125
Pradhan Mantri Krishi Sinchayee Yojana (PMKSY) District Irrigation Plan (2016-2020) BHAVNAGAR, GUJARAT BHAVNAGAR

BHAVNAGAR, GUJARAT - Pradhan Mantri Krishi … | P a g e LIST OF TABLES Table 1.1: District Profile 23 Table 1.2: Administrative set-up of Bhavnagar 24

  • Upload
    vokhue

  • View
    225

  • Download
    1

Embed Size (px)

Citation preview

Pradhan Mantri Krishi Sinchayee Yojana (PMKSY)

District Irrigation Plan (2016-2020)BHAVNAGAR, GUJARAT

BHAVNAGAR

Pradhan Mantri Krishi Sinchayee Yojana (PMKSY)

District Irrigation Plan (2016-2020)BHAVNAGAR, GUJARAT

BHAVNAGAR

1 | P a g e

CONTENTS

EXECUTIVE SUMMARY ............................................................................................................ 5

INTRODUCTION ...........................................................................................................................10

Background ................................................................................................................................10

Vision.......................................................................................................................................... 17

Objective ..................................................................................................................................... 17

Strategy/approach ...................................................................................................................... 18

Programme Components ........................................................................................................... 19

Rationale/ Justification ............................................................................................................. 21

Methodology.............................................................................................................................. 22

Chapter 1. General Information of the District ........................................................................ 23

1.1 District Profile ...................................................................................................................... 23

1.2 Demography ........................................................................................................................ 25

1.3 Biomass and Livestock ........................................................................................................ 28

1.4 Agro-Ecology, Climate, Hydrology and Topography ........................................................... 30

1.5 Soil Profile ............................................................................................................................. 31

1.6 Land Use Pattern ................................................................................................................. 33

Chapter 2. District Water Profile .............................................................................................. 37

2.1 Area Wise, Crop Wise Irrigation Status ............................................................................... 37

2.2 Area and Production of major crops ................................................................................... 38

2.3 Irrigation based classification ............................................................................................. 39

Chapter 3. Water Availability .................................................................................................... 41

3.1 Status of Water Availability .................................................................................................. 41

3.2 Status of Ground Water Availability ................................................................................... 42

3.3 Status of Command Area .................................................................................................... 44

3.4 Existing Type of Irrigation .................................................................................................. 45

Chapter 4. Water Requirement /Demand ................................................................................ 48

2 | P a g e

4.1 Domestic Water Demand .................................................................................................... 48

4.3 Livestock............................................................................................................................... 51

4.4 Industrial Water Requirement ............................................................................................ 52

4.5 Water Demand for Power Generation................................................................................. 53

4.6 Water demand ..................................................................................................................... 53

4.7 Water Budget ....................................................................................................................... 54

Chapter 5. Strategic Action Plan for Irrigation in District under PMKSY ............................... 56

5.1 Year wise total Plan of the district: ...................................................................................... 56

5.2 Department wise plan ......................................................................................................... 58

5.3 Component wise plan .......................................................................................................... 59

5.4 Block wise Plan .................................................................................................................... 60

5.5 Additional area under irrigation .......................................................................................... 61

5.6 Employment ........................................................................................................................ 63

5.7 Monitoring and Evaluation ................................................................................................. 64

5.8 Suggestions.......................................................................................................................... 65

Year wise summary of funds for different blocks and activities ................................................... 69

3 | P a g e

LIST OF TABLES

Table 1.1: District Profile ........................................................................................................................ 23

Table 1.2: Administrative set-up of Bhavnagar .................................................................................... 24

Table 1.3: Distribution of male, female and children population in blocks of Bhavnagar ............. 26

Table 1.4: Category wise population in blocks of Bhavnagar .......................................................... 27

Table 1.5: Population of small animals in the blocks of Bhavnagar .................................................. 28

Table 1.6: Population of large animals in the blocks of Bhavnagar ................................................... 29

Table 1.7: Soil Profile of the district ...................................................................................................... 32

Table 1.8: Area under agriculture (Area in ha.) ................................................................................. 34

Table 1.9: Area under forest, wasteland and other uses ..................................................................... 35

Table 2.1: Area Wise, Crop Wise irrigation Status ............................................................................ 37

Table 2.2: Area Wise, season wise irrigation Status of different blocks of Bhavnagar ............... 37

Table 2.2: Production and area of Major Crops ................................................................................ 38

Table 2.3: Irrigation based classification ............................................................................................ 40

Table 3.1: Status of water availability in Bhavnagar(MCM) .......................................................... 42

Table 3.2: Status of block as per central ground water board notification ...................................... 44

Table 3.3: Status of Command Area ...................................................................................................... 44

Table 3.4: Existing type of irrigation – Surface irrigation .................................................................. 45

Table 4.1: Domestic Water Demand (MCM) ........................................................................................ 48

Table 4.2 Crop wise Water Requirement .............................................................................................. 49

Table 4.3: Crop Water Requirement in Million Cubic Meter ........................................................... 50

Table 4.4: Livestock water demand (in MCM) ..................................................................................... 51

Table 4.5 Industrial water demand ........................................................................................................ 52

Table 4.6: Present Water Demand of the district for various sectors (2015)................................... 53

Table 4.7: Total Water Demand of the district for various sectors (Projected for 2020) .............. 54

Table 4.8: Water Budget (Volume in MCM) ....................................................................................... 55

Table 5.1: Summary of PMKSY plan District Bhavnagar, Gujarat. (in Rs. Lakh) ...................... 56

Table 5.2: Department-wise plan ........................................................................................................... 58

Table 5.3: Component wise plan ............................................................................................................ 59

Table 5.4: Block wise year wise PMKSY Plan of Bhavnagar District ................................................ 60

Table 5.5: Block wise year wise plan for bringing additional area under irrigation in Bhavnagar

District ....................................................................................................................................................... 62

Table 5.6: Block wise year wise plan for bringing additional area under micro irrigation in

bhavnagar District .................................................................................................................................... 62

Table 5.7: Block wise year wise employment generation potential in Bhavnagar District (in man

days) ........................................................................................................................................................... 63

4 | P a g e

LIST OF FIGURES & Maps

Figure 1.1: Block wise male and female population of Bhavnagar District ................................... 27

Figure 1.2: Block wise percentage of SC, ST & General population in Bhavnagar District ............ 28

Figure 1.3: block wise population of small and large animals in Bhavnagar ............................... 30

Figure 1.4: TGA, GCA and Cropping Intensities of the blocks ........................................................... 35

Figure 5.1: Block wise share in PMKSY Plan of Bhavnagar District ................................................. 61

Map 1 Administrative map of Bhavnagar District ............................................................................... 24

Map 2 District Soil Map .......................................................................................................................... 32

Map 3 - Land use map of the district ..................................................................................................... 36

Map 4 River and water bodies map of Bhavnagar district ................................................................. 41

Map 5 Watershed map of Bhavnagar .................................................................................................... 47

5 | P a g e

EXECUTIVE SUMMARY

In an agrarian economy like India, agriculture utilizes the major share of country‟s

exploitable water resources. Though the sector utilizes the maximum share of

exploitable water resources, availability of the same at different locations to different

extent makes it vital to adopt effective utilization of water through storage, channelizing

and judicial use. At some places like Punjab and Haryana, the environmental and socio-

economic rationale for this capture by the sector is now being questioned. Accordingly,

it is needed to challenge and change the fundamentals of the prevailing view of water

resources exploitation. A new and more suitable approach to water resources allocation

is necessary if the population is to be adequately fed, without further degradation and

destruction of the critical ecosystem services. Water productivity needs to be enhanced

considerably, and economic cost-benefit analysis and pricing regimes can play a

significant role in such a process. However, these economic measures will not be

sufficient on their own. They will need to be buttressed by technological innovation and

institutional changes in order to encourage a more equitable distribution of resources

and to mitigate potential international conflicts across 'shared' water basins.

Water has unique characteristics that determine both its allocation and use as a resource

by agriculture. Agricultural use of water for irrigation is itself contingent on land

resources. In a situation of growing water scarcity and rising demands for non-

agricultural (household and industrial) use of water, reassessment of sectoral allocations

of water are inevitable. In developing countries, irrigated agriculture plays a vital role in

contributing towards domestic food security and poverty alleviation. Therefore,

achievement of these objectives is dependent on adequate allocations of water to

agriculture. Justification of such allocations requires that irrigated agriculture be a cost-

effective means of achieving stated political or social objectives, such as food security or

poverty alleviation, and that all externalities be taken into account in the pricing

mechanism. Improved allocation of irrigation water is required within the agriculture

sectors in order to achieve greater efficiency in the use of irrigation water and existing

irrigation infrastructure. Reallocation is also required in order to reduce waterlogging

and salinization of irrigated land, to decrease the negative environmental impacts and

6 | P a g e

other externalities of irrigation (caused by over extraction of groundwater and depletion

and pollution of surface water).

Government of India launched Pradhan Mantri Krishi Sinchayee Yojana (PMKSY) to

address the constraints in providing assured irrigation as well as increasing efficiency

and productivity of current water use to bring more prosperity to the rural areas.

Priorities of Government of India were reflected in the Hon‟ble President‟s address to

the joint Session of the Parliament of 16th Lok Sabha where he indicated that “Each

drop of water is precious. Government is committed to giving high priority to water

security. It will complete the long pending irrigation projects on priority and launch the

„Pradhan Mantri Krishi Sinchayee Yojana‟ with the motto of „Har Khet Ko Pani‟. There is

a need for seriously considering all options including linking of rivers, where feasible;

for ensuring optimal use of our water resources to prevent the recurrence of floods and

drought. By harnessing rain water through „Jal Sanchay‟ and „Jal Sinchan‟, we will

nurture water conservation and ground water recharge. Micro irrigation will be

popularised to ensure „Per drop-More crop”.

PMKSY has been approved with an indicative outlay of Rs.50,000 crore over a period of

five years from 2015-16 to 2019-20. The programme is an amalgamation of on-going

schemes of Ministry of Water Resources, River Development and Ganga Rejuvenation,

Ministry of Agriculture & Cooperation and Ministry of Rural Development. The existing

schemes AIBP, CADWM, MI, SWMA, Watershed & Convergence with MGNREGA were

brought together under the umbrella program of PMKSY. Further the scheme seeks

convergence with scheme like Mahatma Gandhi National Rural Employment Guarantee

Scheme (MGNRES), Rashtriya Krishi Vikas Yojana (RKVY), Jawaharlal Nehru National

Solar Mission and Rural Electrification programmes (JLNNSM&REP), Rural

Infrastructure Development Fund (RIDF), Members of Parliament Local Area

Development Scheme (MPLAD), Members of Legislative Assembly Local Area

Development Fund (MLALAD), Local Body Funds (LBF), Working Plan of State Forest

Department (WPSFD) etc. The PMKSY will be implemented in an area development

mode only by adopting a decentralized state level planning and projectised execution

structure that will allow the state to draw up their own irrigation development plans

based on DIPs and SIPs with a horizon of 5-7 years. The program will be supervised and

7 | P a g e

coordinated utilizing the existing mechanism and structure available under Rashtriya

Krishi Vikas Yojana (RKVY) program with state agriculture department acting as the

State Nodal Agency for implementation of PMKSY. However, the implementing

departments for the four components like AIBP, PMKSY (Har Khet Ko Pani), PMKSY

(Per drop more crop) and PMKSY (watershed development) will be decided by the

respective program ministry/department.

The 05 chapters along with introduction chapter, explains the profile of district, its

water requirement for agriculture and allied sector, water availability, assessment of

water requirement for various sectors and strategic action plan for augmentation and

effective management of available water resources.

District Demography: In the year 2013, the district of Botad was created by seceding

two Talukas of Bhavnagar, i.e. Botad and Gadhada from the district. As per District

Statistical Office, the total population of the district (excluding the seceded talukas) can

be calculated as 2410211 out of which population of female and male are 1161541 and

1248670 respectively.

Agriculture in Bhavnagar: Agriculture and horticulture plays an important role

inrural economy in Bhavnagar district. The Gross Irrigated Area of Bhavnagar district

during the year 2013-14 was 189341 hectare which is around 40.82% of the 463868

hectare of gross cropped area.

District Water Profile: Water available in the district is mostly sourced from surface

water. The groundwater irrigation availability for the district is lower than the

availability of surface water irrigation. 1062.08 mcm water through surface irrigation

and 687.4mcm through ground water is available in the district

It is observed that 28% of the total agricultural area of Bhavnagar district falls in

Mahuva Block. The lowest irrigated area under agriculture is in Palitana with 48% of the

total irrigated land in the district, while Talaja has the highest irrigated area with 66% of

the total irrigated area.

Yield per Hectare of Major Crops: In Kharif season majority of crops are grown

under rainfed conditions, where as in summers and rabi cultivation is mostly done in

8 | P a g e

irrigated conditions. Cultivation of horticulture crop is mainly done in irrigated area,

while only 10% of the fruits production land is reported to be rainfed. Yields reported in

Bhavnagar district are reportedly lesser than state average. By enhancing the water

resources availability for irrigation purpose through rainwater harvesting, soil & water

conservation measures, the productivity of crops can be enhanced further.

Existing Type of Irrigation: Mahuva block has the maximum number of canal and

reservoir structures (19.12%) while covering a command area of 38645 hectares

(21.15%). Vallbhipur block has the minimum number of canal and reservoir structures

but has the maximum command area of 43728 hectares under surface irrigation in the

district. Gariyadhar block has the least command area covered by surface irrigation.

Water Budget: The total water gap for the district is currently 319.41 MCM and has

been estimated at 332.67 MCM during 2020, i.e. the supply of water is insufficient to

meet the current and future demand of the district.

Strategic Action Plan under PMKSY: Year wise financial outlay for the four years

can is calculated in the report, i.e. in financial year 2016-17, a budget of Rs48834.14lakh

is proposed. In the subsequent three years, Rs.116882.67lakh, Rs.61688.14lakh and

Rs.25719.07lakh budget is estimated for various departments. The total financial outlay

proposed for the district of Bhavnagar under PMKSY for the year 2016-20 is Rs.

253124.02 lakh.

Department wise Financial Outlay: The highest allocation of funds is proposed for

Accelerated Irrigation Benefits Programme (AIBP) component i.e. Rs. 196188.18 lakh

(77.51%), which is to be executed mainly by Sardar Sarovar Narmada Nigam Ltd.

(SSNNL) and state irrigation departments. Hark het ko pani has the second highest

allocation with Rs. 33105.84 lakh (13.08%). Per drop more crop component of Rs.

17260.20 lakh (6.82%) will be executed by GGRC. This component has one sub

components namely micro irrigation through Drip and Sprinkler. Total Rs.209.46 lakh

has been proposed for extension and training purpose, which shall be undertaken by

ATMA. Gujarat State Watershed Management Agency (GSWMA) has proposed a plan of

Rs. 6360.34 lakh (2.51%) under various component of watershed.

9 | P a g e

Expected Output and Outcome: In the district of Bhavnagar, the plan for four year

plans to bring an additional 69260.01 ha under irrigation. The blockwise distribution is

provided in table 5.5. Vallbhipur taluka has the highest area planned to be brought

under irrigation by this plan (37527.08 ha), while Jesar has the least (706.08 ha).

The employment generation is being calculated for Bhavnagar district by taking 40%

cost of watershed dept. and 20% cost of all other dept. as labor charge, the cost is

divided by Rs.178 to generate total Man-days. The total man-days after calculation come

29131176.

It can be observed that highest employment potential is in Mahuva (25.16%), while

Ghogha has the least (0.85%). The PMKSY interventions are also likely to generate an

additional income of Rs. 59395.82 lakh to the farmers of the district. This is based on

the assumption of at least 60% of potential utilised and Rs. 42,000 per ha incremental

income from rainfed to irrigated farming and 60695 jobs on recurring basis (in 141419

ha additional area brought under irrigation at the rate of 2.33 ha average land holding

by farmers).

10 | P a g e

INTRODUCTION

Background

Preparation of decentralized area specific district planning process visualized in various

plans took concrete shape through the years and initiatives like specific guidelines on

methodologies and processes for preparation of district plans; framework for

preparation of perspective plan, medium term and annual plans by then planning

commission in 1969 and the 73rd and 74th constitutional amendments conferring

constitutional status to Panchayats at district and sub district level; local self-

government in urban areas; constitution of district planning committee to consolidate

the plans prepared at Panchayats and municipalities and prepare a draft development

plan for the whole district.

The decentralized planning process was further strengthened through emphasis by

planning commission on preparation of district level plans and making it an integral

part of the process of preparation of the states 11th five year plan. The Planning

commission issued guidelines in August 2006 for preparation of the district plans. The

guidelines define the District Planning as „the process of preparing an integrated plan

for the local government sector in a district taking into account the resources (natural,

human and financial) available and covering the sectoral activities and schemes

assigned at the district level and below and those implemented through local

governments in a state. The document that embodies this statement of resources and

their allocation for various purposes is known as the District Plan”.

Government of India through a resolution in National Development Council on 29th May

2007 conceived a special Additional Central Assistance Scheme (ACAS) to address the

slow growth of agriculture and allied sectors by incentivizing states to draw up plans for

their agriculture sectormore comprehensively. The NDC resolution states "GoI

introduced a new Additional Central Assistance Scheme to incentivize states to draw up

plans for their agriculture sector more comprehensively, taking agro-climatic

conditions, natural resource issues and technology into account, and integrating

livestock, poultry and fisheries, etc. This involved a new scheme for Additional Central

11 | P a g e

Assistance (ACA) to State Plans, administered by the Union Ministry of Agriculture over

and above its existing Centrally Sponsored Schemes, to supplement the State-specific

strategies including special schemes for beneficiaries of land reforms. The newly created

National Rainfed Area Authority on request, was to assist States in planning for rainfed

areas".

The NDC in its resolution advised the states to prepare a comprehensive district

agriculture plan (C-DAP) that will fully utilize available resources and include allied

agriculture sectors. Further, GOI issued a manual on preparation of comprehensive

district agriculture plans to help the states prepare C-DAP. As per these guidelines, the

objective of district planning is „to design an integrated and participatory action plan for

the development of local area in general and agriculture and allied sectors in particular‟.

The objectives of Comprehensive District Agriculture Plan (C-DAP) were:

To prepare a Comprehensive District Agriculture Plan (C-DAP) through

participatory process involving various organisations and stakeholders.

To enable optimum utilisation of scarce natural, physical & financial resources.

To assess and plan for the infrastructure required to support the agriculture

development.

To establish linkages with the required institutional support services, like

credit, technology transfer, ICT, research etc.

To evolve an action plan for achieving sustainable agricultural growth with food

security and cropping system that will improve farmers‟ income.

The guidelines required the state/district authorities to (i) ensure that the agricultural

plans are prepared for the district and then integrated into the agricultural plans of the

State based on the agro-climatic conditions, availability of technology, trained

manpower and natural resources; (ii) local needs / crops / feed and fodder / animal

husbandry / dairying / fisheries / priorities are reflected in the plan; (iii) productivity

gaps for important crops and livestock and fisheries are reduced; and (iv) the returns to

the farmers from these are maximized.

12 | P a g e

The latest move in the process of strengthening of decentralized planning process was

the Government of India guidelines issued in 2015 in the form of a template for the

preparation of District Irrigation Plan (DIP) and State Irrigation Plan (SIP) as part of

the Pradhan Mantri Krishi Sinchayee Yojana (PMKSY) program and made the

preparation of DIP and SIP mandatory for the states to receive funds from the program.

The present report is a product of these long drawn efforts of Government of India to

strengthen the decentralized planning process in the country focusing on the vital

resource i.e., water.

Water is of vital importance for human & animal life, maintenance of ecological balance

and promotion of developmental activities. Considering its vital importance and ever

increasing demand for water, in the face of population growth, urbanization &

industrialization and considerations of climatic change, making water, an increasingly a

scarce resource, available to multiple uses, planning and management of this vital

resources, utilization of water economically, optimally and equitably assumes greater

importance.

According to the 12th Five year Plan the water budget estimates of India by Ministry of

Water Resources suggests an availability of 1123 billion cubic meters (BCM) against a

current estimated demand of 710 BCM. The Standing Committee of the Ministry of

Water Resources estimates that this water demand will rise to 1093 BCM by 2025.

Though the existing water availability in the immediate future seems to be adequate,

with the near constant supply of water resources in the face of increasing demand on

account of population growth, urbanisation and industrialization will strain the water

supply-demand balance.

The per capita water availability which stood at 5,177 cubic meters in 1951 was reduced

to 1820 cubic meters in 2001 while the international prescribed limit is 1800 cubic

meters. The projected per capita availability of water is 1341 cubic meters in 2025 and

1140 cubic meters in 2050 suggesting shortage of water in the medium term1. Further,

the all India water balance estimates does not reflect the variations in water balance

1Ministry of Water Resources (2011), Strategic Plan for Ministry of Water Resources, Government of India, New

Delhi.

13 | P a g e

across time and space. Certain areas having a positive water balance and the others

facing acute shortage of water. The problem is further accentuated by water quality

related issues.

With the abundant surface and ground water supply in the first five decades since

independence, more than 80 percent of the total available water resources were

allocated for irrigation purposes and the rest meeting the domestic and industrial

demands. In a recent study2on the demand for water from agriculture, domestic and

industrial uses in 2000, 2025 and 2050 seems to suggest that domestic demand (34

BCM in 2000, 66 BCM in 2025 and 101 BCM in 2050) and industrial demand (42 BCM

in 2000, 92 BCM in 2025 and 161 BCM in 2050) for water will utilize the total balance

water available while agriculture demand for water will be (605 BCM in 2000, 675 BCM

in 2025 and 637 BCM in 2050). This change is partly because of the changing sectoral

contributions of India‟s GDP and also partly because of dynamics of irrigation

development in the country where the initial expansion in area under irrigation is

propelled by the availability of abundant water resources and availability of good quality

land. This is no longer the case in many of the states where the availability of land and

water are serious constraints for further expansion of irrigation. Further, as per the

erstwhile planning commission up to March 2012 out of 141 million hectares of net sown

area in the country 114 (or 81%) million hectares is Irrigation Potential Created (IPC)

and 88 (or 62%) million hectares is Irrigation Potential Utilised (IPU) leaving almost

20% of irrigated potential unutilized. This leaves 40 percent of the net sown area in the

country dependent on rainfall which makes farming a high risk and less productive.

