70
May 1 992 Bechtel National, Inc.

Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

May 1 992

Bechtel National, Inc.

Page 2: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

POST-REMEDIAL ACTION REPORT

FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT

THE ALBANY RESEARCH C E W R

ALBANY, OREGON

Prepared for

United States Department of Energy

Oak Ridge Field Office

Under Contract No. DE-AC05-9 1OR2 19 4 9

Bechtel National, Inc.

Oak Ridge, Tennessee

Bechtel Job No. 14501

Page 3: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

Page

F i g u r e s . . . . . . . . . . . . . . . . . . . . . . . . . . . i v T a b l e s . . . . . . . . . . . . . . . . . . . . . . . . . . . v i Acronyms . . . . . . . . . . . . . . . . . . . . . . . . . vii Units of Measure . . . . . . . . . . . . . . . . . . . . viii 1 . 0 INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . 1 . . . . . . . . . . . . . . . . . . . . 1.1 BACKGROUND 1 . . . . . . . . . . . . . . . . . . . . . . 1 . 2 HISTORY 4

. . . . . . . . . . . . . . . 2 . 0 REMEDIAL ACTION GUIDELINES 6

3 . 0 REHEDIALACTION . . . . . . . . . . . . . . . . . . . . 11 3 . 1 CLEANUP/DECONTAMINATION A C T I V I T I E S . . . . . . . . 11 . . . . . . . . . . . . . . 3 . 1 . 1 E x t e r i o r A r e a s : 11

3 . 1 . 2 B u i l d i n g s . . . . . . . . . . . . . . 26 . . . 3 . 2 CONTAMINATION CONTROL DURING -DIAL ACTION 45

4 . 0 POST-=DIAL ACTION MEASUREMEMTS . . . . . . . . . 47 4 . 1 EXTERIORAREAS . . . . . . . . . . . . . . . . . . 47 4 . 2 BUILDINGS . . . . . . . . . . . . . . 49

5 . 0 POST-REMEDIALACTION STATUS . . . . . . . . . . 56

GLOSSARY . . . . . . . . . . . . . . . . . . . . 59

iii

Page 4: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

Title Page

Location of the Albany Research Center . . . . . 2

Plan View of ARC . . . . . . . . . . . . . . . . 3

Remediated Areas at Exterior Area 1 (Parking Lot) ~ . . . . . . . . . . . . . . . . . . 14 Remediated Areas at Exterior Area 2 . 15

Photograph Showing Chambers of Lime Pit . 16

Photograph Showing Gas Chromatograph for PCB Analysis . . . . . . . . . . . . . 17 Correlation of PCB Data Using CLP Analysis Versus Onsite Analysis at the Albany Research Center . . . . . . . . . . . . . . . 19

Location of LSA Boxes Containing Drums of PCB Waste . . . . . . . . . . . . . . . . . . . . 20

. . . . . . . Remediated Areas at Exterior Area 3 24

Remediated Areas at Exterior Area 4 (ParkingLot) . . . . . . . . . . . . . . . . . 25

. . . . . . . Remediated Areas at Exterior Area 5 27

Remediated Areas in Building 1 . . 28

Remediated Areas in Building 3 . . 29

ReanediatedRreas in Building 4 . . . 30

Remediated Areas in Building 5 . . . 31

Remediated Areas in Building 17 . . . . 32

Remediated Areas in Building 23 . . . 33

. . . . Remediated Areas in Building 23 Basement 34

~kediated Areas in Building 24 . . . . . . . . . 35

. . . . . . . . . Remediated Areas in Building 25 36

. . . . . . . . . Remediated Areas in Building 26 37

. . . . . . . . . Remediated Areas in Building 28 38

Page 5: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

Figures

(cont inued)

Figure Title Page

3-21 Remediated Areas i n Bui ld ing 28 Basement . 39

3-22 Remediated Areas in Bui ld ing 29 . . . . . . 4 0

3-23 Remediated r re as i n Bui ld ing 30 . . . . . 4 1

3-24 Remediated Areas i n Bui ld ing 3 1 . . . . . . . . 4 2

3-25 Remediated Areas i n B u i l d i n g 33 . . . . . . . . . 4 3

3-26 Remediated Areas i n B u i l d i n g 34 . . . . . . . . 44

Page 6: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

TABLES

Table

2-1

Title Page

Summary of Residual Contamination Guidelines . . 7

Supplemental Guidelines for Selected Areas at A R C . . . . . . . . . . . . . . . . . . . . . . . 9

. . . . . . . Cleanup/Decontamination Techniques 12

PCB Drum Inventory . . . . . . . . . . . . . . 21 Analytical Results for Soil Following Remedial Action . . . . . . . . . . . . . . . . . 48

PIC Ueasurements in Exterior Areas Following Remedial Action . . . % . . . . 50

Post-Remadial Action Surface Activity Heasurements . . . . . . . . . . . . . . . . . 51

PIC Measurements in Buildings Following . . . . . . . . . . . . . . . . . Remedial Action 53

Page 7: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

AEC

ANL

ARC

BNI

CFR

DOE

EPA

ERDA

FUSRAP

GC

HEPA

IVC

LSA

ORAU

PCB

PIC

PMC

TSCA

Atomic Energy Commission

Argonne National Laboratory

Albany Research Center

Bechtez National, Inc.

Code of Federal Regulations

Department of Energy

Environmental Protection Agency

Energy Research and Development Administration

Formerly Utilized Sites Remedial Action Program

gas chromatography

high-efficiency particulate air

independent verification contractor

low-specific-activity

Oak Ridge Associated Universities

polychlorinated biphenyls

pressurized ionization chamber

project management contractor

Toxic Substances Control Act

vii

Page 8: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

cm

cpm

dpm f t

g

gal h

ha

in.

L

m

pci

P9

PR mi

ml

mrad

mrem

pCi

PPm

Yd

Yr

centimeter

counts per minute

disintegrations per minute

foot

gram

gallon

hour

hectare

inch

liter

meter

microcurie

microgram

microroentgen

mile

milliliter

mill irad

millirem

picocurie

parts per million

yard

year

Page 9: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

This report documents remedial actions performed at the Albany

Research Center (ARC) in Albany, Oregon (Figure 1-l), which is

owned by the U.S. Department of Interior and operated by the U.S.

Bureau of Mines, Work was performed under the Formerly Utilized

Sites Remedial Action Program (F'USRAP), a U . S . Department of Energy

( W E ) program instituted in 1974 to identify and clean up or

otherwise control sites where resiaual radioactive contamination

remains from activities carried out under contract to the Manhattan

Engineer District and the Atomic Energy ~obission (AEC) during the

early years of the nation's atomic energy program. In 1978,

Congress added ARC to the list of FUSRAP sites because of the type

of commercial operations performed there. Bechtel National, Inc.

(BNI), the project management contractor (PMC), represented DOE in

the planning, management, and implementation of this PUSRAP

remedial action. Oak Ridge Associated Universities was the

independent verification contractor (IVC).

ARC is located on the 17-ha (42-acre) site of the former Albany

College. The ARC property is rectangularly shaped and is bounded

on the north by Queen Avenue, on the east by Liberty Street, on the

south by a tennis club, and on the west by Broadway Street.

Figure 1-2 depicts a plan view of the site.

The site includes three main areas: ARC proper, which consists

of 31 buildings in the northern and central portions of the site; a

0.8-ha (2-acre) area that once contained a biomass research

facility (decommissioned) in the southern portion: and an open area

identified as the "Back Forty," which occupies approximately 5.7 ha

(14 acres) at the southern end of the facility.

Phase I of the remedial action project was conducted in 1987

and 1988, and a post-remedial action report describing this work

was published in 1989 (BNI 1989a). Subsequent radiological survey

data indicated that additional remedial action was necessary; this

formed the basis for Phase I1 work. In Phase 11, radioactive

Page 10: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

W A S H I N G T O N

O R E G O N

Figure 1-1 Location of the Albany Research Center

Page 11: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

Figure 1-2 Plan View of ARC

Page 12: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

contamination was removed from 5 exterior areas and from portions

of 15 buildings at ARC during the 1990-91 remedial action.

This report documents the methods used to determine the extent

of contamination, the type of remedial action performed during

Phase 11, guidelines used in performing this remedial action, final

excavation limits and depths, and post-remedial action data on the

current radiological status of the property.

ARC was established in 1943 to investigate innovative

approaches for developing strategic mineral resources in the United

States, reducing costs for metallurgical m&nufacturing processes,

developing materials to reduce corrosion, and conducting other

metallurgical research.

