Bituminous road constructions steps.docx

Embed Size (px)

Citation preview

  • 8/12/2019 Bituminous road constructions steps.docx

    1/17

    Bituminous road constructions steps:

    1. Preparation of the existing base course layer

    The existing surface is prepared by removing the pot holes or rust if any. The irregularities are filled in with premix chippings at least a week

    before laying surface course. If the existing pavement is extremely way, a bituminous leveling course of adequate thickness is provided to lay

    a bituminous concrete surface course on a binder course instead of directly laying it on a WBM.

    2. Application of Tuck Coat

    It is desirable to lay AC layer over a bituminous base or binder course. A tack coat of bitumen is applied at 6.0 to 7.5 kg per 10 sq.m area,

    this quantity may be increased to 7.5 to 10 kg for non-bituminous base.

    3. Preparation and placing of Premix

    The premix is prepared in a hot mix plant of a required capacity with the desired quality control. The bitumen may be heated upto 150 177

    deg C and the aggregate temperature should not differ by over 14 deg C from the binder temperature. The hot mixed material is collected

    from the mixture by the transporters, carried to the location is spread by a mechanical paver at a temperature of 121 to 163 deg C. the

    camber and the thickness of the layer are accurately verified. The control of the temperatures during the mixing and the compaction are of

    great significance in the strength of the resulting pavement structure.

    4. Rolling

    A mix after it is placed on the base course is thoroughly compacted by rolling at a speed not more than 5km per hour.

    The initial or break down rolling is done by 8 to 12 tonnes roller and the intermediate rolling is done with a fixed wheel pneumatic roller of 15

    to 30 tonnes having a tyre pressure of 7kg per sq.cm. the wheels of the roller are kept damp with water.

    The number of passes required depends on the thickness of the layer. In warm weather rolling on the next day, helps to increase the density

    if the initial rolling was not adequate. The final rolling or finishing is done by 8 to 10 tonne tandem roller.

  • 8/12/2019 Bituminous road constructions steps.docx

    2/17

    Fig: Tandem Roller

    5. Quality control of bituminous concrete construction

    The routine checks are carried out at site to ensure the quality of the resulting pavement mixture and the pavement surface.

    Periodical checks are made for

    a) Aggregate grading

    b) Grade of bitumen

    c) Temperature of aggregate

    d) Temperature of paving mix during mixing and compaction.

    At least one sample for every 100 tonnes of the mix discharged by the hot mix plant is collected and tested for above requirements.Marshall

    testsare also conducted. For every 100 sq.m of the compacted surface, one test of the field density is conducted to check whether it is atleast

    95% of the density obtained in the laboratory. The variation in the thickness allowed is 6mm per 4.5m length of construction.

    6. Finished surface:

    The AC surface should be checked by a 3.0 m straight edge. The longitudinal undulations should not exceed 8.0 mm and the number of

    undulations higher than 6.0 mm should not exceed 10 in a length of 300 m. The cross-traffic profile should not have undulations exceeding

    4.0mm.

    COMPOSITION AND STRUCTURE OF FLEXIBLE PAVEMENT

    Flexible pavements support loads through bearing rather than flexural action. They comprise several

    layers of carefully selected materials designed to gradually distribute loads from the pavement surface

    to the layers underneath. The design ensures the load transmitted to each successive layer does not

    exceed the layers load-bearing capacity. A typical flexible pavement section is shown in Figure 1. Figure

    2 depicts the distribution of the imposed load to the subgrade. The various

    http://theconstructor.org/practical-guide/marshall-stability-test-flow-test/2640/http://theconstructor.org/practical-guide/marshall-stability-test-flow-test/2640/http://theconstructor.org/practical-guide/marshall-stability-test-flow-test/2640/http://theconstructor.org/practical-guide/marshall-stability-test-flow-test/2640/http://theconstructor.org/practical-guide/marshall-stability-test-flow-test/2640/http://theconstructor.org/practical-guide/marshall-stability-test-flow-test/2640/
  • 8/12/2019 Bituminous road constructions steps.docx

    3/17

    layers composing a flexible pavement and the functions they perform are described below:

    a) Bituminous Surface (Wearing Course). The bituminous surface, or wearing course, is made up of a

    mixture of various selected aggregates bound together with asphalt cement or other bituminous

    binders. This surface prevents the penetration of surface water to the base course; provides a smooth,

    well-bonded surface free from loose particles, which might endanger aircraft or people; resists thestresses caused by aircraft loads; and supplies a skid-resistant surface without causing undue wear on

    tires.

    b) Base Course. The base course serves as the principal structural component of the flexible pavement.

