Upload
ntlong76
View
219
Download
0
Embed Size (px)
Citation preview
8/13/2019 Boiler System Functional Test
1/8
Boiler SystemFunctional Test FT___
Functional Test
Project ____________________________________
FT- BOILER SYSTEM
HW Boilers B-1 & 2 (condensin! and B-"# $% # Includin 'ssociatedri)ar* HW u)+s 1# 2# "# $% and Secondar* u)+s ,# % .
and T/eir 0ariale S+eed ri3es
14 artici+antsParty Participation
Party filling out this form and witnessing testing ______________________________Dates of tests ______________________Dates of tests ______________________Dates of tests ______________________
24 Test rere5uisitesa. __ The following have been started up and startup reports and prefunctional checklists submitted and
approved ready for functional testing:
__ Boilers __ Heating water piping and valves
__ Heating water pumps __ Variable speed drives
b. __ All control system functions for this and all interlocking systems are programmed and operable per
contract documents including final setpoints and schedules and with debugging loop tuning and sensor anddevice calibrations completed. _________________________________ _________________________
!ontrols !ontractor "ignature or Verbal #ate
c. __ $iping system flushing complete and re%uired report approved.
d. __ &ater treatment system complete and operational.
e. __ Vibration control report approved 'if re%uired(.
f. __ Test and balance 'TAB( complete and approved for the hydronic system.
g. __ All A)* punchlist items for this e%uipment corrected.
h. __ These functional test procedures reviewed and approved by installing contractor.
i. __ "afeties and operating ranges reviewed.
+. __ Test re%uirements and se%uences of operation attached.
k. __ "chedules and setpoints attached.
l. __ "ufficient clearance around e%uipment for servicing.
Notes:
File: ,---/01, !"!" Commissioning Guide Specification --PECI Page1of 0
8/13/2019 Boiler System Functional Test
2/8
Boiler SystemFunctional Test FT___
m. __ Have all energy savings control strategies setpoints and schedules been incorporated that this boiler and
control system are capable of2 3f not list recommendations below.
n. __ BAS Program Review. 4eview the BA" software control program's( for this e%uipment. $arameters
setpoints and logic se%uences appear to follow the specified written se%uences.
o. __ Packaged Control Program Review. 4eview the packaged control program's( for this e%uipment.$arameters setpoints and logic se%uences appear to follow the specified written se%uences.
p. __ 4ecord made of All Values for !urrent "etpoints '"$t( !ontrol $arameters 5imits #elays 5ockouts
"chedules *tc. !hanged to Accomodate Testing:
ara)eterre-Test
0alues
Returned to re-Test
0alues
Space Temp# Setpts
Time delay $etween stages
Setpoint range for condensing $oilers: %&F'(&F
Differential pressure setpoint: Basement:Penthouse:
Supply temp# reset schedule: )S*T +ST %-F(&F .-F"&F
/hanges for False 0oading:
"4 Sensor 6aliration 6/ec7s4 !heck the sensors listed below for calibration and ade%uate location. This is asampling check of calibrations done during prefunctional checklisting.
Notes:
File: ,---/01, !"!" Commissioning Guide Specification --PECI Page2of 0
8/13/2019 Boiler System Functional Test
3/8
Boiler SystemFunctional Test FT___
63n calibration7 means making a reading with a calibrated test instrument within 1 inches of the site sensor. Verify that the sensor
reading 'via the permanent thermostat gage or building automation system 'BA"(( compared to the test instrument8measured valueis within the tolerances specified in the prefunctional checklist re%uirements '__________________________(. 3f not install offset
in BA" calibrate or replace sensor. 9se the same test instruments as used for the original calibration if possible.
Sensor 1 0ocation 0ocation)2
1st 3age orB*S4alu
e
5nstrument6easured
4alue
Final 3age orB*S
4alue
Pass7!N8
"AT
H&"T 'bldg loop(
H&4T 'bldg loop(
H&B8, ; < B8, B8< B8, B8< B8, B8