Various operations involving radioactive materials were

conducted at ARC. From 1948 to 1956, the U.S. Bureau of Mines

conducted work for AEC that involved melting, machining, welding,

and alloying thorium. Additional work with uranium and thorium was

conducted for the Energy Research and Development Administration

(ERDA) and others involving radioactive materials that resulted in

contamination of buildings not subject to FUSFtAP responsibility.

At various times while work was being conducted on AEC and ERDA

contracts with the Bureau of Mines (1948 to 1978), process

buildings and surrounding areas were decontaminated to ARC, ERDA,

and DOE cleanup guidelines in effect at those times. Those

guidelines were not as stringent as those in effect when the

contract work at ARC was terminated, and the records relating to

the decontamination efforts were not adequate to determine whether

the buildings and surrounding areas met the current W E

radiological cleanup guidelines. Therefore, in 1978 a radiological

assessment of ARC was initiated. The assessment determined that

although the levels of contamination at ARC did not pose an

immediate health hazard, further decontamination of the property

was advisable (ANL 1983).

Page 13: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

In early 1984, a more detailed radiological survey was

conducted at ARC to determine actual levels of radioactivity in

each area that had been identified previously as being contaminated

and to define the exact boundaries of contamination. This survey

revealed that approximately 1,988 m3 (2,600 yd3) of contaminated

material would require removal from the A R C site to comply with DOE

remedial action guidelines. A report documenting an evaluation of

remedial action alternatives for the site was issued in June 1985

(BNI 1985). This evaluation included decontamination of buildings,

excavation of contaminated soil, backfilling and seeding of excavated areas, and transportation of much of the waste, soil, and

rubble for disposal at the DOE Hanford Reservation in Richland,

Washington. Phase I of remedial action wa's initiated in 1987 to decontaminate most of the areas at ARC that required remediation

under FUSRW. Surveys conducted after 1987 identified additional

areas of radioactive contamination exceeding DOE remedial action

guidelines, primarily in building areas that had not been

previously surveyed under PUSRAP. Further characterization to

delineate the boundaries of contamination and subsequent remedial

action (Phase 11) was initiated in August 1990 and completed in

April 1991. This report provides information on the status of ARC

after completion of the 1990-91 remedial action effort.

Page 14: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

Radioactive contamination at ARC consisted primarily of

thorium-232; however, uranium-238 was found in association with

thorium-232 at varying ratios in several areas. Table 2-1 lists

the W E residual contamination guidelines for unrestricted release

of formerly contaminated property (DOE 1990) ; Table 2-2 lists

supplemental guidelines for areas where uranium-238 was the primary

contaminant. DOE adopted these guidelines based on their

compatibility with Enviranmental Protection Agency (EPA) criteria

in 40 CFR 192 for remedial action (DOE 1986).

The remedial action guidelines used at ARC for thorium-232 in

soil were 5 pCi/g averaged over the first 1 5 cm (6 in.) of soil

below the surface and 15 pCi/g averaged over any 15-cm- (6-in.-)

thick soil layer below the first layer. These guidelines were

applied to thorium-232 concentrations in soil after background

concentrations were subtracted.

There are no generic DOE guidelines for uranium in soil. At

ARC, characterization data indicated that uranium-238 and

radium-226 were in secular equilibrium; therefore, compliance with

the remedial action guideline for radium in soil (which was the

same as that for thorium-232) ensured that the concentration of

residual uranium-238 is also acceptably low (DOE 1986). For this

reason, a separate site-specific guideline for uranium was not

calculated.

Remedial action guidelines for surface contamination at ARC

varied depending upon the primary contaminant. For areas where

thorium-232 was the primary contaminant, the remedial action

guidelines were 1,000 dpm/100 d average and 3,000 dpm/100 cmz maximum for fixed contamination, and 200 dpm/100 cd for removable

contamination. For areas where natural uranium-238 was the primary

contaminant gut was associated at varying ratios with thorium-232,

supplemental guidelines for fixed contamination were used.

Table 2-2 shows the supplemental guidelines agreed upon between the

PMC and DOE for these areas. The average and maximum beta-gamma

radiation levels associated with surface contamination were not to

Page 15: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

TABLE 2-1 SUMMARY OF RESIDUAL CONTAMlNATlON GUIDELINES

BASK: DOSE LIMITS

The basic limit for Me annual radiation dose (excludiw radon) received by an M u a l member of the general puMi is 100 mmrru'yr. In implementing thk limn, DOE applies as low as reasonable achievable principles to set site-speciflc guidelines.

SOIL G U I D E L M

Other Radionudldes

8 d l ~ ~ ) * b w r ~ ~ ~

5 pCVg when avwa@%j over ths f i rd l5 an of mil b d w the surf-; 15 pWg rrhar a v e m wsr my 15an-thiik sdl layer below the surf- layer.

Soit guidsliw wiH be calwlatej on a s#sapsciflc beds uahg ihe W E m w l - for this uw.

Gene& gublhea for -tratbns of a i b m radon decay p m d a shall appty to edst[ng ocwpled or habiteble atrudures on privats property that has no raddogical mdctions on iE8 stnxhrss that will tm demdlshed or krried am excLded. The a p p l i i gawk guideline (40 CFR 192) is: In any occup(ed or habitable buldlng, the obJective of remedial action shaU be, and reason* elfal shall be made to a c h i , an annual (or equivalen8) radm &cay produa caroentrnlion (including beckground) not to exceed 0.02 WL~. In any case, the radon decay product wncentratbn ( W n g background) shall nol exceed 0.03 WL. Remedial a5b-t~ are not required in order to comply wlth mis guideline when *re is reasonable a s s u r m that reskiual radoactive matera am not tha cause.

External Gamma R.dbtion

The average level of gamma redlatlon inslde a building or habitable structure on a slte that has no r a d i i b g d restridions on its we shall not exceed the badaground level bv more than 20 u R ~ and wlll comotv wlth me . . basic dose l imb when an appropriatsuse sceneirio is consideied.

U-Natural, U-235, U-238, and associated decay products 5,000 a 15,000 a 1,000 a

btagamma 9mitte.r~ (radionudides with decay 5.000B-T 15,OoDB-y 1,ODDe-y modes other than alpha mission or spontaneous fission) e m p t Sr-gO and others noted above'

Page 16: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

TABLE 2-1 (CONTINUED)

%ese guidelines take into ecmunt inglpwth of radium226 Irun thorium-230 and of radium-228 from lhorium-232, and assume secular equilbrlum. If either tholfum-290 and radlum-226 or thorium-292 and radium-ps are both present, not in secular equlibrkm, the guidelines apply to the hlgher concsnfratbn. If other mbmlres of m d l r m c l i i occur, the wncen t ra t i i of individual radionudides shal be reduced sa that (1) the dose for the rn'ktures will nol exceed the bask dose limit, or (2) the sum of ratios d the soil ccncemat'ion of each radionuclie to the albwable lbnlt lor that radionudide will not exceed 1 WM'f).

"These guidelines represent a l l w e residal ccnwntrations above -round averaged acmss any i5m- th ick layer lo any depth and over any contiguous 100.M svrfaoe area.

'lf the average concentratkn in any surlaca w b e l ~ u W a m less than w epral to 25 mP exceeds the authorized lbnl or p u W h by a f&m d (1 DO/A)V: where A is the area of the elevated regbn in s q u m meters, limb for 'hot *' shall also be applicable. Pmcedurea for dadd i r rp t h w ho4 .pot hk, lvhii depend on the exlent d the slsMtsd bcal mmentratbm, am @ven in ihe W E Mwwd for lmpbmenthg Rssidud RaBoaclive M.teri& Guidelime, DWCHIBBO/. In sddltion, ewy rsasonPMe e M shell ba rmde lo re- any source of rsdlonudide thal e*oseda 30 timsa ths appropriale hit for dl, inaapsctive d the aversge camxdmlion in h soil.

d~ working level (WL) is any aunblnah of 6hrI-lived radon decay produds in I liter d sir that WH mull in the u h l e emlseion of 1.3 x 1W MeV of polentiad alpha energy.

'AS used in Ws table, apm (diintsg- per mhute) roans ihe he d emis&m by radlowtlw rna(erlal as deter&& by conedlnp the counts per mlnute measured by an appropriate detector for beckglMnd, el'k+Mw, and gem& factors aseDclated wiih the instrumentation.

'Where surlece cartsmhatlon by b& alpha- and bet.-gamma-emlltlng radlonudldes enlsts, the h l t s established for alpha- and bete-gamma-ernlttlng rediudldes sharld apply hdependently.

%hsmments d s v v cxxltMnlnaIbn should not be averaged over an area d more then 1 d. Fcr objects d bss wrfaoe area, the averege should be derived fa each such cqect.

