[2015 - 2016 Development Plan]
Web Development Plan Nov 2015-Dec 2016
WEB TEAM COLLABORATIVE WORK
Time Line Development Area Sprint(s) Outline
Strategic Impact Areas
External Dependencies Sprint length Status
Nov 2015 Review/embedding
Review and embed underlying website developments.Example areas of development :
Optimisation of header and footer for mobile device usage
Page performance improvement
Information architecture review
Completion of user testing process and annual plan
Template and design pattern enhancement review
Beta web site redevelopment.
Study with us page
Operational excellence
4 weeks Complete
Notes:
Page performance review – will continue to be reviewed throughout the year
Information architecture – final review due in April
User testing - ongoing
Dec 2015 Student information
**See Appendix A for more detailed student information.
Student information Phase 1:Development of a plan for the student Information pages of the web site :
Web and Communications team workshop
University interested parties’ workshop
User research
Outstanding student ExperienceGlobal engagement
Availability of University staff involved in student communications, marketing, support and provision of facilities.
4 weeks Complete
Notes:
Meetings held with SEES and RIO
Updated – March 2016 - Page 1 of 15
[2015 - 2016 Development Plan]
WEB TEAM COLLABORATIVE WORK
Time Line Development Area Sprint(s) Outline
Strategic Impact Areas
External Dependencies Sprint length Status
Projected outcome is a phased-implementation plan, timeline outlining phase schedule and Information Architecture (IA).
Jan 2016 Enhanced user testing
The finalisation and implementation of user testing annual plan.
Measure and review the requirements of the user and the success of changes to the web site.
Operational excellence.Global engagement.Outstanding student experience.
Access to suitable user groups for testing.
On going Complete
Notes:
User testing ongoing
Jan 2016 Research Research content review and aligning university priorities
• scope requirements• marketing and strategic
prioritiesProjected outcome is a phased-implementation plan, timeline outlining phase schedule and information architecture.
World-leading innovation and impact.Global engagementOutstanding student experience.
Availability of University staff with research, strategic and marketing overview.
Guidance on research priorities.
4 weeks On hold – research themes under review by senior management team
Jan 2016 Student information
Student information Phase 2:Implementation of student information identified in Phase 1 as required:-
Information Architecture (IA) construction
Outstanding student experience.Global engagement
Availability of University staff involve in student communications, marketing, support and provision of facilities with responsibility in this area.
4 weeks Complete
Notes:
Workshops with around 40 members of staff
Updated – March 2016 - Page 2 of 15
[2015 - 2016 Development Plan]
WEB TEAM COLLABORATIVE WORK
Time Line Development Area Sprint(s) Outline
Strategic Impact Areas
External Dependencies Sprint length Status
Content audit Content creation Functionality
development
designed, planned and completed
Team toolkit developed
Courses – career tab improvements completed and on live site
Jan 2016 Personalisation Personalisation Phase 1 Personalisation
technical framework development
Personalisation content framework construction
The development of a personalisation implementation time line
Development plan Implementation of
personalised content on live site
Outstanding student experience.Global engagement.Operational excellence.
4 weeks Complete
Jan 2016 Digital brand Documentation of digital brand rules.
• Work with Media & Corporate Communications colleagues to develop key brand rules.
Operational excellenceOutstanding student experience.Global engagement
Availability of communications & marketing staff.
Sign off procedures.
4 weeks On hold
Notes:
Waiting for input from other marketing colleagues
Updated – March 2016 - Page 3 of 15
[2015 - 2016 Development Plan]
WEB TEAM COLLABORATIVE WORK
Time Line Development Area Sprint(s) Outline
Strategic Impact Areas
External Dependencies Sprint length Status
Feb 2016 Features pages The development of ‘features’ templates to allow the presentation of one-off pages of extra interest ie pages highlighting a particular example of University innovation.
Global engagementOperational excellence.
2 weeks On hold
Notes: other priorities
Feb 2016 Personalisation Personalisation Phase 2 Further development
and implementation of personalisation
Implementation of personalised content on beta site
Outstanding student
experience.Global
engagement.
