Upload
imran-arshad
View
217
Download
0
Embed Size (px)
Citation preview
7/28/2019 bma9e06
1/28
Chapter 6Principlesof
CorporateFinance
Ninth Edition
Why Net Present Value Leadsto Better Investment Decisions
Than Other Criteria
Slides by
Matthew Will
Copyright 2008 by The McGraw-Hill Companies, Inc. All rights reservedMcGraw Hill/Irwin
7/28/2019 bma9e06
2/28
Copyright 2008 by The McGraw-Hill Companies, Inc. All rights reserved
6- 2
McGraw Hill/Irwin
Topics Covered
A Review of The BasicsNPV and its Competitors
The Payback Period
The Book Rate of ReturnInternal Rate of Return
Capital Rationing
7/28/2019 bma9e06
3/28
Copyright 2008 by The McGraw-Hill Companies, Inc. All rights reserved
6- 3
McGraw Hill/Irwin
NPV and Cash Transfers
Every possible method for evaluating projects
impacts the flow of cash about the company
as follows.
Cash
Investment
opportunity (real
asset)
Firm ShareholderInvestment
opportunities
(financial assets)
Invest Alternative:
pay dividend
to shareholders
Shareholders invest
for themselves
7/28/2019 bma9e06
4/28
Copyright 2008 by The McGraw-Hill Companies, Inc. All rights reserved
6- 4
McGraw Hill/Irwin
CFO Decision Tools
Profitability
Index, 12%
Payback, 57%
IRR, 76%
NPV, 75%
Book rate of
return, 20%
0% 20% 40% 60% 80% 100%
Survey Data on CFO Use of Investment Evaluation Techniques
SOURCE: Graham and Harvey, The Theory and Practice of Finance: Evidence from the Field,
Journal of Financial Economics 61 (2001), pp. 187-243.
7/28/2019 bma9e06
5/28
Copyright 2008 by The McGraw-Hill Companies, Inc. All rights reserved
6- 5
McGraw Hill/Irwin
Book Rate of Return
Book Rate of Return - Average income divided by averagebook value over project life. Also called accounting rateof return.
Managers rarely use this measurement to make decisions.The components reflect tax and accounting figures, notmarket values or cash flows.
assetsbook
incomebookreturnofrateBook
7/28/2019 bma9e06
6/28
Copyright 2008 by The McGraw-Hill Companies, Inc. All rights reserved
6- 6
McGraw Hill/Irwin
Payback
The payback period of a project is the number ofyears it takes before the cumulative forecasted
cash flow equals the initial outlay.
The payback rule says only accept projects that
payback in the desired time frame.
This method is flawed, primarily because itignores later year cash flows and the the present
value of future cash flows.
7/28/2019 bma9e06
7/28Copyright 2008 by The McGraw-Hill Companies, Inc. All rights reserved
6- 7
McGraw Hill/Irwin
Payback
ExampleExamine the three projects and note the mistake
we would make if we insisted on only taking
projects with a payback period of 2 years or less.
050018002000-C
018005002000-B50005005002000-A
10%@NPVPeriod
PaybackCCCCProject 3210
7/28/2019 bma9e06
8/28Copyright 2008 by The McGraw-Hill Companies, Inc. All rights reserved
6- 8
McGraw Hill/Irwin
Payback
ExampleExamine the three projects and note the mistake
we would make if we insisted on only taking
projects with a payback period of 2 years or less.
502050018002000-C
58-2018005002000-B2,624350005005002000-A
10%@NPVPeriod
PaybackCCCCProject 3210
7/28/2019 bma9e06
9/28Copyright 2008 by The McGraw-Hill Companies, Inc. All rights reserved
6- 9
McGraw Hill/Irwin
Internal Rate of Return
ExampleYou can purchase a turbo powered machine tool
gadget for $4,000. The investment will generate
$2,000 and $4,000 in cash flows for two years,
respectively. What is the IRR on this investment?
