Upload
dangdan
View
221
Download
2
Embed Size (px)
Citation preview
1
BEFORE THE NATIONAL GREEN TRIBUNAL
PRINCIPAL BENCH
NEW DELHI
APPEAL NO. 8 OF 2011
In the matter of :
1. North East Affected Area Development Society (NEADS) Through Girin Chetia, Director
Post & Village Dhekiokowa District-Jorhat Assam -785700
2. Bimal Gogoi
Chandmari, Majar Ali PO-Golaghat Assam …..Appellants
Versus
1. Union of India
Through the Secretary Ministry of Environment & Forests Paryavaran Bhawan CGO Complex, Lodhi Road New Delhi-110003
2. Arunachal Pradesh State Pollution Control Board Through Member Secretary APSPCB Itanagar Arunachal Pradesh-791111
3. M/s Athena Demwe Power Pvt. Ltd. Through the Managing Director 1st Floor, NBCC Tower 15 Bhikaji Cama Place New Delhi- 110066
4. State of Arunachal Pradesh Through the Chief Secretary Civil Secretariat Itanagar, Arunachal Pradesh-791111
5. Mr. P. Abraham .….Respondents
2
Counsel for Appellants: Mr. Ritwick Dutta and Mr. Preeta Dhar, Advs (in Appeal No. 8 of 2011). Counsel for Respondents: Mr. Vivek Chib with Mr. Asif Ahmed, Advs., Mr. Joby Varghese, Adv, Ms. Ruchika Goel, Adv., Mr. Kushal Gupta, Adv. for respondent no. 1. Mr. Tarun Johri and Mr. Ankur Gupta, Advs. for respondent no.3 Mr. A.D.N. Rao and Mr. Sudipto Sircar, Advs. for respondent no.4
ORDER/JUDGMENT
PRESENT :
Hon’ble Mr. Justice Dr. P. Jyothimani (Judicial Member) Hon’ble Mr. Justice U.D. Salvi (Judicial Member) Hon’ble Dr. G.K. Pandey (Expert Member) Hon’ble Ranjan Chatterjee (Expert Member)
Dated : 13th January, 2015
1. Whether the judgment is allowed to be published on the net? 2. Whether the judgment is allowed to be published in the NGT Reporter? JUSTICE DR. P. JYOTHIMANI (JUDICIAL MEMBER):
1. On conclusion of the arguments by all the respective counsel
we have pronounced the following brief order in the open court on
this day.
“We have heard the learned Counsel appearing for appellant as well
as respondents in detail. We are satisfied that there are absolutely
no merits on all the grounds, raised by the learned counsel
appearing for appellant. Accordingly Appeal No.. 8 of 2011 stands
dismissed. There is no order as to cost. Reasons for Judgment to
follow”.
Accordingly, we proceed to give our detail reasoning in the form of
Judgment which are as follows-
3
2. This appeal is directed against the Environment Clearance
granted by the MoEF dated 12.02.2010 to the Demwe Lower
HEP (1750 MW) project in Lohit District of Arunachal Pradesh
under taken by M/s Athena Demwe Power Pvt. Ltd. The
appellant is an NGO working in upper Assam on livelihood and
development issues. North East Affected Area Development
Society (NEADS) who is the first appellant is working with
disaster affected communities with the right to food and
livelihood as a major thrust area and has also been working
with local communities in Sadiya sub-division of Tinsukia
district of Assam, which is part of both Lohit and Dibang river
basins. The first appellant has also made submissions to the
MoEF during the appraisal stage of the project. The second
appellant is an environmental activists from Assam who has
also made submissions before the MoEF against the project in
respect of which environmental clearance has been granted by
MoEF. It is a Hydro Electric Project (HEP) envisaging
construction of a concrete gravity dam of 163.12 m height
above deepest foundation level (124.8 m above average river bed
level) across river Lohit in Lohit District, Arunachal Pradesh.
The third respondent is the project proponent which is a
company responsible for implementing the project. It is the
case of the appellants that in the downstream stretches the
Lohit river flows through the State of Assam before joining the
Dibang and Siang to form Brahmaputra river in Assam. It is
further stated that the maximum water level and FRL of the
4
project are appraised at the elevation of 424.8 m. The
minimum draw down level will be at the elevation of 408 m with
live storage of about 171.20 M.cum. It is stated that the SRC
power house is right back to the Lohit river to accommodate five
vertical Francis Turbines of 342 MW each and one unit of 40
MW to generate a total installed capacity of 1750 MW. The total
land proposed to be acquired for the project is 1589.97 ha
including submergence area of 1131 ha consisting of 174.05 ha
as community Jhum land, 720 ha under Community Forest,
192 ha under Reserved Forest and 502.92 ha as River Bed
(Forest Land). According to the appellants the acquisition of
land will affect 23 villages/hamlets and around 204 project
affected families are likely to lose their land. However, it is
stated that the total land and the people impacted by the
project has been grossly underestimated and in reality the
numbers are much higher.
3. The project was considered by the Expert Appraisal Committee
(EAC) for River Valley and Hydro Electric Projects (HEP) at its
meeting held on 22.10.2009, 16.11.2009 and 16.12.2009 and
ultimately 1750 MW Demwe Lower Project was granted
Environment Clearance on 12.02.2010 by the MoEF namely
respondent no. 1.
4. According to the appellants, the respondents have shown
great disregard to the Environment Impact Assessment Notification,
2006 (EIA Notification 2006) both at the scoping as well as at the
public hearing stages. According to the appellants the EIA Report is
5
grossly in-adequate ignoring important data. The appellants case is
that the procedure followed in the scoping stage is totally faulty due
to the reason that Mr. P. Abraham, Director of one of the promoting
companies of the project proponent, was the Chairman of EAC and
therefore, the entire process has to be struck down. The scoping
being a very crucial initial stage of the process by which the EAC
determines the comprehensive Terms of Reference (TOR),
participation of the above said person which has got an element of
bias makes the entire process including EC as unsustainable in
law. It is the further case of the appellants that the project has
many lacunae including that Form 1 particulars were inaccurate
like the permanent and temporary change in land use as the major
impact of the riverine islands and the tracts in the downstream
areas in both Arunachal Pradesh and Assam being ignored, that it
also ignored the Catchment Area Treatment and Compensatory
Afforestation, that there is no mention of impacts due to
decommissioning of the project, that there is no proper answer
regarding the undeveloped and agricultural land, that there is no
detail about the possible accident resulting in explosions, spillages,
fires etc from storage, handling, use or production of hazardous
substances, that the answer has been given in negative in respect of
cumulative effects due to proximity to other existing or plant
projects with similar effects since the hydroelectric project
concerned in the EC is one among the 11 core projects with the
installed capacity of around 8200 MW, that the areas of sensitivity
for ecological reasons like wetlands, watercourses, water bodies,
6
coastal zones, mountains, forests etc have not been properly
explained except a reference made relating to Kamlang Wildlife
Sanctuary, that there is no reply regarding the area containing
important high quality or scarce resources including the important
area for religious tourism in Parasuram Kund.
5. The conflict of interest has been raised by the appellants on
the ground that the Chairman of EAC which examined the project
namely Mr. P. Abraham was a Director on the Board of PTC India
Ltd which is one of the 3 promoters of the project in question; As
PTC India Ltd, has invested Rs 30 Crores in Athena Energy
Ventures Private Ltd and committed to invest 150 Crores, the
Committee headed by Mr. P. Abraham played a critical role in the
scoping stage and an interested person himself has been sitting for
clearing the project and therefore the subsequent decision taken by
EAC is doubtful of any credibility. This according to the appellant
is because of the reason like the non consideration of crucial issue
by EAC regarding downstream impacts of the dam which includes
loss of fisheries, change in wetland ecology in the flood plains,
agricultural losses due to massive daily fluctuations in flow,
increased flood vulnerability due to massive boulder extraction from
river beds and sudden water releases from reservoirs. The
downstream impact study relating to Arunachal Pradesh as well as
Assam is relevant which according to the appellants have been
ignored. The only study goes beyond 10 Km as per TOR analysis
which relates to the flooded downstream if the dam breaks. There
is no other relevant study made which includes the habitation
7
importance of bird area etc. It is also the case of the appellants
that while granting Environmental Clearance, upper and lower
Demwe were deliberately delinked from the cumulative river basin
study especially when 11 hydroelectric projects are planned in Lohit
river basin, six on the main Lohit river itself at a distance of 86
kms. The EAC has prescribed advanced cumulative study in the
Lohit river basin. The decision of EAC under the Chairmanship of
Mr. P. Abraham that the environmental clearance to Demwe Upper
and Lower HE Project should not be linked with the completion of
basin study is improper. As the decision taken in EAC meeting on
15th and 16th December, 2008 states that the study will be
completed in two years by entrusting the job to WAPCOS, issuance
of Environmental Clearance should have been postponed till such
study is completed. According to the appellants, the stipulation in
the EC that depending upon the ongoing basin studies such further
recommendations shall be binding on the project developer is
meaningless and there may not be any possibility of rectifying the
defects in the EC at a later stage.
6. Apart from the objection relating to the scoping, the appellants
have also objected regarding the public hearing process. According
to the appellants, no notice of public hearing was given to the
affected people both in upstream and downstream areas and the
Gram Panchayats are not informed about the public hearing, the
people living on the downstream left and right of the Bank were not
informed and that the public hearing procedure has not been
properly followed. The comments of the interested persons were not
8
called upon by sharing the full reports with the affected persons.
Further it is stated by the appellants that EIA report submitted by
the project proponent and the appraisal have many lacunae
including that the downstream impacts of the dam has not been
considered, that the study going beyond 10 kms downstream
regarding dam break analysis is of no use that after public
consultation, the study made by the project authority on a partial
water flow study for a longer distance of approx. 40 km only for
predicting the impact on fish on the free spawning and spawning
period by ignoring several other material facts like daily flow
fluctuation, winter cold water flood, chapories (Riverine Islands and
Tracts) of Lohit river both in Arunachal Pradesh and neighbouring
Assam, devastating impact on wildlife by the winter flood are all
lethal to the EC granted for the project. The appellants would state
that after commissioning of 1750 MW Demwe Lower Project there
will be a daily drastic fluctuation namely that everyday of 18/19
hours the flow of water will be 35 cumecs which will shoot up
drastically for 5-6 hours in a day to an abnormal extent of 1729
cumecs. This will flood the chapories, affect the habitat of species
like Bengal Florican and Swamp Francolin apart from affecting wild
buffalo, gaur, tiger, hog deer and elephants. The representations
given to MoEF by scientists and civil societies group pointing out
the faulty TOR the improper downstream study including the
wildlife biologist Firoz Ahmed and others have not been considered.
As far as Dibru-Saikhowa National Park is concerned, there will be
major fluctuation of flow in winter. Presently a flow between
9
400/500 cumecs is a contribution of Lohit and the contribution
from Dibang joining the Lohit is around 800/1000 cumecs. It
enters national parks in January, during the peaking hours where
the project on the Lohit will release 1729 cumecs and the proposed
3000 MW Debang multipurpose project on the Debang river will
release around 2853.6 cumecs water and that will submerge vast
areas and have drastic impact on the natural ecology of the area
and this aspect has not been considered by the EAC.
7. Even the appellants have raised a point that the project
proponent has not sought for permission under the Wildlife
(Protection) Act which is now not in dispute that the National Board
of Wildlife has granted clearance which is the subject matter of
disputed in another appeal. It is further stated by the appellants
that EIA report has grossly underestimated the impact of the
project on the lands of the indigenous people and environmental
clearance has been granted based on an inaccurate estimate. The
finding of EIA report that 1598 ha are likely to be impacted is
grossly inadequate. Further the report has not taken note of the
plantations in 5767 ha of land in the catchment area. Moreover,
the impact on Parasuram Kund which is an important heritage
cultural site has not been considered by the EIA report. It is stated
that the large number of pilgrims converge to Parasuram Kund
during Makar Sankranti in January. The power house and the
project will pose a serious threat to the religious sentiment and
sanctity and on wildlife apart from the serenity of the sacred site.
The MoEF has not taken note of the same in spite of having been
10
brought to its notice. India being a signatory to the Convention on
Biological Diversity should have considered the cultural,
environmental and social impact assessment regarding the
developments made in the traditional place by indigenous and local
communities.
8. It is further stated that the concerns of the citizens which were
raised were referred in a vague manner without expressing
independent opinions on various representations as decided in
various cases of High Courts and Tribunal. Therefore the decision
making process in respect of the Mega Dam suffers from gross
illegality in the absence of proper consultation including non
consideration of a representation made by a responsible Legislative
Assembly Member. The EC granted under the impugned order is in
gross violation of the principle of Precautionary Principle and the
Polluter Pays Principle as enumerated by the Hon’ble Supreme
Court in Vellore Citizens Welfare Forum Case and Arunachal
Pradesh PCB V/s Prof. M.V. Nayadu (Retd.) and Ors. It is based on
the above said averments the appellants have challenged the
validity of EC granted for the project.
9. The first respondent, MoEF, in its reply has stated by raising a
preliminary objection that the appellants having raised all these
points during the public hearing and having participated in the
process including before the EAC and those objections having been
considered by the EAC and consequently MoEF, cannot maintain
the same objections before the Tribunal. This is so, especially when
an elaborate public consultation process was followed, the
11
presentation of the project proponent as well as the objections were
considered in their proper perspectives. It is also stated that all the
objections including the downstream effects, effect on Parasuram
Kund, geological and seismicity aspects, rehabilitations have been
duly considered by the EAC which has made field visit through its
subcommittee, and recommended for issuance of the EC and
ultimately the MoEF has issued EC subject to various stringent
conditions.
10. While denying all other averments made by the appellants, it
is stated by the 1st respondent that the EAC has taken on record
the details enclosed with Form 1 during scoping appraisal for TOR
and after having been satisfied has recommended the project for
scoping and issued TOR. It is stated that as per the EIA
Notification 2006, Form 1, pre-feasibility report and proposed TOR
were submitted to the 1st respondent which were referred to EAC
which has considered on 10.07.2007 and the first respondent, on
07.08.2007 has granted scoping approval with TOR. It is stated
that subsequently the project proponent has informed the
EAC/MoEF that during the reconnaissance survey of allotted
stretch of Lohit River, it was found that the original proposal of
3000 MW Demwe HEP Project conceived by the Central Electricity
Authority (CEA) with FRL at 490m was to cause submergence of
Kamlang Wildlife Sanctuary (KWLS), and it was in order to avoid the
same that the project was divided into two stages namely Demwe
Lower HEP (Project) and Demwe Upper HEP within the allotted
stretch given by the State Government of Arunachal Pradesh. A
12
revised Form 1 was received by the 1st respondent for scoping on
01.02.2008 and the EAC directed the Model TOR approval for
North-East project to be made applicable to the project to Demwe
Upper HEP and accordingly the 1st respondent has issued a revised
TOR on 25.03.2008, in order to achieve 3000 MW project in two
stages.
