32
MEG Review Meeting June 2 MEG Review Meeting June 2 006 006 1 Peter-Raymond Kett Peter-Raymond Kett le le Beam Beam Line Line Status Status

Beam Line Status

Embed Size (px)

DESCRIPTION

Beam Line Status. Topics to be Addressed. 4. 4. COBRA End-Cap & Insertion + Drive System Status. 3. 3. COBRA/BTS Fringe Field Beam alignment influence. Degrader Commissioning Run Results. 1. 2. 2. COBRA He-atmosphere. 5. 5.  - Beam Test BTS. 6. - PowerPoint PPT Presentation

Citation preview

MEG Review Meeting June 2006MEG Review Meeting June 2006 11Peter-Raymond KettlePeter-Raymond Kettle

Beam Beam LineLine StatusStatus

Beam Beam LineLine StatusStatus

MEG Review Meeting June 2006MEG Review Meeting June 2006 22Peter-Raymond KettlePeter-Raymond Kettle

1.1. Degrader Degrader Commissioning RunCommissioning Run ResultsResults

1.1. Degrader Degrader Commissioning RunCommissioning Run ResultsResults

Topics to be AddressedTopics to be AddressedTopics to be AddressedTopics to be Addressed

2. COBRA 2. COBRA He-atmosphereHe-atmosphere

2. COBRA 2. COBRA He-atmosphereHe-atmosphere

3. COBRA/BTS 3. COBRA/BTS Fringe Field Fringe Field

Beam alignmentBeam alignment influenceinfluence

3. COBRA/BTS 3. COBRA/BTS Fringe Field Fringe Field

Beam alignmentBeam alignment influenceinfluence

5.5. - Beam Test BTS- Beam Test BTS5.5. - Beam Test BTS- Beam Test BTS

4. COBRA End-Cap4. COBRA End-Cap& Insertion + Drive& Insertion + Drive

System StatusSystem Status

4. COBRA End-Cap4. COBRA End-Cap& Insertion + Drive& Insertion + Drive

System StatusSystem Status1.1.

2.2.

44..

5.5.

3.3.

6.6... Target SystemTarget System

MEG Review Meeting June 2006MEG Review Meeting June 2006 33Peter-Raymond KettlePeter-Raymond Kettle

Degrader Run StatusDegrader Run Status

Total 5 weeks planned:Total 5 weeks planned: Many Problems encountered & several SurprisesMany Problems encountered & several Surprises However: some interesting facts learned !!!However: some interesting facts learned !!! Goal:Goal:

• first time measurement of Beam in COBRA with Degraderfirst time measurement of Beam in COBRA with Degrader System deployed at the centre of BTSSystem deployed at the centre of BTS

• understand misalignment problem seen Dec. 2005understand misalignment problem seen Dec. 2005

Complications:Complications:

First time 6cm Target E employed during MEG Commissioning timeFirst time 6cm Target E employed during MEG Commissioning time Lost more than 2 weeks of real beam timeLost more than 2 weeks of real beam time 11 days11 days due to accelerator due to accelerator 2 days2 days due to controller problems 3-D scanner due to controller problems 3-D scanner 1 day1 day control computer problems BTS control computer problems BTS 1 day1 day Separator vacuum interlock problems Separator vacuum interlock problems Measurements stopped Measurements stopped 4 last days4 last days lost due to interference COBRA stray lost due to interference COBRA stray field with other Users beam lines field with other Users beam lines µSR µSR M3 (LTF, GPS) M3 (LTF, GPS) E3 µCap-Expt.E3 µCap-Expt.

Run Programme SHORTENED Could Not Finish everything !!!Run Programme SHORTENED Could Not Finish everything !!!

Total 5 weeks planned:Total 5 weeks planned: Many Problems encountered & several SurprisesMany Problems encountered & several Surprises However: some interesting facts learned !!!However: some interesting facts learned !!! Goal:Goal:

• first time measurement of Beam in COBRA with Degraderfirst time measurement of Beam in COBRA with Degrader System deployed at the centre of BTSSystem deployed at the centre of BTS

• understand misalignment problem seen Dec. 2005understand misalignment problem seen Dec. 2005

Complications:Complications:

First time 6cm Target E employed during MEG Commissioning timeFirst time 6cm Target E employed during MEG Commissioning time Lost more than 2 weeks of real beam timeLost more than 2 weeks of real beam time 11 days11 days due to accelerator due to accelerator 2 days2 days due to controller problems 3-D scanner due to controller problems 3-D scanner 1 day1 day control computer problems BTS control computer problems BTS 1 day1 day Separator vacuum interlock problems Separator vacuum interlock problems Measurements stopped Measurements stopped 4 last days4 last days lost due to interference COBRA stray lost due to interference COBRA stray field with other Users beam lines field with other Users beam lines µSR µSR M3 (LTF, GPS) M3 (LTF, GPS) E3 µCap-Expt.E3 µCap-Expt.

Run Programme SHORTENED Could Not Finish everything !!!Run Programme SHORTENED Could Not Finish everything !!!

MEG Review Meeting June 2006MEG Review Meeting June 2006 44Peter-Raymond KettlePeter-Raymond Kettle

11st st Surprise: Missing RateSurprise: Missing Rate from 6 cm Target!from 6 cm Target!

