Upload
pradeepika04
View
219
Download
0
Embed Size (px)
Citation preview
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 1 of 1
ENCLOSURE – I
CURRENT POWER SCENARIO & POLICIES
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 2 of 2
ENCLOSURE - I : CURRENT POWER SCENARIO & POLICIES
Power generation is the harbinger of economic growth and industrial development of any country.
Although it is a life stream of country like India, it contributes to the GHG emissions as the fossil
fuels have major share in total power generation. This section covers the current power situation in
India and Uttar Pradesh (UP), development of renewable energy sources, central and state policies,
future energy projections, current power delivery system etc.
1.0 National Power Scenario
Indian power sector is facing challenges and despite significant growth in generation over
the years, it has been suffering from shortages and supply constraints. Energy and peak
load shortages were 7.8 % and 13 % respectively in the year 2000-01. The per capita
electricity consumption in India is about 400 kWh/year, which is significantly lower than
the world average of around 2,100 kWh/year. As GDP growth accelerates to an ambitious 8
to 10 %, the shortage of power will become more severe (source: Reference No. 27)
The power situation in India is characterised by demand in excess of supply, high
Transmission and Distribution (T&D) losses, low Plant Load Factor (PLF), peak demand
and energy shortages, poor financial health of the State Electricity Boards (SEBs) and
severe resource crunch. The power sector reforms in the country and consequent
privatisation of generation, T & D have been sluggish, due to complexities involved. The
Ministry of Power has been making continuous efforts for promoting reduction of T&D
loss and re-structuring of SEBs. The electricity regulatory commissions, recently formed as
a part of the reforms, have been still learning to exercise adequate control on power tariffs.
With reference to above power and energy scenario, Ministry of Power (MoP) and
Ministry of Non-conventional Energy Sources (MNES), Government of India, has been
promoting viable renewable energy technologies including wind, small hydro and biomass
power, energy conservation, demand side management etc. MNES has been promoting
various sources of renewable energy since 1990.
Wide spread need of power generation has created the need for a cheap and readily
available commercial fuel for generating electricity at low cost. Coal was the first to be
selected in India as a commercial fuel in early thermal power stations and is still king of the
power market.
Central Electricity Authority (CEA) has initially projected a shortfall of 1,50,000 MW in
15 years and therefore, a capacity addition target of 10,000 MW every year, the actual
capacity addition has been far short of targets. The CEA has recently revised the capacity
addition target to 1,00,000 MW from earlier target. This implies an annual addition of
8,500 MW as against earlier fixed of 10,000 MW. Capacity addition in the last five years
including financial year 2000 was average 3,000 MW per year. Out of the total capacity
added during last five years, 49% was added by the states and balance by central plants,
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 3 of 3
excluding only 4% contributed by private sector. This indicates that, the states have been
the largest contributors to incremental capacity.
The sustained economic development in India has created a critical need for additional
power generation capacity. To augment the existing installed capacity of about 101,154
MW (year 2000-01), the Government of India has encouraged private sector participation
in the power generation.
To assess the all India capacity requirements by the end of eleventh plan to meet the
demand projected by 15th Electric Power Survey (EPS) report, Central Electricity Authority
(CEA) carried out planning studies using updated version of Integrated System Plan
(ISPLAN) model, which optimises generation capacity additions in an integrated manner
with power transmission and fuel transportation. The studies are based on updated data
base, keeping in view the development in power sector in recent past, likely achievement
during 9th Plan, the perspective plans prepared by Central Power Units (CPUs) and also
latest status of Independent Power Producers (IPP) and state sector projects.
The CEA report “Power on Demand By 2012” has indicated that the level of satisfaction
would be 85% only with the identified installed capacity of about 2,10,000 MW by the end
of eleventh Plan (2011-12), leaving a gap of about 22,600 MW in demand. Additional
projects to the tune of 30, 000 MW capacity need to be identified to meet the full peaking
requirements. On the other hand, if the demand in terms of peak as well as energy is
reduced by 15%, then the present level of identified projects including projects covered in
CPUs perspective plan is found to be adequate. Hence, energy conservation activities and
power generation from renewable sources have an important role in management of
demand and energy requirement.
Out of total existing generation capacity, nearly 72% is contributed by thermal power. With
a need for sustainable economic growth, the Government of India, through the Ministry of
Non-Conventional Energy Sources (MNES), is encouraging and catalysing the growth of
renewable energy based power including biomass, wind, hydro, solar photo-voltaic etc. It
is expected that a judicious mix of centralised fossil fuel power plants and decentralised
renewable energy based power plants will lead to an environmentally friendly
augmentation of the power sector in India. In addition to this central government and all
the State Governments are encouraging the Energy conservation activities in all the sectors
like industrial, domestic, commercial, agricultural etc. Implementation of electrical energy
conservation projects / programmes at various sectors will also help in reduction of peak
demand along with the financial gains through reduction of energy consumption.
2.0 Power From Renewable Energy Sources
Renewable energy technologies based on the inexhaustible resources of sunlight, wind,
water and biomass are considered to offer sustainable energy alternatives to a world beset
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 4 of 4
by serious environmental problems and volatile fossil fuel politics. An increasing share of
global energy needs is expected to be met by renewable in the years ahead. (Source :
Reference No. 28)
India is abundantly endowed with renewable energy resources viz. solar energy,
wind energy, biomass and small hydro, widely distributed across the country, and
can be utilised through commercially viable technologies to generate power.
Increasing use of these sources will also be instrumental in simultaneously
achieving environmental objectives like reduction of GHG emission. Details of
renewable energy potential and achievement as on December 31, 2001 is presented
in Table-2.1.
Table – 2.1 : Renewable Energy Potential & Achievement
Sr.No. Source / Technologies Approximate Potential Achievement
1. Wind Energy 45,000 MW 1,267 MW
2. Small Hydro (up to 25 MW) 15,000 MW 1,341 MW
3. Biomass / Bagasse
Co-generation
19,500 MW 273 MW
4. Solar PV 20 MW / km2
47 MW
5. Urban & Industrial Waste 1,700 MW 15.15 MW
6. Biogass Plants 120 Millions 3.182 Millions
Source: Background Paper of International Conference and Business Meet on ‘Non Fossil Fuel
Generation’ organized jointly by CII, NHPC & NPC of India Ltd
From above table, around 3000 MW (3 % of total installed capacity) capacity of
Renewable Energy (RE) projects have been installed in the country. India is planning to
add about 12,000 MW power generating capacity from renewable by the end of 11 th plan
(2011-2012). Almost half of it is expected to come from wind, 3,500 MW from biomass
and 2,000 MW from small hydro.
As per CEA’s Fourth National Power Plan, anticipated capacity additions from Non-
Conventional energy sources is presented in following Table-2.2
Table – 2.2 : Capacity additions from non-conventional energy sources
Sr.No. Source of Energy Programme capacity in MW
9th
plan 10th
plan 11th
plan
1. Wind Power 3,000 6,000 9,000
2. Small Hydro 1,000 2,000 3,000
3. Biomass Cogeneration 1,000 2,000 3,000
4. Solar Thermal Power 300 600 900
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 5 of 5
Sr.No. Source of Energy Programme capacity in MW
9th
plan 10th
plan 11th
plan
5. Solar Photovoltaic 200 400 600
6. Bio energy / Biomass Power 1,000 2,000 3,000
TOTAL 6,500 13,000 19,500
Source: CEA report on fourth national power plan
Although, India is implementing one of the world’s largest programmes on renewable
energy, the present output from “renewable”, in the national energy scene, is less than
two per cent of the installed capacity, it has not matured into a major alternative. The
major barriers and bottlenecks for development of renewable energy includes following:
High captive investment and low commercial viability
Lack of adequate capital at affordable cost
Limited access to financial resources and high cost of finance
Lack of awareness (e.g. bagasse is available with farmers with no exposure of power
sector economics)
Lack of large scale production facilities
If the projects get the financial benefit under flexibility mechanisms of Kyoto Protocol then
above barriers can be overcome to some extent.
3.0 Potential Of Sugar Cogeneration In India1
Cogen power plants at sugar mills in India are getting stabilised / commercialised with
pressure / temperature configurations up to 87 kg/ cm 2 and 5100C. Internationally, in
countries like Mauritius, Re Union Island and USA, bagasse co-generation plants with high
pressure of more than 80 kg/cm2 and modern technology are established and exporting
power to grid. Maximum pressure configuration employed internationally, is 105 kg/cm 2 in
a sugar mill at Okilanda, USA. (Source: Reference No.25)
The potential for power generation from bagasse-based cogeneration at sugar industries
with implementation of high-pressure configurations above 60 kg/cm 2 is around 4,000
MW. Based on separate studies conducted by MNES / IREDA and Tata Energy Research
Institute (TERI) break up of potential for cogeneration from sugar mills of major sugar
producing states, is given in the following table:
1 Sources: 1) CII Investor Guide Book on cogeneration
2) Background Paper of International Conference and Business Meet on ‘Non Fossil Fuel Generation’
organized jointly by CII, NHPC & NPC of India Ltd
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 6 of 6
Table – 3.3 : Cogeneration Potential from Sugar Mills
State Potential in MW
Maharashtra 1,250
Uttar Pradesh 1,350
Tamil Nadu 300
Karnataka 200
Andhra Pradesh 300
Bihar 150
Gujarat 150
Punjab 125
Haryana 100
Madhya Pradesh 50
Others 25
Total 4,000
Source: All India Bagasse Co-generation Study of IREDA, taken from CII
investor guidebook for bagasse based cogeneration
Considering above potential for cogeneration in India, the major stakeholders like, sugar
industry and policy makers started the developmental efforts in the early eighties.