%w average and manimurn doee rates assdatsd with subface contaminabion resulting from betagamma emitters should not exceed 0.2 mradm and 1.0 rnradh, respedively, at a depth of 1 an.

h e n-mjrnum cantemhation level applies to an area d not more than 100 c ~ .

he amount of re- radiottcttve material per 1 W cm' d s u b area should be determined by M p i q an area of that size wlth dry fiter or d l abmtmi paper, a o M n g moderate pcessure. and rneasudna the amount of r a d i m d h material on the wpe wlth an appmprbte.In&ru-mnt of k m efticbncy. When rekwabb cartamination m obieds d wrfaca area less then 100 anP is d e t e M , the actlviiy per unit area should be based on the actuai area and the entire surtace should be vped. ll is not nec&.to use wiping tehnlques to measure removable antarnhalim w s i f drect scan sumvs lndcale that total residual sulfaoe cotamlnatim I d s are within the limits for removaMe wntaminalbn.

"GuideUnes for theae r a d i a x l c l i i are not given in DOE Order 5400.5; however, these guldelires are arnsidared a p p l i b 3 mtil @J&mcE is prwided.

I This category of ~ad i iud ides inckdes mlxed fission products, Muding the SI-90 which is present in them. It does rat apptj to SrgO which has been %parated from the other fission products or mimres where the Sr-W has been enrich&.

Page 17: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

Table 2-2

Bupplemental Guidelines for Selected Areas

at ARC

Average Total

Contaminationn Building Area (dpm/lOO cm2)

Lab 10 (floor)

Lab 10 (other)

Attic

Attic

Fab. room

First floor

Lime pit walls

Forklift

'Areas containing removable contamination were to meet thorium-232 criteria (200 dpm/100cd).

b ~ o i l containing thorium at concentrations of less than 5 pCi/g and polychlorinated biphenyls at less than 1 ppm was mixed with clean topsoil fill and placed back into the pit.

'This guideline was used for any contamination found within tfie top 15 cm (6 in.) of the walls; the criteria for any contamination below 15 cm (6 in.) was the soil guideline for residual thorium-232 (15 pCi/g).

Page 18: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

exceed 0.2 and 1.0 mrad/h, respectively, at a depth of 1 cm

(0.4 in.) (see Table 2-1).

During the remedial action work, a few areas were identified as

being extremely difficult and expensive to clean up and yet

representing little or no risk to human health and the environment.

A hazard assessment was performed to justify that any residual

contamination above t h e , W E cleanup guidelines remaining after

remedial action was completed would not pose a significant risk

(BNI 1991). Several other areas found to be contaminated were not

decontaminata, at the request of ARC representatives, due to the

possibility of future recontamination. These areas included the

baghouse, piping, centrifuge, and collection drum east of

Building 23; a 25-cm 0 - n ) pipe originating on the west side of

the crusher room in Building 23; and the conical mill located in

the crusher room in Building 23.

Page 19: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

3.0 =MEDIAL ACTION

3.1 CLEANUP/DECOHTAlIIHATIOM ACTIVITIEB

3efore initiation of the remedial action in 1990, the site was

resurveyed to more accurately define the boundaries of

contamination in designated and additional areas. Five exterior

areas and 15 buildings identified as being contaminated were

cleaned up to meet current DOE remedial action criteria and

restored. As remediation and restoration work was being completed,

measurements were taken w i t h a pressurized ionization chamber

(PIC), direct contact beta-gamma measurements were taken with a

Geiger-Mueller counter, and direct contact'alpha measurements were

taken with an AC-3 alpha scintillation detector to confirm that the

remediated areas met the cleanup guidelines.

A variety of techniques were used to perform the

cleanup/decontamination work: these techniques are surmaarized in

Table 3-1. Following decontasination, most areas and equipment

were restored to their original or similar condition. For example,

if contaminated cabinets or shelves had to be removed and disposed

of, they were typically replaced with similar items. In a few

instances, it was determined that replacement or restoration of

items was not necessary: these exceptions are noted in this

section.

3.1.1 Exterior Areas

The background radiation level in asphalt was established by

taking direct beta-gamma readings on asphalt in several locations

throughout Albany. These measurements were averaged to establish a

background radiation level of 17 cpm. This background value was

subtracted from all measurements taken on asphalt in the exterior

areas.

Page 20: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

Table 3-1

cleanup/~econtamiliation Techniques

Technique Description

Hand wiping

vacuuming

Wire brushing/ grinding

Using needle gun

Scabbl ing

Small areas or equipment that had loose dirt, dust, greasy film, etc., were wiped with a dry cloth or a cloth wetted with a detergent solution to remove the loose surface contamination.

Large areas, items, and pieces of equipment (e.g., floors, shelves, cabinets, rafters) that had large amounts of dust in or on them were vacuumed with a high-efficiency particulate air- (HEPA-) filterad vacuum to remove the loose surface contamination.

Hard, nonporous surfaces (e.g., steel plate, pipes, equipment) could often be decontaminated by using a wire brush to remove loosely adherent dirt, scale, rust, etc. A power hand grinder was used to remove the surface layer of more adherent contamination.

The needle gun is a hand-held device with abrasive needles that abrade a surface; it is used on hard surfaces where wire brushing or grinding is not practical.

Reciprocating pistons on the scabbler head were used to break up the surface layers of concrete or asphalt so that loose material could be vacuumed.

Jackhammering A conventional jackhammer was used to remove larger layers or chunks of concrete and asphalt.

Planing

Excavation

A conventional table-top or hand-held wood planer was used to remove the surface layer of wood.

Contaminated concrete, asphalt, and soil were removed from exterior areas by using backhoes and shovels.

Page 21: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

Exterior Area 1

Area 1 is an asphalt and concrete parking lot south of

Building 30 and southwest of Building 31 (Figure 3-1). During

characterization between Phase I and Phase 11, radioactive

contamination at concentrations above remedial action guidelines

was found in samples from boreholes 4 and 5. The thorium-232

concentrations in these two samples were 16 and 26 pCi/g,

respectively. Contamination extended from the top surface of the

asphalt to a soil depth of approximately 15 cm (6 in.). The area

was remediated by renoving approximately 1.5 m3 (2 yd3) of

contaminated soil, asphalt, and concrete from the parking lot.

Area 2, known as the lime pit area, is the largest, most

complex exterior area remediated at ARC. It is east of Building 31

and adjacent to a concrete loading dock (Figure 3-2). The pit

contains three concrete chambers and is approximately 2.2 by 6.5 m

(6 by 18 ft) in area and 3 m (10 ft) deep (Figure 3-3). he‘ pit was used to segregate heavy metals from waste residue; however,

characterization did not indicate the presence of heavy metals or

any residual contamination covered by the Resource Conservation and

Recovery Act. The soil in the pit contained thorium-232 at an

average concentration of 32 pCi/g and polychlorinated biphenyls

(PCBs) at levels of up to 2,625 ppm. Because of the potential

volume [approximately 23 m3 (800 ft3)j and location of soil

containing PCB-contaminated radioactive waste, remedial action was

performed in accordance with Toxic Substances Control Act (TSCA)

regulations, which require that wastes containing PCBs at

concentrations greater than or equal to 50 ppm be handled in

accordance with 40 CFR Part 761. As required under TSCA, DOE

notified EPA, which issued a PCB waste storage identification

number for the eventual shipping and disposal of the waste.

To fully characterize the extent of PCB contamination within

the lime pit, an onsite gas chromatograph (GC) (Figure 3-4) wqs

used to analyze samples for PCBs using the Modified Spittler method

Page 22: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

rn Hole 115 n r w

Hole %4 area

Figure 3-1 Remediated Areas at Exterior Area 1 (Parking Lot)

Page 23: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department
Page 24: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

Figure 3-3 Photograph Showing Chambers of Lime Pit

Page 25: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

Figure 3-4 Photograph Showing Gas Chromatograph for PCB Analysis

Page 26: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

(Spittler 1984). Approximately 10 percent of the soil samples

collected were divided so that an aliquot could be sent to the

offsite contract laboratory for analysis to confirm the data

obtained from the onsite GC. The correlation of the onsite GC data

and laboratory data is illustrated in Figure 3-5.

PCB levels ranged from less than 1 ppm to 2,625 ppm and

averaged 315 ppm. The soil excavated from the lime pit also

contained thorium-232 at concentrations of 0.9 to 43.6 pCi/g (with

an average concentration of 32 pCi/g), radium-226 at 0.5 to

1.6 pCi/g, and uranium-238 at 1.8 to 5.8 pCi/g (BNI 1989b).

Approximately 23 m3 (800 ft3) of soil was excavated from the

lime pit and a small area adjacent to the pit, including 12 m3

(420 ft3) of PCB-contaminated soil and 9. 5'm3 (330 ft3) of mixed

PCB-contaminated radioactive soil.

