Bid Volume -II Sec Vii-ted-131

Embed Size (px)

Citation preview

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    1/291

    Page 1 of 291

    SPECIFICATIONS

    Supply of material and Erection, testing andcommissioning of New 11 kV lines for bifurcation of 25

    nos overloaded feeders and Augmentation of 88 nosexisting 11 kV feeders covered under Sirsa Circle on

    turnkey basis.

    VOLUME II

    SECTION VII

    BID NO. PD&C/TED 131/2010

    DAKSHIN HARYANA BIJLI VITRAN NIGAM

    HISAR

    June-2010

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    2/291

    Page 2 of 291

    INDEX

    VOLUME II

    SECTION DESCRIPTION PAGE NO.

    VII A, B & C Technical Specifications

    VII D Drawings

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    3/291

    Page 3 of 291

    SECTION VII-A

    1. Introduction

    The scope of this specification covers construction of new 11 KV lines for feeder

    bifurcation and augmentation of overloaded 11 kV feeders under Sirsa circle on

    supply-cum-erection (turnkey ) basis.

    1.1 Scope :

    1.1.1 This specification covers detailed survey, spotting of location of poles, supply and

    erection of PCC poles in single pole support / double pole / 4 pole arrangement

    with complete 11 KV line material such as disc insulators with fittings, 11 KV Pin

    Insulators with Pins, V-Shape Cross arms, pole top bracket, straight X arms,

    earthing material, guy sets with complete material with nuts & bolts washers, pole

    clamps and all other required lines accessories and Belts & Bracings, ACSR

    Conductor, AB Cable, Earth wire, fixing of insulator strings, stringing of

    conductor and earth wire, fixing of stays and testing and commissioning of

    erected 11 KV lines etc.

    1.1.2 This specification also includes the supply of the poles, insulators and their

    hardware, conductor, AB Cable, earth wire etc. The bidder shall clearly indicate

    in his offer the sources from where he proposes to procure the raw material /

    completed material and its components.

    1.1.3 Any material not specifically mentioned in the contract but required to complete

    the job is deemed to be included in the scope of work of the Contractor.

    1.1.4 The entire stringing work of the conductor,cable,messenger and earth wire shall

    be carried out by standard practice. The bidder shall indicate in his offer the

    detailed description of procedure to be deployed for stringing operation.

    1.1.5 Location Details : The line shall be laid in the areas covered under DHBVN in

    Haryana.

    1.2 Details of Line Route and Terrain :

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    4/291

    Page 4 of 291

    The 11 KV Power Lines, LT lines etc will be running almost through plain and

    cultivated area. Preliminary route alignment maps of Power lines covered under

    this package giving the general topography and major crossings like river, power

    lines, railway lines and roads are in the bidders scope. Wherever, special river

    crossings are involved proper strengthening of the normal pole locations will be

    done by the Contractor.1.3 Access to the Line and Right of Way :

    Employer will facilitate and assist the contractor in getting clearance and

    securing way leave and right of way from private/public/Govt owned

    lands.However it shall be the responsibility of the contractor to conduct

    preliminary survey before quoting the Bid and further getting clearance for right

    of way during execution.The employer shall not be responsible for delay on this

    account or pay any compensation in lieu of getting clearance /any damages for

    right of way during execution of the project.

    1.4 Detailed Survey of Optimization Pole Location :

    1.4.1 The detailed survey for the line route and optimization of the pole location along

    with profiling shall be carried out by the successful bidder. The provisional

    quantity has been indicated in the Bill of Material for each package.

    1.4.2 (a) The tentative sketches of the lines / works to be carried out are available in

    the Office of the Nodal officer i.e. GM/Operation concerned from where

    the same can be obtained. The detailed survey shall be carried out by the

    bidder along the approved alignment. The bidder will examine the site of

    works and its surroundings and obtain himself, at his own responsibility

    and expenses, all information regarding general site characteristics,

    crossings accessibility, infrastructure details etc. The purchaser will,

    however, assist the interested bidder to see and inspect the site of work.

    For this purpose the bidders are requested to contact : General Manager,

    Planning & Design, DHBVN, Vidyut Sadan, Vidyut Nagar, Hisar or the

    respective DGM (Operation) / AGM(OP) of the area as indicated on

    sketch.

    Pole & 4 Pole Structure as per site requirements shall be provided where

    the situation so demands. Drawings of 2/4 Pole Structure is provided for

    guidance.

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    5/291

    Page 5 of 291

    (b) Additional H Poles required for Pole Mounting Sub-Station under the

    existing 11 KV feeders are to be taken care of by the Bidder as per the

    requirement of Operation Organization.

    1.4.3 The bidder should note that the Employer will not furnish the topographical map

    prepared by survey of India but will make available any assistance that may berequired for obtaining topographical map.

    1.4.4 Route Marking :

    At the starting point of the commencement of route survey the peg marking shall

    be done with iron spikes, driven firmly into the ground. A Benchmark on top

    section of the angle iron shall be made to indicate the location of the survey

    instrument. Teakwood peg shall be driven at prominent Position at intervals of

    not more than 750 meters along the Power line to be surveyed up to the next angle

    point. At angle position stone / concrete pillar with DHBVN marked on it shall

    be put firmly on the ground for easy identification.

    1.4.5 Pole Locations :

    With the help of pole spotting data, pole locations shall be marked on the profiles

    prepared to check the required ground clearances. While locating the poles on the

    profile sheets the following shall be borne in the mind.

    a) Extension:

    An individual span shall be as near to the normal design span as possible. In case

    an individual span becomes too short or long with normal supports on account of

    ground profile, one or both supports of the spans may be extended with standard

    design or provision of a special structure for the purpose according to technical

    specifications. The design of such extension shall be prepared & supplied by the

    Contractor and shall be got approved from the Employer.

    b) Road Crossings :

    At all the important road crossings, the protective cradle guarding will be

    provided and poles shall be fitted with normal tension insulators strings

    depending upon the location but the ground clearing at the roads at the maximum

    temperature and in the still air shall be such that even with the conductor broken

    at adjacent span, the ground clearance of the conductor from the road surface will

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    6/291

    Page 6 of 291

    not be less than 5.125 meter. For road and lines crossings 11 meter PCC poles

    (400 Kg.) shall be provided to achieve required clearances. H pole structure on

    11 meter PCC poles for road crossings and single 11 meter PCC poles for line

    crossing shall be provided.

    c) Railway Crossings :

    The Contractor will make preliminary survey to assess the requirement ofRailway Crossing and take the same into account in his Bid. The work of

    Railway Crossings will be got executed by him as a deposit work with the

    Railways or otherwise as per rules of Railway Department. The Employer will

    arrange to get the approval from Railway Authorities expedited. The case for

    approval will be submitted by the Contractor on the behalf of the Employer well

    in time.

    d) Power Line Crossings :

    Wherever the line is to cross over / below the other line of the same voltage or

    higher or low voltage the requisite clearances will be ensured in accordance with

    the Indian Electricity Rules. The Contractor shall submit and get approved from

    the Employer any special design where required in order to achieve such

    clearances.

    e) River Crossing:

    The route of 11 KV New / Augmented line/LT line if routed through a river bed /

    mullah or rivulet must have concrete foundation for erection of poles and must be

    supported by a good number of stay-supports capable to withstand water / wind

    pressure and must be executed to the entire satisfaction of the Engineer.

    f) In case the 11 KV U/G cable is to be laid along the Municipal Road / High way,

    the Contractor will make preliminary survey to assess such requirement and take

    into account in his Bid. The employer will arrange to get the approval from the

    Civic Authorities. However, the case for approval will be submitted by the

    Contractor on behalf of the employer well in time.

    1.4.6 Clearance from Ground, Building, Trees etc.:

    Clearance from Ground, Building, Trees and Telephone lines shall be provided in

    conformity with the Indian Electricity Rules 1956.

    1.4.7 The tree cutting shall be the responsibility of the Contractor at the time of survey

    as well as during actual execution. However, the Contractor shall count, mark

    and put proper Nos. with suitable quality of paint at his own cost on all the trees

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    7/291

    Page 7 of 291

    that are to be cut by him at the time of actual execution of work. Contractor may

    please be note that the Employer shall not pay any compensation for any loss or

    damage to the properties or for tree cutting necessitated due to Contractors work.

    1.4.8 Any way leave which may be required by the Contractor shall be arranged by the

    Employer.

    1.4.9 To evaluate and tabulate the trees and bushes coming 6.096m on either side of thecentral alignment of the support, the trees will be numbered and marked with

    quality paint serially from angle point 1 onwards and corresponding number will

    be painted on the stem of trees at a height of 1m from ground level. The trees list

    should contain the following information:

    a) Girth (circumference) measured at a height of 1 m from ground level.

    b) Approximate height of the tree with an accuracy of +/- 2 mtrs.

    c) Name of the type of the species / tree.

    1.4.10 The profile sheets duly spotted along with preliminary schedule indicating

    position of poles, wind span, weight span, angle of deviation, river or road

    crossings and other details shall be submitted for the approval of the Employer.

    After approval the, Contractor shall submit six more sets of approved reports

    along with one set of reproducible final profile drawings to the Employer for

    record purpose.