11. As per the stipulation of the 1st respondent in the revised
TOR, the subgroup of EAC made a field visit of the project site on
1st and 2nd June 2008 and recommended additional conditions in
TOR and accordingly the 1st respondent has stipulated additional
TOR on 04.08.2008. Further, the project proponent has apprised
the MoEF from time to time of various parameters like Full
Reservoir Level (FRL), Maximum Water Level (MWL), Water
Availability Series, Power Potential Studies and other Technical
materials, and accordingly additional TOR have been issued to the
3rd respondent.
12. It is specifically stated that the EAC consisted of 14 Experts
from various fields and considered each and every aspect of TOR
and even though Mr. P. Abraham was the Chairman of EAC,
decisions were taken by EAC collectively and Mr. P. Abraham has
never attempted to influence the members who are independent.
Regarding the river Basin study it is stated by the MoEF that world
wide it is recognised that River Basin is developed in a cascade
manner to work out the cumulative impact of all the projects in the
River System. The purpose of basin study is only to supplement the
Environment Management Plan efforts and to optimise them for
13
ecological conservation and social upliftment of the area by
additional measures. Moreover, there was no cumulative effect in
the lower projects which are in less eco-fragile zone and that too it
being the 1st project. The EAC has noted that on Lohit river Six
HEPs are likely to come and except the said projects, no other
projects were presented before the MoEF for EC. Therefore, the
EAC has decided that basin study is required for understanding the
capacity of the river for generating hydropower after fulfilling the
requirement of water for local habitants and aquatic life. The MoEF
while granting EC has delinked the Demwe Lower and Upper
Project from the completion of basin study as it was done in Teesta,
Sikkim. Further, the delinking was done to evolve a suitable
framework to guide and accelerate the development of hydropower
projects in the North-East. It is also based on IMG in which it was
suggested that in view of uniqueness of the fragile eco-system in
North East Region (NER), due importance need to be given to
environment and forest concerns while planning the hydropower
project. It was also suggested that EIA studies may be taken up
basin wise in place of individual project to know the downstream
impact on development projects in cascading manner and minimum
release required to maintain aquatic life downstream. Therefore,
according to the MoEF, there is nothing wrong in deciding to delink
the Lower and Upper Demwe Projects from the river basin study.
13. While denying that the process of scoping was having any
lacuna, it is stated that the project proponent in Form 1 has given
information related to change in flow regime, which is the normal
14
consequence in the operation of any hydropower projects. It is also
the case of the MoEF that, as no requirement for acquisition arose,
the Catchment Area Treatment Measures and Compensatory
Afforestation Scheme is not called for. It is also stated that no
hazardous waste is to be created except explosives for blasting
purpose for which the project proponent has to obtain permission
in accordance with law. It is also stated that the Important Bird
Area (IBA) site referred by the appellants is located beyond 15 Km
from the project site.
14. It is also stated that the impact regarding influx of labour
has been considered and that the project which would span for a
period of 5 years with diverse activities, the labour and technicians
required would be around 8933 and regarding the impact due to
involvement of influx, the same has been addressed by the EIA and
an Influx Management Plan has been prepared as part EMP with
measures like segregation of the work force, health screening of
labourers before and after their employment, sensitization of
outside labourers; culture and local traditions, to provide for
designated labour camp to minimise interference with locals and
environment, sanitation etc. It is stated that in fact the EC has
provided elaborately about this.
15. The representation of Mr. Krong was considered after
verifying from the project proponent. It also stated that after TOR
was issued, the 3rd respondent has made an extensive study and
submitted its EIA report. The proposal for EC was submitted by the
project proponent on 01.10.2009 and EAC in its appraisal meetings
15
on 22.10.2009, 16.11.2009 and 16.12.2009 considered it.
Regarding the public hearing it is stated by the MoEF that the State
Pollution Control Board has conducted the same as per the rules
and large number of people have participated. The EAC has
considered the methodology in respect of each of the parameters
and recommended for issuance of EC and ultimately the MoEF,
after having been satisfied with the reasons given by the EAC, has
granted EC on 12.02.2010.
16. Regarding the flows it is the case of the MoEF that diurnal
variation due to project operation is associated with all
hydroelectric projects and such variation is also associated with
Demwe Lower HE Project. It is specifically stated from the approved
hydrological series that flow are in no way significantly higher than
the non-monsoon floods witnessed by the Lohit River System. It is
also stated that the hydro projects are site specific in nature with
varying ecological parameters.
17. While dealing with the braided river course of downstream, it
is stated by the MoEF, that while the project proponent has
sufficiently made study and answered, alternative arrangement for
migrating fishes by trapping and transportation is also widely
recognised and in fact recommended by the World Commission on
Dams Environmental Issues, Dams and Fish Migration, Final
Drafts, June 30 of 2000. Regarding the impact of Demwe Lower
HEP on Dibru-Saikhowa National Park, it is stated that the said
park is situated 100 Km downstream from the dam site. During
monsoon period where reservoir will be operated at MDDL, the river
16
flow will be normal as there is no storage. In non-monsoon period
water will be released daily during power generation, and no impact
is envisaged on the park.
18. Regarding the habitations of Gangetic dolphins it is the case
of the MoEF that as per the paper by Dr. Abdul Wakid, the area
mentioned in the report are located far away from the project site.
The nearest Dolphin sighting site, Tengapanimukh is at aerial
distance of 63.71 Km and others like Uriamghat is 103.4 Km and
Balijan is at 124.74 Km. Therefore, the project has no impact on
Dolphins. Likewise, regarding the impact on chapories, the aerial
distance of Urpad beel is about 597 Km and Deeper is about 501
Km from the dam site. The nearest chapori from the dam site is
stated to be about 33 Km along the river Lohit. Therefore, the
impact on the chapories is minimal. Regarding the sediments, the
MoEF states that the project contains adequate safeguard to flush
out the possible sediments. While meeting the averment regarding
the river bed erosion by the project, it is stated by the MoEF that
the project proponent has clarified that due to maintenance of the
reservoir at MDDL of EL 408m, the incoming flood will be
moderated in the available reservoir having a capacity of 171.2 M.
cum between MDDL of 408 m and FRL 424-8. As the velocity will
be lower there is no possibility of bank erosion. Again regarding the
impact of boulder collection from river bed for construction, the
MoEF has stated that the project proponent has made clear that the
excavation are from non-river bed areas and elaborate quarrying
measures have been explained. Therefore, according to the MoEF,
17
major effect of downstream impacts have been clarified by the
project proponent and the EAC as well as the MoEF are satisfied
about the process.
19. Regarding the compensatory afforestation, it is stated by the
MoEF, that the project proponent has undertaken to do so in
degraded forest land identified by the Forest Department.
Afforestation shall be raised in the area of 2818 ha and degraded
forest land identified in lieu of 1408.30 ha of forest land to be
diverted for execution by the project. Again, while meeting the
averments regarding the Parasuram Kund proximity, the MoEF has
stated that in fact on deliberation with the Parasuram Kund
Improvement Society (PKIS), release of water during mela period
was agreed to be regulated with various safeguards and the
regulatory measures for preserving Parasuram Kund and protecting
the devotees during “mela period” have been duly incorporated in
the conditions of EC. Again regarding the preservation of
Biodiversity, it is stated by the MoEF that the project proponent is
directed to fulfil the guidelines issued by Akwe:Kon guidelines
under convention on Biodiversity.
20. Therefore, according to the MoEF, the impugned EC has been
granted to the 3rd respondent after meticulous study make by EAC
and independent consideration by the MoEF itself by following the
entire procedure contemplated under the EIA Notification of 2006.
The MoEF has also specifically stated that monitoring of the project
will be done as continuing process based on environmental
management plan and as and when required, additional mitigative
18
measures will be stipulated by the MoEF and therefore the Appeal
is liable to be dismissed.
21. The 2nd respondent, the Arunachal Pradesh Pollution
Control Board, in its reply while raising preliminary submissions,
has stated that the 1750 MW Demwe Lower Hydro Power Project
envisage the construction of a concrete gravity dam of 163.12 m
height above deepest foundation level (124.8 m above average river
bed level) across river Lohit in Lohit District, Arunachal Pradesh,
with the total project cost of about Rs.13144.91 crores, scheduled
to complete in 5 years. Even though the appellants have raised two
issues of scoping and public hearing, the Board is concerned with
the conducting of public hearing as per the EIA Notification 2006.
It is stated by the Board that the public hearing was arranged in a
systematic, time bound and transparent manner ensuring widest
public participation at the project site and in its close proximity. It
is the case of the State Pollution Control Board that on receipt of
the application from the project proponent, the time and venue of
public hearing was finalised after consulting the Deputy
Commissioner of Lohit and Anjaw districts. Notices of public
hearing were issued in an English, local Mishmi dialect and in a
Hindi Newspaper giving wide publicity. The EIA report and the
Executive summary was clearly mentioned during the public
hearing and the documents were made available in all offices
accessible to the public. The details of public notices advertised in
various newspapers as stated in the reply of the Board shows that
publications have been made in 6 Newspapers in 3 languages as
19
stated above. In addition, the Deputy Commissioner Lohit District,
Tezu and Deputy Commissioner Anjaw District, camp-Tezu has
also issued circulars enclosing copies to all the affected villages.
The Executive summary of the EIA report was uploaded in the
Website of the Board to make it available in public domain.
22. It is stated by the Board, that the public hearing proceedings
were conducted as per EIA Notification 2006 and as many as 509
persons attended public hearing at Parasuram Kund Mela Ground
in Lohit district on 11.08.2009 and 237 persons attended at Paya in
Anjaw District on 12.08.2009. The public hearing has been video-
graphed and sent to MoEF. It is stated that Mr. Kapriso Krong was
present in the public hearing on 11.08.2009 at Parasuram Kund
and also on 12.08.2009 at Paya (Machima Community Hall) and he
was given ample opportunity and he participated in full swing.
Therefore, according to the Pollution Control Board, there is no
fault in conducting the public hearing.
23. The respondent no. 3, the project proponent, in its reply, in
the preliminary objection stated to the effect that all the points
raised in the appeal were raised by the appellants in detail
throughout the proceedings including at the time of public hearing
before EC was granted by the MoEF, and the same have been
elaborately considered by all the authorities and decision arrived at
and at this stage the appellants cannot be permitted to raise the
same once again.
24. While dealing with the merits of the appeal, while it is the
case of the 3rd respondent that when admittedly, the 1st appellant
20
is not working in Arunachal Pradesh, filing of the appeal is an
abuse of process of law and filed without loco standi. It is also
stated that the project proponent has strictly followed the
provisions of the EIA Notification 2006, while denying all the other
allegations. While dealing with the averments regarding the
scoping, it is stated that the Demwe HEP (3000 MW) is one of the
Prime Minister’s 50,000 MW initiatives. The PFR was made by
Central Electricity Authority (CEA) with Full Reservoir Level (FRL) at
EL 490 m to generate 3000 MW. As per the EIA Notification 2006,
the 3rd respondent has submitted Form 1, Pre-Feasibility Report of
Demwe HEP (3000 MW) and the proposed Terms of Reference to the
MoEF for consideration by EAC on 10.07.2007 and the MoEF has
granted scoping approval on 07.08.2007 along with TOR. However
after availing of TOR, during reconnaissance survey of the stretch of
Lohit River and additional data collection, it was found that 3000
MW Demwe HE Project as conceived by the Central Electricity
Authority would cause partial submergence within the Kamlang
Wildlife Sanctuary (KWLS). It was to avoid the submergence that
the project was split into two as Demwe Lower and Demwe Upper
HEP and accordingly revised Form 1 was submitted to MoEF on
01.02.2008 for scoping. The scoping approval of TOR was granted
by MoEF again on 25.03.2008 for Demwe Upper HEP. It is stated
that the TOR has been issued as per the prevailing model Terms of
Reference for hydropower projects in North East.
25. It is the case of the project proponent that after TOR, the
EAC, considering the fact that Arunachal Pradesh is hotspot for
21
Bio-diversity, has decided to make a field visit and issue further
TOR based on such visit. A sub-group of EAC has in fact visited the
spot on 1st and 2nd June 2008 based on whose recommendations,
the MoEF has issued additional TOR on 04.08.2008. A Detailed
Project Report (DPR) was submitted to the CEA in September 2008
for concurrence as per Section 8 of the Electricity Act 2003. The
CEA has made appraisal and considered various parameters like
Full Reservoir Level (FRL), Maximum Water Level (MWL), Water
Availability Series, Power Potential Studies and other technical
parameters and finalised along with the Central Water Commission
and informed to EAC/MoEF.
26. It is stated that the EAC has approved the installed capacity
of the project to 1750MW, pursuant to which the project is to
release 35 cumecs of minimum flow downstream of the dam
through a separate unit of 40 MW which will run continuously as a
base unit for sustenance of aquatic ecology of the river stretch
downstream immediately below the dam. Further it is stated that a
comprehensive Environment Impact Assessment/Environment
Management Plan study was undertaken by the Centre for
Interdisciplinary studies on Mountain and Hill Environment, Delhi
University (CISMHE) based on base line data collection, prediction
of impacts and formulation of Environment Management Plan as
per TOR.
27. As per EIA, the public hearing was to be held in the Lohit
and Anjaw Districts of Arunachal Pradesh in accordance with EIA
Notification 2006. Accordingly notice for public hearing was given
22
in the newspapers as stated by the State Pollution Control Board in
its reply. Wide publicity was made about the public hearing and
the executive summary of the report were made available in the
office of the District Magistrate of Lohit and Anjaw, Arunachal
Pradesh, Zila Parishad of Lohit and Anjaw, District Industries Office
of Lohit and Anjaw, Regional Offices of MoEF Shillong and MoEF,
New Delhi. As stated by the Board, public hearing was held at
Parasuram Kund, Lohit District and Paya, Anjaw District. People
from downstream area villages like Chongkham, Alubari, Naupatia,
Kyaung, Tissa, Namsai etc have participated and raised issues like
property survey and compensation for land, Basin studies, change
of installed capacity, R and R policy, provision for medical, health
and educational facilities, impact on religious places like Parasuram
Kund, Nimka, Tello, impact on Kamlang Wildlife Sanctuary, influx
of labour, employment and contracts to locals, Dam District ,
geology and dam safety aspects and submergence and downstream
impacts etc. According to the 3rd respondent, majority of the people
have welcomed the project. Copies of the public hearing
proceedings were forwarded by the Board to the Deputy
Commissioner of Anjaw and Lohit on 04.09.2009 to display at the
designated places as per EIA Notification 2006.