The interior walls and floors of the pit were scabbled until

the PCB levels were below 50 pg/100 cm2. [The EPA guideline for

PCB-contaminated surfaces is 100 pg/100 cma (40 CFR 761).] During

both remedial action and post-remedial action surveys, cotton gauze

was dipped in an appropriate solvent and used as a swipe material

for determining surface contamination; the swipes were then

analyzed using the GC. The walls of the pit were not restored

because ARC has no plans to return the lime pit to active use.

Waste containing only radioactive contamination was placed into

low-specific-activity (LSA) containers and transported to the

Hanford Reservation for disposal. PCB-contaminated radioactive

waste was placed in 208-L (55-gal) Deparhent of Transportation

(DOT) 17-C drums. Three drums were placed in each of 42 LSA boxes

and stored in a weather-protected, secure area onsite (Figure 3-6),

pending acceptance of the waste for disposal by Hanford. A label

identifying the level of PCBs in the waste was placed on each drum,

as required by Hanford. Table 3-2 provides the individual drum

inventory, including PCB levels and contents.

Post-remedial action soil samples were collected to ensure that

all contamination was remediated to remedial action guidelines.

Analytical results of these samples showed an average thorium-232

concentration of 2.4 pCi/g. The maximum uranium-238, radium-226,

and thorium-232 levels were 11.2, 1.9, and 8.3 pCi/g, respectively.

Page 27: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

..............................................................................................................................................

..............................................................

..................................

...................................................................................................................

I I I I I I I I

1 100 200 300 400 500 600 700 800 900 Bechtel Results (ppm)

Figure 3-5 Correlation of PCB Data Using CLP Analysis Versus

Onsite Analysis at the Albany Research Center

Page 28: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

N 0

Figure 3-6 Q1 - Location of LSA Boxes Containing Drums of PCB Waste m

00 0 -

Z BUILDING 18

I 014 020'

Z " E 0

018 z

025 ,002 2 028

027 029 PPU EIH7RIL

028 EmmnINT

030 032 6 ft.

32 ft, 031

1 , 033 035 Not drawn t o scale.

034 Measurements are approxlma.ted -to 036 038 the neorest foot,

037 Numbers are lndlvldual drum 039 041 Identlf lcatlon.

040 044 046

045

9 ft, 2 7 q i N 71' N

BuLSABUXESIVI 0

Page 29: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

T a b l e 3-2

PCB D r m Inventory

Pnae 1 o f 2

D r m PCB6 D a t e Yunber (ppn) Packaged D r u m C o n t e n t s <% Volume)

P -002 P -014 P -018 P -020 P -025 P -026 P-027 P -028 P-029 P - 0 3 0 P-031 P -032 P - 0 3 3 P -034 P -035 P -036 P - 0 3 7 P - 0 3 8 P - 0 3 9 P - 0 4 0 P - 0 4 1 P - 0 4 4 P -045 P - 0 4 6 P - 0 4 7 P - 0 4 8 P - 0 4 9 P - 0 5 0 P - 0 5 1 P -052 P -053 P -054 P -055 P - 056 P -057 P - 058 P - 0 5 9 P - 060 P - 0 6 1 P - 062 P - 063 P -064 P - 065 P - 0 6 6 P - 067 P - 068 P - 069 P -070 P - 0 7 1 P - 089 P - 090 P - 091 P - 092 P - 093 P - 094 P -095 P - 096 P - 0 9 7 P -098 P - O W P-100 P.101 P -102 P.103 P.104

SOIL (50%). GRAVEL (50%) GRkVEL (45%). SOIL C50%), GRAVEL (45%). SOIL (50%), GRAVEL (45%). SOIL (50%), GRAVEL (45%). SOlL (50%), GRAVEL (45%). SOIL (50%), GRAVEL (45%). SOlL (50%). GRAVEL (45%). SOlL (50%), GRAVEL (45%). SOlL (50x1, GRAVEL (45%). SOlL (50%). GRAVEL (45%). ao1L (50%). GRAVEL (45%). SOIL (50%), GRAVEL (45%). SOIL (50%), PRAVEL (45%). SOIL (50%). GRAVEL (45%). SOlL ( %), Y GRAVEL (18%). SOIL ( 0%). GRAVEL (18%). SOIL (70%). GRAVEL (?8%), SOlL (70%). GRAVEL (18%). SOIL (70%). GRAVEL (18%). SOlL (70%). S R A V ~ L (18%). SOlL (70%). GRAVEL (10%). SOlL (90%) GRAVEL (10%). SOIL (90%) GRAVEL (50%). SOlL (90%) PRAVEL (10%). SOlL (90%) GRAVEL (10%). SOIL (90%) GRAVEL {lox), SOIL cvox) GRAVEL (10%). SOIL (90%) GRAVEL (10%). SOlL (90%) GRAVEL ( lo%) , SOIL (80%). GRAVEL (10%). SOlL (80%). GRAVEL (10%). SOlL (80%). GRAVEL I IO%>, SOlL (80%). GRAVEL ( l o % > , SOIL (80%). GRAVEL ( l o % > , SOIL (80%). GRAVEL I IOX) . SOIL (80%). GRAVEL ( l o % ) , SOlL (80%). SOIL ,(95%), RAGS (5%) SOlL (95%). PLASTIC (5%) SOlL (95%). PLASTIC (5%) SOIL (95%). PLASTIC (5%) SOlL (95%). PLASTIC (5%) SOlL (95%). PLASTlC (5%) SOIL (95%). PLASTIC (5%) SOlL (95%). PLASTlC (5%) SOlL (95%). PLASTIC (5%)

SOlL (90%). CONCRETE

PLASTIC P L A S ~ IC PLASTIC PLASTIC PLASTIC PLASTIC PLASTIC PLASI IC PLASI IC PLASTIC PLASI tC PLASTIC PLASI IC PLASTIC PLASTIC PLAST1C PLIST I C PLASTIC PLASTIC PLASTIC

PLASTIC PLAST 1 C PLAST 1 C PLASTl C PLASTIC PLAST 1 C PLASTIC PLASTIC

SOlL (90%): CONCRETE (10%) SOIL IVOX); CONCRETE i i o x ) SOlL (90%). CONCRETE (10%) SOlL (90%). CONCRETE (10%) SOlL (POX), CONCRETE (10%) SOIL (98%). PLASTIC (2%) SOIL (98%). PLASTIC (2%) SOlL <Pa%), PLASTIC (2%) SOlL (98%). PLASTIC ( 2 X l SOIL &.xi; PLASTIC i z x ) SOIL (Pax), PLASTIC (2%) SOIL (98%). PtASTIC (2%) SOIL (90%). RAGS (5%). P l a s t i c (5%) SOIL (90%). RAGS (5%). P l a s t i c (5%)

Page 30: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

O r m PCBs o a t e N m b e r (PPR) P a c k a g e d D r u m C o n t e n t s (% v o l u m e )

UYKYOUY UYKYOUY UYKYOUY UYKYOUY UUKYOUY UYKYOUY UYKYOUY UYKYOUY UYKYOUY UYKYOUN UYKYOUY UYKYOUN UYKNOUY UYKNOUY UYKNOUN UYKNOUN

SOIL (POX), RAGS (2%). PROTECTIVE CLOTHING (8%) SOIL (100%) s o t . (100%) SOIL (POX), RAGS (ZX), PROTECTIVE CLOTHING (8%) S o l . (90%). RAGS (2%). PROTECTIVE CLOTHING (8%) SOIL POX^: RAGS (2%;: PROTECTIVE CLOTHIWG (8x1

i p s % ) ; RAGS (5%) SOIL t 1 O M ) SOIL t 9 8 X 1 , PLASTIC (2%) SOIL t 1 O M ) SOtL (100%) SOIL t 1 0 0 X I SOIL (95%); PROTECTIVE CLOTH I Y G (5%) SOIL t 1 0 O X ) SOIL t 1 0 0 X ) W I L (100%) SOIC (100%) SOtL 1100%) SOIL t10ML) SOIL l l O M l EoiL ilooxi SOIL t10M) SOIL ( E X ) , PROTECTIVE CLOTHING ( 5 % ) SOIL (100%) SOIL (100%) SOIL ( loox) SOIL i ioox i SOIL ( l o rn ) SOIL (98%). PLASTIC (2%) SOIL (POX), RAGS (2%). PROTECTIVE CLOTHIYG ( 8 % ) PLASTIC ( 4 0 % ) . COYCRETE (60%) PLASTIC (40%). COYCRETE (60%) GRAVEL (18%). S O I L (70%). PLASTIC CZX), M O D (10%) COYCRETE (POX), PROTECTIVE CLOTHING (10%) COYCRETE 150%). YOOD (30%). PROTECTIVE CLOTHING 120%)