    1.5 Environmental Conditions :

    1.6.1 General Climatic Conditions :

    The area is in extreme climatic belt. Monsoons are generally active in the area

    from the month of July to September. The area is also prone to mild dust storms

    during the months of March to May. The maximum temperature shall be of the

    order of 50C and minimum temperature shall be of the order of -2C. Normal

    every day temperature is 32C.

    1.7 Technical Data:

    The bidder shall furnish all technical data as per relevant schedules in five copies.

    1.8 Statutory Regulations and Standards :

    1.8.1 Statutory Regulations:

    The Contractor is required to follow Statutory Regulations stipulated in Electricity

    Act 1948 and Indian Electricity Rules 1956 as amended to-date and other local

    rules and regulations referred to in this specification.

    1.8.2 Reference Standards :

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    8/291

    Page 8 of 291

    The work shall be carried out in accordance with specifications & construction

    standards attached hereto. The codes or standards referred to in this specification

    shall govern in all cases wherever such references are made. In case of conflict

    between such codes or standards and specification, latter shall govern. Such

    codes or standards referred to shall mean the latest revision, amendments /

    changes adopted and published by relevant agencies. Other internationallyaccepted standards, which ensure equivalent or better performance than those

    specified shall also be accepted. All tested steel sections shall be supplied

    conforming to relevant Indian Standard Specifications.

    1.9 Quality Assurance, Inspection and Testing :

    1.9.1 Quality Assurance :

    The Contractor shall adopt suitable quality assurance programme to control each

    activity. Such programme shall be outlined by the Contractor and shall be finally

    accepted by the Employer.

    1.9.2 Quality Assurance Document :

    The Contractor shall be required to sub it all quality assurance documents as

    stipulated in quality plan at the time of Employers inspection of material. The

    Employer through his duly authorized representative reserves the right to carry

    out quality inspection / audit & checks to see the adequacy of the Contractors

    quality management programme.

    1.9.3 Inspection and Testing :

    The Employer shall inspect the major material i.e. Poles, Conductors, Earth wire,

    Insulators, Pins, Hardware fittings at the works of supplier before dispatch. The

    requisite original type test certificates wherever required will be submitted by the

    Contractor / Supplier at the time of inspection for verification / examination by

    the Inspector. The material shall not be dispatched without dispatch authorization

    by the Employer. Other material shall be inspected by the Employer before

    erection at site. The Employer shall have the right to re-inspect at his expenses

    any material through previously inspection and approved by him at the

    Contractors / Suppliers works, before / after the same are erected at the site. If

    following the latter, the material is found defective, then the Contractor shall bear

    the cost of this inspection and re-instatement according to specifications. The

    Employer shall get the material inspected from his Engineers or from any other

    inspection agency at its discretion.

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    9/291

    Page 9 of 291

    2.0 Technical Parameters of 11 KV Line :

    Electrical System Data :

    a) Nominal Voltage 11 KV

    b) Maximum system voltage 12 KV

    c) BIL (Impulse) 75 KV (Peak)

    d) Power frequency withstand voltage 28 KV

    3. Details of line material for 11 KV Line(with ACSR):

    3.1 Particulars of Conductor:

    Sr.

    No.

    Particulars Conductor

    1 Type ACSR 50 mm

    2

    2 Standing and wire diameter in mm 6/3.35(AI)

    1/1.35(Steel)6/4.09(AI)

    1/ 4.09 (steel)

    3 Approximate Mass Kg. Per KM. 214/319

    4 Approximate calculated breaking load KN 18.25/26.91

    5 Calculated DC resistance at 20oC 0.5560 Ohm/0.3736 Ohm

    6 Mass of Zine coating 190 gm.m2

    7 Configuration of Conductor Triangular

    3.2 Particular of Pin Insulator / Disc Insulators:

    Sr.No. Particulars I-Pole Str. H-Pole Str. 4-Pole Str.

    1 No. of Disc Insulators - 6 62 E&M Strength of each Disc

    Insulator KN

    45 45 45

    3 11 KV Pin Insulator with Pins 3 3 6

    4 E&M Strength of each PinInsulator KN

    10 10 10

    3.3 Material for Single / H-Pole/4 Pole Structure1 PCC Pole 11 Mtr. 1 No. 2 No. 4 No.

    2 V-Shape Cross Arm 1 No. - -

    3 M.S.Channel X-Arm (100x50x6-2200mm)

    - 1 No. 5 Nos.

    4 Pole Top Bracket 1 No. - -5 Back Clamps 1 No. As required As required

    6 11 KV Pin Insulator with Pins 3 Nos. 3 Nos. 9 Nos.

    7 11 KV Disc Insulators - 6 Nos. 6 Nos.

    8 Guy Sets with stay wire As required 4 Nos. 8 Nos.

    9 Earthing material as per design As required As required As required

    10 Nuts & Bolts, Pole Clamps As per design As per design As per design

    11 MS Flat, 50x50x6mm, 2200mm for

    4-Pole &1400mm for H-Pole

    - 2 Nos. -

    12 MS Bracing 50x50x6mm, 3230mm - 2 Nos. 8 Nos.

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    10/291

    Page 10 of 291

    for 4-Pole &2860mm for H-Pole

    13 Tension fittings suitable for 50

    sq.mm conductor

    - 6 Nos. 8 Nos.

    14 P.G.Clamps for 50 sq.mm conductor - 6 Nos. 6 Nos.

    15 Eye Screw bolts for earth wire 6 Nos

    16 M.S.Angle 50x50x6mm (2400mm)

    for earth wire.

    - - 4 Nos.

    17 Danger Plate - - 2 Nos.

    18 Number Plate 1 No. 1 No. 1 No.

    3.4 Tentative Bill of material for each Package is as per Schedule of Prices Vol-I.

    3.5 Meteorological Data is as per Annexure-II.

    4. Bolts , Nuts & Washers :

    4.1 All Bolts and Nuts shall conform to IS:1363-1967 (amended to-date) or

    equivalent to IES Standard. All Bolts and Nuts shall have Hexagonal head Nuts,

    the heads being forged out of the solid steel rods and shall be truly pen centric and

    square with the shank, which must be perfectly straight. Small Nuts & Bolts both

    shall be fully threaded whereas long bolts shall be partially threaded.

    4.2 Steel Items : All steel items shall be conform to IS:2062 Grade-A (amended to

    date) or equivalent to IEC Standard.

    5. Spares and Clearances:

    5.1 Normal Span :

    The normal running span of the line shall be approx. 60 Mtrs. For 11 KV Line in

    the Cross Country.5.2 Wind Span :

    The wind Span is the sum of two half spans adjacent to the support under

    consideration. For normal horizontal spans this equals to normal running span.

    5.3 Electrical Clearances:

    5.3.1 Ground Clearances:

    The minimum ground clearances from the bottom conductor shall not be less than

    5.125 meter at the maximum sag conditions i.e. at maximum temperature and

    still air.

    Any LT/HT/Telecommunication line falling around of new 11 KV line should

    have enough clearances as prescribed in I.E. rules applicable in this respect.

    5.3.2 For river crossing, the minimum electrical clearance including ground clearance

    will be the same as for normal poles.

    5.4 Conductor and Earth Wire Configuration:

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    11/291

    Page 11 of 291

    The three phases shall be in triangular formation. The phase to phase spacing

    shall not be less than 1.070 Mtr.

    6. Drawings:

    6.1 The design and drawings submitted by the Contractor shall be

    approved/commented by the Employer as the case may be within 20 days of

    receipt of design/drawings in the office of the Engineer. If the design/drawingsare commented by the Employer, the Contractor shall submit revised

    design/drawings within 15 days of date of issue of comments. The drawing will

    also be submitted by the Contractor to the Engineer who will take further

    necessary action to approve the same or get it approved from the competent

    authority.

    6.2 The Contractor is required to furnish the progress of submissions and approvals of

    design and drawings on 25th

    day of every month till the completion of all the

    design activities.

    7. Excavation & Erection of Poles:

    7.1 The Pits for the Poles are to be excavated in the direction of the line, as this will

    facilitate the erection of pole and given internal stability. The depth of the

    foundations to be excavated for the poles shall be approximately 1/6th

    of the

    Poles length. The alignment of the Poles are to be set right and the earth-filling

    will be done after checking the alignment vertically and earth will be rammed

    afterwards properly.

    7.2 11 Poles are to be erected on almost 10th location when the line is going straight

    and it is also to be provided wherever there is an angle of deviation in the line.

    When the angle of deviation is 60C, 4 pole structure will be provided. In case

    of angle H-Pole, the pits are to be excavated along the bi-section of the angle of

    deviation. It will be ensured that the poles are held in vertical position and earth

    is filled in the pits and proper ramming is done so that pole remains in proper

    position. On every H-Pole, 4 stays are to be provided along the line i.e. 2 on each

    direction and in addition two more stays along the bi-section of the angle of

    deviation are to be provided as required depending upon the site conditions as per

    the drawings attached with the specifications.

