Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
2017 UNDERWATER
BRIDGE INSPECTION REPORT
BRIDGE #
DISTRICT: COUNTY: CITY/TOWNSHIP:
Date of Inspection:
Equipment Used:
Inspected By:
Report Written By:
Report Reviewed By:
Final Report Date:
07569
CSAH 90 over BLUE EARTH RIVER
District 7 Blue Earth SOUTH BEND
12/02/2016
Forsyth, Roy
Roy Forsyth
County Highway AgencyOwner:
MinnesotaSTATE:
UNDERWATER SUMMARY 3
UNDERWATER INSPECTION 4
UNDERWATER INSPECTION PROCEDURES 6
STRUCTURE INVENTORY 7
ELEMENTS 8
PICTURES 12
DRAWINGS 16
TABLE OF CONTENTS
PAGE NUMBER
Contractor:
Reinspect the submerged substructure units at the normal maximum recommended (NBIS) interval of sixty (60) months.
Collins Engineers, Inc.
9687Contractor Job Number:
RECOMMENDATIONS
REPORT SUMMARY
UNDERWATER INSPECTION
The substructure units inspected at Bridge No. 07569, Piers 2, 3, and 4, were in good condition with no defects of structural significance observed. The channel bottom around the substructure units consisted of firm material, which was well established and appeared stable. The west river bank exhibited vertically eroded slopes. Timber debris has accumulated at the Piers 2 and 3.
(A) The channel bottom material around the substructure units consisted of sand, gravel, and 2 to 4 foot diameter cobbles with up to 1 inch of probe rod penetration. (B) Timber debris, 2 foot diameter and smaller was observed around the upstream nose and along both faces of Pier 2, extending from the channel bottom to 10 feet above the waterline. (C) Overall the concrete of the piers was in good condition and only exhibited random vertical cracks.(D) Vertical bank erosion was observed along the river bank, consisting of up to 15 feet high vertical cut embankments. (E) Timber debris, 3 feet diameter and smaller was observed along the east face of Pier 3 from the channel bottom to 10 foot above the waterline and 30 feet upstream and downstream of the fascias.
INSPECTION FINDINGS
Page 3 of 17
WATERLINE DATUM4.
13.1
Water Level Reference:
76.1Waterline Elevation (feet):
Top of pier cap at downstream nose of Pier 3.
Substructure(s) Inspected:
SUBSTRUCTURE INSPECTION DATA3.
Piers 2, 3, and 4
Maximum Water Depth at Substructure(s) Inspected (feet):
Each pier consists of a rectangular reinforced concrete shaft supporting a concrete hammerhead cap. The pier shafts have tapered ends with blunt noses. The piers have rectangular footings founded on caissons.
General Shape:
Code:Item 61: Channel and Channel Protection:
7
6
Code:Item 62: Culvert:
5.
The waterline was located 23.9 ft below the reference. Description:
NBIS CODING INFORMATION
Code:Item 60: Substructure:
(Minnesota specific codes are used for 92B and 113)
1
District:
CSAH 90Facility Carried:
District 7
Bridge Description:
007 - Blue EarthCounty:
BRIDGE DATA1.
UNDERWATER INSPECTION
Bridge #:
BLUE EARTH RIVERFeature Intersected:
07569
Weather Conditions:
12/02/2016Date of Underwater Inspection:
Cloudy, 30F
Waterway Velocity (ft/sec):
1Underwater Visibility (feet):
INSPECTION DATA2.
The superstructure consists of a five spans of multiple prestressed concrete beams supporting a reinforced concrete deck. The superstructure is supported by two reinforced concrete abutments and four reinforced concrete piers. The abutment footings are founded on steel H-piles, while the pier footings are founded on 48 inch diameter caissons. The piers are numbered 1 through 4 starting from the west end of the bridge.
Professional Engineer/Team Leader:
Marc SternInspection Diver:
Roy Forsyth
Page 4 of 17
885 1EAScour 0
STRUCTURAL ELEMENT CONDITION RATING6.
No (Mark your selection with an X)
Item 113: Scour Critical Bridge: Code:
Y 48 12/2016Item 92B: Underwater Inspection: Code:
Yes X
I
Bridge is scour critical because abutment or pier foundation is rated as unstable due to observed scour at bridge site.