. . -~ . , - . ... COYCRETE (80%) . YOOD ((OX), PROTECTIVE CLOTHIhC (10%) CONCRETE (BOX). UOOD (10%). PLASTIC <IO%) CONCRETE (BOX), WOOD (10%). PROTECTIVE CLOTHlhC (10%)

COYCRETE (TSX); ASPHALT (15X>. SOIC ( 7 0 % ) COYCRETE 180%): SOIL I Z O X l p ~ o r ~ c r i v ~ ~ c ~ o i n ~ ~ ~ (i5z); SOIL (85%) COYCRETE (80%). SOIL CZOX) P . I l l P 1 0 5 Y \ P I I S T I C < 5 Y I - - . - . . - . . , , . - . . - . - - . - . - , SOIL (POX), PROTECTIVE CLOTHING (8%). MISC (2%) VACUUM DEBRIS (80%). PROTECTIVE CLOTHING (20%) PROTECTIVE CLOTHI Y G ~ (30%). PLASTIC (90%)

. . . . . . . . . .. .- -.-. . - ~ ~ ~

. ~ . ~. UYKNOJN 0 4 / 2 6 / 9 1 u&I (50%), PLASTIC ( 5 0 % ) UMKNOJN 0 4 / 2 6 / 9 1 MOOD (50%). PLASTIC (50%) UYKNOJN 0 4 / 2 6 / 9 1 UOOD (50%). PLASTIC (50%) UYI(N0JN 0 4 / 2 6 / 9 1 UOOO (50%). PLASTIC (50%) UYKNOUN 0 4 / 2 6 / 9 1 UDOD (50%): PLASTIC (50%) UYKNOUN 0 4 / 2 6 / 9 1 UOOD (50%); PLASTIC (50%) UYKNOUN 0 4 / 2 6 / 9 1 U W O (50%), PLASTIC (50%)

4 6 1 0 4 / 2 9 / 9 1 GLASS (ZOX), SOIL (80%) 4 6 1 0 4 / 2 9 / 9 1 GLASS CZOX), SOIL (80%)

i n k s u e r e r e p a c k a g e d i n 2 0 8 - L ( 5 5 - g a l ) drum on 03/08/91. c o n t a i n m a t e r i a l s u s e d d u r i n g d e m o b i l i z a t i o n a n d c l e a n u p . c o n t a i n s a m p l e s e x t r a c t e d f r a m o t h e r d r u m s f o r a n a l y s i s o f drum c o n t e n t s .

Page 31: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

The remaining soil excavated from the lime pit that had thorium

concentrations of less than 15 pCi/g and PCB levels of less than

50 ppm was used as backfill in other non-PCB-contaminated areas

where more than 15 cm (6 in.) of soil had been excavated; these

areas were subsequently covered with 15 cm (6 in.) of

uncontaminated topsoil. Soil with combined radionuclide

concentrations at less than 5 pCi/g and PCBs at less than 1 ppm was

mixed with clean topsoil fill and placed back into the lime pit.

Exterior Araa 3

Area 3 contained two areas with radioactive contamination: one

west of Building 27 and one beneath ~uildi'ng 27 (Figure 3-7).

The area west of Building 27 consisted of concrete, soil, and

asphalt. Radioactive contamination was limited to an area of

approximately 1 by 1 m (3 by 3 ft) and a depth of 0.3 m (1 ft).

Thorium-232 concentrations in smples collected from boreholes in

this area before remedial action ranged from 17 to 53 pCi/g. The

area was remediated by using a jackhammer and shovel to remove

contaminated asphalt and soil [approximately 0.5 m3 (18 ft3)]; this

material was placed in LSA containers.

In 1989, remedial action was conducted beneath Building 27;

however, additional contamination was discovered during later

surveys. Thorium-232 was found at concentrations-of up to

21 pCi/g. Remedial action was performed by using small hand-held

shovels and scooping the contaminated soil [approximately 0.06 m3

(2 ft3)] into large plastic bags that were placed in LSA

containers.

Enterior mea 4

Area 4 is an asphalt parking lot east of Building 27

(Figure 3-a), with contamination only on the surface of the

asphalt. The contaminated area [approximately 46 m2 (500 ft2)] was

remediated by scabbling the asphalt surface and removing the

debris.

Page 32: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

Figure 3-7 Remediated Areas at Exterior Area 3

N 50 -

F E 0 Z

N 40 -

N 30 -

N 20 -

N 10 -

N 00 -

W 3 K I-

Bulldlng 27

I I ::

I S

I e D

I :: 2 I

> 3 3 3 >

@ Excavated area

0 PIC measurement

Grtd Is !n f e e t .

Page 33: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

Figure 3-8 Remediated Areas at Exterior Area 4 (Parking Lot)

= c NO6 - E z w 3 a C

NO5 -

NO4 -

NO3 -

NO2 - + P I C MEASUREMENT

REMEOIATED AREA NO1 -

N O 0 - , 0

DRAINAGE TRENCH

/ L

ASPHALT

1

/BUILDING 27 WALL

I I I

0 0 N P? v 0 0

ur a W W

0 0 W

0 W W W w

Page 34: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

Exterior Area 5

Area 5 is an open asphalt parking lot south of Building 5

(Figure 3-9). Direct contact beta-gamma measurements and a

subsurface soil sample were taken to determine whether the asphalt

surface area and/or soil exceeded remedial action guidelines. The

beta-gamma measurements ranged from 493 to 1,384 dpm/100 cm2 after

the background level was subtracted. The asphalt containing

contamination exceeding the remedial aation guidelines [an area of

approximately 93 m2 (1,000 ft2)] was remediated by scabbling and

jackhammering. Based on direct beta-gamma measurements,

approximately 0.03 m3 (1 ft3) of contaminated soil was also removed

from the area under the contaminated asphait.

3.1.2 Buildings

The first step in undertaking remedial action in the buildings

was to perform radiological surveys to confirm and delineate the

exact boundaries of contamination. A strategy and work plan were

developed and, as remediation work progressed, additional

radiological surveys were continuously performed to determine which

areas and equipment met cleanup guidelines and which ones required

additional cleanup.

Contaminated areas and items within 15 buildings at ARC were

remediated during the Phase I1 remedial action. Figures 3-10

through 3-26 identify these areas and items, show their locations,

and indicate the types of remedial action conducted.

The contaminated materials and equipment generated during the

building decontamination work were packaged in LSA boxes having a

total volume of 127 m3 (4,500 ft3) and subsequently shipped to

Hanford for disposal.

A hazard- assessment was conducted for seven areas and items in

Buildings 23 and 30 (BNI 1991). Four were in Building 23:

(1) contaminated pipes and sumps in the floor beneath the southwest

stairway to the basement, (2) the main collection drain in the

basement, (3) trenches 1, 2, and 18 in Laboratories 1 and 2, and

(4) the drain in the transformer room. The remaining three items

Page 35: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

" ~ a r g e nachne used In netclllurglcal research, It was not replaced.

b ~ h e crusher was moved.

8 Renedlated area

0 PIC neasurenen-t loco-klon

0 6 12 - scats h f e e t

- * I4QUMOW

Figure 3-1 1 o Remediated Areas in Building 3 00

8

Page 36: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

'~h. h.nter/blower/.xhoust. fan urut w&r not r-plnwd at th r*qu*rt oP th* Wpartnmt o f In+erlor.

I I B-1 Figure 3-12 a

8 Remediated Areas in Building 4 co m

Page 37: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

O898

F i r s t f loor I

Carpenter shop

Machrne layout

-4

Motor Electrical shop Lumber storage

0 PI[: n-mmt locatron

* mtd v..

0 u &dern*..t Second story and r o o f

Bm-uamn

Figure 3-1 3 Remediated Areas in Building 5

ROOM

Hebl stornge

P-

kdme

-s

"3 stora*

m e *.P

Mach& shop

w-0 shDp

ITEM NO.