The competing demands for water resources and the emerging issues and concerns were

to be addressed through certain basic principles and commonality in approaches in

dealing with planning, development and management of water resources3 under an

Integrated Water Resource Management framework. The main objectives of water

resource management as delineated in National Water Policy 2012 are:

2 Amarasinghe, U.A., Shah T., Turral, H. and Anand, B.K. 2007. India’s water future to 2025-

2050:Business-as-usual scenario and deviations. Research Report 123, International Water Management

Institute, Colombo. 3Ministry of Water Resources, National Water Policy, 2012, Government of India, New Delhi.

14 | P a g e

a) Planning, development and management of water resources need to be governed

by common integrated perspective considering local, regional, State and national

context, having an environmentally sound basis, keeping in view the human,

social and economic needs.

b) Principle of equity and social justice must inform use and allocation of water.

c) Good governance through transparent informed decision making is crucial to the

objectives of equity, social justice and sustainability. Meaningful intensive

participation, transparency and accountability should guide decision making and

regulation of water resources.

d) Water needs to be managed as a common pool community resource held, by the

state, under public trust doctrine to achieve food security, support livelihood, and

ensure equitable and sustainable development for all.

e) Water is essential for sustenance of eco-system, and therefore, minimum

ecological needs should be given due consideration.

f) Safe Water for drinking and sanitation should be considered as pre-emptive

needs, followed by high priority allocation for other basic domestic needs

(including needs of animals), achieving food security, supporting sustenance of

agriculture and minimum eco-system needs. Available water, after meeting the

above needs, should be allocated in a manner to promote its conservation and

efficient use.

g) All the elements of the water cycle, i.e., evapotranspiration, precipitation, runoff,

river, lakes, soil moisture, and ground water, sea, etc., are interdependent and the

basic hydrological unit is the river basin, which should be considered as the basic

hydrological unit for planning.

h) Given the limits on enhancing the availability of utilizable water resources and

increased variability in supplies due to climate change, meeting the future needs

will depend more on demand management, and hence, this needs to be given

priority, especially through (a) evolving an agricultural system which economizes

on water use and maximizes value from water, and (b) bringing in maximum

efficiency in use of water and avoiding wastages.

i) Water quality and quantity are interlinked and need to be managed in an

integrated manner, consistent with broader environmental management

15 | P a g e

approaches inter-alia including the use of economic incentives and penalties to

reduce pollution and wastage.

j) The impact of climate change on water resources availability must be factored

into water management related decisions. Water using activities need to be

regulated keeping in mind the local geo climatic and hydrological situation.

Government of India launched Pradhan Mantri Krishi Sinchayee Yojana (PMKSY) to

address the constraints in providing assured irrigation as well as increasing efficiency

and productivity of current water use to bring more prosperity to the rural areas.

Priorities of Government of India were reflected in the Hon‟ble President‟s address to

the joint Session of the Parliament of 16th Lok Sabha where he indicated that “Each

drop of water is precious. Government is committed to giving high

priority to water security. It will complete the long pending irrigation

projects on priority and launch the ‘Pradhan Mantri Krishi Sinchayee

Yojana’ with the motto of ‘Har Khet Ko Pani’. There is a need for seriously

considering all options including linking of rivers, where feasible; for

ensuring optimal use of our water resources to prevent the recurrence of

floods and drought. By harnessing rain water through ‘Jal Sanchay’ and

‘Jal Sinchan’, we will nurture water conservation and ground water

recharge. Micro irrigation will be popularised to ensure ‘Per drop-More

crop”.

PMKSY has been approved with an indicative outlay of Rs.50,000 crore over a period of

five years from 2015-16 to 2019-20. The programme is an amalgamation of on-going

schemes of Ministry of Water Resources, River Development and Ganga Rejuvenation,

Ministry of Agriculture & Cooperation and Ministry of Rural Development. The existing

schemes AIBP, CADWM, MI, SWMA,Watershed & Convergence with MGNREGA were

brought together under the umbrella program of PMKSY. Further the scheme seeks

convergence with scheme likeMahatma Gandhi National Rural Employment Guarantee

Scheme (MGNRES), Rashtriya Krishi Vikas Yojana (RKVY), Jawaharlal Nehru National

Solar Mission and Rural Electrification programmes (JLNNSM&REP), Rural

Infrastructure Development Fund (RIDF), Members of Parliament Local Area

16 | P a g e

Development Scheme (MPLAD), Members of Legislative Assembly Local Area

Development Fund (MLALAD), Local Body Funds (LBF), Working Plan of State Forest

Department (WPSFD) etc. The PMKSY will be implemented in an area development

mode only by adopting a decentralized state level planning and projectised execution

structure that will allow the state to draw up their own irrigation development plans

based on DIPs and SIPs with a horizon of 5-7 years. The program will be implemented

as part of Rashtriya Krishi Vikas Yojana (RKVY) with state agriculture department

acting as the State Nodal Agency. However, the implementing departments for the four

components like AIBP, PMKSY (Har Khet Ko Pani), PMKSY (Per drop more crop) and

PMKSY (watershed development) will be decided by the respective program

ministry/department.

The funds under this program would be provided to the states as per the pattern of

assistance of Centrally Sponsored Schemes (CSS) decided by the Ministry of Finance

and NITI Aayog. During 2015-16 the existing pattern of assistance of ongoing scheme

was continued. An outlay of Rs. 50,000 crore has been approved for 2015-20. The

financial assistance provided to the state governments from this centrally sponsored

scheme is subject to fulfillment of certain conditions. Firstly, a state will become eligible

to access PMKSY fund only if it has prepared the District Irrigation Plans (DIP) and

State Irrigation Plan (SIP), excepting for the initial year, and the expenditure in water

resource development for agriculture sector in the year under consideration is not less

than the baseline expenditure, which is defined as the average of the expenditure in

irrigation sector irrespective of the department in the state plan in three years prior to

the year under consideration. Secondly, States will be given additional weightage for

levying charges on water and electricity for irrigation purposes, so as to ensure

sustainability of the programme. Thirdly, interstate allocation of PMKSY fund will be

decided based on

Share of percentage of unirrigated area in the state vis-à-vis national average

including prominence of areas classified under Desert Development Programme

(DDP) and Drought Prone Area Development Programme (DPAP)

17 | P a g e

Increase in percentage share of expenditure on water resource development for

agriculture sector in State Plan expenditure in the previous year over three years

prior to it and

Improvement in irrigation efficiency in the state.

Vision

The overreaching vision of Pradhan Mantri Krishi Sinchayee Yojana (PMKSY) will be to

ensure access to some means of protective irrigation to all agricultural farms in the

country, to produce „per drop more crop‟, thus bringing much desired rural prosperity.

Objective

The objectives of the PMKSY are to:

a) Achieve convergence of investments in irrigation at the field level (preparation of

district level and, if required, sub district level water use plans).

b) Enhance the physical access of water on the farm and expand cultivable area

under assured irrigation (Har Khet Ko Pani),

c) Integration of water source, distribution and its efficient use, to make best use of

water through appropriate technologies and practices.

d) Improve on-farm water use efficiency to reduce wastage and increase availability

both in duration and extent,

e) Enhance the adoption of precision-irrigation and other water saving technologies

(More crop per drop).

f) Enhance recharge of aquifers and introduce sustainable water conservation

practices

g) Ensure the integrated development of rainfed areas using the watershed

approach towards soil and water conservation, regeneration of ground water,

arresting runoff, providing livelihood options and other NRM activities.

h) Promote extension activities relating to water harvesting, water management and

crop alignment for farmers and grass root level field functionaries.

i) Explore the feasibility of reusing treated municipal waste water for peri-urban

agriculture, and

18 | P a g e

j) Attract greater private investments in irrigation.

Strategy/approach

To achieve these objectives PMKSY adopted strategies that include

a) Creation of new water sources; repair, restoration and renovation of defunct

water sources; construction of water harvesting structures, secondary & micro

storage, groundwater development, enhancing potentials of traditional water

bodies at village level like Jal Mandir (Gujarat); Khatri, Kuhl (H.P.); Zabo

(Nagaland); Eri, Ooranis (T.N.); Dongs (Assam); Katas, Bandhas (Odisha and

M.P.) etc.

b) Developing/augmenting distribution network where irrigation sources (both

assured and protective) are available or created;

c) Promotion of scientific moisture conservation and run off control measures to

improve ground water recharge so as to create opportunities for farmers to access

recharged water through shallow tube/dug wells;

d) Promoting efficient water conveyance and field application devices within the

farm viz, underground piping system, Drip & Sprinklers, pivots, rain-guns and

other application devices etc.;

e) Encouraging community irrigation through registered user groups/farmer

producers‟ organisations/ NGOs; and

f) Farmer oriented activities like capacity building, training and exposure visits,

demonstrations, farm schools, skill development in efficient water and crop

management practices (crop alignment) including large scale awareness on more

crop per drop of water through mass media campaign, exhibitions, field days, and

extension activities through short animation films etc.

19 | P a g e

Programme Components

PMKSY has following four components:

1. Accelerated Irrigation Benefit Programme (AIBP)

To focus on faster completion of ongoing Major and Medium Irrigation including

National Projects.

2. PMKSY (Har Khet ko Pani)

This component focuses on-

a) Creation of new water sources through Minor Irrigation (both surface and ground

water)

b) Repair, restoration and renovation of water bodies; strengthening carrying

capacity of traditional water sources, construction rain water harvesting

structures (Jal Sanchay);

c) Command area development, strengthening and creation of distribution network

from source to the farm;

d) Ground water development in the areas where it is abundant, so that sink is

created to store runoff/ flood water during peak rainy season.

e) Improvement in water management and distribution system for water bodies to

take advantage of the available source which is not tapped to its fullest capacity

(deriving benefits from low hanging fruits). At least 10% of the command area to

be covered under micro/precision irrigation.

f) Diversion of water from source of different location where it is plenty to nearby

water scarce areas, lift irrigation from water bodies/rivers at lower elevation to

supplement requirements beyond IWMP and MGNREGS irrespective of

irrigation command.

g) Creating and rejuvenating traditional water storage systems like Khatri, Kuhl etc.

at feasible locations.

20 | P a g e

3. PMKSY (Per Drop More Crop)

a) Programme management, preparation of State/District Irrigation Plan, approval

of annual action plan, Monitoring etc.

b) Promoting efficient water conveyance and precision water application devices

like drips, sprinklers, pivots, rain-guns in the farm (Jal Sinchan);

c) Topping up of input cost particularly under civil construction beyond permissible

limit (40%), under MGNREGS for activities like lining inlet, outlet, silt traps,

distribution system etc.

d) Construction of micro irrigation structures to supplement source creation

activities including tube wells and dug wells (in areas where ground water is

available and not under semi critical/ critical/ over exploited category of

development) which are not supported under AIBP, PMKSY (Har Khet Ko Pani),

PMKSY (Watershed) and MGNREGS as per block/district irrigation plan.

e) Secondary storage structures at tail end of canal system to store water when

available in abundance (rainy season) or from perennial sources like streams for

use during dry periods through effective on-farm water management;

f) Water lifting devices like diesel/ electric/ solar pumpsets including water carriage

pipes, underground piping system.

g) Extension activities for promotion of scientific moisture conservation and

agronomic measures including cropping alignment to maximise use of available

water including rainfall and minimise irrigation requirement (Jal Sarankchan);

h) Capacity building, training and awareness campaign including low cost

publications, use of pico projectors and low cost films for encouraging potential

use water source through technological, agronomic and management practices

including community irrigation.

i) The extension workers will be empowered to disseminate relevant technologies

under PMKSY only after requisite training is provided to them especially in the

area of promotion of scientific moisture conservation and agronomic measures,

improved/ innovative distribution system like pipe and box outlet system, etc.

Appropriate Domain Experts will act as Master Trainers.

21 | P a g e

j) Information Communication Technology (ICT) interventions through NeGP-A to

be made use in the field of water use efficiency, precision irrigation technologies,

on farm water management, crop alignment etc. and also to do intensive

monitoring of the Scheme.

4. PMKSY (Watershed Development)

a) Effective management of runoff water and improved soil & moisture conservation

activities such as ridge area treatment, drainage line treatment, rain water

harvesting, in-situ moisture conservation and other allied activities on watershed

basis.

b) Converging with MGNREGS for creation of water source to full potential in

identified backward rainfed blocks including renovation of traditional water

bodies

Rationale/ Justification

In reference to the status and need of irrigation, the water resource management

including irrigation related priorities was identified for Bhavnagar district by the

peoples‟ representatives of district with support from administration and technical

experts. For instance the reports of Strategic Research and Extension Plan (SREP)

prepared under ATMA program, Comprehensive District Agriculture Plan (C-DAP)

prepared as part of Rashtriya Krishi Vikas Yojana (RKVY), Potential Linked Credit Plans

(PLP) of NABARD and the Integrated District Development Plan etc. identified number

of irrigation related issues for Bhavnagar district including (i) promoting water use

efficiency through sprinkler and drip irrigation; (iii) promoting protected polyhouse

cultivation to minimize risk factors and enhance quality and productivity; (iv)

Improvement of on-farm water delivery and efficiency of existing irrigation systems; (v)

promotion of soil conservation of arable & non-arable land through engineering

measures; (vi) creation of new water harvesting structures, check dams, ponds, tanks,

etc (vii) increase the forest cover in the district and (viii) land improvement measures.

22 | P a g e

Methodology

During the course of preparation of District Irrigation Plan (DIP) the team visited

Bhavnagar district to collect data and had interacted with all the stakeholders.

Methodology adopted to prepare DIP is outlined in brief as under:

a) Collection of primary and secondary data from field from various sources

including published documents and websites.

b) Various meetings were held to obtain ground level realities and data from key

personnel/stakeholders through structured, unstructured interviews, focused

group discussions etc.

c) Meetings with various State Government departments and related institutions

were held

d) Meeting through VC was also held with State Level authorities.

e) GIS maps of the area‟s/clusters were studied to understand the land

morphology, topography of the district.

f) Focused group discussions and interaction with agriculture officers,

horticulture officers, soil conservation officers, extension officers, rural

development department, animal husbandry department, irrigation officers

both at blocks and district level for identifying the key issues and focus areas of

the region.

g) Discussion with NABARD officer of Bhavnagar district was also held during the

visit.

h) Team members also participated in the State Level workshop and had active

discussionwith GoI officers, State Level officers and scientists of various

institutions

On the basis of detailed discussion and analysis of data, the team arrived at the

projections of various components of PMKSY and Department wise plan for four years

from 2016-17 to 2019-20 as detailed in the plan.

23 | P a g e

CHAPTER 1. GENERAL INFORMATION OF THE

DISTRICT

1.1 District Profile

Bhavnagar District is situated in South East corner of Saurashtra Peninsula of Gujarat

between 21.18° North Latitude and 71.03° to 72.09° East Longitude. It is surrounded by

Surendranagar, Botad and Ahmedabad Districts on North, Rajkot and Amreli Districts

on the west, Arabian Sea on South and Gulf of Cambay on East. It has a Coast line of

about 152 Kms. It has a geographical area of 9971 Sq. Kms.

The district is an agro-climatic zone VI (South Saurashtra) and VII (North Saurashtra).

The climate of the district varies from hot to moderately hot throughout the year except

in winter. The climate is humid along with the belt. The maximum temperature of the

district is 44.0 degree centigrade while the minimum temperature is 9.0 degree

centigrade. The average rainfall of the district is 732 mms brought by south west wind

during rain in the district. The rainfall at the main headquarter in the district was

registered 732 mms. The entire district receives an equal rainfall.

Table 1.1: District Profile

Name of

the District

District

Code

Latitude Longitude

Bhavnagar 481 21.5092° N 71.8571° E

Administrative setup of Bhavnagar

Bhavnagar is the headquarters of the Bhavnagar district. For administrate purpose, the

district is divided in to 10strata called blocks or Talukas with their headquarters at

(1)Bhavnagar (2)Sihor (3)Umrala (4)Vallabhipur (5) Ghogha (6)Gariadhar (7)Palitana

(8)Mahuva (9)Talaja (10) Jesar

Bhavnagar and Vallabhipur talukas are locally known as „Bhal‟ vistar. Palitana and

Gariadhar talukas are known „Khara-pat‟ vistar.Bhavnagar district has 656Gram

Panchayats and 689 inhabited villages.

24 | P a g e

Table 1.2: Administrative set-up of Bhavnagar

No. of Development

Blocks/ Talukas

(1)Bhavnagar (2)Sihor (3)Umrala (4)Vallabhipur (5) Ghogha

(6)Gariadhar (7)Palitana (8)Mahuva (9)Talaja (10) Jesar

No. of Panchayats 656

No. of Villages 689

The district is headed by the Collector & District Magistrate. At the Sub Division level an

officer Called Prant Officer & SDM holds the office and a Mamlatdar in each Taluka

Office for the smooth administration and quick disposal of services to the people of the

district.

Map 1 Administrative map of Bhavnagar District

25 | P a g e

The District Development Officer looks after the development activities of the district

supported by the Taluka Development Officers in each Taluka along with Chief Judicial

Magistrate, Executive Engineers and other officers look after their respective

departments for carrying out development and regulatory functions. At Village level,

Talati cum Mantri functions under Gram Panchayat and carry out revenue and

developmental work of the Government.

1.2 Demography

Until the independence of India in 1947, Bhavnagar was an independent state ruled by

the Rajput Gohil family. The last Maharaja of Bhavnagar, Krishnakumar Sinhji handed

over the administration of his Bombay State to the people's representative in 1948, and

26 | P a g e

Bhavnagar was the first state to join the Indian Union. In the year 2013, the district of

Botad was created by seceding two Talukas of Bhavnagar, i.e. Botad and Gadhada from

the district. As per District Statistical Office, the total population of the district

(excluding the seceded talukas) can be calculated as 2410211 out of which population of

female and male are 1161541 and 1248670 respectively.

Table 1.3: Distribution of male, female and children population in blocks of Bhavnagar

Block Population

Male Female Total

Vallabhipur 41335 38857 80192

Umrala 44391 41932 86323

Bhavnagar 409978 377341 787319

Ghogha 51861 49116 100977

Sihor 110343 101893 212236

Gariadhar 58669 56218 114887

Palitana 107424 103142 210566

Talaja 174482 151185 325667

Mahuva 206965 200294 407259

Jesar 43222 41563 84785

Total 1248670 1161541 2410211

Source: District Statistical Office, Bhavnagar

Bhavnagar is the most populated block of the district whereas,Vallbhipur has lowest

population (Table 1.3). The population density of Bhavnagar district is 288 people per

sq. km. The population density of Bhavnagar is slightly lower as compared to the

population density of the State (308 person per sq.km.).

27 | P a g e

Figure 1.1: Block wise male and female population of Bhavnagar District

In terms of sex-ratio, Bhavnagar has930 females per 1,000 males as against 919 females

per 1,000 males of state average. Sex ratio in all the Talukas is unfavorable (<1000

male) to females. It is highest in Mahuva (968 female per 1000 male) and lowest in

Talaja (866 female per 1000 male).

Table 1.4: Category wise population in blocks of Bhavnagar

Name of Sub-

District

Total

population

Total

scheduled

castes

population

Total scheduled

tribes population

General

Population

Vallabhipur 80192 4447 163 75582

Umrala 86323 8246 138 77939

Bhavnagar 787319 43412 4717 739190

Ghogha 100977 2081 170 98726

Sihor 212236 17757 647 193832

Gariadhar 114887 10589 354 103944

Palitana 210566 14262 761 195543

Talaja 325667 9035 196 316436

Mahuva 407259 15612 893 390754

Jesar 84785 4118 582 80085

0

50000

100000

150000

200000

250000

300000

350000

400000

450000

Male Female

28 | P a g e

Total 2410211 129559 8621 2272031

Source: District Statistical Office, Bhavnagar

Figure 1.2: Block wise percentage of SC, ST & General population in Bhavnagar

District

Source: District Statistical Office, Bhavnagar

1.3 Biomass and Livestock

Livestock Population

The current livestock population in the district is 2017960 of which 1338937 are small

animals while 679023 are large animals.

Out of 2017960 animals in Bhavnagar district, 61.37% of the animals are from Mahuva,

11.20% from Talaja and 5.69% fromBhavnagar Block. Poultry accounts for 49.92% of the

total animals followed by Indescriptive buffalo which accounts for 17.54% of the total

animals and indigenous cows (15.52%). Large Animals account for 33.65% of the total

livestock while small animals constitute only 66.35%.

Table 1.5: Population of small animals in the blocks of Bhavnagar

Block Small Animals Total Small

Animals Poultry Goats Sheep

Vallabhipur

UmralaBhavnag

arGhogha Sihor

Gariadhar

Palitana Talaja Mahuva Jesar

Total scheduled castes population 4447 8246 43412 2081 17757 10589 14262 9035 15612 4118

Total scheduled tribes population 163 138 4717 170 647 354 761 196 893 582

General Population 75582 77939 739190 98726 193832 103944 195543 316436 390754 80085

0

100000

200000

300000

400000

500000

600000

700000

800000

0

5000

10000

15000

20000

25000

30000

35000

40000

45000

50000

29 | P a g e

Vallbhipur 327 5018 1296 6641

Umarala 100 4645 1358 6103

Bhavnagar 2178 17653 12397 32228

Ghogha 1978 18028 18495 38501

Shihor 634 19570 7033 27237

Gariadhar 19 8927 6621 15567

Palitana 3448 20753 10695 34896

Talaja 19783 29290 50690 99763

Mahuva 977962 45222 49537 1072721

Jesar 930 930 3420 5280

Total 1007359 170036 161542 1338937

Source: Department of Animal Husbandry, Bhavnagar

Table 1.6: Population of large animals in the blocks of Bhavnagar

Block Large Animals Draft

Animal

Total

Large

Animals

Indigenous

Cow

Hybrid

Cow

In

descript

Buffalo

Vallbhipur 19196 672 9605 91 29564

Umarala 17604 1543 10371 85 29603

Bhavnagar 35584 1243 44838 940 82605

Ghogha 19967 431 30278 262 50938

Shihor 43456 1014 33653 348 78471

Gariadhar 20179 426 13376 24 34005

Palitana 36500 901 35866 874 74141

Talaja 37589 434 87899 413 126335

Mahuva 80270 755 84327 436 165788

Jesar 2848 217 3668 840 7573

Total 313193 7636 353881 4313 679023

30 | P a g e

Source: Department of Animal Husbandry, Bhavnagar

Figure 1.3: block wise population of small and large animals in Bhavnagar

1.4 Agro-Ecology, Climate, Hydrology and Topography

Based on different factors of climate, the district has three climatic zone.