28. The EAC has subsequently incorporated based on the views
expressed in the public hearing, in the draft Environment Impact
Assessment/Environment Management Plan Reports and final
copies were sent to MoEF on 01.10.2009. The EAC has considered
the proposal for EC in its meeting on 22.10.2009. Based on the
23
detailed presentation and discussions and all other material things
post public hearing, the EAC has recommended the project for EC
subject to submissions of additional information and clarifications.
The additional information and clarification were furnished on
09.11.2009 and the EAC in its next meeting held on 16.11.2009
considered the same. It is stated that during public hearing
representatives like Mr. Krong and Mr. Suraj Tayan participated
and in the meantime number of representations were received by
MoEF, by group of citizens and civil society, Assam, Mr. Feroz
Ahmed and Dr. Abdul Wakid of Aaranyak, North East affected Area
Development Society, Mr. Suraj Tayan, Mr. Himanshu Thakkar and
many others and all the points raised in this appeal have been
raised. After the response submitted by the project proponent on
13.11.2009, the EAC in its appraisal meeting held on 16.11.2009
reiterated the recommendation for the project for issuance of EC
subject to submission of some more response, which was submitted
on 17.11.2009, 02.12.2009 and 14.12.2009 and the same was
again considered by EAC on 16.12.2009 and recommended
issuance of EC and accordingly, after considering all the aspects,
the MoEF has issued EC on 12.02.2010. Therefore, according to
the project proponent, as the studies were conducted in greater
detail by all authorities, it is incorrect to say that the procedure
under EIA Notification 2006 were not followed.
29. It is stated that EAC is a broad based committee consisting
of Experts from hydrology, water resources, forestry, ecology,
fisheries, socio- economy, geology etc and all decisions were taken
24
collectively and the entire scoping process has been done in detail.
The EAC is only an advisory body and it is ultimately the MoEF
which takes decision. It is denied that the delinking was done
because of the influence of Mr. P. Abraham in the EAC as its
Chairman. It is the case of the 3rd respondent that all the
particulars given in Form I are correct and the correctness of
everyone of information has been verified at every stage. It is also
stated that the project proposal is a Run of the River Scheme with
divisional storage and there is no diversion or consumption as the
water will be released downstream immediately. The 3rd respondent
also denies the averments regarding the winter flood. It is stated
that the hydro-electric projects are basically peaking stations,
providing the Nation muck deficit peaking power.
30. It is the case of the 3rd respondent that as per the TOR,
study was made with respect to Catchment Area Treatment and
Compensatory Afforestation in consultation with the State Forest
Departments as explained in detail by the MoEF in its reply. All the
rationale behind the contents of Form 1 have been explained by the
project proponent and there was no suppression of any material
fact or misleading statement. It is also stated that in hydropower
projects no hazardous waste is generated or handled except the
blasting materials. It is stated by the project proponent that the
question relating to downstream impact has been raised in the
public hearing and were answered properly. The downstream
impact assessment study has been carried out as per the TOR
similar to other hydropower projects in the North-East. 10 Km radii
25
from outer most components of the project area comprising of
83361 ha have been taken as study area. In addition to the 13 Km
of river stretch which falls within 10 Km study area, river stretch
upto 58 Km has been studied with respect of aquatic ecology,
minimum flow, dam break analysis and disaster management etc.
Independent fisheries expert had carried out the study on
evaluation of flow requirements for various fish species in the
downstream stretch for their sustenance and likelihood of breading
grounds etc. and accordingly mitigating measures have been
furnished. The project proponent has also in detail chosen to state
regarding identifying fish migrating path, alterative arrangements
for migratory fishes, changed flow pattern of downstream of the
dam due to the reserve operations, Impact of Demwe Lower
Hydroelectric project on Dibru-Saikhowa National Park, Impact of
the dams in Brahmaputra on the Gangetic Dolphin, impact on
chapories, sediment trappings, riverbed erosion as detailed by the
MoEF in its reply. Thus all the major impacts of downstream river
have been considered fully by the EAC.
31. While reiterating that the river basin study is not to supplant
Environment Impact Assessment/Environment Management Plan of
a project but to supplement the plan to optimize them for ecological
conservation and social upliftment of the area, it is stated by the
Project proponent, that the project was the Lower Most project in
the cascade development of the Hydropower potential of the Lohit
Basin and was also the first planned project in the Lohit Basin and
located in the area which was much less ecologically fragile and
26
prone to environmental degradation. It was considering these facts
the EAC observed that the process of EC for Demwe Upper and the
project in question should not be linked with the completion of the
basin study. It is further stated that the question regarding the
impact due to involvement of influx has been adequately addressed.
As the river Lohit, a tributary of river Brahmaputra, contributes
only 18% annual average flow, the downstream impact study of
Lohit on Brahmaputra is not necessary and therefore the Dibru-
Saikhowa National Park and Biosphere Reserve which is more than
100 Km downstream from the project is also not affected.
32. Regarding Parasuram Kund, while reiterating that the
apprehension of the appellants have been sufficiently answered in
the EAC as well as conditions of the EC, the project proponent
would state that as per EAC’s desire, the project proponent has
enhanced the financial allocation for protection of the Kund from 2
crores to about 10 crores and would maintain adequate water flow
in the Kund during Mela to protect the devotees and maintain the
holy and serene atmosphere with all necessary measures.
Regarding the muck collection and averments made therein by the
appellants, the project proponent reiterates the reply given by MoEF
as enumerated above in detail. The project proponent has also
reiterated the reply by MoEF regarding the compliance of Akwe: Kon
guidelines under convention of Biodiversity.
33. It is stated that scoping, public hearing and every other
requirements for EC as per the EIA Notification 2006, have been
scrupulously followed and EAC has critically examined all aspects
27
including the major aspects regarding the downstream impact and
MoEF has considered each one of them which cannot be found fault
with by the appellants. It is also stated by the Project Proponent,
that it has already spent an approximate amount of Rs 240 Crores
for conducting various studies and for obtaining various clearance.
Accordingly, it is prayed that the appeal should be dismissed with
cost.
34. The 4th respondent, Government of Arunachal Pradesh, in
its reply has stated that Arunachal Pradesh which is the North-
eastern most state in the country is having immense Hydroelectric
power potential. The State is drained by 8 major river basins at
Tawang, Kemeng, Subansiri, Dikrong, Siang, Dibang, Lohit and
Tirap. The hydroelectric power potential of the river basins are
assessed at 57000 MW. In addition 2000 MW hydropower potential
can also be harnessed by small hydroelectric projects. The status
of hydropower potential is more than 1/3rd of India’s total
estimated hydropower potential of 1,47,000 MW. The Central
Electricity Authority in 2010 has given statistical particulars that
the country till May 2011 could harness only 37817.40 MW which
is only 26%. The peak power deficit of Arunachal Pradesh is 15.8%.
The power deficit has hampered all developments in the State.
35. In line with the National Policy, the State has also
formulated its own Hydropower Policy in 2008 and small
hydropower policy in 2007. In spite of high potential, the State is
able to augment only 450 MW which is less than 0.79% of the total
potential. The State Government has entered a MOU with Athena
28
Energy Ventures Pvt. Ltd. (AEVPL) on 09.07.2007 entrusting the
development of Lohit river basin in one or more stages between
elevations from EL + 589 m upto EL + 300 m. In order to avoid
submergence of Kamlang wildlife Sanctuary, the project has been
planned for the development in two stages in consultation with
MoEF as Demwe Upper HEP near Mompani and Demwe Lower
HEP near Parasuram Kund. The State has been constantly holding
review meetings with project developer and obtained requisite
clearance such NOC from State Fisheries Department, State
Irrigation Department, Cultural Department, for Utilization of water
from Lohit River, permission to carry out survey and investigation
from forest department apart from State Power Department for two
stages of developments. According to the 4th respondent, the
appellants who are not undertaking any of their activities in the
State of Arunachal Pradesh, cannot be permitted to stall the
development of State and the appeal by them is not only an abuse
of process of law but also they have no loco standi.
36. While reiterating the grounds stated by the 3rd respondent in
its reply stating that scoping, public hearing have been done as per
the provisions of EIA Notification 2006, and it is stated that the
appellants are attempting to put an end to the project somehow or
other. The State has also in detail responded to various aspects
raised by the appellants namely, scoping and TOR approval
process, identification of project affected families, public hearing
process, EIA and EAC, Downstream impact due to flow variation on
wildlife habitats including Important Bird Area, River Dolphins and
29
Dibru-Saikhwa-National Park, cumulative impacts of multiple
projects in Lohit River Basin, relevance of Forest Right Act for area
under Catchment Area Treatment, and compensatory afforestation,
impact on Parasuram Kund, and balance of convenience. The State
has specifically brought to the notice of the Tribunal, a report
submitted by a committee constituted by the National Environment
Appellate Authority (NEAA) dated 03.05.2010, with three Members
consisting of Shri M.K. Patil, Conservator of Forests, State Forest
Department, Arunachal Pradesh, Dr. Awadesh Kumar, Assistant
Professor, North East Regional Institute of Technology, Itanagar and
Dr. P. Nath, Director, State Fisheries Department, Itanagar to study
the downstream effects of the project on River Dolphins and
important Bird Areas. The Committee after making a thorough
study of all materials including the report on River Dolphins and
Important Bird Habitats and visited the site during the 3rd week of
February 2011 and last week of March 2011 and concluded that
there are no adverse downstream impacts foreseen on River
Dolphins and Important Bird Habitats due to the project during
construction as well as in operational phase. Therefore, the 4th
respondent State, has prayed for dismissal of the appeal as not
maintainable and as abuse of process of law.
37. The 5th respondent Mr. P. Abraham who was impleaded
subsequently by an order of this Tribunal dated 17.07.2013, in his
reply, while narrating the posts held by him apart from stating that
he worked in the Power Sector of the Government for 30 years and
that he has published many books to his credit, has clearly stated
30
that while holding any post as Power Secretary in any organization,
he never took any equity interest or monetary interest in any
company in which he has been in the Board of Directors. His only
interest is being in the Board of Power Sector companies was to
share his knowledge in the field. He has stated that the
Government of India, on 03.04.2007 has reconstituted the EAC for
River Valley and Hydro Electrical Projects and he was nominated as
its Chairman. The EAC consists of Experts from various fields
throughout the country and in respect of hydro projects, decisions
are taken by EAC by the collective wisdom with all Members of the
EAC taken together. According to him, during his Chairmanship,
there was no complaint from any Member of the EAC and
discussions of the Member were free.
38. He has also stated that he was nominated as an
independent/Non- Executive Director of PTC India Ltd. promoted by
Central PSU’s, as a premier Electricity Trading licencee of India,
and listed company in BSE and NSE from 01.06.2004 to
28.09.2011. When M/s Athena Energy Ventures Pvt. Ltd (AEVPL)
was incorporated on 12.03.2007, and PTC India Ltd has become a
share holder in the company, the said company has not decided to
invest in Hydro Electric Projects nor Demwe HEP has been
envisaged as a project to be undertaken by AEVPL. According to
him, the PTC has primarily become a member to perform the role of
providing fuel supply, logistics and tolling services through its
subsidiary. According to him, scoping is only the intermediate
31
process and at that stage it is highly premature to conclude the
environmental sustainability of any project.
39. While meeting the allegation made against him by the
appellants that he being the Chairman of EAC ignored the likely
impacts on cultural sites of Parasuram Kund, Kamlang WLS,
Biodiversity, wildlife habitat, IBA and downstream impact etc. while
denying the allegations as false he has reiterated that the decisions
were collective, joint and unanimous by all Members of the EAC.
He has also stated that during his tenure of 2 years in the EAC, no
undue favour was shown to the Demwe HEP and he do not have
any pecuniary or any other intent whatsoever in Athena Demwe
Power Ltd. He has also stated that he has resigned as Chairman of
EAC on 22.06.2009 voluntarily.
40. Mr. Ritwick Dutta, learned counsel appearing for the
appellants, has raised many issues while challenging the EC
granted by the MoEF to the 3rd respondent project proponent for
the 1750 MW Demwe Lower Project. The first contention raised by
him is that the participation of Mr. P. Abraham, as the Chairman of
EAC in the preliminary scoping stage vitiates the entire process
culminating into the issuance of EC to the project proponent for the
reason that the said Mr. P. Abraham being a Director of PTC India
Ltd. which is one of the founder promoter of M/s Athena Ventures
Private Ltd. which has taken up the project. Therefore, according to
him, the participation of an interested Director of the promoter
company of the project proponent at the earliest scoping stage has a
definite tendency of influencing the decision of EAC. As the
32
application can be rejected at the initial stage of scoping as per the
EIA Notification, 2006, the participation of the interested Director
as the Chairman of EAC has thwarted such action. According to
him, the scoping is the first foundation stage and it plays a
significant role of permitting preconstruction activities and site
clearance. He would rely upon a Judgment of the High Court of
Punjab and Haryana in Vijay Bansal and others Vs State of Haryana
and others in CWP No. 2013 4/2004 dated 15.05.2009 to contend
that the “relevant environmental concerns” stated in the EIA
Notification 2006 forms the ‘soul’ and ‘spirit’ of the Notification. He
also cited a Judgment of the NGT in Bharat Patel Vs Union of India
in Application No. 55/2013 (WZ) wherein it was held that TOR
could be challenged under Section 14 of NGT Act, 2010. According
to him, the siting of the project which should have been considered
in the scoping stage has been ignored. He also submits that at that
stage the Cultural heritage of Parasuram Kund and downstream
impact has been ignored. The presence of Mr. P. Abraham as the
EAC Chairman would result in conflict of interest and prejudicially
affects the neutral decision making process. It establishes bias.
Further, it was because of the objections raised by the civil society
groups the then Minister has directed Mr. P. Abraham to resign.
According to him, as per EIA Notification 2006, the Chairperson of
EAC has to endeavour to reach consensus in each case and
thereafter mere non objection raised by any Members of EAC is not
a sufficient defence for the possible bias which the Chairman would
have exercised on the Members of the EAC by citing the clause in
33
EIA Notification 2006. He submits that the selective delinking the
project with Basin study is the obvious influence by Mr. P.
Abraham. He submits that delinking is arbitrary and illegal.
According to him, none of the other projects in the Lohit River Basin
have been appraised for grant of EC pending completion of Lohit
river basin study.
41. According to Mr. Dutta, after resignation of Mr. P. Abraham
which was done on realizing the conflict of interest, the EAC ought
to have taken a revision of the decision already taken. Therefore
there was a likelihood of bias and the EAC should have revised the
decision and its failure would vitiate the subsequent proceedings.
He has also submitted that the failure of EAC in deliberating on the
public hearing during appraisal whether accepting or rejecting the
objections is a serious lacuna.
