Europe, Far East, USA
Buildings m2 ~ 17,000 Miscellaneous sources
Landscaping m2 ~ 600,000 Local sources
1) Sand fill in embankments, rest areas and protection islands2) Sand fill/imported fill in embankments for interchanges & link roads in Qatar and
Bahrain.
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
5/35
“BRIDGING” THE ARABIAN-GULF BETWEEN QATAR AND BAHRAIN CONCEPTUALDESIGN & CONSTRUCTION
467
1.4. Studies, Surveys, Site-lnvestigations, Conceptual Design,
Time and Cost
The works carried out so far were accomplished in two phases.
1.4.1. During Phase 1 the following tasks were undertaken:
· Studies, Surveys and Site-investigations in a 15 x 40 km study
corridor,
· alternative alignments and recommending in favour of one
alignment,
· a Sketch Design for the Causeway.
1.4.2. During Phase 2 the following tasks were accomplished:
· detailed studies, surveys and site investingations for the
selected alignment,· developing a conceptual design for the Causeway
1.4.3. A very brief summary of Phase 2 accomplishments is as
follows:
Planning Study: A further review of the existing and planned land
use and drawing up Conceptual Local Area Plans for the areas adjecent
to the Causeway landing points.
Traffic Study: Updating and detailing of the Phase 1 Traffic Study
for the selected alignment. The traffic forecast made in Phase 1 was
confirmed with Causeway average daily traffic of 3,900 vehicles in 2005,
5,000 in 2010 and eventually reaching 12,000 in 2050.
Topographic Survey: Detailed survey of a 300 m wide corridor
around the onshore part of the alignment to create a digital terrain model.Also, the selected alignment has been staked out on site in both countries.
Utility Survey: The information collected in Phase 1 on existing
and planned services close to the landing points has been updated and
further detailed.
Bathymetric and Geophysical Surveys: Close grid Bathymetric and
Geophysical Surveys have been conducted in the selected alignment.
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
6/35
DR. RAINA ON468
Geotechnical Investigations and Evaluation: A total of 14 onshore
boreholes, 8 trial pits and 110 offshore boreholes have been made inPhase 2 along with laboratory testing. These have been used as basis
for a geotechnical evaluation to establish feasible foundation methods
for bridges and embankments.
Marine Studies: The Phase 1 marine surveys and measurements
have been supplemented during Phase 2. The numerical hydraulic modelling
has been refined and optimised. The modelling concludes that the ‘Zero-
solution’ on water exchange can be achieved by dredging of two channels,that also serve for navigational purposes.
Environmental Impact Assessment: An EIA study has been
conducted, reported and presented to the Qatar Supreme Council for
Environmental & Natural Reserves and to Environmental Affairs in Bahrain.
Conceptual Design, Time & Cost Study: Conceptual Design has
been made for the following components of the project:
Alignment and Road: Drawings of horizontal alignment and vertical
profile for the selected road including the interchanges onshore Qatar
and Bahrain.
Bridges: Toal bridge length of 22 km, with two main navigation
span bridges made as cable stayed, each with a main span of 225 m. Allother bridges are low level viaduct bridges using a concept of span-long
(50 m) pre-cast units made onshore and placed by heavy marine lifting
equipment.
Embankment and Dredging: About 18 km of the Causeway will be
made as embankment using dredged fill as core material with stone bunds
and armour slope protection at the sides. Extended embankments at two
locations provide rest and turn-around facilities for the Causeway users.Surplus dredged materials will be placed in two fill depots located close
to the dredged shipping channels.
Tolling and Border Facilities: Tolling facilities will be located
onshore in the two countries. Border facilities and Causeway Operation
& Maintenance complex will be located onshore in Qatar.
Utilities and Services: Utilities and Services are required for theCauseway itself in addition to space provision for a possible future
national electrical link.
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
7/35
“BRIDGING” THE ARABIAN-GULF BETWEEN QATAR AND BAHRAIN CONCEPTUALDESIGN & CONSTRUCTION
469
Construction Time: A review of the expected construction period
has concluded with 4¾ years as a realistic, albiet tight constructionprogramme.
Construction Cost: Cost estimates have been prepared and conclude
with a total estimate for the tender sum of QR 6,200 million (USD 1,700
million) for the coast-to-coast Causeway including services and onshore
facilities and interchanges, but excluding wastage, VAT and various
other items but including 7 per cent escalation of price; rates and costs
based on January, 2002 values and best guesses of Contractor’s DirectCosts. However, the actual overall cost today is likely to exceed the
above figure, which will soon be known when the job is put to tender.