Operational excellence.
Charlie is leaving end of Feb 2016
3 weeks Complete
Notes:demonstrated at Web Forum
Feb 2016 Student information
Student information – application experience
Workshop delivery Begin to map
application journey
Outstanding student experience.Global engagement
3 weeks Complete
Feb 2016 Student information
Student information – accommodation
Review of existing information
Development of new design and IA
Photography arranged
Outstanding student experience.Global engagement
Availability of accommodation staff, University photographer and access to accommodation.
3 weeks Complete
Feb 2016 Staff profiles Staff profile – ongoing Global Availability of other technical 3 weeks Complete
Updated – March 2016 - Page 4 of 15
[2015 - 2016 Development Plan]
WEB TEAM COLLABORATIVE WORK
Time Line Development Area Sprint(s) Outline
Strategic Impact Areas
External Dependencies Sprint length Status
improvements – early development work on:
Groupings PGR profiles Social media buttons
engagement.Operational excellence.
staff. Potential data protection issues.
Feb 2016 Font Font - review and implementation
Test on fezzi and beta sites
Global engagement.Operational excellence
3 weeks Complete
Notes:
Further development and testing required
Feb / March 2016
Why Strathclyde? Why Strathclyde Phase 1: Review of corporate
supporting information Production / migration of
content over to the new site
IA review and enhancement as required
Further development plan
Global engagementOperational excellence.
Availability of University staff involved in communications, marketing, statutory requirements for central corporate information.
4 Weeks Complete
Notes:
Priority area identified as Court pages. Section designed and populated, waiting for content and sign off from Strategy & Planning team.
March 2016
Research centres The development of a research centre site template.
Identify requirements IA construction Template for roll out to
others centres
World-leading innovation and impact.Global engagementOperational excellence.
Availability of a pilot research centre staff to work with web team.
4 weeks Moved to April
Notes:
AFRC has agreed to work with us as one of the first centres. PNDC is on Beta site but not
Updated – March 2016 - Page 5 of 15
[2015 - 2016 Development Plan]
WEB TEAM COLLABORATIVE WORK
Time Line Development Area Sprint(s) Outline
Strategic Impact Areas
External Dependencies Sprint length Status
approved.
March 2016
Google Analytics Overview of Google Analytics to enable the team to
extract the insights we need to understand user behaviour
ensure everyone can run a basic report in GA
identify other ways we can measure performance
World-leading innovation and impact.Global engagementOperational excellence.
Identification of external company
1 week Complete
March 2016
Student information
Student information - implementation of Student Information identified in Phase 1 as required:-
Information Architecture (IA) construction
content audit content creation functionality
development
Outstanding Student Experience.Global engagement
Availability of University staff involved in student communications, marketing, support and provision of facilities with responsibility in this area.
4 weeks Complete
Notes:
Student application journey mapped out – to be reviewed
March 2016
Alumni Deliver of alumni information – in partnership with the Big Partnership:-
review of corporate supporting information
production / migration of content over to the new site
Global engagement
Availability of alumni staff. 8 weeks (Jamie from Big will work 2 days a week)
Ongoing
Updated – March 2016 - Page 6 of 15
[2015 - 2016 Development Plan]
WEB TEAM COLLABORATIVE WORK
Time Line Development Area Sprint(s) Outline
Strategic Impact Areas
External Dependencies Sprint length Status
handover to alumni team
March 2016
Technical debt Outstanding technical work including:
Geo personalisation Mobile Header CRM T4 Upgrade preparation Font
Operational excellence
3 weeks Ongoing
April 2016 Student information
Student information – registration process
Information Architecture (IA) construction
Content audit Content creation Functionality
development
Outstanding student Experience.Global engagement
Availability of University staff involved in student communications, marketing, support and provision of facilities with responsibility in this area.
3 weeksComplete
April 2016 Student information
Student information – accommodation – phase 2
Information Architecture (IA) construction
Content creation
Outstanding student Experience.Global engagement
Availability of accommodation staff, University photographer and access to accommodation.
