Upload
tsiva947
View
193
Download
3
Embed Size (px)
Citation preview
BRIDGE FOUNDATION DESIGNSiva
TheivendrampillaiSivakumar
Principal Engineer (Geotechnical)
Geotechnical Branch
2
OverviewBrief Discussion on:
• Foundation Type
• Foundation Design
• Pile Load Testing
• Approach Embankment to Bridge
3
TMR-Specifications
• Cast-in-Place Piles – MRTS63 and 63A• Driven PSC Piles – MRTS65• Driven Steel Piles –MRTS66• Dynamic Testing of piles—MRTS68
• Project Specific- Geotechnical Design Standard – Minimum Requirements
4
Basic Foundation Types
• Shallow FoundationsBearing strata at shallow depths
• Deep Foundation (Piles)Deeper bearing strata
Driven PilesCast-in-Place Piles
5
Basic Foundation Types
SHALLOW FOUNDATIONS
6
7
When can we use Shallow Foundations?
When Surface strata are:
• Strong ( Adequate bearing capacity and no settlement issues).
• Not vulnerable to Scour
• Non-expansive
• Low ground water level
8
Shallow Foundation Design – Things to Consider
• Concentric / Eccentric Loading
• Overturning moment
• Sliding
• Global Stability ( esp. footing on / adjacent to
slope)
9
Basic Foundation Types
DEEP FOUNDATIONS - PILES
10
When do we need piles?• When surface strata are
WeakCompressibleErodableExpansive
• To resist flood, earth pressuresLateral loadsUplift loadsOverturning loads
11
Pile Use: Transfer load through surface strata which may be weak, compressible, expansive etc.
12
Pile Use: For resisting lateral loading
13
Pile Use: For resisting uplift
14
Pile Use: Support against scour or lateral loading due to excavation
15
Pile Use – Further example of lateral support for deep excavation induced lateral loading
16
Deep Foundations - Pile Types
• Driven pilesDisplacement piles
Soil is ‘displaced’ within the adjoining soil mass (displaced volume ≈ pile volume)
• Cast-in-place piles or Bored pilesNon-Displacement pilesSoil is removedThe excavation may or may not be supported
17
Driven Piles - Types and basic requirement in design
• TypesOctagonal Prestressed Concrete(PSC)Reinforced Concrete (RC)Steel “H Pile”Timber Piles
• Limitations on maximum length
18
DRIVEN PILES
PSC Piles in use at Wetheron Creek Bridgesite
19
Pile Driving Frame
20
SITE INVESTIGATION FOR DRIVEN PILES
1. Soil strength and stiffness
2. Soil chemical analysis ⇒corrosion/aggressiveness
3. Possible obstructions to installation
4. Potential for damage to adjoining structure due to “ground heave”
5. VibrationsVibrations
21
Driven Piles• Will refuse in SPT N>50 material• Loads: e.g.,550mm PSC working 1500kN• Settlement: ~ 10 mm• Vulnerable to:
Lateral movement / Negative skin frictionExcess vertical settlement
• Drive after construction of approach embankments
22
Example of NegativeSkin friction
23
Bored or Cast-in-place Piles
• TypesShort bored piersCylinders on rockCylinders socketed into rock**
Belled sockets
• Bored pilesCould be up to 4 x cost of driven pile
Bedrock
24
Bored Piles - Construction
• Bored piles are cast in place cylindrical piles
• Excavated byAugers
Buckets
Large drill bit (for hard rock)
Chisel grab and casing oscillator for boulderyground, etc.