1.5. Special Features of Qatar-Bahrain Causeway (QBC)
The most important special features of the Conceptual Design for
the Qatar-Bahrain Causeway are:
Environmental Impact
· A zero-solution for exchange of water and salt from Bay of
Salwa has been obtained for the conceptual design solution.
· Optional culverts can be made in long embankments to improve
exchange of water-mainly to benefit shrimp spawning and
nursery.· All reclamation including the surplus material from dredging
of navigation channels are placed behind bunds to keep spillage
low.
Alignment & Layout
· Large radii horizontal curves assure a view to the oncoming
parts of the Causeway, variatioion in the view and avoidanceof sun glare over longer distances.
· A free view over the sea area and other Causeway elements
is assured all along the causeway.
· The longitudinal profile places the bridge girders high enough
to avoid wave loads and severe salt water spray.
· Provisions are made in the longitudinal profile for free vertical
clearances for the main bridges of 35 m (Qatar) and 27 m
(Bahrain) in addition to two secondary navigation routes withvertical bridge clearances of 15 m.
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
8/35
DR. RAINA ON470
Bridges
· Rational prestressed concete box girder design over entire
length and cable stayed altenative over two large navigation
portions.
· Same generic shape is applied for all bridge piers in order to
obtain a coherent design and the appearance as a same family
of bridge components.
· Large diameter bored pile design for pier foundations assures
a great flexibility in the contractor’s design and work schedule.(Precast tubular concrete piles placed in pre-drilled vertical
holes).
· The overall structural systems are designed for efficient
construction methods.
· The components are well suited for mass production onshore,
which will help to obtain a good quality and durability for the
elements.
· Landmark qualities of the main bridges are aimed at.
· Design is for a 100 years service life of the Causeway.
Embankments & Dredging (Marine Works)
· Conventional revetment design.
· use of materials available from the Gulf region is emphasized.
· Revetment protection designed for wave action.
· Limited inconvenience from overtopping waves for travellers.
· Limited likelihood of soft soil and need for soil replacement.
· Low spillage dredging methods for the works.
Tolling & Border facilities
· Tolling and border facilities located onshore.
·
Tolling, immigration, car insurance check and customs check in Qatar.
· Tolling and arrrival check in Bahrain.
· Access to rest areas for Tourists and visitors.
Installations & Services
· Provision of power, water and sanitary systems at border
stations and rest areas.· Road lighting sysyem all along the Causeway.
· Illumination of landmark main bridge structures.
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
9/35
“BRIDGING” THE ARABIAN-GULF BETWEEN QATAR AND BAHRAIN CONCEPTUALDESIGN & CONSTRUCTION
471
· Illumination and marking of navigation spans of bridges.
·
Traffic Monitoring and Surveillance System (TMSS) to securesafe and efficient use of the Causeway facilities.
· Electroinic Payment Systems for collection of toll and transfer
of information to banking systems and administrative systems
at the Causeway Authority.
· SCADA – Supervisory Control and Data Acquisition System
for collection of all measurement data and information on the
status of Causeway systems.
· Communication systems for internal and external communicationby the Causeway Authority and communication by travellers.
· Povisions for 3 future HV-Interconnection Cables between
Qatar and Bahrain.
· Provisions for Telecommunication Cables between Qatar and
Bahrain.
Time, Quantities and Cost
· Design & Build contract assumed at conceptual design stage
for coast-to-coast part of Causeway.
· 4¾ years construction period is estimated for the project (very
tight).
· A tender price estimate (mentioned above) is provided for the
Causeway including the land works.
Aesthetics
· A smooth crossing experience for the travellers.
· Efficient handling at check points by a linear layout of the
facilities.
· A pronounced visual variation is obtained by the curved
alignment, variations in longitudinal profile due to navigation
bridges, rest areas and landmark structures like main bridges
and canopy structures at the land facilities and rest areas.
· Landmark bridges are focus points along the Causeway.
· A unique, strong and simple visual entity.
· Transparent and light structures are at the border facilities
and at the rest areas.
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
10/35
DR. RAINA ON472
2. GEOMETRICAL AND FUNCTIONAL REQUIREMENTS
2.1. The geometrical requirements to roadway layout and width are
to accommodate an emergency lane of 3.0 m and two travel lanes of
3.65 m each, with a shoulder of 1.2 m, thereby giving two 11.5 m wide
roadways kerb to kerb.