42. He submits that downstream impact study has not been
effected and ultimately people in downstream of the project
especially in Assam like the Appellants are affected. The absence of
downstream study affected their livelihood. He has also submitted
that the impacts on chapories of the Lohit river has not been
studied. The impact of flow fluctuations which are to be looked in
terms of the entire complex of water bodies, riverine islands,
grassland and forest has also not been done. The three Member
Committee constituted by the State of Arunachal Pradesh has been
widely criticized by the wildlife biologists from North East like Dr.
Gautam Narayan, and Dr. Abdul Wakid. He also submits that
impact of peaking operation on downstream area including Dibru-
34
Saikhowa National Park has not been studied. According to the
learned Counsel the respondent’s stand is misleading. He has
also referred to some of the views expressed by Experts to support
his contention that such study comprehensively is a must for
approval of such mega projects. He submits that the post clearance
downstream study is against the precautionary principles and
principles of sustainable development.
43. The learned Counsel also submits that the impact of
endangered wildlife and their habitat are not considered by the
EAC. According to him, Kamlang Sanctuary cannot be the primary
motive but it must be the economic viability of cascade development
along the river stretch. He submit that the bifurcation 3000 MW
project into two was mainly based on the upstream investigated site
at Mompani and it is purely a commercial angle rather than
environmental issue. The principles of protection of endangered
species has been held to be imperative by the Hon’ble Supreme
Court in the judgment reported in (2013) 8 SCC 234 and species
like Bengal Florican and Wild buffalo ought to have been studied
before clearance. He also submit that non study of impact of Lohit
Basin study and cumulative impact of the projects in the basin are
sufficient to hold that the EC is illegal.
44. While referring to the non consideration of the Cultural
impact studies including the Parasuram Kund, he submits that it
results in appropriate siting of the project. He submits that on
cultural impact earlier projects like Lohari Nagarpala, Pala Maneri
and Bhaironghati have been scraped. He submits that Parasuram
35
Kund being a cultural heritage, it is declared as an Archaeological
heritage of Arunachal Pradesh. The excavated materials if loaded in
the area the aesthetic sense and serene nature of the Kund will be
affected and the same has not been considered. According to him,
the importance of Parasuram Kund has been well recognized by the
Hon’ble Supreme Court in its Judgment in State of Arunachal
Pradesh V/s Khudiram Chakma reported in 1994 SCC(1) (Suppl)
615. Mr. Dutta while concluding his submissions, has reiterated
that as the EC is vitiated for more than one reason, wildlife
clearance has to go, as the same was vehemently opposed by all the
non official Members. He again reiterates that by not making the
downstream study, there is a total breech of precautionary
principles and therefore, it is his submission that the EC should be
set aside.
45. Per Contra, it is the contention of Mr. Tarun Johri, the
learned Counsel appearing for the 3rd respondent, project
proponent, that as per the project study, minimum flow of 10% of
water was to be maintained and in fact downstream study has been
conducted and therefore it is not proper to say that no study was
conducted and the project has been approved just like that. It is
his submission that even for siting, a thorough study was
conducted by agencies like NEEPC, Brahmaputra Board, NHPC
from 1980 till finalisation of Demwe Lower HEP by the 3rd
respondent. According to him, 4 alternative sites were suggested
but it was ultimately found that site about 1600 m upstream of
Parasuram Kund Bridge was considered to be topographically and
36
geologically best. This was referred by project proponent to the
Committee for River Valley and Hydroelectric projects of MoEF and
after detailed discussions MoEF has approved the revised TOR with
two conditions that the Kamlang Wildlife Sanctuary shall be kept
outside the submergence area of the project and keeping in view the
seismologically sensitive area, dam height should be kept minimum
as required for power generation purpose. Therefore, it is not
proper to say that no siting criteria was followed at the time of
scoping, according to the learned Counsel.
46. It is his submission that considering the proximity of the
Kamlang Wildlife Sanctuary, a Biodiversity and Wildlife
Management Plan was formulated in the EMP with the objective of
maintaining a sustainable approach between customs and culture
of the local communities and biodiversity conservation etc. apart
from Forest Protection Plan and it was after careful study especially
of dam safety, downstream impact, minimum flow, protection
measures of Parasuram Kund, geological and seismicity aspects,
sedimentation and silt flushing etc. raised in various
representation, EC was granted and there can be no fault in that at
all.
47. Regarding the status of projects coming up in Arunachal
Pradesh, while contradicting the stand of the learned Counsel for
appellant that MOU have been entered for more than 125 projects,
Mr. Johri, would submit that out of 14 projects for which EC was
granted only 4 are under construction and only 1 has been
commissioned in Subansiri, other than the Lohit project for which
37
EC has been granted by the MoEF on 10.02.2010 which is
impugned and NWLB has also granted its permission and stage II
clearance was given on 03.05.2013 which is also challenged in
Appeal No. 9/2010. Therefore, it is not correct to give a wrong
picture as if many projects have come in the area.
48. Regarding the effect on Parasuram Kund, the learned
Counsel for the project proponent would submit that there are no
major impacts envisaged. Infrastructure developments, muck
disposal system protects sufficiently the cultural site. It is his
submission that a society which is maintaining the Mela called
Parasuram Kund Improvement Society has given no objection and
the project proponent would increase the payment from 2 Crores to
10 Crores to be spent for the benefit of the devotees. In fact, the EC
has taken care of the same by imposing strict conditions relating to
release of water during the Mela period. The public hearing and
consultations have been considered for such imposition of stringent
conditions.
49. While meeting the arguments relating to scoping raised by
Mr. Datta, Mr. Johri would submit that no projects are rejected at
scoping stage except when on the face of it such projects cannot be
sustained. Mr. P. Abraham was an independent Director of PTC
India Ltd, but as a Chairman of EAC in respect of Demwe Lower
HEP, all decisions were taken collectively. He submits that in the
absence of any instance that any of the Member of the EAC have
raised objection at scoping stage, it cannot be said that Mr. P.
Abraham has influenced any Members. He also submits that
38
scoping is in the most preliminary stage and even if some mistakes
are committed the same can always be rectified by additional TOR
and as such it has been done in this case at a later stage. The
project being site specific there is no scope for any one influencing
the decision regarding site identification. He submits that in any
event as stated by him the above site has been choosen after
thorough study and there is absolutely no scope for any mistake.
50. Regarding delinking of EC from Lohit river basin study, the
learned Counsel while denying the contention raised by the learned
Counsel for the appellant that it is against the precautionary
principles, would submit that such delinking was not done only for
Demwe Lower HEP and such delinking has been done in many
projects like Kalai-I, Kalai-II, Hutong II HEP, Anjaw HEP 280 MW,
Raigam HEP, Gimliang HEP 80 MW and Gimliang HEP 74 MW. He
also submits that the Inter- Ministerial Group (IMG) has
recommended not to hold up EC pending basin study as such study
is elaborate and comprehensive would take 1 to 2 years. He has
also stated that while Mr. P. Abraham was involved only in the
scoping stage, actual environmental appraisal and clearance was
considered by EAC chaired by Shri. Devendra Pandey and therefore
there is no question of likelihood of any bias.
51. While dealing with the contention of Mr. Dutta about
peaking operation and Diurnal variation in Demwe Lower HEP, the
learned Counsel for respondent no. 3 would submit that hydro
power stations have inherent ability of instant starting, stopping,
managing of load variations and help in improving the reliability of
39
the power system, particularly for meeting the peaking
requirements and by taking note of the study for a period of 19
years about flow variation, he would submit that the project is not
going to alter or increase the natural variation significantly as
revealed by the scientific study. He has also submitted that the
appraisal process carried out by the EAC shows that it was
considered for 3 times and in fact every time the EAC required
clarifications from the project proponent based on which additional
information have been furnished. Therefore, it was by proper
application of mind entire procedure have been done and no
distraction can be drawn. Therefore, he submits that the appeal is
devoid of any merits and is liable to be dismissed.
52. Mr. Vivek Chib, learned Counsel appearing for the MoEF,
while reiterating the contents in reply and also adopting the
arguments advanced on behalf of the project proponent, would
submit, that at the stage of scoping there is no possibility of any
bias especially when Mr. P. Abraham was not in the appraisal
process and therefore the Utkash Mandal Judgment has no
application. His submission is that the entire process as envisaged
shows that there is a proper application of mind and in fact TOR
was issued by the MoEF after the field visit by a sub-committee
from among EAC, in which Mr. P. Abraham was not a party and
therefore the decision has been taken strictly in accordance with
the EIA Notification 2006. Even if there is no application of mind,
according to the learned Counsel, in accordance with EIA
Notification 2006, this Tribunal sitting as a second Appellate
40
Authority to decide question of law akin to Civil Court power under
Section 90 of the Code of Civil Procedure, cannot interfere unless
there is gross violation of law or Notification itself. He submits that
under EIA Notification 2006, Clause 7(IV) while speaking about
“appraisal” clearly states that EAC while recommending the project
shall stipule special or general conditions and only in cases of
rejections reasons must be given. When that is the legislative
intention, imposing of conditions while granting recommendations
or EC itself amounts to application of mind and cannot be
questioned as arbitrary. The said clause read with Appendix V
shows that the minutes of the meeting of the EAC to be read
together.
53. He further submits that the Tribunal being a creature of law
must act within the boundaries of law by which it is created, and
must take a holistic view as to whether there has been an
application of mind by EAC and MoEF before granting EC. He
submits that Utkash Mandal Judgment was given without
considering Appendix V of the EIA Notification 2006. He also
submits that in the Judgment of the NGT Eastern Zonal Bench,
Bhopal in Ramesh Agarwal Vs Union of India and Others, the
Tribunal has taken such a stand in paras 28, 31 and 32.
54. He also submits that the Hon’ble Supreme Court in
Maharashtra State Board of Secondary and Higher Secondary
Education Vs K.S. Gandhi and others reported in (1991) 2 SCC 716,
at Para 20 has clearly stated that “unless the rule expressly or by
necessary implications exclude” and that when read Clause 7(IV)
41
with Appendix V, one can understand about the specific exclusion
of reasons. To substantiate his case about the application of mind
and reasons to be given or nor he relied upon the Judgment of the
Supreme Court reported in (2004) 4 SCC 615 and (2010) 9 SCC
486.
55. Mr. A.D.N Rao, the learned Counsel appearing for the State
of Arunachal Pradesh, the 4th respondent has submitted that the
State which is situated in the extent of 83743 sq km, has 67321 sq.
km forest area with about 80.1 per cent forest cover. There are 8
major river basin as stated in the reply and presently Lohit river
basin has the potential of hydro-electric plants covering 57000 MW
and 2000 MW of small hydro electric stations against the National
potential of 1,47,000 MW. Therefore, 1/3 of power potential of the
country is available in the State. In spite of such huge potential, as
on date the State is power deficit producing a meagre 450 MW
Power, which is only 0.79 per cent of its total potential in the State.
In the Lohit River Basin, 7 projects were proposed out of which only
one Demwe Lower HEP is given EC and FC. He has also brought to
the notice of the Tribunal that the Tribunal in M.A. 53/2013 in its
order dated 18.03.2013 has rejected the contention regarding
public hearing that State of Assam is not a party. The impleading
petition by Assam was rejected even though in the FC Assam is a
party. Property connected with the project which is in 70 Km as
crow flies, 60 Km lies within the State of Arunachal Pradesh. He
submits that regarding public hearing notice as against the 2
42
Newspapers required as per EIA Notification 2006, 6 publications
were effected so as to give wide publicity of the proposed project.
56. In the public hearing 519 people participated at Parasuram
Kund and 237 in paya, apart from many representations made in
writing. For want of electricity the State is using 230 lakhs litre of
diesel annually emitting 50 lakhs tonnes of carbon monoxide and
over 40 years, about 250 million of carbon dioxide are emitted
which is not only dangerous to human habitation but also causes
global warming. Therefore, HEP is a matter of necessity for the
State not only for its economic survival but also to retain the
environment clear in the State. That apart he adopts the
arguments advanced by the learned Counsel for the project
proponent and submits that the appeal is liable to be dismissed.
57. We have heard all the learned Counsel extensively, referred
and traversed through all the bulky documents filed by all the side
and given our anxious thoughts to the issues involved in this case.
Accordingly we arrive at the following issues to be discussed and
decided:-
1) Whether the presence of Mr. P. Abraham during the scoping
stage of EAC in considering Demwe Lower HEP would vitiate
all the consequent proceedings of EAC and the EC?
2) What is the scope of scoping under EIA Notification 2006 and
whether any decision taken at the scoping stage cannot be
changed and has to be treated final?
3) Whether EAC has considered all the issues relating to
43
(i) The effect of the project on the cultural heritage of
Parshuram Kund?
(ii) Appraisal proceedings done as per the EIA Notification?
(iii) Delinking of the basin study from the EC and its effect?
(iv) Effect of peaking operations of the project?
(v) Effect on Biodiversity including the effect on Dibru-
Saikhowa National Park?
(vi) Cumulative impact study? And
(vii) Muck disposal and suggested sufficient safeguards.
4) Whether public consultation process has been done properly
and in accordance with the EIA Notification 2006.
5) Whether the EC is liable to be held invalid.
58. In the background of the above undisputed facts elaborately
explained and based on the pleading we propose to approach the
issues one by one. Before adverting to the same, we think it
appropriate to examine the position of Arunachal Pradesh and its
requirements especially regarding the present status pertaining to
the environmental issues and incidentally consider its other
requirements.
59. Arunachal Pradesh which is a North Eastern most State in
the country is situated in the total area of 83747 square Kms and
as stated by the learned Counsel appearing for the said State
Government Mr. A.D.N. Rao, out of the total extent, 67321 sq.km of
area is covered by forest. Therefore, the state has got the forest
cover of 80.1 per cent. It has got 8 major river Basin with the total
44
hydroelectric power potential of the said Basin which has been
assessed at 57000 MW apart from the 2000 MW hydropower
potential from smaller hydro electric projects. The National
potential estimated of hydro electric power is stated to be 1,47,000
MW and if that is taken into consideration the hydroelectric power
potential of Arunachal Pradesh is 1/3rd of the National potential.
While the countries big power deficit is 9.8 per cent, the deficit in
the North East is 18.5 per cent. In spite of the hydroelectric
potential of the river Basin situated in Arunachal Pradesh to the
extent of 57000 MW the State is able to develop as on date its
capacity of 460 MW which is less than 0.79 per cent of the National
potential. This statistical points conformed by the Central
Electricity Authority shows that in spite of its hydroelectric power
potential the State of Arunachal Pradesh is suffering of power
deficit. Admittedly there are no industries in the State for
augmenting its economic development.
