BelarusDenmarkEstoniaFinlandGermanyLatviaLithuaniaNorwayPolandRussiaSweden
Financial Report
BSR INTERREG III B Joint SecretariatRostislav Zatloukal
Seminar on Financial Management and Auditing Rostock, 12 November 2004
Financial Report
The financial report (FR) has to provide information about:
allocated costs per work package (FR I)
used financial sources and the confirmation by an independent auditor (FR II)
other costs, equipment and in kind contribution (FR IIIa)
small scale investments carried out in the reporting period (FR IIIb)
changes of non-eligible budgets
division of eligible expenditures by PP and reporting period/MS
Financial reportBSR INTERREG III B *** Progress Report *** Cover Sheet
1
Contact person:Institution:
Account no. / IBAN:
(pre-filled by JS)
01.07.2004 - 31.12.2004 Number of the report:Reporting period:
Project name:
Name of LP: (pre-filled by JS)
Contact information Project co-ordinator/Project managerLead Partner (LP)
E-mail:
Address:ZIP code, city:
SWIFT code:National bank code:
Address:
Holder of the account:
Contact person:
Country:
Bank information
Web: (Homepage of the LP institution)
Name of the bank:Address:
Telephone:Fax:
(Project homepage)
Internal reference:
Institution:
ZIP code, city:Country:Telephone:
Auditor
Web:
Contact information Financial Manager
Fax:E-mail:
Financial report
Cover sheet – part 2
Number of pages:
Confirmation by lead partner (LP)
0,00
5. Financial report IIIa, FR_others6. Financial report IIIb, FR_investments7. Financial report IV, FR_non-eligible8. Financial report V, FR_partner_budgets
(further documents e.g. broschures, presentations, explanations, ...)
Place, Date:
The information and documentation in this progress report and its attachments gives a correct description of the implementation and the present status of the project. The total request of payments of ERDF and Norwegian grants amounts to: EURO
Signature, Stamp:
Name, Position:
List of all attachements to this report:1. Progress report cover sheet (incl. signature by LP)2. Activity report (separate Word-file)3. Financial report I, FR_expenditures4. Financial report II, FR_finances (incl. signature by auditor)
Financial report
BSR INTERREG III B *** Financial Report I *** Eligible Expenditures
Project name:Reporting period: 1
TotalBudget
Previously reported
Current Report
Remaining Budget
[Euro] [Euro] [%] [Euro] [Euro] [Euro]1 408.438,37 0,00 0,00 0,00 408.438,372 1.200.712,24 0,00 0,00 0,00 1.200.712,243 50.882,48 0,00 0,00 0,00 50.882,484 130.700,00 0,00 0,00 0,00 130.700,005 121.430,00 0,00 0,00 0,00 121.430,006 14.020,00 0,00 0,00 0,00 14.020,007 21.652,63 0,00 0,00 0,00 21.652,63
1.947.835,72 0,00 0,00 0,00 1.947.835,72
1 69.246,12 0,00 0,00 69.246,122 223.053,86 0,00 0,00 223.053,863 8.932,00 0,00 0,00 8.932,004 25.163,00 0,00 0,00 25.163,005 4.766,00 0,00 0,00 4.766,006 4.110,00 0,00 0,00 0,00 4.110,007 1.211,88 0,00 0,00 0,00 1.211,88
336.482,86 0,00 0,00 0,00 336.482,86
Travel and accommodationMeetings and dissemination
(pre-filled by JS)
Personnel (incl. OH)Project co-ordination
Summary budgetBudget line and specification Total cumulated reported
(previously+current)
01.07.2004 - 31.12.2004 Number of the report:
Project co-ordinationPersonnel (incl. OH)Meetings and dissemination
External expertise
TOTALSmall scale investmentsOther
SUB TOTAL
Travel and accommodationExternal expertiseOtherSmall scale investments
WP 2 - WP5
WP 1
Financial report
Financial report
BSR INTERREG III B *** Financial Report II *** Expenditures financed by ... (indicative financial table)