    7.3 The stays will be provided at all dead end locations, angle locations and T-Off

    points and also on normal locations as wind stays to counter the pressure of the

    winds. Normally every fourth pole of the line shall be provided with two wind

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    12/291

    Page 12 of 291

    stays one on either side of the pole. The angle of the stays will be generally kept

    on 30 to 45 degrees depending upon the tension and the location of the line.

    Every stay shall be provided with 11 KV Disc Insulators as per drawing.

    7.4 Earthing shall be provided on every 4th pole as per the design attached hereto in

    addition to the continuous Earth Wire. H-pole structures will be provided with 2

    No. earthings.7.5 Number plate shall be provided on each location indicating the No. of Structure

    S1, S2 etc. 2 pole and 4 pole structures will be numbered both for structure Nos.

    as well as H-Pole /4-pole marking. For example if Ist H-pole appear at Structure

    No. 10, plate will be denoted as S-10/H-1. Similarly, if Ist 4-pole appear at

    structure No. 25, the same will be denoted by S-25/4P-1 & so on.

    7.6 All unpainted /Un-galvanized iron sections like Channel, Angle/Clamps Stay sets

    etc. shall be given 2 coating of Red Oxide before installation to prevent rusting.

    To avoid rusting anti-corrosion aluminium paint shall also be provided.

    7.7 One set of 11 KV lightning arrestor shall be provided within 3 KM area. 11 KV

    G.O. Switch shall be provided on the terminal structure near the grid S/Station &

    at the interconnection point with existing feeder to facilitate the complete

    isolation of the line.

    8. Handling of Conductor and Earth Wire:

    8.1 The Contractor shall be entirely responsible for any damage to the poles,

    insulators and conductors during transportation & stringing. While running out

    the conductors, care shall be taken that the conductors do not touch or rub against

    the ground or objects, which could cause scratches or damages to the strands. The

    conductors shall be run out of the drums from the top in order to avoid damage

    due to chaffing.

    8.2 The stringing blocks shall be suspended in a manner to suit the design of the X

    arms. Proper T&P shall also be made available to the Employer by the Contractor

    for checking the tensions in the guy wires. The drums shall be provided with a

    suitable braking device to avoid damages, loose running out and kinking of the

    conductor. The conductor shall be continuously observed for loose or broken

    strands or any other damage. When approaching end of a drum length atleast

    three coils shall be left when the stringing operations are to be stopped. These

    coils are to be removed carefully and if another length is required to be run, a

    joint shall be made as per the recommendations of the manufacturers.

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    13/291

    Page 13 of 291

    8.3 Repairs to Conductors if necessary shall be carried out during the running out

    operations with repair sleeves. Repairing of Conductors surface shall be done

    only in case of minor damage scuff marks etc. keeping in view both electrical and

    mechanical safe requirements. The final conductors shall be cleaned smooth and

    without any projections, sharp points cuts, abrasions.

    8.4 Conductors Splices shall be made so that they do not crack or get damaged in thestringing operations. The Contractor shall use only such equipment/methods

    during Conductor stringing which ensures complete compliance in this regard.

    8.5 Derricks shall be used where roads, rivers, channels, telecommunications or

    overhead power line, railway lines, fences or walls have to be crossed during

    stringing operations. It shall be seen that normal services are not interrupted or

    damage caused to property. Shut down shall be obtained when working at

    crossing of overhead power lines as per para 8.8. Contractor shall be responsible

    for proper handling of the Conductor. Earth wire and accessories in the field.

    8.6 The sequence of stringing of Conductors/Earth wire shall be from top to

    downwards i.e. conductors will be run out in succession & earth wire will be

    strung in the last.

    8.7 The proposed 11 KV power lines may run parallel for certain distance with the

    existing power lines, which may remain energized during the stringing period. As

    a result there is a possibility of dangerous voltage build up due to electromagnetic

    and electrostatic coupling in the pulling wire, conductors and earth wires which

    although comparatively small during normal operations can be severe during

    switching. It shall be Contractors responsibility to take adequate safely

    precautions to protect his employees and others from this potential danger.

    8.8 The Contractor shall inform the Engineer whenever he wants to avail the Permit

    to Work from the local sub-division for erecting the new 11 KV line or

    augmenting the existing 11 KV line. A minimum 48 hours advance notice in

    writing for availing the shutdown on any live 11 KV feeder/LT lines shall be

    given to the Engineer. The 11 KV LT line on which permit is takenshould be

    made clear from all the temporary earth, men and material before cancellation of

    the Permit to Work. It is worth mentioning here that the Permit to Work on

    existing line shall be arranged through the Engineer or his representative and the

    same shall also be got cancelled through the same agency only./ No Permit to

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    14/291

    Page 14 of 291

    Work shall be issued on any line directly to Contractor or his staff from any 33

    KV or 66 KV Sub-Station.

    9. Stringing of Conductor & Earth Wire:

    9.1 The stringing of conductor shall be done by standard stringing method.

    9.1.1 After being pulled the Conductor/Earth wire shall not be allowed to hang in the

    stringing blocks for more than 6 hours before being pulled to the specified sag.9.1.1.1Conductors creep in respect of ACSR 50 mm2/ 80mm2 Conductors are to be

    compensated by over tensioning the conductor at a temperature of 21C or lower

    during stringing.

    9.1.2 The bidder shall give complete details of the stringing method, which he proposes

    to follow. Before the commencement of stringing the Contractor shall submit the

    stringing charts for the Conductor and Earth wire for various temperatures and

    spans along with equivalent spans to the Engineer for the approval of the

    Employer.

    9.2 Sagging in Operation:

    9.2.1 The Conductor shall be pulled up to the desired sag and left in running blocks for

    atleast one hours after which the sag shall be re-checked and adjusted if necessary

    before transferring the Conductor from the running blocks to the pin insulators.

    The conductor shall be clamped within 36 hours of sagging.

    9.2.2 The sag will be checked in the first and the last span of the section in case of

    sections upto 8 spans and in one intermediate span also for sections with more

    than eight Spans. The sag shall also be checked when the Conductor have been

    drawn up and transferred from running clocks to the insulators.

    9.2.3 The running blocks when suspended from the structures for sagging shall be so

    adjusted that the Conductors on running blocks will be on the same height as a 11

    KV Pin Insulators to which it is to be secured.

    At sharp vertical angle, the sag and tensions shall be checked on both sides of the

    angle, the conductor wire shall be checked from the running blocks for equality of

    tension on both sides.

    9.2.4 Tensioning and sagging operations shall be carried out in calm weather when

    rapid changes in temperature are not likely to occur.

    9.3 Tensioning and Sagging of Conductor and Earth Wire:

    The Tensioning and Sagging Operations shall be done in accordance with the

    approved stringing chart before the Conductor and Earth wire are finally attached

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    15/291

    Page 15 of 291

    to the poles through the earth wire clamps and insulators for the Conductor. The

    relevant stringing charts for the Conductor and earth wire should be employed for

    this purpose.

    9.4 Final Checking, Testing and Commissioning:

    After completion of the works, final checking of the line and equipment shall be

    carried out by the Contractor to ensure that all the foundation works, pole erectionand stringing has been done according to the specifications and as apaproved by

    the Employer. All the works shall be thoroughly inspected keeping in view the

    following main points:

    a) All the structures are straight & erect and in proper alignment. Sufficient back

    filed earth is lying over each pit and it is adequately rammed / compacted.

    b) All bolts are properly tightened and punched / tack welded.

    c) The stringing of the Conductors and Earth Wire has been done as per the

    approved sag and tension charts and desired clearances are clearly available.

    d) All Conductors and Earth wire accessories are properly installed & fixed.

    e) All other requirements to complete the work like fixing of danger plate, phase

    plate, number plate, barbed wire etc. are properly installed.

    f) The insulation of line as a whole is tested by the Contractor by providing his

    own equipment, labour etc. to the satisfaction of the Employer.

    g) The line is tested satisfactorily for commissioning purpose.

    h) Earth resistance of every earth wire & P/M S/Stn. will be measured and result

    shall be supplied and same will also be checked by the Engineer or his

    representative.

    10. General Technical Conditions :

    10.1 The above provisions shall supplement all the detailed technical specifications

    and requirements brought out herein. The Contractors proposal shall be based on

    the use of materials complying fully with the requirements specified herein.

    10.2 Engineering Data:

    10.2.1 Thefurnishing of engineering data by the Contractor shall be in accordance with

    the schedule as specified in the technical specifications. The review of these data

    by the Employer will cover only general conformance of the data to the

    specifications and not a thorough review of all dimensions quantities and details

    of the materials or items indicated or the accuracy of the information submitted.

    The review of the Employer shall not be considered by the Contractor as limiting

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    16/291

    Page 16 of 291

    any of his responsibilities and liabilities for mistakes and deviations from the

    requirements specified under these specifications.

    10.2.2 All engineering data submitted by the Contractor after review by the Employer

    shall form part of contract document.

    If errors are discovered any time during the validity of the contract then the

    Contractor shall be responsible for their consequences.10.2.3 The quantities worked out here are only tentative. The Contractor shall work out

    actual requirement and get it approved from the Engineer-in-Charge. The

    payment shall be made on actual basis.