CS4CS3CS1 CS2
LF 162162210 Concrete pier wall
Conditions
Quantity UnitElement DescriptionELEM #
Page 5 of 17
The routine underwater inspection of Bridge 07569 (CSAH 90 over Blue Earth River) was completed on December 2, 2016. The underwater inspection was conducted from shore. The inspection was conducted by a team consisting of a PE-Diver with a valid MnDOT Team leader certification, a backup diver and a dive tender. The inspection utilized commercial dive equipment and techniques (SSA and/or SCUBA) in accordance with OSHA regulations. Profiles were taken along the upstream and downstream faces of the bridge and around the periphery of substructure units to determine the presence, location and area of scour.The bridge elements inspected consisted of 3 concrete pier walls. According to the bridge inventory or design drawings, Piers 2through 4 were founded on piles. Inspection procedures followed FHWA guidance and the MnDOT Bridge and Structure Inspection Program Manual with channel bottom probing to search for bottom of foundations. The routine underwater inspection frequency is recommended to remain at 60 months based on those findings and risk factors. Also, inspection procedures should continue to follow the above approach and standard guidance with 100% Level I and 10% Level II intensity efforts.
INSPECTION PROCEDURES
UNDERWATER INSPECTION
Page 6 of 17
Spec. Feat.Pier Foundation (Material/Type)
1 - CONCCantilever ID
+ W A T E R W A Y +Number of Spans Historic Status
3 - FTG PILE
Underwater 60Culvert Type 3 - FTG PILE
Pinned Asbly.
12/02/2016
Barrel Length
706.7 ft. Navigation Control
Waterway Opening (sf.) 9144Structure Length
ft. Year Painted
0 - No nav. control on waterwayDeck Width (Out-to-Out) 65.3
+ P A I N T +
APPR: 0 TOTAL:5 - Not eligible
MAIN: 5
Main Span Length 140.0 ft.Drainage Area (sq. mi.) 3553.0
B R I D G E D A T A +Main Span Detail
1 - MEETS STANDARDS+ M I S C.
Appr. Span Type Structure Flared
GR Termini 1 - MEETS STANDARDS
Appr. Guardrail
Main Span Type 5 - Prestress or Precast Median Width On Bridge
ft. Bridge Railing 1 - MEETS STANDARDS
1 - MEETS STANDARDS
Main Span Design 01 - Beam Span
ft. GR Transition
Skew 30 LEFT
Y/N Freq Date
Abutment Foundation (Material/Type)
1 - CONC Frac. Critical
D E P T H I N S P. +Appr. Span Design
1 - Flared+ I N
Appr. Span Detail Field Conn. ID
Parallel Structure N - No parallel structure
Pier Protection
0 - Not Required
Rating Date 10/14/201639407 sq. ft. Traffic
ft. 50B. Rt 0.00Sidewalk Width 50A. Lt 10.00
Roadway Area (Curb-to-Curb)
Posted Load 0 - Not Required
PostingStructure Area (Out-to-Out) 49678 sq. ft.
DBL:VEH: SEMI:
Rt 01 ARail Type Lt 01 C 1 - No Restriction
1 - No Restriction
B 1 - No Restriction
N - Not Applicable Overweight Permit CodesCurb Height Lt
ft. Horizontal 0 - Not Required
0.00 ft. Vertical0.00 ft. Rt
Wear Surf Install Year 1995
sq. ft. Nav. Vert. Lift Bridge Clear. (ft.)
I - LOW RISK Year 1996Primer Type MN Scour Code
Painted Area
Unsound Paint % Nav. Clr. (ft.)
1 - Not required
Deck Material 1 - Concrete Cast-in-Place 0.0Wear Surf Type 4 - Low Slump Concrete
Vert. 0.0 Horiz.
S I G N S +Operating Rating 2 - HS TRUCK
1 - Epoxy Coated Reinforcing + B R I D G E
Inventory Rating 2 - HS TRUCK 20.80
53.30Deck Rebars Install Year 1995
Deck Rebars
Finish TypeWear Course/Fill Depth 0.17 ft.