0,00
Project name:Reporting period:
(pre-filled by JS)01.07.2004 - 31.12.2004 1Number of the report:
Total eligible expenditures in current report [Euro]
[Euro] [Euro] [%] [Euro] [Euro]A 174.200,00 0,00 0,00 174.200,00B 0,00 0,00 0,00 0,00C 1.773.635,72 0,00 0,00 1.773.635,72
1.947.835,72 0,00 0,00 1.947.835,72
D 0,00 0,00 0,00 0,00E 152.000,00 0,00 0,00 152.000,00F 38.000,00 0,00 0,00 38.000,00G 607.500,00 0,00 0,00 607.500,00H 0,00 0,00 0,00 0,00I 0,00 0,00 0,00 0,00J 0,00 0,00 0,00 0,00K 0,00 0,00 0,00 0,00L 0,00 0,00 0,00 0,00
797.500,00 0,00 0,00 797.500,00
2.745.335,72 0,00 0,00 2.745.335,72
TOTAL II
TOTAL I + II
Tacis fundingTacis national co-financingNational financing (BY,RU)Private financing (BY,RU)
PHARE fundingPHARE national co-financing
Norway
National financing (EE,LV,LT,PL)Private financing (EE,LV,LT,PL)
BSR EU Non-Objective 1 areas TOTAL I
Non eligible / other expenditures financed byBSR EU Member States, Norway
BSR EU Objective 1 area
Eligible expenditures financed by
Project partner coming fromTotalBudget
Previously reported Current Report
Remaining Budget
[%] [Euro] [Euro] [%] [Euro] [Euro]
75,00 130.650,00 0,00 0,00 130.650,0050,00 0,00 0,00 0,00 0,0050,00 886.817,86 0,00 0,00 886.817,86
52,24 1.017.467,86 0,00 0,00 1.017.467,86
Previous payments
Current paymentrequest Remaining
Interreg co-financing
Rate Maximumallocation
Financial report
FR II – part 2Confirmation by an independent auditorBased on our examination, we verify:1. The reality of "deliverables" (services, works, supplies, etc.) against plans, invoices, acceptance documents,
experts' reports, etc., and, where appropriate, on the spot;2. The observance of conditions of grant approval (Approval Letter and Subsidy Contract);3. The eligibility of amounts claimed (Commission Regulation (EC) No 448/2004) and the correctness of this
financial report;4. The adequate follow-up of all outstanding questions before acceptance of claim;5. The maintenance of an adequate and reliable accounting system and the maintenance of the audit trail
(Commission Regulation (EC) 438/2001, Annex I) at all levels within the project;6. During the reporting period covered by this report the first costs have been paid on ___________ (date) and
the last costs have been paid on ___________ (date). In the case of the first progress report, the first costs incurred on ___________ (date).
7. For this financial report the total paid eligible expenditure amounts to € _________________ .8. The project management set up has been established as described in the project application (Point 10).
The auditor confirms that she/he is independent from the project and has observed all relevant national auditing standards.
Place: __________ Name: __________ Signature: __________
Date: __________ Position: __________ Stamp: __________
Financial report
BSR INTERREG III B *** Financial Report IIIa *** Others
01.07.2004 - 31.12.2004 Number of the report: 1
Specification of cost item Location Amount (EUR)
0,00
0,000,00
Please do not add new lines, collumns and rows!
For adding further information about the investments please use footnotes or additional documents!
TOTAL
(pre-filled by JS)Project name:Reporting period:
Subtotal
Subtotal
WP2 - WP5
WP1
Specification of budget line no 6 Others of the actual reportWP #
Financial report
BSR INTERREG III B *** Financial Report IIIb *** Investments
01.07.2004 - 31.12.2004 Number of the report: 1
Specification of cost item Location Amount (EUR)
0,00
0,000,00
Please do not add new lines, collumns and rows!