Agro

Ecological

Zone Type

Normal

Annual

Rainfall

(mm)

Average

Monthly

Rainfall

(mm)

No of

Rainy

Days

Average Weekly Temperature (0C)

Period

Summer (Apr-

May) Winter (Oct- Mar) Rainy (Jun-Sep)

Min Max Mean Min Max Mean Min Max Mean

Agro

Climatic

Zone VI -

South

Saurashtra,

Zone VII -

North

Saurashtra

655.9 153.1 29.4 21.7 42.8 32.25 13.52 35.47 24.49 23.48 37.75 30.61

VALLABHIPUR

UMARALA

BHAVNAGAR

GHOGHA

SHIHORGARIYADHAR

PALITANA

TALAJAMAHUV

AJesar

Small animals 6641 6103 32228 38501 27237 15567 34896 99763 1072721 5280

Large animals 29564 29603 82605 50938 78471 34005 74141 126335 165788 7573

0

200000

400000

600000

800000

1000000

1200000

Axi

s Ti

tle

31 | P a g e

and Zone

VIII – bhal

and coastal

region

Source: IMD, Gandhinagar

Based on the Hazard Risk Vulnerability Assessment, Bhavnagar faces a number of

hazards, which pose the threat of disaster, the threat (risk) and possible impact

(vulnerability) which can be actualized from these hazards range from minor impacts

affecting one village to events impacting larger than the state alone.

One of the major vulnerable aspect identified in the district is the increasing sea surge in

the area. The report gives sea surge a vulnerability rating of 16 (High) and the vunerable

areas are identified as the Coastal Talukas i.e. Bhavnagar, Ghogha, Mahuva and Talaja

with a vulnerable population of 0.22 million (2,27,264) in 31 Coastal villages in 4 taluka

are likely to be affected if a surge is recordedof 3 meters. (list of villages provided in

annexure 2)

Another major aspect identified as a threat is the drought condition in the district. The

report rates it also at 16 (high) in the vulnerability rating affecting four Taluka i.e.

Vallabhipur, Bhavnagar, Gariadhar and Umrala

1.5 Soil Profile

The geographical formation of Saurashtra is of volcanic origin; hence the soils of

Bhavnagar district with the exception of a few strips, are derived from basalt rock

known as deccan trap. The outcrop of granite rocks is visible at certain places like Talaja

indicating that granite was the original rock formation. However, the volcanic effusions

and spread of lava, followed by denudation have resulted in the creation of a basaltic

topography. The black cotton soils which are not very deep are susceptible to erosion in

the undulating areas in the interior of the district due to rains. The soils along the

coastal belt are however, deeper and plainer but due to their lowness get inundated by

the ingress of sea water.

The soil of the district can be divided into the following types.

32 | P a g e

Medium black soil found in parts of Sihor, Bhavnagar, Talaja, Mahuva, Palitana

and Botad talukas and Umrala and Gadhada mahals. This is the most

predominent type of soil in the district and covers a major part of its area.

Coastal sandy alluvial soil in Mahuva taluka.

Light murram soil in elevated areas of Sihor, Bhavnagar and Palitana talukas.

Clay lime soil in Gariadhar mahal.

Clay alluvial soil of Bhal tract.

Map 2 District Soil Map

Table 1.7: Soil Profile of the district

Block Soil Type

Major Soil Cluster Area (Ha)

Bhavnagar Red 25830

33 | P a g e

Sandy loams 3846

Gariyadhar Black 37677

Others 507

Ghogha Black 23798

Red 26987

Saline 6800

Mahuva Black 3500

Sandy 1500

Saline 5900

Others 500

Palitana Black 24410

Shihor Black 1500

Sandy loams 500

Others 9327

Talaja Black 64999

Saline 1502

Umrala Black 23133

Saline 9230

Vallbhipur Black 8700

Sandy loams 500

Saline 12040

Source: CDAP, Bhavnagar

1.6 Land Use Pattern

The total geographical area (TGA) of Bhavnagar is 613,438 hectare. The largest block of

the district is Mahuva which comprises TGA of 121,469 hectare i.e. about 19.80% of the

TGA of the district. The Gross Cropped Area of the district is 411,062 hectare out of

which 87,772 hectare i.e.21.35% of the area falls in Mahuva Block, followed by Talaja

block having GCA of 61,816 ha i.e. 15.04% of the district. MahuvaBlock alsohas the

maximum net sown area of 53,921 hectare i.e. 20.87% of the net sown area of the

district.

34 | P a g e

Table 1.8: Area under agriculture (Area in ha.)

Block TGA Area Under Agriculture

GCA NSA AST Cropping

Intensity

(%)

Vallbhipur 55248 43307 34225.2 9081.5 127

Umrala 38619.1 29113.3 16850 12263.1 173

Bahvnagar 89683.8 34554.9 27063.6 7491.3 128

Ghogha 42591.2 28959 14683.4 14275.4 197

Sihor 68006 46245.1 28658.6 17586.2 161

Gariadhar 45668.1 36994.6 26335.1 10659.4 140

Palitana 69034.6 42299.8 27652.8 14646.8 153

Talaja 83118.4 61816.7 29020.6 32796.1 213

Mahuva 121468.7 87772.1 53921.5 33850.6 163

Total 613437.9 411062.5 258410.8 152650.4 161

*The data of Jesar taluka is included in Mahuva taluka

Source: Census of India, 2011

TGA- Total Geographical Area, GCA- Gross Cropped Area, NSA- Net Sown Area, AST-

Area Sown more than once

35 | P a g e

Figure 1.4: TGA, GCA and Cropping Intensities of the blocks

The cropping intensity in Ghogha block is 197% and ranks second in the district after

Talaja block where cropping intensity is 213%. In other blocks of Bhavnagar, cropping

intensity ranges from 127% to 173%. Cropping intensity of the district is 162%.

Table 1.9: Area under forest, wasteland and other uses

Block Area Under

Forest

Area Under

Wasteland

Area under other uses

Grasslands

and fallow

land

Non-Agri.

Uses

Vallbhipur 512.8 5123.9 5430.4 874.1

Umrala 135.8 3107.6 5249.2 1013.8

Bahvnagar 5281.6 29801.9 13119.4 6926.2

Ghogha 777.9 5123.6 4774.7 2955.5

Sihor 2851.9 6856.1 10754.8 1297.6

Gariadhar 20.2 1993 6073.5 586.6

127%

173%

128%

197%

161%

140%153%

213%

163%

0%

50%

100%

150%

200%

250%

0

20000

40000

60000

80000

100000

120000

140000

Vallbhipur Umrala Bahvnagar Ghogha Sihor Gariadhar Palitana Talaja Mahuva

TGA GCA NSA AST Cropping Intensity (%)

36 | P a g e

Palitana 1082.5 8341.1 16427.1 883.8

Talaja 2281.1 5150.7 12252.7 1616.1

Mahuva* 1900 9278.3 19605.4 2913.3

Total 14843.8 74776.2 93687.2 19067

*The data of Jesar taluka is included in Mahuva taluka

Source: Census of India, 2011

The district with a total geographical area of 460,920hectare but has an area of only

14,843hectare under forest. Of the total geographical area, 15% of the land is under

grasslands and fallow while 12% of the area are wastelands.

Map 3 - Land use map of the district

37 | P a g e

CHAPTER 2. DISTRICT WATER PROFILE

Bhavnagar district is primarily an agricultural district with cotton, groundnut and wheat

as the predominant crops. The other major crops cultivated are bajra, sesame, pearl

millet, green gram etc.

2.1 Area Wise, Crop Wise Irrigation Status

The total geographical area reported in the district for land uitlisation is 613,438 ha. The

major crops grown in Kharif are Groundnut and Cotton and that in Rabi are Wheat,

gram and Cumin. During summer, Groundnut, pearl millet, sesame and vegetables are

the main crops.

Table 2.1: Area Wise, Crop Wise irrigation Status

Crop Type kharif (Area in ha.) Rabi (Area in ha.) Summer (Area in ha.)

Total (Area in ha.)

Irr Rf Total Irr Rf Total Irr Rf Total Irr Rf Total (A)Cereals 0 29006 29006 25686 2501 28187 2993 0 2993 28679 31507 60186 (B) Coarse Cereals

0 0 0 0 0 0 0 0 0 0 0 0

(C) Pulses 25 1566 1591 775 351 1126 639 0 639 1439 1917 3356 (D) Oil Seeds

265 120577 120842 61 0 61 12101 0 12101 12427 120577 133004

(E) Fibre 165890 62460 228350 0 0 0 0 0 0 165890 62460 228350 (F) Any other crops..

2457 34595 37052 39934 675 40609 19146 0 19146 61537 35270 96807

168637 248204 416841 66456 3527 69983 34879 0 34879 269972 251731 521703

Source: Department of Agriculture, Gandhinagar

Table 2.2: Area Wise, season wise irrigation Status of different blocks of Bhavnagar

Crop Type kharif (Area in ha.) Rabi (Area in ha.) Summer (Area in ha.) Horticulture

&Plantation crops

(Area in ha.)

Irr Rf Total Irr Rf Total Irr Rf Total Irr Rf Total

BHAVNAGAR 15359 21680 37039 2793 40 2833 453 0 453 8184 497 8681

GARIYADHAR 20250 19252 39502 1767 0 1767 80 0 80 836 10 845

GHOGHA 10800 17945 28745 988 0 988 0 0 0 9065 316 9381

MAHUVA 30850 63669 94519 43570 0 43570 12567 0 12567 15604 649 16253

PALITANA 17273 24359 41632 1281 3047 4328 1625 0 1625 5170 359 5529

SHIHOR 20550 38480 59030 7855 50 7905 380 0 380 8328 608 8936

TALAJA 20930 32069 52999 6797 0 6797 19544 0 19544 13496 403 13899

38 | P a g e

UMARALA 18280 13780 32060 1000 0 1000 230 0 230 2064 114 2178

VALLABHIPUR 14345 16970 31315 405 390 795 0 0 0 1044 13 1057

Total 168637 248204 416841 66456 3527 69983 34879 0 34879 63790 2969 66759

*The data of Jesar taluka is included in Mahuva taluka

Source: Department of Agriculture, Gandhinagar

2.2 Area and Production of major crops

It is apparent from the table that 28% of the total agricultural area of Bhavnagar district

falls in Mahuva Block. The lowest irrigated area under agriculture is in Palitanawith48%

of the total irrigated land in the district, while Talaja has the highest irrigated area with

66% of the total irrigated area.

Table 2.3: Production and area of Major Crops

Season Crops

Rainfed Irrigated Total

Area

(ha)

Production

(Qtn/Yr)

Area

(ha)

Production

(Qtn/Yr)

Area(ha) Production

(Qtn/Yr)

kharif Paddy 0 0 0 0 0 0

JOWAR 0 0 0 0 0 0

BAJRI 15486 331864.98 0 0 15486 331864.98

MAIZE 0 0 0 0 0 0

RAGI 0 0 0 0 0 0

MUNG 458 1964.82 0 0 458 1964.82

MATH 136 715.36 0 0 136 715.36

UDID 125 787.5 0 0 125 787.5

TUR 192 1920 0 0 192 1920

GROUNDNUT 95516 1259856.04 0 0 95516 1259856.04

CASTOR 257 5276.21 250 5132.5 507 10408.71

SESAMUM 2094 10386.24 0 0 2094 10386.24

COTTON 37860 75341.4 112890 843288.3 150750 918629.7

TOBACCO 0 0 0 0 0 0

GUAR SEED 213 1420.71 20 133.4 233 1554.11

SOYABEAN 0 0 0 0 0 0

Rabi WHEAT 2431 24310 17962 533471.4 20393 557781.4

39 | P a g e

JOWAR 0 0 104 1109.68 104 1109.68

MAIZE 0 0 0 0 0 0

GRAM 341 4361.39 600 7674 941 12035.39

RAPESEED &

MUSTARD

0 0 26 390 26 390

SUGARCANE 0 0 2 117.98 2 117.98

ISABGUL 0 0 0 0 0 0

FENNEL 0 0 0 0 0 0

TOBACCO 0 0 0 0 0 0

Summer GROUNDNUT 0 0 11452 227894.8 11452 227894.8

BAJRA 0 0 2623 65994.68 2623 65994.68

PADDY 0 0 0 0 0 0

MAIZE 0 0 0 0 0 0

MUNG 0 0 372 2086.92 372 2086.92

UDID 0 0 0 0 0 0

SESAMUM 0 0 11493 1735.82 11493 1735.82

Horticulture Fruits 2969.3 0 26723.7 0 29693 0

Vegetable 0 0 35669 0 35669 0

Flowers 0 0 1122 0 1122 0

Spices 0 0 275 0 275 0

Source: Department of Agriculture, Bhavnagar for the year 2013-14

2.3 Irrigation based classification

Cropping pattern in Bhavnagar is mostly cotton-wheat, groundnut-wheat, cotton-gram

and horticulture based under irrigated conditions. The system is mostly uniform in all

the blocks. Under irrigated conditions, oilseed crops are cultivated in most blocks.

During kharif season, cotton is sown in more than 57 percent area, while groundnut

occupies 36% of the remaining area. While in Rabi 95% of the area cultivated is

occupied by wheat.

40 | P a g e

Table 2.4: Irrigation based classification

Name of Block/ Taluka Irrigated (Area

in ha)

Rainfed (Area

in ha) Total

BHAVNAGAR 12581 21345 33926

GARIYADHAR 9762 19006 28768

GHOGHA 14955 11713 26668

MAHUVA 38646 63459 102105

PALITANA 14735 27169 41904

SHIHOR 21792 38590 60382

TALAJA 45388 68678 114066

UMARALA 13088 13780 26868

VALLABHIPUR 7020 10787 17807

JESAR 11374 - 11374

BHAVANAGAR DIST 189341 274527 463868

Source: State irrigation department, Bhavnagar for the year 2013-14

The Gross Irrigated Area of Bhavnagar district during the year 2013-14 was 189341

hectare which is around 40.82% of the 463868 hectare of gross cropped area.

41 | P a g e

CHAPTER 3. WATER AVAILABILITY

3.1 Status of Water Availability

River/ Khads/ Tributaries

There are no perennial rivers flowing through Bhavnagar district. The rivers, Kansara

Nala, Shetrunji, Ranghola and kalundhar are the major ephemeral rivers flowing in the

district. Canals from these rivers are important sources for lift and surface irrigation.

Canal irrigation from SSNNL is the other major source of surface irrigation in the

district.

Map 4 River and water bodies map of Bhavnagar district

42 | P a g e

The Shetrunji river is the major river in the district with its tributaries viz., Kalubhar,

Ghelo, Vagad, Kalbi, Padala, Keri, Goma, Utavli, Dhantarvadi, Surajvadi, Melan and

Bagad. Most streams are ephemeral. Shetrunji flows towards Southeast and meets with

the Arabian Sea.TheriverShetrunji flows in the south-central part of the district covering

Gariadhar, Palitana and Talajatalukas. Originating in the Dundhi hills in the Gir, it

enters the district about 1.5 km north of Karjala and flows almost towards east and

northeast to east of Palitana and takes a southeasterly turn afterward and debouches in

the Gulf of Cambay near Sultanpur. The total length of the river in the district is about

98 km.

The other important rivers that provide irrigation potential to the central and northern

part of the districts include the Kalubhar, Ghelo, Vagad etc. These rivers have generally

easterly and southeasterly flow and debouch in the marshy land adjoining the Gulf of

Cambay in the north-eastern part of the district. The Kalubhar has a total flow length of

45 km, the Ghelo 72 km and the Vagad 38 km in the district. A number of

rivers/streams originate and flow in a southerly direction in the southern part of the

district south of Shetrunji basin-divide and debouches in the Gulf of Cambay. Important

among them are Dhantarvadi, Nadhi, Surajvadi, Nandh, Malan Nadi and BagadNadi.

Table 3.1: Status of water availability in Bhavnagar(MCM)

S.No. Sources Kharif Rabi Summer Total

1 Surface Irrigation 303.92 758.16 0.00 1,062.08

(i) Canal (Major & Medium

Irrigation)

79.55 603.69 0.00 683.24

(ii) Minor Irrigation tanks 0.00 154.47 0.00 154.47

(iii) Lift Irrigation/Diversion/Check

Dam

224.37 0.00 0.00 224.37

2 Ground Water 618.84 68.56 0 687.4

Source: State Irrigation Department, Bhavnagar

3.2 Status of Ground Water Availability

The Central Ground Water board conducted chemical analysis of the ground water

samples collected during the ground water network monitoring of 2012 in Bhavnagar

43 | P a g e

district. It was found that major part of the District fall under desirable or permissible

category and hence are suitable for drinking purposes. However, a small percentage of

well water is found to have concentrations of some constituents beyond the permissible

limits. Such water is not fit for human consumption and is likely to be harmful to health

on continuous use.

Based on the results it is found that groundwater in the District is mostly of calcium

bicarbonate type when the Electrical conductivity is below 750uS/cm. They are of mixed

cation and mixed anions type when the electrical conductance is between 750 and 3200

uS/cm and waters with electrical conductance more than 3200 uS/cm are of sodium

chloride type. In general in most parts of the District the EC value is found to be very

high i.e. 3200uS/cm to 15000uS/cm and more. It was observed that out of 24water

samples, 7 samples show EC value more than 3200 uS/cm, which indicates the gravity

of salinity problem in the area.

Nitrate value varies from Nil to 460mg/L. High Nitrate > 100mg/L, have been found in

four number of samples out of 24 total number of samples analyzed indicating high

nitrate pollution due to use of nitrogen containing fertilizer, domestic and agriculture

waste and man-made anthropogenic activities. Nitrate value as high as 460mg/L at

Ghogha, 380mg/LatTansa, 340mg/L at Tatum, 110mg/L at Khijadiya, have been

observed in the District. Further, seven water samples in the range of 45mg/L- 100mg/L

representing desirable limit of nitrate content and alternate source of drinking water

may be used in High nitrate content area.

In most of other places having nitrate < 45mg/L there is no problem with respect to

nitrate pollution. Range of Fluoride value varies from 0.20mg/L to 2.50mg/L .High

Fluoride>1.5mg/L, which is mainly attributed due to geogenic conditions, have been

observed in 4 water samples out of 24 water samples analyzed. Fluoride values to the

extent of 2.50mg/L at Vallabhipur, 2.00mg/L at lonjdhara, 1.74mg/L at Jalia and 13

1.70mg/L at Tardhera have been observed indicating prominence of fluoride problem in

these areas. Apart from above locations there is no problem with respect to fluoride

contamination.

44 | P a g e

Table 3.2: Status of block as per central ground water board notification

Sr

No

Taluka/

Block

Status of block as per central ground

water board notification

Ground water (BCM)

OE Critical Semi-

Critical

Safe Saline Draft Recharge Gap

1 Bhavnagar Safe 0.033 0.048 -0.014

2 Gariyadhar Safe 0.037 0.069 -0.032

3 Ghogha Safe 0.031 0.045 -0.014

4 Mahuva Safe 0.089 0.135 -0.046

5 Palitana Safe 0.061 0.090 -0.028

6 Sihor Safe 0.058 0.088 -0.030

7 Talaja Safe 0.081 0.120 -0.039

8 Umarala Safe 0.039 0.057 -0.018

9 Vallabhipur Safe 0.016 0.040 -0.024

*The data of Jesar taluka is included in Mahuva taluka

Source: GWRE-2011

As per the report on Ground Water Resource Estimation (GWRE), 2011, all the blocks in

the district were declared safe.

3.3 Status of Command Area

Total area developed through canal command is 208,723 Ha in the district. Talaja block

has the maximum area with45,388 hectares of land which is irrigated through canal

command.An area of 400849 hectares is undeveloped in the district. Of the total area

only 34% of the area has been developed with canal command.

Table 3.3: Status of Command Area

S.No. Name of

the

Taluka

Information of Canal

Command

Total Area Developed Area Total

Developed

Area

Undeveloped

Area Irrigation

Department

SSNL

45 | P a g e

1 Bhavnagar 92905.41 12580.77 1,597.00 14177.77 78727.64

2 Ghogha 42590.98 14954.66 0 14954.66 27636.32

3 Jesar 39085.55 11374 0 11374 27711.55

4 Mahuva 106339.79 38645.6 0 38645.6 67694.19

5 Palitana 62440.91 14735.44 0 14735.44 47705.47

6 Shihor 73454.54 21792 0 21792 51662.54

7 Talaja 93541.67 45388.43 0 45388.43 48153.24

8 Umarala 39906.93 13087.54 3,146.00 16233.54 23673.39

9 Vallabhipur 56156.31 7020.4 27,220.00 34240.4 21915.91

10 Gariyadhar 45932.03 9762 0 9762 36170.03

Total 652354.12 189340.84 31,963.00 221303.84 431050.28

Source: SSNL and State irrigation department

3.4 Existing Type of Irrigation

Mahuva block has the maximum number of canal and reservoir structures (19.12%)

covering a command area of 38645 hectares (21.15%). Vallbhipur block has the

minimum number of canal and reservoir structures but has the maximum command

area of 43728 hectares under surface irrigation in the district. Gariyadhar block has the

least command area covered by surface irrigation.

Table 3.4: Existing type of irrigation – Surface irrigation

Blocks Source of

Irrigation

Govt. Canal Govt.

Reservoirs/

Dams

BHAVNAGAR No. 7 565

Command

Area(HA)

4,909.77 7,671.00

GARIYADHAR No. 1 770

Command

Area(HA)

113 9649

GHOGHA No. 10 600

46 | P a g e

Command

Area(HA)

4263.66 10691

MAHUVA No. 15 1065

Command

Area(HA)

19352.6 19293

PALITANA No. 8 730

Command

Area(HA)

4283.44 10452

SHIHOR No. 13 1049

Command

Area(HA)

3,820.00 17972

TALAJA No. 25 761.00

Command

Area(HA)

31,588.43 13,800.00

UMARALA No. 2 461

Command

Area(HA)

6,241.54 6846

VALLABHIPUR No. 1 347

Command

Area(HA)

1,077.40 5943

JESAR No. 3 148.00

Command

Area(HA)

580.00 10,794.00

Total No. 84 6496

Command

Area(HA)

76,229.84 113,111.00

47 | P a g e

Map 5 Watershed map of Bhavnagar

48 | P a g e

CHAPTER 4. WATER REQUIREMENT /DEMAND

The earlier Chapters deal with the general profile, water profile and water availability of

Bhavnagar district. The present chapter deals with the current (2015) and projected

(2020) demand of water for various sectors. The demand for water has been assessed on

the basis of data obtained from different departments.