    It distributes the imposed wheel load to the pavement foundation, the subbase, and/or the subgrade.

    The base course must have sufficient quality and thickness to prevent failure in the subgrade and/or

    subbase, withstand the stresses produced in the base itself, resist vertical pressures that tend to

    produce consolidation and result in distortion of the surface course, and resist volume changes caused

    by fluctuations in its moisture content. The materials composing the base course are select hard and

    durable aggregates, which generally fall into two main classes: stabilized and granular. The stabilized

    bases normally consist of crushed or uncrushed aggregate bound with a stabilizer, such as Portland

    cement or bitumen. The quality of the base course is a function of its composition, physical properties,

    and compaction of the material.

    c) Subbase. This layer is used in areas where frost action is severe or the subgrade soil is extremely

    weak. The subbase course functions like the base course. The material requirements for the subbase are

    not as strict as those for the base course since the subbase is subjected to lower load stresses. The

    subbase consists of stabilized or properly compacted granular material.

    d) Frost Protection Layer. Some flexible pavements require a frost protection layer. This layer functions

    the same way in either a flexible or a rigid pavement.

    e) Subgrade. The subgrade is the compacted soil layer that forms the foundation of the pavement

    system. Subgrade soils are subjected to lower stresses than the surface, base, and subbase courses.

    Since load stresses decrease with depth, the controlling subgrade stress usually lies at the top of the

    subgrade. The combined thickness of subbase, base, and wearing surface must be great enough to

    reduce the stresses occurring in the subgrade to values that will not cause excessive distortion or

    displacement of the subgrade soil layer.

  • 8/12/2019 Bituminous road constructions steps.docx

    4/17

    Fig 2: Distribution of load stress in flexible pavement

    Compaction means pressing of soil particles close to each other by mechanical methods. Air during

    compaction is expelled from the void space in the soil mass and therefore the mass density is increased.

    Compaction is done to improve the engineering properties of the soil. Compaction of soil is required for

    the construction of earth dams, canal embankments, highways, runways and many other structures.

    STANDARD PROCTOR TEST

    To assess the amount of compaction and water content required in the field, compaction tests are done

    on the same soil in the laboratory. The test provides a relationship between the water content and the

    dry density. The water content at which the maximum dry density is attained is obtained from the

    relationship provided by the tests. Proctor used a standard mould of 4 inches internal diameter and an

    effective height of 4.6 inches with a capacity of 1/30 cubic foot. The mould had a detachable base plate

    and a removable collar of 2 inches height at its top. The soil is compacted in the mould in 3 layers, eachlayer was given 25 blows of 5.5 pounds rammer filling through a height of 12 inches.

    IS: 2720 part VII recommends essentially the same specification as in Standard Proctor test, some minor

    modifications. The mould recommended is of 100mm diameter, 127.3 mm height and 1000ml capacity.

    The rammer recommended is of 2.6 kg mass with a free drop of 310mm and a face diameter of 50mm.

    The soil is compacted in three layers. The mould is fixed to the detachable base plate. The collar is of

    60mm height.

    Procedure

    About 3kg of air dried soil is taken for the test. It is mixed with 8% water content and filled in the mouldin three layers and giving 25 blows to each layer. The volume of the mould and mass of the compacted

    soil is taken. The bulk density is calculated from the observations. A representative sample is placed in

    the oven for determination of water content. The dry density id found out from the bulk density and

    water content. The same procedure is repeated by increasing the water content.

    Presentation of results

  • 8/12/2019 Bituminous road constructions steps.docx

    5/17

    Compaction curve

    A compaction curve is plotted between the water content as abscissa and the corresponding dry density

    as ordinate. It is observed that the dry density initially increases with an increase in water content till

    the maximum density is attained. With further increase in water content the dry density decreases. The

    water content corresponding to maximum dry density is known as the optimum water content (O.W.C)

    or the optimum moisture content (O.M.C).