For adding further information about the investments please use footnotes or additional documents!
TOTAL
(pre-filled by JS)Project name:Reporting period:
Subtotal
Subtotal
WP2 - WP5
WP1
Specification of budget line no 7 Small scale investments of the actual reportWP #
Financial report
BSR INTERREG III B *** Financial Report IV *** Changes of the non-eligible budget
D 0,00 0,00E 152.000,00 0,00F 38.000,00 0,00G 607.500,00 0,00H 0,00 0,00I 0,00 0,00J 0,00 0,00K 0,00 0,00L 0,00 0,00M 0,00N 0,00O 0,00P 0,00
797.500,00 0,00TOTAL II
Tacis fundingTacis national co-financingNational financing (BY,RU)Private financing (BY,RU)
Approved/received budgetNon eligible / other expenditures financed by
Remarks
Project name:Reporting period:
(pre-filled by JS)01.07.2004 - 31.12.2004 1Number of the report:
Private financing (EE,LV,LT,PL)National financing
BSR EU Member States, NorwayPHARE fundingPHARE national co-financing
Planned budget
Financial report
BSR INTERREG III B *** Financial Report V *** Division of eligible expenditures by project partner and reporting period
1.1.-30.6. 1.7.-31.12. 1.1.-30.6. 1.7.-31.12.
1 PP1 FI 363.867,72 - 363.867,72 - - - -
2 PP2 FI - - - - - - -
3 PP3 FI 135.000,00 - 135.000,00 - - - -
4 PP4 FI 86.000,00 - 86.000,00 - - - -
5 PP5 FI 174.200,00 - 174.200,00 - - - -
6 PP6 FI 33.600,00 - 33.600,00 - - - -
7 PP7 DE 660.000,00 - 660.000,00 - - - -
8 PP8 DE 50.000,00 - 50.000,00 - - - -
9 PP9 DE - - - - - - -
10 PP10 DK - - - - - - -
11 PP11 DK - - - - - - -
12 PP12 DK 385.168,00 - 385.168,00 - - - -
13 PP13 DK 60.000,00 61.000,00 - 1.000,00 - 61.000,00 -
14 PP14 LT - - - - - -
50 - -
1.947.835,72 61.000,00 1.886.835,72 - 61.000,00 - -
2005
No. Reporting periodReporting period
2004
Total
Budget remainingPartnerExpenditures
reportedBudgetCountry
To avoid irregularities, the reported expenditures...
have to be paid within the reporting period concerned
have to be eligible (according to BSR INTERREG III B rules, EU rules and national rules)
have to be assigned to the correct BL and WP (according to BSR INTERREG III B rules)
have to be documented (in particular personnel costs: time sheets and overhead costs: calculation scheme)
Financial report
Most frequent shortcomings in the Financial Reports
General:
• changed structure of the reporting form (AR, FR)
– cells/formulas changed, figures filled in manually
• late reporting
• changes done without a prior agreement with JS
• missing signatures and/or stamps
Cover sheet:
• bank information
• Payment request amount does not match FR II
Most frequent shortcomings in the Financial Reports
Financial Report I:
• given budget of the particular BL is exceeded
• costs are reported under wrong BL and/or WP
• costs do not correspond to the Activity report
Financial Report II:
• Current payment request does not match Cover sheet
• non eligible expenditures (lines D-L) are not reported
• dates of the costs incurred/paid are not filled in
• auditor changes the confirmation text
Most frequent shortcomings in the Financial Reports
Financial report IIIa/b:
• items are not clearly specified
• location/PP of the equipment/investment is not in line with the application
• amount of the equipment/investment is higher than stated in application
• changes done without the prior agreement with JS
Financial report V:
• project partners´budgets are exceeded
http://www.bsrinterreg.net
More information are available at our homepage: