Benefits of Implementing Primavera P6 R8.1 and Integration to Oracle Carol C. Johnson, MBA, PMP, CMQ/OE Vice President, Enterprise Applications DRS Defense Solutions Tamim Kulaly, PMP Vice President, PPM Division Project Partners Session 10638, 4/23 at 3:45 to 4:45 PM

Benefits of implementing primavera p6 r8.1 and integration to oracle ppt

Embed Size (px)

Citation preview

Benefits of Implementing Primavera P6 R8.1 and Integration to Oracle

Carol C. Johnson, MBA, PMP, CMQ/OE

Vice President, Enterprise Applications

DRS Defense Solutions

Tamim Kulaly, PMP

Vice President, PPM Division

Project Partners

Session 10638, 4/23 at 3:45 to 4:45 PM

DRS Defense Solutions

• Wholly Owned Subsidiary of DRS Technologies

• Created in 2008 when DRS was acquired by Finmeccanica (Italy)

• Focus on defense programs, engineering and manufacturing

• $1.3 billion annual rev, approx 3,000 employees

• Headquartered in Rockville, MD

• Five primary Business Units

DRS History with Primavera

• Use of Primavera since 2000 at several

DRS Divisions

• Use of the Application:

– For all Projects Planning Management

– Recourse Management

– Budget & Forecast tracking

– EVM in Limited fashion

• Integration to EBS via OP3

Outline

• New Initiative to Upgrade

– EBS, Primavera & Integration

• Corporate Challenges and Benefits

• Upgrade of Primavera and EBS and

Impacts

• Benefits going Forward

• How our Lessons Changed our Approach

New Initiative to Upgrade • Migration of business units to R12

– Change from Project Costing to Project Management Model

– Change the Resource Structure in EBS

– Change the to WorkPlan/Financial Plan Model

• Upgrade of Primavera version 7 to Primavera P6 R8.1

• Upgrade Integration Platform (P6 R8.1 to R12) via

OP3

• Timeline April 2011 to Aug 2011

Corporate Challenges • No consistent program management practices,

data, reporting, or visibility across programs would remain

• Decided to implement to other locations after this one – How to accomplish a design usable at other sites

without affecting current implementation schedule

– Proposed Solution – Keep the global team involved and updated, any changes to the system at the site should go through that team

– Consequence – knew there would be items still left to review, but at least we would have a global framework we could implement on and refine.

Corporate Challenges

• Units using different tools: MS Project, Excel, Primavera, MPM, and don’t like change

• How do you solve the problem of lots of entrenched tools and processes but go global

– Proposed Solution – Involve representatives from across the units and different functions to help identify gaps and requirements, and solutions

– Consequence – Do not mandate use of the tool up front until solutions can be shown

– Excel and reporting still remain, but original team has grown and is in tact

Other Benefits

• “Primavera is a critical tool for our business and management of our programs”

• Linking multiple schedules together easily

• Multiple baselines

• Portfolio View

• Resource Capacity Planning

• Linkage to EBS

Impact of Primavera

Upgrade and R12 Upgrade

Together

Implementation Approach

Focus on one Division

• Upgrade P6 R7 to P6 R8.1

• Upgrade EBS 11.5.10 (Project Costing Model) to

R12 (Oracle Project Management Model)

• Focus on one division as a Pilot

• Implementation Team

– DS Project Management

– Vendor 1 – EBS Upgrade

– Vendor 2 – Primavera and Integration Upgrade

– Tight timeline

Implementation Challenges • P6 Upgrade to Web Platform:

– Harder to Transition to Web Platform. UI differences

impacted adoption

– Had to still provide P6 R8.1 client to limited users

– IT involvement to maintain and support a global

Platform

• Migration of Projects (Not as Simple):

– Changes to the Configuration impacted the

migration effort - (EPS, OBS, Codes, Recourses, etc

were all changed.

– Project Budgets had to be migrated from the old

Resources Model to New Resources Model

Implementation Challenges • Oracle Project Management vs Oracle Project

Costing

– Business Users did not have a good

understanding of the differences

– Changes to the Budgeting Process

– Changes to the Resource Planning Structures

– Understand differences between Work Plan

and Financial Plan

– Migration of Projects (Not as Simple):

Impact on Integration

Prima

P6 V7

Project Header Sync

WBS/Tasks/Dates

(Structure)

Budget Update at

Resource Assignment

and WBS Log Level

(Cost)

Actual Financial Costs &

Effort

Scheduled Progress

Classification Codes

Global Resources &

Rates

EBS

R12.1.1

Proj

Mgmt

Primavera P6 R8.1

Activity Coded to DFF

Current Data Flow

OP3 Upgrade

• OP3 Needed to be tested and certified

quickly on 8.1 and R12 to make the

deadline

• Changes made in what would be linked

and synchronized between EBS and P6

– Actual Costs

– Some customizations were removed

Overall Challenges • Underestimated the impact of EBS upgrade

on data flow

• Underestimated the migration effort

• Coordination between teams was not as expected. – This included between EBS and Primavera, but

also Primavera and the technical team.

• Testing suffered (CRP/UAT) was not fully flushed as some data was always missing.