3 weeksComplete
April 2016 Student information
Student information – equality & diversity services
Information Architecture (IA) construction
Outstanding student Experience.Global
Availability of Equality staff. 3 weeks Complete
Updated – March 2016 - Page 7 of 15
[2015 - 2016 Development Plan]
WEB TEAM COLLABORATIVE WORK
Time Line Development Area Sprint(s) Outline
Strategic Impact Areas
External Dependencies Sprint length Status
Content audit Content creation Functionality
development
engagement
April 2016 Alumni The development of the Alumni section of the web site.
User journey analysis Content audit IA development Page/content
construction
Global engagement
Availability of Alumni team to work with web team.
4 weeks Complete
April 2016 AFRC The development of the AFRC section of the web site.• User journey analysis• Content audit• IA development• Page/content construction
World-leading innovation and impact.Global engagementOutstanding student experience
Availability of AFRC team to work with web team.
3 weeks Ongoing
May2016 Student information
Student information – accommodation.
Outstanding student experience.Global engagement
Availability of University staff involved in student communications, marketing, support and provision of facilities with responsibility in this area.
4 weeks Complete, section live on beta
May 2016 Research Research – tbc World-leading innovation and impact.
Availability of University staff with research strategic and marketing overview.
4 weeks On hold – awaiting guidance from Tim Bedford.
Updated – March 2016 - Page 8 of 15
[2015 - 2016 Development Plan]
WEB TEAM COLLABORATIVE WORK
Time Line Development Area Sprint(s) Outline
Strategic Impact Areas
External Dependencies Sprint length Status
Global engagementOutstanding student experience.
Guidance on research priorities.
May 2016 Personalisation Continued development, tbc World-leading innovation and impact.Global engagementOutstanding student experience.
Ongoing – delayed after Charlie left the team.
May 2016 Maps Maps Phase 1:The development of a framework for including maps on the web site.
If possible the inclusion of building floor plans
The user of maps on staff pages
Maps for “visitors” Mobile version Inclusion on events
pages – eg graduations, open days
Global engagementOperational excellence.
Availability of required staff from Estates and IS.
Google API for maps.
4 weeks On hold
Updated – March 2016 - Page 9 of 15
[2015 - 2016 Development Plan]
WEB TEAM COLLABORATIVE WORK
Time Line Development Area Sprint(s) Outline
Strategic Impact Areas
External Dependencies Sprint length Status
May 2016 IPPI Development of IPPI section of the web site.
User journey analysis Content audit IA development Page/content
construction
World-leading innovation and impact.Global engagementOutstanding student experience
Availability of AFRC team to work with web team.
3 weeks Complete – section live on website
April 2016 Alumni 2nd phase of the development of the Alumni section of the web site.
User journey analysis Content audit IA development Page/content
construction
Global engagement
Availability of Alumni team to work with web team.
4 weeks Complete – section live on beta site
May 2016 Research centres - generic
Development of generic research section of the web site.
IA development Page/content
construction Guide for users Build section on beta for
users to access
World-leading innovation and impact.Global engagementOutstanding student experience
3 weeks Complete – section live on beta site
Updated – March 2016 - Page 10 of 15
[2015 - 2016 Development Plan]
WEB TEAM COLLABORATIVE WORK
Time Line Development Area Sprint(s) Outline
Strategic Impact Areas
External Dependencies Sprint length Status
May 2016 AFRC 2nd phase of the development of the AFRC section of the web site.• User journey analysis• Content audit• IA development• Page/content construction
World-leading innovation and impact.Global engagementOutstanding student experience
Availability of AFRC team to work with web team.
3 weeks Complete – section live on beta
June 2016 Review Integration and consolidation: Review the progress to
date and reassess plan Integration of new
developments into current site.
Analytics review Analysis of user testing
Operational excellence.
4 weeks
July 2016 Student information
Student information - tbc Outstanding student experience.Global engagement
Availability of University staff involved in student communications, marketing, support and provision of facilities with responsibility in this area.
