29
Design, Fabrication, and Test of a 5-kWh/100-kW Flywheel Energy Storage Utilizing a High-Temperature Superconducting Bearing M. Strasik, P. E. Johnson, A. C. Day, J. Mittleider, M. D. Higgins, J. Edwards, J. R. Schindler, K. E. McCrary, C.R. McIver, D. Carlson, J. F. Gonder, and J. R. Hull November 6, 2007 ISS 2007, Tsukuba Japan This work was partially supported by the U.S. Department of Energy, Offices of Electricity Delivery and Energy Reliability under the Cooperative Agreement DE-FC36-99G010825, Contract W-31-109-Eng-38, and Sandia National Laboratories Energy Storage Program Contract 24412

Boeing Flywheel ISS 2007

Embed Size (px)

DESCRIPTION

Flywheel

Citation preview

Page 1: Boeing Flywheel ISS 2007

Design, Fabrication, and Test of a 5-kWh/100-kW Flywheel Energy Storage

Utilizing a High-Temperature Superconducting Bearing

M. Strasik, P. E. Johnson, A. C. Day, J. Mittleider, M. D. Higgins, J. Edwards, J. R. Schindler, K. E. McCrary, C.R. McIver, D.

Carlson, J. F. Gonder, and J. R. Hull

November 6, 2007ISS 2007, Tsukuba Japan

This work was partially supported by the U.S. Department of Energy, Offices of Electricity Delivery and Energy Reliability under the Cooperative Agreement DE-FC36-99G010825, Contract W-31-109-Eng-38, and Sandia National Laboratories Energy Storage Program Contract 24412

Page 2: Boeing Flywheel ISS 2007

Boeing Technology | Phantom Works Flywheel Energy Storage

Outline

• Flywheel application description• 5 kWh /100 kW FES design and test results• Previous HTS bearing and cryogenic set-up

and results• Direct cooled bearing design and test results• Description of direct cooled test set-up• Summary

Page 3: Boeing Flywheel ISS 2007

Boeing Technology | Phantom Works Flywheel Energy Storage

Lobby

Free Electron Laser Bldg.

Flywheel

Offices

Boeing Flywheel Facility - Seattle

Mt. Rainier

Offices

Page 4: Boeing Flywheel ISS 2007

Boeing Technology | Phantom Works Flywheel Energy Storage

Page 5: Boeing Flywheel ISS 2007

Boeing Technology | Phantom Works Flywheel Energy Storage

Boeing Flywheel Spin Test Facility

Test pit with concrete blocks Flywheel test chamber Control room

Flywheel test facilityBalancing spin system2nd Level test area

Largest Flywheel Spin Test Facility on the West CoastLargest Flywheel Spin Test Facility on the West Coast

Page 6: Boeing Flywheel ISS 2007

Boeing Technology | Phantom Works Flywheel Energy Storage

Flywheel Electricity Systems

Uninterrupted Regulated (Load Leveled) Power Out

High PulsedPower Out

Surges

Outage

Noise

Freq Var

Spikes

Sags

POWER INVERTERAND CONDITIONER

FLYWHEEL MOTORCONTROLLER

POWER TO CUSTOMER

CUSTOMERUTILITYVAULT

POWER FROMUTILITY GRID

FLYWHEELSTORAGE UNIT

¢¢

Page 7: Boeing Flywheel ISS 2007

Boeing Technology | Phantom Works Flywheel Energy Storage

Boeing Flywheel Development History

1994 200420001998 2002 2006 20081996 2010

Design Concept 1 MWh FES for Commonwealth Edison

DOE Phase 1 and 2 Contract ($12M)

3 kW10 kWh

100 kW5 kWh

DOE/Sandia Off-Grid FES Contract($1.5M)

50 kW5 kWh

IR&D Flywheel Demonstrator

3 kW2 kWh

100 kW100 kWh

IR&D High Energy/Power Density Flywheel (Military)

New ProjectProprietary Customer

Page 8: Boeing Flywheel ISS 2007

Boeing Technology | Phantom Works Flywheel Energy Storage

Why Flywheels and Superconducting Bearings?

• Why Pursue Flywheel Energy Storage?

• Non-toxic and low maintenance• Potential for high power density (W/ kg)

and high energy density (W-Hr/ kg)• Fast charge / discharge times possible• Cycle life times of >25 years• Broad operating temperature range

• Why use HTS bearings?• Simple passive system• Very low frictional loss• Very long lifetime• Low cost and

maintenance• Lower tolerance for

balancing of dynamic structures

• High speed capability (> 500,000 RPM)

• Adjustable stiffness and damping

Boeing Superconducting Bearing Offers Many Design

and Operational Benefits Over Conventional Bearing

Systems

Boeing Superconducting Bearing Offers Many Design

and Operational Benefits Over Conventional Bearing

Systems

Page 9: Boeing Flywheel ISS 2007

Boeing Technology | Phantom Works Flywheel Energy Storage

Boeing 100 kW / 5 kWh UPS Flywheel System Design

Lift Bearing

Aluminum Hub

Touchdown Bearing

Stability HTS Bearing

Steel Vacuum Vessel

Energy-AbsorbingContainment Liner

Motor/Generator

Power Electronics

Hex YBCO

HTS Bearing

Bearing Rotor

Touchdown Bearing

Composite Rotor

60 W GM Cryocooler

System tested up to 15,000 RPM

Page 10: Boeing Flywheel ISS 2007

Boeing Technology | Phantom Works Flywheel Energy Storage

Boeing Cryogenic Bearing Enables Low Loss

Boeing-Patented Superconducting Bearing is a Unique Discriminating Technology Enabling Efficient Flywheel Systems

Boeing-Patented Superconducting Bearing is a Unique Discriminating Technology Enabling Efficient Flywheel Systems

Page 11: Boeing Flywheel ISS 2007

Boeing Technology | Phantom Works Flywheel Energy Storage

Superconducting Bearing System

HTS Crystals

HTS Crystals

Stainless Steel Cryostat

HTS Bearing RotorElectromagnetic Models

Structural Bearing Models

10”

Trapped Field Profile

Page 12: Boeing Flywheel ISS 2007

Boeing Technology | Phantom Works Flywheel Energy Storage

Flywheel Rotor Assembly

• The flywheel team has successfully tested a composite flywheel system weighing 360 lbs and supported by HTS bearing up to 15,000 RPM

• Superconducting bearing performance confirmed estimate of < 0.2% per hour

Stability Bearing Magnet Rotor Installed

Motor Rotor Installed

Page 13: Boeing Flywheel ISS 2007

Boeing Technology | Phantom Works Flywheel Energy Storage

Stability Bearing Rotor Installation

Stability Bearing Magnet Rotor Installed

Stability Bearing Magnet Rotor Installed

Composite Retaining Ring for Bearing Magnets

HTS Stainless Cryostat

Page 14: Boeing Flywheel ISS 2007

Boeing Technology | Phantom Works Flywheel Energy Storage

Rotor Installation and Lift Magnet Assembly

Lift PM Magnet

Page 15: Boeing Flywheel ISS 2007

Boeing Technology | Phantom Works Flywheel Energy Storage

Closing Flywheel Assembly

Page 16: Boeing Flywheel ISS 2007

Boeing Technology | Phantom Works Flywheel Energy Storage

100 kW Power Electronics

100 kW system test at Ballard Power

Utility Remote Control Interface

Page 17: Boeing Flywheel ISS 2007

Boeing Technology | Phantom Works Flywheel Energy Storage

Containment Structure for Rotor Drop/Burst - Subscale Test (after)

Top of rotor: small scratches.

Container brackets slightly damaged,can be re-used

Dropped rotor at 41,000 rpm following quill shaft failure

Bottom of rotor: lost < 1”.

Hub broken, some melting

Page 18: Boeing Flywheel ISS 2007

Boeing Technology | Phantom Works Flywheel Energy Storage

After

1 kWh Burst Rotor & Container Before/After

Before

Rotor

Container

ShaftTest Assembly

Successfully Verified Boeing Patented Safety ContainmentSuccessfully Verified Boeing Patented Safety Containment

S-Brackets Flat in Center

Page 19: Boeing Flywheel ISS 2007

Boeing Technology | Phantom Works Flywheel Energy Storage

Results of High Speed Touch Down Event

• Many lessons learned• Conservative safety approach verified – no external damage• Testing confirmed high risk component designs

• Many lessons learned• Conservative safety approach verified – no external damage• Testing confirmed high risk component designs

Test experience resulted in an improved modular re-design

Test experience resulted in an improved modular re-design

Page 20: Boeing Flywheel ISS 2007

Boeing Technology | Phantom Works Flywheel Energy Storage

480 VAC

5 kWh/100 kW UPS Flywheel Technical Issues

480 VAC

600 VDC

Variable Freq VAC

Inverter

MotorController

Flywheel

Motor controller over-current shutdown resolved

Motor controller algorithm

Rotor spun to 15,000 RPM non-contact

Motor stator over-heating during drive

Inverter system tested and ready for integration

Facility prepared for SCE tests

HTS Bearing nominal to 15,000 RPM

Rotor has sub-sync vibration at higher RPM

Page 21: Boeing Flywheel ISS 2007

Boeing Technology | Phantom Works Flywheel Energy Storage

Sub-sync Whirl

Upper w/o sub-sync

Upper with sub-sync

Lower w/o sub-sync

Lower with sub-sync

FFT note sub- sync frequency stays fixed

Dec 7, 2005 Run #5

0

0.5

1

1.5

2

2.5

3

3.5

4

4.5

5

5.5

6

6.5

7

7.5

8

8.5

9

0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75

Time (minutes)

Rel

ativ

e S

ub-S

ync

Am

plitu

de

0

1000

2000

3000

4000

5000

6000

7000

8000

9000

10000

11000

12000

13000

14000

15000

16000

17000

18000

RPM

Sub-syncRPM

Low energy in sub-sync, but do not want to contact excursion surface

Page 22: Boeing Flywheel ISS 2007

Boeing Technology | Phantom Works Flywheel Energy Storage

Proposed System Architecture for Deployment of a 50kW / 5kWh Flywheel Energy Storage System

Benefits of Using FESS Instead of Idling 2nd Generator on Standby• Reduce Generator Maintenance by 50% (estimate)• Reduce Fuel Costs by $80k/yr (estimate)• Lower Pollution

50 kWWind

Turbine

50 kWWind

Turbine

100 kWDieselGenset

50 kWDieselGenset

50 kW / 5 kWhFlywheel

FlywheelPower

Electronics

IntegratedHybridPowerControlSystem

Off GridVillage

Flywheel Energy Storage System would supply powerduring short peak demand periods

Page 23: Boeing Flywheel ISS 2007

Boeing Technology | Phantom Works Flywheel Energy Storage

Key Issues for HTS Bearing Design

• Overall efficiency needs to be >95% in operating range• Low loss superconducting bearing• No criticals in operating range

• System needs to be stiff enough to follow disturbances, yet not so stiff critical frequencies are produced in the operating range

• Interactions between rotating portions (hub, spokes, & rotor)• Bearing stiffness• M/G stiffness• HTS damping – Jc and temperature dependent• Cooling type – parasitic losses, temperature• HTS samples size and superconducting properties

Page 24: Boeing Flywheel ISS 2007

Boeing Technology | Phantom Works Flywheel Energy Storage

Previous DOE/Boeing Flywheel Terrestrial Cryogenics

Return LN2 & N2 (Two phase flow)

LN2

Cryostat (HTS)

Cold Head (to re-condense N2 gas for closed loop LN2 Operation) & ~ Liter Size LN2 Reservoir

Use of a Thermosiphon eliminated a cryogenic pump requirement

HTS Stability Bearing Cryostat Installed in DOE 5 kWh Flywheel

HTS Stability Bearing Cryostat Installed in DOE 10 kWh Flywheel Input LN2 (gravity fed)

Page 25: Boeing Flywheel ISS 2007

Boeing Technology | Phantom Works Flywheel Energy Storage

Direct Cooled HTS Bearing

Page 26: Boeing Flywheel ISS 2007

Boeing Technology | Phantom Works Flywheel Energy Storage

Sandia 50 kW / 5kWh Flywheel Energy Storage System 2007 Direct Cooled Bearing Tests

HTS Bearing Stator

Hex YBCOHTS Bearing Rotor

Page 27: Boeing Flywheel ISS 2007

Boeing Technology | Phantom Works Flywheel Energy Storage

G-10 Bearing Support

Page 28: Boeing Flywheel ISS 2007

Boeing Technology | Phantom Works Flywheel Energy Storage

Experimental Spin Down Results from Direct Cooled HTS Bearing

y = 0.000356x + 5.644164

0

2

4

6

8

10

12

0 2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000Rotational Rate (rpm)

Rot

atio

nal L

oss

(rpm

/min

)

Below Resonance

Above Resonance

Linear (Above Resonance)

T = 50K, Gap = 2.1 mm

Total Loss• 3.3 W at 2.1 mm gap• 1.6W at 3.9 mm gap

Page 29: Boeing Flywheel ISS 2007

Boeing Technology | Phantom Works Flywheel Energy Storage

Boeing Flywheel Project Summary

• Program goal is to design, develop, and demonstrate a 100 kW UPS flywheel electricity system

• Flywheel system spin tested up to 15,000 RPM in a sensorless, closed loop mode

• Testing identified a manufacturing deficiency in the motor stator – overheats at high speed, limiting maximum power capability

• Successfully spin tested direct cooled HTS bearing up to 14,500 RPM (limited by Eddy current clutch set-up)

• Testing confirmed commercial feasibility of this bearing design – Eddy Current losses are within acceptable limits

• Boeing’s investment in flywheel test facilities increased our spin-test capabilities to one of the highest in the nation