In spite of having huge potential, the actual achievements till date are very poor due to
major barriers related to initial capital, low cost financing, state and central regulatory
policies and other barriers related to technology, social factors, specialised experience etc.
In the above perspective BCML has taken commendable step togo ahead with installation
of two bagasse based co-generation units with export of power to the state grid; one at
Haidergarh and another one at Balrampur.
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 7 of 7
4.0 UP’s Current Delivery System2
Indian power grid system is divided into five regions namely Northern, North Eastern,
Eastern, and Southern and Western Regions. The state of Uttar Pradesh is situated in the
Northern part of India and forms a major constituent of northern region. These regions
have independent load dispatch centres that manage the flow of power in their jurisdiction.
At present, the inter-regional flows of power are quite low. Hence, each region may be
considered as an island due to which the power generated in each region is distributed in
their jurisdiction only.
The Northern Region consists of Delhi, Himachal Pradesh, Punjab, Uttar Pradesh, Haryana,
Jammu & Kashmir, Rajasthan and newly formed Uttaranchal State. Each state will have
their own power generation plants (State Government owned) managed by respective State
Electricity Boards / Corporations. In Uttar Pradesh, power transmission and distribution is
managed by Uttar Pradesh Power Corporation Ltd.(UPPCL), Lucknow. State governments
thermal power generation plants are managed by the state authority Uttar Pradesh Rajya
Utpadan Nigam (UPRUN) and Hydro power plants by the state authority Uttar Pradesh Jal
Vidut Nigam (UPJVN).
In addition to the state govt. owned power generation plants, there are private owned power
generation plants exporting power to UPPCL and central government (Government of
India) owned power generation plants managed by Government of India Enterprises like
National Thermal Power Corporation Ltd., Nuclear Power Corporation Ltd., National
Hydro Electric Power Corporation Ltd. etc. Power generated by all generation units is
being fed to the grid (Northern Grid), which is accessible to all states forming part of the
northern grid. Power mix may be thermal, hydro, wind, nuclear. In India, nuclear power
generation is allowed only by central sector organisations.
Power generated by state owned generation units and private owned generation units would
be consumed totally by respective states. But the power generated by central sector
generation plants will be shared by all states forming part of the grid in fixed proportion.
2 Sources: 1) UPPCL Statistics at a Glance-March 2002 and other available UPPCL documents.
2) Website of Uttar Pradesh Power Corporation Limited (UPPCL)- http://www.uppcl.org
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 8 of 8
5.0 Uttar Pradesh Power Scenario
5.1 Present Fuel Mix in Electricity Generation and Power Deficit
As mentioned above UPPCL distribution network gets major portion of thermal and hydro
power from UPRVUN and UPJVN respectively along with the central sector generation
plants and a small portion from private sector power generation /cogeneration plants and
ultimately distributed to the consumer / end users.
Source wise present installed capacity and power generation in UP shows that the share of
UPPCL coal based power projects is 73 % of total UPPCL installed capacity and 77% of
total generation capacity in the state. Detailed break-up is as under.
Table - 5.1.1: Installed Capacity and Power Generation in UP
Sr. No. Energy Source Installed Capacity
in MW
Net Generation in
MkWh
A. UPPCL
1. Thermal (coal) 4,092 17,565
2. Hydro 1,494.35 5,232
3. Micro Hydel 26.43 29
4. Total (UPPCL) 5,612.78 22,826
B. U.P’s share in Central Schemes
(coal/gas/hydro/nuclear)
3,166.49 18,087.41
C. Import from other sources (incl.
Renewable)
– 156.80
Total 8,844.27 41,069.80
Source: UPPCL statistics at a glance-March 2002 and other available documents
Above table shows that present share of Uttar Pradesh in central power generating schemes
is quite substantial i.e 35% in installed capacity and 44% in generation. Import from other
sources includes power generation in UP by private sector projects, renewable energy
projects (bagasse / biomass based cogenerations) etc.
Last five year data analysis of power data of UP state shows that installed capacity is
dominated by thermal source with share of more than 75 %. Table 5.1.2 shows source-wise
installed capacity peak demand variation during last five years (UPPCL Statistics at a
Glance). In the last ten years total installed capacity increased to 8,383.93 MW (year 1999-
2000) from 7,038.75 MW (year 1990-91) with average increase of 135 MW or 1.91% per
year. Table 5.1.2 also shows that the rise in peak demand met by UPPCL is 1,517 MW
(average 3.4%) in the same period. Further analysis also shows that the actual peak demand
met will be around 70% of total installed capacity.
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 9 of 9
Table 5.1.2 : Source wise Installed Generation Capacity and Peak Demand met
Years Installed Generation Capacity (MW)
(Share in % )
Actual Peak
Demand met
% of
Total
MW
Thermal Hydro Central Total
1999-00 4,532 (75.11) 1,501.44 (24.89) 2,350.49 8,383.93 5,960 71.09
1998-99 4,564 (75.25) 1,501.44 (24.75) 2,350.19 8,234.63 5,708 69.31
1997-98 4,544 (75.12) 1,504.75 (24.88) 1,961.0 8,009.75 5,666 70.73
1996-97 4,544 (75.12) 1,504.75 (24.88) 2,278.0 8,326.75 5,391 64.73
1995-96 4,544 (75.12) 1,504.75 (24.88) 2,433.0 8,481.75 5,420 63.90
1994-95 4,544 (75.12) 1,504.75 (27.1) 2,562 8,610.75 5,296 61.50
1993-94 4,054 (72.9) 1,504.75 (27.1) 2,496 8,054.75 5,055 62.75
1992-93 3,554 (71.3) 1,504.75 (29.7) 2,270 7,328.75 4,955 67.61
1991-92 3,554 (71.3) 1,504.75 (29.7) 2,152 7,210.75 4,750 65.87
1990-91 3,554 (71.3) 1,432.75 (28.7) 1,632 7,038.75 4,443 63.12
Source: UPPCL statistics at a glance-March 2002 and other available documents
With respect to present power scenario, following Table-5.1.3 shows an actual power demand and
energy requirement, deficit in energy availability, deficit in peak load. On per day basis energy
shortage is about 13.56 % and peak load shortage is about 24.50 %. These actual figures gives fair
idea about the present situation of overall UP power sector. The data furnished in the Table 5.1.3 is
based on the published Information as per UPPCL document Statistics at a Glance: 2000-01.
Table – 5.1.3 : Energy and Peak Demand Requirements, Availability & Shortages
Particulars Figures, per day
Energy Requirement,
Million Units (MU)
140.79
Energy Availability, in MU 123.97
Energy Shortage in MU ( %) 16.82 (13.56 %)
Peak Demand Registered, MW 7,138
Peak Demand Met, MW 5,733
Peak Demand Shortage, MW (%) 1,404 (24.50 %)
Source: UPPCL Statistics at a Glance March 2002
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 10 of 10
Future Energy Requirement and Peak Demand Projections by CEA 16 th Power Survey is as under
(Table- 5.1.4).
Table 5.1.4 : Future Projections of Energy Requirement (as per CEA)
Sr.No Year Energy Requirement in
GWh(rise)
Peak Load
In MW (rise)
1 2001-02 50,087 8,018
2 2002-03 53,671 (7.15 %) 8,601 (7.27 %)
3 2003-04 57,531(7.19 %) 9,230 (7.31 %)
4 2004-05 61,681(7.21 %) 9,907 (7.33 %)
Source: CEA 16th
Power Survey
The expected rise in Energy requirement is about 7.18 % and demand of power is about 7.30 % per
annum and no other mega projects are expected to be coming up in the state, the demand-supply
gap is expected to be more widen.
5.2 Plans of Capacity Additions
Considering the present scenario of shortage of energy and power, capacity additions
planned for Uttar Pradesh by CEA and UPPCL in the three 5 year plans are presented in
Table – 5.2.1.
Table – 5.2.1 : CEA and UPPCL Plans
Sr.
No.