    I) In case of availability of space, in the Control Room, for the

    installation of only one 11 KV breaker panel & more than one feeder

    are to be emanated from the concerned sub-station, the 11 KV breaker

    panel incoming type shall be installed which shall cater to the

    requirement of one or more than one outdoor type VCBs (kiosk). The

    11 KV HT supply shall be extended through 11 KV underground

    cable.

    II) A- Back Filling of Pits :

    a) All the locations, (with following exceptions), the pits after erection of

    poles shall be back filled with excavated or borrowed earth in layers

    taking care to ram the earth in one layer at a time to the satisfaction of

    site-in-charge.

    b) For all the failure containment structures, described earlier & repeated

    below, the pits shall be hack filled with excavated / borrowed earth

    and broken bricks (Jhama) back properly rammed to the satisfaction of

    site-in-charge.

    i) At some the tapping points & dead end poles

    ii) At all the points where DT is to be installed.

    iii) At all the points as per REC construction dwg. No. A-10 ( for

    the diversion angle of 10-60 degree).

    iv) At the distance of 1 km max. from the last Jhama filled pole

    structure.

    v) Both side poles at all the crossing for main road, nallaha

    railway crossings etc.

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    17/291

    Page 17 of 291

    vi) Al DP structures.

    Tapping points & roads where the failure containment

    structures is to be erected shall be decided during detailed

    engineering.

    c) The cost of backfilling including all material /borrowed

    earth/Jhama etc. is deemed to be included in the quoted price.The above clauses shall be read in conjunction with clause given

    below:

    B- Foundation & Pole Erection:

    a) The foundation of poles shall be of the following types:-

    i) Foundation back-filled and rammed with excavated soil and brick

    batting for 200 Kg. PCC Poles.

    ii) Foundation back-filled and rammed with excavated/borrowed soil.

    b) The Type of foundation for individual poles shall be decided

    during detailed engineering. The bidder shall quote their rates as

    per the quantity of both types of foundations indicated in the BPS.

    The pole erection rate shall include excavation in all types of

    soil/rock, back-filling of the foundation pole as specified, cost of

    all materials, labour etc.

    c) Foundation back-filled and rammed with excavated soil and brick-

    batting for 200 Kg, PSC poles - The foundation pit of the pole

    should be of size 600 mm x 500 mm x depth. The base of the

    foundation shall be either of PCC (1:2:4) of size 400 x 400 x 70

    mm or a stone plate of size 400 x 400 x 35 mm duly back-filled as

    explained in clause above.

    d) Foundation back-filled and rammed with excavated / borrowed soil

    and brick batting for 200 Kg. PSC Poles. The foundation pit of the

    pole should be of size 600 mm x 400 x depth. The base of the

    foundation shall be either of PCC (1:2:4) of size 400 x 400 x 70

    mm or a stone plate of size 400 x 400 x 35 mm, duly back-filled

    as explained in clause above.

    e) It is envisaged that 11 KV line may be traversing marshy & low

    laying area for which special type of foundation shall be required.

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    18/291

    Page 18 of 291

    In such a case, difference in excavation quantity, concreting &

    reinforcement between special foundation and normal foundation

    shall be part of the package.

    f) Erection of Poles: The poles are to be erected in alignment with

    utmost care. The poles shall then be lifted to the pit with the help

    of wooden supports. The pole shall then be kept in the verticalposition with the help of 25 mm (min.) manila ropes which shall

    act as the temporary anchor. The verticality of the pole shall be

    checked by spirit level in both longitudinal & transverse directions.

    Once, this is done, the back filling / concreting shall be done in the

    pit. The temporary anchor shall be removed only when poles set

    properly in the foundation.

    C- Erection of Stay Sets:

    The Contractor shall install the stay set complete in all respect. This

    includes excavation of pit size 0.5 m x 0.5 m x 1.6 m in all kinds of soil

    including laterite/hard rocks. Stay plate and rod (leaving the top 10 cm)

    shall be embedded in the pit with PCC in the ratio 1:2:4 (the volume of

    PCC shall be 0.5 m x 0.5 m x 0.8 m ). The rest (upper half) of the pit shall

    be filled with excavated soil duly compacted layer by layer. An angle

    between 30 to 45 degrees shall be maintained between stay wire and the

    pole. The stay wire shall be used with a stay insulator at a height of 5 m

    above ground level with G.I. turn buckle.

    Stay set shall be grouted as per drawing No. PGCIL/RE/Stay-Set.

    Cl 11.0:

    1. For the Drawings/GTPs/Standards which are not included in the above tender

    documents, latest REC standards are to be followed.

    2. The technical specifications as given in the tender documents are covering a range

    of items, in that case only the material as per the schedule of prices is to be considered

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    19/291

    Page 19 of 291

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    20/291

    Page 20 of 291

    SECTION VII- B

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    21/291

    Page 21 of 291

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    22/291

    Page 22 of 291

    SECTION VII-B1. Drawings:

    1.1 All drawings submitted by the Contractor including those submitted at the time ofBid shall be with sufficient detail to indicate the type, size, arrangement,

    dimensions, material description, Bill of materials, weight of each component,

    break-u[p for packing and transportation, fixing arrangement required, the

    dimensions required for installation and any other information specificallyrequested in these specifications.

    1.2 Each drawing submitted by the Contractor shall be clearly marked with the nameof the Employer, the specification title, the specification number and the name ofthe project. All titles, notings, markings and writings on the drawing shall be in

    English. All the dimensions should be to the scale and in metric units.

    1.3 The Contractor shall submit the necessary detailed route plan or other necessaryconstruction drawings for approval to the Employer within 20 days of Letter of

    Intent.

    1.4 The route plan drawings submitted by the Contractor shall be examined by theEmployer as far as practicable within 20 days and shall be modified by theContractor, if any modifications and/or corrections are required by the Employer.

    The Contractor shall incorporate such modifications and/or corrections and

    submit the final drawings for approval.Any delays arising out of failure by theContractor to rectify the drawings in good time shall not alter the contract

    completion date.

    1.5The drawings submitted for approval to the Employer shall be inquadruplicate. One print of suet drawings shall be returned to the Contractor

    by the Employer marked approved/approved with corrections . The

    Contractor shall thereupon furnish the Employer additional prints as may berequired along with one reproducible in original of the drawings after

    incorporating all corrections.

    1.6The work shall be performed by the Contractor strictly in accordance withthese drawings and no deviation shall be permitted without the approval of the

    Employer, if so required.1.7All manufacturing, fabrication and erection work under the Scope of

    Contractor, prior to the approval of the drawings shall be at the Contractorsrisk. The Contractor may make any changes in the design which are necessary

    to conform to the provisions and intent of the Contract and such changes will

    again be subject to the approval by the Employer.1.8The approval of the documents and drawings by the Employer shall mean that

    the Employer is satisfied that:

    a) The Contractor has completed the part of the Works covered be thesubject document (i.e., confirmation of progress of work).

    b) The work appears to comply with requirements of specifications.

    In no case the approval by the Employer of any document does implycompliance with all technical requirements, nor the absence of errors insuch documents.

    1.9The following is the general list of the documents and drawings that are to beapproved by the employer:

    a) Work Schedule (Master Network) Plan.b) Sag tensions calculation and sag template curve drawing.c) Pole spotting data.

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    23/291

    Page 23 of 291

    d) Detailed survey report and profile drawings showing groundclearance and pole locations.

    e) Pole earthing trawing.f) Pole accessories drawings like danger plate, number plate, phase

    plates etc.

    g) Pert Chart.1.10 Design Improvements :1.10.1 The Employer or the Contractor may propose changes in the specification

    and if the parties agree upon any such changes and the cost implication,the specification shall be modified accordingly.

    1.10.2 If any such agreement affects the price and schedule of completion, theparties shall agree in writing as to the extent of any change in the price and

    schedule of completion before the Contractor proceeds with the change.

    Following such agreement, the provision thereof, shall be deemed to havebeen amended accordingly.

    1.11 Design Co-ordination.The contractor shall be responsible for the selection and design ofappropriate material/item to provide the best co-ordinated performance of

    the entire system. The basic design requirements are detailed out in this

    specification. The design of various components, sub-assembly andassemblies shall be so done that it facilitates easy field assembly and

    maintenance.

    1.12 Design Review MeetingsThe contractor will be called upon to attend design review meetings withthe Employer and the consultants of the Employer during the period of

    contract. The Contractor shall attend such meetings at his own cost atHisar or at mutually agreed venue as and when required. Such review

    meeting shall be held as & when required.

    2. Packing

    2.1 All the material shall be suitably protected, coated, covered of boxed andcreated to prevent or deterioration during transit, handling & storage at sitetill the time of erection. The Contractor shall be responsible for any loss or

    damage during transportation, handling and storage due to improper

    packing.2.2 The contractor shall include and provide for securely protecting and

    packing the materials so as to avoid loss or damage during transport

    during transport by air, sea, rail and road.

    2.3 All packing shall allow for easy removal and checking at site. Wherevernecessary, proper arrangement for attaching slings for lifting shall be

    provided. All packages shall be clearly marked for with sign showing up

    & down on.3. Progress Report

    Appropriate visual charts shall accompany the monthly progress reportdetailed out the progress achieved on all erection activities as compared to

    the schedules. The report shall also indicate the reasons for variance

    between the scheduled and actual progress and the action proposed for

    corrective measures wherever necessary.4. Manpower Deployment Report

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    24/291

    Page 24 of 291

    4.1 The Contractor shall submit to the employer on the first day of everymonth a manpower deployment schedule for each activity.