2.2. The soffit of girders shall be at a certain height above water,
the three criteria being:
Requirement 1
Dictated by two main navigation channels at stations 34335 and
57175, both with a width of 160 m and vertical clearances of 35 m and
27 m respectively, corresponding to heights of 35.3 m and 27.3 m above
QBC2001. (The 0.3 m portions allow for the long term sea – level rise
due to feared Global Warming Effect.)
Requirement 2
Dictated by two secondary navigation channels at stations 21210
and 54045, both with a width of 45 m, and vertical clearance of 15 m
corresponding to a height of 15.3 m above QBC2001. (The 0.3 m portions
allow for the long term sea-level rise due to feared Global Warning
Effect.)
Requirement 3
Dictated by the requirement that the deck-soffit should be at a
certain height above the sea to avoid direct hit of waves and to have only
a limited amount of salt spray on the structure. The required height is
7.2 m above QBC2001 for bridge structures from station 20500 (BR1,
begin-station) to station 36000, and 5.8 m above QBC2001 for bridgestructures from station 36000 to station 58647.5 (BR5, end-station).
2.3. Various ‘Requirements’ for the Bridges have already been
reported in the other related Papers dealing with “Conceptual Design
Basis”1 and “Conceptual Study & Strategy for Durability”2 for the QATAR
– Bahrain CAUSEWAY (QBC), to which reference may be made.
2.4. A longitudinal and a plan profile have been developed for theselected alignment according to the above requirements.
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
11/35
“BRIDGING” THE ARABIAN-GULF BETWEEN QATAR AND BAHRAIN CONCEPTUALDESIGN & CONSTRUCTION
473
2.5. Accordingly following three Bridge – types have been
developed:
· Viaduct Bridge – Low Level type
· Viaduct Bridge – Elevated type
· Main Bridge – Cable Stayed type
The Viaduct Bridge – Low Level portions cover majority of the
bridge structure with a length of 18,450 m out of the total bridge length
of 21,950 m. The Viaduct Bridge – Elevated portions cover a length of 2,672 m while the two Main Bridges each have a length of 414 m (main
span and anchor span).
The location of the bridge structures is defined in Fig. 1 and
Table 1.
Fig. 1. Naming and numbering of bridge structures and embankments
The requirement for two navigational channels each with a navigation
width of 160 m has led to the introduction of a cable-stayed bridge type
that has landmark qualities and will be the central attraction for the
Causeway.
3. STRUCTURAL CAPACITY REQUIREMENTS
The structural capacity has been verified according to the AASHTO
Load and Resistance Factor Design specifications. The LRFD specifications
have been followed in general with the exceptance where it is found not
to represent the local conditions for the Causeway.
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
12/35
DR. RAINA ON474
The modifications to the LRFD have been introduced in the following
areas:
· Wind pressure:
The available extreme wind data at the Al Arish site during the
years 1985-1995 has been studied. A design gust wind velocity VG at
10 m above design water level of 36.2 m/s has been found to represent
the conditions at the site. This value has been used in the conceptual
design as the VG value when defining the wind pressure according toAASHTO LRFD, section 3.8. This represents a reduction from the default
design gust wind velocity value of 44.4 m/s. The corresponding design
mean wind velocity averaged over 10 minutes and measured in 10 m
height is V10
=24 m/s.
· Site-specific ship collision forces have been considered as per
Conceptual Design Basis document mentioned above, and
not according to AASHTO Load and Resistance Factor Design.
· Durability aspects against the harsh environmental exposure
dictate modifications and additions to concrete specifications
and workmanship.
4. MATERIALS AND WORKMANSHIP REQUIREMENTS
The Causeway is located in a severe marine environment with extreme
exposure to salt from water, water spray and salt-laden dust in combination
with high temperatures. The exposure calls for the highest attention to
durability during design, construction and operation and maintenance of
the Causeway. In combination with state-of-the art material and
workmanship specifications the structural detailing requires all external
surfaces to have sloping surfaces to secure good run-off of water with
minimum collection of salt-laiden dust and water. Corners are rounded or
chamfered to avoid acute corners likely to deteriorate and spall. With
regard to workmanship following have been suggested.
· Use of slip-forming should be prohibited and in-situ concrete
work in the sea severely limited.
· Compulsory use of permeable form liner shall be considered in
selected areas (to give clean solid surfaces).· The curing requirements shall be strict and comprehensive.
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
13/35
“BRIDGING” THE ARABIAN-GULF BETWEEN QATAR AND BAHRAIN CONCEPTUALDESIGN & CONSTRUCTION
475
· Steam curing shall not be allowed (to cut out possibility of
differential temperature cracks from probable human error).· Strict restictions shall be applied to maximum and differential
temperatures during casting and curing of concrete.