Ref . Document / Plan Thermal
MW
Hydro
MW
Total
MW
A As per CEA planning
1. Ninth 5 year Plan 4,580 42 4,622
2. Tenth 5 year plan 4,250 2,776 7,026
3. Eleventh 5 year plan 500 3,867 4,367
B. As per UPPCL planning
1. Ninth 5 year Plan NA NA NA
2. Tenth 5 year plan 2,050 727.6 2,777.6
3. Eleventh 5 year plan NA NA NA
Reference: Fourth national power plan - 1997-2012, CEA document & UPPCL letter to Chief
Secretary (Energy), dated August 28, 2001).
The above table shows as against the requirement of 7,026 MW of capacity additions only
2,777.6 MW is planned to be added by UPPCL (this excludes the additions by centre) This
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 11 of 11
huge gap between capacity addition plans of central Government and state Government
will lead to create a huge shortfall of demand and supply situation of the state. To reduce
this, UP government is encouraging the private participation in power generation sector,
however, yet the due success is to be achieved.
As per Fifteenth Electric Power Survey of India by CEA, the energy requirements and peak
load demand projections for UP are as under (Table – 5.2.2).
Table – 5.2.2 : Five Year Plans (FYPs) for UP
Sr.No Five Year Plan Energy requirement
(GWh)
Peak Load Demand(MW)
1. Ninth 5 year Plan 61,066 11,280
2. Tenth 5 year plan 86,452 (25,386) 15,841(4,561)
3. Eleventh 5 year plan 1,21,253 (34,801) 22,041(6,200)
Figures in bracket indicates capacity additions rise with respect to previous FYP
Above figures of Five Year Plans (FYPs) show that the additional power generation
required in tenth and eleventh plan is 25,386 GWh and 34801 GWh respectively. The rise
in generation predicted is around 45.57 % and 40.25% in tenth and eleventh plan
respectively as compared to the previous FYP. Also the rise predicted in peak demand is
around 40.43 % and 39.13 % in tenth and eleventh plan respectively as compared to the
previous FYP.
5.3 Private Sector Participation
Private sector participation is currently still very limited in India. When the Indian power
sector opened up in 1991, more then 250 Memorandum of Understanding (MoUs) were
submitted by Independent Power Producers (IPPs). However, only few IPPs have been set
up since then.
Total IPP capacity amounts to about 6,000 MW, compared to a total installed capacity in
India of 103,000 MW (Indian Infrastructure May 2002). Only few IPPs are listed for the
state of UP. In addition to the poor financial condition of the SEBs, IPPs faces additional
challenges:
Doubt about sanctity of contracts (PPA)
Uncertainty on tariff stability
Difficulty in obtaining funding from banks/financial institutions
Discouragement by the State Government of third party sales/captive use.
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 12 of 12
ENCLOSURE – II
BASELINE STUDY REPORT
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 13 of 13
ENCLOSURE - II : BASELINE STUDY REPORT
IDENTIFICATION OF THE MOST LIKELY BASELINE AND THE ASSOCIATED GHG
EMISSIONS
1.0 Selection of Baseline Methodology
The Indian economy is in transition from a planned economy to a market based economy.
For the coming years the market is still expected to operate imperfectly. The growth rate of
the infrastructure is inadequate and there is a substantial shortfall in planed projections.
Therefore a scenario analysis is the best to be adopted as the baseline methodology for this
project.
At present details of approved methodology for baseline calculations for CDM projects of
capacity more than 15 MW is not available on the UNFCCC website3. However, reference
has been taken from OECD and IEA information document regarding baseline
methodology (Reference # 31) and UNFCC document “Indicative simplified baseline and
monitoring methodologies for selected small scale (CDM projects less than 15 MW)
project activity categories” (Reference # 05).
As per the Kyoto Protocol (KP)4 baseline should be in accordance with the additionality
criteria of article 12, paragraph 5(c), which states that the project activity must reduce
emissions that are additional to any that, would occur in the absence of the certified project
activity.
With reference to above, a new baseline methodology has been developed as mentioned in
section ‘B’of the CDM-PDD report. Following two baseline approaches/scenarios have
been considered for methodology development.
1. Combined Margin scenario with use of actual available information / data of past
and years and base year.
2. Modified Combined Margin scenario with use of futuristic projections for credit
period.
3 Source: Indicative Simplified baseline and monitoring methodologies for selected small-scale CDM project activity
categories. 4 Source: Kyoto Protocol to the UNFCCC agreed by Conference of Parties (CP)
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 14 of 14
2.0 Application of methodology for estimation of GHG emissions
UPPCL grid receives power generated by state, central and private power plants based on
coal, gas, hydro, nuclear and small portion of renewable sources like bagasse / biomass,
solid waste, solar etc. The present project is a bagasse based electricity generation project
supplying power to UPPCL grid. For Scenario I, the reference case for the baseline is the
generation mix of the base year along with the recently built projects and for scenario II,
the baseline reference case is the generation mix of particular year, considering projected
future capacity additions to the UPPCL. Future capacity addition in the UPPCL grid is to
reduce the shortage of energy and peak demand. The following basis was used at arriving
at the reference baseline.
o Existing mix of power generation by UPPCL is considered for base year reference
o The future mix of generation is considered as future baseline, since UPPCL grid has a
power deficit. To meet the present deficit and to enable future growth, additional
capacity is required.
o The fuel and technology choice for additional capacity depends on a number of factors
like availability of finance, location of the project site, the availability of fuel, the
availability of infrastructure to support the project, the policy framework for
investment in power and renewable energy projects, the purchase of fuel, the sale of
power etc. Therefore, a number of market and non-market factors that control the
choice of fuel-technology combination.
2.1 Baseline Selection
The first step in determining the baseline is the selection of the reference region. As
described in Enlosure -I, the state electricity grid (UPPCL) is part of the northern grid with
similar resource base of recent projects. In line with the UP state government policy,
project promoter has signed a Power Purchase Agreement (PPA) with Uttar Pradesh state
grid (UPPCL) and proposes to export surplus power to UPPCL. In view of above,Uttar
Pradesh state grid (UPPCL) is considered as a reference for baseline calculations.
Scenario I - Baseline is based on the actual generation mix data of UPPCL.
Scenario II - The baseline is based on the likely new project portfolio during the crediting
period. For the estimation of the baseline, historical information on recently commissioned,
under implementation, proposed or announced projects is used. These projects are
considered to be indicative of the intentions of the players in the sector and provide a fair
estimate of the generation portfolio that will emerge in the period up to 2012. Since the
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 15 of 15
crediting period extends to the year 2013 the baseline emissions for the 2013 is statistically
calculated.
2.2 UP state grid : GHG Sources in the Current Situation
Figure 2.2.1 shows the flow chart of the current delivery system, producing the same
amount of electricity as the proposed project. The main GHG emissions in this system arise
from burning fossil fuels for electricity generation.
In addition to the emissions arising from fossil-fired power generation, additional CO 2
emissions occur during the transport of coal and oil from coalmines and oil wells (or ports).
In the northern region coalfields are far from the coal-fired power stations. The
transportation distance is much smaller for the bagasse used in the proposed project than
for the coal-fired power stations. This means transport emission will be lower in the CDM
project then they are currently. Because of a lack of data on average transport distance for
coal to power stations in Uttar Pradesh and the northern grid, we have not included fuel
transport emissions in the system boundary of both the current situation and the project.
This also provides a conservative estimate of the emission reductions.
Since the fuel requirement of the project will be fulfilled by saved bagasse of Haidergarh
and Babhnan sugar mills and biomass will only be used in case of fuel shortage. The DPR
indicates that no biomass will be required for 320 days of operation of the cogen.
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 16 of 16
Figure 3.2.1 : Flow Chart Of Current Delivery System OF Uttar Pradesh
UPRVN
THERMAL
PROJECTS
(coal / Gas
based)
CENTRAL SECTOR
GENERATION
(Thermal/Hydro/Nuclear/RE)
Private Sector
Generation
(Thermal/Hydro/
Renewables)
UPJVN
(Hydro
Project)
UPPCL GRID
NORTHERN REGION
GRID
UPPCL DISTRIBUTION
NETWORK
HYDROTHERMAL
NUCLEAR
HCM
(Cogen
Pro ect
OTHER REGIONAL
GRIDS
END USERS / CONSUMERS OF UTTAR PRADESH
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 17 of 17
2.3 Existing Generation Facilities
The consumer of an Indian state gets a mix of power from the different sources. The figures
of installed power capacity, share of the state in the central pool, and actual plant
availability decides the content of power. In India, the thermal power is mainly generated
by burning bituminous coal mined in central and eastern parts and lignite mined in Tamil
Nadu, Andhra Pradesh and Gujarat. Only a small fraction of the thermal power capacity is
based on naphtha and natural gas. Also, the maximum extent of hydropower is generated in
Himalayan region and the south western mountain ranges.
The real mix of power in a particular year is however based on actual units generated from
various sources of power. The installed capacity and generation statistics for the state of
Uttar Pradesh presented in Table – 2.3.1 below are compiled from UPPCL & NEDA
documents.