    4.2 The Contractor shall also submit to the employer on the first day of everymonth a manpower deployment report of the previous month detailingthe No. of persons scheduled to have been employed and actuallyemployed.

    4.3 Tools, Tackle and Scaffolding

    The Contractor shall provide all the construction equipment, tools,tackle and scaffoldings required for construction, erection andcommissioning of the power line covered under the contract. Heshall submit a list of all such material of the employer before thecommencement of work at site. These tools and tackle shall not beremoved from the site without the written permission of theEmployer.

    4.4 First Aid and General Hygiene

    The Contractor shall provide necessary first aid & reasonable

    Hygiene facilities for all his employees, representatives andworkmen working at the site Enough number of Contractorspersonnel shall be trained in administering the first aid.

    4.5 Security

    The Contractor shall have total responsibility for all requirement andmaterials in his custody, stored, loose, semi-assembled and orerected by him at site. The Contractor shall make suitable securityarrangements including employment of security personnel toensure the protection of all materials, equipment and works from

    theft, pilferage and any other damages and loss.

    4.6 Materials Handling and Storage:

    4.6.1 All the supplies under the Contract as well as arriving at Site shallbe promptly received, unloaded and transported and stored in thestores by the Contraction.

    4.6.2 Contractor shall be responsible for examining all the shipment andnotify the employer immediately of any damage, shortage,discrepancy etc for the purpose of Employers information only. TheContactor shall submit to the Employer every week a report

    detailing all the receipts during the week. However, the Contactorshall be solely responsible for any shortage or damages in transit,handling and/ or in storage and erection at Site.

    4.6.3 The Contractor shall maintain an accurate and exhaustive recorddetailing out the list of all items received by him for the purpose oferection and keep such record open for the inspection of theEmployer.

    4.6.4 Each package shall be legibly marked by the Contractor/ Supplierat his expenses showing the details such as description andquantity of contents, the name of the consignee and address, the

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    25/291

    Page 25 of 291

    gross and net weight of the package, the name of the Contractoretc.

    5. Erection Conditions

    5.1 The following shall supplement the conditions already contained inthe other parts of these specifications and documents and shallgovern that portion of the work on this Contract to be performed atsite.

    5.2 Regulation of local Authorities and Statutes

    5.2.1 The Contractor shall comply with all the rules and regulations oflocal authorities during the performance of his field activities. Heshall also comply with the Minimum Wages Act, 1948 and thepayment of Wages Act (both of the Govt. of India) and the rulesmade there under in respect of any employee or workmanemployed or engaged by him or his Sub-Contractor.

    5.2.2 All registration and statutory inspection fees, if any, in respect of hiswork pursuant to this Contract shall be to the account of theContractor. However, any registration, statutory inspection fees

    lawfully payable under the provisions of the statutory law and itsamendments from time to time during erection in respect of the 11KV line, ultimately to be owned by the Employer, shall be to theaccount of the Employer. Should any such inspection or registrationneed to be re-arranged due to the fault of the Contractor or his Sub-Contractor, the additional fees to such inspection and /orregistration shall be borne by the Contractor.

    5.3 Contractors Field Operation.5.3.1 The Contractor shall keep the Employer informed in advance

    regarding his field activity plans and schedules for carrying-outeach part of the works. Any review of such plan or schedule or

    method of work by the Employer shall not relieve the Contractor ofany of his responsibilities towards the field activities. Such reviewsshall also not be considered as an assumption of any risk

    by the Employer or any of his representatives and no claimof the Contractor will be entertained because of the failure orinefficiency of any such plan or schedule or method of workreviewed. The Contractor shall be solely responsible for the safety,adequacy and efficiency of tools and plants and his erectionmethods.

    5.3.2 All the materials stored in the open or dusty location must becovered with suitable weather-proof and flameproof covering

    material as applicable.5.3.3 The Contractor shall be responsible for making suitable indoor

    storage facilities at various locations to store all items /materialswhich require indoor storage.

    6. Construction Management

    Time is the essence of the Contract and the Contractor shall beresponsible for performance of his works in accordance with thespecified construction schedule. If at any time, the Contractor is

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    26/291

    Page 26 of 291

    falling behind the schedule for reasons attributable to him, he shalltake necessary action to make good for such delays by increasinghis work force or by working overtime or otherwise to accelerate theprogress of the work and to comply with schedule and shallcommunicate such actions in writing to the Employer, satisfying thathis action will compensate for the delay. The Contractor shall notbe allowed any extra compensation for such action.

    7. Field Office Records

    The Contractor shall set up his site offices at different locations to

    facilitate smooth working. The site offices shall be manned by his

    supervisors/ other staff. The Contractor shall maintain at his Site

    office up-to-date copies of all drawings, specifications and other

    supplementary data complete with all the latest revisions thereto.

    The Contractor shall also maintain, in addition, the continuous

    record of all changes to the above Contract Documents, drawings,

    specifications, supplementary data etc. effected in the field and on

    completion of his total assignment under the Contract shall

    incorporate data to indicate as installed conditions of the material

    supplied and erected under the contract. Such drawings and

    engineering data shall be submitted to the Employer in required

    number of copies.

    8. Protection of Property and Contractors Liability :

    The Contractor will ensure provision of necessary safety equipment such

    as barriers, sign-boards, warning lights and alarms etc. to provide

    adequate protection to persons and property. The Contractor shall be

    responsible to give reasonable notice to the Employers and the Owners of

    public or private property and utilities when such property and utilities are

    likely to get damaged or injured during the performance of his works and

    shall make all necessary arrangements with such owners, related to

    removal and/or replacement or protection of such property and utilities.

    9. Insurance:

    The Contractor shall arrange & keep alive all the required insurance

    covers for his Employees/third parties as under :-

    9.1 Workmens Compensation Insurance:

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    27/291

    Page 27 of 291

    This insurance shall protect the Contractor against all claims applicable

    under the Workmens Compensation Act, 1948 (Government of India).

    This policy shall also cover the Contractor against claims for injury,

    disability disease or death of his or his Sub-Contractors employees, which

    for any reason are not covered under the Workmens employees, which

    for any reason are not covered under the workmens Compensation Act,1948. The liabilities shall not be less than:

    Workmens Compensation As per statutory Provisions

    Employees Liability As per statutory Provisions

    9.2 Comprehensive Automobile Insurance

    This insurance shall be in such a form to protect the Contractor against all

    claims for injuries, disability, disease and death to members of public

    including the Employers men and damage to the property of others

    arising from the use of motor vehicles during on or off the site operations,

    irrespective of the ownership of such vehicles. The minimum liability

    covered shall be as herein indicated:

    Fatal Injury : Rs. 100,000 each person

    : Rs. 200,000 each occurrence

    Property Damage : Rs. 100,000 each occurrence

    In case the employer is made to pay such compensation, the Contractor

    will be liable to reimburse the Employer such amount even in addition to

    the compensation indicated above.

    9.3 Comprehensive General Liability Insurance

    9.3.1 The insurance shall protect the Contractor against all claims arising from

    injuries, disabilities, disease or death of members of public or damage to

    property of others, due to any act or omission on the part of the

    Contractor, its agents, its employees, its representatives and Sub-

    Contractors or from riots, strikes and civil commotion.

    9.3.2 The above are only illustrative list of insurance covers normally required

    and it will be the responsibility of the Contractor to maintain all necessary

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    28/291

    Page 28 of 291

    insurance coverage to the extent both in time and amount to take care of

    all its liabilities either direct of indirect, in pursuance of the Contact.

    10. Protection of Measurements and Reference Points :

    The Contractor shall ensure that any finds such as relics, antiques, coins,

    fossils, etc. which he may come across during the course of performance

    of his works either during excavation or elsewhere, are properlyprotect3ed and handed over to the Employees. Similarly, the Contractor

    shall ensure that the bench marks, reference points etc. which are marked

    either with the help of Employer shall or by the Employer shall not be

    disturbed in any way during the performance of its works. If, any work , is

    to be performed which disturbs such reference, the same shall be done

    only after these are transferred to other suitable locations under the

    direction of the Employer. The Contractor shall provide all necessary

    materials and assistance to such relocation of reference points etc.

    11. Work and Safety Regulations:

    11.1 The Contractor shall ensure safety of all the workmen, materials plant and

    equipment belonging to him or to the others, working at the Site. The

    Contractor shall also provide for all safety notices and safety equipment

    required by the relevant legislations and deemed necessary by the

    Employer.

    11.2 The Contractor will notify, well in advance to the Employer, its intention to

    bring to the site any Container filled with liquid or gaseous fuel or

    explosive or petroleum substance or such chemicals which may involve

    hazards. The employer shall have the right to prescribe the conditions,

    under which such a container is to be stored, handled and used during the

    performance of the works and the Contractor shall strictly adhere to and

    comply with such instructions. The Employer shall also have the right, at

    his sole discretion, to inspect any such container or such construction

    plant/equipment for which materials in the container is required to be used

    and dif in his opinion, its use is not safe, he may forbid its use.