4.1 Domestic Water Demand

Data of Census 2011 and 2001 has been considered to arrive at the growth rate of

population of the district. As per Census 2011, the district has shown an annual growth

rate of 1.663%. Current population (in 2015) has been calculated by assuming a growth

rate of 6.652% (1.663% × 4 Years) over a period of four years (from 2011-2015).

Projected population has been calculated in similar way by assuming a growth rate of

8.32% (1.663% × 5 Years) over the period of five years (from 2015-2020).

It has been assumed that per capita daily water requirement of people residing in urban

areas of the district is 140 litres and for population in rural areas, the daily per capita

daily water requirement is 100 litres. Using the same norms, block-wise domestic water

supply demand has been worked out and is given in table 4.1 below.

Table 4.1: Domestic Water Demand (MCM)

Taluka Rural/Urban 2011 CP Population

in 2015

Projected

Population

in 2020

Present Water

Requirement

(2015)

Annual Water

Requirement

in 2020

Vallabhipur Rural 64340 69487 76436 2.54 2.79

Urban 15852 17120 18832 0.87 0.96

Umrala Rural 70719 76377 84014 2.79 3.07

Urban 15604 16852 18538 0.86 0.95

Bhavnagar Rural 144056 155580 171139 5.68 6.25

Urban 643263 694724 764196 35.50 39.05

Ghogha Rural 88769 95871 105458 3.50 3.85

Urban 12208 13185 14503 0.67 0.74

Sihor Rural 151662 163795 180174 5.98 6.58

Urban 60574 65420 71962 3.34 3.68

Gariadhar Rural 80938 87413 96154 3.19 3.51

49 | P a g e

Urban 33949 36665 40331 1.87 2.06

Palitana Rural 146069 157755 173530 5.76 6.33

Urban 64497 69657 76622 3.56 3.92

Talaja Rural 271056 292740 322015 10.69 11.75

Urban 54611 58980 64878 3.01 3.32

Mahuva Rural 308740 333439 366783 12.17 13.39

Urban 98519 106401 117041 5.44 5.98

Jesar Rural 84785 91568 100725 3.34 3.68

Urban 0 0 0 0.00 0.00

Source: District Statistical Office, Bhavnagar

It can be inferred from the table that considering the growth rate of population of the

district, the quantity of water required in 2020 for domestic consumption shall be

approximately 121.84 MCM which is 11.08MCM more than the present water

requirement.

4.2 Crop water Requirement

Crop water requirement for the blocks and district have been calculated based upon the

cropping pattern followed in the various blocks of the district. Cropping pattern under

irrigated and rainfed system is different in the district. Oilseeds and cotton based

cropping system is followed under unirrigated conditions in all the blocks. Under

irrigated conditions, in almost all the blocks vegetable based cropping system is

followed. However, under irrigated system, wheat, cotton and horticulture based

cropping systems are also being followed.

The crop wise water requirement has been taken based upon discussion with

Agriculture Universities and department officials as per practice prevailing in the State

which is as under:

Table 4.2 Crop wise Water Requirement

Season Crops MCM/Ha Season Crops MCM/

Ha

Season Crops MCM/H

a

kharif Paddy 0.005 Rabi WHEAT 0.0052 Horticulture Banana 0.025

JOWAR 0.0035 JOWAR 0.007 Fruits 0.012

BAJRI 0.0035 MAIZE 0.007 Vegetables 0.006167

50 | P a g e

MAIZE 0.0035 GRAM 0.003 Chilies 0.009

RAGI 0.002 RAPESEED &

MUSTARD

0.0035 Fennel 0.007

MUNG 0.0024 SUGARCANE 0.018 Cumin 0.0032

MATH 0.0024 ISABGUL 0.0032 Fenugreek 0.0059

UDID 0.0024 FENNEL 0.007 Other

Spices

0.0032

TUR 0.0024 TOBACCO 0.0063 Flower 0.006

GROUNDNUT 0.003 Summ

er

GROUNDNU

T

0.0075

CASTOR 0.005 BAJRA 0.0065

SESAMUM 0.002 PADDY 0.017

COTTON 0.005 MAIZE 0.0098

TOBACCO 0.0042 MUNG 0.007

GUAR SEED 0.0035 UDID 0.007

SOYABEAN 0.0024 SESAMUM 0.0035

Area under different crops has been discussed in Chapter 2 (Table 2.2). Taking into

account, the water requirement (Table 4.2), requirement of water for different crops

have been worked out. Existing water potential available (being utilized) has been

assumed as the water used in irrigated land.

Table 4.3: Crop Water Requirement in Million Cubic Meter

Block Area

sown

(Ha)

Irrigated

area (ha)

Crop

Water

Demand

Existing

Water

Potential

Water

Potential

to be

created

Bhavnagar 8183.80 8681.00 82.49 76.52 5.97

Gariyadhar 70961.50 87601.00 282.10 240.63 41.47

Ghogha 29512.80 42669.00 166.74 127.56 39.18

Mahuva 78850.30 138369.00 465.16 311.12 154.04

Palitana 29166.40 54052.00 178.27 113.19 65.08

Shihor 17263.60 17872.00 121.70 114.40 7.30

Talaja 61508.70 88531.00 332.05 261.72 70.34

51 | P a g e

Umrala 4241.60 4356.00 27.69 26.32 1.37

Vallbhipur 16711.00 32347.00 72.57 40.18 32.40

Total 316399.70 474478.00 1728.78 1311.63 417.15

*The data of Jesar taluka is included in Mahuva taluka

It is observed that there is a gap of 417.15 MCM in the district under crop water

requirement.

4.3 Livestock

The requirement of water for livestock of the district has been derived from the

Department of Animal Husbandry. The table below represents the animal wise water

requirement as well as total water requirement of the district for livestock.

The block wise water estimation for livestock is as follows;

Table 4.4: Livestock water demand (in MCM)

Block

Total

number of

livestock

(2015)

Present

water

demand

(MCM)

Water

Demand in

2020

(MCM)

Existing

water

potential

(MCM)*

Water

potential to

be created

(MCM)

VALLABHIPUR 36205 0.59 0.68 0.59 0.09

UMARALA 35706 0.59 0.68 0.59 0.09

BHAVNAGAR 114833 1.74 2.00 1.74 0.26

GHOGHA 89439 1.12 1.29 1.12 0.17

SHIHOR 105708 1.61 1.86 1.61 0.24

GARIYADHAR 49572 0.70 0.81 0.70 0.11

PALITANA 109037 1.55 1.79 1.55 0.23

TALAJA 226098 2.80 3.22 2.80 0.42

MAHUVA 1238509 3.65 4.20 3.65 0.55

JESAR 12853 0.16 0.19 0.16 0.02

Total 2017960 14.52 16.70 14.52 2.18

* it is assumed that present water requirement of animal is met from existing water

52 | P a g e

usage and hence existing potential is equal to existing demand.

Based on the projected water requirement for livestock in 2020, the gap has been

assessed. The total potential which has to be created for livestock in 2020 is 2.18MCM.

This has been assessed on the terms of the following:

Per capita daily water requirement for cows/buffaloes 60 litres, sheep/goats/pigs

6 litres and Poultry 0.3 liters.

For projecting the water demand of livestock, growth rate as deduced from

census has been considered during calculations, a growth rate of 3% per annum

growth has been assumed. It is assumed that present water requirement of

livestock is met from existing water usage and hence existing potential is equal to

existing demand.

4.4 Industrial Water Requirement

The current total industrial water demand for the district as per GIDC stands at 0.0026

MCM and is expected to increase to 0.0037 MCM by 2020

Table 4.5 Industrial water demand

Taluka Current

water

demand

In MCM Projected

Water

Demand

(2020)

In MCM

Vallabhipur 0.059 0.0000 0.084 0.0000

Umrala 0.0000 0.0000

Bhavnagar 20.767 0.0021 29.667 0.0030

Ghogha 0.0000 0.0000

Sihor 2.472 0.0002 3.53 0.0004

Gariadhar 0.0000 0.0000

Palitana 1.109 0.0001 1.585 0.0002

Talaja 0.0000 0.0000

Mahuva 1.443 0.0001 2.061 0.0002

Jesar 0.0000 0.0000

53 | P a g e

Total 25.791 0.0026 36.843 0.0037

4.5 Water Demand for Power Generation

The district is not having any thermal or nuclear power plant where water may be

consumed. Therefore, demand of water for power generation has been taken as nil.

4.6 Water demand

This section presents the total water demand of the district and has been calculated by

summing up all major sectors consuming water. The current water demand has been

indicated in Table 4.4 and the projected water demand has been depicted in Table 4.5.

Table 4.6: Present Water Demand of the district for various sectors (2015)

Blocks Demand from components (MCM) Total

Domestic Crop Livestock Industrial Power

Generation

Vallabhipur 3.41 158.05 0.59 0.0000 - 162.05

Umrala 3.65 27.69 0.59 0.0000 - 31.93

Bhavnagar 41.18 82.49 1.74 0.0021 - 125.41

Ghogha 4.17 171.77 1.12 0.0000 - 177.06

Sihor 9.32 121.70 1.61 0.0002 - 132.63

Gariadhar 5.06 173.25 0.70 0.0000 - 179.02

Palitana 9.32 233.07 1.55 0.0001 - 243.94

Talaja 13.70 393.50 2.80 0.0000 - 410.00

Mahuva 17.61 582.09 3.65 0.0001 - 603.34

Total 110.76 1943.60 14.52 0.0026 - 2068.89

*The data of Jesar taluka is included in Mahuva taluka

The present water demand of the district has been assessed at 2068.89 MCM annually,

with Mahuva being the block with maximum water requirement (603.34 MCM). Talaja

and Palitana blocks stand at 2nd and 3rd position with approximately 19.82% and

11.79% of total water required by district.

54 | P a g e

Table 4.7: Total Water Demand of the district for various sectors (Projected for 2020)

Blocks Projected Demand from components (MCM) Total

Domestic Crop Livestock Industrial Power

Generation

Vallabhipur 3.75 158.05 0.68 0.0000 - 162.47

Umrala 4.01 27.69 0.68 0.0000 - 32.38

Bhavnagar 45.30 82.49 2.00 0.0030 - 129.79

Ghogha 4.59 171.77 1.29 0.0000 - 177.65

Sihor 10.25 121.70 1.86 0.0004 - 133.81

Gariadhar 5.57 173.25 0.81 0.0000 - 179.63

Palitana 10.25 233.07 1.79 0.0002 - 245.11

Talaja 15.07 393.50 3.22 0.0000 - 411.79

Mahuva 19.37 582.09 4.20 0.0002 - 605.65

Total 121.84 1943.60 16.70 0.0037 - 2082.14

*The data of Jesar taluka is included in Mahuva taluka

During 2020, total water requirement of the district has been assessed at 2082.14 MCM.

The projected requirement of the blocks is almost in the similar proportion to present

requirement

4.7 Water Budget

A water budget reflects the relationship between input and output of water through a

region. The water balance in table 4.6 shows the existing water usage and the current

and potential water demand. Thus we have a direct comparison of supply of water and

the natural demand for water. It is possible to identify the gaps in the supply and

demand, thereby planning to invest in irrigation structures to support the blocks and

villages and fulfill the water needs.

55 | P a g e

Table 4.8: Water Budget (Volume in MCM)

Name of

Blocks

Existing water

availability/ Usage

(MCM)

Total

(MCM)

Water Demand

(MCM)

Water Gap (MCM)

Surface

Water

Ground

Water

Present Projected

(2020)

Present Projected

(2020)

Vallabhipur 206.60 40.3 246.90 162.05 162.47 -84.85 -84.42

Umrala 81.41 57.27 138.68 31.93 32.38 -106.75 -106.29

Bhavnagar 115.67 47.76 163.43 125.41 129.79 -38.03 -33.65

Ghogha 55.63 45.09 100.72 177.06 177.65 76.34 76.93

Sihor 42.60 87.65 130.25 132.63 133.81 2.38 3.56

Gariadhar 7.90 68.51 76.41 179.02 179.63 102.61 103.22

Palitana 76.31 89.52 165.83 243.94 245.11 78.11 79.28

Talaja 251.56 117.17 368.73 410.00 411.79 41.27 43.06

Mahuva 224.40 134.13 358.53 603.34 605.65 244.81 247.12

Total 1062.08 687.4 1749.48 2068.89 2082.14 319.41 332.67

*The data of Jesar taluka is included in Mahuva taluka

The total water gap for the district is currently 319.41 MCM and has been estimated at

332.67 MCM during 2020, i.e. the supply of water is insufficient to meet the current and

future demand of the district.

56 | P a g e

CHAPTER 5. STRATEGIC ACTION PLAN FOR IRRIGATION

IN DISTRICT UNDER PMKSY

5.1 Year wise total Plan of the district:

Total plan for four years works out to be Rs. 253124.02 lakh (Table5.1). Maximum share of Rs.

64063.28 lakh (25.31%) is for Mahuva block followed by Palitana with Rs. 54029.70 lakh (21.35%)

and Umrala with Rs.31506.26 lakh (12.45%).

Table 5.1: Summary of PMKSY plan District Bhavnagar, Gujarat. (in Rs. Lakh)

Block wise name of

Department 2016-17 2017-18 2018-19 2019-20 Total

Bhavnagar 3909.48 4007.91 1947.56 672.57 10537.52

ATMA 35.72 46.97 56.59 70.18 209.46

GGRC 291.72 218.79 218.79 218.79 948.08

GSLDC 79.60 79.60 79.60 79.60 318.40

GWRDC 20.00 20.00 20.00 20.00 80.00

SSNNL 3178.40 3178.40 1176.13 0.00 7532.92

State Irrigation

department

274.00 443.00 389.00 284.00 1390.00

GSWMA (MGNREGA) 30.05 21.16 7.45 58.66

Gariyadhar 22818.42 780.99 624.01 507.76 24731.18

GGRC 416.54 312.40 312.40 312.40 1353.74

GSLDC 70.36 70.36 70.36 70.36 281.44

State Irrigation

department

22057.50 110.00 125.00 125.00 22417.50

GSWMA (PMKSY

Watershed)*

274.03 288.23 116.24 678.50

Ghogha 747.28 1025.77 753.77 1065.77 3592.59

GGRC 486.04 364.53 364.53 364.53 1579.63

GSLDC 71.24 71.24 71.24 71.24 284.96

State Irrigation 190.00 590.00 318.00 630.00 1728.00

57 | P a g e

department

Jesar 297.50 10955.45 10850.45 3955.45 26058.86

GGRC 123.80 92.85 92.85 92.85 402.36

GSLDC 67.60 67.60 67.60 67.60 270.40

State Irrigation

department

106.10 10795.00 10690.00 3795.00 25386.10

Mahuva 3150.30 40534.48 14639.98 5738.53 64063.28

GGRC 1466.73 1100.05 1100.05 1100.05 4766.87

GSLDC 78.48 78.48 78.48 78.48 313.92

GWRDC 20.00 20.00 20.00 20.00 80.00

State Irrigation

department

584.60 38864.00 13308.00 4540.00 57296.60

GSWMA (PMKSY

Watershed)*

1000.49 471.95 133.45 1605.89

Palitana 1693.57 30797.10 15260.17 6278.86 54029.70

GGRC 499.68 374.76 374.76 374.76 1623.96

GSLDC 72.36 72.36 72.36 72.36 289.44

GWRDC 8.50 8.50 8.50 8.50 34.00

State Irrigation

department

441.10 29984.00 14633.00 5622.00 50680.10

GSWMA (PMKSY

Watershed)*

671.93 357.48 171.55 201.24 1402.20

Shihor 1738.77 933.03 896.71 921.71 4490.23

GGRC 554.66 415.99 415.99 415.99 1802.64

GSLDC 80.72 80.72 80.72 80.72 322.88

State Irrigation

department

198.62 198.62 400.00 425.00 1222.24

GSWMA (PMKSY

Watershed)*

904.77 237.70 1142.46

Talaja 2516.14 2042.47 2964.47 2829.47 10352.54

GGRC 788.99 591.75 591.75 591.75 2564.23

GSLDC 68.72 68.72 68.72 68.72 274.88

58 | P a g e

GWRDC 37.00 37.00 37.00 37.00 148.00

State Irrigation

department

1198.86 1345.00 2267.00 2132.00 6942.86

GSWMA (PMKSY

Watershed)*

422.57 422.57

Umrala 2952.38 16799.30 8431.12 3323.45 31506.26

GGRC 334.79 251.09 251.09 251.09 1088.08

GSLDC 77.36 77.36 77.36 77.36 309.44

SSNNL 1093.01 1093.01 612.67 0.00 2798.69

State Irrigation

department

680.00 15095.00 7490.00 2995.00 26260.00

GSWMA (PMKSY

Watershed)*

767.22 282.84 1050.05

Vallbhipur 9010.30 9006.17 5319.89 425.49 23761.86

GGRC 316.49 237.37 237.37 237.37 1028.61

GSLDC 68.12 68.12 68.12 68.12 272.48

SSNNL 8580.68 8580.68 4894.40 0.00 22055.77

State Irrigation

department

45.00 120.00 120.00 120.00 405.00

Grand Total 48834.14 116882.67 61688.14 25719.07 253124.02

*GSWMA in Bhavnagar Taluka has only component of MGNREGA, which is the district total displayed in

the block for the purpose of calculation. In all other blocks amount of PMKSY Watershed amount is

considered adding the district amount of other components propotionatly.

5.2 Department wise plan

Analysis of PMKSY plan (Table5.2) for the period from 2016-17 to 2019-20 indicates that State

Irrigation department has the maximum share of Rs 193728.40 lakh (76.53%).

Table 5.2: Department-wise plan

Departments 2016-17 2017-18 2018-19 2019-20 Total

ATMA 35.72 46.97 56.59 70.18 209.46

GGRC 5279.45 3959.59 3959.59 3959.59 17158.20

GSLDC 734.56 734.56 734.56 734.56 2938.24

59 | P a g e

GWRDC 85.50 85.50 85.50 85.50 342.00

SSNNL 12852.09 12852.09 6683.20 0.00 32387.38

State Irrigation

department

25775.78 97544.62 49740.00 20668.00 193728.40

GSWMA* 4071.05 1659.35 428.70 201.24 6360.34

Grand Total 48834.14 116882.67 61688.14 25719.07 253124.02

*GSWMA is the total of PMKSY Watershed and Convergence of MGNREGA.

5.3 Component wise plan

As discussed above regarding various components of PMKSY, the plan is prepared accordingly.

Table 5.3 shows component wise plan for 4 years starting from 2016-17 to 2019-20. The highest

allocation of funds is proposed for Accelerated Irrigation Benefits Programme (AIBP)

componenti.e. Rs. 196188.18 lakh, which is to be executed mainly by Sardar Sarovar Narmada

Nigam Ltd. (SSNNL) and state irrigation departments. Hark het ko pani has the second highest

allocation with Rs. 33105.84 lakh (13.08%). Per drop more crop component of Rs.17260.20 lakh

(6.82%) will be executed by GGRC. This component has one sub components namely micro

irrigation through Drip and Sprinkler. Total Rs.209.46 lakh has been proposed for extension and

training purpose, which shall be undertaken by ATMA.

Table 5.3: Component wise plan

PMKSY component Amount (Rs. In lakh)

2016-17 2017-18 2018-19 2019-20 Total

AIBP 30686.67 101229.51 46134.00 18138.00 196188.18

HAR Khet Ko Pani 8735.76 9961.76 11083.76 3324.56 33105.84

Per Drop more crop 5304.95 3985.09 3985.09 3985.09 17260.20

PMKSY-Watershed Component 4041.00 1638.19 421.25 201.24 6301.68

Convergence with MGNREGA 30.05 21.16 7.45 - 58.66

Training 35.72 46.97 56.59 70.18 209.46

Grand Total 48834.14 116882.67 61688.14 25719.07 253124.02

PMKSY-Watershed Component (erstwhile named as Integrated Watershed Management

Programme) is one of the flagship program of Govt. of India. The main objectives of this is to

restore the ecological balance by harnessing, conserving and developing degraded natural

60 | P a g e

resources such as soil, vegetative cover and water. Gujarat is one of the largest States in context of

land area treatment under PMKSY-Watershed project. The important activities carried out under

this projects are Soil moisture conservation, Water harvesting, Vegetative cover and Plantation,

Agricultural production and Productivity improvement, Dairy development, Agro processing,

Livelihood and Income Generating Activities etc. In Gujarat PMKSY-Watershed component is

implemented through a State Level Nodal Agency constituted as Gujarat State Watershed

Management Agency (GSWMA), an autonomous society supported under the Rural Development

Department (RDD) of Government of Gujarat. GSWMA has vision of “Enhancing the quality of

rural population through Sustainable, Equitable and Participatory Natural resources Management”

and also has Mission of “Creating sustainable rural livelihoods through scientific and Integrated

Watershed Development Approach”. GSWMA works in all the 33 districts of Gujarat. GSWMA

planned to cover all the micro-watersheds (at village level) of the state in the next 18 years. Thus it

will cover all the talukas of the state. Total 610 no. of PMKSY-Watershed Component projects

under six batches covering 31.04 lakh hectors of land are currently under implementation.

GSWMA has its own structural arrangements (GSWMA, District Watershed Development Unit,

PIA, and Watershed Committee) from state to village level for implementation of program and has

system of internal monitoring of project activities through different means. GSWMA has its own

web based monitoring system as Soil Water Resource Management System (SWaRSys). The said

system is online and helps not only for the monitoring/documentation of all the main project

activities but also facilitates to collect and collate monthly and quarterly data from District level

offices. For preparation of DIP, the watershed component information is collected from various

levels and incorporated in this document for the years 2016-20.

However all the stakeholders need to have coordination among themselves to have the maximum

irrigation efficiency and to avoid duplicity.