• Delay in Delivery of Project. (Over Budget/Schedule)

Post-Upgrade • After the upgrade, had to complete migration of unit’s

programs into P6

• 3 months to migrate, link, and work out any kinks

– WBS task order out of synch with EBS

– Templates not set up correctly in EBS

– Duplicated resources

– Performance issues

– Java client issues

– Bug in PSI number in EBS (remains an issue)

Benefits Going Forward

Global Framework

• Global Framework wasn’t completed during the

initial implementation

• PM Working Group defining common practices

now

• Primavera Working Group-Implementation Team

working to define gaps and solutions to meet

those requirements

• Global Design currently in motion

Resources • Global Resource Usage Capacity Planning

• Current: Department Only

• Future: Consistent Resource Lists at a mid/aggregated

level with Department, Speciality, Level, Location, Average

Rate

• This plan will span into other types of tools and reporting

Example Resource Map Old Title

HR Title

Pool title

Location

Avg Rate

Esc 1 Esc 2 Esc 3 Esc 4 Esc 5

Technical Engineer I

Technical Engineer JR

Dayton, OH

$50 $52 $55 $58 $63 $65

Technical Engineer II

Technical Engineer JR

Dayton, OH

$50 $52 $55 $58 $63 $65

Technical Engineer II

Technical Engineer JR

Cypress, CA

$70 $73 $78 $81 $84 $87

Technician Level 3

Technical Engineer III

Technical Engineer Mid

Cypress, CA

$80 $83 $86 $89 $91 $93

WBS/CBS Templates

• Set of templates that can be mixed and matched

by type of project and provide common reporting

• Current: No templates or Activity Codes are

implemented

• Future: Templates include Activity Codes to map

between required CBS and Program’s WBS

Example WBS / CBS CWBS Task name PM WBS Task Name

1 Program Management and Support 1 Program Management

1.1 Program Management 1.1 Program Planning

1.2 Program Support 1.2 Program Monitoring & Control

1.2.1 Developmental Quality Assurance 1.3 Customer Management Reviews

1.2.2 Project Training 1.4 Subcontract/ Material Management

1.2.3 Project Work Environment (if not capital) 1.5 Project Training

1.6 Project Closure

1.7 Project Work Environment

2 System Development 2 System Development

2.1 Technical Reviews and Management 2.1 System Requirements Definition (Requirements

Analysis)

2.2 Systems Engineering 2.2 System Architecture Design

2.3 Support Engineering

2.4 Internal Reviews/Meetings

2.5 Customer Technical Reviews

2.6 Program Support

3 Product Development 3 Product Engineering

3.1 CI #1 3.1 Configuration Item #1

3.2 CI #2 3.1 Configuration Item #2

4 System Test and Evaluation 4 System Integration and Test (Product Integration

Verification and Validation)

4.1 Integration, Verification, Validation 4.1 Test Plans & Procedures

4.2 Test Equipment

4.3 Integration Test

4.4 Risk Reduction Test / HALT

4.5 System Verification & Validation Tests - Internal

4.6 PIVV / Formal System Qualification

CBS WBS

Apply Activity Code

WBS turns to CBS View

Project and Activity Codes

• Sets of Consistent Project and Activity Codes to

use for global reporting

• Current: Not defined yet, only at unit level

• Future: Define sets of codes that will be

common and those that are optional

Operations Data

• Provide program managers the ability to

see key operations data and analyze

affect on the program

• Current: No link to Operations data, all

manual

• Future: Link to key summary data in

MRP/ASCP in EBS

Reports • Define the key set of reports needed for different

levels of users that are consistent so that ALL Program

Reporting comes out of Primavera as much as

possible

• Current: Only using the workbooks

• Future: Define required data sets from out of the box

as much as possible, but also using BIApps as needed

• This project intersects with a general ERP project to

globalize and consolidate ALL reporting in our systems

Other Plans

• Implement the Risks functionality in P6

– Look at Risk Module in future

• Define the best way to get ETCs into the

system from workers that is quick but

allows for discussion and collaboration

• Look at P6 Analytics in the Future

How our Lessons

Changed our Approach

Lessons and Changes • Vision

– Global Framework is the primary goal not schedule

– Communication of vision and approach occurs

constantly to all levels

– Vision is tool agnostic in many ways

• Sponsorship

– Vision comes from the highest levels of the company

so has teeth

– PM Working Group chaired by Senior Execs

Lessons and Changes • Teams

– Single project/program manager to coordinate across

aspects

– Oracle EBS and Primavera support team overlaps

Kept the Same

– Maintain the PM Working Group for requirements, but

the Implementation team is more hands on – with

overlap

– Teams should be cross-functional and cross unit

Lessons and Changes • Training

– Training is split into pieces so not all at once

• Just complete basic training on PMs for sandbox

• Will do 2-3 day trainings every 45 days or so

– Train key team individuals up front

– Work side by side with partners to learn the

system

Lessons and Changes • Technical

– Defined CM and Instance Management

Strategy

– Environment stable and in place with support

plan implemented

– Performance issues seem resolved

– Testing and piloting will be key to the process