    No Claim due to such prohibition or towards additional safety provisions

    called for by him shall be entertained by the Employer.

    Further, any such decision of the Employer shall not, in any way, absolve the

    Contractor of his responsibilities under the Laws of land and in case use of such

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    29/291

    Page 29 of 291

    a Container or entry there of into the Site area is forbidden by the Employer, the

    Contractor shall use alternative methods with the approval of the Employer

    without any cost implication to the Employer or extension of work schedule.

    11.3 Where it is necessary to provide and/or store petroleum products or

    petroleum mixtures and explosives, the Contractor shall be responsible for

    carrying out such provision and/or storage in accordance with the rulesand regulations laid down in Petroleum Act, 1934, Explosives Act, 1948 or

    any other statuary acts in regard there of and amendments thereof, and

    petroleum and carbide of Calcium Manual published by the Chief

    Inspector of Explosives of India. All such storage shall have prior approval

    of the Employer. In case, any approval is necessary from the Chief

    Inspector (Explosives) or any statutory authorities, the Contractor shall be

    responsible for obtaining the same.

    11.4 All equipment used in construction and erection by Contractor shall meet

    Indian/International Standards land where such standards do not exist, the

    Contractor shall ensure these too be absolutely safe. All equipment shall

    be strictly operated and maintained by the Contractor in accordance with

    manufacturers operation manual and safety instructions and as per any

    existing Guidelines/rules in this regard.

    11.5 Periodical examinations and all tests for all lifting/hoisting equipment and

    tackle shall be carried-out in accordance with the relevant provisions of

    Factories Act 1948. Indian Electricity Supply Act and associated

    Laws/Rules in force from time to time. A register of such examinations

    and tests shall be properly maintained by the Contractor and will be

    promptly produced as land when desired by Employer or by the persons

    authorized by him.

    11.6 The Contractor shall provide suitable safety equipment of prescribed

    standard to all employees and workmen according to the need as may be

    directed by the Employer who will also have the right to examine these

    safety equipment to determine their suitability, reliability, acceptability and

    adaptability.

    11.7 The Contractor employing more than 250 workman whether temporary,

    casual, probationer, regular or permanent or on contract, shall employ at

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    30/291

    Page 30 of 291

    least one full time officer exclusively as safety officer to supervises safety

    aspects of the equipment and workman.

    The name and address of such Safety Officer of the Contractor will be

    promptly informed in writing to the Employer with a copy to the Safety

    Officer-Incharge before he starts work or immediately after any change of

    the incumbent is made during currency of the Contract.11.8 In case any accident occurs during the construction/erection or other

    associated activities undertaken by the Contractor, thereby causing any

    minor or major or total injury to his employees due to any reason

    whatsoever, it shall be the responsibility of the Contractor to promptly

    inform the same to the Employer and also to all the authorities envisaged

    under the applicable laws.

    11.9 The Employer shall have the right to stop the work, if in its opinion the

    work is being carried out in such a way as may cause accidents and

    endanger the safety of the persons and /or property. In such cases, the

    Contractor shall be informed in writing about the nature of the hazards and

    possible injury /accident and he shall remove shortcomings promptly. The

    Contractor after stopping the specific work, can if felt necessary, appeal

    against the order of stoppage of work to the Employer within 3 days of

    such stoppage of work and the decision of the Employer in this respect

    shall be conclusive.

    11.10 The Contractor shall not be entitled for any damages /compensation for

    stoppage of work due to safety reasons and the period of such stoppage

    of work will not be taken as an extension of time for completion of work

    and will not be the ground for waiver of any part of Contractors liability for

    timely completion of the works.

    11.11 The Contractor shall follow and comply with all safety rules, relevant

    provisions of applicable laws pertaining to the safety of workman,

    employees plant and equipment as may be prescribed from time to time

    without any demur, protest or contest or reservation. In case of any

    conflict between statutory requirement and safety rules referred above, the

    most stringent clause shall be applicable.

    11.12 If the Contractor fails in providing safe working environment as per Safety

    Rules or continues the work even after being instructed to stop work by

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    31/291

    Page 31 of 291

    the Employer, the Contractor shall promptly pay to the Employer on

    demand, compensation at the rate of Rs. 5000/- per day or part thereof till

    the instructions are complled with and so certified by the Employer.

    11.13 If the Contractor does not take all safety precautions and /or fails to

    comply with the safety Rules as prescribed by the Employer or as

    prescribed under the applicable law for the safety of the equipment, plantand personnel and the Contractor does not prevent hazardous conditions

    which may cause injury to his own employees or employees of other

    Contractors, or Employer or any other person at site or adjacent thereto,

    the Contractor shall be responsible for payment of compensation in the

    form of first hand relief as per the following schedule:-

    a) Fatal Injury or Rs. 1,00,000/- :

    accident causing per person : Applicable

    death : for death/injury

    b) Major injuries or Rs. 20,000/- : to any person

    accident causing per person : whosoever

    25% or more

    Permanent disability :

    The contractor,however, shall be responsible for full amount of

    compensation admissible as per the law of land

    Permanent disability shall have the same meaning as indicated in

    Workmens Compensation Act. The compensation mentioned

    above shall be in addition to the compensation payable to the

    workmen/ employees under the relevant provisions of the

    Workmens Compensation Act and rules framed there under or any

    other applicable law as applicable from time to time. In case the

    Employer is made to pay any such compensation, the Contractor

    will be liable to reimburse the Employer such amount (s) even in

    addition to the compensation indicated above.

    12. Code Requirements

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    32/291

    Page 32 of 291

    The erection requirements and procedures to be followed during

    the execution of the project shall be in accordance with the

    applicable Indian / International standards /regulations, as indicated

    in Technical Specifications, good engineering practice, the

    Drawings and other applicable Indian codes, laws and regulations.

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    33/291

    Page 33 of 291

    SECTION VII-C

    Technical Specification of EquipmentsSr No Description No.

    1 PCC Poles 11M (400 kg WL) CSC-XV/DH/UH/P&D/2009-2010

    2 PCC Poles 9M (200 kg WL) CSC-VII/DH/UH/P&D/2009-2010

    3 ACSR 80 mm2 HSD-S-658-ST-87

    4 ACSR 50 mm2 CSC-X/DH/UH/P&D/2009-20105 Stay Wire 7/8 SWG(GSS) CSC-VI/DH/UH/P&D/2009-2010

    6 GI wire(GSL 8 SWG) CSC-XVI/DH/UH/P&D/2009-2010

    7 MS Nuts and Bolts HSD/S-364/ST-163

    8 Porcelain insulators and insulators

    fittings for 11 kV overhead power

    lines

    CSC-XXIX/DH/UH/P&D/2009-2010

    9 GO switch CSC-XXVIII/DH/UH/P&D/2009-2010

    10 11 kV XLPE cable 185 mm2 CSC- 44 /DH/UH/P&D/2009-2010

    11 Lightening Arrestor 9 kV

    12 Barbed wire

    13 11 kV VCB O/G outdoor type S-51/DD-121

    14 11 kV VCB O/G indoor type (on 33

    kV S/Stn)

    S-76/DD-161

    15 11 kV VCB O/G indoor type (on 132

    kV S/Stn)

    S-81/DD-116

    16 11 kV XLPE Aerial Bunched Cable S-143/DD-177

    17 Heat shrinkable termination kit for

    11 kV Cables

    CSC-XXXVI/DH/UH/P&D/2009-2010

    18 Control cable

    19 Heavy duty LA

    20 Feeder meterCSC-45/DH/UH/P&D/2009-2010

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    34/291

    UTTAR & DAKSHIN HARYANA BIJLI VITRAN NIGAM

    Specification No. CSC-XV/DH/UH/P&D/2009-10

    TECHNICAL SPECIFICTION

    FOR

    PCC POLES (400 KG) W.L. (F.O.S.-2.5) 11 METER LONG.

    Common Specifications

    Committee

    UHBVN & DHBVN

    Page 34 of 291

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    35/291

    Page 35 of 291

    TECHNICAL SPECIFICATION FOR PCC POLES (F.O.S=2.5)11M LENGTH

    1. SCOPE : This specification covers manufactures assembly testing at

    manufacturer works of PCC poles with an over all length of 11.00 M and working

    load of 400 kg at 0.6 M from the top (As per drawings attached) suitable for use

    in over head 33 kV & 11 kV lines as per schedule of requirement.

    2. APPLICABLE STANDARDS : Except when they conflict with specific

    requirement in the specification , the poles shall comply with the relevant

    provisions made in the following Indian standards specification with the latest

    version there of .

    a) IS : 1678-1978 Specification for priestessed concrete pole for overhead

    power telecommunication lines

    b) IS: 2905-1966 Methods of test for concrete pole for overhead power, traction

    telecommunication lines.

    c) IS: 7321-1974 code of practice for selection, handling and erection of

    concrete poles for overhead power and telecommunication lines.

    d) IS: 1343-1980 code of practice for pre-stressed concrete.

    e) IS: 456-1978 code of practice for plain & reinforced concrete.

    f) IS: 1785 (Latest edition) for H.T. steel wires for pre-stressed concrete.