5.4 Block wise Plan

There are 10 blocks in Bhavnagar district. Total PMKSY plan for four years is Rs. 253124.02 lakh.

Block wise year wise plan is given in Table 5.3. Fig. 5.1 shows the share of blocks in the plan.

Table 5.4: Block wise year wise PMKSY Plan of Bhavnagar District

Name of Block 2016-17 2017-18 2018-19 2019-20 Total

61 | P a g e

Bhavnagar 3909.48 4007.91 1947.56 672.57 10537.52

Gariyadhar 22818.42 780.99 624.01 507.76 24731.18

Ghogha 747.28 1025.77 753.77 1065.77 3592.59

Jesar 297.50 10955.45 10850.45 3955.45 26058.86

Mahuva 3150.30 40534.48 14639.98 5738.53 64063.28

Palitana 1693.57 30797.10 15260.17 6278.86 54029.70

Shihor 1738.77 933.03 896.71 921.71 4490.23

Talaja 2516.14 2042.47 2964.47 2829.47 10352.54

Umrala 2952.38 16799.30 8431.12 3323.45 31506.26

Vallbhipur 9010.30 9006.17 5319.89 425.49 23761.86

Grand Total 48834.14 116882.67 61688.14 25719.07 253124.02

Figure 5.1: Block wise share in PMKSY Plan of Bhavnagar District

5.5 Additional area under irrigation

One of the major objective of PMKSY is to bring additional area under irrigation and in the district

of Bhavnagar, the plan for four year plans to bring an additional 69260.01 ha under irrigation. The

blockwise distribution is provided in table 5.5. Vallbhipur taluka has the highest area planned to be

brought under irrigation by this plan (37527.08 ha), while Jesar has the least (706.08 ha)

Bhavnagar4%

Gariyadhar10%

Ghogha2%

Jesar10%

Mahuva25%

Palitana21%

Shihor2%

Talaja4%

Umrala13%

Vallbhipur9%

62 | P a g e

Table 5.5: Block wise year wise plan for bringing additional area under irrigation in Bhavnagar

District

Taluka Total additional area

Talaja 5933.03 Palitana 1633.86 Mahuva 2077.07 Bhavnagar 10519.32 Shihor 1349.09 Umarala 6829.72 Gariyadhar 943.00 Jesar 706.08 Vallabhipur 37527.08 Ghogha 1741.76 Grand Total 69260.01

The table 5.5 represents the additional area planned to be brought under irrigation by the

interventions of State Irrigation Department, Panchayat irrigation Department, GWSMA, GWRDC

and GLDC. The per drop more crop component of the programme plans to bring additional area

under micro irrigation, which is mainly undertaken in Gujarat by Gujarat Green Revolution

Company (GGRC). Due to the intervention of GGRC, there is a potential saving of 28% to 48% of

water requirement for crops in the district. The table below provides the additional area planned to

be brought under micro irrigation

Table 5.6: Block wise year wise plan for bringing additional area under micro irrigation in

bhavnagar District

Taluka 2016-17 2017-18 2018-19 2019-20 Total

Bhavnagar 651.16 488.37 488.37 488.37 2116.26

Gariyadhar 929.77 697.33 697.33 697.33 3021.74

Ghogha 1084.91 813.68 813.68 813.68 3525.96

Jesar 276.34 207.26 207.26 207.26 898.12

Mahuva 3273.95 2455.46 2455.46 2455.46 10640.33

Palitana 1115.36 836.52 836.52 836.52 3624.91

Shihor 1238.08 928.56 928.56 928.56 4023.76

Talaja 1761.15 1320.86 1320.86 1320.86 5723.73

Umrala 747.31 560.48 560.48 560.48 2428.74

Vallbhipur 706.46 529.85 529.85 529.85 2296.00

63 | P a g e

Grand

Total

11784.48 8838.36 8838.36 8838.36 38299.56

5.6 Employment

Another important outcome expected from PMKSY is the increase in employment in the district.

The potential employment generation is calculated based on an average estimation of 20% of total

fund of all the departments except GSWMA shall be used to hire labour while 40% of total fund for

GSWMA is used for hiring labour. The labour rate in Gujarat is considered to be Rs. 178 per man

day. Thereby the following table (Table 5.6) is derived.

Table 5.7: Block wise year wise employment generation potential in Bhavnagar District (in man

days)

Taluka 2016-17 2017-18 2018-19 2019-20 Total

Bhavnagar 439011 459898 205754 47411 1152074

Gariyadhar 2768773 57916 38513 24146 2889347

Ghogha 32288 81726 48108 86670 248793

Jesar 21469 1342569 1329591 477400 3171028

Mahuva 208082 4873918 1673475 573295 7328770

Palitana 147560 3760064 1839770 729720 6477114

Shihor 146350 63903 59415 62505 332173

Talaja 213468 179302 293258 276572 962600

Umrala 323522 2045284 1011015 379730 3759550

Vallbhipur 1074515 1083785 628177 23251 2809727

Grand

Total

5375036 13948365 7127074 2680700 29131176

It can be observed that highest employment potential is in Mahuva (25.16%), while Ghogha has the

least (0.85%). The PMKSY interventions are also likely to generate an additional income of Rs.

59395.82 lakh to the farmers of the district. This is based on the assumption of at least 60% of

potential utilised and Rs. 42,000 per ha incremental income from rainfed to irrigated farming and

60695 jobs on recurring basis (in 141419 ha additional area brought under irrigation at the rate of

2.33 ha average land holding by farmers).

64 | P a g e

5.7 Monitoring and Evaluation

The Strategic Action Plan of PMKSY will be monitored by the respective departments through the

regular reporting system and component wise progress will be monitored by the District Level

Irrigation Committee. Further, the activities, outputs and outcomes will be reported in web based

MIS of PMKSY for review at state and national level. Some of the key indicators that will be used to

monitor and evaluate the progress of PMKSY include:

Annual irrigation water supply per unit irrigated area measured as the ratio of total volume

of irrigation water supplied at intake divided by total area irrigated in all seasons

Potential created and utilized measured as the ratio of total potential utilized (measured

crop area) to irrigation potential created

Output (agricultural production) per unit irrigated area measured as the ratio of total value

of agriculture production divided by the total irrigated area.

Output (agricultural production) per unit irrigation water supply measured as the ratio of

total value of agriculture production divided by the total volume of irrigated water supplied.

Total Operations & Maintenance (O&M) cost per unit irrigated area measured as the total

Management, Operation and Maintenance (MOM) costs for the system divided by total area

irrigated (potential utilized).

Total Operations & Maintenance (O&M) cost per unit volume of water supplied measured as

total Management, Operation and Maintenance (MOM) costs for the system divided Total

volume of water supplied (all uses)

Equity performance measured as actual area irrigated in head, middle and tail divided by

Command area in head, middle and tail.

GSWMA has its own structural arrangements (GSWMA, District Watershed Development Unit,

PIA, and Watershed Committee) from state to village level for implementation of program and has

system of internal monitoring of project activities through different means. GSWMA has its own

web based monitoring system as Soil Water Resource Management System (SWaRSys). The said

system is online and helps not only for the monitoring/documentation of all the main project

activities but also facilitates to collect and collate monthly and quarterly data from District level

offices. For preparation of DIP, the watershed component information is collected from various

levels and incorporated in this document for the years 2016-20.

65 | P a g e

5.8 Suggestions

For successful implementation of PMKSY plan it is suggested that:

All the stakeholders should convene meeting of Panchayat samities and then finalise the

village plan and prepare DPR.

There should not be duplicity of project.

The Department should supplement each other so that the maximum irrigation

efficiency is achieved.

Agriculture and Horticulture Department should take micro irrigation projects in the

command of minor irrigation projects completed or likely to be completed in near future.

All the irrigation projects should have a component of water conveyance so that the each

drop of water is judiciously utilized.

Where ever feasible solar pump sets should be installed.

All the structures planned should be geo tagged and marked on map, so that social

monitoring of the projects can be conducted. This will also avoid the duplicity.

Priority should be given to projects minimize the gap in potential created and potential

utilized.

Execution of the scheme should be expeditiously completed.

There should be smooth fund flow to timely complete the project.

***

66 | P a g e

Strategic Action Plan

Concerned

Ministry/

Department

Component Activity Total Number/

Capacity

(M.Cum)

Command

Area/

Irrigation

Potential

(Ha)

Period of

Implementation

(5/7 yrs)

Estimated

Cost ( Rs.

in Lacs)

MoWR AIBP Major Irrigation 1/308.68 34,473.00 4 3,374.00

MoWR Medium Irrigation 6/117.36 17,515.84 4 3,135.00

MoWR Minor Irrigation 71/1690.64 24,241.00 4 4,636.40

MoWR Sauni Yojana 0.00 4 1,72,705.00

MoWR Kalpsar 0.00 4 0.00

MoWR SSNNL major

irrigation

38 No/ 6.18 cum 18,161.00 2 12,337.78

MoWR Har khet ko

pani

Lift Irrigation 4 0.00

MoWR Ground Water

Development/Check

dam/Tank

6496/224.37 1,13,111.00 4 8,728.00

MoWR RRR of Water Bodies 6/31.36 4 1,150.00

MoWR SSNNL UGPL 717 No/17.09 cum 50,124.00 3 20,049.60

MoWR New exploratory

tubewells by GWRDC

2.4 36 4 102

MoWR Recharge Tubewell by

GWRDC

24 120 4 240

67 | P a g e

MoWR GLDC Farm pond 852 1226.88 4 954.24

MoWR GLDC Sim pond 184 772.8 4 920

MoWR GLDC Village pond 104 2995.2 4 728

MoWR GLDC WHS 300 1800 4 336

MoWR Per drop

more crop

(Micro

Irrigation)

DPAP Drip 14362 22980 4 15442

MoWR DPAP Sprinkler 9575 15320 4 1716

DoLR-MoRD PMKSY

Watershed

Existing/Old Water

Harvesting Structure

Maintance

(Renovation &

Repair)