4 weeks
July 2016 Search Review and enhance the search functionality on all areas of the site:
SEO review. Full site search (GSA) On site searches (eg
staff, course, country)
Outstanding student experience.Global engagement
4 weeks
Updated – March 2016 - Page 11 of 15
[2015 - 2016 Development Plan]
WEB TEAM COLLABORATIVE WORK
Time Line Development Area Sprint(s) Outline
Strategic Impact Areas
External Dependencies Sprint length Status
August 2016
Student information
Student information - tbcOutstanding student experience.Global engagement
Availability of University staff involved in student communications, marketing, support and provision of facilities with responsibility in this area.
4 weeks
August 2016
Personalisation Personalisation tbc Implementation of
agreed developments from phase 1
Analytics review Phase 3 content
creation
Outstanding student experience.Global engagement.Operational excellence.
Availability of University staff required.Any external information or services required.
4 weeks
September 2016
Student information
Student information tbc Outstanding student experience.Global engagement
Availability of University staff involved in student communications, marketing, support and provision of facilities with responsibility in this area.
4 weeks
September 2016
Courses Review of courses and the production of a standard output for use by internal and external systems:
XCRI-CAP stands for eXchanging Course Related Information, Course Advertising
Outstanding student experience.Global engagement
Availability of staff from marketing, RIO and if required IS
4 weeks
Updated – March 2016 - Page 12 of 15
[2015 - 2016 Development Plan]
WEB TEAM COLLABORATIVE WORK
Time Line Development Area Sprint(s) Outline
Strategic Impact Areas
External Dependencies Sprint length Status
Profile
October 2016
Events Events sprint to present University events on the website
Global engagement
Events and communications team to work with web team
4 weeks
November 2016
Student information
Student information tbcOutstanding student experience.Global engagement
Availability of University staff involved in student communications, marketing, support and provision of facilities with responsibility in this area.
4 weeks
November 2016
Research Research tbcWorld-leading innovation and impact.Global engagementOutstanding student experience.
Availability of University staff with research strategic and marketing overview.
Guidance on research priorities.
4 weeks
December 2016
Review Integration and consolidation: Review the progress to
date and reassess plan Integration of new
developments into current site
Analytics review Retrofit enhancements
as requiredAnalysis of user testing.
Operational excellence.
4 weeks
Updated – March 2016 - Page 13 of 15
[2015 - 2016 Development Plan]
WEB TEAM COLLABORATIVE WORK
Time Line Development Area Sprint(s) Outline
Strategic Impact Areas
External Dependencies Sprint length Status
**APPENDIX A - STUDENT EXPERIENCE
We have identified the following content requirements which must be included on www.strath.ac.uk. For planning purposes, we have split them into four student experience areas but many of these sections of content will be appropriate for more than one stage of the student experience.
Application experience ˃˃ academic experience ˃˃ campus experience ˃˃ graduate experience
Entry routes Grades & subjects required Grade translator Courses UG/PGT Research/PGR Study abroad options Parent/carer information Teacher information Open days Pre-entry requirements Student support Bringing a family etc Meet Strathclyde (HE
conventions etc) Fees & funding Scholarships Admissions International student info Clearing information Travel information/getting to
Strathclyde Student success stories Contact information Visa information
Registration Induction information First week, what to do First year, what to expect Academic calendar Staff information/
profiles/features Course structures Exam timetables Exam support Policies and procedures IS services, wifi etc Facilities
Sports & recreation centre Accommodation/halls of
residence Eating and drinking Clubs and societies Part-time work etc Religious/spiritual information Travel around Scotland USSA and union activities Maps Building information/facilities Fitness, gyms general Council facilities Health Student counselling Glasgow Disability services Police/doctors etc
Graduation ceremonies including video streams
Alumni Unistats/job destinations Careers Service Events Further study opportunities Industry links Enterprise activities Jobs/graduate careers
Updated – March 2016 - Page 14 of 15
[2015 - 2016 Development Plan]
Updated – March 2016 - Page 15 of 15