Table – 2.3.1: Installed Capacity and Power Generation Statistics of UP
Sr. No. Energy Source Installed Capacity
in MW
Net Generation
in GWh
A. UPPCL
A.1 Thermal (coal based) 4,092.00 17,565.00
A.2 Hydro 1,494.35 5,232.00
A.3 Micro/small Hydro 26.43 29.00
A.4 Renewable sources/MSW etc 40.00 87.00
A.5. Import from other sources incl.
Industrial cogeneration etc.
25.00 69.80
A.6 UPPCL total 5677.78 22982.8
B. U.P’s share in Central Schemes
(coal/gas/hydro/nuclear)
B.1 Thermal (coal) 2510.00 15103.00
B.2 Thermal (gas based) 203.00 1082.00
B.3 Hydro 239.49 805.00
B.4 Nuclear 214 1097.00
B.5 U.P’s share in Central Schemes 3,166.49 18,087.00
Total 8,844.27 41,069.80
Source: Letter of UPPCL No. 1774-Ni/GP/DPU/2002-07 dated August 28, 2001 regarding
capacity addition plan for 10th FYP’s
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 18 of 18
2.4 Capacity addition forecasts
The main key factor effecting the baseline emissions in scenario II approach, is the change
in generation mix of the UP State. As per the data available, all new projects that are under
planning stage or that have got clearance from UPPCL for implementation are projected as
future capacity addition projects in the coming years up to 2007 (see Table 2.4.1 above and
UPPCL documents & website). This will clearly indicate the expected change in generation
mix up to 2007 and the trend for next years of credit.
Information / date gathered from various published documents concerned sources like
CEA, CMIE, UPPCL, NEDA, MoP, MNES, GoUP is used for predicting the capacity
additions during tenth & eleventh plan (2002-03 to 2011-12). Following Table-2.4.1 shows
the capacity additions planned at UPPCL from 2002 until 2007
Table 2.4.1 – Capacity Additions Projected by UPPCL by the year 2007
Sr.No. Project details Fuel used
Capacity
(MW)
Present Status / Remarks
A. Thermal power projects
1. Aanpara-c project Coal 2 X 500 Implemented by 2005
2. Panki expansion project Gas 1 X 210 Implemented by 2006
3. Parichha Expansion project Coal 2 X 210 Implemented by 2007
4. Hardua expansion project Gas 2 X 210 Implemented by 2007
Sub Total 2050
B. Hydel projects
1. Maneri Bhali – II 304.00 Targeted for 10th plan (2007)
2. Lakhwad Vyasi 420.00 Targeted for 10th plan (2007)
3. Shitala 3.60 Targeted for 10th plan (2007)
4. Sub Total 727.60
C. Total (Thermal + Hydal) 2,777.60
Source: 1) Information received / published documents of CEA, CMIE, UPPCL, NEDA, MoP,
MNES, GoUP etc.
2) Letter of UPPCL No. 1774-Ni/GP/DPU/2002-07 dated August 28, 2001 regarding
capacity addition plan for 10th FYP’s
The actual generation data of the entire UP for the year 2000 - 2001 is available in the form
of UPPCL statistics which includes own generation, purchase from central sector power
plants, purchase from private sector power plants/ cogeneration plants etc.
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 19 of 19
It has been observed that an average capacity addition is in the installed capacity of UP
including state and central projects is only about 18-19% during last ten years. (1990-91 to
1999 – 2000). This will be assumed for prediction of capacity addition in the central
schemes for tenth and eleventh plan.
As per sixteenth power survey of CEA, average capacity addition is in the state of UP
including State and central projects is predicted as 7.19%. The same has been considered
for predicting the capacity additions of thermal and hydropower projects of UPPCL during
the year 2007 to 2012.
The total installed capacity with addition of around 9,000 MW during the year 2002-03 to
2011-12 or around 900 MW average addition per year is arrived as 17,690 MW, which is
lower than the required by the end of eleventh five year plan value of 22,040 MW (year
2011-12). With this scenario expected shortage will be of 4,350 MW. Also, there is a good
potential for small hydro projects which can be set up on irrigation canals, tanks etc. that
will not alter the generation mix substantially.
The additional data collected from official documents/website of UP Government in which
list of new projects proposed / sanctioned and new expansion proposals which indicates the
future capacity additions. These projects are available for private sector promoters. The
same data is reproduced and presented in the Annexure A and summary of the same is
mentioned as under.
Table 2.4.2 Summary of New Projects Available in UP for private sectors
Sr.
No.
Project Details Capacity (MW) Remarks
1. Thermal projects 1,000 UPPCL project
2. Hydro projects 2,023 50 % is expected to be implemented by
10th
plan & balance by 11th plan
Source: Website of Uttar Pradesh Power Corporation Limited (UPPCL), - http://www.uppcl.org
In addition to the above scenario there are number of proposed renewable energy projects.
If these capacities are realised as planned, then will help a lot to reduce the shortage of
demand for power in the State. Present status of renewable energy projects along with the
future projections are as under (Table-2.4.3). Potential for renewable energy projects (REP)
excluding solar, in UP is more than 4,000 MW.
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 20 of 20
Table 2.4.3 Projections of Renewable Energy Projects (REP)
Sr.
No.
Renewable Energy Source Present installed
capacity
Expected
additions during
10th
plan
Expected
additions during
11th
plan
1. Micro / Mini Hydel
Micro / Mini Hydel 26.43 MW 117.00 MW 600.00 MW
Total 117.00 MW 600.00MW
2. Renewable/Cogen/MSW
and other sources
(i) Bagasse / Biomass based
cogeneration
40.00 MW 300.00 MW 400.00 MW
(ii) Municipal Waste 15.00 MW* 82.00 MW 100.00 MW
(iii) Biomass Gasifier / misc 2.27 MW
25.00 MW** 50.00 MW**
(iv) Wind N.A
(v) Solar Photovoltaic 0.40 MW
Total 407 550
Sources: Published documents of NEDA, website of government of UP etc
* Projects are under implementation
** minimum expected additions
Source of the above information regarding installed capacities is various published
documents of NEDA and MNES including the website of Govt. of UP. Since there is no
clear cut plan available regarding capacity additions during the tenth & eleventh plan,
estimations have been carried out based on the discussions with NEDA officials, the
available potential of each of the source, present central policy regarding 10 % share of
REP in the total power generation, revised energy policy of UP govt. towards development
of renewable energy sector, UPPCL policy for purchase of renewable energy power etc.
The total capacity addition in each plan is considered to be equally distributed during the
five years span.
Based on the capacity addition statement, it is expected that by the eleventh FYP, out of the
total installed capacity 62% will be the thermal plants. Balance 38% comprises of hydro,
nuclear and renewable energy (9.25%) including micro hydel projects. Considering all the
above it is concluded that the thermal generation mix will continuously increase slightly
towards 2012. For the detailed calculation please refer to the Annexure C.
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 21 of 21
2.5 Calculations of Baseline Emissions
2.5.1 On-site Emissions
UPPCL grid is considered for baseline analysis and calculation of anthropogenic emissions
by fossil fuels during power generation. As mentioned earlier the UPPCL generation mix,
coal and gas based power projects are responsible for GHG emissions. Two scenarios
considered for baseline calculations are :
(i) The Combined Margin scenario (average of the “approximate operating margin” and
the “build margin”).
(ii) Modified Combined Margin scenario
The distribution of capacity additions over the two plan periods is undertaken in the
following manner:
Based on the reported and collected information on the likely commissioning of
projects, the capacities for the projects are listed under the respective years. The
expected capacity additions have been listed as new capacities for the year.
The capacity additions till the year 2007 are based on information gathered from
various sources as mentioned above (also in the reference list). Wherever the
particular year of commissioning is not available, these capacities are assumed to
equally spread over the plan period.
Estimated capacity addition factor is applied for the predictions of conventional
power projects of centre and UPPCL during the year 2007 to 2013.
Capacity additions through renewable energy projects by the year 2007 is also based
on the information collected from concerned sources as mentioned above. Beyond
the year 2007 till 2012 it is based on the potential available for each type.
The generation from each fuel source was calculated, considering previous year
generation as a basis.
The most important parameter in estimating the emissions is the future thermal efficiency
of the power plants. As per the CEA report, it is assumed that all the coal and lignite based
plants coming up in tenth and eleventh five year plan will use pulverized coal sub-critical /
super critical pressure technology with the thermal efficiency of around 34 % and gas
based plants will use combined cycle gas turbine (CCGT) technology with thermal
efficiency of around 43 %. The percentage of carbon that is not burnt is very low and,
hence, complete combustion is assumed.
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 22 of 22
Scenario-wise, description of estimation of CO2 emissions is as under
I) Scenario 1: The average of the approximate operating margin and the build margin.
Similar to the scenario I, baseline calculations were carried out under this scenario.
Approximate operating margin and build margin is to be calculated as per the OECD
and IEA reference document (reference # 5) and UNFCCC methodology specified for
small scale activities.