7/28/2019 bma9e06
10/28Copyright 2008 by The McGraw-Hill Companies, Inc. All rights reserved
6- 10
McGraw Hill/Irwin
Internal Rate of Return
Example
You can purchase a turbo powered machine tool gadget for $4,000.
The investment will generate $2,000 and $4,000 in cash flows for two
years, respectively. What is the IRR on this investment?
0)1(
000,4
)1(
000,2000,4
21
IRRIRRNPV
%08.28IRR
7/28/2019 bma9e06
11/28Copyright 2008 by The McGraw-Hill Companies, Inc. All rights reserved
6- 11
McGraw Hill/Irwin
Internal Rate of Return
-2000
-1500
-1000
-500
0
500
1000
1500
2000
2500
10 20 30 40 50 60 70 80 90 100
Discount rate (%)
NPV(,0
00s)
IRR=28%
7/28/2019 bma9e06
12/28Copyright 2008 by The McGraw-Hill Companies, Inc. All rights reserved
6- 12
McGraw Hill/Irwin
Internal Rate of Return
Pitfall 1 - Lending or Borrowing? With some cash flows (as noted below) the NPV of theproject increases s the discount rate increases.
This is contrary to the normal relationship between NPV and
discount rates.
364%50500,1000,1364%50500,1000,1
%10@Project 10
BA
NPVIRRCC
7/28/2019 bma9e06
13/28Copyright 2008 by The McGraw-Hill Companies, Inc. All rights reserved
6- 13
McGraw Hill/Irwin
Internal Rate of Return
Pitfall 2 - Multiple Rates of Return Certain cash flows can generate NPV=0 at two different discount rates.
The following cash flow generates NPV=$A 3.3 million at both IRR%
of (-44%) and +11.6%.
150120120600
............10910
CCCC
Cash Flows (millions of Australian dollars)
7/28/2019 bma9e06
14/28Copyright 2008 by The McGraw-Hill Companies, Inc. All rights reserved
6- 14
McGraw Hill/Irwin
Internal Rate of Return
Pitfall 2 - Multiple Rates of Return
Certain cash flows can generate NPV=0 at two different discount rates.
The following cash flow generates NPV=$A 3.3 million at both IRR% of
(-44%) and +11.6%.
600NPV
300
0
-30
-600
DiscountRate
IRR=11.6%
IRR=-44%
7/28/2019 bma9e06
15/28Copyright 2008 by The McGraw-Hill Companies, Inc. All rights reserved
6- 15
McGraw Hill/Irwin
Internal Rate of Return
Pitfall 2 - Multiple Rates of Return It is possible to have a zero IRR and a positive NPV
339500,2000,3000,1
%10@Project 210
NoneC
NPVIRRCCC
7/28/2019 bma9e06
16/28Copyright 2008 by The McGraw-Hill Companies, Inc. All rights reserved
6- 16
McGraw Hill/Irwin
Internal Rate of Return
Pitfall 3 - Mutually Exclusive Projects
IRR sometimes ignores the magnitude of the project.
The following two projects illustrate that problem.
818,11%75000,30000,20182,8%100000,20000,10
%10@Project 10
E
D
NPVIRRCC
7/28/2019 bma9e06
17/28Copyright 2008 by The McGraw-Hill Companies, Inc. All rights reserved
6- 17
McGraw Hill/Irwin
Internal Rate of Return
Pitfall 3 - Mutually Exclusive Projects
7/28/2019 bma9e06
18/28Copyright 2008 by The McGraw-Hill Companies, Inc. All rights reserved
6- 18
McGraw Hill/Irwin
Internal Rate of Return
Pitfall 4 - Term Structure AssumptionWe assume that discount rates are stable during
the term of the project.
This assumption implies that all funds are
reinvested at the IRR.This is a false assumption.
7/28/2019 bma9e06
19/28Copyright 2008 by The McGraw-Hill Companies, Inc. All rights reserved
6- 19
McGraw Hill/Irwin
Profitability Index
When resources are limited, the profitability index(PI) provides a tool for selecting among various
project combinations and alternatives
A set of limited resources and projects can yieldvarious combinations.