60. It is stated that even though a significant number M.O.U.
have been entered with the Government, as on date if one refers to
the status of hydroelectric power projects coming up in Arunachal
Pradesh, it would only show an alarming situation. It appears as
circulated in the list of projects and stages as on May 2014, as on
date there has been only 14 projects in respect of which EC has
been granted, nevertheless it is only in respect of one project in
Subansiri, Ranganadi HTP with an installed capacity of 450 MW
which has been commissioned. The other projects which are not
commissioned in spite of EC having been granted by MoEF, other
45
than Demwe Lower 1750 MW of Lohit River Basin for which both
EC and FC are granted which is a subject matter of dispute in this
appeal and another appeal are:
1. Kameng Basin, Gongri with the installed capacity of 90 MW.
2. Kameng Dibbin 125 MW
3. Kameng Khuitam 66 MW
4. Kameng Nafra 120 MW
5. Kameng Kameng 600 MW
6. Siang, Tato-II 700 MW
7. Siang, Sian Middle (Siyom) 100 MW
8. Subansiri, Lower Subansiri 2000 MW
9. Dikrong, Pare 110 MW
10. Tawang, Nyamjangchhu 780 MW
11. Tawang, Tawang stage 1 HEP 600 MW
12. Tawang, Tawang stage 2 HEP 600 MW which are still pending.
It is in the light of the above said real situation which in our
considered view is also concerning the sustainable development,we
have to approach the dispute in question.
61. Before taking up everyone of the issues framed by us
individually we propose to take the issue no. 2 as a first one for our
consideration. Issue no. 2 which we have framed is as follows:
Issue No. 2: What is is scope of scoping under the EIA Notification
2006 and whether any decision taken at the scoping stage cannot
be changed and has to be treated as final?
The Environment Clearance Regulation 2006, herein after referred
to EIA Notification 2006 is a statutory notification issued by the
46
Government of India in exercise of its powers conferred under
Section 3 (2)(v) of the Environment (Protection) Act 1986 read with
Rule 5(3)(d) of the Environment (Protection) Rules 1986. By the
said Notification the Government has prescribed the procedure to
be followed for construction of new projects or activities or
expansion or modernisation of existing projects or activities listed in
the Schedule to the Notification entitling capacity addition with
change in process and or technology to be undertaken in any part
of India and only after obtaining prior Environment Clearance from
Central Government or from the State Level Environment Impact
Assessment Authority as the case may be.
62. While the notification makes certain activities as ‘A’ category
for which Central Government in MoEF and certain activities as ‘B’
category for which the SEIAA in the State Level are made competent
to give prior EC as Regulatory Authorities. As the Hydro Electric
Power Projects, are categorised as ‘A’ projects in the Schedule to the
Notification while following various stages prior to grant of
Environment Clearance, the new projects of Demwe Lower HEP
1750 does not require to undergo the first stage of ‘screening’ as per
clause 7 of the Notification which enumerates 4 stages to be
undergone by a project before EC is granted. That takes us to the
stage no. 2 called ‘scoping’ to be undergone by the project in issue.
It is common ground that as a first step, the project proponent is
expected to make his proposal as an application in Form I
prescribed in appendix I of the EIA Notification 2006. “Scoping”
refers to the process by which the Expert Appraisal Committee
47
(EAC)determine detailed and comprehensive Terms of Reference
(TOR) addressing all relevant environmental concerns for the
preparation of Environment Impact Assessment (EIA) Report to be
prepared by the project proponent in respect of the project or
activity for which prior Environment Clearance is sought. The EAC
determines Terms of Reference on the basis of information
furnished in the prescribed application in Form I, a site visit by a
sub group of EAC only if considered necessary by the EAC, Model
Terms of Reference if suggested and furnished by applicant and
other information’s that may be available with the EAC. Therefore,
the said word “scoping” forms the first part of the stage no. 2
contemplated in clause 7 (II)(2) of the EIA Notification 2006.
63. It is no doubt true, as stated in clause 7 (II) (2)(iii) that the
application for prior EC may be rejected by the Regulatory
Authority, on the recommendation of the EAC at the stage of
scoping itself, with reasons for such rejection, which should be
communicated within 60 days of receipt of the application. But
that does not mean that at the scoping stage the proposal could
deemed to be sanctioned based on the contents of Form I after
60days of the application and deemed to be recommended by the
EAC for issuance of EC. The EAC can always reappraise and issue
additional TOR seek information or clarification till it is satisfied
that the entire material particulars have been placed before it for its
thorough consideration so as to enable the final TOR to be
formulated so that the project proponent can go for Environment
Impact Assessment (EIA) study and submit the same again to MoEF
48
which will be referred to EAC once again for its consideration and
final recommendation. As submitted by the learned Counsel
appearing for the appellant Mr. Ritwick Dutta it is no doubt true
that the “scoping” stage is the foundation stage of a project and it is
definitely the “soul” and “spirit” of the EIA Notification as held by
the High Court of Punjab and Haryana. But we are unable to
accept his contention as if any decision taken by the EAC during
“scoping” cannot be changed or altered for the better Environmental
protection by EAC. The TOR prescribed by the EAC based on the
contents of the application in Form I, site visit of the sub group if
found necessary and other particulars can always be altered by
additional TOR by asking the project proponent to explain doubts if
any raised by EAC regarding any material facts found or discovered
in Form I or site visit. In the absence of any bar in the EIA
Notification 2006 for the EAC to issue additional TOR till it is
completely satisfied about the project there EAC is entitled either to
call for additional particulars or ask for rectification based on site
visit by the sub group. In respect of Hydro Electric Power Plants
which are normally site specific in nature, the site visit by the sub
group of EAC certainly helps the experts constituting the EAC to
modify the proposed TOR of the project proponent or make
alternation or addition to the TOR. On the facts of this case itself it
is seen clearly that in respect of Demwe Lower HEP 1750 MW in
Lohit River basin of Arunachal Pradesh the EAC has considered the
proposal along with other projects at least on 3 occasions namely
21st & 22nd October, 2009, 16th November 2009 , 15th and 16th
49
December 2009. In fact as it is seen in the summary of records of
discussion of the 31st meeting of the EAC dated 21st and 22nd
October, 2009, after the EAC has taken note of the fact that the
initial TOR issued for the project in July/August 2007 and
subsequent bifurcation of the project into Demwe Lower HEP and
Demwe Upper HEP, the meeting considered in greater detail about
the situation of the project including that the Dam access is located
about 100m upstream of Parshuram Kund Bridge on NH-52 and
falls in Lohit District with reservoir extended into Anjaw District of
the State. The EAC in the said meeting has also considered that
the minimum draw down level of the project will be at elevation of
408 m as finalized by CEA/CWC with live storage of about 171.20
m.cum and that a surface power house is proposed on the right
bank of Lohit river to accommodate 5 numbers of vertical Francis
turbines of 342 MW each and 1 unit of 40 MW to generate a total
installed capacity of 1750 MW. It was taken note of by the
Committee that the water after power generation will be discharged
back to the river through a 130 m long tail race channel and the
project will generate 6322 million units in a 90 per cent dependable
year at 95 per cent machine availability. A reference to the minutes
also shows that this project after bifurcation was granted TOR on
scoping approval on 25th March 2008 for generation of 1200 MW
which was subsequently increased to 1750 MW based on study of
water availability without changing the physical parameter. The
Committee in the said meeting has considered height of the dam at
160 m and therefore it needs to provide dependable warning system
50
to the downstream flood plain upon the event of a dam break. It
was found that the rise in water surface elevations in the event of
PMF plus dam break would be seen in the downstream reach of 58
km and this entire area lies within geographical boundary of
Arunachal Pradesh and concluded that 23 villages in the
downstream reaches would be affected. It also considered the
clarification issued by the developer that dam break analysis has
been carried out using HEC/RAS model for the critical condition
when the reservoir is at FRL and design flood hydrograph (PMF) is
impinged. Further the Committee has considered the Disaster
Management Plan, Glacial Lake Outburst Flood (GLOF) studies and
called for clarification on segments uploading and silt disposal
system. The Committee also considered the biodiversity and
ecological aspect and took note of the primary data with appropriate
details and suggested that some more maps like the one shown in
for sampling locations of soil could be prepared for terrestrial
ecology, water quality. Further it has considered about the nearest
boundary of Kamlang Wildlife Sanctuary (KWLS) which is about 9.3
km upstream aerial distance from the dam site apart from the
minimum flow and fisheries aspect. In fact in this regard the report
shows that the Committee desired that for the environmental
release of 35 cumecs, adequate depth and velocity for the dominant
channel in the downstream reaches be provided as several braided
streams from the Lohit river downstream of the dam site.
Regarding the seismic activities the Committee desired the details of
investigation on geological aspects carried out and submitted.
51
64. Further the Committee in the meeting has in detail
considered about the representation on the impact of Parasuram
Kund. It considered the provisions made for developing basic
infrastructure for bathing ghats, sewage/ sanitation facilities,
marketing complex, shelter, recreation area (Parks, sitting space
etc) and found that on completion of the project huge water body
would be created that will have its own scenic beauty and therefore
it would add to the development of Parasuram Kund site into a
tourism destination. It was considering the same, the Committee
has recommended the increase of financial allocation for Parasuram
Kund from 2 Crores to 10 Crores. In that meeting after critically
examining all environmental aspects considering the discussion
and clarifications given by the project proponent on various
environmental concerns especially dam safety and downstream
impact, minimum flow, protection measures for Parasuram Kund,
geological and seismicity, sedimentation and silt flushing etc along
with public hearing, the Committee has directed the project
proponent to give additional informations regarding various aspects
namely:
Maps depicting locations of sampling sites for terrestrial
ecology and water quality.
Methodology adopted for Ecological studies be elaborated for
clear understanding.
The Ecological species mentioned in the EIA/EMP report
should be cross checked with the Literature by Dr. Haridasan
(SFRI), and incorporated in the EIA/EMP report.
52
Additional information of river cross sections of the D/S
reaches considered for dam-break analysis along with Tail
water rating curve and flow velocity of various reaches in the
event of dam break analysis.
Details of braided river course of the downstream reach in
which fish migration would take place during the release of
environmental flow.
The 5 micro stations installed for seismic monitoring, should
be increased to at least 7 no in consultation with NSIT, Jorhat.
Salient findings of geological assessment carried out in the
project area as a part of EIA.
Alternate arrangements along with hatcheries, if feasible may
be explored for the migratory fishes.
The financial allocation for the protection of the Parasuram
Kund needs to be enhanced from Rs. 2 crores to about Rs. 10
crores.
Regarding the flow requirements at the Parasuram Kund
during Mela period in the month of January, letter to be
obtained for the duration as determined by the Parasuram
Kund Improvement Society.
Confirmation from State Pollution Control Board in respect of
para 6.6, Appendix IV of EIA Notification 2006.
65. In a subsequent meeting of the EAC held on 16th November,
2009, the Committee has considered the additional remarks
required earlier which runs to nearly 8 pages relating to
methodology adopted for ecological studies and maps depicting the
53
locations, cross checking of species with Dr. Haridansan’s Report,
additional informations of river cross sections in the downstream
reaches for dam analysis, details of braided river course of
downstream reaches for identifying fish migration path, installation
of adequate number of microstations for seismic monitoring,
salient features of geological assessment, alternate arrangement of
migratory fishers, enhancement of financial location for the
protection of the Parasuram Kund, requirement of adequate water
flow at Parasuram Kund during Mela period in the month of
January, changed flow pattern in downstream of dam due to the
reservoir operations, impact of Demwe Lower HEP on Dibru
Saikhowa National Park, impact of dams in Brahmaputra on the
habitations of the Gangetic Dolphin, impact of Demwe Lower HEP
on Beels and Chapories, impact of Demwe Lower HEP on sediment
trapping, GLOF studies, flood moderation, river bed erosion due to
reservoir operations, impact of tail water release on the Parasuram
Kund, impact of bolder collection from river bed for construction,
compliance of Akwe: Kon guidelines under the convention of
biodiversity and failure of Coffer Dam.
66. It was in that meeting on 16th November, 2009 the
Committee has considered various representations by public/civil
societies and NGO’s Mr. Ahmed Ramyak, Mr. Neeraj Vagholikar of
Kalpavriksha, NEADS Jorhat, group of citizens and civil society,
Assam and also representations from Mr. K. Krom Ex-Minister
Arunachal Pradesh, Dr. Chandan Kumar Sharma Associate Prof.
54
Department of Sociology, Tezpur University Assam and Bimal Goi,
Assam.
67. After examining the environmental aspects and considering
the comprehensive clarifications and responses submitted by the
project proponent in respect of various observations and the
representations submitted by the members of various Civil
Society/Individuals/ NGOs, while reiterating its recommendation
for EC, the Committee has called for additional information
regarding written response in respect of the representation made by
Mr. Krom, Mr. Gogoi and Dr. Sharma apart from report by fisheries
Expert of technical evaluation regarding possible breeding grounds
including Parasuram Kund.
68. The meeting of the EAC dated 21 and 22 October, 2009 was
charied by Dr. Devendra Pandey along with the Vice Chairman Dr.
A.K. Bhattacharya and Members Dr. O.P. Sisodiya, Dr. B.P Das,
Shri R.K Singh, Prof D. Goswamy, Dr. J.K Sharma, Prof. D.K. Paul,
Dr. D.K. Alva and Dr. S. Bhowmik being its Member Secretary.
Likewise in the meeting held on 16th November, 2009 it was chaired
by Dr. Devendra Pandey along with Vice Chairman Dr. A.K
Bhattacharya and Members Dr. O.P Sisodiya, Dr. B.P Das, Prof. D
Goswami, Dr. J.K Sharma, Dr. S.R Yousuf, Shri R.K Singh, Dr. S.
Bhowmik as a Member Secretary apart from Dr. P.V Subba Rao
from MoEF.
69. In the 3rd meeting of EAC conducted on 15th & 16th of
December, 2009 which was in fact the 33rd meeting of the EAC
again while considering the Demwe Lower HEP 1750 in Lohit
55
District of Arunachal Pradesh the Committee took note of the
submission of fisheries expert regarding fish breeding grounds in
and around Parasuram Kund apart from the response for the
representations of the above said 3 persons. The Committee has
taken note of various representations and the impact study on the
downstream made upto 10 kms and there has been representations
that the impact was likely to be beyond 10 kms downstream and
directed that the study beyond 10 km should be produced for a
separate TOR and thus the meeting was adjourned to 19th and 20th
January, 2010. It was in that meeting also Dr. Devendra Pandey
was sitting as a Chairman apart from Dr. A.K Bhattacharya as Vice
Chairman, Dr. O.P Sisodiya, Dr. B.P das, Dr. D.K Paul, Dr. D.K
Alva, Shri R.K Singh, Dr. S. Bhowmick as Member Secretary apart
from Dr. B.V Subarao from MoEF.