For estimation of operating margin, weighted average of all resources, excluding
hydro, geothermal, wind, low-cost biomass and solar generation is considered.
For estimation of the build margin (or ‘recently built’) the weighted average emissions
(in kgCO2/kWh) as most recent 20% of plants built or the 5 most recent plants of
recent capacity additions, which ever is greater.
In this case also, actual performance data including CO 2 emission figures of coal based
thermal power plants operating in UP state are considered. Details of coal based
projects is as per Table # 2.5 (a) below
Share of gas-based projects is very small (2.81%) as compared to coal based, hence
standard value of CO2 emission by combustion of gas is considered for baseline
calculations (and not actual values). For Natural Gas based power plants IPCC
standard emission factor of 56.10 kg CO 2/GJ and 45% efficiency is considered.
For calculation of build margin, UPPCL data regarding recently build 5 power plants is
used which accounts for more than 20 % of total installed capacity of UPPCL. As per
the Table # 2.5(b)below, build margin factor for base year (2001) comes out to be
1.0750 kg of CO2/kWh.
As per the table, average build margin CO 2 emission factor is considered as 1.075 kg
CO2/kWh. An improvement of 10% is assumed for build margin, till 2010 considering
the central government guideline regarding increase of renewable energy share in the
present generation mix to 10% by the year 2010.The same trend has been extended till
end of credit period i.e. 2013. Looking at the progress made in the renewable energy
power sector (as mention in Enclosure-I) this is a conservative assumption.
Step by step calculation of CO2 emissions due to burning of coal and gas for power
generation and emission reductions by project activity is as under.
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 23 of 23
Step 1 : Net emission factor for
coal
= Actual emission factor for coal x % of
generation by coal out of total generation
excl.Hydro and RE projects.
Step 2 : Net emission factor for
gas
= Step 1 is to be repeated for gas
Step 3 : Operating margin
factor
= Net emission factor for coal + Net emission
factor for gas
Step 4 : Built margin factor = (Avg. actual emission factor for thermal
projects x recently build thermal projects +
emission factor for hydro x recently build hydro
projects) / (total of recently build thermal &
hydro projects)
Step 5 : Average of operating
and build margin factor
= (Operating margin factor + Built margin factor)
/ 2
Step 6 : Units exported to
UPPCL
= Export in season + Export in off-season
Step 7 : CO2 emission
reduction
= Units exported to UPPCL grid x average of
operating and build margin factor.
II) Scenario 2: Modified Combined Margin Method
Since the selected state grid is power deficit, there is a continuous addition of capacity in
all sectors of grid mix. To take care of this, a modified combined margin method (MCMM)
has been developed which has takes into account the present generation mix as well as the
capacity additions for the credit period ( Ex Post & Ex Ante calculations). In the combined
margin methodology, the effect of proposed / future capacity additions are not considered
for estimation of carbon intensity of the grid for future years (credit period). Operating
margin is calculated as in combined margin method for each year of the credit period with
capacity addition consideration.
Step 1 : Modified Combined
Margin Factor
= Selected lowest conservative value Combined
Margin over of Credit Period.
Step 2 : Units exported to
UPPCL
= (Export in season) + (Export in off-season )
Step 3 : CO2 emission
reduction
= Units exported to UPPCL grid x Modified
Combined Margin Factor
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 24 of 24
Table 2.5(a): Power Plant performance and CO2 emissions
Sr. Power plant Installed Generation Plant Coal Coal CO2 Calculated
No. location capacity Capacity Efficiency required Grade emission CO2 emission
(MW) (MW) (%) (kg/kWh) (kg/kg) (kg/kWh)
1 Anpara 1630 1630 31 0.70 E,F 1.329 0.93030
2 Harduaganj 385 135 22 1.02 E,F 1.329 1.35558
3 Dadri 848 653 34 0.65 E,F 1.329 0.86385
4 Obra 1442 1014 25 0.88 E,F 1.329 1.16952
5 Panki 274 165 24 0.90 E,F 1.329 1.19610
6 Paricha 220 80 25 0.88 E,F 1.329 1.16952
7 Rihand 1000 960 33 0.66 E,F 1.217 0.80322
8 Singrauli 2000 1545 36 0.61 E,F 1.620 0.98820
9 Tanda 330 195 23 0.96 E,F 1.329 1.27584
10 Unchahar 840 826 30 0.74 E,F 1.329 0.98346
Total /
wt.Avg.
8969 7203 31.04 0.72 E, F 1.38 0.986
Source: A paper on Anthropogenic Emissions from Energy Activities in India: Generation and Source
Characterization by Moti L.Mittal and C.Sharma
For calculation of build margin, following UPPCL data regarding recently build 5
power plants is used as under. Also this capacity is more than 20 % of total installed
capacity
Table 2.5(b) :Build margin calculation
Sr.No. Power plant
name / location
Type Capacity
(MW)
Year of
commissioning
CO2
emission
(kg/kWh)
1. Anpara A Thermal- coal based 420
(2 x 10)
1987 0.93030
2. Anpara A-Phase
II
Thermal- coal based 1x210 1988 0.93030
3. Anpara B Thermal- coal based 1x500 1994 0.93030
4. Tanda Thermal- coal based 930
(3x310)
1987 1.27584
5. Khara Hydro 1x22 1992 0.00
TOTAL 2082 Wt. Avg. 1.0750
Source: 1) UPPCL Report, Statistics at a Glance – March 2002
2) A paper on Anthropogenic Emissions from Energy Activities in India: Generation and
Source Characterization by Moti L.Mittal and C.Sharma
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 25 of 25
Following table indicate the net baseline emission factors and certified emissions
reductions (CERs) of each year, for Scenario 1 as given above.
Table 2.5 (c) Certified Emission Reductions with scenario 15
Operati
ng
Years
Net Baseline
Emission
Factor
(kgof CO2 /
kWh)
Baseline
Emissions
(tones of
CO2)
Project
Emissions
(tones of
CO2)
Leakage
emissions
(transportation)
Certified
Emission
Reductions
(CERs)
(tones of CO2 )
2004 1.021 96,926 0 1,950 94,976
2005 1.021 102,984 0 1,950 101,034
2006 1.021 109,042 0 1,950 107,092
2007 1.021 109,042 0 1,950 107,092
2008 1.021 109,042 0 1,950 107,092
2009 1.021 109,042 0 1,950 107,092
2010 1.021 109,042 0 1,950 107,092
2011 1.021 109,042 0 1,950 107,092
2012 1.021 109,042 0 1,950 107,092
2013 1.021 109,042 0 1,950 107,092
Total 1,072,245 0 19,500 1,052,745
Following table indicate the net baseline emission factors and certified emissions reductions
(CERs) of each year, for Scenario 2 as given above.
Table 2.5 (d) : Certified Emission Reductions with Scenario 26
Sr.
No.
Operatin
g
Years
Net Baseline
Emission Factor
(kg of CO2 / kWh)
Baseline
Emissions
(tones of
CO2)
Project
Emissions
(tones of
CO2)
Leakage
emissions
(transportation)
Certified
Emission
Reductions,
CERs
(tones of CO2 )
1. 2004 0.91 86,399 0 1,950 84449
2. 2005 0.91 91,799 0 1,950 89849
3. 2006 0.91 97,199 0 1,950 95249
4. 2007 0.91 97,199 0 1,950 95249
5. 2008 0.91 97,199 0 1,950 95249
5 As per Annexure C(Combined margin)
6 As per Annexure C-2 (Modified)
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 26 of 26
Sr.
No.
Operatin
g
Years
Net Baseline
Emission Factor
(kg of CO2 / kWh)
Baseline
Emissions
(tones of
CO2)
Project
Emissions
(tones of
CO2)
Leakage
emissions
(transportation)
Certified
Emission
Reductions,
CERs
(tones of CO2 )
6. 2009 0.91 97,199 0 1,950 95249
7. 2010 0.91 97,199 0 1,950 95249
8. 2011 0.91 97,199 0 1,950 95249
9. 2012 0.91 97,199 0 1,950 95249
10. 2013 0.91 97,199 0 1,950 95249
Total CERs 955,789 0 19,500 936,289
Therefore an conventional energy equivalent of 1050.32 Million kWh for a period of 10
years in UP would be saved by the exporting power from the proposed 20 MW non-
conventional renewable sources bagasse based cogeneration power plant which in turn will
reduce 1,052,745 tons of CO2 emissions considering baseline calculations as per scenario
1, 936,289 tons of CO2 emissions considering baseline calculations as per scenario 2.
As being a realistic and conservative approach, which also takes into account the
recent trend of power projects build for estimation of CO2 emissions reductions,
scenario 2 has been considered for further calculations.
2.5.2 Off-site emissions
In the power generation process at thermal power plant, major activities responsible for -
site emission are construction of infrastructure for the movement of fuel and transport of
the fuel.