245 607 4 386

DoLR-MoRD Ground Water

Recharging

Structures

2488 0 4 547

DoLR-MoRD Administration cost 0 0 4 389

DoLR-MoRD AGRICULTURE

ACTIVITIES

2573 0 4 831

DoLR-MoRD AGRO PROCESSING

ACTIVITIES

54 0 4 44

DoLR-MoRD Animal Husbandry 717 0 4 420

DoLR-MoRD Capasity building,

Monitoring &

0 0 4 499

68 | P a g e

Evaluation

DoLR-MoRD Cosolidation Phase 0 0 4 311

DoLR-MoRD EPA 394 5 4 25

DoLR-MoRD Establishing linkages 45 0 4 44

DoLR-MoRD Land development 582297 0 4 691

DoLR-MoRD Local traditional

handicraft

17 0 4 9

DoLR-MoRD Minor Activities 157 0 4 82

DoLR-MoRD Non-conventional

Energy Sources

59 0 4 12

DoLR-MoRD Soil and moisture

conservation

140907 236 4 937

DoLR-MoRD Water harvesting

structure

927 1357 4 1074

DoRD-MoRD Convergence

with

MGNREGA

Causeway cum

checkdam

4 59

Irrigation

Scheme of State

Agriculture

Capacity

Building by

ATMA

Training Programmes 2606 Trainings 30080

Trainees

4 209.46

69 | P a g e

YEAR WISE SUMMARY OF FUNDS FOR DIFFERENT BLOCKS AND ACTIVITIES

Name of the

blocks / Sub

district

Concerned

Ministry/

Department

Component Activity 2016-17 2017-18 2018-19 2019-20

Umrala SSNNL AIBP Major Irrigation 480.34 480.34 0.00 0.00

Bhavnagar SSNNL AIBP Major Irrigation 2002.26 2002.26 0.00 0.00

Vallbhipur SSNNL AIBP Major Irrigation 3686.28 3686.28 0.00 0.00

Umrala SSNNL HAR Khet Ko

Pani

UGPL 612.67 612.67 612.67 0.00

Bhavnagar SSNNL HAR Khet Ko

Pani

UGPL 1176.13 1176.13 1176.13 0.00

Vallbhipur SSNNL HAR Khet Ko

Pani

UGPL 4894.40 4894.40 4894.40 0.00

Talaja State

Irrigation

department

AIBP Major Irrigation 666.00 575.00 804.00 877.00

Talaja State

Irrigation

department

AIBP Medium Irrigation 0.00 0.00 0.00 0.00

Talaja State

Irrigation

department

AIBP Minor Irrigation 169.86 270.00 252.00 140.00

Talaja State AIBP Sauni Yojana 0.00 0.00 145.00 0.00

70 | P a g e

Irrigation

department

Talaja State

Irrigation

department

AIBP Kalpsar

Talaja State

Irrigation

department

Har khet ko

pani

Lift Irrigation

Talaja State

Irrigation

department

Har khet ko

pani

Ground Water

Development/Check

dam/Tank

273.00 400.00 941.00 1095.00

Talaja State

Irrigation

department

Har khet ko

pani

RRR of Water

Bodies

90.00 100.00 125.00 20.00

Talaja State

Irrigation

department

Har khet ko

pani

Construction of

Field Channels

0.00 0.00 0.00 0.00

Talaja State

Irrigation

department

Har khet ko

pani

Lined field Channel 0.00 0.00 0.00 0.00

Talaja State

Irrigation

department

Har khet ko

pani

UnLined Channel 0.00 0.00 0.00 0.00

71 | P a g e

Palitana State

Irrigation

department

AIBP Major Irrigation 0.00 9.00 9.00 8.00

Palitana State

Irrigation

department

AIBP Medium Irrigation 50.00 45.00 35.00 25.00

Palitana State

Irrigation

department

AIBP Minor Irrigation 126.10 100.00 99.00 694.00

Palitana State

Irrigation

department

AIBP Sauni Yojana 0.00 29600.00 14300.00 4800.00

Palitana State

Irrigation

department

AIBP Kalpsar

Palitana State

Irrigation

department

Har khet ko

pani

Lift Irrigation

Palitana State

Irrigation

department

Har khet ko

pani

Ground Water

Development/Check

dam/Tank

95.00 95.00 90.00 95.00

Palitana State

Irrigation

department

Har khet ko

pani

RRR of Water

Bodies

170.00 135.00 100.00 0.00

72 | P a g e

Palitana State

Irrigation

department

Har khet ko

pani

Construction of

Field Channels

0.00 0.00 0.00 0.00

Palitana State

Irrigation

department

Har khet ko

pani

Lined field Channel 0.00 0.00 0.00 0.00

Palitana State

Irrigation

department

Har khet ko

pani

UnLined Channel 0.00 0.00 0.00 0.00

Palitana State

Irrigation

department

Har khet ko

pani

Micro Irrigation 0.00 0.00 0.00 0.00

Mahuva State

Irrigation

department

AIBP Major Irrigation 20.00 25.00 25.00 25.00

Mahuva State

Irrigation

department

AIBP Medium Irrigation 0.00 400.00 300.00 300.00

Mahuva State

Irrigation

department

AIBP Minor Irrigation 304.60 100.00 163.00 170.00

Mahuva State

Irrigation

department

AIBP Sauni Yojana 0.00 37650.00 11300.00 3900.00

73 | P a g e

Mahuva State

Irrigation

department

AIBP Kalpsar

Mahuva State

Irrigation

department

Har khet ko

pani

Lift Irrigation

Mahuva State

Irrigation

department

Har khet ko

pani

Ground Water

Development/Check

dam/Tank

230.00 689.00 1520.00 145.00

Mahuva State

Irrigation

department

Har khet ko

pani

RRR of Water

Bodies

30.00 0.00 0.00 0.00

Mahuva State

Irrigation

department

Har khet ko

pani

Construction of

Field Channels

0.00 0.00 0.00 0.00

Mahuva State

Irrigation

department

Har khet ko

pani

Lined field Channel 0.00 0.00 0.00 0.00

Mahuva State

Irrigation

department

Har khet ko

pani

UnLined Channel 0.00 0.00 0.00 0.00

Mahuva State

Irrigation

department

Har khet ko

pani

Micro Irrigation 0.00 0.00 0.00 0.00

74 | P a g e

Bhavnagar State

Irrigation

department

AIBP Major Irrigation 67.00 78.00 79.00 79.00

Bhavnagar State

Irrigation

department

AIBP Medium Irrigation 0.00 0.00 0.00 0.00

Bhavnagar State

Irrigation

department

AIBP Minor Irrigation 47.00 140.00 130.00 0.00

Bhavnagar State

Irrigation

department

AIBP Sauni Yojana 0.00 0.00 0.00 0.00

Bhavnagar State

Irrigation

department

AIBP Kalpsar

Bhavnagar State

Irrigation

department

Har khet ko

pani

Lift Irrigation

Bhavnagar State

Irrigation

department

Har khet ko

pani

Ground Water

Development/Check

dam/Tank

110.00 95.00 90.00 95.00

Bhavnagar State

Irrigation

department

Har khet ko

pani

RRR of Water

Bodies

50.00 130.00 90.00 110.00

75 | P a g e

Bhavnagar State

Irrigation

department

Har khet ko

pani

Construction of

Field Channels

0.00 0.00 0.00 0.00

Bhavnagar State

Irrigation

department

Har khet ko

pani

Lined field Channel 0.00 0.00 0.00 0.00

Bhavnagar State

Irrigation

department

Har khet ko

pani

Micro Irrigation 0.00 0.00 0.00 0.00

Shihor State

Irrigation

department

AIBP Major Irrigation 0.00 0.00 0.00 0.00

Shihor State

Irrigation

department

AIBP Medium Irrigation 0.00 0.00 0.00 0.00

Shihor State

Irrigation

department

AIBP Minor Irrigation 198.62 198.62 305.00 325.00

Shihor State

Irrigation

department

AIBP Sauni Yojana 0.00 0.00 5.00 5.00

Shihor State

Irrigation

department

AIBP Kalpsar

76 | P a g e

Shihor State

Irrigation

department

Har khet ko

pani

Lift Irrigation

Shihor State

Irrigation

department

Har khet ko

pani

Ground Water

Development/Check

dam/Tank

0.00 0.00 90.00 95.00

Shihor State

Irrigation

department

Har khet ko

pani

RRR of Water

Bodies

0.00 0.00 0.00 0.00

Shihor State

Irrigation

department

Har khet ko

pani

Construction of

Field Channels

0.00 0.00 0.00 0.00

Shihor State

Irrigation

department

Har khet ko

pani

UnLined Channel 0.00 0.00 0.00 0.00

Shihor State

Irrigation

department

Har khet ko

pani

Micro Irrigation 0.00 0.00 0.00 0.00

Umrala State

Irrigation

department

AIBP Major Irrigation 0.00 0.00 0.00 0.00

Umrala State

Irrigation

department

AIBP Medium Irrigation 680.00 400.00 400.00 400.00

77 | P a g e

Umrala State

Irrigation

department

AIBP Minor Irrigation 0.00 0.00 0.00 0.00

Umrala State

Irrigation

department

AIBP Sauni Yojana 0.00 14600.00 7000.00 2500.00

Umrala State

Irrigation

department

AIBP Kalpsar

Umrala State

Irrigation

department

Har khet ko

pani

Lift Irrigation

Umrala State

Irrigation

department

Har khet ko

pani

Ground Water

Development/Check

dam/Tank

0.00 95.00 90.00 95.00

Umrala State

Irrigation

department

Har khet ko

pani

RRR of Water

Bodies

0.00 0.00 0.00 0.00

Umrala State

Irrigation

department

Har khet ko

pani

Construction of

Field Channels

0.00 0.00 0.00 0.00

Umrala State

Irrigation

department

Har khet ko

pani

Lined field Channel 0.00 0.00 0.00 0.00

78 | P a g e

Umrala State

Irrigation

department

Har khet ko

pani

UnLined Channel 0.00 0.00 0.00 0.00

Umrala State

Irrigation

department

Har khet ko

pani

Micro Irrigation 0.00 0.00 0.00 0.00

Gariyadhar State

Irrigation

department

AIBP Major Irrigation 0.00 0.00 0.00 0.00

Gariyadhar State

Irrigation

department

AIBP Medium Irrigation 0.00 0.00 0.00 0.00

Gariyadhar State

Irrigation

department

AIBP Minor Irrigation 57.50 15.00 30.00 30.00

Gariyadhar State

Irrigation

department

AIBP Sauni Yojana 22000.00 0.00 0.00 0.00

Gariyadhar State

Irrigation

department

AIBP Kalpsar

Gariyadhar State

Irrigation

department

Har khet ko

pani

Lift Irrigation

79 | P a g e

Gariyadhar State

Irrigation

department

Har khet ko

pani

Ground Water

Development/Check

dam/Tank

0.00 95.00 95.00 95.00

Gariyadhar State

Irrigation

department

Har khet ko

pani

RRR of Water

Bodies

0.00 0.00 0.00 0.00

Gariyadhar State

Irrigation

department

Har khet ko

pani

Construction of

Field Channels

0.00 0.00 0.00 0.00

Gariyadhar State

Irrigation

department

Har khet ko

pani

Lined field Channel 0.00 0.00 0.00 0.00

Gariyadhar State

Irrigation

department

Har khet ko

pani

UnLined Channel 0.00 0.00 0.00 0.00

Gariyadhar State

Irrigation

department

Har khet ko

pani

Micro Irrigation 0.00 0.00 0.00 0.00

Jesar State

Irrigation

department

AIBP Major Irrigation 0.00 0.00 0.00 0.00

Jesar State

Irrigation

department

AIBP Medium Irrigation 0.00 0.00 0.00

80 | P a g e

Jesar State

Irrigation

department

AIBP Minor Irrigation 106.10 100.00 0.00 0.00

Jesar State

Irrigation

department

AIBP Sauni Yojana 0.00 10600.00 10600.00 3700.00

Jesar State

Irrigation

department

AIBP Kalpsar

Jesar State

Irrigation

department

Har khet ko

pani

Lift Irrigation

Jesar State

Irrigation

department

Har khet ko

pani

Ground Water

Development/Check

dam/Tank

0.00 95.00 90.00 95.00

Jesar State

Irrigation

department

Har khet ko

pani

RRR of Water

Bodies

0.00 0.00 0.00 0.00

Jesar State

Irrigation

department

Har khet ko

pani

Construction of

Field Channels

0.00 0.00 0.00 0.00

Jesar State

Irrigation

department

Har khet ko

pani

UnLined Channel 0.00 0.00 0.00 0.00

81 | P a g e

Jesar State

Irrigation

department

Har khet ko

pani

Micro Irrigation 0.00 0.00 0.00 0.00

Vallbhipur State

Irrigation

department

AIBP Major Irrigation 0.00 0.00 0.00 0.00

Vallbhipur State

Irrigation

department

AIBP Medium Irrigation 25.00 25.00 25.00 25.00

Vallbhipur State

Irrigation

department

AIBP Minor Irrigation 0.00 0.00 0.00 0.00

Vallbhipur State

Irrigation

department

AIBP Sauni Yojana 0.00 0.00 0.00 0.00

Vallbhipur State

Irrigation

department

AIBP Kalpsar

Vallbhipur State

Irrigation

department

Har khet ko

pani

Lift Irrigation

Vallbhipur State

Irrigation

department

Har khet ko

pani

Ground Water

Development/Check

dam/Tank

20.00 95.00 95.00 95.00

82 | P a g e

Vallbhipur State

Irrigation

department

Har khet ko

pani

RRR of Water

Bodies

0.00 0.00 0.00 0.00

Vallbhipur State

Irrigation

department

Har khet ko

pani

Construction of

Field Channels

0.00 0.00 0.00 0.00

Vallbhipur State

Irrigation

department

Har khet ko

pani

Lined field Channel 0.00 0.00 0.00 0.00

Vallbhipur State

Irrigation

department

Har khet ko

pani

UnLined Channel 0.00 0.00 0.00 0.00

Vallbhipur State

Irrigation

department

Har khet ko

pani

Micro Irrigation 0.00 0.00 0.00 0.00

Ghogha State

Irrigation

department

AIBP Major Irrigation 0.00 10.00 8.00 10.00

Ghogha State

Irrigation

department

AIBP Medium Irrigation 0.00 0.00 0.00 0.00

Ghogha State

Irrigation

department

AIBP Minor Irrigation 0.00 120.00 120.00 125.00

83 | P a g e

Ghogha State

Irrigation

department

AIBP Sauni Yojana 0.00 0.00 0.00 0.00

Ghogha State

Irrigation

department

AIBP Kalpsar

Ghogha State

Irrigation

department

Har khet ko

pani

Lift Irrigation

Ghogha State

Irrigation

department

Har khet ko

pani

Ground Water

Development/Check

dam/Tank

190.00 460.00 190.00 495.00

Ghogha State

Irrigation

department

Har khet ko

pani

RRR of Water

Bodies

0.00 0.00 0.00 0.00

Ghogha State

Irrigation

department

Har khet ko

pani

Construction of

Field Channels

0.00 0.00 0.00 0.00

Ghogha State

Irrigation

department

Har khet ko

pani

Lined field Channel 0.00 0.00 0.00 0.00

Ghogha State

Irrigation

department

Har khet ko

pani

UnLined Channel 0.00 0.00 0.00 0.00

84 | P a g e

Ghogha State

Irrigation

department

Har khet ko

pani

Micro Irrigation 0.00 0.00 0.00 0.00

Umrala GSLDC Har Khet ko

Pani

Farm pond 24.64 24.64 24.64 24.64

Umrala GSLDC Har Khet ko

Pani

Sim pond 25.00 25.00 25.00 25.00

Umrala GSLDC Har Khet ko

Pani

Village pond 21.00 21.00 21.00 21.00

Umrala GSLDC Har Khet ko

Pani

WHS 6.72 6.72 6.72 6.72

Gariyadhar GSLDC Har Khet ko

Pani

Farm pond 22.40 22.40 22.40 22.40

Gariyadhar GSLDC Har Khet ko

Pani

Sim pond 25.00 25.00 25.00 25.00

Gariyadhar GSLDC Har Khet ko

Pani

Village pond 14.00 14.00 14.00 14.00

Gariyadhar GSLDC Har Khet ko

Pani

WHS 8.96 8.96 8.96 8.96

Ghogha GSLDC Har Khet ko

Pani

Farm pond 23.52 23.52 23.52 23.52

Ghogha GSLDC Har Khet ko

Pani

Sim pond 20.00 20.00 20.00 20.00

Ghogha GSLDC Har Khet ko Village pond 21.00 21.00 21.00 21.00

85 | P a g e

Pani

Ghogha GSLDC Har Khet ko

Pani

WHS 6.72 6.72 6.72 6.72

Jesar GSLDC Har Khet ko

Pani

Farm pond 25.76 25.76 25.76 25.76

Jesar GSLDC Har Khet ko

Pani

Sim pond 20.00 20.00 20.00 20.00

Jesar GSLDC Har Khet ko

Pani

Village pond 14.00 14.00 14.00 14.00

Jesar GSLDC Har Khet ko

Pani

WHS 7.84 7.84 7.84 7.84

Talaja GSLDC Har Khet ko

Pani

Farm pond 25.76 25.76 25.76 25.76

Talaja GSLDC Har Khet ko

Pani

Sim pond 20.00 20.00 20.00 20.00

Talaja GSLDC Har Khet ko

Pani

Village pond 14.00 14.00 14.00 14.00

Talaja GSLDC Har Khet ko

Pani

WHS 8.96 8.96 8.96 8.96

Palitana GSLDC Har Khet ko

Pani

Farm pond 22.40 22.40 22.40 22.40

Palitana GSLDC Har Khet ko

Pani

Sim pond 20.00 20.00 20.00 20.00

Palitana GSLDC Har Khet ko Village pond 21.00 21.00 21.00 21.00

86 | P a g e

Pani

Palitana GSLDC Har Khet ko

Pani

WHS 8.96 8.96 8.96 8.96

Bhavnagar GSLDC Har Khet ko

Pani

Farm pond 24.64 24.64 24.64 24.64

Bhavnagar GSLDC Har Khet ko

Pani

Sim pond 25.00 25.00 25.00 25.00

Bhavnagar GSLDC Har Khet ko

Pani

Village pond 21.00 21.00 21.00 21.00

Bhavnagar GSLDC Har Khet ko

Pani

WHS 8.96 8.96 8.96 8.96

Mahuva GSLDC Har Khet ko

Pani

Farm pond 23.52 23.52 23.52 23.52

Mahuva GSLDC Har Khet ko

Pani

Sim pond 25.00 25.00 25.00 25.00

Mahuva GSLDC Har Khet ko

Pani

Village pond 21.00 21.00 21.00 21.00

Mahuva GSLDC Har Khet ko

Pani

WHS 8.96 8.96 8.96 8.96

Vallbhipur GSLDC Har Khet ko

Pani

Farm pond 20.16 20.16 20.16 20.16

Vallbhipur GSLDC Har Khet ko

Pani

Sim pond 25.00 25.00 25.00 25.00

Vallbhipur GSLDC Har Khet ko Village pond 14.00 14.00 14.00 14.00

87 | P a g e

Pani

Vallbhipur GSLDC Har Khet ko

Pani

WHS 8.96 8.96 8.96 8.96

Shihor GSLDC Har Khet ko

Pani

Farm pond 25.76 25.76 25.76 25.76

Shihor GSLDC Har Khet ko

Pani

Sim pond 25.00 25.00 25.00 25.00

Shihor GSLDC Har Khet ko

Pani

Village pond 21.00 21.00 21.00 21.00

Shihor GSLDC Har Khet ko

Pani

WHS 8.96 8.96 8.96 8.96

Bhavnagar GWRDC Har Khet ko

Pani

Recharge Structure 20.00 20.00 20.00 20.00

Mahuva GWRDC Har Khet ko

Pani

Recharge Structure 20.00 20.00 20.00 20.00

Palitana GWRDC Per Drop

more crop

New Tubewell with

Drip

8.50 8.50 8.50 8.50

Talaja GWRDC Har Khet ko

Pani

Recharge Structure 20.00 20.00 20.00 20.00

Talaja GWRDC Per Drop

more crop

New Tubewell with

Drip

17.00 17.00 17.00 17.00

Bhavnagar GGRC Per Drop

more crop

Drip Irrigation

System (DIS)

262.55 196.91 196.91 196.91

Gariyadhar GGRC Per Drop Drip Irrigation 374.88 281.16 281.16 281.16

88 | P a g e

more crop System (DIS)

Ghogha GGRC Per Drop

more crop

Drip Irrigation

System (DIS)

437.44 328.08 328.08 328.08

JESAR GGRC Per Drop

more crop

Drip Irrigation

System (DIS)

111.42 83.57 83.57 83.57

Mahuva GGRC Per Drop

more crop

Drip Irrigation

System (DIS)

1320.06 990.04 990.04 990.04

Palitana GGRC Per Drop

more crop

Drip Irrigation

System (DIS)

449.71 337.28 337.28 337.28

Shihor GGRC Per Drop

more crop

Drip Irrigation

System (DIS)

499.19 374.40 374.40 374.40

Talaja GGRC Per Drop

more crop

Drip Irrigation

System (DIS)

710.10 532.57 532.57 532.57

Umrala GGRC Per Drop

more crop

Drip Irrigation

System (DIS)

301.31 225.99 225.99 225.99

Vallbhipur GGRC Per Drop

more crop

Drip Irrigation

System (DIS)

284.85 213.63 213.63 213.63

Bhavnagar GGRC Per Drop

more crop

Sprinkler Irrigation

System (SIS)

29.17 21.88 21.88 21.88

Gariyadhar GGRC Per Drop

more crop

Sprinkler Irrigation

System (SIS)

41.65 31.24 31.24 31.24

Ghogha GGRC Per Drop

more crop

Sprinkler Irrigation

System (SIS)

48.60 36.45 36.45 36.45

JESAR GGRC Per Drop Sprinkler Irrigation 12.38 9.29 9.29 9.29

89 | P a g e

more crop System (SIS)

Mahuva GGRC Per Drop

more crop

Sprinkler Irrigation

System (SIS)

146.67 110.00 110.00 110.00

Palitana GGRC Per Drop

more crop

Sprinkler Irrigation

System (SIS)

49.97 37.48 37.48 37.48

Shihor GGRC Per Drop

more crop

Sprinkler Irrigation

System (SIS)

55.47 41.60 41.60 41.60

Talaja GGRC Per Drop

more crop

Sprinkler Irrigation

System (SIS)

78.90 59.17 59.17 59.17

Umrala GGRC Per Drop

more crop

Sprinkler Irrigation

System (SIS)

33.48 25.11 25.11 25.11

Vallbhipur GGRC Per Drop

more crop

Sprinkler Irrigation

System (SIS)

31.65 23.74 23.74 23.74

Bhavnagar ATMA Training Training 35.72 46.97 56.59 70.18

Bhavnagar GSWMA Convergence

with

MGNREGA

Total 30.05 21.16 7.45

Palitana GSWMA PMKSY-

Watershed

Component

total 568.14 283.70 131.27 114.05

Palitana GSWMA PMKSY-

Watershed

Component

total 103.79 73.78 40.28 87.19

90 | P a g e

Gariyadhar GSWMA PMKSY-

Watershed

Component

total 170.24 214.45 75.96

Gariyadhar GSWMA PMKSY-

Watershed

Component

total 103.79 73.78 40.28

Talaja GSWMA PMKSY-

Watershed

Component

total 318.78

Talaja GSWMA PMKSY-

Watershed

Component

total 103.79

Mahuva GSWMA PMKSY-

Watershed

Component

total 896.70 398.17 93.17

Mahuva GSWMA PMKSY-

Watershed

Component

total 103.79 73.78 40.28

Umrala GSWMA PMKSY-

Watershed

Component

total 663.43 209.06

Umrala GSWMA PMKSY-

Watershed

Component

total 103.79 73.78

91 | P a g e

Shihor GSWMA PMKSY-

Watershed

Component

total 800.98 163.92

Shihor GSWMA PMKSY-

Watershed

Component

total 103.79 73.78

GSWMA : District Bhavnagar

Activity Unit

Physical Target for FY (2016-17)

Unit

Cost (In

Lakhs)

IWMP

Storage

Volumes

(Cubic

Meter)

Command

Area/

Irrigation

Potential

(Ha.)

Person

days/Manday

s Planned

Convergence

Unit

Amoun

t (In

Lakhs)

Name of

Schemes

EPA

Animal camp No. 0 0.00 0.00 0.00 0 0 0.00

Animal water trough (Havada) No. 0 0.37 0.00 0.00 82 0 0.00

Causeway on connecting roads No. 2 5.46 0.00 0.00 1226 0 0.00

Check / Protection wall No. 0 0.02 0.00 0.00 5 0 0.00

Demonstration for Agricultural / Animal

Husbandry Productivity Enhancement No. 0 0.00 0.00 0.00 0 0 0.00

Drainage line correction (To prevent

flooding of Gamtal) rmt 1 2.99 0.00 0.00 672 0 0.00

Drinking water facility No. 4 5.57 31575.96 0.00 1252 0 0.00

Fencing for protection from wild animals rmt. 0 0.00 0.00 0.00 0 0 0.00

92 | P a g e

Grassland/Gauchar Development Ha. 0 0.00 0.00 0.00 0 0 0.00

Improvised and energy efficient smashan

gruh (Cemetery ) No. 0 0.00 0.00 0.00 0 0 0.00

Panchayat Well Repair & Pump Room No. 0 0.01 0.00 0.00 2 0 0.00

Rain water harvesting system No. 0 0.00 0.00 0.00 0 0 0.00

Recharge / Repair of open wells No. 3 2.58 0.00 0.00 580 0 0.00

Repair / development of artificial water

bodies No. 2 4.66 3000.00 4.80 1047 0 0.00

Revival of natural water bodies with

recharge activities No. 0 0.00 0.00 0.00 0 0 0.00

Sanitation facilities/Sewerage line rmt 0 0.00 0.00 0.00 0 0 0.00

Use solar power for productive activities No. 0 0.00 0.00 0.00 0 0 0.00

Wind energy development No. 0 0.00 0.00 0.00 0 0 0.00

OTHERS No. 0 0.00 0.00 0.00 0 0 0.00

Snanghat No. 0 0.00 0.00 0.00 0 0 0.00

Water Pipeline rmt 380 1.64 0.00 0.00 0 0 0.00

Improved Cremetoriya No. 0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

Land Development 0 0.00 0.00 0.00 0 0 0.00

Farm Bunding rmt. 31135

7 155.06 0.00 0.00 87112 20320 2.50

Afforestation Ha. 80 112.00 0.00 0.00 62922 0 0.00 Forest

Agriculture Demo No. 0 0.00 0.00 0.00 0 0 0.00

Agro Forestry Ha. 0 0.00 0.00 0.00 0 0 0.00

Horticulture Ha. 20 26.00 0.00 0.00 14607 0 0.00 Horti. Dep.

Land leveling Ha. 64579 151.02 0.00 0.00 84843 6 1.44 Self Con.

Pasture development Ha. 155 35.70 0.00 0.00 20056 0 0.00

OTHERS (Wire Fencing) rmt 12601 9.50 0.00 0.00 5337 5 0.00

93 | P a g e

Non-conventional Energy No. 9 9.50 0.00 0.00 0 0 0.50

Nursery raising No. 97 3.50 0.00 0.00 0 0 41.40

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

Soil & Moisture Conservation 0 0.00 0.00 0.00 0 0 0.00

Check wall No. 152 153.71 83600.00 133.76 34541 0 0.00

Earthen bund No. 14255 47.29 0.00 0.00 26567 2741 1.00

Protection Wall No. 0 0.00 0.00 0.00 0 0 0.00

Waste weir No. 154 39.00 0.00 0.00 8764 0 0.00

Bench Terracing cume

c 0 0.00 0.00 0.00 0 0 0.00

Bori bandh No. 0 0.00 0.00 0.00 0 0 0.00

Brushwood Checks No. 0 0.00 0.00 0.00 0 0 0.00

Countour Bunding rmt. 4000 2.00 0.00 0.00 1124 0 0.00

Countour Trenches rmt. 69811 23.32 0.00 0.00 13101 0 0.00

Earthern Dam No. 0 0.00 0.00 0.00 0 0 0.00

Field Outlet No. 847 118.07 0.00 0.00 26532 21 0.63 Self Con.

Gabion structure No. 0 0.00 0.00 0.00 0 0 0.00

Graded Bunding rmt. 0 0.00 0.00 0.00 0 0 0.00

Gully plug No. 307 106.14 7368.00 11.34 23852 0 0.00

Loose boulder Checks No. 0 0.00 0.00 0.00 0 0 0.00

Nala Plug No. 283 160.39 22640.00 34.83 36043 0 0.00

Stone bunding rmt. 0 0.00 0.00 0.00 0 0 0.00

Straggred Contour trenching(Terrace

Talavadi) No. 28694 11.37 0.00 0.00 6388 0 0.00 MGNREGA

OTHERS (Specifiy activities ) No. 0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

94 | P a g e

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

Water Harvesting Structure 0 0.00 0.00 0.00 0 0 0.00

Cause way cum Chek dam No. 39 120.25 21060.00 31.20 27022 0 0.00

Check dam No. 135 473.56 202500.00 300.00 106417 0 0.00

Village/Community Pond No. 16 47.90 160000.00 237.04 26910 0 1.77

Farm Pond No. 471 101.88 188400.00 279.11 57236 0 0.00 Self Con.

Percolation Tank No. 11 31.76 110000.00 162.96 17843 0 0.00

Pond Inlet No. 0 0.00 0.00 0.00 0 0 0.00

Pond Outlet No. 3 10.50 4500.00 6.67 2360 0 0.00

OTHERS (Specifiy activities ) No. 0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

Existing/Old Water Harvesting

Structure Maintance (Renovation &

Repair)

0 0.00 0.00 0.00 0 0 0.00

Deepening/Desiltation Of Pond No. 46 75.78 115000.00 170.37 42572 17 32.73 MGNREGA

Deepening Of Percolation Tank No. 0 0.00 0.00 0.00 0 0 0.00

De-siltation of Checkdam No. 18 23.66 16875.00 25.00 13291 16 18.75 MGNREGA

Repairing of Checkdam No. 61 84.23 91500.00 135.56 18929 0 0.00 MGNREGA

OTHERS (Specifiy activities ) No. 0 0.00 0.00 0.00 0 0 0.00

Ground Water Recharging

Structures

0 0.00 0.00 0.00 0 0 0.00

Dugwell Recharge structure No. 191 22.54 2698.83 0.00 5065 0 0.00 MGNREGA

Farm Recharge Filter No. 0 0.00 0.00 0.00 0 0 0.00

Holiya in farm/Field No. 0 0.00 0.00 0.00 0 0 0.00

95 | P a g e

Pond Recharge structure No. 0 0.00 0.00 0.00 0 0 0.00

OTHERS (RWHS) No. 819 168.73 3723.70 0.00 35876 112 6.72 Self Con.

OTHERS (Injection Well) No. 3 1.80 21.60 0.00 404 2 0.90 Self Con.

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

LH & ME & Production System 0 0.00 0.00 0.00 0 0 0.00

AGRICULTURE ACTIVITIES 0 0.00 0.00 0.00 0 0 0.00

Agro Center No. 29 69.95 0.00 0.00 0 0 0.00

Agricultural Implements No. 50 24.60 0.00 0.00 0 0 0.00

Agro- Forestry No. 0 0.00 0.00 0.00 0 0 0.00

Crop Demonstration Plot No. 138 31.81 0.00 0.00 0 7 0.73 KVK

Fishery Development No. 0 0.00 0.00 0.00 0 0 0.00 Fishery

Dep.

Floriculture Development No. 0 0.00 0.00 0.00 0 0 0.00

Fodder Bank Development No. 0 0.00 0.00 0.00 0 0 0.00

Green House No. 95 102.00 0.00 0.00 0 36 7.20

Horticulture Plantation No. 240 36.13 0.00 0.00 0 25 3.95 Horti. Dep.

Kitchen Garden No. 0 0.00 0.00 0.00 0 0 0.00

Nursery raising No. 5 10.00 0.00 0.00 0 0 0.00

OTHERS No. 174 54.21 0.00 0.00 0 28 10.00 Horti. Dep.

INPUT SUPPORT No. 2 0.48 0.00 0.00 0 2 1.72

Promoting Micro-Irrigation Systems like

drip and Sprinkler Irrigation No. 830 188.21 0.00 0.00 0 290 266.55 GGRC

Sprinkler Demo. No. 40 4.00 0.00 0.00 0 40 8.00

Vegetable Nursery Raising with drip

irrigation No. 4 8.00 0.00 0.00 0 0 0.00

Vermi compost No. 289 100.46 0.00 0.00 0 3 0.30 KVK

96 | P a g e

AGRO PROCESSING ACTIVITIES 0 0.00 0.00 0.00 0 0 0.00

Dal Making Unit No. 0 0.00 0.00 0.00 0 0 0.00

Flour & Dal/Rice Processing unit No. 1 0.50 0.00 0.00 0 1 0.50 Self Con.

Garam Masala No. 0 0.00 0.00 0.00 0 0 0.00

Grading and packaging of agricultural

produces, No. 0 0.00 0.00 0.00 0 0 0.00

Jam-jelly making No. 0 0.00 0.00 0.00 0 0 0.00

Microenterprises based on Minor Forest

Produce (MFP) No. 0 0.00 0.00 0.00 0 0 0.00

Oil extraction mill No. 2 6.00 0.00 0.00 0 0 0.00

OTHERS No. 43 24.78 0.00 0.00 0 4 2.00 Self Con.

Package Food Products No. 0 0.00 0.00 0.00 0 0 0.00

Pulp making No. 0 0.00 0.00 0.00 0 0 0.00

Rice mill No. 2 3.60 0.00 0.00 0 0 0.00

Value added products from milk No. 0 0.00 0.00 0.00 0 0 0.00

Animal Husbandry 0 0.00 0.00 0.00 0 0 0.00

Cattle Feed and Nutrition Store No. 36 80.67 0.00 0.00 0 5 3.14 Self Con.

Animal Health camps No. 288 85.30 0.00 0.00 0 31 4.65 Animal

Dep.