PP

µµ

AHWAHW

AHUAHU

AHVAHV

RR4cm4cm=(0.55=(0.55±0.05)R±0.05)R6cm 6cm (1.8)(1.8) Measured Measured L. Simons et al L. Simons et al

(Pions!!!)(Pions!!!)from geometry alone would expect ~ from geometry alone would expect ~ 0.67 (1.5)0.67 (1.5)

RR4cm4cm=(0.55=(0.55±0.05)R±0.05)R6cm 6cm (1.8)(1.8) Measured Measured L. Simons et al L. Simons et al

(Pions!!!)(Pions!!!)from geometry alone would expect ~ from geometry alone would expect ~ 0.67 (1.5)0.67 (1.5)

Very PROVISIONAL !!!Very PROVISIONAL !!!Measured RMeasured R6cm6cm~ 1.24 R~ 1.24 R4cm4cm

With slits openWith slits open

However: - at 1.8mAHowever: - at 1.8mA

6cm Target6cm Target ~ 1.1 ~ 1.1·10·1099 e e++/s at/s at

4cm Target ~ 7.74cm Target ~ 7.7·10·1088 e e++/s at/s at factor 1.38factor 1.38** Naïve Model could explain** Naïve Model could explainmissing µmissing µ++ rate **: rate **:Surface µSurface µ++ Target Surface Target Surfacee+ e+ Target Volume Target Volume

Very PROVISIONAL !!!Very PROVISIONAL !!!Measured RMeasured R6cm6cm~ 1.24 R~ 1.24 R4cm4cm

With slits openWith slits open

However: - at 1.8mAHowever: - at 1.8mA

6cm Target6cm Target ~ 1.1 ~ 1.1·10·1099 e e++/s at/s at

4cm Target ~ 7.74cm Target ~ 7.7·10·1088 e e++/s at/s at factor 1.38factor 1.38** Naïve Model could explain** Naïve Model could explainmissing µmissing µ++ rate **: rate **:Surface µSurface µ++ Target Surface Target Surfacee+ e+ Target Volume Target Volume

Low energy Low energy -production X-sections -production X-sections rel. stop density factors rel. stop density factors back face/side face/front face = 3.3/2.5/1.7back face/side face/front face = 3.3/2.5/1.7Low energy Low energy -production X-sections -production X-sections rel. stop density factors rel. stop density factors back face/side face/front face = 3.3/2.5/1.7back face/side face/front face = 3.3/2.5/1.7

ProjectedProjectedIntensityIntensity distdist.. (surface)(surface)

Target ETarget E4/6 cm4/6 cm

If interpretation Correct If interpretation Correct 6 cm Target BAD for MEG 6 cm Target BAD for MEGDon’t gain Don’t gain µµ++ have ~ 1.4 more background e have ~ 1.4 more background e++

If interpretation Correct If interpretation Correct 6 cm Target BAD for MEG 6 cm Target BAD for MEGDon’t gain Don’t gain µµ++ have ~ 1.4 more background e have ~ 1.4 more background e++

EXPECTEDEXPECTED

MEG Review Meeting June 2006MEG Review Meeting June 2006 55Peter-Raymond KettlePeter-Raymond Kettle

22ndnd Surprise: Beam Misalignment Cause! Surprise: Beam Misalignment Cause!

Bfield measurements with triple-axis Tesla meter & Bfield measurements with triple-axis Tesla meter & BTS showed:BTS showed:

• BTS Bfield asymmetry at symmetric distances from axis of max. 10G BTS Bfield asymmetry at symmetric distances from axis of max. 10G (below axis)(below axis) Equivalent toEquivalent to extra Dipole fieldextra Dipole field• symmetry points above/below axis for equal Bfield ~ 30 cm displaced symmetry points above/below axis for equal Bfield ~ 30 cm displaced (therefore (therefore not error in measurement)not error in measurement)• Area Floor exhibits Area Floor exhibits RemanenceRemanence & & HysterisisHysterisis (remembers if BTS +ve/-ve (remembers if BTS +ve/-ve polarity)polarity) fields very reproducible, max. value on Area Floorfields very reproducible, max. value on Area Floor

Shows iron under the floor !!! which causes field lines to be diverted & Shows iron under the floor !!! which causes field lines to be diverted & alters the alters the symmetry of the solenoidal field at a point which is important for symmetry of the solenoidal field at a point which is important for focusingfocusing

Further field measurements after DC-test – with COBRA & BTS ON !!!Further field measurements after DC-test – with COBRA & BTS ON !!!

Enquired about Hall floor- plans should exist lay-out for 40t/mEnquired about Hall floor- plans should exist lay-out for 40t/m22

• 40 cm thick layer of steel reinforced concrete40 cm thick layer of steel reinforced concrete• steel layer ~ 30 cm thick starts about 10 cm downsteel layer ~ 30 cm thick starts about 10 cm down• high-quality steel but NOT STAINLESS !!!high-quality steel but NOT STAINLESS !!!

Enquired about Hall floor- plans should exist lay-out for 40t/mEnquired about Hall floor- plans should exist lay-out for 40t/m22

• 40 cm thick layer of steel reinforced concrete40 cm thick layer of steel reinforced concrete• steel layer ~ 30 cm thick starts about 10 cm downsteel layer ~ 30 cm thick starts about 10 cm down• high-quality steel but NOT STAINLESS !!!high-quality steel but NOT STAINLESS !!!

MEG Review Meeting June 2006MEG Review Meeting June 2006 66Peter-Raymond KettlePeter-Raymond Kettle

33rdrd Surprise: Muons Prematurely Range-out! Surprise: Muons Prematurely Range-out!

100%100%

50%50%

R~ 1460 mm HeR~ 1460 mm He

TTMATMAT

Expected:Expected: 100% transmission to centre COBRA, 100% transmission to centre COBRA, 50% to ~ end COBRA50% to ~ end COBRAAfter degrader ~21 MeV/c entry to COBRAAfter degrader ~21 MeV/c entry to COBRA

Measured:Measured:Mean Range at COBRA z= -900 mm Mean Range at COBRA z= -900 mm R ~1460 mm He Equiv.R ~1460 mm He Equiv. 235 235 µm CHµm CH22

Extra Material Thickness Extra Material Thickness TTMATMAT~ ~ 900 mm He Equiv. or 145 µm CH900 mm He Equiv. or 145 µm CH22

OR OR 9 % Air Contamination 9 % Air Contamination Know that air back diffusion Know that air back diffusion via leaks problematic as well as via leaks problematic as well as suspect “laminar flow” Mixing!suspect “laminar flow” Mixing! test measurement after DC-Testtest measurement after DC-Test Measure Range CurveMeasure Range Curve post BTS to test Momentumpost BTS to test Momentum hypothesishypothesis