    3. CLIMATIC CONDITIONS: The PCC poles are required to be used under the

    following site conditions :-

    1. Max ambient temperature 50c

    2. Min. ambient temperature -2.5 c

    3. Max. relative humidity 100%

    4. Min. relative humidity 26%

    5. Average number of rainy days per annum. Nearly 120 days

    6. Average number of dust storm days per annum. 900 mm

    7. Isoceraunic level 45

    8. Average number of dust storm days per annum. 35

    9. Max. wind pressure 195 kg/m

    10. Altitude above mean sea level less than 1000 meter

    4. TERMINOLOGY: For the purpose of is standard, the following definitions shall

    apply.

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    36/291

    Page 36 of 291

    4.1 AVERAGE PERMANENT LOAD: That fraction of the working load which

    may be considered of long duration over a period of one year.

    4.2 LOAD FACTOR: The ratio of ultimate transverse load to the transverse

    load at first crack.

    4.3 TRANSVERSE: The direction of the line bisecting the angle contained

    by the conductor at the pole. In the case of straight run, this will be normal to therun of the line.

    4.4 TRANSVERSE LOAD AT FIRST CRACK: For design, the transverse

    load at first crack shall be taken as not less than the value of the working load.

    4.5 WORKING LOAD: The maximum load in the transverse direction, that is

    ever likely to occur, including the wind pressure on the pole. This load is assured

    to act at a point 600 mm below the top with the butt end of the pole planted to the

    required depth, as intended in the design.

    4.6 ULTIMATE FAILURI: The conditions existing when the pole ceases

    to sustain a load increment owing to either crush of concrete, or snapping of the

    prestressing tendon or permanent stretching of the steel in any part of the pole.

    4.7 ULTIMATE TRANSVERSE LOAD: The load at which failure occurs,

    when it is applied at a point 600 mm below the top and perpendicular to the axis

    of the pole alongwith the transverse direction with the butt end of the pole planted

    to the required depth as appended in the design.

    5. MATERIALS :

    5.1 CEMENT: The cement used in the manufacture of pre-stressed concrete

    poles shall be ordinary or rapid hardening Portland cement conforming to IS:

    269-1976 (specifications of ordinary and low heat Portland cement) or IS-804 IE-

    1978 (specifications for rapid hardening Portland cement).

    5.2 AGGREGATES: Aggregates used for the manufacture of pre-stressed

    concrete poles shall conform to IS: 383-1970 (Specification for coarse and fine

    aggregates from natural sources for concrete). The nominal max. size of

    aggregates shall in no case exceed 10 mm.

    5.3 WATER: Water should be free from chlorides, sulphate other salts and

    organic matter portable water shall be generally suitable.

    5.4 ADMIXTURE: Admixtures should not contain calcium chloride or other

    chlorides and salts which are likely to procorrosion of pre-stressing steel.

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    37/291

    Page 37 of 291

    5.5 PRE STRESSING STEEL : The pre-stressing steel wires, including those

    used as untensioned wires, should conform to IS ;1985 (part-1)- 1966

    (specification for plain hard drawn steel wire for pre-stressed concrete part-1 cold

    drawn stress relieved wire), IS :1785 (part-II ) -1967 (specification for plain hard

    drawn steel wire for prestressed concrete part-II as drawn wire), or IS :6003-1970

    (specification for intended wire for prestressed concrete )or the latest versionthereof.

    5.6 The concrete Mix. Shall be designed to the requirement laid down for

    controlled concrete (also called design mix. Concrete) in IS :1343-1980(code of

    practice for plain & reinforced concrete) subject to the following special

    conditions :-

    A) Minimum works cube strength at 28 days should be at least 400kg/cm2 .

    B) The concrete strength at transfer should be at least 200kg/cm2 .

    C) The mix. Should contain at least 380kg of cement per cubic meter or

    concrete.

    D) The Mix should contain as low a water content as is consistent with

    adequate workability, if it become necessary to add water to increase the

    workability. If it becomes necessary to add water to increase the

    workability, the cement content also should be raised in such a way that

    the original value of water cement ratio is maintained.

    6. WELDING AND LAPPING OF STEEL: The high tensile steel wire shall be

    continuous over the entire length and the tendon welding shall not be allowed in

    any case. However, jointing or coupling be permitting provided the strength of the

    joint or coupling is not less than the strength of each individual wire.

    7. MANUFACTURE

    7.1 All prestressing wires and re-enforcements shall be accurately fixed as

    shown in the drawings and maintained in position during manufacture. The

    unmentioned re-informants, as indicated in the drawing, should be held in

    position by use of stirrups which should go round all the wires.

    7.2 All wires shall be accurately stretched with uniform prestress in each wire.

    Each wire or group of wires shall be anchored positively during casting care shall

    be taken to see that the anchorages do not yield before the concrete attains

    necessary strength.

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    38/291

    Page 38 of 291

    7.3 COVERS ; The cover concrete measured from the outside of the

    prestressing tendon shall be normally 22mm.

    7.4 COMPACTING Concrete shall be compacted by spinning , vibrating

    shocking or other suitable mechanical means. Hand compaction shall not be

    permitted.

    7.5 CURING :The concrete shall be covered with a layer of socking canvas,Hessian or similar absorbent material and kept constantly wet up to the time

    when the strength or concrete at least equal to the minimum strength of concrete

    at transfer of pros tress . Thereafter, the pole may be removed from the mould

    and watered at intervals to prevent surface cracking of the unit, the interval

    should depend on the atmospheric humidity temperature.

    7.6 The prestressing wires shall be detensioned only when the concrete has

    attained the specified strength all transfer (i.e. 200kg/cm2). The cubes cast for

    the purpose of determining the strength at transfer should be cured, as for as

    possible, under conditions similar to those under which the poles are cured. The

    transfer stage shall be determined based on the daily tests carried out on

    concrete cubes till the specified daily tests carried out on concrete cubes till the

    concrete strength indicated above is reached. thereafter the test on concrete

    shall be carried out as detailed in IS-1343-1980(code of practice for prestressed

    concrete )The manufacturer shall supply, when required by the purchaser or his

    representative , results of compressive test conducted in accordance with IS:456-

    1978(code of practice for plain and re-inforced concrete) on concrete cubes

    made from the concrete used for the poles . if the purchaser so desire

    manufacturer shall supply cubes for test purposes &such cubes shall be tested in

    accordance with IS :456-1978 (code of practice for plain & reinforced concrete).

    The detensioning shall be done by slowly releasing the wires , without imparting

    shock or sudden load to the poles. The rate of detensioning may be controlled by

    any suitable mean either mechanical (screw type) or hydraulic. The poles shall

    not be detensioned or released by cutting the pre-stressing wires using flames or

    bar coppers while the wires are still under tension.

    8. EARTHING: Earthing shall be provided by having a length of 8 SWG GI wire

    embedded in concrete during manufacture and the ends of the wires left

    projecting from the pole to a length of 175mm at 250mm from top and 450mm

    below ground level.

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    39/291

    Page 39 of 291

    The earth wire shall not be allowed to come in contact with the prestressing

    wires.

    9. HANDLING ; Separate eye hooks shall be provided for handling and transport

    one each at a distance of 165cms from either end of pole and they should be on

    the face that has the shorter dimension of the cross section.

    10. TESTS :10.1 Transverse strength test :

    10.1.1. Pole made from ordinary Portland cement shall be tested only on the

    completion of 28 days and poles made form rapid hardening cement only on the

    completion of 14 days after the date of manufacture.

    10.1.2. The pole may be tested in either horizontal or vertical position. If tested

    in horizontal position, provisions shall be made to compensate for the

    overhanging weight of the pole for this purpose the over hanging portion of the

    pole may be supported on a movable trolley or similar device.

    10.1.3. The pole shall be rigidly supported at the butt and for a distance equal

    to the agreed depth of planting i.e. 1.80 M.

    10.1.4. Load shall be applied at a point 600mm from the toe of the pole and

    shall be steadily and gradually increased to the design value of the transfer load

    at first crack. The deformation at this load shall be measured.

    A prestressed concrete pole shall be deemed not to have passed the test of

    visible cracks appear at a stage prior to the application of the design transfer load

    for the first crack.

    The load shall then be reduced to zero and increased gradually to a load equal to

    the first crack load plus 10%of the minimum ultimate transverse load, and held

    up for 2 minutes. This procedure shall be repeated until the load reaches the

    value of 80 percent of the minimum ultimate transverse load and thereafter

    increased by 5 percent of the minimum ultimate transverse load until failure

    occurs. Each time of the load is supplied it shall be held for 2 minutes. The load

    applied to prestressed concrete pole at the point of failure shall be measured to

    the nearest five kilograms . concrete pole shall be deemed not to have passed

    the test if the observed ultimate transverse load is less than the design ultimate

    transverse load.

    10.2 MEASUREMENT OF COVER :-After completion of the transverse

    strength test, the sample pole shall be taken and checked for cover . The cover

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    40/291

    Page 40 of 291

    of the pole shall be measured at 3 points, one within 1.8 meter from the butt end

    of the pole , the second within 0.6meter from the top and the third at an

    intermediate point and the mean value compared with the specified value .