    At a water content more than the optimum, the additional water reduces the dry density as it occupies

    the space that might have been occupied by the solid particles.

    For a given water content, theoretical maximum density is obtained corresponding to the condition

    when there are no air voids (degree of saturation is 100%). The theoretical maximum density is also

    known as saturated dry density. The line indicating theoretical maximum density can be plotted along

    with the compaction curve. It is known as the zero air void line.

    MODIFIED PROCTOR TEST

    The modified Proctor test was developed to represent heavier compaction than that in the standard

    Proctor test. The test is used to simulate field conditions where heavy rollers are used. The test was

    standardized by American association of State Highway Officials and is, therefore also known as

    modified AASHO test.

    In this, the mould used is same as that in the Std Proctor test. However, the rammer used is much

    heavier and has a greater drop than that in the Std Proctor test. Its mass is 4.89 kg and the free drop is

    450mm. The soil is compacted in five equal layers; each layer is given 25 blows. The compactive effort in

  • 8/12/2019 Bituminous road constructions steps.docx

    6/17

    modified Proctor test is 4.56 times greater than in the Std Proctor test. The rest of the procedure is

    same

    FACTORS AFFECTING COMPACTION

    o Water Content

    At low water content, the soil is stiff and offers more resistance to compaction. As the water content is

    increased, the soil particles get lubricated. The soil mass becomes more workable and the particles have

    closer packing. The dry density of the soil increases with an increase in the water content till the O.M.C

    is reached.

    o Amount of compaction

    The increase in compactive effort will increase the dry density at lower water content to a certain

    extent.

    o Type of soil

    The dry density achieved depends upon the type of soil. The O.M.C and dry density for different soils are

    different

    o Method of compaction

    The dry density achieved depends on the method of compaction

    EFFECT OF COMPACTION ON PROPERTIES OF SOILS

    1. Soil Structure

    Soils compacted at a water content less than the optimum generally have a flocculated structure. Soils

    compacted at water content more than the optimum usually have a dispersed structure.

    2. Permeability

    The permeability of a soil depends upon the size of voids. The permeability of a soil decreases with an

    increase in water content on the dry side of optimum water content.

    3. Swelling

    4. Pore water pressure

    5. Shrinkage

    6. Compressibility

    7. Stress-strain relationship

    8. Shear strength

  • 8/12/2019 Bituminous road constructions steps.docx

    7/17

    METHODS OF COMPACTION USED IN THE FIELD

    Several methods are used in the field for compaction of soils. The choice of method will depend upon

    the soil type, the maximum dry density required and economic consideration. The commonly used

    methods are

    1. Tampers

    2. Rollers

    3. Vibratory compactors

    The compaction depends upon the following factors

    o Contact pressure

    o Number of passes

    o Layer thickness

    o Speed of roller

    Types of rollers

    o Smooth-wheel rollers

    o Pneumatic tyred rollers

    o Sheep foot rollers

    COMPACTION CONTROL

    Compaction control is done by measuring the dry density and the water content of compacted soil in the

    field

    o Dry density

    The dry density is measured by core cutter method and sand replacement method

    o Water content

    For the measurement of water content, oven drying method, sand bath method, calcium carbidemethod etc are used. Proctor needle is also used for this.

    Compaction is the application of mechanical energy to a soil to rearrange the particles and reduce the void ratio. By doing compaction, we are i ncreasing the shearstrength of soils. There are different methods of compaction which are discussed here. The purpose, laboratory tests, effect of moisture etc has been discussedhere.

    Purpose of Compaction

    o The principal reason for compacting soil is to reduce subsequent settlement under working loads.

  • 8/12/2019 Bituminous road constructions steps.docx

    8/17

    o Compaction increases the shear strength of the soil.

    o Compaction reduces the voids ratio making it more difficult for water to flow through soil. This is important if the soil is being used to retain

    water such as would be required for an earth dam.

    o Compaction can prevent the build up of large water pressures that cause soil to liquefy during earthquakes.