In context of this project, leakage activity identified, which contributes for GHG emissions
outside the project boundary is transportation of saved bagasse from Babhnan Sugar Mill to
proposed cogen power project at Haidergarh. Calculation of leakage has been carried-out
as under:
• Bagasse to be procured from Bhabnan plant - 81120 MT
• Distance between Bhabnan & Haidergarh - 160 km
• Bagasse load per truck - 5 MT
• Number of trips - 16224
• Consumption of Diesel per trip - 40 litres (@4km/litre)
• Total Diesel consumption per annum - 648960 litre
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 27 of 27
• CO2 emission factor for Diesel - 74.10 tonne CO2 / TJ
• Per annum co2 emission - 1950 tons (approx) per year
The same type of CO2 emission (leakage) occurs during transportation of coal from coal
mines to respective power plants and distance between the coal mine and power plant is
quite higher as compared to the transportation distance between Babhnan and Haidergarh
and hence the higher CO2 emission. To be on conservative side, this leakage due to coal
transportation has not been added while calculating the baseline of UP grid and hence a
small leakage due transportation of bagasse has been neglected from the calculations.
Total baseline emissions
Total baseline emissions will be addition of on-site emissions and off-site emissions. Since
off-site emissions are not considered for baseline emission calculations, as mentioned
above, the total baseline emission will be same as on-site emissions.
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 28 of 28
Annexure – A
List of Conventional Power Project Available in the State of Uttar Pradesh to be
Implemented in the Near Future7
Sr.No. Name of Project & Location Capacity
(MW)
Remarks
A. Thermal
1. Anpara ‘C’,
District sonbhadra
2 x 500 The project is open for private
sector participation
Sub Total 1000
B. Hydro – Big Projects These projects are open for
private sector participation
1. Bowla Nand Prayag,
Dist. Chamoli
3 x 144
2. Pala Manari,
Dist. Uttar Kashi
4 x104
3. Tapovan Vishnugad,
Dist. Chamoli
3 x 120
4. Lohari Nagpala,
Dist. Uttar Kashi
4 x 130
5. Tuni Plasu,
Dist. Dehradun
3 x 14
Sub Total 1770
C. Hydro – Small Projects These projects are also open for
private sector participation
These projects are also open for
private sector participation
1. Supin, Uttarkashi 11.20
2. Tons, Uttarkashi 14.40
3. Yamuna-1, Uttarkashi 3.60
4. Barnigad, Uttarkashi 6.50
5. Kakorigad, Uttarkashi 3.60
6. Kaldigad, Uttarkashi 7.00
7. Asiganga-I, Uttarkashi 4.50
8. Asiganga – II, Uttarkashi 3.00
9. Asiganga – III, Uttarkashi 3.00
10. Hanumanganga, Uttarkashi 3.50
11. Jalandharigarh, Uttarkashi 4.00
12. Pilanggad II, Uttarkashi 4.00
7 Source: Official website of Government of Uttar Pradesh, India – http://www.upindia.org
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 29 of 29
Sr.No. Name of Project & Location Capacity
(MW)
Remarks
13. Balganga – I, Tehri 5.40
14. Balganga –II,Tehri 7.00
15. Bhilganga – II, Tehri 10.50
16. Bhilganga – III, Tehri 8.40
17. Ksheer-Ganga, Chamoli 4.00
18. Urgam – II, Chamoli 3.80
19. Guarikund, Chamoli 13.20
20. Patha-Buying, Chamoli 9.70
21. Kaliganga – I, Chamoli 4.60
22. Kaliganga – II, Chamoli 6.00
23. Nandakini – I, Chamoli 4.80
24. Nandakini – II, Chamoli 6.20
25. Nandakini – III, Chamoli 4.25
26. Birahi-Ganga - I, Chamoli 5.40
27. Birahi-Ganga – II, Chamoli 4.50
28. Naxman-Ganga, Chamoli 4.40
29. Alaknanda –I, Chamoli 15.00
30. Alaknanda – II, Chamoli 10.00
31. Madhya Mahashwarganga, Chamoli 5.60
32. Mandakini-I, Chamoli 7.50
33. Mandakini-II,Chamoli 8.00
34. Mandakini-III,Chamoli 8.00
35. Pabar, Dehradun 5.20
36. Relagad, Pithoragarh 3.55
37. Painagad, Pithoragarh 4.00
38. Jimbagad, Pithoragarh 6.00
39. Tankul, Pithoragarh 7.80
Sub total C 251.10
TOTAL 3021.10
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 30 of 30
Annexure – B8
List of Renewable Energy Projects Available in the State of Uttar Pradesh to be implemented
in the Near Future - Under NEDA’s Programme
Sr.No. Name of Project & Location Capacity
(MW)
Remarks
A. Small Hydro
A1. New Small & Micro hydel projects to
be implemented
117 (estimated) 44 projects are under detailed
survey. UPPCL already signed
MoU’s with 23 projects of total
capacity 68.50 MW
A2. Partial list of the projects is as
under
1. Harsila, Almora 1.00 These projects are open for
private sector participation
2. Mansuna, Chamoli 2.00
3. Palalganga, Chamoli 1.40
4. Gaurikund, Chamoli 2.00
5. Gharitganga, Chamoli 1.25
6. Baram, Pithoragarh 1.00
7. Bhadeli, Pithoragarh 1.00
8. Jimigarh, Pithoragarh 1.35
9. Chalthi, Pithoragarh 1.50
10. Seragad, Pithoragarh 1.50
11. Aglar, Tehri 1.35
12. Lastergad, Tehri 1.20
13. Jalkur, Tehri 2.00
14. Jakhol, Uttarkashi 2.00
15. Sawrigad, Uttarkashi 1.50
16. Siyan, Uttarkashi 3.00
17. Supin, Uttarkashi 3.00
SUB TOTAL A2 28.05
8 Source: Official website of Government of Uttar Pradesh, India – http://www.upindia.org
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 31 of 31
Sr.No. Name of Project & Location Capacity
(MW)
Remarks
A3. Additional estimated Potential 600 Expected to be implemented by
10th & 11th FYP
Sub Total A 717
B. Municipal Solid Waste
1. Agra 8.00 These projects are open for
private sector participation
(Expected to be implemented in
2-3 years)
2. Aligarh 5.00
3. Allahbad 7.00
4. Bareilly 7.00
5. Ghaziabad 5.00
6. Gorakhpur 5.00
7. Kanpur 20.00
8. Lucknow 20.00
9. Meerut 7.00
10. Muradabad 5.00
11 Varanashi 8.00
Sub Total B 97.00
C. Bagasse Cogeneration
C1. Actual implementation 40 Implemented by 7 sugar mills.
C2. Additional Projected potential 700 It is expected that around 300
MW will be implemented by 10th
FYP.
Sub Total C 740
Total 1554
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 32 of 32
ENCLOSURE – III
EIA SUMMARY REPORT
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 33 of 33
ENCLOSURE – III : EIA SUMMARY REPORT
ENVIRONMENTAL IMPACT ASSESSMENT
The environmental impacts can be categorized as either primary or secondary. Primary impacts are
those that are attributed directly by the project, secondary impacts are those which are indirectly
induced and typically include the associated investment and changed patterns of social and
economic activities by the proposed action.
The proposed project would create an impact on the environment in two distinct phases:
During the construction phase and
During the operation phase which would have long term effects.
The proposed cogeneration plant will be set up adjacent to the proposed sugar-manufacturing unit
at Haidergarh. The land is presently barren with not much vegetation. No cutting of trees is
involved and there is no deforestation required. During the study of environmental impact
assessment, a few additional mitigating measures have been identified to further minimize the net
impact. These issues have been covered with each of the impacts below.
IMPACTS DURING CONSTRUCTION
The impacts envisaged during the construction of the proposed plant are:
Impact on Land use and Hydrology
Due to the terai region, the water level is very high. The pumping of ground water will
help in lowering the water level in the factory area. The Sugarcane requires large
quantities of water for irrigation. 59% of area is irrigated by tube-wells and increase
sugarcane crop will help in bringing down the water table.
Impact on Terrestrial Ecology
The proposed land is barren and there is no requirement to clear the land. There is no negative
effect of the proposed project on the terrestrial ecology of the area. The project site will also be
extensively landscaped with the development of green belt consisting of variety species which
would enrich the ecology of the area.
Impact on Aquatic Ecology
There is no tank, lake, river or surface water body very close to the project site. Hence no impact
is envisaged in the construction phase on the aquatic ecology of the area.
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 34 of 34
Demography and Socio-Economics
Land has been purchased from local villages for which proper price has been paid. Some efforts
are necessary to resettle their families.
The establishment of the factory will prove highly beneficial to the rural population neighboring
the site. There will be a marginal increase in the employment of some persons living in the
nearby villages both at the time of construction as well as during operation.
Traffic and Traffic Hazards for Access Roads
During construction phase, the building material, equipment and machinery and labour will be
transported to the site and this will increase the volume of traffic on access roads. However this
effect will not be very significant in view of the fact that the construction activities will be
spread over a period of 10 months.
