Beacon Hill Voids Update_compressed

Embed Size (px)

Citation preview

  • 8/6/2019 Beacon Hill Voids Update_compressed

    1/25

    Voids Investigation andRemedial Work

    Capital Committee

    May 12, 2011

  • 8/6/2019 Beacon Hill Voids Update_compressed

    2/25

    1. Background Information2. Voids Identification, Exploration and Filling

    3. Bulking of Soils

    4. Conclusions

    5. Actions Taken for University Link

    Presentation Outline

    2

  • 8/6/2019 Beacon Hill Voids Update_compressed

    3/25

    Background Information

    3

  • 8/6/2019 Beacon Hill Voids Update_compressed

    4/25

    Tunnel Work Earth pressure balance tunnel

    boring machine[1 TBM for both tunnels]

    Southbound tunnel drive:February 2006 to May 2007

    Northbound tunnel drive:July 2007 to March 2008

    Background Information

    4

  • 8/6/2019 Beacon Hill Voids Update_compressed

    5/25

  • 8/6/2019 Beacon Hill Voids Update_compressed

    6/25

  • 8/6/2019 Beacon Hill Voids Update_compressed

    7/257

    Beacon Hill Station

    Findings : Excess spoil removed => conveyor weight scale data Nine target areas located in zone ( ~300-feet long ) Identified potential voids volume of 3,296 cy based on

    weight

    Background Information

    7

  • 8/6/2019 Beacon Hill Voids Update_compressed

    8/258

    Excess Belt Scale Weight Gradation Scale

    Voids Identification, Exploration and Filling

  • 8/6/2019 Beacon Hill Voids Update_compressed

    9/25

    PHASE 1 [Void Identification & Filling]

    April & May 2009 Performed investigation utilizing

    Subsurface explorations andprobes along tunnel centerline

    Used targeted approach based onweight-scale data

    Microgravity measurements trialto delineate disturbed zones andvoids

    Drilled 38 probe holes

    Filled voids with CDF

    Voids Identification, Exploration and Filling

    9

  • 8/6/2019 Beacon Hill Voids Update_compressed

    10/2510

    Beacon Hill Station

    Voids discovered in each of the 9 zones Voids coincided with over-excavation identified by weigh-scale

    data Phase 1 found and filled 2,544 of 3,296 cy ( 78% fill factor )

    Voids Identification, Exploration and Filling

    10

  • 8/6/2019 Beacon Hill Voids Update_compressed

    11/25

    PHASE 2 [Compaction Grouting]

    June and July 2009 Developed a program to compact

    loose zones

    Pumped cement grout through patternof holes

    Grout pressures 300 to 600 psi tocompact loose zones

    Drilled 61 holes Placed another 293 cy of grout

    Voids Identification, Exploration and Filling

    11

  • 8/6/2019 Beacon Hill Voids Update_compressed

    12/2512

    Beacon Hill Station

    Phase 1 & 2 => found and filled 2,837 of 3,296 cy

    Fill Factor = 87% Six of nine areas filled within 10% of total theoretical volume

    (blue ovals ) Potential for approximately 430 cubic yards of subsurface

    ground loss distributed in three areas ( purple ovals )

    Voids Identification, Exploration and Filling

    12

  • 8/6/2019 Beacon Hill Voids Update_compressed

    13/2513

    Beacon Hill Station

    Phase 3

    Step 1 Step 3 Step 5 CompactionGrout

    Step 2 Step 4 Throughout

    Voids Identification, Exploration and Filling

    13

  • 8/6/2019 Beacon Hill Voids Update_compressed

    14/25

    PHASE 3 [Verification Explorations]

    July 2010 December 2010

    Delineate the extent/nature ofdisturbed zones

    Backfill any remaining loose zones

    Drilled 108 holes ( steps 1 thru 4 )

    Placed another 115 cy of grout

    Voids Identification, Exploration and Filling

    14

  • 8/6/2019 Beacon Hill Voids Update_compressed

    15/25

    Voids Identification, Exploration and Filling

    Total fill placed (Phases 1, 2 & 3) = 2,952 cy of 3,269 cy Fill factor = 90% No need for Step 5: Compaction grouting throughout