    The mean value of the measured cover should not differ by more than the 1mm

    from the specified cover. The individual values should not differ by more than

    3mm from the specified value.If these requirements are not met the workmanship with reference to aligning of

    the end plates and pre-stressing and assembly of moulds should be improved

    and inspection at production stage tightened suitably.

    11. INSPECTION : Inspection of material and supervision of tests in accordance with

    the relevant Indian standards mentioned in clause-2 above and supporting

    drawing and schedules and approved manufacture specification shall be carried

    out by the purchaser or duly authorized representative. The material shall be

    inspected and tested before dispatch by an authorized representative of the

    Nigam in respect of quality . The manufacturer shall provide to the inspecting

    officer all reasonable facilities without charge to satisfy him that the material is

    being furnished in accordance with the specifications/drawings.

    The purchaser has the right to have tests carried out at the cost of supplier by

    and independent Govt. agency where ever there is dispute regarding the quality

    of material supplied.

    12. MARKING ; The pole shall be clearly and indelibly marked with the following

    particulars either during or after manufacture but before testing at a position so

    as to be easily read after erection in position.

    A) Month and year of manufacture

    B) Transfer strength of pole in kg.

    C) Maker s serial no. and mark

    D) UHBVN/DHBVN PO No. & Dt.

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    41/291

    Page 41 of 291

    ANNEXURE - A

    SCHUDULE OF GUARANTEED AND OTHER TECHNICAL PARTICULARS FOR 11METER PCC POLES.

    Sr. No. Particulars Value

    1. Overall length of pole (mtrs).2. Working load at 0.6 Mtr. From top(kg)

    3. Factor of safety

    4. Bottom depth cm)

    5. Top depth(cm)

    6. Breadth (cms.)

    7. No. tensioned wires per pole(Nos.)

    8. No. of untensioned wires per pole( Nos.)

    9. Length of each untensioned wire

    10. Concrete QTY(m3/pole)

    11. Steel Qty (kg/pole).

    12. Weight of complete pole (kg).

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    42/291

    UTTAR & DAKSHIN HARYANA BIJLI VITRAN NIGAM

    Specification No. CSC-VII/DH/UH/P&D/2009-2010

    TECHNICAL SPECIFICATION

    FOR

    PCC POLES (200KG) W.L. (F.O.S-2.5) 8/9 METER

    LONG

    IssueoftheMonth: JUNE-2009 Common Specifications

    Page 42 of 291

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    43/291

    Page 43 of 291

    TECHNICAL SPECIFICATION FOR

    PCC POLES (200KG) W.L. (F/O/S-2.5)

    8/9 METER LONG.

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    44/291

    Page 44 of 291

    TECHNICAL SPECIFICATION FOR PCC POLES (F.O.S-2.5) 8M

    AND 9M LENGTH

    1. SCOPE:

    This specification covers manufacture, assembly, testing and inspection

    before dispatch at manufacturers works of PCC poles with an overall length

    of 8 M and 9 M and working load of 200Kg at 0.6 M from the top suitable for

    use in overhead LT & HT lines.

    2. APPLICABLE STANDARDS:

    Except when they conflict with requirement in this specification, the poles

    shall comply with relevant provisions made in the following Indian Standards

    Specification.

    2.1. IS - 1678/1960/1978 Specification for prestressed concrete poles foroverhead power, traction and telecommunication lines.

    2.2. IS - 2905/1966 Methods of test for concrete poles for over head power

    and telecommunication lines.

    2.3. IS 7321/1974 Code of practice for selection, handling and erection of

    concrete poles for over head power and telecommunication lines.

    3. CLIMATIC CONDITIONS:

    The PCC poles are required to be used under the following site conditions

    3.1. Max. Temp. 500C

    3.2. Min. Temp. -2.50C

    3.3. Max. relative humidity 100%

    3.4.Average no. of rainy days 120 days

    per annum.3.5. Min. relative humidity 26%

    3.6.Average annual rainfall 900mm

    3.7. Isoceraunic level 453.8. Max. wind pressure 195Kg./Mtr2

    3.9.Average no. of dust storm 35

    days per annum.3.10.Altitude above mean sea 1000Mtrs.

    Level less than.

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    45/291

    Page 45 of 291

    4. TERMINOLOGY:

    For the purpose of this standard the following definition shall apply.

    4.1. AVERAGE PERMANENT LOAD;

    That fraction of the working load which may be considered of long duration

    over period of one year.

    4.2. LOAD FACTOR:The ratio of ultimate transverse load to the transverse load at first crack.

    4.3. TRANSVERSE:

    The direction of the lines bisecting the angle contained by the conductor

    at the pole. In the case of straight run this will be normal to the run of the

    pole.

    4.4. TRANSVERSE LOAD AT FIRST CRADK:

    For design, the transverse load at first crack shall be taken as not less

    than the value of the working load.

    4.5. WORKING LOAD:

    The maximum load in the transverse direction, that is ever likely to occur,

    including the wind pressure on the pole. This load is assumed to act at a

    point 600 mm below the top with the butt end of the pole planted to the

    required depth as intended in the design.

    4.6. ULTIMATE FAILURE:

    The conditions existing when the pole ceases to sustain a load increment

    owing to either crushing of concrete, or snapping of the prestressing

    tendon of permanent stretching of the steel in any part of the pole.

    4.7. ULTIMATE TRANSVERSE LOAD:

    The load at which failure occurs, when it is applied at a point 600 mm

    below the top and perpendicular to the axis of the pole along with the

    transverse direction with the butt end of the pole planted to the required

    depth.

    5. MATERIALS:

    5.1. CEMENT:

    The cement used in the manufacture of prestressed concrete poles shall

    be ordinary or rapid hardening Portland cement conforming to IS:

    269/1978 (specifications for ordinary and low heat Portland cement) or IS:

    8041/1976/1978 (specifications for rapid hardening Portland cement).

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    46/291

    Page 46 of 291

    5.2. AGGREGATES:

    Aggregates used for the manufacture of prestressed concrete shall

    conform to IS: 383/1970 (specifications for coarse and fine aggregate

    from natural sources for concrete). The nominal max. size of aggregate

    shall in no case exceed 10mm.

    5.3. WATER:

    Water should be free from chlorides, sulphates, other salts and organic

    matter. Potable water will be generally suitable.

    5.4. ADMIXTURES:

    Admixtures should not contain calcium chloride or other chlorides and

    salts which are likely to promote corrosion of prestressing steel.

    5.5. PRESTRESSING STEEL:

    The prestressing steel wires, including those used as untensioned wires,

    should conform to IS: 1785/Part-1 /1966 (specification for plain hard

    drawn steel wire for prestressed concrete part-1 cold drawn stress

    relieved wires (IS: 1785/Part-II) 1967 (specification for plain hard drawn

    steel wire for prestressed concrete Part-II As drawn wire) or IS:

    6003/1970 (specification for indented wire for prestressed concrete).

    5.6. CONCRETE MIX. :

    The concrete mix shall be designed to the requirements laid down for

    controlled concrete (also called design mix concrete) in IS: 1343/1960

    (code of practice for prestressed concrete) and IS: 456/1964 (code of

    practice for plain and reinforced concrete) subject to the following special

    conditions.

    a. Min. works cube strength at 28 days should be at least 420 Kg./Sq.

    cm.

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    47/291

    Page 47 of 291

    b. The concrete strength at transfer should be at least 210 Kg./Sq.

    cm.

    c. The mix should contain at least 380 kg of cement per cubic meter

    of concrete.

    d. The mix should contain as low a water content as is consistent with

    adequate workability if it becomes necessary to add water toincrease the workability, the cement content also should be raised

    in such a way that the original value of water cement ratio is

    maintained.

    6. WELDING & LAPPING OF STEEL:

    The high tensile steel wire shall be continuous over the entire length of the

    pole tendon. Welding shall not be allowed in any case, however, jointing or

    coupling may be permitted provided the strength of the joints or coupling is

    not less than the strength of each individual wire.

    7. MANUFACTURE:

    7.1.All prestressing wires and reinforcements shall be accurately fixed as

    shown in the drawings and maintained in position during manufacture.

    The untensioned re-inforcement as indicated in the drawing should be

    held in position by the use of strips which should go around all the wires.

    7.2.All wires shall be accurately stretched with uniform prestress in each wire.

    Each wire or group of wires shall be anchored positively during casting.

    Care shall be taken to see that the anchorages do not yield before the

    concrete attains the necessary strength.

    7.3. COVER:

    The cover concrete measured from the outside of the prestessing tendon

    shall be normally 20mm.

    7.4. COMPACTING:

    The concrete shall be compacted by spinning, vibrating shocking or other

    suitable mechanical means. Hand compaction shall not be permitted.

    7.5. CURING:

    The concrete shall be covered with a layer of sacking, canvas, Hessian or

    similar absorbent material and kept constantly wet up to the time when

  • 7/31/2019 Bid Volume -II Sec Vii-ted-131

    48/291

    Page 48 of 291

    the strength of concrete is at least equal to the minimum strength of

    concrete at transfer of prestress. Thereafter, the pole may be removed

    from the mould and watered at intervals to prev