Animal Travis (Pinjaru) No. 1 0.04 0.00 0.00 0 0 0.00

Apiculture (Bee keeping) No. 0 0.00 0.00 0.00 0 0 0.00

Artificial insemination No. 0 0.00 0.00 0.00 0 0 0.00

Back-yard poultry No. 0 0.00 0.00 0.00 0 0 0.00

Dairy cooperative promotion, No. 5 6.66 0.00 0.00 0 0 0.00

OTHERS No. 83 18.73 0.00 0.00 0 0 0.00

Pasture development No. 89 145.31 0.00 0.00 0 0 0.00

Poultry Farming to individuals No. 0 0.00 0.00 0.00 0 0 0.00

Sericulture No. 0 0.00 0.00 0.00 0 0 0.00

97 | P a g e

Small ruminants No. 0 0.00 0.00 0.00 0 0 0.00

Veterinary Aid for livestock No. 0 0.00 0.00 0.00 0 0 0.00

Cattle Shed No. 3 1.20 0.00 0.00 0 0 0.00 Self Con.

Establishing linkages 0 0.00 0.00 0.00 0 0 0.00

Credit linkages No. 0 0.00 0.00 0.00 0 0 0.00

Linkages with Future Markets, No. 0 0.00 0.00 0.00 0 0 0.00

Market linkages, No. 0 0.00 0.00 0.00 0 0 0.00

OTHERS No. 3 2.08 0.00 0.00 0 1 0.50 Self Con.

Raw material supply channel, No. 0 0.00 0.00 0.00 0 0 0.00

Local traditional handicraft 0 0.00 0.00 0.00 0 0 0.00

Bamboo based products, No. 0 0.00 0.00 0.00 0 0 0.00

Kutchi Bandhini, No. 0 0.00 0.00 0.00 0 0 0.00

OTHERS No. 5 4.80 0.00 0.00 0 3 0.80 Self Con.

Pottery No. 0 0.00 0.00 0.00 0 0 0.00

Minor Activities 0 0.00 0.00 0.00 0 0 0.00

Embroidery Unit No. 0 0.00 0.00 0.00 0 0 0.00

Handicraft Unit No. 14 12.14 0.00 0.00 0 8 0.96 Self Con.

OTHERS (Cement block, mandap

decoration) No. 31 36.67 0.00 0.00 0 11 1.80 Self Con.

Provision Store No. 0 0.00 0.00 0.00 0 0 0.00

stiching machine No. 2 3.50 0.00 0.00 0 0 0.00

Up Gradation of centering materials No. 6 0.15 0.00 0.00 0 6 0.15 Self Con.

Vegetable shop No. 0 0.00 0.00 0.00 0 0 0.00

Non-conventional Energy Sources 0 0.00 0.00 0.00 0 0 0.00

Bio gas plant, No. 0 0.00 0.00 0.00 0 0 0.00

Bio-fuel plantation, No. 0 0.00 0.00 0.00 0 0 0.00

energy conservation measures, No. 0 0.00 0.00 0.00 0 0 0.00

OTHERS No. 34 6.85 0.00 0.00 0 15 1.85 Self Con.

98 | P a g e

Solar energy promotion, No. 0 0.00 0.00 0.00 0 0 0.00

Wind energy production, No. 0 0.00 0.00 0.00 0 0 0.00

Capacity Building, Monitoring &

Evaluation 339.57

Admin 193.58

Consolidation 89.57

Total 4041.0

0 1532.63

Activity Unit

Physical Target for FY (2017-18)

Unit

Cost

(In

Lakhs)

IWMP

Storage

Volumes

(Cubic

Meter)

Command

Area/

Irrigation

Potential

(Ha.)

Person

days/Mandays

Planned

Convergence

Unit

Amount

(In

Lakhs)

Name of

Schemes

EPA

Animal camp No. 0 0.00 0.00 0.00 0 0 0.00

Animal water trough (Havada) No. 0 0.00 0.00 0.00 0 0 0.00

Causeway on connecting roads No. 0 0.00 0.00 0.00 0 0 0.00

Check / Protection wall No. 0 0.00 0.00 0.00 0 0 0.00

Demonstration for Agricultural / Animal

Husbandry Productivity Enhancement No. 0 0.00 0.00 0.00 0 0 0.00

Drainage line correction (To prevent

flooding of Gamtal) rmt 0 0.00 0.00 0.00 0 0 0.00

Drinking water facility No. 0 0.00 0.00 0.00 0 0 0.00

Fencing for protection from wild animals rmt. 0 0.00 0.00 0.00 0 0 0.00

99 | P a g e

Grassland/Gauchar Development Ha. 0 0.00 0.00 0.00 0 0 0.00

Improvised and energy efficient smashan

gruh (Cemetery ) No. 0 0.00 0.00 0.00 0 0 0.00

Panchayat Well Repair & Pump Room No. 0 0.00 0.00 0.00 0 0 0.00

Rain water harvesting system No. 0 0.00 0.00 0.00 0 0 0.00

Recharge / Repair of open wells No. 2 1.28 0.00 0.00 288 0 0.00

Repair / development of artificial water

bodies No. 0 0.00 0.00 0.00 0 0 0.00

Revival of natural water bodies with

recharge activities No. 0 0.00 0.00 0.00 0 0 0.00

Sanitation facilities/Sewerage line rmt 0 0.00 0.00 0.00 0 0 0.00

Use solar power for productive activities No. 0 0.00 0.00 0.00 0 0 0.00

Wind energy development No. 0 0.00 0.00 0.00 0 0 0.00

OTHERS No. 0 0.00 0.00 0.00 0 0 0.00

Snanghat No. 0 0.00 0.00 0.00 0 0 0.00

Water Pipeline rmt 0 0.00 0.00 0.00 0 0 0.00

Improved Cremetoriya No. 0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

Land Development 0 0.00 0.00 0.00 0 0 0.00

Farm Bunding rmt. 121806 67.98 0.00 0.00 38191 0 0.00

Afforestation Ha. 0 0.00 0.00 0.00 0 0 0.00 Forest

Agriculture Demo No. 0 0.00 0.00 0.00 0 0 0.00

Agro Forestry Ha. 0 0.00 0.00 0.00 0 0 0.00

Horticulture Ha. 0 0.00 0.00 0.00 0 0 0.00 Horti. Dep.

Land leveling Ha. 293 68.40 0.00 0.00 38427 8 1.92 Self Con.

Pasture development Ha. 1 1.70 0.00 0.00 955 0 0.00

OTHERS (Wire Fencing) rmt 0 0.00 0.00 0.00 0 0 0.00

Non-conventional Energy No. 0 0.00 0.00 0.00 0 0 0.00

100 | P a g e

Nursery raising No. 0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

Soil & Moisture Conservation 0 0.00 0.00 0.00 0 0 0.00

Check wall No. 48 52.97 26400.00 42.24 11903 0 0.00

Earthen bund No. 17630 45.31 0.00 0.00 25455 0 0.00

Protection Wall No. 0 0.00 0.00 0.00 0 0 0.00

Waste weir No. 7 19.39 0.00 0.00 4357 0 0.00

Bench Terracing cumec 0 0.00 0.00 0.00 0 0 0.00

Bori bandh No. 0 0.00 0.00 0.00 0 0 0.00

Brushwood Checks No. 0 0.00 0.00 0.00 0 0 0.00

Countour Bunding rmt. 0 0.00 0.00 0.00 0 0 0.00

Countour Trenches rmt. 0 0.00 0.00 0.00 0 0 0.00

Earthern Dam No. 0 0.00 0.00 0.00 0 0 0.00

Field Outlet No. 509 61.08 0.00 0.00 13726 88 2.64 Self Con.

Gabion structure No. 0 0.00 0.00 0.00 0 0 0.00

Graded Bunding rmt. 0 0.00 0.00 0.00 0 0 0.00

Gully plug No. 50 18.99 1200.00 1.85 4267 0 0.00

Loose boulder Checks No. 0 0.00 0.00 0.00 0 0 0.00

Nala Plug No. 68 45.54 5440.00 8.37 10233 0 0.00

Stone bunding rmt. 0 0.00 0.00 0.00 0 0 0.00

Straggred Contour trenching(Terrace

Talavadi) No. 0 0.00 0.00 0.00 0 0 0.00 MGNREGA

OTHERS (Specifiy activities ) No. 0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

101 | P a g e

Water Harvesting Structure 0 0.00 0.00 0.00 0 0 0.00

Cause way cum Chek dam No. 1 2.75 540.00 0.80 618 0 0.00

Check dam No. 41 162.20 61500.00 91.11 36449 0 0.00

Village/Community Pond No. 5 16.95 50000.00 74.07 9522 0 0.00

Farm Pond No. 176 42.24 70400.00 104.30 23730 4 0.16 Self Con.

Percolation Tank No. 2 5.98 20000.00 29.63 3360 0 0.00

Pond Inlet No. 0 0.00 0.00 0.00 0 0 0.00

Pond Outlet No. 3 10.50 4500.00 6.67 2360 0 0.00

OTHERS (Specifiy activities ) No. 0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

Existing/Old Water Harvesting

Structure Maintance (Renovation &

Repair)

0 0.00 0.00 0.00 0 0 0.00

Deepening/Desiltation Of Pond No. 29 55.38 72500.00 107.41 31112 8 17.64 MGNREGA

Deepening Of Percolation Tank No. 5 6.75 12500.00 18.52 3792 0 0.00

De-siltation of Checkdam No. 49 81.14 45937.50 68.06 45584 4 7.41 MGNREGA

Repairing of Checkdam No. 14 15.06 21000.00 31.11 3384 0 0.00 MGNREGA

OTHERS (Specifiy activities ) No. 0 0.00 0.00 0.00 0 0 0.00

Ground Water Recharging

Structures

0 0.00 0.00 0.00 0 0 0.00

Dugwell Recharge structure No. 54 22.36 763.02 0.00 5025 1 1.41 MGNREGA

Farm Recharge Filter No. 0 0.00 0.00 0.00 0 0 0.00

Holiya in farm/Field No. 0 0.00 0.00 0.00 0 0 0.00

Pond Recharge structure No. 0 0.00 0.00 0.00 0 0 0.00

OTHERS (RWHS) No. 681 163.44 4903.20 0.00 36728 68 4.08 Self Con.

102 | P a g e

OTHERS (Injection Well) No. 18 10.80 129.60 0.00 2427 11 5.40 Self Con.

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

LH & ME & Production System 0 0.00 0.00 0.00 0 0 0.00

AGRICULTURE ACTIVITIES 0 0.00 0.00 0.00 0 0 0.00

Agro Center No. 8 15.90 0.00 0.00 0 0 0.00

Agricultural Implements No. 0 0.00 0.00 0.00 0 0 0.00

Agro- Forestry No. 0 0.00 0.00 0.00 0 0 0.00

Crop Demonstration Plot No. 48 9.62 0.00 0.00 0 10 0.50 KVK

Fishery Development No. 4 0.20 0.00 0.00 0 4 0.20 Fishery

Dep.

Floriculture Development No. 0 0.00 0.00 0.00 0 0 0.00

Fodder Bank Development No. 0 0.00 0.00 0.00 0 0 0.00

Green House No. 16 6.80 0.00 0.00 0 0 0.00

Horticulture Plantation No. 12 1.80 0.00 0.00 0 10 1.50 Horti. Dep.

Kitchen Garden No. 0 0.00 0.00 0.00 0 0 0.00

Nursery raising No. 1 2.00 0.00 0.00 0 0 0.00

OTHERS No. 7 12.60 0.00 0.00 0 1 0.60 Horti. Dep.

INPUT SUPPORT No. 0 0.00 0.00 0.00 0 0 0.00

Promoting Micro-Irrigation Systems like

drip and Sprinkler Irrigation No. 361 85.20 0.00 0.00 0 213 #VALUE! GGRC

Sprinkler Demo. No. 30 3.00 0.00 0.00 0 30 6.00

Vegetable Nursery Raising with drip

irrigation No. 0 0.00 0.00 0.00 0 0 0.00

Vermi compost No. 91 30.50 0.00 0.00 0 14 1.40 KVK

AGRO PROCESSING ACTIVITIES 0 0.00 0.00 0.00 0 0 0.00

Dal Making Unit No. 0 0.00 0.00 0.00 0 0 0.00

103 | P a g e

Flour & Dal/Rice Processing unit No. 1 1.55 0.00 0.00 0 0 0.00 Self Con.

Garam Masala No. 0 0.00 0.00 0.00 0 0 0.00

Grading and packaging of agricultural

produces, No. 0 0.00 0.00 0.00 0 0 0.00

Jam-jelly making No. 0 0.00 0.00 0.00 0 0 0.00

Microenterprises based on Minor Forest

Produce (MFP) No. 0 0.00 0.00 0.00 0 0 0.00

Oil extraction mill No. 0 0.00 0.00 0.00 0 0 0.00

OTHERS No. 3 3.50 0.00 0.00 0 1 0.50 Self Con.

Package Food Products No. 0 0.00 0.00 0.00 0 0 0.00

Pulp making No. 0 0.00 0.00 0.00 0 0 0.00

Rice mill No. 0 0.00 0.00 0.00 0 0 0.00

Value added products from milk No. 2 4.00 0.00 0.00 0 0 0.00

Animal Husbandry 0 0.00 0.00 0.00 0 0 0.00

Cattle Feed and Nutrition Store No. 11 17.59 0.00 0.00 0 2 1.26 Self Con.

Animal Health camps No. 93 24.90 0.00 0.00 0 6 0.90 Animal

Dep.

Animal Travis (Pinjaru) No. 0 0.00 0.00 0.00 0 0 0.00

Apiculture (Bee keeping) No. 0 0.00 0.00 0.00 0 0 0.00

Artificial insemination No. 0 0.00 0.00 0.00 0 0 0.00

Back-yard poultry No. 0 0.00 0.00 0.00 0 0 0.00

Dairy cooperative promotion, No. 4 7.12 0.00 0.00 0 0 0.00

OTHERS No. 37 5.55 0.00 0.00 0 0 0.00

Pasture development No. 6 10.20 0.00 0.00 0 0 0.00

Poultry Farming to individuals No. 0 0.00 0.00 0.00 0 0 0.00

Sericulture No. 0 0.00 0.00 0.00 0 0 0.00

Small ruminants No. 0 0.00 0.00 0.00 0 0 0.00

Veterinary Aid for livestock No. 0 0.00 0.00 0.00 0 0 0.00

104 | P a g e

Cattle Shed No. 21 2.38 0.00 0.00 0 21 2.38 Self Con.

Establishing linkages 0 0.00 0.00 0.00 0 0 0.00

Credit linkages No. 0 0.00 0.00 0.00 0 0 0.00

Linkages with Future Markets, No. 0 0.00 0.00 0.00 0 0 0.00

Market linkages, No. 0 0.00 0.00 0.00 0 0 0.00

OTHERS No. 21 21.32 0.00 0.00 0 4 0.30 Self Con.

Raw material supply channel, No. 0 0.00 0.00 0.00 0 0 0.00

Local traditional handicraft 0 0.00 0.00 0.00 0 0 0.00

Bamboo based products, No. 0 0.00 0.00 0.00 0 0 0.00

Kutchi Bandhini, No. 0 0.00 0.00 0.00 0 0 0.00

OTHERS No. 6 2.40 0.00 0.00 0 5 1.10 Self Con.

Pottery No. 0 0.00 0.00 0.00 0 0 0.00

Minor Activities 0 0.00 0.00 0.00 0 0 0.00

Embroidery Unit No. 0 0.00 0.00 0.00 0 0 0.00

Handicraft Unit No. 43 6.93 0.00 0.00 0 41 4.97 Self Con.

OTHERS (Cement block, mandap

decoration) No. 8 12.69 0.00 0.00 0 1 0.23 Self Con.

Provision Store No. 0 0.00 0.00 0.00 0 0 0.00

stiching machine No. 0 0.00 0.00 0.00 0 0 0.00

Up Gradation of centering materials No. 24 0.61 0.00 0.00 0 24 0.61 Self Con.

Vegetable shop No. 0 0.00 0.00 0.00 0 0 0.00

Non-conventional Energy Sources 0 0.00 0.00 0.00 0 0 0.00

Bio gas plant, No. 0 0.00 0.00 0.00 0 0 0.00

Bio-fuel plantation, No. 0 0.00 0.00 0.00 0 0 0.00

energy conservation measures, No. 0 0.00 0.00 0.00 0 0 0.00

OTHERS No. 9 2.75 0.00 0.00 0 1 0.75 Self Con.

Solar energy promotion, No. 0 0.00 0.00 0.00 0 0 0.00

Wind energy production, No. 0 0.00 0.00 0.00 0 0 0.00

105 | P a g e

Capacity Building, Monitoring &

Evaluation 84.02

Admin 119.67

Consolidation 165.21

Total 1638.19 584.13

Activity Unit

Physical Target for FY (2018-19)

Unit

Cost (In

Lakhs)

IWMP

Storage

Volumes

(Cubic

Meter)

Command

Area/

Irrigation

Potential

(Ha.)

Person

days/Mandays

Planned

Convergence

Unit

Amount

(In

Lakhs)

Name of

Schemes

EPA

Animal camp No. 0 0.00 0.00 0.00 0 0 0.00

Animal water trough (Havada) No. 0 0.00 0.00 0.00 0 0 0.00

Causeway on connecting roads No. 0 0.00 0.00 0.00 0 0 0.00

Check / Protection wall No. 0 0.00 0.00 0.00 0 0 0.00

Demonstration for Agricultural / Animal

Husbandry Productivity Enhancement No. 0 0.00 0.00 0.00 0 0 0.00

Drainage line correction (To prevent

flooding of Gamtal) rmt 0 0.00 0.00 0.00 0 0 0.00

Drinking water facility No. 0 0.00 0.00 0.00 0 0 0.00

Fencing for protection from wild animals rmt. 0 0.00 0.00 0.00 0 0 0.00

Grassland/Gauchar Development Ha. 0 0.00 0.00 0.00 0 0 0.00

Improvised and energy efficient smashan

gruh (Cemetery ) No. 0 0.00 0.00 0.00 0 0 0.00

106 | P a g e

Panchayat Well Repair & Pump Room No. 0 0.00 0.00 0.00 0 0 0.00

Rain water harvesting system No. 0 0.00 0.00 0.00 0 0 0.00

Recharge / Repair of open wells No. 0 0.00 0.00 0.00 0 0 0.00

Repair / development of artificial water

bodies No. 0 0.00 0.00 0.00 0 0 0.00

Revival of natural water bodies with

recharge activities No. 0 0.00 0.00 0.00 0 0 0.00

Sanitation facilities/Sewerage line rmt 0 0.00 0.00 0.00 0 0 0.00

Use solar power for productive activities No. 0 0.00 0.00 0.00 0 0 0.00

Wind energy development No. 0 0.00 0.00 0.00 0 0 0.00

OTHERS No. 0 0.00 0.00 0.00 0 0 0.00

Snanghat No. 0 0.00 0.00 0.00 0 0 0.00

Water Pipeline rmt 0 0.00 0.00 0.00 0 0 0.00

Improved Cremetoriya No. 0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

Land Development 0 0.00 0.00 0.00 0 0 0.00

Farm Bunding rmt. 10 1.20 0.00 0.00 674 0 0.00

Afforestation Ha. 0 0.00 0.00 0.00 0 0 0.00 Forest

Agriculture Demo No. 0 0.00 0.00 0.00 0 0 0.00

Agro Forestry Ha. 0 0.00 0.00 0.00 0 0 0.00

Horticulture Ha. 13 1.95 0.00 0.00 1096 13 1.95 Horti. Dep.

Land leveling Ha. 37 11.92 0.00 0.00 6697 37 16.96 Self Con.

Pasture development Ha. 0 0.00 0.00 0.00 0 0 0.00

OTHERS (Wire Fencing) rmt 0 0.00 0.00 0.00 0 0 0.00

Non-conventional Energy No. 0 0.00 0.00 0.00 0 0 0.00

Nursery raising No. 0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

107 | P a g e

Soil & Moisture Conservation 0 0.00 0.00 0.00 0 0 0.00

Check wall No. 2 2.20 1100.00 1.76 494 0 0.00

Earthen bund No. 0 0.00 0.00 0.00 0 0 0.00

Protection Wall No. 0 0.00 0.00 0.00 0 0 0.00

Waste weir No. 1 3.53 0.00 0.00 793 0 0.00

Bench Terracing cumec 0 0.00 0.00 0.00 0 0 0.00

Bori bandh No. 0 0.00 0.00 0.00 0 0 0.00

Brushwood Checks No. 0 0.00 0.00 0.00 0 0 0.00

Countour Bunding rmt. 0 0.00 0.00 0.00 0 0 0.00

Countour Trenches rmt. 0 0.00 0.00 0.00 0 0 0.00

Earthern Dam No. 0 0.00 0.00 0.00 0 0 0.00

Field Outlet No. 55 6.60 0.00 0.00 1483 10 0.30 Self Con.

Gabion structure No. 0 0.00 0.00 0.00 0 0 0.00

Graded Bunding rmt. 0 0.00 0.00 0.00 0 0 0.00

Gully plug No. 0 0.00 0.00 0.00 0 0 0.00

Loose boulder Checks No. 0 0.00 0.00 0.00 0 0 0.00

Nala Plug No. 14 12.60 1120.00 1.72 2831 0 0.00

Stone bunding rmt. 0 0.00 0.00 0.00 0 0 0.00

Straggred Contour trenching(Terrace

Talavadi) No. 0 0.00 0.00 0.00 0 0 0.00 MGNREGA

OTHERS (Specifiy activities ) No. 0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

Water Harvesting Structure 0 0.00 0.00 0.00 0 0 0.00

Cause way cum Chek dam No. 0 0.00 0.00 0.00 0 0 0.00

Check dam No. 12 44.82 18000.00 26.67 10072 0 0.00

108 | P a g e

Village/Community Pond No. 0 0.00 0.00 0.00 0 0 0.00

Farm Pond No. 12 2.88 4800.00 7.11 1618 12 0.48 Self Con.