70. Therefore, in all the above said 3 meetings of EAC additional
TOR’s have been prepared and issued and recommended by the
EAC based on various clarifications submitted by the project
proponent and after considering the entire gamut of environmental
issues by all the Members thoroughly. All the 3 meetings have
taken place during the scoping study. This clearly shows that
scoping is not only an initial process but it is a continuing process
and EAC is entitled to recommend additional TOR till all requisite
information is available for appraisal of the project. A close study of
the entire minutes of EAC as elicited above shows the healthy trend
and implementation of the spirit of the EIA Notification 2006 by
EAC during the process of scoping. Therefore it is clear that the
56
scoping which is an initial process and decision taken during
scoping process continues till final TOR is recommended by EAC
and certainly during that period the EAC is entitled to make
changes, alterations and additions and therefore till final TOR is
issued one cannot say that decision taken in the EAC meeting
during scoping are final. The second issue raised by us is answered
accordingly.
71. Issue No. 1: Whether the presence of Mr. P. Abraham during
the scoping stage of EAC in considering Demwe Lower HEP, vitiate
all consequent proceedings of EAC and the EC?
The EAC at the level of Central Government is as contemplated in
clause 5 of the EIA Notification 2006 and its composition is as given
in Appendix no. VI. As per Appendix No. VI it is made clear that the
EAC shall consist of only professionals and experts fulfilling the
various criteria contemplated therein. The Appendix also states
that the members of EAC shall be experts with requisite experience
in various fields or disciplines like environment quality, Sectoral
Project Management, Environment Impact Assessment process,
Risk Assessment, Life science, Forestry and Wildlife, Environmental
Economics with experience in project appraisal, public
administration or management, and the number of Members of EAC
shall not exceed 15, however, with liberty to the Chairperson to co-
opt an expert as a member in a relevant field for a particular
meeting of the Committee. The maximum tenure of a Member
including Chairperson is 2 terms of 3 years each.
57
72. It is also relevant to point out at this stage that Clause 5 of
the EIA Notification 2006 while speaking about the screening ,
scoping and appraisal committees states in clause 5 (e) as follows:
“EAC and SEAC’s shall function on the principle of
collective responsibility. The Chairperson shall
endeavour to reach a consensus in each case, and
if consensus cannot be reached, the view of the
majority shall prevail”.
It is the contention of Mr. Ritwick Dutta, that as the Chairperson is
entitled to take efforts to reach a consensus, his position is more
influential. This he has raised in the context of Mr. P. Abraham
who was appointed as the Chairperson of the EAC which has
considered Demwe Lower HEP 1750 MW project. His contention is
that Mr. P. Abraham was already a non executive director of PTC
India Ltd which is stated to have promoted the 3rd respondent
project proponent herein and therefore his presence as a
Chairperson in the EAC to consider the project concerned is capable
of influencing in decision making process and therefore there a
likelihood of bias. It is for that purpose he has relied upon the
above said clause 5 (e) of the EIA Notification 2006. The above said
contention in our view is baseless. As per the notification any
decision is based on collective responsibility. As per Appendix VI all
the members including Chairperson are well qualified experts and
one cannot accept the contention that such experts would yield to
the Chairperson if any illegal or unsustainable proposals are
insisted on them. The said provision should be only construed to
58
mean that in normal circumstances the collective responsibility with
the consensus of all Members shall be taken in which event, the
Chairperson responsibility is to endeavour to reach consensus
which cannot mean that his influence should be binding on all
members. Each of the expert members who are well qualified as
prescribed under the notification are entitled to take their views in
which case majority will prevail. Therefore, there cannot be any
presumption that the Chairperson will influence the other expert
members. Such view will be only undermining the independent
status of the members of the EAC.
73. Now coming to the fact of the present case, it is not in dispute
that the Government of India while reconstituting EAC for river
valley and hydro electric projects has nominated Mr. P. Abraham as
it is Chairman on 03.04.2007 and he has resigned from the post on
22.06.2009 and thereafter it was Dr. Devendra Pandey who became
the Chairman. It is true that originally the project proponent has
given proposal for Demwe HEP (3000 MW) and that was submitted
on 10.07.2007 by the Government for consideration by EAC. On
that day it is no doubt true that Mr. P. Abraham was the
Chairperson of EAC and TOR was also granted. But the fact
remains that during reconnaissance survey of the allotted stretch of
Lohit River and additional data collection the 3000 MW Demwe HEP
was found by Central Electricity Authority (CEA) with FRL at 490m
causing partial submergence of Kamlang Wildlife Sanctuary (KWLS)
and to avoid the same the earlier project was decided to be
developed in 2 stages Demwe Lower Project and Demwe Upper
59
Project within the allotted stretch given by the Government of
Arunachal Pradesh. The project proponent has submitted a revised
Form I afresh on 01.02.2008 seeking EC for Demwe Lower HEP
1750 MW. Therefore, upto the period on 1st February 2008 from the
date of original application namely July 2007, there could not be
any dispute by Mr. P. Abraham sitting as Chairman of EAC, as the
decision for bifurcation was taken due to reconnaissance. After
01.02.2008 Mr. P. Abraham remained as Chairperson till his
resignation on 22.06.2009.
74. After the revised application in Form I was filed by the project
proponent on 01.02.2008 the scoping approval was granted for
Demwe Lower HeP 1200 MW on 25.03.2008 and it was
subsequently raised to 1750 MW based on study on water
availability without changing physical parameter. On record it is
clear that either when Demwe Lower HEP 1200 MW was granted
TOR on 25.03.2008 or subsequently when it was increased to 1750
MW, such decision was arrived at collectively by all members of
EAC and no one of the members have ever given any descenting
opinion. In such view of the matter we are unable to appreciate the
contention that the above (TOR) was issued by EAC because of the
influence of Mr. P. Abraham.
75. Be that as it may, as it is seen on the record of the
proceedings of EAC, the effective consideration of Demwe Lower
HEP 1750 MW for scoping process was started for the first time on
21st and 22nd October 2009 as stated above. This was subsequently
continued on 15th and 16th December, 2009. It was in these 3
60
meetings of EAC, a clear cut and catagoric decision on discussion
regarding the project in question was taken. When Mr. P. Abraham
has resigned much before the said date namely on 22.06.2009 as
the Chairman, we are at last to understand as to how Mr. P.
Abraham would have influenced the members of EAC. During the
above said 3 meetings, Mr. P. Abraham was neither directly nor
indirectly involved in EAC and it was Dr. Devender Pandey who was
nominated as the Chairman and continued in these 3 meetings. In
the light of the thorough study made by all EAC members in these 3
meetings as enumerated by us while discussing issue no.2, the
contention of the learned Counsel for the appellant in this regard
has to be totally rejected on the simple ground that there is no
scope for bias at all. The next question which may be relevant to
some extent may be relating to the principle that one cannot sit on
judgment over his case. As a non- executive director of PTC India
Ltd. which was to supply certain materials to the project proponent
in this case, it is not understood as to how Mr. P. Abraham can be
said to sit in judgment over his case. Admittedly he is not
connected with Demwe Lower HEP 1750 MW project and it is not
even the case of the appellant that Mr. P. Abraham has any
monitory or other interest over the project. In the absence of any
materials on record to show that Mr. P. Abraham has any interest
over the project and he has influenced the other expert members,
which in our view cannot be even remotely possible, since all
experts are eminent persons in their field, there is no doubt in our
61
mind that the presence of Mr. P. Abraham in EAC as the Chairman
would vitiate all proceedings of the EAC.
76. At the cost of repetition, we are to say that in the above said 3
critical meetings of the EAC in which the project in question was
elaborately discussed by EAC, and recommended for EC, Mr. P.
Abraham was not the Chairman or Member of EAC and therefore,
the question of bias or a person cannot sit as a Judge of his own
case does not arise. In any event as stated above that was the most
preliminary scoping stage which was liable for alteration, addition
and modification by EAC based on not only the contents of Form 1,
site visit and other materials including the presentation by the
project proponent. In fact, in this case as stated above, based on
subsequent meetings of EAC additional TOR has been issued and
therefore, if there was any mistake committed, which is not even the
case of the appellant, there was lot of scope for EAC in the
subsequent meetings to rectify. It is further relevant to note that
EAC has sent its sub-group for site visit on 21.02.2008 and in the
site visit sub-committee of EAC Mr. P. Abraham was not a party.
Mr. P. Abraham in his reply has also stated that he has no personal
interest over the project concerned and in fact he has been working
in the hydro-electric power project for nearly 30 years. As
contended by the learned Counsel appearing for the appellant there
is absolutely nothing on record to show that Mr. P. Abraham was
made to resign at the instance of the then Hon’ble Minister of
Environment and Forests especially when it is the case of Mr. P.
Abraham that he voluntarily quit the post.
62
77. Further, even after the detailed EAC study, which was only a
recommendary body, it is ultimately the MoEF which is to issue the
EC which has in fact issued the EC on independent application of
mind and there is absolutely no scope to hold that views of Mr. P.
Abraham even if it is intentionally favourable to the project in
question would influenced the Government of India, when it is the
case of the learned Counsel appearing for the appellant himself that
the Hon’ble Minister himself wanted Mr. P. Abraham to go out of
EAC, which averment in fact is not supported by any acceptable
evidence. But then, in fact the same Hon’ble Minister of
Environment and Forest later approved the project for grant of EC
for the same.
78. Even otherwise, this Tribunal which is consisting of expert
members who have gone through the entire case relating to the
various proceedings of the EAC and granting of EC and applied their
technical mind and concluded that there is no flaw either in the
project or in the proceedings of the EAC or EC.
79. For all the above said reasons, we answer issue no, 1 against
the appellant and hold that the presence of Mr. P. Abraham has no
tendency of vitiating the EAC proceedings and consequently EC
issued by the MoEF.
80. Issue No. 3
3) Whether EAC has considered all the issues relating to
(i) The effect of the project on the cultural heritage of
Parshuram Kund?
(ii) Appraisal proceedings done as per the EIA Notification?
63
(iii) Delinking of the basin study from the EC and its effect?
(iv) Effect of peaking operations of the project?
(v) Effect on Biodiversity including the effect on Dibru-
Saikhowa National Park?
(vi) Cumulative impact study? And
(vii) Muck disposal and suggested sufficient safeguards.
The next important issue that arises for our consideration is as to
whether the EAC has considered the underlined 7 points in detail
and applied its mind and that application of mind is technically
feasible. This is relevant because if this Tribunal is satisfied that
that EAC being a statutory authority has applied its mind which
also consists of Expert Members, the Tribunal performing Judicial
function can always take a complete decision by itself.
81. The first and foremost point in this regard relates to the affect
of the project on the cultural heritage of Parasuram Kund. This
point can be clubbed with the 7th point in the said category namely
“muck disposal whether suggested sufficient safeguards.
82. While speaking about the history of the mountainous and
multitribal north-east frontier region called Arunachal Pradesh and
its tradition and mythology and while observing that it has a long
international border with Bhutan, China and Burma now called
Myanmar and also observing that the Tribals of North Eastern
States are historically protected, the Hon’ble Apex Court in State of
Arunachal Pradesh Vs Khudiram Chakma reported in 1994 supp.
(1SCC) 615, referring to Parasuram Kund observed as follows:
64
“41. The history of the mountainous and multitribal
north-east frontier region which is now known as
Arunachal Pradesh ascends for hundreds of years
into the mists of tradition and mythology. According
to Puranic legend, Rukmini, the daughter of King
Bhishmak, was carried away on the eve of her
marriage by Lord Krishna himself. The ruins of the
fort at Bhalukpung are claimed by the Akas as
original home of their ancestor Bhaluka, the
grandson of Bana Raja, who was defeated by Lord
Krishna at Tezpur (Assamuy). A Kalita King,
Ramachandra, driven from his Kingdom in the
plains of Assam, fled to the Dafla (now Nishang)
foothills and established there his capital of
Mayapore, which is identified with the ruins on the
Ita hill. A place of great sanctity in the beautiful
lower reaches of the Lohit River, the Brahmakund,
where Parasuram opened a passage through the
hills with a single blow of his mighty axe, still
attracts the Hindu pilgrims from all over the
country”.
83. Mr. Ritwick Dutta contends that in as much as Parasuram
Kund has got an aesthetic value on the religious point of view,
while approving any project which is likely to affect its sanctity
should be carefully considered while deciding about the effects
of such project on the said Kund. According to him this has
65
not been considered as per the requirement. It is not in
dispute that during the auspicious days of Makar Sakranti,
for a period of 10 days before and after, Hindu devotees visit
the Parasuram temple situated nearly 100 ms away from
Parasuram Kund and large number of people take sacred bath
in Parasuram Kund before climbing up to Parasuram temple
and the Hanuman Temple situated adjacent to that. Therefore
it is clear that Parasuram Kund is a place in the running
water where devotees take their sacred bath before reaching
the temple. Admittedly it is not the temple which is affected
by the project but even according to the appellant it is the
running water called Parasuram Kund which may be affected
either by the unregulated flow of water due to the project or by
accumulation of muck either during the time when the project
construction is on or subsequently. On the other hand it is
the contention of the learned Counsel for the project
proponent which is also not in the much dispute that
Parasuram Kund is located 100 ms along the river from dam
site of Demwe Lower HE Project and the temple is located on
the Hill on the left Bank river about 100m high from river bed.
On a reference to the 31st meeting of the EAC held on 21st and
22nd October, 2009 it is clear that the EAC has taken note of
the objection raised to the above said effect and it was ensured
from the developer that continuous flow of water will be
maintained downstream through a separate diversion channel
of 6m dia and during the operation period, continuous water
66
will be released downstream through a separate 40 MW
installed unit which shall run 24 hours continuously to
release 35 cumecs of water downstream to maintain the needs
at Parasuram Kund. It is also informed that during the time
of bridge construction by which traffic is regulated heavy
machinery was used apart from huge blasting operations and
that had no impact on the Kund. It was also informed that
regarding the impact of flow variations from 35 cumecs to
1729 cumecs especially during the month of January when
the normal flow is stated to be around 400 cumecs, a flow
regulation with the project would take place and during the
said month of January when Parasuram Kund Mela takes
place, 1 unit of 342 MW will be operated as determined.
84. It is stated by the project proponent that regarding the
tourism at Parasuram Kund even though as on date there is
no major infrastructure, provisions are being made for
developing infrastructure, sewage/ sanitations facilities,
marketing complex, shelter, recreation areas with a provision
of Rs. 2 Crores. It is seen in the minutes of the said meeting
that the amount of Rs. 2 Crores would be enhanced to 10
Crores which was agreed by the developer which amount is
directed to be used to ensure that no adverse impact takes
place during the construction and operation stage. It was also
directed by the EAC that during Mela period the release of
water must be regulated. Regarding the sedimentation and
silt flushing which includes the muck formation, it was
67
informed that regarding the periodic reservoirs flushing,
CEA/CWC has set certain guidelines and that the reservoir
operation and all necessary precautions shall be taken and
the reservoir be maintained at the MDDL during the period of
monsoon. This was again considered by the EAC in its
meeting held on 16.11.2009. It was confirmed that a warning
system to be installed at Parasuram Kund, that there shall be
no damage to the water body; Hill-Flora-Fauna, that there
shall be no encroachment in the entire temple area, that
efforts to beautify and develop the area should be taken up
and that the availability of water to the devotees should not be
hampered. The EAC has also taken note of the commitment
made by the project proponent to implement the conformation
of the SPCB. Therefore, it is clear that sufficient safeguard has
been taken for preserving Parasuram Kund and its water flow
that has been duly considered by the EAC on its application of
mind.