0

@

@

0

0

@

0

ITEM/AREA

nmr

~lectrlrnl condtm

Cast errn p ~ p s rn

Honored

Sunp cover and mr+ [edw

b o r cracks

flmr

REMEDIAL ACTION CUNIWCTED

ScaMed

Removed

R e " w d

Va-

Scabbled

ScabNed

scaued

Page 38: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

. . i I.: . '% ~. .~ .-.

h b 10 @ bzt.Wi, Rrno\rdb -tb-,

Lab 10 @ T n a - (4) A& w - b b 10 O W.gn "aft.?* Raft- W " a d

L W a* 0 T r u n M v - m -w

Loadlng dock East end -

Open storage

Lunch room

Storage rwn

9 R-W-

PIC n-mwnt 1-tCn

-fff.H C m b * t . d truss

access h n k h

'Ln --I - s d l - 3 - d mod w e art out

Figure 3- 1 4 Remediated Areas in Building 17

Page 39: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

I 1 :: .. : . .;:- . . -. .~ . ,

. . . Figure 3-1 5 :. Remediated Areas in Building 23

I ~ 33

Page 40: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department
Page 41: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

I I I- LL 0 z W 3 w ?-

Laboratory 106

-ted ,. 0 9 I0 u

0 Scale h Fwet PIC ne-t IDE.DO.

%wLA!w3\rl

Figure 3-1 7 Remediated Areas in Building 24

Page 42: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

0 PIC meosurenent locntton

I r--t

Storage

I -

Page 43: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

// Renedlated area

PIC measurement locatlon

Scale In f e e t

B I P W ( H l * v l

Figure 3-1 9 Remediated Areas in Building 26

RODM

103

103 7

ITEM NO.

@

@

@

ITEM/AREA

Ioor (concrete 8, :Inoleurn 2 areas)

Cablnet, slnk

Abandoned furn- ace p l ts (2)

REMEDIAL ACTION CONDUCTED

Removed Imoteun, scabbled concrete

Removed

Scabbled and Jockhamnered

Page 44: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

ITEM REMEDIAL ACTIUN ROOM NO. ITEM/AREA CONDUCTED

3 @ Floor, watls Scabbled

Cablnet, sink, @ prpe dratn Removed

Floor beneath @ cablnet Scabbled

0 16 32 I I I

Scale In f e e t

ITEM REMEDIAL ACTIUN RDOM NO. ITEM/AREA CONDUCTED

Maln Removed lrnoleunj hall f loor scabbled

concrete

East @ Header plate Used needle gun at t lc

East Trusses and Vacuuned, attlc braces planed

ewu\Nyv1

Figure 3-20 Remediated Areas in Building 28

Page 45: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

Figure 3-21 Remediated Areas in Building 28 Basement

Page 46: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

F i r s t f I o o r

ITEM ITEWAREA REMEDIAL ACTION I CONDUCTED I Scabbled drain I LO6 1 @ / Floor drain I Removed some I wood I

109

111

Rened[ated a r e a

0 PIC measurement location

111

Second f l o o r

@

@

ITEM/AREA REMEDIAL ACTION

CONDUCTED

Removed f R t e r s

Alr (HEPA) unlt

@ Scale In f e e t

Draln

Dralns (3)

Figure 3-22 Remediated Areas in Suifding 29

Used needle gun

Used needIe gun

floor-wall Interface Scabbled

Page 47: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department
Page 48: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

. 10

Figure 3-24 B Remediated Areas in Building 31 2'

8

Page 49: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

I t- z n Z

W 3 rn c.

0 P a -*n

0 3 6 - Scale m f e e t

Figure 3-25 Remediated Areas in Building 33

ROM m m

1 @

>

CTwIY(U

F t m

A n h r bolts (4)

nDw, f-1- htdm

R W m K AtllW cmmuxm

I t * n o V d u*s scablred ancrttr

ReaM Mbb1.d srar-xhu -

R m m n d tncs scabbled -te

Page 50: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

ITEM NO. CONWCTED

Base metals smelter

Base netols Pedestnl smelter tube Scabbled

Figure 3-26 Remediated Areas in Building 34

Page 51: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

covered by the hazard assessment were pieces of equipment in

Building 30: (1) the hydraulic press, (2) the Baldwin press, and

(3) the Lindberg furnace. The hazard assessment provides a

detailed description of each of these contaminated areas or items

as well as an evaluation of the potential radiation dose to workers

from them. Calculations show that potential present or future

exposure to residual radioactive contamination in these areas would

be well below the DOE standard (100 mrem/yr) for protection of the

general public.

3.2 CONTAMIIPLLTIOII COMTltOL DURING =DIAL ACTION

During remedial action at ARC, several'methods of contamination

control were implemented to protect workers and the public from

exposure to radiation and to prevent the spread of radioactive

contamination. The radiation dose rates at ARC were very low, and

the primary personnel exposure pathway was from airborne

contamination that could be inhaled or ingested.

All personnel working in contaminated areas were required to

wear disposable coveralls, safety glasses, rubber boots, and

gloves. Additional protective clothing and equipment such as hoods

and respirators were used in areas where there was a possibility of

exposure to airborne contaminants.

Workers leaving radiologica$ly restricted work areas were

monitored at the control point with a hand-held detector by a

health physics technician to ensure that they were not contaminated

and to prevent the spread of contamination to a clean area. If

large portions of their disposable protective clothing were

contaminated, the clothing was disposed of. If only small areas of

the clothing were contaminated, those areas were cut out and

disposed of to minimize the amount of radioactive waste generated.

Because spread of contaminated dust particles was a significant

concern during all radiological work at ARC, measures were taken to

control airborne contamination.

I n interior building areas that were being scabbled,

jackhammered, and treated with a wire brush or needle gun, plastic

sheeting tents were used to prevent the spread of airborne

Page 52: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

particulates. High-efficiency particulate air (HEPA) filtering

units were used inside the tents to create a negative air pressure

environment and to filter the air. During remediation of exterior work areas, contamination

control techniques included the use of containment tents and light

wetting of soils to prevent the spread of dust. Where practical

and necessary (i.e., around the lime pit), large plastic

containment tents were built around the contaminated work areas,

and I-IBPA-filtered vacuum/blower units were used to keep dust from

migrating outside of the containment area. In smaller areas (i.e.,

Areas 1, 2, 4, and 5), plastic sheeting was placed around the

contaminated area, and a field technician held a portable

HEPA-filtered vacuum over the immediate wok& area.

During remedial action activities that had the potential for

generating airborne contamination, particulate air monitoring

devices were placed near the work area to provide continuous air

monitoring and to ensure that contamination was not being spread

outside the work area. All concentrations of airborne contaminants

were conpared to the DOE guideline of 1.0 x 10-l2 pCi/ml for thorium-232. General area measurements ranged from 5.05 x lo-" to 3.19 x 10-l2 #bCi/ml and averaged 5.73 x 10-l4 ~.rCi/ml. The single

sample that exceeded the guideline was not of concern as it was in

an enclosed attic of Building 17 and was for a duration of less

than 9 h. Measurements from lapel pins worn by the workers ranged

from 8.41 x lo-" to 3.78 x lo-" pCi/ml and averaged 8.58 x lo-'' pCi/ml. In all cases where lapel pin measurements

exceeded guidelines, workers were wearing protective equipment,

including masks.

Page 53: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

4.0 POST-REMEDIAL ACTIOH HEASUItEIIEWl!B

The PMC conducted preliminary radiological surveys as remedial

actions were being completed. After remediation, the independent

verification contractor conducted radiological surveys to verify

that remediated areas contained no radioactivity exceeding DOE

guidelines. These surveys included direct surface measurements and

soil smples taken and analyzed from outsicfe areas and beta-gamma

and alpha measurements taken inside the buildings with portable

Eberline AC-3 alpha scintillation and Geiger-Mueller detectors.

Exposure rates in exterior areas and inside buildings were

determined using a PIC.

Walkover gamma radiation scans were conducted to determine

whether all soil that was radioactively contaminated in excess of

W E remedial action guidelines had been removed from the remediated

areas. The technician held the radiation detector a few

centimeters above the ground surface and slowly moved it over the

ground while walking over the excavated areas. The advantage of

the walkover survey is that the detector quickly scans the areas as

the excavation proceeds, thereby providing immediate results. If

residual contamination appeared to exceed remedial action

guidelines, additional excavation was performed; the area was then

scanned again. After gamma scanning indicated successful

remediation, soil samples were collected for laboratory analysis to

verify that the cleanup objectives had been met.

Soil sampling was the primary method used in exterior areas to

confirm that all radioactive contamination exceeding DOE remedial

action guidelines had been removed. Soil samples were collected at

grid intervais of 2 rn (6 ft) in each excavated area and composited

to provide samples representative of a 100-m2 (1,080-ftZ) area.

Analytical results for soil samples taken after remediation

indicate that no radioactivity in excess of DOE remedial action

guidelines remains in the excavated areas. Table 4-1 provides the

results of the samples taken [from depths greater than 15 cm

Page 54: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

(6 in.). These results include background levels, which are

1.0 pCi/g for thorium-232, 0.8 pCi/g for radium-226, and 1.6 pCi/g

for total uranium (uranium-238 accounts for 48.9 percent by

activity of the total, or 0.8 pCi/g).