· Strict restrictions shall apply to ensure careful handling during
transport and erection of elements.
· Strict QA procedures shall apply.
5. BRIDGE LOCATIONS AND TYPE
The proposed Causeway bridge structures are numbered according
to the figure below. The exact locations of the three bridge types are
identified with regard to ‘station begin’ and ‘station end’.
TABLE-2. BRIDGE NUMBER, TYPE, LENGTH AND STATIONING
Bridge Bridge type Length Station (m)
No: (m) Begin End
BR1 Viaduct type, Low Level 10070 20500,0 30570,0
BR2 Viaduct type, & Main type 2620 33012,5 35632,5
Viaduct type, low level 342 33012,5 33354,5
Viaduct type, elevated 686 33354,5 34040,5
Main
(cable stayed portion) 414 34040,5 34454,5
Viaduct type, elevated 850 34454,5 35304,5
Viaduct type, low level 328 35304,5 35632,5
BR3 Viaduct type, low level 1320 41420,0 42740.0
BR4 Viaduct type, low level 5220 48985,0 54205,0
BR5 Viaduct type, & Main type 2720 55927,5 58647,5
Viaduct type, low level 492 55927,5 56419,5
Viaduct type, elevated 636 56419,5 57055,5
Main
(cable stayed protion) 414 57055,5 57469,5
Viaduct type, elevated 500 57469,5 57969,5
Viaduct type, low level 678 57969,5 58647,5
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
14/35
DR. RAINA ON476
6. CONCEPTUAL DESIGN PHILOSOPHY
6.1. The objective of the conceptual design has been to identify,
visualise, verify and document a feasible rational design and construction
method that fulfils overall functional and engineering requirements taking
into account prevailing conditions and restraints.
6.2. However, if the conceptual design were to be developed into
a tender design, it may not necessarily turn out to be the lowest cost
solution among alternative tender design submittals. An alternativetender desing has the benefit of being suited to a specific contractor’s
work methods and available equipment and on the marked situation with
regard to material cost. The presented conceptual design uses a
prestressed concrete deck girder but the possibiliy of a steel bridge
solution or a composite steel/concrete solution being cost competitive
exists and cannot be ruled out at this stage although prestressed concecte
has more advantages. The preparation of tender documents will therefore
consider carefully the requirements that would be applicable to thesealternative solutions.
The durability and maintenance requirements are more stringent for
the structural steel as also for the composition of the wearing course for
the ‘steel only’ solution. The hot climate and a relatively flexible steel
deck plate requires careful considerations into a suitable wearing course.
More importantly it should be noted that the steel box decks willrequire to be permanently equipped with perenially power – driven de-
humidifiers to control humidity perpertually to control corrosion. This
factor, together with other Durability considderations, itself is likely to
tilt the balance in favour of prestressed concrete, as happened in the case
of King Fahad Causeway.
6.3. Some key factors have been identified in achieving the rational
design in ‘concrete’ that is considered to yield a cost efficient and
durable design. These key factors are:
· Relatively, ‘short’ span lengths:
-economical best solution for relatively shallow foundations
for the given substrata conditions.
·
Prefabrication in a precast yard on–shore:-‘maximum work on-shore/and minimum work at sea’ is the
economical best solution.
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
15/35
“BRIDGING” THE ARABIAN-GULF BETWEEN QATAR AND BAHRAIN CONCEPTUALDESIGN & CONSTRUCTION
477
· Prestressed concrete:
-material preferred in achieving specified design requirementsand ‘durability’ with low maintenance cost.
· Repetition in prefabrication:
- results in a rational and cost effective solution.
· Large prefabricated elements:
-shortens construction time and reduces cost but limit weights
to 1000 T (because of limitation on available draught).
· Minimum draught required for the barges to carry heavy P/c
elements:
-the average 4 to 5 m deep stretches along the alignment will
allow just about enough draught for these barges to cary
about 1000 T P/c elements. This sets the weight limit if these
stretches do not have to be dredged generally. (Bridge to be
replaced by Embankment in shallower stretches.)
6.4. The draught for a barge loaded by a 1000 t carrying crane is
around 2.0 m to 2.4 m and allowance for waves and clearance under keel
is required for a weather-independent and safe construction progress.