    Factors affecting Compaction

    o Water content of the soil

    o The type of soil being compacted

    o The amount of compactive energy used

    Laboratory Compaction tests

    There are several types of test which can be used to study the compactive properties of soils. Because of the importance of compaction in

    most earth works standard procedures have been developed. These generally involve compacting soil into a mould at various moisture

    contents.

    o Standard Compaction Test AS 1289-E1.1

    Soil is compacted into a mould in 3-5 equal layers, each layer receiving 25 blows of a hammer of standard weight. The apparatus is shown in

    Figure 1 below. The energy (compactive effort) supplied in this test is 595 kJ/m3. The important dimensions are

    Volume of mould Hammer mass Drop of hammer

    1000 cm3 2.5 kg 300 mm

    Because of the benefits from compaction, contractors have built larger and heavier machines to increase the amount of compaction of the

    soil. It was found that the Standard Compaction test could not reproduce the densities measured in the field and this led to the development

    of the Modified Compaction test.

    o Modified Compaction Test AS 1289-E2.1

    The procedure and equipment is essentially the same as that used for the Standard test except that 5 layers of soil must be used. To provide

    the increased compactive effort (energy supplied = 2072 kJ/m3) a heavier hammer and a greater drop height for the hammer are used. The

    key dimensions for the Modified test are

    Volume of mould Hammer mass Drop of hammer

    1000 cm3 4.9 kg 450 mm

  • 8/12/2019 Bituminous road constructions steps.docx

    9/17

    Presentation of Results

    To assess the degree of compaction it is important to use the dry unit weight, dry, because we are interested in the weight of solid soil

    particles in a given volume, not the amount of solid, air and water in a given volume (which is the bulk unit weight). From the relationships

    derived previously we have

    which can be rearranged to give

    Because Gsand ware constants it can be seen that increasing dry density means decreasing voids ratio and a more compact soil .

    In the test the dry density cannot be measured directly, what are measured are the bulk density and the moisture content. From the

    definitions we have

  • 8/12/2019 Bituminous road constructions steps.docx

    10/17

    This allows us to plot the variation of dry unit weight with moisture content, giving the typical reponse shown in Figure 2 below. From this

    graph we can determine the optimum moisture content, mopt, for the maximum dry unit weight, (dry)max.

  • 8/12/2019 Bituminous road constructions steps.docx

    11/17

    Figure 2 A typical compaction test result

    If the soil were to contain a constant percentage, A, of voids containing air where

    writing Vaas V VwVswe obtain

    then a theoretical relationship between dryand m for a given value of A can be derived as follows

    If the percentage of air voids is zero, that is, the soil is totally saturated, then this equation becomes

    From this equation we see that there is a limiting dry unit weight for any moisture content and this occurs when the voids are full of water.

    Increasing the water content for a saturated soil results in a reduction in dry unit weight. The relation between the moisture content and dry

    unit weight for saturated soil is shown on the graph in Figure 3. This line is known as the zero air voids line.

  • 8/12/2019 Bituminous road constructions steps.docx

    12/17

    Figure 3 Typical compaction curve showing no-air-voids line

    Effects of water content during compaction

    As water is added to a soil ( at low moisture content) it becomes easier for the particles to move past one another during the application of

    the compacting forces. As the soil compacts the voids are reduced and this causes the dry unit weight ( or dry density) to increase. Initially

    then, as the moisture content increases so does the dry unit weight. However, the increase cannot occur indefinitely because the soil state

    approaches the zero air voids line which gives the maximum dry unit weight for a given moisture content. Thus as the state approaches the

    no air voidsline further moisture content increases must result in a reduction in dry unit weight. As the state approaches the no air voids line

    a maximum dry unit weight is reached and the moisture content at this maximum is called the optimum moisture content.

    Effects of increasing compactive effort

    Increased compactive effort enables greater dry unit weights to be achieved which because of the shape of the no air voids line must occur at

    lower optimum moisture contents. The effect of increasing compactive energy can be seen in Figure 4. It should be noted that for moisture

    contents greater than the optimum the use of heavier compaction machinery will have only a small effect on increasing dry unit weights. For

    this reason it is important to have good control over moisture content during compaction of soil layers in the field.