Radiation exposure rate measurements were taken using a PIC at

1 m (3 it) above the ground surface in remedlated areas;

measurement locations are shown in Figures 3-1, 3-2, and 3-6

through 3-25. The average background exposure rate for the Albany

area was 11.4 pR/h. General area PIC measurements and the

resulting exposure rates are presented in Table 4-2; all exposure

rates include background. If a member of the public were to

receive this exposure rate for one year, tfie total dose would not

exceed the DOE dose limit of 100 mrem/yr above background .

Remediated areas in the buildings at ARC were surveyed to

determine whether DOE residual surface contamination guidelines had

been met. Direct contact beta-gamma measurements were taken with a

Geiger-Mueller counter, and direct contact alpha measurements were

taken with an AC-3 alpha scintillation detector. Where physical

features permitted, an average of two to five measurements were

taken in 1- by 1-11 (3- by 3-ft) squares. At a minimum, removable

alpha and beta-gamma contamination was measured in locations that

exhibited direct measurements above guidelines for renovable

contamination. Removable alpha and beta/gamuaa activity was

determined by wiping a 100-cmz (16-in.2) area with an absorbent

medium (filter paper) and measuring the emissions from the paper.

All post-remedial action direct-contact radiation measurements in

the buildings were well below the DOE surface contamination

guidelines listed in Table 2-1 and site-specific adjusted

guidelines listed in Table 2-2. Direct-contact and removable

radiation measurements are presented in Table 4-3.

As part of the post-remedial action verification survey, PIC

measurements were taken in each remediated area to ensure that the

exposure rates are below the DOE residual contamination guideline

Page 55: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

Table 4 - 1

Analytical Results for Soil

Following Remedial Action

Depth Concentrationn (~Ci/s f 2 0 ) Area (ft) Uranium-238 Radium-226 Thorium-232

Area 1 0 - 0.5 0 - 1

Area 2 0 - 6 2 2

0 - 3 0 - 3

1 0

0 - 6

Area 3

Area 4 0 - 0.5

Area 5 0 - 0.5

'Resu.lts include background values of 0.8 pCi/g for radium-226, 1.0 pCi/g for thorium-232, and 1.6 pCi/g for total uranium (0.8 pCi/g for uranium-238).

Page 56: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

Tabla 4-2

PIC Measurements in Exterior weas Following Remedial Action

Measurement Exposure Rateb Locationn (PR/h)

Area 1

Area 2

N 2 4 E 5

N 7 0 E 5

N 5 5 3 7

E 07 N 2 4

E 11 N 2 4

E 1 9 N 2 4

Area 3

Center of excavation 10.6

Area 4 7.5

Area 5 8.8

%rid coordinates and measurement locations are shown in Figures 3-1, 3-2, and 3-7 through 3-9.

b~xposure rates include a background value of 11.4 pR/h.

Page 57: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

Table 4-3

P o s t - M i a 1 A c t i o n S u r f a o e A c t i v i t y MQ-tsm

Fixed Removable Loca t ion Average Minimum ~ a x i m u d Average Minimum ~ a r i m d

Lime Pit 71 Bu i ld ing 3 34 Bui ld ing 4 04 Bu i ld ing 5 43 Bu i ld ing 17 162 Bu i ld ing 23 43 Bu i ld ing 24 51 Bui ld ing 25 47 Bu i ld ing 26 40 Bu i ld ing 27 3 1 Bu i ld ing 28 47 Bu i ld ing 30 38 Bu i ld ing 31 108

L h P i t 916 Bui ld ing 3 784 Bu i ld ing 4 651 Bu i ld ing 5 630 Bu i ld ing 17 005 Bu i ld ing 23 629 Bu i ld ing 24 607 Bu i ld ing 25 626 Bu i ld ing 26 549 Bu i ld ing 27 765 Bu i ld ing 28 631 Bu i ld ing 30 548 Bu i ld ing 31 666

~ ~ ~- -~

'Associated gu ide l i nen are l o c a t e d i n T a b l e s 2-1 and 2-2.

*he g u i d e l i n e for maximum a l l owab le r e e i d u a l surface contamina t ion i s t h r e e times t h e average g u i d e l i n e .

qemovable a c t i v i t y was not measured i n Bui ld ing 27.

Page 58: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

of 20 bR/h above background inside structures. Table 4-4 provides

the gross PIC measurements for all interior remediated areas at ARC

(shown in Figures 3-10 through 3-26). All levels are well below

the W E guideline.

Page 59: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

Table 4-4

P I C Heaelrremants Fn Buildings Fol lmlng M i a 1 A c t i o n

Location within Expomure e ate^ Building NO.. Room/Area Room/Area l*/h)

306 119

101 101 102 102 103 103

103 105 105 106 206

Machine hop

10-A Open storage

2nd f loor

Att ic

Storage room

Crusher room

storage 2

N s ide Center

Center of SW corner Center of lm corner S side n side s side II side

Cente r of trench E trench W trench Osnter S wall

E end Osnter Metal storage rarm Plumbing .hop S of plumbing shop

NW corner S trench W end S trench E end N trench W end N trench E end W end N center S center % end NW corner SW corner W end Cente r W center

N side S aide Rbove N H wall Basement tunnel W aide Center NE

Page 60: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

Location within Exposure ~ a t d Building NO: Room/Area Room/Rrea ( ( I R / ~ )

Baeement

L a b 1

Att ic

tunnel SE side Elevator shaft MW corner N center BB cornmr 813 corner SE cornmr E center Thorium room

N center , 8 e e r 8 center Nw corner ME c o r m r by sink center South wall by panel SE corner MW corner SW corner

South end Canter SW corner MW corner W end canter

1st f loor taw corner smelter rwm SW corner

SE center NE center

103 Center of W side

Basement N4 E8 W10 EB N4 El6 N10 El6 N4 E21 N10 E24 H4 E32 W 1 0 E32 M4 E40 N10 E40 Center

Page 61: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

Table 4-4

(continued)

Paae 3 of 3

Location within Expomure e ate^ Building No.' Room/Area Room/Area ( P R / ~ )

15

Lab 3

S center M s ide Hallway Center

Center Center center Cente r

Fabrication sw c o r n ~ r NW corner SE corner rn corner

Machine shop N-xt to Baldwin press

3 Canter 2 center Att ic s and

A end

104 next t o remediated area

103 Next t o remediated area

Next t o pedestal

'PIC maaeureslent locations in buildings a re ahown i n Figures 3-10 through 3-26.

bExpoaure r a t e Lncludes a background value of 11.4 p / b .

Page 62: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

5.0 POST--DIAL ACTIOH 8 T A m 8

Analytical results from post-remedial action radiological

surveys indicate that the levels of residual radioactivity in areas

identified at ARC during the 1989 and 1990 characterizations are in

compliance with applicable DOE cleanup guidelines for radioactive

contamination. The IVC reviewed the post-remedial action survey

results, measurement procedures, and quality assurance data to

determine whether the meaeurements obtained verify that these areas

comply with the established DOE guidelines for the site.

The IVC conducted both type A and type B verification reviews

as specified in its verification plan. Type A verification

consisted of reviewing the post-remedial aktion survey results and

included collecting and analyzing additional samples as necessary.

The type B verification review consisted of a survey of the site

that included direct measurements, review of the post-remedial

action survey methods and results, sampling, and laboratory

analyses of soil samples. The findings and recommendations of the

verification study have been transmitted to WE-Headquarters and

the DOE Oak Ridge Field Office (ORAU 1991a, 1991b, 1991~).

If radiological conditions at the site are determined to be in

compliance with the DOE decontamination criteria and standards

developed to protect health, safety, and the environment, DOE will

certify the site as being appropriate for future use without

radiological restrictions.

Page 63: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

Argonne National Laboratory (ANL), 1983. Formerlv Utilized MEDlAEC

Remedial Action Prosram. Radiolwical Sunrev of the Albanv

petalluraical Research Center. United States Bureau of Mines.

plbanv. Oreaon, DOE/EV-0005/40 (June) . Bechtel National, Inc. ( B N I ) , 1985.

. . 'n er'n

t' C '0 0 Research C-, DOE/OR/20722-14, Oak Ridge, Tenn. (June).

BNI, 1989a. post-Remedial Action B ~ o r t for the Albanv Research

Cente~, DOE/OR/20722-207, Oak Ridge, ~enn.' (April).

BNI, 198933. Radioloaical Characterization Re~0rt for the Albany

Research Center. A W n V Oreaon, DOE/OR/20722-204, Oak Ridge, Tenn.

(April).

BNI, 1991. Addendum to the Hazard Asse~sment for Radioactive

Dntamination in and Beneath Certain Buildinas at t . . he Albany

Research Center (Draft), Oak Ridge, Tenn. (May).