The impacts during the construction phase are regarded as temporary or short term and hence do
not have an everlasting affect on the soil, air, noise or water quality of the area.
During Construction Phase
The impact from the construction phase is not envisaged to be serious. However the following
factors should be kept in mind to make certain that the impacts are minimal.
Site Preparation
No major leveling operations are required. However during dry weather conditions, it is necessary
to control the dust generated by excavation and transportation activities. At the site such activity
will be carried out after water sprinkling.
Sanitation
The construction site should be provided with sufficient and suitable toilet facilities for workers
meeting the proper standards of hygiene. These facilities should preferably be connected to a septic
tank and maintained to ensure minimum environmental impact.
Noise
The impact of noise on the nearest inhabitants during the construction activity will be negligible.
However it is advisable that on site workers using high noise equipment use noise protection
devices like ear muffs. Noise prone activities have to be restricted to the extent possible during
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 35 of 35
night particularly during the period 10 p.m. to 6 a.m. in order to have minimum environmental
impact.
Construction Equipment and Waste
It should be ensured that both gasoline and diesel powered vehicles are properly maintained to
minimize smoke in the exhaust emissions. The vehicle maintenance area should be located in such
a manner to prevent contamination of surface and ground water sources by accidental spillage of
oil. Unauthorized dumping of waste oil should be prohibited.
Deforestation
Although the site is not endowed with trees and vegetation, in order to avoid felling of trees in the
vicinity, the construction site workers should be assisted in procuring fuel for cooking purposes in
order to avoid felling of any trees in the neighborhood.
Storage of Hazardous Materials
The following hazardous materials are anticipated to be stored at site during construction:
Petrol and Diesel
Gas for welding purpose
Painting materials
These materials should be stored in drums as per international safety norms.
Land Environment
As soon as construction is over the surplus earth has to be utilized to fill up low lying areas, the
rubbish is to be cleared and all unbuilt surfaces reinstated. There are no trees at the present site
hence no felling of trees is involved. Appropriate vegetation will be planned after construction
activity.
During construction the impacts are generally manifested by loss of minor vegetative cover,
migration of minor avian population restricted to site. After green belt development these will be
mitigated and the avian population will increase after green belt development since there are no
tress presently.
Development of green belt is to be taken up along with civil works.
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 36 of 36
IMPACTS DURING OPERATION
The operational phase will involve power production using bagasse. The following activities in
relation to the operational phase will have varying impact on the environment and are considered
for impact prediction.
Impact on Air Quality
The EIA study establishes that the existing status of the ambient air quality of the area is well
within the national ambient air quality standard.
The pollutants envisaged from the proposed co-generation power plant are Suspended Particulate
Matter (SPM), Oxides of Nitrogen (NOx), Carbon mono-oxide (CO) and CO 2.
As such the bagasse has very low ash content (1.5%). The SPM as ash is controlled by high
efficiency Electro-Static Precipitator (ESP). High efficiency (> 99%) ESP will ensure SPM
levels less than 150 mg/Nm3 in the stack. There will not be any Sulpher di-oxide (SO 2) emission
considering bagasse do not contain sulpher. Moisture content of 50% in bagasse will keep the
burner temperatures low so that NOX formation will not take place. Similarly the for high
efficiency combustion is envisaged so that CO formation do not take place and the CO 2 gets
absorbed by the sugar canes harvested each year.
To reduce the ground level concentrations of the pollutants still further, 72 m high R.C.C. stack
height is proposed. This will further help is fast dispersion of pollutants into the atmosphere,
thus, reducing their impact in the vicinity of the project area.
The predictions for air quality during operation phase were carried out for suspended particulate
matter, concentrated for using Air Quality model “Industrial Source Complex Version 99155
(ISCST3)” developed by the US Environmental protection agency in 1995 for atmospheric
dispersion of stack emissions from point source (Details provided in the EIA Report). The
maximum predicted ground level concentrations for SPM were 3.14 ug/m 3 and these were
observed in the North-North-West at a distance of 2.2 km. This shows that HCM will be taking
adequate measures such that air quality impacts of running the power plant operation phase are
reduced to a minimum.
There may be some adverse impact on air quality from truck/tractor exhaust and dust due to
transport of bagasse from Babhnan to the site considering per truck load 2 to 5 tones of loose
bagasse or 8 tones of bale bagasse will be transported. That is additional trips per day based on
the bale or loose type bagasse transport respectively.
About 81,120 tones of bagasse will be transported to plant site from Bhabnan per annum. It is
recommended that HCM should transport bagasse as compressed bales to reduce number of
transport trips. For this HCM has to install ‘baling machine’ at Bhabnan and ‘de-baling machine’
at their Haidergarh sugar unit. Considering the advantage of transporting 5 to 8 tones of bagasse
as bales over 2 to 5 tones per truck without baling the system will have economic benefits along
with environmental benefits. Also, it will be ensured that the bagasse transporting trucks do not
return empty.
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 37 of 37
The air pollution from the plant in the form of particulate matter emitted mainly from the boiler
are found to be well within the prescribed norms and hence no mitigation measures are
envisaged. In case of non-availability of bagasse, is envisaged to be used as fuel. Considering
bio-mass has more ash content (17%) against 1.5% of bagasse the ESP needs to be fine tuned so
that stack emissions remains within limits.
Impact on Soil
Most of the impacts on soil due to the project are negligible and restricted to the construction
phase and will get stabilized during the operational phase. Fly ash collected from the ESP
hoppers and air heater hoppers and the ash collected from the furnace bottom hoppers can be
used as landfills and also can used as fertilizers in the sugar cane fields. The ash content in the
bagasse is less than 2%. The total fly ash collected may be mixed with press mud from the sugar
plant and sold to farmers as manure because of its high nutrient value.
The boiler soot after cleaning should be stored in a closed drum and to be disposed properly.
Similarly the oily waste, cloth etc. should be stored in a drum and disposed properly.
Impact On Water Resources
The proposed cogeneration unit’s water requirement would be met by the ground water
resources. This is considering abundant ground water with continuous recharge is available.
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 38 of 38
Impact on Noise
For assessing the impact of noise during operation phase, considerations have been given to two
aspects, those relating to the noise sources and the other relating to potential receivers.
The sound pressure level generated by noise sources decreases with increasing distance from the
source due to wave divergence. An additional decrease in sound pressure level with distance
from the source is expected due to atmospheric effect in its interaction with objects in the
transmission path. Hence, the maximum exposure of noise is when a person is at line of sight
from the noise generating source.
In the cogeneration unit continuous and very high noise levels are generated near primary air
fans, forced drafted fans, boilers, generators, compressors and pumps.
Plant equipments are designed to keep noise levels less than 90 dB(A). This is considering
damage risk criteria as enforced by OSHA (Occupational Safety and Health Administration) to
reduce hearing loss, stipulates that noise level upto 90 dB(A) are acceptable for 8 hour working
shift per day.
For computing the noise levels at various distances with respect to the plant site in general and
the turbo-generator bay in particular, noise propagation analysis was undertaken. The noise
computed at a far distance of about 1000m is of the order of 35dB(A) during the operation of the
plant. The ambient noise level recorded in the nearby villages ranges between 40-55 dB(A).
(Details provided in the EIA Report) Due to masking effect, the ambient noise levels in the
nearby villages will not increase during the operation phase.
The noise levels in the work areas like generator room and boiler room may be slightly on the
higher side (>85dB(A) continuously) but at these places, continuous attendance of workers are
not required and workers will be on duty only in shifts as required. Provision of protective
personnel equipment in addition will reduce the impact of noise level. Hence these noise levels
may not be of much concern from occupational health point of view. However under the general
health check-up scheme as per factory act, a trained doctor will check up the workers for any
Noise Induced Hearing Loss (NIHL).
The greenbelt, which is being provided by HCM will act as noise attenuator.
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 39 of 39
Impact on Water Quality
The EIA study establishes that the existing status of the water quality of the area are well within
the environmental norms. The effluent generated from the proposed sugar plant and the project
activity – the cogeneration power plant will be treated in the effluent treatment plant to ensure
there is no environmental deterioration.
The liquid effluents from the power plant would include effluent generated from DM water
treatment plant, boiler blow down, cooling tower blow-down, floor washings, sanitation etc.
Effluent from DM Plant: Hydrochloric acid and sodium hydroxide will be used as
regenerants in the DM water plant for boilers and effluent would be drained into epoxy
lined underground neutralizing pits. Generally, these effluents are self neutralizing,
however provisions will be made such that the effluents are completely neutralized by
addition of acid/alkali. The effluent would then be pumped into the effluent treatment
ponds, which are a part of the effluent disposal system.