18MeV/c18MeV/c

18 MeV/c18 MeV/c in Hein He

MEG Review Meeting June 2006MEG Review Meeting June 2006 77Peter-Raymond KettlePeter-Raymond Kettle

Beam Test ConclusionsBeam Test Conclusions

• more than 2 weeks of real beam time lost mainly due to the acceleratormore than 2 weeks of real beam time lost mainly due to the accelerator• 6 cm target proved problematic since beam wasn’t as expected &6 cm target proved problematic since beam wasn’t as expected & took time to investigatetook time to investigate• possible explanation for lack of increase in possible explanation for lack of increase in µµ++ rate from 6 cm Target rate from 6 cm Target• if true 6 cm Target No good for MEG signal/noise(eif true 6 cm Target No good for MEG signal/noise(e++) bad) bad• magnetic field anomaly found (Iron in floor) causes BTS field asymmetry magnetic field anomaly found (Iron in floor) causes BTS field asymmetry & beam& beam misalignment (misalignment (further investigation needed)further investigation needed)• good He circulation crucial for MEG – good He circulation crucial for MEG – possible cause of our muons ranging-outpossible cause of our muons ranging-out range curve post degrader & BTS should answer thisrange curve post degrader & BTS should answer this

Need extra Beam Time (4 weeks) with 4 cm Target + DegraderNeed extra Beam Time (4 weeks) with 4 cm Target + Degrader

• Only possible after end July (4cm Target) –start 4cm Target unstable + lowOnly possible after end July (4cm Target) –start 4cm Target unstable + low Current MEGAPIECurrent MEGAPIE• Only possible after COBRA stray field influence on other beams solvedOnly possible after COBRA stray field influence on other beams solved• To Not Delay MEG - has to be when End-Caps mounted – however problemTo Not Delay MEG - has to be when End-Caps mounted – however problem no magnet measuring machine possible therefore NEW APD array Detector no magnet measuring machine possible therefore NEW APD array Detector NEEDED – (presented Tokyo Meeting)NEEDED – (presented Tokyo Meeting)

Need extra Beam Time (4 weeks) with 4 cm Target + DegraderNeed extra Beam Time (4 weeks) with 4 cm Target + Degrader

• Only possible after end July (4cm Target) –start 4cm Target unstable + lowOnly possible after end July (4cm Target) –start 4cm Target unstable + low Current MEGAPIECurrent MEGAPIE• Only possible after COBRA stray field influence on other beams solvedOnly possible after COBRA stray field influence on other beams solved• To Not Delay MEG - has to be when End-Caps mounted – however problemTo Not Delay MEG - has to be when End-Caps mounted – however problem no magnet measuring machine possible therefore NEW APD array Detector no magnet measuring machine possible therefore NEW APD array Detector NEEDED – (presented Tokyo Meeting)NEEDED – (presented Tokyo Meeting)

MEG Review Meeting June 2006MEG Review Meeting June 2006 88Peter-Raymond KettlePeter-Raymond Kettle

Question of Question of Muons Muons “ “Ranging-out”Ranging-out”

Question of Question of Muons Muons “ “Ranging-out”Ranging-out”

MEG Review Meeting June 2006MEG Review Meeting June 2006 99Peter-Raymond KettlePeter-Raymond Kettle

COBRA He-AtmosphereCOBRA He-AtmosphereMeasure Profiles Measure Profiles @ Centre COBRA@ Centre COBRAX X = 11.8 mm = 11.8 mm YY = 12.0 = 12.0XX00 4mm offset 4mm offsetYY0 0 on axison axisRate ~ 8Rate ~ 8·10·1077 µ µ++/s /s at 1.8mA, 6cm Targetat 1.8mA, 6cm Target ~ 64% of muons~ 64% of muons reach centre !!!reach centre !!!

Measure Profiles Measure Profiles @ Centre COBRA@ Centre COBRAX X = 11.8 mm = 11.8 mm YY = 12.0 = 12.0XX00 4mm offset 4mm offsetYY0 0 on axison axisRate ~ 8Rate ~ 8·10·1077 µ µ++/s /s at 1.8mA, 6cm Targetat 1.8mA, 6cm Target ~ 64% of muons~ 64% of muons reach centre !!!reach centre !!!WHY?WHY?WHY?WHY?

1.1. Too much material in beam?Too much material in beam?• Degrader too thick? Degrader too thick? • New beam window >190 micronsNew beam window >190 microns Mylar Mylar • Air contamination in He Air contamination in He !!!!!!

2.2. Momentum too low?Momentum too low?• 6cm Target (transverse offset) 6cm Target (transverse offset) ??????• AHW41 Bending magnet AHW41 Bending magnet measured momentum spectrummeasured momentum spectrum

1.1. Too much material in beam?Too much material in beam?• Degrader too thick? Degrader too thick? • New beam window >190 micronsNew beam window >190 microns Mylar Mylar • Air contamination in He Air contamination in He !!!!!!

2.2. Momentum too low?Momentum too low?• 6cm Target (transverse offset) 6cm Target (transverse offset) ??????• AHW41 Bending magnet AHW41 Bending magnet measured momentum spectrummeasured momentum spectrum

CheckedCheckedCheckedChecked

CheckedCheckedCheckedChecked

Muons Range-out prematurelyMuons Range-out prematurelyMuons Range-out prematurelyMuons Range-out prematurely

MEG Review Meeting June 2006MEG Review Meeting June 2006 1010Peter-Raymond KettlePeter-Raymond Kettle

Beam Materials & MomentumBeam Materials & Momentum

• Degrader: Degrader: – 33 measurements per foil made – 33 measurements per foil made • New Mylar Window:New Mylar Window: - - 16 measurements of 16 measurements of

sample of same foil made sample of same foil made • Beam Momentum: Beam Momentum: - - Integral & Differential Range CurveIntegral & Differential Range Curve

measured post BTS using 50measured post BTS using 50µm & 100 µm & 100 µmµm Mylar foilsMylar foils