TABLE-3. WATER DEPTH AT BRIDGE LOCATIONS
Bridge Min. water Max. water Depth Average water depth (m) depth (m)
BR1 2.0 7.4 5.6
BR2 1.3 4.5 3.0
BR3 1.4 6.2 5.0
BR4 2.8 6.9 5.7
BR5 3.8 6.1 5.3
6.5. The listed water depths at various bridge locations given in
Table 3 confirms the generally shallow water along the Causeway location.
The very shallow water at BR2 over a fairly long section is considered to be
insufficient for the construction without dredging. Dredging has to done for
water depth less than 4 m. Lesser water depths for the remaining bridges are
very localised and do not represent a significant problem for the construction.
The average water depth is more than 4 m, except for BR2.
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
16/35
DR. RAINA ON478
6.6. The selection of a limiting lifting capacity of 1000 t allows the
construction to be carried out with existing standard equipment that can beobtained in the construction market at reasonable commercial rates. (KFC
could use slightly heavier lifting capacity for its water depth.).
6.7. Longer spans, requiring heavier lifts, would increase the required
draught and hence the water depth. This would require additional dredging
in localised areas for all bridges and for deeper dredging for the entire length
of BR2. After due consideration, this idea of heavier lifts was given up finally.
However, the issue can be re-visited during detailed design for the possibilityof heavier lifts.
6.8. The 50 m optimum span lengh for the Causeway has been
considered at a conceptual level but the cost difference between 50 m span
and longer spans up to 65 m is within a few percent. This can be considered
in the detailed design.
6.9. Infact even the span articulation of ‘50 m spans with 8 m cantileverarms’ and ‘34 m drop spans’, as in KFC, could also be looked into in detailed
design stage, yielding a determinate structural system too.
7. CONCEPTUAL DESIGN
7.1. Foundation
7.1.1. For viaduct bridges: It is ‘pile’ foundation for all viaductbridges, consisting of precast prestressed concrete hollow 4.5 m diameter
piles, installed into predrilled holes. The conceptual design of the piles
has established that piles are to be installed with pile tip elevation at a
depth of approximaterly 10 m into competent rock. The average pile
length has been found to be just short of 17 m with a variation from 10
to 27 m. The magnitude of the soft sand, silt and clay layers varies along
the alignment according to the geological profile of sub strata.
An alternative open foundation for the viaduct bridges is feasible
but is not favoured for the following reasons:
· The pile foundation is more flexible in obtaining the required
load bearing capacity as the depth of the boring/pile can be
increased to adjust for corrections to the assumed bearing
capacity during construction.· The pile foundation working is less prone to adverse weather
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
17/35
“BRIDGING” THE ARABIAN-GULF BETWEEN QATAR AND BAHRAIN CONCEPTUALDESIGN & CONSTRUCTION
479
conditions in comparison, with the benefit of an almost
uninterrupted construction cycle. Interruptions are likely tobe more problematic for the open foundation where adverse
weather conditions will cause longer delays during installation
of numerous such foundations in the open sea.
The difference in cost was found to be marginal with a small cost
advantage to the pile alternative, even ignoring the possible weather-
related delay problems with open foundation work.
The (deeper) pile foundation could present a problem if fresh-water
aquifers were to be found at their locations. The bore hole information
obtained during Phases 1 and 2 has not identified the existence of aquifers
but it is considered too early to rule out the existence of aquifers all
together. Fresh water aquifers are known to exist below the sea bed close
to the coastline of Bahrain and therefore the Bahrain Water Resource
Directorate was contacted. Their initial conclusion is that the proposed
deeper pile foundation along the selected alignment will not be a problemto aquifers. This conclusion should be verified by the selected contractor
once his pile design has been completed. There are no records of fresh
water aquifers close to the Qatar coast.
The open foundation could be an alternative solution. It is
recommended to keep it as an alternative in the preparation of tender
documents to allow contractors such option.
The foundation for the low level sections of the Viaduct Bridges is
a single pile per pier (i.e. per carriageway). The single pile solution has
been found to possess sufficient structural capacity up to a roadway
elevation of approximately 19 m above QBC2001. The soil-structure
interaction has not been fully studied and the maximum elevation of the
roadway with a single pile could be further raised when taking the soil-
structure interaction into considerat ion. The information available inPhase 2 has not been sufficient to fully determine further relief from the
soil-structure interaction. This should be the focus of the tender Document
and the detailed design when the soil data collection has been carried out
rigorously.
In the elevated portions of Vaiduct–Bridges at a roadway height
above approximately 19 m above QBC2001, a single pile is inadequate. A
two-pile support is introduced under each pier and foundations underadjacent piers at the same station are tied togerther with a cross beam
connector.