0 - None
Design Load 9 - HS 25 (OR GREATER)
+ C A P A C I T Y R A T I N G S +Deck Membrane
44 ° 7
Inspector Name Forsyth, Roy
Latitude Control Section (TH Only) Status' 55.96 ''
2 - 2-way traffic
Routine Inspection Frequency 24
Sect., Twp., Range
2.2 MI SE OF JCT TH 169 Level of Service 1 - MAINLINE
- 27W Roadway Type26 - 108N
Detour Length 4.0 mi.R A T I N G S +
Custodian 02 - County Highway Agency
Owner 02 - County Highway AgencyDeck 7 Unsound
Deck %
C O N D I T I O N° 2 '
A - Open
Longitude 94 002+00.200 + N B I 45.12 '' Reference Point
170 Crew
+ I N S P E C T I O N +
Agency Br. No. 47
District 07
Bridge Match ID (TIS) 0 Userkey
CSAH 90 over BLUE EARTH RIVER
Minnesota Structure Inventory Report
Bridge ID: 07569
+ G E N E R A L + + R O A D W A Y +
Date: 01/16/2017
Sufficiency Rating 99.6Roadway Name or Description
90
City
Routine Inspection Date 10/24/2014
Desc. Loc.
Township 07021 - SOUTH BEND CSAH 90
Number
NRoadway O/U Key Route On StructureMaint. Area Structurally Deficient
NRoute Sys 04 - CSAHCounty 007 - Blue Earth Functionally Obsolete
Lanes
Waterway Adequacy 8Max. Vert. Clear.
ft.Legislative District 24Bft.Potential ABC 2 - N/A ft.
ft.On - Off System Roadway Width 50.80 ft.
Vertical Clearance ft.1 - ON
Underclearances N
Service On 5 - Highway-pedestrian Appr. Surface Width+ S A F E T Y F E A T U R E S +
5 - Waterway Bridge Roadway Width 50.8
44.0 ft.
Service Under
ft.
50.7 ft. Approach Alignment 8Horizontal Clear.
ft.
ft.+ S T R U C T U R E + Lateral Clearance
HCADT ADTT7
Year Built 1995
MN Year Reconstructed Functional Class
%Channel 6
Substructure
0Superstructure 8
ON 2 UNDER
1283 YEAR 2008BMU Agreement ADT
Structure Evaluation 7If Divided
D I M E N S I O N S +Bridge Plan Location 3 - COUNTY
Deck Geometry 9NB-EB SB-WBDate Opened to Traffic
+ R D W Y
FHWA Year Reconstructed
MN Temporary Status
07 - Rural - Major CollectorCulvert N
A P P R A I S A L R A T I N G S ++ N B I
Page 7 of 17
County:
City:
Township:
Township:Section: Range:
Span Type:
NBI Deck: Super: Sub: Chan: Culv:
Appraisal Ratings - Approach: Waterway:
Required Bridge Signs - Load Posting:
Horizntal:
Traffic:
Vertical:
MN Scour Code:
Open, Posted, Closed:
Location:
Route:
Control Section:
Local Agency Bridge Nbr.:
Ref. Pt.:
Maint. Area:
Length:
Deck Width:
Rdwy. Area/ Pct. Unsnd:
Paint Area/ Pct. Unsnd:
Culvert:
Blue Earth
07021 - SOUTH BEND
108N26 27W
5 - Prestressed Concrete 2 -Stringer/Multi-beam or Girder
7 8 7 6 N
8 8
0 - Not Required
0 - Not Required
0 - Not Required
N - Not Applicable
I - LOW RISK
2.2 MI SE OF JCT TH 169
04 - CSAH 90
170
002+00.200
706.7
65.3
39407 sq. ft. / %
sq. ft. / %
N/A
A - Open
ft.
ft.
Postings:List:
MINNESOTA BRIDGE INSPECTION REPORT
01/30/2017
BRIDGE 07569 CSAH 90 OVER BLUE EARTH RIVER
Unofficial Structurally Deficient N
NUnofficial Functionally Obsolete
Unofficial Sufficiency Rating 99.6
ELEMNBR ELEMENT NAME INSP. DATE QUANTITY
QTYCS 1
QTYCS 2
QTYCS 3
QTYCS 4REPORT TYPE
Reinforced Concrete Deck 01/16/2017 49678 SF 49678 0 0 012 Underwater
49678 SF 49678 0 0 0Migrated Values
Notes: 2012 - No leaching showing on underneath showing.2014 - Minor leaching showing up.
510 - Wearing Surfaces 39407 SF 38619 0 788 0
Notes: Low Slump Overlay with Epoxy Rebar Notes: 2010, 2014 - Several small spalls in both lanes.