Mylar foilsMylar foils+ Holder+ HolderMylar foilsMylar foils+ Holder+ Holder

APD+ HolderAPD+ HolderAPD+ HolderAPD+ Holder

MEG Review Meeting June 2006MEG Review Meeting June 2006 1111Peter-Raymond KettlePeter-Raymond Kettle

Momentum MeasurementMomentum Measurement

Low Low thresholdthreshold

High High thresholdthreshold

+ 45.5 mm Air+ 20 µm Al foil• Counts Counts µ+eµ+e

• no threshold dependenceno threshold dependence• Michel MS ~ same for allMichel MS ~ same for all measurementsmeasurements

• Counts Counts µ+eµ+e• no threshold dependenceno threshold dependence• Michel MS ~ same for allMichel MS ~ same for all measurementsmeasurements

• Counts Counts µ only (Landau!)µ only (Landau!)• possible threshold dependencepossible threshold dependence

• Counts Counts µ only (Landau!)µ only (Landau!)• possible threshold dependencepossible threshold dependence

TTµµ = (2230 = (2230 ± 60)keV± 60)keV

PPµµ = (21.8 = (21.8 ± 0.3)MeV/c± 0.3)MeV/c

3.8% higher than expected, 3.8% higher than expected,

Possible with 6cm Tg ! Possible with 6cm Tg !

Gives lateral shift – p changeGives lateral shift – p change

TTµµ = (2230 = (2230 ± 60)keV± 60)keV

PPµµ = (21.8 = (21.8 ± 0.3)MeV/c± 0.3)MeV/c

3.8% higher than expected, 3.8% higher than expected,

Possible with 6cm Tg ! Possible with 6cm Tg !

Gives lateral shift – p changeGives lateral shift – p change

MylarRLL= 355 µmRUL= 389 µm

MylarRLL= 355 µmRUL= 389 µm

BEAM MOMENTUM OK !!!

MEG Review Meeting June 2006MEG Review Meeting June 2006 1212Peter-Raymond KettlePeter-Raymond Kettle

COBRA He-atmosphereCOBRA He-atmosphere

TU-1530 He-Monitor (Japan)TU-1530 He-Monitor (Japan)

• Range 0-100% HeRange 0-100% He• accuracy accuracy ±±1 %1 %• Probe part magneticProbe part magnetic

TU-1530 He-Monitor (Japan)TU-1530 He-Monitor (Japan)

• Range 0-100% HeRange 0-100% He• accuracy accuracy ±±1 %1 %• Probe part magneticProbe part magnetic

2 Measurements used as cross-check2 Measurements used as cross-check

Sonic Gas Monitor SGM (home-made)Sonic Gas Monitor SGM (home-made)

• Calibrated Range 92-100% HeCalibrated Range 92-100% He• precision precision ±±0.3 %0.3 %• microphone + speaker magneticmicrophone + speaker magnetic

Sonic Gas Monitor SGM (home-made)Sonic Gas Monitor SGM (home-made)

• Calibrated Range 92-100% HeCalibrated Range 92-100% He• precision precision ±±0.3 %0.3 %• microphone + speaker magneticmicrophone + speaker magnetic

MEG Review Meeting June 2006MEG Review Meeting June 2006 1313Peter-Raymond KettlePeter-Raymond Kettle

He Monitor Cross CalibrationHe Monitor Cross Calibration

HeHeHeHe

AirAirAirAir

Gas Rack (mixer)Gas Rack (mixer)Gas Rack (mixer)Gas Rack (mixer)

True He-mixtureTrue He-mixture

TU-153 TU-153 3.5% 3.5%

SGM SGM 0.2% 0.2%

Measu

red

Conc

Measu

red

Concnn

TU-153 Monitor needs correctionTU-153 Monitor needs correction within 92-100% Range of within 92-100% Range of 3.5% 3.5%TU-153 Monitor needs correctionTU-153 Monitor needs correction within 92-100% Range of within 92-100% Range of 3.5% 3.5%

MEG Review Meeting June 2006MEG Review Meeting June 2006 1414Peter-Raymond KettlePeter-Raymond Kettle

COBRA He-MeasurementsCOBRA He-MeasurementsTU-153 sample He via inserted tubeSampling points:A: SGMA: SGMB: z = + 2085 B: z = + 2085 mmmmC: z = + 705 mmC: z = + 705 mmD: z = + 45 mmD: z = + 45 mmE: z = - 355 mmE: z = - 355 mm

SGMTU-153

AAAA

BBBB

CCCCDDDDEEEE

Pos Comm Run DC Pos Comm Run DC RunRun

B 97% 93%B 97% 93%

C 96% 92%C 96% 92%

D 90% 89%D 90% 89%

E 91% 89%E 91% 89%

Pos Comm Run DC Pos Comm Run DC RunRun

B 97% 93%B 97% 93%

C 96% 92%C 96% 92%

D 90% 89%D 90% 89%

E 91% 89%E 91% 89% He-gradient, worst US !!! He-gradient, worst US !!! • explains ranging-outexplains ranging-out of Muons of Muons• He gas distribution too simpleHe gas distribution too simple• Care with final gas system !!!Care with final gas system !!!

He-gradient, worst US !!! He-gradient, worst US !!! • explains ranging-outexplains ranging-out of Muons of Muons• He gas distribution too simpleHe gas distribution too simple• Care with final gas system !!!Care with final gas system !!!