85. In the impugned EC also the MoEF while imposing
specific conditions has clearly specified in Clause 17 and 18
as follows:
“(xvii) The project will release normal lean season
flow for a period of 7 days during mela (Sankranti)
period in Parsuram Kund, in the month of January
as per the condition stipulated by the Parashuram
Kund Improvement Society.
68
(xviii) The financial allocation for the protection of
the Parasuram Kund should be enhanced from Rs.
2 crores to about Rs. 10 crores as suggested by the
EAC. The said amount would be utilized for
creating appropriate amenities infrastructure,
structures and safeguards etc. as decided by
Parasuram Kund Improvement Society who are
looking after the developmental activities related to
the Parasuram Kund”.
In such view of the matter we are of the considered view that
the said two aspects of preserving Parasuram Kund and proper
muck disposal have not only been considered but answered
properly and therefore we are of the view that the effect of
Demwe Lower HEP 1750 MW does not effect the cultural
heritage of Parasuram Kund and sufficient safeguards has been
taken up for an effective muck disposal.
86. Regarding the point as to whether the appraisal
proceedings have been done as per EIA Notification 2006, as it
is seen in Cluase7 stage IV, the EAC has not only taken note
of the undertaking given by the project proponent but also
studied the outcome of public consultation and in fact as
stated earlier, at least in three meetings, the EAC has
considered not only the contents of the proposal in Form 1 but
also all other aspects which are required as per EIA
Notification 2006, and Appendix V which prescribes the
procedure for appraisal and ultimately recommended the
69
issuance of EC to the project proponent. There is absolutely
no procedural flaw in the appraisal proceedings and therefore
one cannot come to a conclusion that appraisal regarding
Demwe Lower HEP is not in accordance with the EIA
Notification 2006.
87. As far as the decision regarding delinking of basin study from
EC and its effects, it is the contention of the learned Counsel
appearing for the appellant that the condition in the impugned
EC which states in Clause no. 16 as follows:
“(xvi) The project since falls in Lohit Basin and at present
the Basin Studies is ongoing and it was stipulated
during the grant of TOR for scoping that the
Environmental Clearance for Demwe Lower HEP
should not be linked with the completion of basin
studies. However, any recommendations that
emerge out from the basin studies shall be a binding
on the project developer in future”, makes it clear
that as the Lohit Basin Study is ongoing, the same
need not be linked with the issuance of EC. It is his
contention that the said condition is abnormal
specially when it also states that any
recommendations that emerge out from the basin
study after completion will bind the project
developer in future has no meaning because by that
time the project would have come into effect.
70
According to him it is putting the cart before the
horse”.
88. On the other hand it is the case of the project proponent
as well as the MoEF that the delinking of Lohit basin study
from the projects have been done in similar cases like Kalai-II
HEP for TOR, Hutong II HEP 1250 MW in Anjaw district,
Anjaw HEP 280 MW, Raigam HEP 96 MW on Dalai river in
Anjaw district and Gimliang HEP 99 MW on Dav river in
Anjaw district. It is also their case that delinking process for
grant of environmental clearance to the projects from
completion of the river basin study is a well practised
procedure and the same has been followed by EAC on earlier
occasion in respect of EC granted for Gongri HEP 90 MW,
Nafra HEP 96 MW, Divvin HEP 125 MW which were granted in
the year 2010 and 2011 and that the basin study which was
allotted in 2008 was completed in July 2011. Likewise EC
was granted in respect of Teesta Stage VI HEP 500 MW, Teesta
Stage III HEP 1200 MW, Roler HEP 36 MW, Jorethang, Loop
HEP 96 MW in the year 2004 to 2007 while the basin study
was completed in the year November, 2007. It is also stated
that in respect of TATO and HEP 700 MW, EC was granted on
27.06.2011 while the Siang basin study which was allotted on
23.12.2010 is still in progress. Likewise it is pointed out that
EC was granted on 19th May, 2011 regarding Sangtong,
Karchham HEP 402 MW while its Sutlej basin study was
allotted on 26.02.2011 which is still pending. It is also
71
pointed out that EC in respect of Selisep 400 MW was granted
on 02.06.2012 while the Chenab Basin Study was directed to
be continued. In addition to that many other instances have
also been pointed out wherein while river basin study are
going on, they were delinked from EC proceeding.
89. The report of inter ministerial group prepared by the
Government of India 2010 to evolve a suitable framework to
guide and accelerate the development of hydro power in North
Eastern Region has categorically decided that studies in the
Basin should be taken up by CWC but that will not hold up
the EC of individual projects. In as much as it is not in
dispute that in respect of many other projects it has been the
practice that regarding the hydro electric power projects, the
pendency of river basin study cannot be an impediment for
granting EC we cannot presume that the EC proceedings will
be vitiated by the delinking process. In fact sufficient
safeguard has been provided in the EC specifically stating that
any result of river basin study should be binding upon the
project proponent.
90. In respect of the effect of peaking operation, a reference to the
data analysis taken for 19 years regarding the flow in Lohit
river shows that the said river is well acquainted with flow
variability ranging from 200 cumecs to more than 12000
cumecs. It is also seen that more than 54 per cent times the
flow in Lohit River at Dam site is more than 1000 cumecs out
of which about 33.23 per cent time flow is about 1729 cumecs
72
which is the designed discharge of Demwe Lower HEP. It is
also seen that even during non monsoon months of December,
January and February the river rejoin experience large
discharge varying in the range from ranging from minimum of
1010 cumecs to 1373 cumecs and during monsoon season,
the same will be operated at MDDL by keeping the natural
flow regime since no storage is allowed. During lean season
the flow at dam site will vary between environmental flow
release and design discharge from power generations. It is
stated that to minimise the impacts of downstream
ecologically, detail assessment of environmental flow release is
carried out by M/s WEAPCOS as part of Lohit Basin study
and the same has been considered by the Expert Appraisal
Committee as also the MoEF. In such circumstances we have
to necessarily come to a conclusion that the effect of peaking
operations of the projects has been thoroughly considered by
the EAC. Regarding study of effect on biodiversity including
Dibro-Saikhowa National Park, it is clear from the records
that as the Government of India has been implementing the
National Wetlands Conservation Programmes (NWCP), and as
per the guidelines for conservation and management of
wetlands in India prepared in June 26, 2009 the Government
has identified nearly 15 wetlands and there are no wetlands
from the State of Arunachal Pradesh, except 3 namely Depar
Beel, Urpad Beel and Sone Beel which are located about 501
km, 557 km and 529 km respectively from Demwe Lower
73
Project. It is also clear that chapories of Lohit River have not
been identified as wetlands of national importance. The
chapories of Lohit river stated by the appellants relying upon
BMHS publication is stated to be located about 33 km away
downstream from the project site. The chapories are the
elevated regions provide retreat and shelter for animals during
flood. A study made by a three Member Committee
constituted by the National Environment Appellate Authority
covering 60 kms of river stretch from the dam site of Demwe
Lower HEP in Assam/ Arunachal Pradesh Boarder, found that
no endangered bird species including Bengal Floricam were
recorded by the Committee.
91. To study the variation between design discharge of 1729
m 3/s and average river discharge of 400 m 3/s, four
representative cross sections at the identified chapories were
taken and variation in water level was assessed by the
Committee which shows that maximum water elevation in all
4 locations remain well below the lowest elevation of
representative chapories. The project being run of the river
scheme is not likely to retain the inflow and
sediment/silt/boulders/nutrients etc and during monsoon,
river flow would be released normally and it was found during
the field visit that none of the Avian/ fauna / species were
encountered and their presence in area was also negated by
the local communities. Regarding the river dolphins it was
found as seen in the GOAP Committee that dolphin were
74
recorded only in Brahmaputra main stream. However, during
low water period, the upstream limit of dolphin distribution in
the river Lohit is Tengapanimukh which is stated to be located
about 72 km downstream along the river from Demwe Lower
HEP. Therefore it was found that the likelihood of the
presence of dolphins in the upstream of Tengapanimukh
during dry season is negligible. It is found to be not an ideal
condition for habitat of dolphins owing to limitations of low
depth. There has been interaction with local communities
including fisherman by the committee who conformed the non
availability of dolphins in the downstream dam. Regarding the
globally threatened avian species stated to have been situated
in chapories like Bengal Florican, Swam Francolin, Lesser
Adjutant, white beak Duck, Jerdom’s Babbler, Indian
Skimmer and Black- breasted Parrot Bill, the same are not
regularly found and the impact of the project was found to be
negative. Therefore the EAC has considered the downstream
impacts including those on the habitat of Bengal Florican and
MoEF is stated to be taking steps for conservation and
preservation of the said species in the entire country.
92. Relating to the downstream flow characteristics, the
studies show various data’s taken of 95% dependable year to
consider the worst case. Catchment area proportion method
was used for working out contribution of each tributary on 10
daily basis in the downstream stretches.
75
93. Regarding the impact on Dibru-Saikhowa National Park
(DSNP), it is seen from the minutes of EAC that it was at its
direction and as part of Lohit Basin studies the flow variations
at Dibru-Saikhowa was undertaken by M/s WAPCOS which
has filed its report to MoEF and it was stated that the National
Park is situated about 105 km downstream of the project. It is
also stated in the report that the flow in lean season at Dibru-
Saikhowa National Park in Lohit River varies between 400-700
cumec while the maximum discharge of peaking of Demwe
Lower would be at 500 cumec at National Park which is well
within the range of natural flow. The report thus concluded
that there is no other effect on non monsoon peaking
operation, as the submergence level at all times remain below
the lowest elevation of the park. All these facts have been
thoroughly considered by the EAC as it is seen in the minutes
of its three meetings.
94. The last point under the above topic is as to whether the
EAC has considered the cumulative impact study. The
meeting of EAC dated 21st, 22nd October, 2009 has taken
note of the entire cumulative aspect ranging from vast and
various states of divergent subjects including the minimum
flow and fishery aspects. As the area is highly seismic zone
the geological and seismological studies were carried out at
DPR studies apart from the social aspects and R&R plans
including the preservation of religious sanctity of Parasuram
Kund was duly considered and cumulative study in the form
76
of River Basin Studies which are going on, the Tribunal see
absolutely no reason to hold otherwise. The minutes of the
meeting of the EAC held on the said three occasions are the
standing testimony to show that there has been total
application of mind. Therefore, the issues raised in point no.
3 are all answered in favour of the project proponent.
95. Issue No. 4
Whether public consultation process has been done properly
and in accordance with the EIA Notification 2006.
The EIA Notification 2006 in Clause 7 stage number 3
explains the public consultation and it is stated to be a
process by which the concerns of local affected persons and
others, who have plausible stake in the environmental impacts
of the project are taken into account. As per the EIA
Notification 2006, the public consultation has two
components:
1) A public hearing at the site or in its close proximity as per
the manner prescribed in Appendix IV for ascertaining
concerns of local affected persons and
2) Obtain responses in writing from other concern persons
having plausible stake in the environmental aspects of the
projects.
The public hearing is conducted by the SPCB in a specified
manner and forward to the regulatory authority namely MoEF.
There is a clause which provides that in cases it is reported to the
Regulatory Authority that it is not possible to conduct public
77
hearing in which even the Regulatory Authority may decide that
the public consultation in a particular case need not include
public hearing. However, this later aspect does not arise in this
case as admittedly public hearing has taken place in two places.
After the completion of public consultation it is the duty of the
project proponent to address all the material environmental
concerns expressed during the said process and effect
appropriate changes in EIA report and submit the same to the
appropriate authority.
96. Appendix IV while contemplating the procedure for public
hearing to be conducted by the SPCB states about the notice
of public hearing stating that the same shall be advertised in
one National Daily and one Regional Vernacular Daily/ Official
State language giving 30 days minimum time to the public to
furnish their response. It also further states that the
proceedings of public hearing should be at the supervision of
the District Magistrate/District collector/Deputy
Commissioner or his representative not below the rank of an
Additional District Magistrate assisted by a representative of
SPCB who shall arrange videography of the entire proceedings
and forward the same to the Regulatory Authority. A time
limit has also been prescribed under the said appendix for
conducting public consultation.
78
97. On the facts of the present case it is not in dispute that
the following are details of notification published in the
newspaper:
Therefore it is clear that the publication of the notice about
the public hearing is more than what it is required under the
notification. It is also not in dispute that such public hearing
took place at Parasuram Kund Lohit District and Paya, Anjaw
District on 11.08.2009 and 12.08.2009 and about 519 and
237 people respectively have participated. During the public
hearing detailed written representations have been received,
19 persons from Parasuram Kund on 11.08.2009 and 7
persons at Paya on 12.08.2009. It is also stated that people
from downstream villages beyond the project area namely 10
km radius of the project attended public hearing. The said
places are stated to be Chongkham which is 53 kms, Alubari
which is 60 kms, Naupati which is 70 kms, Kathan which is
90 kms, Teesu which is 35 kms and Namsai which is 81 kms.
S.No Name of the Newspaper
Date and Language Publication Remarks
English Hindi Local (Mishmi)
1 Arunachal Times
10thJuly 09 11th July 09 10th July 09 Local Daily
2 Arunachal Front
11th July 09 11th July 09 11th July 09 Local Daily
3 Echo of Arunachal
11th July 09 11th July 09 11th July 09 Local Daily
4 Times of India
10th July 09 11th July 09 - National Daily
5 Purvanchal Prahari
- 11th July 09 - Regional Daily
6 Eastern Mail 12th July 09 12th July 09 12th July 09 Published Weekly on Sundays
79
It is also stated that a copy of EIA report, EMP report and
executive summary of the project were uploaded on the
website of SPCB and MoEF and therefore there is wide
publicity to enable plausible stake holders to effectively
participate and in fact there has been such participation. In
such circumstances we have no hesitation to hold that the
public consultation process has been done on facts of the
present case in accordance with the EIA Notification 2006.
The said issue is answered accordingly.
98. Issue No. 5
Whether the EC is liable to be held invalid.