The highest weighted average PI can indicatewhich projects to select.
6 20
7/28/2019 bma9e06
20/28Copyright 2008 by The McGraw-Hill Companies, Inc. All rights reserved
6- 20
McGraw Hill/Irwin
Profitability Index
1360400
121555
1620552153010
%10@Project 210
D
C
B
A
NPVCCC
Cash Flows ($ millions)
6 21
7/28/2019 bma9e06
21/28Copyright 2008 by The McGraw-Hill Companies, Inc. All rights reserved
6- 21
McGraw Hill/Irwin
Profitability Index
0.4130D
2.4125C
3.2165B
2.12110A
IndexityProfitabil($)NPV($)InvestmentProject
Cash Flows ($ millions)
6 22
7/28/2019 bma9e06
22/28
Copyright 2008 by The McGraw-Hill Companies, Inc. All rights reserved
6- 22
McGraw Hill/Irwin
Profitability Index
Example
We only have $300,000 to invest. Which do we select?
Proj NPV Investment PI
A 230,000 200,000 1.15
B 141,250 125,000 1.13
C 194,250 175,000 1.11
D 162,000 150,000 1.08
Investment
NPVIndexityProfitabil
6 23
7/28/2019 bma9e06
23/28
Copyright 2008 by The McGraw-Hill Companies, Inc. All rights reserved
6- 23
McGraw Hill/Irwin
Profitability Index
Example - continuedProj NPV Investment PI
A 230,000 200,000 1.15
B 141,250 125,000 1.13
C 194,250 175,000 1.11D 162,000 150,000 1.08
Select projects with highest Weighted Avg PI
WAPI (BD) = 1.13(125) + 1.08(150) + 0.0 (25)(300) (300) (300)
= 1.01
6 24
7/28/2019 bma9e06
24/28
Copyright 2008 by The McGraw-Hill Companies, Inc. All rights reserved
6- 24
McGraw Hill/Irwin
Profitability Index
Example - continuedProj NPV Investment PI
A 230,000 200,000 1.15
B 141,250 125,000 1.13
C 194,250 175,000 1.11D 162,000 150,000 1.08
Select projects with highest Weighted Avg PI
WAPI (BD) = 1.01WAPI (A) = 0.77
WAPI (BC) = 1.12
6 25
7/28/2019 bma9e06
25/28
Copyright 2008 by The McGraw-Hill Companies, Inc. All rights reserved
6- 25
McGraw Hill/Irwin
Linear Programming
Maximize Cash flows or NPV
Minimize costs
ExampleMax NPV = 21Xn + 16 Xb + 12 Xc + 13 Xd
subject to
10Xa + 5Xb + 5Xc + 0Xd
7/28/2019 bma9e06
26/28
Copyright 2008 by The McGraw-Hill Companies, Inc. All rights reserved
6- 26
McGraw Hill/Irwin
Vegetron Case
YEAR
1 2 3 4 5
1.Revenue 180 180 180 180 180
2. Operating costs 70 70 70 70 70
3. Depreciation a 80 80 80 80 80
4. Net income 30 30 30 30 30
5. Start-of-year book value 400 320 240 160 80
Book rate of return 7.50% 9.40% 12.50% 18.75% 37.50%(45)
7/28/2019 bma9e06
27/28
6- 28
7/28/2019 bma9e06
28/28
6 28
Web Resources
www.fintools.com
www.loanpricing.com
www.djindexes.com
www.spglobal.com
www.wilshire.com
www.msci.com
www.barra.com
Click to access web sitesInternet connection required
http://www.fintools.com/http://www.loanpricing.com/http://www.djindexes.com/http://www.spglobal.com/http://www.wilshire.com/http://www.msci.com/http://www.barra.com/http://www.barra.com/http://www.msci.com/http://www.wilshire.com/http://www.spglobal.com/http://www.djindexes.com/http://www.loanpricing.com/http://www.fintools.com/