P r o v i s

i o n a l

7% to11% Air

3% to9% Air

MEG Review Meeting June 2006MEG Review Meeting June 2006 1515Peter-Raymond KettlePeter-Raymond Kettle

Beam MisalignmentBeam Misalignment && BTS + COBRA InfluenceBTS + COBRA Influence

Beam MisalignmentBeam Misalignment && BTS + COBRA InfluenceBTS + COBRA Influence

MEG Review Meeting June 2006MEG Review Meeting June 2006 1616Peter-Raymond KettlePeter-Raymond Kettle

Beam Misalignment/Fringe Field ProblemBeam Misalignment/Fringe Field Problem

Initial field measurements during this run with BTS ONLY showed:

iron under the floor !!!iron under the floor !!! which causes field lines to be diverted & alters the which causes field lines to be diverted & alters the symmetry of the solenoidal field at a point which is important for focusingsymmetry of the solenoidal field at a point which is important for focusing Measurements extended to Final BTS settings + COBRA

Series of measurements done atSeries of measurements done at US & DS faces of BTS withUS & DS faces of BTS withBTS alone & BTS +COBRA:BTS alone & BTS +COBRA:

Asymmetry (beam pipe dia.)Asymmetry (beam pipe dia.)BTS alone:BTS alone:US ~ 6 G, C ~ 7G, DS ~ 5G US ~ 6 G, C ~ 7G, DS ~ 5G

BTS + COBRA:BTS + COBRA:US ~ 6G, C ~ 0.6G, DS ~ 29G US ~ 6G, C ~ 0.6G, DS ~ 29G

Series of measurements done atSeries of measurements done at US & DS faces of BTS withUS & DS faces of BTS withBTS alone & BTS +COBRA:BTS alone & BTS +COBRA:

Asymmetry (beam pipe dia.)Asymmetry (beam pipe dia.)BTS alone:BTS alone:US ~ 6 G, C ~ 7G, DS ~ 5G US ~ 6 G, C ~ 7G, DS ~ 5G

BTS + COBRA:BTS + COBRA:US ~ 6G, C ~ 0.6G, DS ~ 29G US ~ 6G, C ~ 0.6G, DS ~ 29G

MEG Review Meeting June 2006MEG Review Meeting June 2006 1717Peter-Raymond KettlePeter-Raymond Kettle

Radial BTS Symmetry (No COBRA)Radial BTS Symmetry (No COBRA)

US Radial Symmetry Centres

y = -0.0096x2 + 0.0879x - 0.0521

0.000

0.020

0.040

0.060

0.080

0.100

0.120

0.140

0.160

0.180

0 1 2 3 4 5 6 7 8 9

Measurement

Rad

ial O

ffset

[cm

]

US Radial Centres

Poly. (US RadialCentres)

DS Radial Symmetry Centres

y = -0.0141x2 + 0.0783x + 0.2861

0.000

0.050

0.100

0.150

0.200

0.250

0.300

0.350

0.400

0.450

0.500

0 1 2 3 4 5 6 7 8 9

MeasurementRa

dial

Offs

et [c

m]

DS Radial Centres

Poly. (DS RadialCentres)

BTS US Radial Btot Distribution

665.0

670.0

675.0

680.0

685.01

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

US Radial Data

BTS DS Radial Btot Distribution

660.0

670.0

680.0

690.0

700.0

710.0

720.01

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16DS Radial Data

USUS DSDS

TopTop

BergBerg

AareAare

BotBot

TopTop

BergBerg

AareAare

BotBot

BTS Measured radialBTS Measured radialSymmetry distributionsSymmetry distributionsUS/DS at beam pipe US/DS at beam pipe Diameter I= -200ADiameter I= -200A

v. Simple “c-of-g” v. Simple “c-of-g” interpretationinterpretation Magnetic axis centreMagnetic axis centre

US: r=1.6 mm, US: r=1.6 mm, =292.5=292.5°° Field Asymmetry ~ 11G Field Asymmetry ~ 11G DS: r= 4.5 mm, DS: r= 4.5 mm, =247.5°=247.5° FieldField Asymmetry ~ 33 G Asymmetry ~ 33 G

BTS Measured radialBTS Measured radialSymmetry distributionsSymmetry distributionsUS/DS at beam pipe US/DS at beam pipe Diameter I= -200ADiameter I= -200A

v. Simple “c-of-g” v. Simple “c-of-g” interpretationinterpretation Magnetic axis centreMagnetic axis centre

US: r=1.6 mm, US: r=1.6 mm, =292.5=292.5°° Field Asymmetry ~ 11G Field Asymmetry ~ 11G DS: r= 4.5 mm, DS: r= 4.5 mm, =247.5°=247.5° FieldField Asymmetry ~ 33 G Asymmetry ~ 33 G

MEG Review Meeting June 2006MEG Review Meeting June 2006 1818Peter-Raymond KettlePeter-Raymond Kettle

Radial COBRA Asymmetry BTS+COBRARadial COBRA Asymmetry BTS+COBRACOBRA US Radial Btot Distribution

3120.0

3140.0

3160.0

3180.0

3200.0

3220.01

2 34

56

7

8

9

10

11

12

1314

1516

171819

202122

2324

25

26

27

28

29

30

3132

3334

35 36

COBRA RadialAsymmetry

BERGAare

Top

Bott

COBRA Measured radial symmetry COBRA Measured radial symmetry distributiondistributionUS at ~ beam pipe diameterUS at ~ beam pipe diameter

IIBTSBTS= = -203A, -203A, IICOBRACOBRA=360/320A=360/320A

v. Simple “c-of-g” interpretationv. Simple “c-of-g” interpretation Magnetic axis centreMagnetic axis centre

US: r=1.7 mm, US: r=1.7 mm, =240=240°° asymmetry ~ 55G asymmetry ~ 55G Problem to be studied by PSI Magnet Problem to be studied by PSI Magnet Group !!!Group !!!

COBRA Measured radial symmetry COBRA Measured radial symmetry distributiondistributionUS at ~ beam pipe diameterUS at ~ beam pipe diameter

IIBTSBTS= = -203A, -203A, IICOBRACOBRA=360/320A=360/320A

v. Simple “c-of-g” interpretationv. Simple “c-of-g” interpretation Magnetic axis centreMagnetic axis centre

US: r=1.7 mm, US: r=1.7 mm, =240=240°° asymmetry ~ 55G asymmetry ~ 55G Problem to be studied by PSI Magnet Problem to be studied by PSI Magnet Group !!!Group !!!