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
18/35
DR. RAINA ON480
7.1.2. For main bridges (Cable Stayed) : The pylon is founded on
a huge open founation (40x40 m). The bottom of this foundation of theQatar side Main Bridge (at station 34222.5) is determined to be at -17.0
m. This foundation level at the Bahrain side Main Bridge (at station
57287.5) is determined to be at – 16.0 m. Both elevations secure the open
foundation in competent material in the Pleistocene deposits. This open
foundation is a cast in-situ concrete footing suggested to be cast in
dry within a cofferdam enclosure. The footing is below the MSL, leaving
the pylon shaft elegantly protruding uninterrupted through the water
line.
7.2. Substructure
7.2.1. In the low level portions of the viaduct bridges: The pier
emerges from the pile from an elevation of approximately 0.75 m below
sea-bed, extending to approximately 0.5 m below soffit of deck girders.
the pier shafts have been shaped with a curved surface for aesthetic
reasons, and are precast prestressed concrete hollow shafts. The piershafts have been sized to support Bearings, provide required load carrying
capacity and have, to some degree, been shaped to minimise the blocking
of the water flow. Up to a roadway elevation of 16 m, the piers have a
depth of 2.50 m in the longitudinal direction of the bridge. For highter
elevations (taller piers) the depth is increased to 3.0 m.
Scour protection shall be provided around the pier shafts unless
rocky sea floor provides sufficient protection against scour.
7.2.2. In the elevated portions of the viaduct bridges: The 3.0 m
deep pier section depth with the same shape as for the low level section
is used for the elevated sections.
7.2.3. In the main bridges (Cable stayed): Each Main Bridge has
a single central pylon. The shape of the pylon shaft is in family withthe pier shapes for the Viaduct Bridges. The pylon is a hollow cast in-
situ concrete pylon with variable wall thickness from 400 mm at the top
of the pylon to 800 mm at the base. The pylon is tapered with decreasting
cross sectional dimensions from its base at footing towards its top. The
top of the pylon can be accessed through a ladder and entry door at the
deck level with an access system inside the pylon. Access to the top
of the pylon is required not only during construction but also for inspection
and maintenance of the cable anchorages and pylon top light.
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
19/35
“BRIDGING” THE ARABIAN-GULF BETWEEN QATAR AND BAHRAIN CONCEPTUALDESIGN & CONSTRUCTION
481
Submerged ship collision fender islands have tentatively been
assumed to be provided at the pylon, at the anchor pier and at the pierclosest to the naviagation channel. Ships not on course will hit shallow
ground at the island edge and the island will absorb the kinetic energy
of the ship’s blow.
Each pier shaft at either end of the Main Bridge will be of the
elevated Viaduct Bridge pier category but will be tied-down to its pile–
cap by 4 Nos: 19 multistrands (through the box decks).
7.3. Superstructure
7.3.1. For viaduct bridges: The Viaduct Bridges have span lengths
of 50 m with a superstructure consisting of two precast prestressed
concrete box girders. The conceptual design of the superstructure for
the Viaduct Bridges consists of two independent identical psc box girders
for both low as well as for elevated portions.
Structural depth of box girder is 2.8 m.
7.3.2. For main bridges (Cable stayed): The standard Viaduct
Bridge deck precast box girder is to be used also for the Main Bridges.
The outside dimentsions of the box will be retained with modifications to
the web thickness and with some additional details to allow for a different
static system, with stay cable ‘support’ at every 7.5 m in the main span
and at every 5.0 m in the back span. A system of in-plan and crossgirder bracings by steel trusses between the boxes is proposed to carry
the horizontal and vertical load component of the stay forces in the main
span; while an in-plan thick cast in-situ concrete slab between the box-
flanges and steel cross-girders, carry such components of the stay forces
in the back span. Box girders are fabricated and installed in 50 m lengths
as for the Viaduct Bridges. The impression will therefore be one of a
soothing single continuous girder all along BR2 and BR5 where the Main
Bridges are located.
Plates 1 to 11 may be referred for explanation.
8. ‘CONSTRUCTION’ AND ‘ERECTION’ CONCEPT
8.1. Introduction
The conceptual study of the optimal construction method resultedin the selection of large prefabricated prestressed concrete elements as
the preferred construction method. This applies to both super and
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
20/35
DR. RAINA ON482
substructure elements. The same erection equipment is assumed to be
used for all components throughtout the construction period.