25
Bored Pile Excavation- Augering
26
Bored Pile Excavation - Bucket
Cleaning Bucket
Excavation Bucket
Drilling Rig
Rock Sockets
Bored Piles – Cylinders Socketed into rock
28
Rock Sockets• High compression loads• Greater resistance to lateral movement• Socket length 2 to 5 x diameter• Diameter from 900mm to 1800mm• High strength rock
Point Load (Is50 > 1 MPa)Rock anchors preferred to resist large uplift loads
29
Rock Sockets• May need casing in overburden soils and
XW rock (SPT N<50)• Sealing/control of groundwater important• Capacity to take heavy loads dependent
on extremely clean socket bases –inspection important (WH&S)
• More expensive - so fewer, larger piles may be more economical
30
Loads on Bridge Foundations
Structural Engineer to advise, consists of but not limited to
• Vertical Compressive (Dead + imposed) loads
Imposed Loads+ ½ Dead Load – highway bridges+ 2/3 Dead Load – railway bridges
• Vertical Upliftflood loads in transverse direction
31
Loads on Bridge Foundations
• Horizontal Loadsbraking force of vehicle in longitudinal direction
flood loads in transverse direction
Earthquake
• Horizontal Loads create Bending Moments
32
Selection of Foundation Type
What influences the decision for driven or bored piles?The following factors will influence the choice of foundation type:
LoadsEnvironmentLogistics andGeology
33
Selection of Foundation Type: Loads
• Structural LoadsHeavy compressive loads from large spans
• Hydraulic IssuesLateral and uplift loads from flood loading
Scour in loose sands and silts
34
Selection of Foundation Type: Environment
• Vibration proximity to people vulnerable structuresdamage to services
• Aggressiveness due to groundwater • Obstructions
overhead power lines / headroom
35
Selection of Foundation Type: Logistics
• Transporting fresh concrete in western Queensland
Distance and temperature
• Availability/Transporting PSC pilesMax length around 25 – 27m
• Quality of access roads
• Accessibility at foundation locationsCrane pads, piling rig pads
36
Selection of Foundation Type: Geology
• Depth to competent strata• Obstructions to pile driving
Coffee rock (Indurated Sand)
• Steeply dipping bearing strataBasalt flows
• Interbedded rock types with different properties
37
Selection of Foundation Type: Geology
• Compressible deposits• Defects with soft infills• High head of groundwater
Sealing issuesHole stabilityConcreting
• Rock excavatability
38
Coffee Rock (Indurated Sand)
39
Steeply Dipping Bearing Strata
40
PILE DESIGN
THEORY EMPIRICISM EXPERIENCE FIELD LOADING TESTS
Engineering GeologySoil Mechanics
Rock MechanicsStructural Mechanics
To account for various methods of
pile installation
Regional (geology + local construction
practices)
StaticDynamic
Design Stage
Construction Stage
Pile Design - Approaches
41
PILES PILES -- designdesign
The following aspects should be considered in
design:
1. Load carrying capacity (Geotechnical Engineer)
- strength and stiffness ⇒ “serviceability”
2. Pile material strength (Structural Engineer)
3. Pile material durability (Structural Engineer)
42
Pile Design - Geotechnical
• Foundations:Load capacitySettlementsLateral FixityUplift resistance
• Scour IssuesLand/water structures
• ApproachesStabilitySettlements
• InteractionAbutmentsWidening/ duplication
The following DESIGN ELEMENTS should be accountedfor in design:
43
Pile Capacity
• Q = Pile Capacity
• Qend = End Resistance
• Qshaft = Shaft Resistance
• Q = Qend + Qshaft
Q
Qshaft
Qend
44
End versus Shaft Bearing Piles• Pile in Clay • Pile in
SandEnd Bearing Pile
Qshaft
Qend = 5-10% Qshaft
Qshaft
Qend
Qshaft
Qend
45
Low load Ultimate load
fs = τ max
fs = τ max
for the full
lengthfs << τ max
Base resistance, fb, mobilized
Driven Pile Capacity
47
Design of PilesTraditional ApproachUltimate Geotechnical Capacity =
Ult. Skin Friction + Ult. End Resistance
Allowable Geotechnical Capacity = Ult. Skin Friction/1.5 + Ult. End Resistance/3.0
OR
Allowable Geotechnical Capacity = Ultimate Geotechnical Capacity/2.5
The allowable geotechnical capacity should be compared with design load (unfactored) from the structure.