Department of Energy (DOE), 1986. Formerlv Utilized Sites Remedial

Action Proaram. Summarv Protocol. Identification - Characterization - Desianation - Remedial Action - Certification, Washington, D.C. (January) . DOE, 1990. Order 5400.5, Radiation Protection of the Public and

Environment (February 5).

Spittler, T. M., 1984. "Field Measurement of Polychlorinated

Biphenyls in-Soil and Sediment Using a Portable Gas Chromatograph,"

Environmental Sam~lina for Hazardous Wastes, American Chemical

Society, pp. 37-42.

Page 64: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

Oak Ridge Associated Universities (ORAU), 1991a. Verification

Survev of Phase I1 Remedial Actions. Albanv Research Center.

Albanv. Oreuon. Interim Re~ort, Oak Ridge, Tenn., (January).

ORAU, 1991b. Verification Survev of Phase I1 Remedial Actions,

blbanv Research Center. Albanv. Oreaon. Interim Re~ort 11,

Oak Ridge, Tenn. , (March) . ORAU, 1991c. Verification Survev of Phase I1 Reme-

er . Albanv. Oreaon. -art I

Oak Ridge, Tan. , (June) .

Page 65: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

I Alpha-emitting - See Radiation.

Background Radiation - Background radiation refers to naturally occurring radiation emitted from either cosmic (e.g., from the sun)

or terrestrial (e.g., from the earth) sources. Exposure to this

type of radiation is unavoidable, an6 its Level varies greatly

depending on geographic location. For example, New Jersey

typically receives 100 milliroentgen per year (mR/yr), Colorado

receives about 300 mR/yr, and some areas in South America receive

up to 7,000 mR/yr. Naturally occurring terrestrial radionuclides

include uranium, radium, potassium, and thbrium (see Radionuclide) . The dose levels do not include the concentrations of naturally

occurring radon inside buildings.

Beta-gamma-enitting - See Radiation.

Cantimeter - A centimeter (cm) is a metric unit of measurement for length; 1 inch is equal to 2.54 cm; 1 foot is equal to

approximately 30 cm.

Contamination - contamination is used generally to mean a concentration of one or more ragioactive materials that exceeds

naturally occurring levels. Contamination may or may not exceed

the DOE cleanup guidelines.

Count6 per minute - A count per minute (cpm) is the unit of measurement registered by a radiation detection instrument when

radiation imparts its energy within the sensitive range of the

detector probe. The number of counts registered per minute can be

related to the number of disintegrations per minute occurring as a

radioactive material decays.

Page 66: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

Disintegrations per minute - Disintegrations per minute (dpm) is the measurement indicating the amount of radiation being released

from a substance per minute. See Picoaurie.

Dose - As used in this report, dose is actually dose equivalent and is used to relate absorbed dose (mad) to an effect on the body.

Dose is measured in mrem. For comparison, a dose of 500,000 mrem

to the whole body within a short time causes death in 50 percent of

the people who receive it; a dose of 5,000,000 mrem may be

delivered to a cancerous tumor during radiation treatment; normal

background radiation results in an annual dose of about 100 mrem:

DOE radiation protection standards limit the dose that may be

received by members of the general public'to 100 mrem/yr above

background levels.

Exposure rate - Exposure rate is the rate at which radiation imparts energy to the air. Exposure is typically measured in

microroentgens (pR), and exposure rate is typically expressed as

pR/h. The dose to the whole body can be approximated by

multiplying the exposure rate by the number of hours of exposure.

For example, if an individual were exposed to gamma raaliation at a

rate of 20 pR/h for 168 h/week (continuous exposure) for

52 weeks/yr, the whole-body dose would be 170 mrem.

Gamma Radiation - See Radiation.

Gram - A gram (g) is a metric unit of weight. There are 454 g in

1 pound and 28 g in 1 ounce.

Meter - A meter (m) is a metric unit of length; 1 m is equal to approximately 39 inches.

Microroentgen - A microroentgen (pR) is a unit used to measure

radiation exposure. For further information, see Exposure rate.

Page 67: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

H i l l i r e m - The millirem (mrem) is the unit used to measure radiation dose to man. The DOE dose limit is 100 mrem above

background radiation levels within any one-year period for members

of the general public. Naturally occurring radioactive substances

in the ground result in a yearly exposure of about 100 mrem to each

member of the population. To date, no difference can be detected

in the health of population groups exposed to 100 mrem/yr above

background and in the health of groups who are not exposed.

Picocurim - A picocurie (pci) is a unit of measure for radioactivity, just as an ounce is a unit to measure weight. A

measurement of 1 pCi equals 2.22 dpm.

Udiation - There are three primary types of radiation: alpha, beta, and gamma. Alpha radiation travels less than an inch in air

before it stops and cannot penetrate the outer layers of human

skin. Beta radiation can penetrate the outer layers of skin but

cannot reach the internal organs. Gamma radiation, the most

penetrating type, can usually reach the internal organs.

Radionuclide - Radioactive elements are also referred to as radionuclides. For example, uranium-235 is a radionuclide,

uranium-238 is another, thorium-232 is another, and so on.

Radium-226 - Radium-226 is a naturally occurring radioactive material that spontaneously emits alpha radiation.

Remedial action - Remedial action is a general term used to mean "cleanup of contamination that exceeds W E guidelines." It refers

to any action required so that a property can be certified as being

in compliance with guidelines and can therefore be released for

future use. In practice, this may require removing grass and soil,

cutting trees, and removing asphalt. Remedial action also includes

restoring remediated properties to their original conditions

insofar as possible.

Page 68: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

secular equilibrium - This is radioactive equilibrium in which the parent and all the daughters in the decay chain have the same

activity.

Thorium - Thorium is a naturally occurring element that is recovered from monazite for commercial purpose. Monazite contains

from 3 to 9 percent thorium oxide. The principal use of thorium to

date has been in the manufacture of gas lantern mantles because

thorium oxide burns with a brilliant white light. Thorium oxide is

also commonly found in high-quality glasses and camera lenses

because of its good optical characteristics.

Uranium - Uranium is a naturally occurring'radioactive element.

The principal use of uranium when refined is for the production of

fuel for nuclear reactors. Uranium in its natural form is not

suitable for use as a fuel source.

Page 69: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

Oak Ri* Corporate Center I51 Lafayem Drive P.O. Box 350 Oak Ridge, Tennessee 378314.550

Job No. 14501, FUSRAP Project DOE Contract No. DE-AC05-910R21949

Code: 733O/WBS: 102

Faaim ile: (6 15) 220-2 I#

HAY 2 9 1432 U.S. Department of Energy Oak Ridge Field Office P.O. Box 2001 Oak Ridge, TN 37831-8723

Attention: David G . Adler, Site Ma~~ager Former Sites Restoration Division

Subject: Publication of Post-Remedial Aotion Re~0rt for Phase I1 Work Conducted Durins 1990-1991 at the Albanv Research Center

Dear Mr. Adler:

Enclosed are three copies of the subject document, which is being published per authorization received from you on May 26. Transmittal of this document meets the DOE milestone for publication in May 1992. The document incorporates comments received from ORISE and FSRD on the prepublication draft.

We have attached a proposed distribution list for your review. Please return any changes or additions to the list by June 5 to allow for proper distribution of the document.

This document was prepared under my direction or supervision in accordance with a system designed to ensure that the information submitted was properly gathered and evaluated. TO the best of my knowledge and belief, information in the document is true, accurate, and complete.

If you have any questions regarding this matter, you may call me or Eric Newberry at 576-0399.

Very truly yours,

JqiwdL& G. L. Palau Project Manager - FUSRAP

ETN:ebs:LR - 0640

Enclosures: As stated

Conclirrence: E. T. Newberry @ '% E"?N E. B. Speaks .&f&

ACl lDM M U D [a YTS [ 1 MO DUE DATE dj(92

eeCnte1 N ~ t i ~ n ~ l , I ~ c . R ~ P O W I E TO CHROW m a

Page 70: Bechtel National, Inc. · POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK CONDUCTED DURING 1990-1991 AT THE ALBANY RESEARCH CEWR ALBANY, OREGON Prepared for United States Department

PROPOSED DISTRIBUTION LIST

POST-REMEDIAL ACTION REPORT FOR PHASE I1 WORK AT ARC

M r . Howard 0. Poppleton Albany Research Center Bureau o f Mines U . S . Department of the Inter ior P,.O. Box 70 Albany, OR 97321

M r . Harry Brooks, Librarian Albany Research Center Bureau of Mines U . S . Department o f the Inter ior P.O. Box 70 Albany, OR 97321

M r . James D . Berger Oak Ridge Associated Univers i t i e s P .O . Box 117 Oak Ridge, TN 37831-0177

M r . Jerry King Science Applications Internatinal Corp. P .O . Box 2501 Oak Ridge, TN 3 7 8 3 1