COBRACOBRAcentrecentre

COBRACOBRAcentrecentre

Influence on Influence on µ-Beamµ-Beam

COBRA Beam Centroid COBRA Beam Centroid ExcursionExcursion

MEG Review Meeting June 2006MEG Review Meeting June 2006 1919Peter-Raymond KettlePeter-Raymond Kettle

COBRA End-Cap COBRA End-Cap ++ Insertion & Drive SystemInsertion & Drive System

COBRA End-Cap COBRA End-Cap ++ Insertion & Drive SystemInsertion & Drive System

MEG Review Meeting June 2006MEG Review Meeting June 2006 2020Peter-Raymond KettlePeter-Raymond Kettle

COBRA US End-Cap SystemCOBRA US End-Cap System

USUSUSUS DSDSDSDS

US End-Cap scheduleUS End-Cap schedule Bieri Engineering manufacture costs ~ 55 kCHfBieri Engineering manufacture costs ~ 55 kCHf

delivery to PSI – THIS WEEK (2 weeks late)delivery to PSI – THIS WEEK (2 weeks late)

MEG Review Meeting June 2006MEG Review Meeting June 2006 2121Peter-Raymond KettlePeter-Raymond Kettle

Insertion SystemInsertion System

Connects to acceleratorConnects to acceleratorBeam pipeBeam pipe

Gliding supportGliding supportringsrings

NBRNBR

RETRACTED into End-CapRETRACTED into End-Cap

ReplaceReplacewithwithwindowwindow

• Gas-tight to He-side CHGas-tight to He-side CH22/EVAL window/EVAL window• normally connected to motor-driven accelerator normally connected to motor-driven accelerator beam tubebeam tube• frictional hand-drive via electric drill/crank-handlefrictional hand-drive via electric drill/crank-handle

Detailed FEM study

Electric-drill or hand driveElectric-drill or hand drive

View from InsideCOBRA

MEG Review Meeting June 2006MEG Review Meeting June 2006 2222Peter-Raymond KettlePeter-Raymond Kettle

COBRA DS End-Cap + Insertion & Drive COBRA DS End-Cap + Insertion & Drive SystemsSystems

Complication encountered with DS End-Cap + Insertion & Drive System:Complication encountered with DS End-Cap + Insertion & Drive System:

Offer received from Bieri Engineering ~ 200kCHf !!!

• successful negotiations with PSI Management for extra money• MEG project raised to priority 1 again – hence PSI workshops can take-over assembly & testing of complete system … Bieri price now ~ 140 kCHf

Delivery schedule: End-August DS End-Cap (as planned but v. tight)Delivery schedule: End-August DS End-Cap (as planned but v. tight) Mid-September Insertion & Drive SystemMid-September Insertion & Drive System

MEG Review Meeting June 2006MEG Review Meeting June 2006 2323Peter-Raymond KettlePeter-Raymond Kettle

BTS BTS

-Beam Test-Beam Test

BTS BTS

-Beam Test-Beam Test

MEG Review Meeting June 2006MEG Review Meeting June 2006 2424Peter-Raymond KettlePeter-Raymond Kettle

BTS Pion Beam TestBTS Pion Beam Test11st st MEG MEG -beam Studies in 2004:-beam Studies in 2004:

• part of momentum spectrum studypart of momentum spectrum study 25-33 MeV/c25-33 MeV/c• dedicated runs at 56 MeV/c & 103 MeV/cdedicated runs at 56 MeV/c & 103 MeV/c• CEX run in CEX run in E5 at 112 MeV/c Oct. 2004E5 at 112 MeV/c Oct. 2004

ALL BEFORE BTS ARRIVED!!!ALL BEFORE BTS ARRIVED!!!

Problem:Problem: BTS cannot be excited to transmit BTS cannot be excited to transmit Momenta >> 70 MeV/c since Momenta >> 70 MeV/c since • maximum Imaximum IBTS BTS ~ 270 A~ 270 A• exceeds allowed force on COBRA coilsexceeds allowed force on COBRA coils

ResultsResults -- Integral Spot Rates in MHzIntegral Spot Rates in MHzfor 1,8mA Proton Current & 4cm Target Efor 1,8mA Proton Current & 4cm Target E

Measured UPSTREAM of BTS positionMeasured UPSTREAM of BTS position Normalized to Momentum Slit Settings:Normalized to Momentum Slit Settings: FS41L/R 250/280 FS43L/R 240/220FS41L/R 250/280 FS43L/R 240/220

ResultsResults -- Integral Spot Rates in MHzIntegral Spot Rates in MHzfor 1,8mA Proton Current & 4cm Target Efor 1,8mA Proton Current & 4cm Target E

Measured UPSTREAM of BTS positionMeasured UPSTREAM of BTS position Normalized to Momentum Slit Settings:Normalized to Momentum Slit Settings: FS41L/R 250/280 FS43L/R 240/220FS41L/R 250/280 FS43L/R 240/220

56 MeV/c 56 MeV/c RR = 7.6 = 7.6 ·10·1066 --/s/s slits open slits open

RR = 7.2 = 7.2 ·10·1055 --/s slits70/70/s slits70/7056 MeV/c 56 MeV/c RR = 7.6 = 7.6 ·10·1066 --/s/s slits open slits open

RR = 7.2 = 7.2 ·10·1055 --/s slits70/70/s slits70/70

Solution:Solution: - should be able to transmit - should be able to transmit56 Mev/c particles (2*28 MeV/c) with56 Mev/c particles (2*28 MeV/c) withGood optics Good optics

Solution:Solution: - should be able to transmit - should be able to transmit56 Mev/c particles (2*28 MeV/c) with56 Mev/c particles (2*28 MeV/c) withGood optics Good optics