8.2. For Superstructure
8.2.1. In viaduct bridges: Typical box elements are fabricated in
span-long lengths. Box sections are constructed as being balanced
cantilevers on piers once erected with internal cantilever post-tensioning
cables installed and stessed in the precast yard. After erection on site,
the external continuity cables are installed and stressed after concreting/ grouting of in-situ ‘stitches’ between successive elements.
Precast prestressed elements are carried by crane or barge to the
location of installation and then lifted into their final positions. The
elements are erected with utmost care as balanced cantilevers with the
pier support at the centre of gravity for each span-long p/c psc double-
cantilever ‘butterfly’ element. Positioning the lifting points is of paramount
importance as also the presence of fair weather and wind. It is considerednecessary to erect the elements on temporary jacks with the capacity to
adjust the final positioning in both vertical and horizontal directions.
Once the girder is located correctly the permanent Bearings are built into
the structure.
The next step in the erection will be to construct the “in-situ stitch”
between the successive erected girders (comprising consprusign the semi
continuous unit between the Expansion Joints) at the Halving Joints.
Before concrete is placed, a positive fixation of the stitch is established
by providing precast concrete pads to maintain the specified gap distance
and at the same time tension temporary post-tensioning bars across the
in-situ stitch. Once the fixation is in place, the in-situ stitch concrete is
cast, using rapid hardening cement. At the prescribed curing age of the
in-stiu stitch, the external continuity tendons can be installed and tensioned.
The temporary post-tensioning bars can then be released and removed.
The erection method does not allow support from a previously
erected girder element as each element in principal is balanced around its
pier-support and would not require external balancing. However, in practice,
the girder elements would not be 100 per cent balanced and during
erection the wind load on the structure would also cause some out-of-
balance forces. These are however to be resisted by the temporary jacks
that are located on either side of the permanent Bearings. Extremecaution is called for this construction method.
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
21/35
“BRIDGING” THE ARABIAN-GULF BETWEEN QATAR AND BAHRAIN CONCEPTUALDESIGN & CONSTRUCTION
483
The adjustment facility in the temporary jacks and the independence
of the neighbouring girder element is considered an advantage whenachieving the correct alignment. At the same time it will cause minimal
restraints to the operations during erection with regard to progress of
previously erected girder elements.
8.2.2. In main bridges (Cable stayed) : Temporary rigid trestle
supports at 50 m intervals are used to allow same erection procedure as
for the Viaduct Bridges, with the entire deck structure erected before
installation of cable stays. Temporary post-tensioning will be used to
control the stresses during transport and erection of the deck girders.
8.3. For Substructure and Foundation
8.3.1. In viaduct bridges : The substructure comprises a single pile
and pier shaft unit constructed by firstly drilling a 4.75 m diameter hole
into the seabed to the required depth. A steel casing supports the
circumference while drilling and while installing the prefabricated pile
unit. The steel casing is afterwards withdrawn while grouting the annularspace between soil and pile. Installation of pile casings, bottom seal
concreting and grouting are carried out from a jack-up platform – working
for two adjacent piers simultaneously. The pier-pile is installed in the
casing by a 1000 t capacity floating crane. The taller piers near the main
bridges require two piles per pier and an interconnection between pile-
caps, and possibly between piers.
Installation is carried out as for the typical viaduct bridges butadditional work must be restricted to within the limit of 1000 t erection
capacity of the floating crane.
To allow for the variation in pier and pile length due to variable
elevation of roadway and pile tip, a large number of different-length
precast pier and pile units has to be considered. A selection of ‘adjustment-
sections’ in intervals of 0.3 m has been considered in the conceptual
design to allow for any late decision of final pile tip elevation. The‘adjustment-sections’ can be added to the bottom of the pile at the last
minute before it is prestressed and transported for installation.
Confirmatory Geotechnical investigations have to be done for each
pile for deciding its exact length.
Despite all this, where the founding level may, at the last minute,
require to be taken slightly deeper still, suitable concrete can plug be castunder – water in the pre-drilled hole and then the already prefabricated
psc pile installed on it.
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
22/35
DR. RAINA ON484
The roadway elevation will be fixed in the design and the variable
length of ‘pier’ can be arranged in adjustment of the shaft length in theprecast yard. Some tolerance in the top of pier elevation of +/-100 mm
is anticipated to be accommodated in an in-situ concrete plinth on which
the Bearing will be positioned with a high degree of accuracy.