48
Design of PilesLimit State Design (e.g AS2159)Rug (Ultimate Geotechnical Capacity) =
Ult. Skin Friction + Ult. End Resistance
Rg* (Design Geotechnical Capacity) = Ф x Rug
Rg* >= N* or S* (Design Action Effect or Ultimate Design Load)
Rg* should be compared with ultimate design load (not driving capacity or structural capacity)
Load and Settlement- (idealized)
(600 mm, 10 m long bored pile in stiff clay)
PILE DESIGN – WIDELY ACCEPTED BEHAVIOUR
Pile
NONDISPLACEMENTDrilled shafts
Micropiles in soils
CFA(Auger cast)
PARTIAL DISPLACEMENTH-Piles
Open-ended pipe piles(in some soils)
FULL DISPLACEMENTPrecast concrete
Closed-ended pipe pilesOpen-ended pipe piles
(in some soils)Franki
Spectrum of soil displacement caused by pile installation and Its relationship to
bearing capacity.
Increasing unit base or shaft resistance
51
2nd Session
• Pile Load Testing• Site Investigation – Need to get it right• Design Elements – Stability and Settlement at
Bridge Approaches• Selection of Design Parameters• Design Charts – for estimating shaft resistance
and settlement of piles
52
Pile Load Test
• Why Pile Load TestDerivation of design parameter
Verification of design load or pile carrying capacity
• MRTS63 Requires that at least 10% of piles at a site to be tested
• Common methods of pile load testStatic Load Test (Kentledge or Reaction Piles)
Dynamic Test (PDA with CAPWAP)
53
Static Load Test
Reaction Piles
Kentledge
54
Kentledge Set up for Static Pile Load Test
55
Static Load Test – Further example of Kentledge
56
Dynamic Load Test – Pile Driving Analyser (PDA)
• The PDA system consists ofTwo strain transducers (to measure strain/force)
Two accelerometers (to measure velocity) Attached to opposite sides of the pile (near the top of the pile).
• The measured force and velocity at the pile top provide necessary information to estimate soil resistance and its distribution.
57
PDA – Set Up
58
Typical arrangement of PDA - Schematic
59
Force & velocity wave traces recorded during initial driving and restriking
Load-settlement Behaviour
Test Pile: Predicted versus Measured Performance
62
Site Investigation - Need to get it right
• What can go wrong?• How can we manage undue contractual
claims as well as save construction time• Limited investigation can be disastrous as
this could lead to undue claims• Example – Six Mile Creek, Central Qld
63
Six Mile Creek, Central Qld
64
Six Mile Creek – Footing Plan Area
65
Six Mile Creek: Additional Investigation-DCP
66
Six Mile Creek - Footing Excavation
67
Six Mile Creek: Footing re-design
68
Design Element – Stability and Settlement at Bridge Approaches
• Stability• Settlement
69
Different Origins that could Lead to Formation of Bump at the Approaches to a Bridge
70
Abutment Stability and Settlement
• Compression of Natural Soil Due to Embankment Load
• What are compressible Soils?Soft clays (SPT N = HW to 6 or Su <25kPa)
• Where can we find soft clays (compressible soils)?