    15

  • 8/6/2019 Beacon Hill Voids Update_compressed

    16/25

    NB NB

    Total

    SB SB

    Total

    Phase

    Total

    Cum

    Total

    Cum

    %

    #holes

    VolPlaced

    #holes

    VolPlaced

    VolPlaced

    VolPlaced

    FillFactor

    EstimateLoss 1,939 1,330 3,296

    Ph 1 Fill 21 1,632 17 912 2,544 2,544 78%

    Ph 2 Fill 26 87 34 206 293 2,837 87%

    Ph 3 Fill 47 71 61 44 115 2,952 90%

    Bulking

    Total Fill 94 1,790 112 1,162 2,952

    % Fill 92.3% 87.4% 90.3%

    Bulking of Soils

    16

    Bulking

  • 8/6/2019 Beacon Hill Voids Update_compressed

    17/25

    3D Interpreted View of Voids (westerly area)

    NB SB

    Bulking of Soils

    17

  • 8/6/2019 Beacon Hill Voids Update_compressed

    18/25

    3D Interpreted View of Disturbed Zones and Voids

    NB SB

    Bulking of Soils

    18

  • 8/6/2019 Beacon Hill Voids Update_compressed

    19/25

    NB NB

    Total

    SB SB

    Total

    Phase

    Total

    Cum

    Total

    Cum

    %

    #holes

    VolPlaced

    #holes

    VolPlaced

    VolPlaced

    VolPlaced

    FillFactor

    Estimate

    Loss 1,957 1,339 3,296Ph 1 Fill 21 1,632 38 17 912 2,544 2,544 78%

    Ph 2 Fill 26 87 60 34 206 293 2,837 87%

    Ph 3 Fill 47 71 108 61 44 115 2,952 90%

    Bulking 167 177 344 3,269 100%

    Total Fill 94 1,957 206 112 1,339 3,296

    % Fill 100.0% 100.0% 100.0%

    Bulking of Soils

    19

  • 8/6/2019 Beacon Hill Voids Update_compressed

    20/25

    The voids were caused by over-excavation

    The over-excavation: failure to operate in closedmode with full excavation face support asrequired by the Contract

    The belt scales measured over-excavation (e.g.high excavated material weights)

    Conclusions

    20

  • 8/6/2019 Beacon Hill Voids Update_compressed

    21/25

    Reviewed data and identified other potential voids

    Developed phased plan with integrated team (CM,Engineers-of-Record, Contractor, Tunnel Experts)

    Executed and completed our phased plan

    Accomplished program objectives (filledvoids/compacted loose zones) within budget

    Actions Taken

    21

  • 8/6/2019 Beacon Hill Voids Update_compressed

    22/25

    22

    TBM Control System: Display 8 hours of face pressure sensor data

    Confirm TBM is consistently operating as required

    (e.g. above ambient pressure)

    Actions Taken for University Link

  • 8/6/2019 Beacon Hill Voids Update_compressed

    23/25

    TBM Data Logger: Obtain/plot data routinely

    Confirm operating parameters are being maintained

    TBM Belt Weigh-Scale Gather data after each ring advance

    Compare to theoretical weight calculation

    Take immediate remedial action, asnecessary

    TBM Conditioning Materials Sufficient/proper materials available

    Used according to soil profile

    Actions Taken for University Link

    23

  • 8/6/2019 Beacon Hill Voids Update_compressed

    24/25

    Construction management team is being trainedto read and interpret the measured data

    CM team will have a trained inspector in the

    tunnel heading at all times

    Real time data will be displayed on a computer inthe CM office

    Actions Taken for University Link

    24

  • 8/6/2019 Beacon Hill Voids Update_compressed

    25/25

    IF any critical parameters (e.g. face pressure, beltscale weights, etc.) are not as required/expected

    THEN Immediately investigate and havecontractor take corrective action

    Actions Taken for University Link