Percolation Tank No. 0 0.00 0.00 0.00 0 0 0.00

Pond Inlet No. 0 0.00 0.00 0.00 0 0 0.00

Pond Outlet No. 0 0.00 0.00 0.00 0 0 0.00

OTHERS (Specifiy activities ) No. 0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

Existing/Old Water Harvesting

Structure Maintance (Renovation &

Repair)

0 0.00 0.00 0.00 0 0 0.00

Deepening/Desiltation Of Pond No. 0 0.00 0.00 0.00 0 3 7.45 MGNREGA

Deepening Of Percolation Tank No. 0 0.00 0.00 0.00 0 0 0.00

De-siltation of Checkdam No. 0 0.00 0.00 0.00 0 0 0.00 MGNREGA

Repairing of Checkdam No. 23 43.50 34500.00 51.11 9775 0 0.00 MGNREGA

OTHERS (Specifiy activities ) No. 0 0.00 0.00 0.00 0 0 0.00

Ground Water Recharging

Structures

0 0.00 0.00 0.00 0 0 0.00

Dugwell Recharge structure No. 171 20.52 2416.23 0.00 4611 0 0.00 MGNREGA

Farm Recharge Filter No. 0 0.00 0.00 0.00 0 0 0.00

Holiya in farm/Field No. 0 0.00 0.00 0.00 0 0 0.00

Pond Recharge structure No. 0 0.00 0.00 0.00 0 0 0.00

OTHERS (RWHS) No. 344 82.56 2476.80 0.00 18553 156 9.36 Self Con.

OTHERS (Injection Well) No. 7 6.30 50.40 0.00 1416 0 0.00 Self Con.

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

109 | P a g e

0 0.00 0.00 0.00 0 0 0.00

LH & ME & Production System 0 0.00 0.00 0.00 0 0 0.00

AGRICULTURE ACTIVITIES 0 0.00 0.00 0.00 0 0 0.00

Agro Center No. 8 10.45 0.00 0.00 0 0 0.00

Agricultural Implements No. 0 0.00 0.00 0.00 0 0 0.00

Agro- Forestry No. 0 0.00 0.00 0.00 0 0 0.00

Crop Demonstration Plot No. 0 0.00 0.00 0.00 0 0 0.00 KVK

Fishery Development No. 0 0.00 0.00 0.00 0 0 0.00 Fishery

Dep.

Floriculture Development No. 0 0.00 0.00 0.00 0 0 0.00

Fodder Bank Development No. 0 0.00 0.00 0.00 0 0 0.00

Green House No. 2 4.00 0.00 0.00 0 0 0.00

Horticulture Plantation No. 0 0.00 0.00 0.00 0 0 0.00 Horti. Dep.

Kitchen Garden No. 0 0.00 0.00 0.00 0 0 0.00

Nursery raising No. 0 0.00 0.00 0.00 0 0 0.00

OTHERS No. 2 1.20 0.00 0.00 0 2 1.20 Horti. Dep.

INPUT SUPPORT No. 0 0.00 0.00 0.00 0 0 0.00

Promoting Micro-Irrigation Systems like

drip and Sprinkler Irrigation No. 67 16.08 0.00 0.00 0 30 25.80 GGRC

Sprinkler Demo. No. 20 2.00 0.00 0.00 0 20 4.00

Vegetable Nursery Raising with drip

irrigation No. 0 0.00 0.00 0.00 0 0 0.00

Vermi compost No. 0 0.00 0.00 0.00 0 0 0.00 KVK

AGRO PROCESSING ACTIVITIES 0 0.00 0.00 0.00 0 0 0.00

Dal Making Unit No. 0 0.00 0.00 0.00 0 0 0.00

Flour & Dal/Rice Processing unit No. 0 0.00 0.00 0.00 0 0 0.00 Self Con.

Garam Masala No. 0 0.00 0.00 0.00 0 0 0.00

Grading and packaging of agricultural No. 0 0.00 0.00 0.00 0 0 0.00

110 | P a g e

produces,

Jam-jelly making No. 0 0.00 0.00 0.00 0 0 0.00

Microenterprises based on Minor Forest

Produce (MFP) No. 0 0.00 0.00 0.00 0 0 0.00

Oil extraction mill No. 0 0.00 0.00 0.00 0 0 0.00

OTHERS No. 0 0.00 0.00 0.00 0 0 0.00 Self Con.

Package Food Products No. 0 0.00 0.00 0.00 0 0 0.00

Pulp making No. 0 0.00 0.00 0.00 0 0 0.00

Rice mill No. 0 0.00 0.00 0.00 0 0 0.00

Value added products from milk No. 0 0.00 0.00 0.00 0 0 0.00

Animal Husbandry 0 0.00 0.00 0.00 0 0 0.00

Cattle Feed and Nutrition Store No. 2 2.00 0.00 0.00 0 1 0.63 Self Con.

Animal Health camps No. 24 10.20 0.00 0.00 0 8 1.20 Animal

Dep.

Animal Travis (Pinjaru) No. 0 0.00 0.00 0.00 0 0 0.00

Apiculture (Bee keeping) No. 0 0.00 0.00 0.00 0 0 0.00

Artificial insemination No. 0 0.00 0.00 0.00 0 0 0.00

Back-yard poultry No. 0 0.00 0.00 0.00 0 0 0.00

Dairy cooperative promotion, No. 0 0.00 0.00 0.00 0 0 0.00

OTHERS No. 0 0.00 0.00 0.00 0 0 0.00

Pasture development No. 0 0.00 0.00 0.00 0 0 0.00

Poultry Farming to individuals No. 0 0.00 0.00 0.00 0 0 0.00

Sericulture No. 0 0.00 0.00 0.00 0 0 0.00

Small ruminants No. 0 0.00 0.00 0.00 0 0 0.00

Veterinary Aid for livestock No. 0 0.00 0.00 0.00 0 0 0.00

Cattle Shed No. 14 1.76 0.00 0.00 0 14 1.76 Self Con.

Establishing linkages 0 0.00 0.00 0.00 0 0 0.00

Credit linkages No. 0 0.00 0.00 0.00 0 0 0.00

111 | P a g e

Linkages with Future Markets, No. 0 0.00 0.00 0.00 0 0 0.00

Market linkages, No. 0 0.00 0.00 0.00 0 0 0.00

OTHERS No. 7 0.83 0.00 0.00 0 7 0.83 Self Con.

Raw material supply channel, No. 0 0.00 0.00 0.00 0 0 0.00

Local traditional handicraft 0 0.00 0.00 0.00 0 0 0.00

Bamboo based products, No. 0 0.00 0.00 0.00 0 0 0.00

Kutchi Bandhini, No. 0 0.00 0.00 0.00 0 0 0.00

OTHERS No. 6 2.03 0.00 0.00 0 5 0.75 Self Con.

Pottery No. 0 0.00 0.00 0.00 0 0 0.00

Minor Activities 0 0.00 0.00 0.00 0 0 0.00

Embroidery Unit No. 0 0.00 0.00 0.00 0 0 0.00

Handicraft Unit No. 14 1.69 0.00 0.00 0 14 1.69 Self Con.

OTHERS (Cement block, mandap

decoration) No. 6 3.13 0.00 0.00 0 5 1.13 Self Con.

Provision Store No. 0 0.00 0.00 0.00 0 0 0.00

stiching machine No. 1 2.00 0.00 0.00 0 0 0.00

Up Gradation of centering materials No. 4 0.20 0.00 0.00 0 4 0.10 Self Con.

Vegetable shop No. 0 0.00 0.00 0.00 0 0 0.00

Non-conventional Energy Sources 0 0.00 0.00 0.00 0 0 0.00

Bio gas plant, No. 0 0.00 0.00 0.00 0 0 0.00

Bio-fuel plantation, No. 0 0.00 0.00 0.00 0 0 0.00

energy conservation measures, No. 0 0.00 0.00 0.00 0 0 0.00

OTHERS No. 16 2.25 0.00 0.00 0 12 1.25 Self Con.

Solar energy promotion, No. 0 0.00 0.00 0.00 0 0 0.00

Wind energy production, No. 0 0.00 0.00 0.00 0 0 0.00

Capacity Building, Monitoring &

Evaluation 55.12

Admin 45.99

112 | P a g e

Consolidation 19.74

Total 421.25 88.37

Activity Unit

Physical Target for FY (2019-20)

Unit

Cost

(In

Lakhs)

IWMP

Storage

Volumes

(Cubic

Meter)

Command

Area/

Irrigation

Potential

(Ha.)

Person

days/Mandays

Planned

Convergence

Unit

Amount

(In

Lakhs)

Name of

Schemes

EPA

Animal camp No. 0 0.00 0.00 0.00 0 0 0.00

Animal water trough (Havada) No. 0 0.00 0.00 0.00 0 0 0.00

Causeway on connecting roads No. 0 0.00 0.00 0.00 0 0 0.00

Check / Protection wall No. 0 0.00 0.00 0.00 0 0 0.00

Demonstration for Agricultural / Animal

Husbandry Productivity Enhancement No. 0 0.00 0.00 0.00 0 0 0.00

Drainage line correction (To prevent

flooding of Gamtal) rmt 0 0.00 0.00 0.00 0 0 0.00

Drinking water facility No. 0 0.00 0.00 0.00 0 0 0.00

Fencing for protection from wild animals rmt. 0 0.00 0.00 0.00 0 0 0.00

Grassland/Gauchar Development Ha. 0 0.00 0.00 0.00 0 0 0.00

Improvised and energy efficient smashan

gruh (Cemetery ) No. 0 0.00 0.00 0.00 0 0 0.00

Panchayat Well Repair & Pump Room No. 0 0.00 0.00 0.00 0 0 0.00

Rain water harvesting system No. 0 0.00 0.00 0.00 0 0 0.00

Recharge / Repair of open wells No. 0 0.00 0.00 0.00 0 0 0.00

113 | P a g e

Repair / development of artificial water

bodies No. 0 0.00 0.00 0.00 0 0 0.00

Revival of natural water bodies with

recharge activities No. 0 0.00 0.00 0.00 0 0 0.00

Sanitation facilities/Sewerage line rmt 0 0.00 0.00 0.00 0 0 0.00

Use solar power for productive activities No. 0 0.00 0.00 0.00 0 0 0.00

Wind energy development No. 0 0.00 0.00 0.00 0 0 0.00

OTHERS No. 0 0.00 0.00 0.00 0 0 0.00

Snanghat No. 0 0.00 0.00 0.00 0 0 0.00

Water Pipeline rmt 0 0.00 0.00 0.00 0 0 0.00

Improved Cremetoriya No. 0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

Land Development 0 0.00 0.00 0.00 0 0 0.00

Farm Bunding rmt. 71240 35.62 0.00 0.00 20011 0 0.00

Afforestation Ha. 0 0.00 0.00 0.00 0 0 0.00 Forest

Agriculture Demo No. 0 0.00 0.00 0.00 0 0 0.00

Agro Forestry Ha. 0 0.00 0.00 0.00 0 0 0.00

Horticulture Ha. 0 0.00 0.00 0.00 0 0 0.00 Horti. Dep.

Land leveling Ha. 0 0.00 0.00 0.00 0 0 0.00 Self Con.

Pasture development Ha. 0 0.00 0.00 0.00 0 0 0.00

OTHERS (Wire Fencing) rmt 0 0.00 0.00 0.00 0 0 0.00

Non-conventional Energy No. 0 0.00 0.00 0.00 0 0 0.00

Nursery raising No. 0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

Soil & Moisture Conservation 0 0.00 0.00 0.00 0 0 0.00

Check wall No. 0 0.00 0.00 0.00 0 0 0.00

Earthen bund No. 0 0.00 0.00 0.00 0 0 0.00

114 | P a g e

Protection Wall No. 0 0.00 0.00 0.00 0 0 0.00

Waste weir No. 0 0.00 0.00 0.00 0 0 0.00

Bench Terracing cumec 0 0.00 0.00 0.00 0 0 0.00

Bori bandh No. 0 0.00 0.00 0.00 0 0 0.00

Brushwood Checks No. 0 0.00 0.00 0.00 0 0 0.00

Countour Bunding rmt. 0 0.00 0.00 0.00 0 0 0.00

Countour Trenches rmt. 0 0.00 0.00 0.00 0 0 0.00

Earthern Dam No. 0 0.00 0.00 0.00 0 0 0.00

Field Outlet No. 0 0.00 0.00 0.00 0 0 0.00 Self Con.

Gabion structure No. 0 0.00 0.00 0.00 0 0 0.00

Graded Bunding rmt. 0 0.00 0.00 0.00 0 0 0.00

Gully plug No. 0 0.00 0.00 0.00 0 0 0.00

Loose boulder Checks No. 0 0.00 0.00 0.00 0 0 0.00

Nala Plug No. 0 0.00 0.00 0.00 0 0 0.00

Stone bunding rmt. 4020 8.00 0.00 0.00 1798 0 0.00

Straggred Contour trenching(Terrace

Talavadi) No. 0 0.00 0.00 0.00 0 0 0.00 MGNREGA

OTHERS (Specifiy activities ) No. 0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

Water Harvesting Structure 0 0.00 0.00 0.00 0 0 0.00

Cause way cum Chek dam No. 0 0.00 0.00 0.00 0 0 0.00

Check dam No. 0 0.00 0.00 0.00 0 0 0.00

Village/Community Pond No. 0 0.00 0.00 0.00 0 0 0.00

Farm Pond No. 0 0.00 0.00 0.00 0 0 0.00 Self Con.

Percolation Tank No. 0 0.00 0.00 0.00 0 0 0.00

115 | P a g e

Pond Inlet No. 0 0.00 0.00 0.00 0 0 0.00

Pond Outlet No. 0 0.00 0.00 0.00 0 0 0.00

OTHERS (Specifiy activities ) No. 0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

Existing/Old Water Harvesting

Structure Maintance (Renovation &

Repair)

0 0.00 0.00 0.00 0 0 0.00

Deepening/Desiltation Of Pond No. 0 0.00 0.00 0.00 0 0 0.00 MGNREGA

Deepening Of Percolation Tank No. 0 0.00 0.00 0.00 0 0 0.00

De-siltation of Checkdam No. 0 0.00 0.00 0.00 0 0 0.00 MGNREGA

Repairing of Checkdam No. 0 0.00 0.00 0.00 0 0 0.00 MGNREGA

OTHERS (Specifiy activities ) No. 0 0.00 0.00 0.00 0 0 0.00

Ground Water Recharging

Structures

0 0.00 0.00 0.00 0 0 0.00

Dugwell Recharge structure No. 0 0.00 0.00 0.00 0 0 0.00 MGNREGA

Farm Recharge Filter No. 0 0.00 0.00 0.00 0 0 0.00

Holiya in farm/Field No. 0 0.00 0.00 0.00 0 0 0.00

Pond Recharge structure No. 0 0.00 0.00 0.00 0 0 0.00

OTHERS (RWHS) No. 200 48.00 1440.00 0.00 10787 0 0.00 Self Con.

OTHERS (Injection Well) No. 0 0.00 0.00 0.00 0 0 0.00 Self Con.

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

0 0.00 0.00 0.00 0 0 0.00

LH & ME & Production System 0 0.00 0.00 0.00 0 0 0.00

AGRICULTURE ACTIVITIES 0 0.00 0.00 0.00 0 0 0.00

116 | P a g e

Agro Center No. 0 0.00 0.00 0.00 0 0 0.00

Agricultural Implements No. 0 0.00 0.00 0.00 0 0 0.00

Agro- Forestry No. 0 0.00 0.00 0.00 0 0 0.00

Crop Demonstration Plot No. 0 0.00 0.00 0.00 0 0 0.00 KVK

Fishery Development No. 0 0.00 0.00 0.00 0 0 0.00 Fishery

Dep.

Floriculture Development No. 0 0.00 0.00 0.00 0 0 0.00

Fodder Bank Development No. 0 0.00 0.00 0.00 0 0 0.00

Green House No. 0 0.00 0.00 0.00 0 0 0.00

Horticulture Plantation No. 0 0.00 0.00 0.00 0 0 0.00 Horti. Dep.

Kitchen Garden No. 0 0.00 0.00 0.00 0 0 0.00

Nursery raising No. 0 0.00 0.00 0.00 0 0 0.00

OTHERS No. 0 0.00 0.00 0.00 0 0 0.00 Horti. Dep.

INPUT SUPPORT No. 0 0.00 0.00 0.00 0 0 0.00

Promoting Micro-Irrigation Systems like

drip and Sprinkler Irrigation No. 0 0.00 0.00 0.00 0 0 0.00 GGRC

Sprinkler Demo. No. 0 0.00 0.00 0.00 0 0 0.00

Vegetable Nursery Raising with drip

irrigation No. 0 0.00 0.00 0.00 0 0 0.00

Vermi compost No. 0 0.00 0.00 0.00 0 0 0.00 KVK

AGRO PROCESSING ACTIVITIES 0 0.00 0.00 0.00 0 0 0.00

Dal Making Unit No. 0 0.00 0.00 0.00 0 0 0.00

Flour & Dal/Rice Processing unit No. 0 0.00 0.00 0.00 0 0 0.00 Self Con.

Garam Masala No. 0 0.00 0.00 0.00 0 0 0.00

Grading and packaging of agricultural

produces, No. 0 0.00 0.00 0.00 0 0 0.00

Jam-jelly making No. 0 0.00 0.00 0.00 0 0 0.00

Microenterprises based on Minor Forest No. 0 0.00 0.00 0.00 0 0 0.00

117 | P a g e

Produce (MFP)

Oil extraction mill No. 0 0.00 0.00 0.00 0 0 0.00

OTHERS No. 0 0.00 0.00 0.00 0 0 0.00 Self Con.

Package Food Products No. 0 0.00 0.00 0.00 0 0 0.00

Pulp making No. 0 0.00 0.00 0.00 0 0 0.00

Rice mill No. 0 0.00 0.00 0.00 0 0 0.00

Value added products from milk No. 0 0.00 0.00 0.00 0 0 0.00

Animal Husbandry 0 0.00 0.00 0.00 0 0 0.00

Cattle Feed and Nutrition Store No. 0 0.00 0.00 0.00 0 0 0.00 Self Con.

Animal Health camps No. 0 0.00 0.00 0.00 0 0 0.00 Animal

Dep.

Animal Travis (Pinjaru) No. 0 0.00 0.00 0.00 0 0 0.00

Apiculture (Bee keeping) No. 0 0.00 0.00 0.00 0 0 0.00

Artificial insemination No. 0 0.00 0.00 0.00 0 0 0.00

Back-yard poultry No. 0 0.00 0.00 0.00 0 0 0.00

Dairy cooperative promotion, No. 0 0.00 0.00 0.00 0 0 0.00

OTHERS No. 0 0.00 0.00 0.00 0 0 0.00

Pasture development No. 0 0.00 0.00 0.00 0 0 0.00

Poultry Farming to individuals No. 0 0.00 0.00 0.00 0 0 0.00

Sericulture No. 0 0.00 0.00 0.00 0 0 0.00

Small ruminants No. 0 0.00 0.00 0.00 0 0 0.00

Veterinary Aid for livestock No. 0 0.00 0.00 0.00 0 0 0.00

Cattle Shed No. 0 0.00 0.00 0.00 0 0 0.00 Self Con.

Establishing linkages 0 0.00 0.00 0.00 0 0 0.00

Credit linkages No. 0 0.00 0.00 0.00 0 0 0.00

Linkages with Future Markets, No. 0 0.00 0.00 0.00 0 0 0.00

Market linkages, No. 0 0.00 0.00 0.00 0 0 0.00

OTHERS No. 14 19.78 0.00 0.00 0 0 0.00 Self Con.

118 | P a g e

Raw material supply channel, No. 0 0.00 0.00 0.00 0 0 0.00

Local traditional handicraft 0 0.00 0.00 0.00 0 0 0.00

Bamboo based products, No. 0 0.00 0.00 0.00 0 0 0.00

Kutchi Bandhini, No. 0 0.00 0.00 0.00 0 0 0.00

OTHERS No. 0 0.00 0.00 0.00 0 0 0.00 Self Con.

Pottery No. 0 0.00 0.00 0.00 0 0 0.00

Minor Activities 0 0.00 0.00 0.00 0 0 0.00

Embroidery Unit No. 0 0.00 0.00 0.00 0 0 0.00

Handicraft Unit No. 0 0.00 0.00 0.00 0 0 0.00 Self Con.

OTHERS (Cement block, mandap

decoration) No. 4 2.65 0.00 0.00 0 0 0.00 Self Con.

Provision Store No. 0 0.00 0.00 0.00 0 0 0.00

stiching machine No. 0 0.00 0.00 0.00 0 0 0.00

Up Gradation of centering materials No. 0 0.00 0.00 0.00 0 0 0.00 Self Con.

Vegetable shop No. 0 0.00 0.00 0.00 0 0 0.00

Non-conventional Energy Sources 0 0.00 0.00 0.00 0 0 0.00

Bio gas plant, No. 0 0.00 0.00 0.00 0 0 0.00

Bio-fuel plantation, No. 0 0.00 0.00 0.00 0 0 0.00

energy conservation measures, No. 0 0.00 0.00 0.00 0 0 0.00

OTHERS No. 0 0.00 0.00 0.00 0 0 0.00 Self Con.

Solar energy promotion, No. 0 0.00 0.00 0.00 0 0 0.00

Wind energy production, No. 0 0.00 0.00 0.00 0 0 0.00

Capacity Building, Monitoring &

Evaluation 20.76

Admin 29.80

Consolidation 36.63

Total 201.24 0.00

119 | P a g e

120 | P a g e

Annexure 2

Detail about Affected village in different aspect the details of coastal villages

Sr. No. Taluka Name Village Name

1 Bhavnagar

1.1 Kalatalav

1.2 Hathab,

1.3 Narmad

1.4 Koliyak

1.5 Jashvantpur

1.6 Kotda

1.7 Kheta khatli

1.8 Ganeshgadh

2 Ghogha

2.1 Kuda

2.2 Ghogha

2.3 Avaniya

3 Mahuva

3.1 Nicha kotda

3.2 Dayal,

3.3 Kalsar

3.4 Naip

3.5 Nikol

3.6 Vaghnagar

3.7 Katpar

3.8 Khared

3.9 Gadhda

121 | P a g e

3.10 Gujarda

3.11 Dudheri

3.12 Doliya

3.13 Padhiyarka

4 Talaja

4.1 Alang

4.2 Mithivirdi

4.3 Sartanpar

4.4 Reliya

4.5 Gadhula

4.6 Zanzmer

4.7 Methala

4.8 Madhuvan

4.9 Juna-rajpara

4.10 Tarasra

The details of water logging villages

Sr.No. Taluka Name Village Name

1 Bhavnagar

1.1 KalaTalav

1.2 Velavadar

1.3 Keta Khatli

1.4 Narmad

1.5 Paliad

1.6 Devalia

122 | P a g e

1.7 Jasvant Pura

1.8 Kotda

1.9 Sanesh

1.10 Ganeshgadh

1.11 Saviakot

COCONUT

ONION