  • 8/12/2019 Bituminous road constructions steps.docx

    13/17

    Figure 4 Effects of compactive effort on compaction curves

    It can be seen from this figure that the compaction curve is not a unique soil characteristic. It depends on the compaction energy. For this

    reason it is important when giving values of (dry)maxand moptto also specify the compaction procedure (for example, standard or modified).

    Effects of soil type

    The table below contains typical values for the different soil types obtained from the Standard Compaction Test.

    Note that these are typical values. Because of the variability of soils it is not appropriate to use typical values in design, tests are always

    required.

    Field specifications

  • 8/12/2019 Bituminous road constructions steps.docx

    14/17

    To control the soil properties of earth constructions (e.g. dams, roads) it is usual to specify that the soil must be compacted to some pre-

    determined dry unit weight. This specification is usually that a certain percentage of the maximum dry density, as found from a laboratory

    test (Standard or Modified) must be achieved.

    For example we could specify that field densities must be greater than 98% of the maximum dry unit weight as determined from the

    Standard Compaction Test. It is then up to the Contractor to select machinery, the thickness of each lift (layer of soil added) and to control

    moisture contents in order to achieve the specified amount of compaction.

    Accept

    Reject

  • 8/12/2019 Bituminous road constructions steps.docx

    15/17

    Accept

    Reject

    (a) (b)

    There is a wide range of compaction equipment. For pavements some kind of wheeled roller or vibrating plate is usually used. These only

    affect a small depth of soil, and to achieve larger depths vibrating piles and drop weights can be used. The applicability of the equipment

    depends on the soil type as indicated in the table below

    Equipment Most suitable soils Typical application Least suitable soils

    Smooth wheeled rollers, static or

    vibrating

    Well graded sand-gravel, crushed

    rock, asphalt

    Running surface, base courses,

    subgrades Uniform sands

    Rubber tired rollers

    Coarse grained soils with some

    fines Pavement subgrade Coarse uniform soils and rocks

    Grid rollers

    Weathered rock, well graded

    coarse soils Subgrade, subbase

    Clays, silty clays, uniform

    materials

    Sheepsfoot rollers, static

    Fine grained soils with > 20%

    fines Dams, embankments, subgrades

    Coarse soils, soils with cobbles,

    stones

    Sheepsfoot rollers, vibratory

    as above, but also sand-gravel

    mixes subgrade layers

    Vibrating plates Coarse soils, 4 to 8% fines Small patches clays and silts

    Tampers, rammers All types Difficult access areas

    Impact rollers Most saturated and moist soils

    Dry, sands and gravels

    Sands and gravels

    For soils without any fines (sometimes referred to as cohesionless) the standard compaction test is difficult to perform. For these soil types it

    is normal to specify a relative density, I d, that must be achieved. The relative density is defined by

  • 8/12/2019 Bituminous road constructions steps.docx

    16/17

    where e is the current voids ratio,

    emax, eminare the maximum and minimum voids ratios measured in the laboratory from Standard Tests (AS 1289-5.1)

    Note that if e = emin, Id= 1 and the soil is in its densest state

    e = emax, Id= 0 and the soil is in its loosest state

    The expression for relative density can also be written in terms of the dry unit weights associated with the various voids ratios. From the

    definitions we have

    and hence

    The description of the soil will include a description of the relative density. Generally the terms loose, medium and dense are used where

    Note that you cannot determine the unit weight from knowing I d. This is because the values of the maximum and minimum dry unit weights

    (void ratios) can vary significantly. They depend on soil type (mineralogy), the particle grading, and the angularity.

    Definition of Embankment

    An embankment is a levee, dike or other artificial bank or barrier used to hold back or redirect water in order to prevent floodingfrom a river, lake, sea or other water source. Embankments can also be constructed to support transportation services, such asroadways, railways and canals. In the case of roadways and railways, embankments often raise the level of the transportation to keepthem removed from flooding or other natural dangers.

    Transportation Embankments

    Transportation embankments are built to support transportation. Normally built to allow for a straight, flat and uninterrupted pathof transportation, these embankments are in many ways the opposite of a transportation cutting, where a section of a mountain orhill is cut to make room for a road or railway. In fact, material gathered from transportation cuttings is often used in theconstruction of transportation embankments.

  • 8/12/2019 Bituminous road constructions steps.docx

    17/17