As stated in detail, we have no doubt in our mind that there is no
suppression of any material fact by the project proponent either in
Form 1 proposal stage or subsequently, that the public consultation
process has been done in accordance with the provisions of the
EIA Notification 2006 and that the EAC which consists Experts
from various fields and who have independent status and merit
have considered in complete details on three of its meetings and in
fact called for more information and additional particulars from the
project proponent to satisfy itself as to whether the
recommendation of EAC is to be granted or not and therefore there
is a proper application of mind by the EAC. A reading of the terms
of EC impugned in this proceedings, issued by the MoEF also shows
that it is not as a matter of routine the impugned EC has been
granted but each one of the recommendations of the EAC has been
taken note of which is reflected from the special conditions
80
enumerated by the MoEF in the impugned EC. Further there was
no participation of Mr. P. Abraham during the most crucial stage of
consideration of environmental appraisal of the proposal of the
project proponent by the EAC on three of its crucial meetings held
on 21st and 22nd October, 2009, 16th November, 2009 and 15th and
16th December, 2009 and during the above said meetings Mr.
Abraham was not the chairman or Member of the EAC. Scoping
being the most initial stage, in respect of hydro electric project
which are site specific in nature except citing the area for the
project no much activities are done. Moreover, at the time of
scoping, as stated earlier the EAC has desired to make a field visit
to find out the suitability of the place during which time of course
Mr. P. Abraham was the Chairman but still the sub-committee
constituted by EAC to visit his part and submit its report does not
include the said Mr. P. Abraham. Therefore, the question of
tendency to influence or bias does not arise for consideration on the
facts and circumstances of the present case. The two contentions
mainly raised by the learned Counsel appearing for the appellants
namely in the scoping stage a foundation has been laid for the
project which cannot be altered subsequently and that public
consultation was not done properly are not acceptable at all. When
it is clear on fact that even during scoping stage there has been an
alteration of the project which was originally proposed as Demwe
Lower HEP 3000 MW for which in fact TOR was issued by EAC and
that has been subsequently changed by dividing it into two parts
when it was found that there was a possibility of submergence of a
81
national park which were on environmental concern. Moreover, the
additional TOR are being issued for the projects based on
subsequent information and clarification which are factually seen
in this case and therefore it cannot be accepted that any decision
taken in scoping stage either cannot be altered or changed by a
change in circumstance. In so far as it relates to the public
consultation on a reference to record it is clear that large number of
people have participated and the public hearing was conducted on
the spot of the project and the appellants who are stated to be living
in the downstream in Assam have been allowed to participate and
in such circumstances it is certainly not open to the appellants to
say that the public consultation was not properly done. Therefore
there is no iota of hesitation in our mind to hold that the EC
granted consequent to such a long drawn process cannot be vitiated
by the averments made by the appellants which are not correct on
the factual matrix.
99. There is one more aspect as raised by the learned Counsel
appearing for MoEF which is of utmost relevance to be considered.
The EIA Notification 2006 in Clause no. 7 (IV) while speaking about
stage 4 appraisal in sub-clause (i) states as follows.
“IV. Stage (4)-(i) Appraisal means the detail scrutiny
by the Expert Appraisal Committee or State Level
Expert Appraisal Committee of the application and
other documents like the Final EIA report, outcome of
the public consultations including public hearing
proceedings, submitted by the applicant to the
82
regulatory authority concerned for grant of
environmental clearance. This appraisal shall be
made by Expert Appraisal Committee or State Level
Expert Appraisal Committee concerned in a
transparent manner in a proceeding to which the
applicant shall be invited for furnishing necessary
clarifications in person or through an authorized
representative. On conclusion of this proceeding, the
Expert Appraisal Committee or State Level Expert
Appraisal Committee concerned shall make categorical
recommendations to the regulatory authority
concerned either for grant of prior environmental
clearance on stipulated terms and conditions, or
rejection of the application for prior environmental
clearance, together with reasons for the same”.
(Emphasis Supplied)
The EIA Notification 2006 in the above said clause also states that
the prescribed procedure for appraisal is given in Appendix V. The
said Appendix V is reproduced as follows for a better appreciation of
the contention raised by the learned Counsel appearing for MoEF:
“APPENDIX V
Procedure Prescribed for Appraisal
1. The applicant shall apply to the concerned regulatory
authority through a simple communication enclosing
the following documents where public consultations
are mandatory:-
83
A copy of the video tape or CD of the public
hearing proceedings
A copy of final layout plan (20 copies)
A copy of the project feasibility report (1 copy)
2. The Final EIA Report and the other relevant documents
submitted by the applicant shall be scrutinized in
office within 30 days from the date of its receipt by the
concerned Regulatory Authority strictly with reference
to the TOR and the inadequacies noted shall be
communicated electronically or otherwise in a single
set to the Members of the EAC/SEAC enclosing a copy
each of the Final EIA Report including the public
hearing proceedings and other public responses
received along with a copy of Form 1 or Form 1-A and
scheduled date of the EAC/SEAC meeting for
considering the proposal.
3. Where a public consultation is not mandatory, the
appraisal shall be made on the basis of prescribed
application in Form 1 and environment impact
assessment report, in the case of all projects and
activities (other than Item 8 of the Schedule), except in
case where the said project and activity falls under
Category ‘B2’, and in the case of Items 8 (a) and 9(b) of
the Schedule, considering their unique project cycle,
the Expert Appraisal Committee or State Level Expert
Appraisal Committee concerned shall appraise projects
84
or activities on the basis of Form 1, Form 1-A,
conceptual plan and the environment impact
assessment report (required only projects listed 8(b)
and make recommendations on the project regarding
grant of environment clearance or otherwise and also
stipulate the conditions for environmental clearance).
4. Every application shall be placed before the
EAC/SEAC and its appraisal completed within 60
days of its receipt with requisite documents/details in
the prescribed manner.
5. The applicant shall be informed at least 15 (fifteen) days
prior to the scheduled date of the EAC/SEAC meeting for
considering the project proposal.
6. The minutes of the EAC/SEAC meeting shall be
finalised within 5 working days of the meeting and
displayed on the website of the concerned regulatory
authority. In case the project or activity is
recommended for grant of EC, then the minutes shall
clearly list out the specific environmental safeguards
and conditions. In case the recommendations are for
rejection, the reasons for the same shall also be
explicitly stated.
(Emphasis Supplied)
100. The contention of Mr. Vivek Chib the learned Counsel
appearing for MoEF is that a combined reading of Clause 7
(IV) stage (4)/ appraisal (i) along with Appendix V especially
85
clause 6 of the said appendix, emphatically shows that in
cases of recommendation of the project and grant of EC by
MoEF or SEIAA, it is duty of the Authority to stipulate clear
terms and conditions based on the recommendations made by
EAC or SEAC as the case may be as that itself would amount
to reasons, and in cases where the MoEF rejects the grant of
EC it is incumbent on the part of the regularity authority to
give reasons explicitly. Otherwise it is his contention that as
per the statutory regulation, except imposing conditions to
safeguard environment either specifically or generally there is
no necessity on the part of regulatory authority to give any
other reason for every aspect of recommendations of EAC but
it is only in the cases of rejection of the proposal the reasons
must be given by MoEF whether it is rejecting the
recommendation of the EAC or otherwise.
101. It is no doubt true that when a proposal is recommended
or rejected, in a common parlance , in order to comply with the
principles of natural justice, assigning of reasons is a healthy
practise. But in cases where statute enumerates a particular
method, necessarily the said statutory method/stipulation ought to
be followed. The Tribunal being a creature of law cannot in our
considered view direct the parties to act against the statutory
regulations even in the guise of enforcing the principles of natural
justice. For taking the view that only in cases of rejection of EC the
regulatory authority has to give reason but for granting prior EC
except stipulating special and general conditions enforcing
86
environmental safeguard, there is a plausible reason. In case of
rejection the project proponent has a statutory right of appeal. For
filing appeal necessarily the affected person must know the reason
for such rejection. Therefore on a combined reading of the above
said provisions enumerated above we are of the view that in case of
grant of EC no specific reasons are necessarily to be assigned by
the regulatory authority which of course is a mandatory
requirement in case of rejection. To put it otherwise, it appears to
be the legislative intent that when EC is granted for a project it is
the utmost concern of the regulatory authority to preserve
environmental safeguard and if it is rejected, reasons are necessary
to be given explicitly to satisfy the concern of the affected project
proponent to enable him to exercise his right of appeal effectively.
102. Further there is no question of applicability of general
principles of administrative law when statute expressly explains
certain provision.
103. This was also the view of the Hon’ble Central Zonal Bench
of the NGT at Bhopal in Appeal no. 8 of 2013 (Ramesh Agrawal Vs
Union of India through MoEF and Ors.) (CZB), wherein under similar
circumstances the Tribunal has held that when the law prescribes a
specific provision of format on a special subject, the same has to be
followed and one cannot infuse the general principles of law. The
relevant paragraph of the Judgment are as follows :
“28. Lastly, it has been submitted by the Appellant
that the EAC ought to have given reasons for
acceptance or rejection. We find from the material on
87
record that at several stages of the appraisal various
queries were raised and further information was
sought from the Project Proponent. This is evident from
the Minutes of the Meetings of the EAC. After each
such meeting the NTPC has submitted its response
with supporting material and documents which came
to be placed before the EAC in the subsequent
meetings where it is recorded that various material
received from the Project Proponent was placed before
the members for consideration and on having
considered the same the Committee was satisfied and
recommended that the EC may be granted.
29. Learned Counsel argued at length that this was
not in accordance with the law as laid down in various
judgements regarding appreciation of the material, it
consideration and requirement to give reasons. We
have given out thoughtful consideration to the above
submission and the judgements relied upon by the
Learned Counsel for the Appellant. While there can be
no quarrel with the general proposition of recording the
facts and circumstances of the present case, the
procedure for appraisal has been prescribed under the
Environment Clearance Regulations, 2006 itself in
detail along with the format prescribed under
Appendix V in which the order is required to be
88
passed. Unfortunately, in the cases cited before us
this aspect has not at all been cited.
30. The procedure as provided and prescribed under
the Environment Clearance Regulations, 2006 is as
follows:
“7. Stages in the Prior Environmental Clearance (EC)
Process for New Projects.
APPENDIX –V (Already enumerated above)
31. The Scheme of appraisal quoted above clearly goes
to show that under para IV Stage (4) Sub para (i) while
carrying out appraisal the Expert may seek to clarify
any doubts by inviting the Project Proponent if any
clarification is required. The necessity is only in the
event of any doubts requiring clarification from the
Project Proponent and not any other person. On
conclusion of these proceedings the EAC or SEAC
concerned shall make their recommendations to the
regulatory authority either for grant of prior EC on
terms and conditions or for rejection of the application
for prior EC. In our view the words “together with
reasons for the same” only refer to reasons for
rejection. This is clear from a perusal of sub-para (iii)
of Para IV. Stage (4) under which it is provided that
“the prescribed procedure for appraisal is given in
Appendix V”. A perusal of Appendix V para 6 quoted
above only requires that in the case of favourable
89
recommendation for grant of EC “the minutes shall
clearly list out the specific environmental safeguards
and conditions” as opposed to giving any reason for
acceptance of the application. It further provides that it
is only “in case the recommendations are for rejection,
the reasons for the same shall also be explicitly
stated. Unfortunately while deciding some of the cases
the above statutory provision and requirement of
giving reasons only in the case of rejection as opposed
to reasons for giving a favourable recommendation
with specific environmental safeguards and
conditions, was not cited and thus the judgements
came to be delivered on the basis of general principles
of administrative law. When there is a specific
provision and a format is prescribed under the law
dealing the special subject the special law shall
override the general law and no fault can be found if
the recommendations for grant of EC by the EAC in
favour of the Project Proponent when made without
elaborating the same in the order for acceptance. The
law has taken care to provide remedy to any person
aggrieved in the form of filing an appeal against the
grant of EC which the Appellant has done in the
present case and on a consideration of the issues
raised in the appeal, we do not find any substance in
any of the objections raised before us so as to warrant
90
interference even assuming the reasons ought to have
been recorded for the benefit of any objector or
member of general public”.
104. While subscribing to the views of the CZB of NGT, Bhopal
as narrated above, we do not subscribe to the views expressed by
the WZB Pune of NGT in this regard as relied upon by the learned
Counsel for the appellant in Gau Raxa Hitraxak Manch and Gauchar
Paryavaran Pouchav Trust, Rjula Vs. Union of India in M.A. No.
94/2014 (WZ) in Appeal No. 16/2014 (WZ). In that case a reference
to the consent order made in M.A. shows that the parties have
accepted that EAC or MoEF shall pass (speaking orders) giving
reasons either for recommendation/non- recommendation of
approval or rejection. Apart from the fact that this is a consent
order passed in M.A. there is no discussion about either clause 7
(IV) and Appendix (V) together and the said order cannot be treated
as laying down a law. In any event, one cannot give a go bye to the
statutory provisions in the guise of entering consent or agreement.
Therefore we disagree with respect, to the views of the WZB, Pune
and totally agree with the elaborate order of the Hon’ble NGT Bench
of CZB, Bhopal. For all the reasons stated above and looking from
any angle we are unable to take a stand that the impugned EC
granted to the project proponent is liable to be held invalid.
Accordingly we hold that the EC granted to the project proponent
dated 10.02.2010 for Demwe Lower HEP 1750 MW project in Lohit
District of Arunachal Pradesh is perfectly valid in law and is in
accordance with the provisions of EIA Notification 2006.
91
Consequently the Appeal is devoid of any merits and liable to be
dismissed and accordingly dismissed, however without any order as
to cost.
105. While, parting with, we make it clear that all the special and
general conditions stipulated in the EC shall be scrupulously
followed by the project proponent and the same has to be properly
monitored by both the regulatory authority and the State Pollution
Control Board, We also reiterate that the project proponent must
take all necessary steps to see that the existing nature of
Parasuram Kund, including its water flow, especially during Mela
season shall be maintained and all agreed developments in and
around the Kund shall be carried out and the entire area is
maintained with serene atmosphere. Further, the River Basin
Study shall be completed expeditiously and any
recommendations/decisions arrived at therein shall be directed to
be strictly followed by the project proponent. The minimum
environmental flow in respect of Demwe Lower HEP as stated in the
studies of EIA/EMP, on the downstream discharges shall be
maintained for the survival of the fish species and all aquatic life.
Experience is the best teacher and therefore, we should not refuse
to learn from our experience of running HEP in the given situation.
We, therefore, direct the MoEF and Arunachal Pradesh State
Pollution Control Board to undertake study of impacts of the project
on the environment including flora and fauna downstream Lohit
92
River till 2020 for a period of next 5 years at the cost of the project
proponent namely respondent no.3.
Delhi
Dated:13th January, 2015.
………….…………….……………., JM
(Justice Dr. P. Jyothimani)
………….…………….……………., JM
(Justice U.D. Salvi)
………….…………….……………., EM
(Dr. G.K. Pandey)
………….…………….……………., EM
(Ranjan Chatterjee)