Underwater 01/16/2017
39407 SF 38619 0 788 0Migrated Values
Prestressed Concrete OpenGirder/Beam
01/16/2017 6706 LF 6706 0 0 0109 Underwater
6706 LF 6706 0 0 0Migrated Values
Reinforced Concrete Pier Wall 01/16/2017 217 LF 201 16 0 0210 Underwater
217 LF 201 16 0 0Migrated Values
Notes: 2012, 2014 - Minor cracking in all four pier walls.2015 - Minor crack from stem thru cap. Observed with MN/DOT snooper truck.
Reinforced Concrete Abutment 01/16/2017 201 LF 181 20 0 0215 Underwater
201 LF 181 20 0 0Migrated Values
Notes: [2016] Migrator added 40 LF to abutment quantity to account for wingwalls (CS1:30 CS2:10 CS3:0 CS4:0).2012 - Minor cracking in both abutments.2014 - East abutment covered with graffiti.
Wingwall notes: 2012 - SE wing wall has minor crack.
Reinforced Concrete Pier Cap 01/16/2017 315 LF 315 0 0 0234 Underwater
315 LF 315 0 0 0Migrated Values
Strip Seal Expansion Joint 01/16/2017 161 LF 0 161 0 0300 Underwater
161 LF 0 161 0 0Migrated Values
Notes: 2002 - Expansion joints are full of compacted sand and road debris. Two expansion cover plates are broken out from the concrete rail.2004 - Both joints are open 4"+ @ 60 degrees F.2006 - East joint is open 4.5 inches & west joint is open 4 inches.2009 - Some plow finger skid plates are missing on both ends.2010 - Two expansion cover plates are broken out from the concrete rail, need to clean expansion joints.2014 - At 65 Degrees, east joint expanded to full width. Both joint full of debris.
Page 8 of 17
Elastomeric Bearing 01/16/2017 96 EA 96 0 0 0310 Underwater
96 EA 96 0 0 0Migrated Values
Reinforced Concrete Approach Slab 01/16/2017 1760 SF 0 1760 0 0321 Underwater
1760 SF 0 1760 0 0Migrated Values
Notes: [2016] Migrator assumed an approach slab length of 20FT and used the inventory quantity of 44FT for the width.2012, 2014 - Both approach slabs have cracks.
Metal Bridge Railing 01/16/2017 5492 LF 4205 1287 0 0330 Underwater
5492 LF 4205 1287 0 0Migrated Values
Notes: 2010 - Paint is flaking off and many rub spots to bare metal.2012 - Same.
[2016] Migrator assumed concrete/metal combination type rail.2010 - paint is starting to flake off.2012 - Both concrete section have minor cracking. EBL metal railing has major scraps from snow plows.
515 - Steel Protective Coating 999 SF 999 0 0 0
Notes: [2016] Migrator assumed CS1 and a quantity of 999 SF.
Underwater 01/16/2017
999 SF 999 0 0 0Migrated Values
Reinforced Concrete Bridge Railing 01/16/2017 4747 LF 3560 1187 0 0331 Underwater
4747 LF 3560 1187 0 0Migrated Values
Notes: [2016] Migrator assumed concrete/metal combination type rail.2010 - paint is starting to flake off.2012 - Both concrete section have minor cracking. EBL metal railing has major scraps from snow plows.
Critical Deficiencies or Safety Hazards 01/16/2017 1 EA 1 0 0 0800 Underwater
1 EA 1 0 0 0Migrated Values
Notes: No critical findings observed during 2014 inspection.
Concrete Decks - Cracking & Sealing 01/16/2017 0 LF 0 0 0 0810 Underwater
0 LF 0 0 0 0Migrated Values
Notes: 2012 - Deck has moderate cracks at minor spacing.
Plow Fingers 01/16/2017 1 EA 0 1 0 0815 Underwater
1 EA 0 1 0 0Migrated Values
Notes: 2004 - Two plowstraps missing @ east end.2006 - Three plowstraps missing at east end & 1 missing at west end.2010 - same. 2012 - Plow straps repaired.
Secondary Members (Superstructure) 01/16/2017 1 EA 1 0 0 0855 Underwater
1 EA 1 0 0 0Migrated Values
Concrete Shear Cracking 01/16/2017 1 EA 1 0 0 0883 Underwater
1 EA 1 0 0 0Migrated Values
Notes: No cracks observed.