Effluent from RO Plant: The wastewater generated from Reverse Osmosis (RO), which by
design will have less than 2100 mg/l Total Dissolved Solids (TDS) will be sent to sugar
factory ETP
Effluent from Boiler:The salient characteristics of the blow down water from the point of
view of pollution would mainly be the pH and temperature since the suspended solids are
negligible. The pH would be in the range of 9.8 to 10.3 and the temperature would be
around 100 oC. The quantity of the blow down water is as low as 1.2 tones/hr it is proposed
to put the blow down into the trench and leave it into the sugar plant effluent ponds.
Therefore there are no major impacts envisaged due to effluent generation from the project
activity.
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 40 of 40
Impact on Ecology
The inventory on terrestrial ecology has been compiled through data collection from marshes,
irrigation canals, agricultural land and groves (Details provided in the EIA Report). Air
emissions from the plant are very low as mentioned above. SPM will contain primarily ash with
high nutrient value and will be beneficial to the plants. Other pollutants like NO X and CO are not
envisaged in much quantity to adversely affect the plants or animals.
There are no liquid discharges from the plant that will interfere with the local aquatic ecological
system. High TDS water (<2100 mg/l) will get diluted and will not deplete the dissolved oxygen
levels if reaches to water body, even though it will be discharged on the land.
Ecology and Green belt Development
Implementation of afforestation program is of paramount importance for any industrial
development. In addition to augmenting green cover, it also checks soil erosion, marks the
climate more conductive, restores water balance and makes ecosystem more complex and
functionally more stable. The proponents are proposing for an extensive program for the
development of green belt around the plant. The green belt is being proposed for the following
objectives:
Mitigation of fugitive dust emissions including any odor problems
Noise pollution control
Controlling soil erosion
Balancing eco-environment
Aesthetics
The tree species selected for green belt would include the native species like Mohua, Dhak,
Neem, Mango, Barad etc. The treated sewage effluent from the plant would be used for watering
the green belt.
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 41 of 41
ENCLOSURE – IV
ABBREVIATIONS
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 42 of 42
ABBREVIATIONS
BCML Balrampur Chini Mills Limited
HCM Haidergarh Chini Mills, a unit of Balrampur Chini Mills Limited
CCGT Combined Cycle Gas Turbine
CC Climate Change
CDM Clean Development Mechanism
CEA Central Electricity Authority
CER Certified Emission Reductions
CMIE Centre for Monitoring Indian Economy
CO2 Carbon di-oxide
CPU Central Power Units
CP Credit Period
DCS Distributed Control System
DPR Detailed Project Report
DM De-Mineralised
EGEAS Electric Generation Expansion Analysis System
EPS Electric Power Survey
ESP Electro Static Precipitator
EIA Environmental Impact Assessment
FYP Five Year Plan
GHG Greenhouse Gas
GOI Government of India
GoUP Government of Uttar Pradesh
GWh Gega Watt hour
HP High Pressure
HV High Voltage
ICICI Industrial credit & Investment Corporation of India
IPCC Intra-governmental Panel for Climate Change
IPP Independent Power Producers
IREDA Indian Renewable Energy Development Agency
ISPLAN Integrated System Plan
KP Kyoto Protocol
km Kilo
KV Kilo Voltage
KW Kilo Watt
KWh Kilo Watt hour
LP Low Pressure
1 Lakh 1,00,000
MkWh Million Kilo Watt hour
MU Million units
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 43 of 43
ABBREVIATIONS (Contd.)
MoP Ministry of Power
MNES Ministry of Non-conventional Energy Sources
MoU Memorandum of Understanding
MSW Municipal Solid Waste
MT Metric Ton
MW Mega Watt
NCE Non Conventional Energy
NEDA Non conventional Energy Development Agency
NTPC National Thermal Power Corporation
NOC No Objection Certificate
p.a Per annum
PLF Plant Load Factor
PPA Power Purchase Agreement
PIN Project Idea Note
REP Renewable Energy Projects
SEB State Electricity Board
STG Steam Turbine Generator
TCD Tones of Crushing per Day
TJ Trillion Joules
TPH Tones Per Hour
TERI Tata Energy Research Institute
UNFCCC United Nations Framework Convention on Climate Change
UP Uttar Pradesh
UPPCL Uttar Pradesh Power Corporation Limited
UPPCB Uttar Pradesh Pollution Control Board
UPERC Uttar Pradesh Electricity Regulatory Commission
UPRVUN Uttar Pradesh Rajya Vidut Utpadan Nigam
UPJVN Uttar Pradesh Jal Vidut Nigam
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 44 of 44
ENCLOSURE – V
REFERENCE LIST
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 45 of 45
REFERENCE LIST
Sr.No Particulars of the references
Kyoto Protocol / UNFCCC Related
1. Kyoto Protocol to the United Nations Framework Convention on Climate Change
2. Website of United Nations Framework Convention on Climate Change (UNFCCC),
http://unfccc.int
3. UNFCCC Decision 17/CP.7 : Modalities and procedures for a clean development mechanism
as defined in article 12 of the Kyoto Protocol.
4. UNFCCC document, Clean Development Mechanism-Project Design Document (CDM-PDD)
version 01(in effect as of: August 29, 2002)
5. UNFCCC document : Annex B to attachment 3 Indicative simplified baseline and monitoring
methodologies for selected small scale CDM project activity categories ver 01, January 21,
2003.
Project Related
6. Detailed Project report on 20 MW Non-Conventional renewable Sources bagasse/biomass
Cogeneration Power Plant at HCM, Haidergarh, prepared by M/s Avant-Garde Engineers and
Consultants (P) ltd., Chennai, India.
7. Executive summary of revised capacity of 20 MW by M/s Avant-Garde Engineers and
Consultants (P) ltd., Chennai, India.
8. Various project related information / documents / data received from Haidergarh Chini Mills,
Haidergarh during the site visits.
Baseline Related
9. Center for Monitoring Indian Economy (CMIE) published document of April 2002 on Energy
which includes the detailed data of Energy sector of India.
10. Website of Center for Monitoring Indian Economy (CMIE) Pvt. Ltd., Mumbai, India –
www.cmie.com
11. Website of Central Electricity Authority (CEA), Ministry of Power, Govt. of India -
www.cea.nic.in
12. CEA published document “Fifteenth Electric Power Survey of India”
13. CEA published Report on “Perspective plan for generating capacity addition, Integrated
Operation of regional grids (Free run studies using EGEAS model)”
14. CEA published Report on “Power on Demand by 2012, Perspective plan studies”
15. CEA Report on, Fourth National Power plan 1997 – 2012.
16. Website of Uttar Pradesh Power Corporation Limited (UPPCL), Energy Ministry, Govt. of UP
– http://www.uppcl.org
17. UPPCL Report, Statistics at a Glance : 2000-2001, a detailed document on power sector
overview of UP.
18. Website of Ministry of Power (MoP), Govt. of Indiawww.powermin.nic.in
CDM-PDD for BCML Haidergarh Bagasse Cogeneration Project
BCML - II ENCLOSURES
Classified - Confidential Page 46 of 46
Sr.No Particulars of the references
19. Website of Ministry Non-Conventional Energy Sources (MNES), Govt. of India –
www.mnes.nic.in
20. Paper by Moti L. Mittal and C. Sharma (Ohio Super Computer Center), ‘Anthropogenic
Emissions from Energy Activities in India: Generation and Source Characterisation’.
21. Website of Indian Renewable Energy Development Agency (IREDA),www.ireda.nic.in
22. Detailed Information document of Non-conventional Energy Development Agency
(NEDA), Govt. of Uttar Pradesh Lucknow. (2001-2002).
23. NEDA’s progress report of the year 2001-02 regarding Non-conventional Energy
Development programs in Uttar Pradesh.
24. Official website of Government of Uttar Pradesh,http://www.upindia.org
25. CII Investor Guidebook on bagasse Co-generation .
26. Paper by H. M. Nandanpawar ; ‘ Overview of Cogeneration Power Projects at Sugar Mills in
India’ at International Conference on ‘Non- Conventional Energy Resources, (Pune, 2001).
27. Background Paper of International Conference and Business Meet on ‘Non Fossil Fuel
Generation’ organized jointly by CII, NHPC and NPC of India Ltd. (New Delhi, 2001).
28. Paper by Dr. V. Bakthavatsalam, (MD, IREDA) ‘Renewable Energy Financing: Indian
Experience’ at International conference and Business Meet on Non-Fossil Fuel Generation.
(New Delhi, 2001).
29. Paper by Mr. Rangan Banerjee, (Energy Systems Engineering, IIT Bombay), ‘Review of
Electricity Generation from Renewables’. (2001).
30. www.infraline.com
31. Paper by Sivan Kartha and Michael Lazarus with Martina Bosi, IEA Practical baseline
recommendations for greenhouse Gas mitigation projects in the electric power sector, an OECD
and IEA Information paper.
32. Official website of Uttar Pradesh Government, India. www.upindia.org
33. India Electrical Distribution Reform Review and Assessment. A report prepared by CORE
international, Washington for USAID, India, September 2002.