Old River ChannelsPaleo-channels (very dangerous)
Paleo-channels
• GUP, near Schultz canal
• From old topography maps and airphotos
72
• Paleochannels
Old buried channels from previous creek routes
Deposits of softer younger alluvium
Can be difficult to identify
Create a sudden change in ground conditions
Abutment Stability and Settlement
Paleo-channels – Long Section
10 – 15m soft clay
74
Abutment Stability and Settlement
• Risks associated with soft claysEmbankment stability and settlementStructures (damage, bumps)Pavements Deterioration - unevennessRetaining wall foundationsConstruction delays Construction access
75
Abutment Stability: Soft Clay Issue Slip Failure - Schematic
76
Abutment Stability and Settlement: Soft Clay Issue
77
Abutment Stability and Settlement: Soft Clay Issue, Bump at Bridge Approach
Vertical Settlement
78
Abutment Stability and Settlement: Soft Clay Issue, Differential Settlement
79
Abutment Stability and Settlement: Typical Exampleson Projects in South East Queensland
• Gateway Arterial @ Bald Hills Creek• East – West Arterial @ Pound Drain• Ipswich Motorway – BR340 @
Dinmore
Gateway Arterial – Bald Hills Creek, Stability
Gateway Arterial - Bald Hills Creek
• 3m high embankment
• 100m failure during construction
• Boreholes 150m apart
82
Bald Hills Creek - Mitigation Strategy
• Stability failure reinstated with timber piled raft• Abrupt differential settlement between
embankment sectionsEmbankment on piles didn’t settleEmbankment on natural did (4-5mm /month)
Bald Hills Creek, Settlement
≈ 800 mm by Jul 98
≈ 150 mm predicted in 1986 by consultant
East – West Arterial @ Pound Drain
85
East – West Arterial @ Pound Drain
• Damaged by lateral loading on piles from the approach embankment
• Differential settlement alsoLoads on abutment piled foundations
Interaction effects on adjacent structures
Functionality of drainage structures
Problems at relieving slab and pavement
86
Ipswich Motorway Ipswich Motorway -- Bridge Bridge BR340, StabilityBR340, Stability
•• Number of Spans = 3Number of Spans = 3
•• Span Length = 13m, 18m & 13mSpan Length = 13m, 18m & 13m
•• Bridge Bridge SpillthroughSpillthrough Embankment Embankment
9m high with batter Slopes 9m high with batter Slopes 1(H):1(V) 1(H):1(V)
•• Number of Piles at Abutments = 3Number of Piles at Abutments = 3
Spaced at 6.5m Spaced at 6.5m c/cc/c
•• Number of Piles at Piers = 5Number of Piles at Piers = 5
Spaced at 3.3m Spaced at 3.3m c/cc/c
87
Ipswich Motorway - 2009
Approach Approach embankment failed. embankment failed. Cracks in embankmentCracks in embankmentplus Pier piles displaced.plus Pier piles displaced.
88
Risks Associated with Soft Clays – ManagingStability and Settlement
• How can we manage stability and settlement
89
Overview of Management Strategies
Light-weight Fill Stone Columns Embankment on Piles
Vacuum Preload
Partial Replacement
Total Replacement
Temporary Surcharge
Height reduction.Counter Berms
Stage Construction
Vertical Drains
Reinforced Embankment
90
SELECTION OF DESIGN PARAMETERS
• SOILS• ROCKS
91
Soils
SAND
CPT SPT
CLAY
OedometerConsolidation
Stiff Soft
UU CPT CPTu UU
SPT: Standard PenetrometerCPT: Cone PenetrometerCPTu: PiezoconeUU: TriaxialVS: Vane Shear Test
VS
92
Selection of Design Parameters : CPT
CPT
Sands / Stiff Clays
fs qc
Shaftresistance
End bearing resistance
93
Selection of Design Parameters : CPTu
CPTu
Soft Clays
qc u
Su (Undrained Strength for stability)
Cv (Rate of settlement)
Drainage lenses
Fs/qc/u
94
Selection of Design Parameters : Su
Undrained Strength
Soft clayStiff Clay
StabilityShaft Resistance
End Bearing
95
Selection of Design Parameters: Rock
XW/HW
Visual SPT Point Load
MW/SW
Visual USC Point Load
Pressure -meter
96
Selection of Design Parameters: Rock Tests
UCS PressuremeterPoint Load (Is)50
HW/MW/SW/Fr
Settlement of Sockets
Shaft Resistance
End Bearing
CNS
MW/SW/Fr
Shaft Resistance
97
Design Charts (after Poulos)
• Design charts for the estimation of shaft resistance and settlement of pilesDriven PilesBored Piles
98
Shaft Resistance
Settlement (Poulos 1989)
Settlement (Poulos 1989)