8.3.2. In main bridges (Cable stayed) : A temporary island,
constructed at the pylon location, will serve as work area for construction
of the pylon and its foundation. The island will subsequently be modified
to serve as submerged ship collision island which shall be containedwithin stone-bunds and protected by armour stone. Landings for
construction materials and equipment are required. The pylon foundation
is constructed in–situ on the work island within a cofferdam enclousure
– which is first excavated and de-watered. The pylon foundation will be
cast in–situ at the bottom of the cofferdamed/ excavated/de-watared area.
The pylons are constructed in a climbing form, assisted by a tower
crane.
The anchor piers are ‘modified taller Viaduct Bridge piers’ but 4
Nos. 19 strand tie-down cables are required to carry the uplift forces
occurring in adverse situations of heavy traffic on the main span.
9. PREFABRICATION YARDS
One or more prefabrication yards will need to be established on-shore at a location where a temporary harbour facility, with 5 m water
depth, can be constructed.
The fabrication yard provides areas for steel fixing, pre-casting of
units, pre-assembly, prestressing, storage, concrete batching facilities,
offices and stores, workshops, etc.
The temporary harbour is to be protected by breakwaters and has
“load-out” facilities for the prefabricated elements and ‘quays’ for
unloading of concrete aggregates, cement, reinforcement, etc., and berthing
and service of marine construction plant.
A single construction yard for fabrication of all p.c. elements is
considered to be the most cost efficient arrangement and locations for
such a yard appear to be technically feasible both on Qatar and Bahrainside.
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
23/35
“BRIDGING” THE ARABIAN-GULF BETWEEN QATAR AND BAHRAIN CONCEPTUALDESIGN & CONSTRUCTION
485
Should it be decided ot establish more fabrication yards, each
facility should be dedicated to fabrication of one type of elements e.g.
piers or deck units, to reap the benefit of repetition in production at same
site. A second fabrication yard with a parallel production would be an
advantage because this provides a full back-up.
The prefabrication yard is arranged such that pile units, pier units
and deck units are constructed ‘between the tracks’ of a 1000 t gantry
crane. The crane lifts fabricated units from casting beds to storage and
transport barges in a ‘load-out’ facility arranged at the end of the track.
Prefabrication of reinorcement cages, small concrete elements and
special parts for sub assemblies is carried out outside the main production
line and moved into the line by cranes.
ACKNOWLEDGEMENTS
I am grateful and highly indebted to the authorities in Bahrain formy association with this mighty and one of the most challenging civil
engineering Projects of the century and cannot thank them enough for
the trust reposed. Participation in this most prestigeous of Projects is
really a lifetime’s dream and opportunity which, for me, nothing else
could equal. Grateful thanks to Cowi Consult who assisted in carrying
out the study.
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
24/35
PLATE 1
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
25/35
“BRIDGING” THE ARABIAN-GULF BETWEEN QATAR AND BAHRAIN CONCEPTUALDESIGN & CONSTRUCTION
487
P l a t e
1 .
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
26/35
DR. RAINA ON488
P l a t e
2 .
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
27/35
“BRIDGING” THE ARABIAN-GULF BETWEEN QATAR AND BAHRAIN CONCEPTUALDESIGN & CONSTRUCTION
489
P l a t e
3 .
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
28/35
DR. RAINA ON490
P l a t e
4 .
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
29/35
“BRIDGING” THE ARABIAN-GULF BETWEEN QATAR AND BAHRAIN CONCEPTUALDESIGN & CONSTRUCTION
491
P l a t e
5 .
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
30/35
DR. RAINA ON492
P l a t e
6 .
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
31/35
“BRIDGING” THE ARABIAN-GULF BETWEEN QATAR AND BAHRAIN CONCEPTUALDESIGN & CONSTRUCTION
493
P l a t e
7 .
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
32/35
DR. RAINA ON494
P l a t e
8 .
“B ” A G Q C
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
33/35
“BRIDGING” THE ARABIAN-GULF BETWEEN QATAR AND BAHRAIN CONCEPTUALDESIGN & CONSTRUCTION
495
P l a t e
9 .
D R496
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
34/35
DR. RAINA ON496
P l a t e
1 0 .
“BRIDGING” THE ARABIAN GULF BETWEEN QATAR AND BAHRAIN CONCEPTUAL 497
8/19/2019 Bridging-The Arabian-Gulf Between Qatar And Bahrain-Conceptual Design and Construction (1).pdf
35/35
BRIDGING THE ARABIAN-GULF BETWEEN QATAR AND BAHRAIN CONCEPTUALDESIGN & CONSTRUCTION
497
P l a t e
1 1 .