Scour 01/16/2017 1 EA 1 0 0 0885 Underwater
ELEMNBR ELEMENT NAME INSP. DATE QUANTITY
QTYCS 1
QTYCS 2
QTYCS 3
QTYCS 4
BRIDGE 07569 CSAH 90 OVER BLUE EARTH RIVER
REPORT TYPE
Page 9 of 17
Other Bridge Signing 01/16/2017 1 EA 1 0 0 0891 Underwater
1 EA 1 0 0 0Migrated Values
Notes: 2012 - SE bridge marker is bent and twisted.2014 - All signs in good shape.
Slopes & Slope Protection 01/16/2017 1 EA 0 1 0 0892 Underwater
1 EA 0 1 0 0Migrated Values
Notes: 2002 - Trees should be cut from slopes and below bridge.2004 - Trees have been cut. Small trees growing in riprap.2006 - Trees ok.2009 - Trees are a continual problem.2012 - Trees at abutments need to be removed.2012 - Revised as per Collins Engineers, Inc. Report dated 09/13/2012.2014 - Trees around abutments cleared off.
Guardrail 01/16/2017 1 EA 1 0 0 0893 Underwater
1 EA 1 0 0 0Migrated Values
Notes: 2009 - SW crash cushion is damaged.2012 - Guard rail damage repaired.
Deck & Approach Drainage 01/16/2017 1 EA 1 0 0 0894 Underwater
1 EA 1 0 0 0Migrated Values
Notes: 2010 - small washout at NE end of walkway.2012 - Same.
Sidewalk, Curb, & Median 01/16/2017 1 EA 1 0 0 0895 Underwater
1 EA 1 0 0 0Migrated Values
Notes: 2012, 2014 - Sidewalk has minor cracking.
Miscellaneous Items 01/16/2017 1 EA 1 0 0 0899 Underwater
1 EA 1 0 0 0Migrated Values
Notes: 2012 - Telephone conduit attached under bridge.
Protected Species 01/16/2017 1 EA 1 0 0 0900 Underwater
1 EA 1 0 0 0Migrated Values
Notes: Use this element to track the presence of protected species living on this structure.
General Notes: 2000 -Graffati on river side of Pier No. 1 and land side of Pier No. 4.2002 - Graffati has been covered over by painting.2006 - Erosion from edge of bituminous trail at NW corner of bridge.2007 - On November 19, 2007, Collins Engineers, Inc. completed an underwater inspection. NBI code for Item 60 changed to7.2008 - Snooper inspected 10/14/2008: underside of deck, concrete girders and diaphragm connections, bearing assemblieson piers. Need to check depth of scour hole at pier 1. 10/23/2008 39' from top of sidewalk to lowest point in scour hole atpier 1, plan shows 51', should not be a problem at this time.2009 - Walked the deck and below at both ends, no structural problems this date.2012, 2014 - Graffiti on end piers and abutments.2012 - Underwater inspection by Collins Engineers, Inc. 09/13/2012. See report.2015 - MN/DOT snooper truck on site 09-10-2015
58. Deck NBI:
36A. Brdg Railings NBI:
36B. Transitions NBI:
36C. Appr Guardrail NBI:
36D. Appr GuardrailTerminal NBI:
59. Superstructure NBI:
60. Substructure NBI:
ELEMNBR ELEMENT NAME INSP. DATE QUANTITY
QTYCS 1
QTYCS 2
QTYCS 3
QTYCS 4
BRIDGE 07569 CSAH 90 OVER BLUE EARTH RIVER
REPORT TYPE
Page 10 of 17
ELEMNBR ELEMENT NAME INSP. DATE QUANTITY
QTYCS 1
QTYCS 2
QTYCS 3
QTYCS 4
BRIDGE 07569 CSAH 90 OVER BLUE EARTH RIVER
REPORT TYPE
Inspector's Signature Reviewer's Signature
60. Substructure NBI:
61. Channel NBI:
62. Culvert NBI:
71. Waterway Adeq NBI:
72. Appr RoadwayAlignment NBI:
Page 11 of 17
Photo 1 - Overall looking south.
Photo 2 - Pier 1 looking east.
Pictures
Page 12 of 17
Pictures
Photo 3 - Pier 2 looking east.
Photo 4 - Pier 3 looking west.
Page 13 of 17
Pictures
Photo 5 - Pier 4 looking west.
Photo 6 - East Abutment looking east.
Page 14 of 17
Pictures
Photo 7 - Typical concrete at waterline of Pier 1 looking east.
Page 15 of 17
Page 16 of 17
Page 17 of 17