Single NodeSingle NodeSNMSNM

Single NodeSingle NodeSNMSNM

Double NodeDouble NodeDNMDNM

Double NodeDouble NodeDNMDNM

56 MeV/c56 MeV/c56 MeV/c56 MeV/c

28 MeV/c28 MeV/c28 MeV/c28 MeV/c

MeasuredMeasuredUS BTSUS BTS

MEG Review Meeting June 2006MEG Review Meeting June 2006 2525Peter-Raymond KettlePeter-Raymond Kettle

BTS BTS -Beam Test cont.-Beam Test cont.BTS test done last week:BTS test done last week:

Problem encountered – Hamamatsu APD Problem encountered – Hamamatsu APD used for used for µµ++ (no scint. but utilize “Nuclear Counter Effect”) (no scint. but utilize “Nuclear Counter Effect”) • has no pulse-ht. resolution for has no pulse-ht. resolution for -- CANNOT DISTINGUISH e CANNOT DISTINGUISH e- - & & --

• measured at 56 MeV/C & 107 MeV/c with APD & Pill Counter (scintillator)measured at 56 MeV/C & 107 MeV/c with APD & Pill Counter (scintillator) see pions & electrons with pill-countersee pions & electrons with pill-counter BUT CANNOT USE WITH BTS BFIELDBUT CANNOT USE WITH BTS BFIELD

HOWEVER:HOWEVER: COULD TRANSMIT 56 MeV/c PARTICLES as expectedCOULD TRANSMIT 56 MeV/c PARTICLES as expected

BTS Excitation CurveBTS Excitation CurveFor 56 MeV/cFor 56 MeV/cparticlesparticles

Question:Question:

What are expected low-energyWhat are expected low-energy Pion Beam Rates at centre of COBRA?Pion Beam Rates at centre of COBRA?

Question:Question:

What are expected low-energyWhat are expected low-energy Pion Beam Rates at centre of COBRA?Pion Beam Rates at centre of COBRA?

MEG Review Meeting June 2006MEG Review Meeting June 2006 2626Peter-Raymond KettlePeter-Raymond Kettle

BTS BTS -Beam Test cont.-Beam Test cont.

CONCLUSION:CONCLUSION:

• APDs with scintillators needed for Expt.APDs with scintillators needed for Expt. Cross-System of 13 APDs must be built Cross-System of 13 APDs must be built before final Commissioning with 4cm Tgbefore final Commissioning with 4cm Tg• max. max. -- momentum for good opticsmomentum for good optics

~ 70 MeV/c !!!~ 70 MeV/c !!!

• expected rate (slits open) 1.6 MHz at COBRA centreexpected rate (slits open) 1.6 MHz at COBRA centre

CONCLUSION:CONCLUSION:

• APDs with scintillators needed for Expt.APDs with scintillators needed for Expt. Cross-System of 13 APDs must be built Cross-System of 13 APDs must be built before final Commissioning with 4cm Tgbefore final Commissioning with 4cm Tg• max. max. -- momentum for good opticsmomentum for good optics

~ 70 MeV/c !!!~ 70 MeV/c !!!

• expected rate (slits open) 1.6 MHz at COBRA centreexpected rate (slits open) 1.6 MHz at COBRA centre

Expected low-energy Expected low-energy Pion Beam Rates at centre COBRAPion Beam Rates at centre COBRAfor 1.8 mA Proton Beam 4 cm Tg.for 1.8 mA Proton Beam 4 cm Tg.Taking decay-rate into accountTaking decay-rate into account

Expected low-energy Expected low-energy Pion Beam Rates at centre COBRAPion Beam Rates at centre COBRAfor 1.8 mA Proton Beam 4 cm Tg.for 1.8 mA Proton Beam 4 cm Tg.Taking decay-rate into accountTaking decay-rate into account

ExpectedExpectedPion Beam RatesPion Beam RatesCentre COBRACentre COBRA

70 MeV/c 70 MeV/c ~ 1.6MHz ~ 1.6MHz

at 1.8mA Iat 1.8mA IPROTPROT

70 MeV/c 70 MeV/c ~ 1.6MHz ~ 1.6MHz

at 1.8mA Iat 1.8mA IPROTPROT

MEG Review Meeting June 2006MEG Review Meeting June 2006 2727Peter-Raymond KettlePeter-Raymond Kettle

Target SystemTarget System

UCI UCI

Target SystemTarget System

UCI UCI

MEG Review Meeting June 2006MEG Review Meeting June 2006 2828Peter-Raymond KettlePeter-Raymond Kettle

Target System Mechanical RequirementsTarget System Mechanical Requirements

Substantial Progress made with Target System since last Review !!!Substantial Progress made with Target System since last Review !!!

• Supported from DC Support StructureSupported from DC Support Structure• externally surveyed & introduced with DCsexternally surveyed & introduced with DCs• possibility to move target for End-Cap Insertion System introduction (C-W, LHpossibility to move target for End-Cap Insertion System introduction (C-W, LH22,…),…)

“ “ target parking”target parking”• Mechanically stable & reproducible positioningMechanically stable & reproducible positioning

DC Support DC Support StructureStructure

InsertionInsertionBellowsBellows

DC structureDC structure

““Target Parking”Target Parking”

New method of “Parking” New method of “Parking” using Translation rather than Rotationusing Translation rather than Rotation

Target movement

Target movement

MEG Review Meeting June 2006MEG Review Meeting June 2006 2929Peter-Raymond KettlePeter-Raymond Kettle

Target System CharacteristicsTarget System Characteristics

Present Target Characteristics:Present Target Characteristics:

• Ellipse (210 x 70)mm Polyester foil 175 Ellipse (210 x 70)mm Polyester foil 175 µmµm• freely suspended by support pins from afreely suspended by support pins from a thin Rohacell support frame at ~22thin Rohacell support frame at ~22° to axis° to axis (differential expansion)(differential expansion)• frame attached by Rohacell support stemsframe attached by Rohacell support stems mounted on v. thin movable rodsmounted on v. thin movable rods• Driven by pneumatic driveDriven by pneumatic drive

Present Target Characteristics:Present Target Characteristics:

• Ellipse (210 x 70)mm Polyester foil 175 Ellipse (210 x 70)mm Polyester foil 175 µmµm• freely suspended by support pins from afreely suspended by support pins from a thin Rohacell support frame at ~22thin Rohacell support frame at ~22° to axis° to axis (differential expansion)(differential expansion)• frame attached by Rohacell support stemsframe attached by Rohacell support stems mounted on v. thin movable rodsmounted on v. thin movable rods• Driven by pneumatic driveDriven by pneumatic drive

polyesterpolyesterpolyesterpolyester

RohacellRohacell

DC SupportDC SupportPneumaticPneumatic DriveDrive

MovementMovement

Current Status UCI:Current Status UCI:

• prototype system prototype system successfully testedsuccessfully tested

Final SystemFinal System

• All parts machinedAll parts machined• Assembly & testing about Assembly & testing about to startto start• target foil material & angletarget foil material & angle still under studystill under study

MEG Review Meeting June 2006MEG Review Meeting June 2006 3030Peter-Raymond KettlePeter-Raymond Kettle

Prototype Target & PerformancePrototype Target & Performance

Test Setup UCITest Setup UCI

Pins on which Pins on which film is hungfilm is hung

Screws for Screws for clamping clamping

frameframe

Rohacell FrameRohacell Frame

DC SupportDC Support TubeTube

Thin film (~175 micron) target – material to be determinedThin film (~175 micron) target – material to be determined““soft” polyethylene too difficult to maintain flatsoft” polyethylene too difficult to maintain flatVarious polyester, polystyrene, “hard” polyethylene materials possibleVarious polyester, polystyrene, “hard” polyethylene materials possible

Implementation Implementation Target flatness controlled by Rohacell frame – clamping two frames Target flatness controlled by Rohacell frame – clamping two frames

together allows control of flatnesstogether allows control of flatnessHanging film between frames Hanging film between frames allows for differential expansion allows for differential expansion without deformation of filmwithout deformation of filmDistance between frames controlled Distance between frames controlled by washers at screw locations by washers at screw locations Final frame cut precisely with high Final frame cut precisely with high speed CNC routerspeed CNC routerNylon screws/nuts used to reduce massNylon screws/nuts used to reduce mass

MEG Review Meeting June 2006MEG Review Meeting June 2006 3131Peter-Raymond KettlePeter-Raymond Kettle

Prototype Target & Performance cont.Prototype Target & Performance cont. Flatness measured by reflected laser off target surface and measuring Flatness measured by reflected laser off target surface and measuring

reflected angle as laser spot is scanned across target.reflected angle as laser spot is scanned across target. Z(x,y) = Z(0,0) + Z(x,y) = Z(0,0) + ∫ (dz/dx)dx + ∫(dz/dy)dy∫ (dz/dx)dx + ∫(dz/dy)dy

Target measured to be flat to less than +/-100 micronsTarget measured to be flat to less than +/-100 microns

x y anglethicknessmicron % mu stops

21 7.7 21.8 150 64.721 7.7 21.8 175 69.6221 6 21.8 175 68.7521 5 21.8 175 66.7220 5 21.8 175 66.0719 5 21.8 175 65.5619 4 21.8 175 60.5621 5 0 175 45.4521 5 5 175 52.5721 5 10 175 62.2321 5 15 175 67.4925 5 5 175 57.0425 5 10 175 67.9925 5 15 175 70.3425 4 15 175 64.2830 4 15 175 66.1335 4 15 175 66.76

Target Size Study

Measured 45° target Measured 45° target 88% stops 88% stopsSlanted target gives “leakage” due to MSSlanted target gives “leakage” due to MS

Relatively insensitive to vertical size down to Relatively insensitive to vertical size down to 5.7cm 5.7cm Relatively insensitive to length down to 19 cm Relatively insensitive to length down to 19 cm HOWEVERHOWEVER Thickness of 175 microns required Thickness of 175 microns requiredFinal Parameters + slope sense still under Final Parameters + slope sense still under studystudy

MEG Review Meeting June 2006MEG Review Meeting June 2006 3232Peter-Raymond KettlePeter-Raymond Kettle

ScheduleSchedule US End-Cap:US End-Cap:• Delivery US COBRA End-Cap: Delivery US COBRA End-Cap: end Juneend June• US End-Cap preparations mounting PSI workshops US End-Cap preparations mounting PSI workshops 6WD installation after US TC6WD installation after US TC• US End-Cap installation US End-Cap installation 5WD Beg. Sept.5WD Beg. Sept.

Target System:Target System:• Production Production End JulyEnd July• Target assembly + installation Target assembly + installation 2W2W

DS End-Cap + Insertion & Drive System:DS End-Cap + Insertion & Drive System:• Delivery DS COBRA End-Cap Delivery DS COBRA End-Cap End Aug. – Mid Sept.End Aug. – Mid Sept.• Delivery Insertion + Drive System Delivery Insertion + Drive System Mid Sept. Mid Sept. • DS End-Cap preparations mounting PSI workshops DS End-Cap preparations mounting PSI workshops 6WD installation after DS TC6WD installation after DS TC• Insertion & Drive SystemInsertion & Drive System mounting + testing PSI workshops mounting + testing PSI workshops 6WD6WD• DS End-Cap + Insertion & Drive System installation DS End-Cap + Insertion & Drive System installation 10WD End. Sept.10WD End. Sept.

Beam Commissioning (degrader + 4cm Tg.)Beam Commissioning (degrader + 4cm Tg.)• Beam Line setup + survey Beam Line setup + survey 5WD post US End-Cap Beg. Sept.5WD post US End-Cap Beg. Sept.• BTS cryo-connections + pump & cool-down BTS cryo-connections + pump & cool-down 8WD8WD• Beam Commissioning Run Beam Commissioning Run 4Weeks Beg. Oct.4Weeks Beg. Oct.• Pion Beam Tune CEX Pion Beam Tune CEX 7D (if not during Comm. Run) before LXe Calib. Mid. Dec.7D (if not during Comm. Run) before LXe Calib. Mid. Dec.